EP0865540A1 - Modularer bahnsteigbausatz - Google Patents
Modularer bahnsteigbausatzInfo
- Publication number
- EP0865540A1 EP0865540A1 EP97945810A EP97945810A EP0865540A1 EP 0865540 A1 EP0865540 A1 EP 0865540A1 EP 97945810 A EP97945810 A EP 97945810A EP 97945810 A EP97945810 A EP 97945810A EP 0865540 A1 EP0865540 A1 EP 0865540A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- platform
- changeable
- spacer elements
- plate
- foundations
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F1/00—Construction of station or like platforms or refuge islands or like islands in traffic areas, e.g. intersection or filling-station islands; Kerbs specially adapted for islands in traffic areas
Definitions
- the present invention relates to a changeable platform with one or more platform plates.
- platforms are designed as fixed structures. Such platforms are manufactured on the condition that they should remain unchanged for many generations. Such static structures, however, no longer meet the requirements of modern rail traffic. On the one hand, they are inflexible with regard to requirements that arise from new technical developments. On the other hand, they do not offer the possibility of making unavoidable dimensional and distance corrections to the building in a simple and cost-effective manner. Under the modern requirements for comfort and safety, it is no longer tolerable to accept such deviations without correction. Last but not least, from today's perspective, the complex, time-consuming, labor-intensive and costly construction method is to be criticized on conventional platforms.
- EP-357 161 describes a platform which is essentially composed of three basic elements. These are initially U-shaped concrete bases, which are placed at fixed intervals parallel to the track. Two longitudinal beams are then placed on the vertical legs of the U-shaped concrete base from base to base, which run parallel to the rail. Finally, the longitudinal beams are covered with rectangular platform slabs and all connections and joints are closed and glued.
- Such a platform system reduces the construction time of a platform compared to the solid construction, but the handling of the solid longitudinal beams and the several platform plates is still relatively complex. Furthermore, the platform slabs are not protected against sagging or "sagging" to the unsupported center between the two longitudinal beams.
- Another particular disadvantage is that the platform is not suitable for later problem-free conversion due to the permanent connection of the components, and in particular does not allow any dimensional adjustment of the system.
- DE-43 16 203 also describes a platform kit which contains in-situ concrete foundations, crossbeams and platform slabs.
- the crossbeams are fastened to the in-situ concrete foundations and then placed from crossbeams to crossbeams on platform slabs, which contain box-shaped support beams on their underside. These platform slabs are firmly connected to the crossbeams.
- This system has disadvantages similar to those described above.
- in-situ concrete has to set up to 28 days, which extends the construction time required. Weather conditions and frost can also hinder the construction site.
- the platform shown in the laid-open specification is a complete platform as a rigid plate. This plate can only be removed by cutting the concrete. Due to the destruction of the reinforcement, the reusability is very limited.
- a height-adjustable platform for trams is also described in the article "Retractable traffic islands” (VerLitestechnik, issue 24 of December 20, 1935, page 666).
- the platform slab rests on four wooden blocks in the normal state. By removing the wooden blocks, they can be sunk into the ground, i.e. be adjusted at street level.
- the platform slab can be moved vertically within a predetermined shaft.
- the height adjustability of the traffic island or platform system disclosed in the aforementioned publication and in DE 42 05 192 A1 can lead to problems, since between the usual platform heights (e.g. 38 cm above the top edge of the rail (SOK)) and larger platform heights (e.g. 55 cm, 76 cm and 96 cm above SOK) the desired distance from the platform edge to the track axis can change. Therefore, in these cases the height adjustment can become an undesirable and lead an intolerably large distance from the platform to the track axis or from the wagon entrance.
- platform heights e.g. 38 cm above the top edge of the rail (SOK)
- larger platform heights e.g. 55 cm, 76 cm and 96 cm above SOK
- the present invention has set itself the task of providing a prefabricated kit for the creation of changeable platforms, which enables the platform to be assembled and disassembled and components replaced in a time and cost-effective manner, and which enables the subsequent change in dimensions the platform, especially the platform height.
- the platform should be mobile in the sense that it should be possible to rebuild it at another location. In the event of a change in height, disadvantages which can result from changed distances from the track axis are to be avoided.
- the platform should also be suitable as part of renovation measures to be installed over the remains of the old platform, with partial or complete use of the old platform edge with its associated strip foundations. In addition, it should also be used in difficult situations, e.g. can be built on dams. After all, the platform should also be able to serve as a provisional or temporary platform in cases where a platform is only being built for a certain period, e.g. in the form of a platform extension, because longer trains are supposed to stop at a platform for a certain time or in the event that a platform is to be temporarily erected at a different location and only comes into its final position later.
- a changeable platform with one or more platform slabs, which can be changed in height in particular, and which is characterized in that the platform slabs have support areas on their underside, within which they are placed at any point on the support points of the platform substructure can, and / or that the platform substructure has on its upper side support areas within which the platform slabs can be placed anywhere, so that the platform slabs can be arranged in different horizontal positions above the foundations.
- the latitude for horizontal displacement of the platform slabs is preferably up to 5 to 20% of the platform width (typically about 1 m).
- the horizontal change in the position of the platform slabs is made possible by a corresponding structural adaptation and design of the platform slabs and / or the platform substructure, so that a stable platform construction is obtained within the latitude of the position.
- a platform is obtained which avoids the disadvantages of the prior art that, after a change in height, the horizontal distances from the track axis are unfavorable or intolerable from the point of view of comfort and safety.
- a decisive improvement has thus been achieved with regard to the usability of height-variable platforms.
- the horizontal position change can be achieved in such a way that the platform plates have support areas on their underside, within which the support points of the platform substructure can be positioned at any point.
- the “support points of the platform substructure” are not only to be understood as punctiform, but can in turn be extensive areas that may only partially come into contact with the platform slabs.
- the platform substructure can also have support areas on its upper side, within which the platform plates (via support points or support areas) can be placed at any point.
- the foundations can lie outside the pressure range of the track.
- an escape area of approximately 70 cm is provided under the platform plate with a corresponding projection of the platform plate.
- the platform slabs are preferably prefabricated components, so that a prefabricated kit to be produced at the factory is obtained.
- the platform according to the invention can contain one or more prefabricated spacer elements which, when assembled, are arranged between the platform plate and foundations and can be replaced without damaging the other elements, ie in particular the foundations and the platform plate.
- the platform plate can be detachably connected or lie unconnected on the spacer elements.
- the spacer elements can in turn be releasably connected or lie unconnected on the foundations.
- the platform is characterized according to the invention in that the horizontal position of the platform plate on the spacer elements and / or the horizontal position of the spacer elements on the foundations can be changed. The lateral position of the platform of the platform is therefore variable during construction or conversion.
- the platform according to the invention surprisingly manages without permanent connections between the components.
- the construction and arrangement of the components alone ensures that the platform is sufficiently stable with regard to the stresses to which it is exposed.
- the platform remains as easy to disassemble for all times as it can be assembled.
- This makes it possible in particular in the course of a conversion measure to replace the built-in spacer elements with those of different dimensions or to set up or dismantle the spacer elements. This makes it possible to bring the platform edge to a new desired height and position in relation to the top edge of the rail. It is also possible to compensate for dimensional shifts by making minor corrections.
- Such conversion and adaptation measures on the platform according to the invention can be carried out with little effort and with only minor interruptions in operation.
- the platform slab is self-supporting between the in-situ concrete foundations or crossbars, so that it can be gripped and raised in this area.
- the latter would not be possible with a system according to EP-357 161, for example, since the longitudinal beams would be detected together with the platform slabs.
- the height-adjustable platforms known from the prior art (DE 42 05 192 A1 and scaffoldtechnik 24, 666) have no lateral displaceability compared to the platform according to the invention, since the traffic island is guided vertically through the excavation and the platform system by securing elements.
- the platform according to the invention can also be used to react to dimensional changes that occur, for example, when changing from various conventional platform heights (eg 38 cm above SOK) to higher ones (eg 55-96 cm above SOK). Especially under today's requirements for comfort and safety, such deviations can no longer be accepted without correction.
- various conventional platform heights eg 38 cm above SOK
- higher ones eg 55-96 cm above SOK
- the production of the platform slab according to the invention from various prefabricated prefabricated parts, instead of from in-situ concrete, has various advantages over DE 42 05 192 A1.
- the width of a platform slab is only specified by the maximum possible transport dimensions or weights.
- the width of the platform is limited by the lost formwork.
- a platform plate prefabricated in the factory can be used immediately after assembly. This shortens the disability times on site considerably, since in-situ concrete is known to have to set up to 28 days. Finished parts can also be assembled in extreme temperatures (frost). This is not the case with local concreting. This also gives greater flexibility in terms of construction time.
- Another major advantage of a prefabricated platform slab as opposed to a concrete slab on site is the division into individual slab parts separated by joints. The platform system is therefore mobile and reusable, not just liftable. A prefabricated platform can be completely dismantled in a short time. Only the permanently elastic joints have to be cut and the individual parts removed.
- the platform shown in DE 42 05 192 A1 is a complete platform as a rigid plate in which the concrete has to be cut to convert it. Due to the destruction of the reinforcement, the reusability is very limited. Also, the formwork of a platform section, which is in the transition arch for sheet layers, is relatively low in the precast plant according to the invention. The arch formwork only has to be adapted for each section of the platform. The sliding formwork shown in DE 42 05 192 A1, however, cannot be used in the transition arch. A prefabricated part therefore has less formwork and therefore lower costs. Furthermore, the platform system according to the invention is completely modular and consists of interchangeable individual components. It is very easy to maintain because all individual parts can be replaced without any problems.
- Factory production also guarantees high dimensional accuracy and flexibility in the surface properties, for example the use of different colored concrete and different surface roughness in one slab. In the case of in-situ concrete, this would mean an additional work step or, due to the poorer quality of the connection between the top covering and the platform slab, higher maintenance costs.
- Another advantage of the later surface underneath in the formwork is the greater concrete density and surface homogeneity that can be achieved (plane level of the vibrating table).
- the system design according to the invention also enables a very high dimensional accuracy, since only a single adjustment of the platform plate is necessary.
- disabling systems in the platform area such as, for example, existing masts
- can be integrated into the system ie cutouts and panel sizes can be selected in order to leave the location of the disabling systems when the panels are moved.
- Recesses that have already been provided can also be closed again in the event that the hindering system ceases to exist later.
- Existing deep drainage systems between the track and the platform can also remain or recesses are provided for this.
- a basic stability of the arrangement is already ensured by the weight of the components, in particular the platform slab.
- a conceivable stress on the platform in exceptional cases consists, for example, in that a horizontal displacement of the components could be caused by the impact of a rail vehicle. If such a displacement is not already adequately absorbed by the frictional forces between the components and their own weight, it can also be provided according to a preferred embodiment of the invention that the components are anchored against such horizontal stresses by a special, interlocking shape. Numerous different connection options are conceivable here, which can work according to the tongue and groove principle, for example.
- the stabilization against a parallel displacement of the parts against one another by means of a corresponding complementary, interlocking shape can take place both for the platform slab and the spacer elements on the one hand and for the spacer elements and the foundations on the other hand. It is particularly preferred if the platform slab, spacer elements and foundations are each interlocked by appropriate shaping. However, the locking against unintentional lateral displacement must be such that it does not prevent the desired lateral variability when converting the platform. Gears should therefore allow various engagement positions, for example, in a grid-like manner, screw connections could ensure appropriate flexibility via elongated holes. A subdivision into individual elements is possible for the spacer elements according to the invention, but preferably they consist of two individually supported parts.
- the in-situ concrete foundations are not one-piece and are designed, for example, in pillar construction or for temporary structures consist of easily reusable threshold stacks one-piece or multi-piece spacer elements also designed as transoms on bored or driven piles.
- This variant is possible in difficult soil conditions or in difficult locations, e.g. on dams.As a rule, however, the surface pressure resulting from the weight of the system platform and its equipment elements is so low that the abovementioned Foundation is sufficient
- In-situ concrete foundations can be caused by spacers of different thicknesses from the horizontal transverse inclinations of the platform slabs.
- multi-piece spacer elements have a lower individual weight and are therefore easier to process
- the platform according to the invention can be designed in the form of four different systems
- System I can be used for narrow platforms or an outer platform.
- System II can be used for platforms with widths larger than 7 m, e.g. central platforms
- System III can be used for platforms with widths of less than 7 m, e.g. the edge areas of central platforms.
- System IV is an implementation when an existing platform is built over Typical configurations of these systems are described in more detail below.
- the platform slabs according to the invention have preferably formed on their underside in the longitudinal direction parallel support beams. These support beams give the platform slabs the necessary stability in the longitudinal direction. This makes it possible to make the platform slab itself less thick, which leads to a weight saving.
- support beams extending transversely to the longitudinal extent can also be arranged below the platform slab. Support beams of this type, which are preferably located at the beginning and at the end of the platform plate, prevent the platform plate from bending in the transverse direction. The spacing of these support beams enables, without changing the supporting structure of the platform system, a technical innovation to arrange the platform in the radius of the curve provided by the course of the track. Also as an innovation, the longitudinal edges of the platform can be designed in the specified radius of curvature or according to other shape specifications.
- the platform plates according to the invention are preferably manufactured in the factory in such a way that recesses for the passage of cable protection tubes are already integrated in them. This makes it possible without problems to provide the necessary (in particular earthing and electrical) installations for the platform. Furthermore, the platform slabs according to the invention can already be mounting sleeves for platform structures, such as Weather protection devices or information boards included. Such pre-devices complete the possibilities for a quick and easy installation of a platform with the modules according to the invention.
- the kit according to the invention consists of a uniaxially tensioned precast reinforced concrete slab in a standard width of, for example, 2-4 m.
- the length is half the platform width, with exceptions as described below.
- the fat the plate only needs to be 14-20 cm.
- the plate itself has a slope for the discharge of the surface water into a continuous channel in the middle of the platform or a slope to the track.
- the system also consists of two edge girders (girder beams). These are self-supporting prefabricated beams with a standard length of up to 9 m. These edge girders absorb the vertical loads from the platform slab. They can be provided with a sound-absorbing surface towards the track (e.g. aggregate concrete).
- the system also consists of a trough element.
- a cantilevered precast girder with a standard length of 9 m, which absorbs the vertical loads from the platform slab and is supported on the foundation beam.
- the outside of the trough can be provided with a sound-absorbing layer or a pre-hung sound-absorbing plate. This is particularly important here in the local transport sector in residential areas.
- the system also consists of a base beam as a precast foundation beam, which is attached to the respective edge of the platform slab, e.g. every 9 m, which braces the edge beams, connects the individual foundations and forwards the horizontal loads and distributes them into the foundations.
- the foundations are made of prefabricated parts or in-situ concrete and are attached to each end of a platform slab.
- the spacer elements are designed as prefabricated parts and guarantee the height adjustability of the platform.
- the overhang of the platform slab over the edge beams is variable, but preferably 70 cm (so-called escape area) can also be zero.
- This system can be used for platform widths of less than 7 m. It consists of a uniaxially tensioned precast slab, the standard width is 2-4 m, the length corresponds to the platform width, the thickness can be carried out like System II, the slope also.
- Other components are edge beams as self-supporting prefabricated beams, base beams as precast beams, in-situ concrete or prefabricated individual foundations and spacer elements as described in System II.
- System IV
- a prefabricated slab When building over an existing platform, a prefabricated slab is tensioned biaxially and attached point-supported over an edge beam and a central beam; for outer platforms over two edge beams. Height adjustment and drainage are carried out as in the aforementioned systems.
- the precast foundation and edge beams are approximately 70 cm or larger from the platform edge, they do not touch the foundation of the old platform edge or the old platform edge itself. This 70 cm can serve as an escape area, and such a distance or greater has the advantage that the foundation work can be carried out without endangering the operation (outside the pressure area of the track).
- the foundations are individual foundations.
- the central support must also be founded if it is a central platform consisting of two platform slabs.
- the edge bars can be Systems with a sound-absorbing surface can be manufactured or hung outwards.
- a further technology for height adjustability can be used, in which the platform plate is supported on the platform substructure by height-adjustable feet.
- These height-adjustable feet can e.g. consist of a threaded anchor that can be screwed into the platform slab or platform substructure to different depths.
- a counter bearing for the threaded anchor can be formed by a base plate in the other component.
- a drainage channel can be arranged either along the longitudinal edge of the platform slab, preferably on the outer platform.
- surface water can also be drained to both sides by means of a corresponding inclination to two sides.
- a drainage channel can be installed in the joint between two platform slabs with a half-channel / box channel under the joint.
- This drain water will depend on Longitudinal slope of the slab, for example, led out every 9 m and drained into the existing drainage. This can be done through a recess in the central trough (System II).
- Systems III and IV also create the possibility of central drainage. With an upstand on the side facing away from the track, even heavy rainwater runoff can be concentrated in just a few processes.
- the advantage of the system according to the invention is that several variants of rainwater drainage are possible and it can therefore be adapted to the wishes of the user.
- the surface of the platform slab is preferably equipped with a non-slip surface and integrable safety and control systems. It can be made in different colors and structures. In particular, it is possible to use different concrete compositions for the production of the surface. Two or more different concretes can be used, e.g. those of different colors or different compositions (e.g. glass fiber reinforced concrete and concrete with other additives). These can be placed one after the other and / or next to each other in the formwork. It is also conceivable that they are arranged in a grid structure in which they are only separated by grid joints. By using different concretes, an appealing aesthetic (including coloring) design of the platform slabs can be achieved as well as advantageous static and functional properties.
- the weight of the platform slab should be less than 10,000 kg, preferably less than 8,000 kg.
- the platform slab preferably has a width of 2 to 5 m, very particularly preferably 2.50 to 3.0 m, and a length of 4 to 10 m, preferably 5 to 7.50 m.
- the prefabricated kit according to the invention can also be used with great advantage if no later conversion measures for adapting dimensions are planned, but rather a permanent platform is to be created.
- the time and cost-effective prefabricated construction of the platform according to the invention benefits the user in any case, even if no later conversion measures are carried out on the platform.
- the prefabricated kit to create a platform that is variable in height and side.
- a height adjustment of the platform by larger distances, e.g. from 38 cm to 96 cm above the top edge of the rail, e.g. required if other rail vehicles are used.
- Such changes in the height requirements are particularly common in today's modernization of the traffic systems. Numerous transport companies are being converted to other wagon technology, which makes it necessary to retrofit the platforms.
- the platform according to the invention is of inestimable advantage, in particular when the modernization of a platform is currently due and the need for retrofitting has already been determined or is probable.
- the invention also relates to a method for height and / or
- Prefabricated kit This method is characterized in that a) the platform slab is first raised, which is preferably done with hydraulic presses, rail cranes or excavators, b) if necessary, the spacer elements against new spacer elements of the desired
- Spacer elements can also be replaced or increased storage elements between the components of the prefabricated kit. Because according to the prior art, it is common to mount so-called elastomer bearings between such components, e.g. in the form of neoprene strips.
- bearing elements are arranged between the platform plate and the spacer on the one hand and the spacer and foundation on the other.
- the toothed profile of the components certainly prevents one
- Figure 1 shows a perspective view of the platform according to the invention (system I).
- Figure 2 shows a side view of the platform (system I).
- Figure 3a shows a front view (cross section) of the platform with one-piece foundations.
- Figure 3b shows a front view (cross section) of the platform with pile foundations.
- FIG. 4 shows a front view (cross section) of two parallel platforms with multi-piece spacer elements
- FIG. 5 shows a perspective of the platform slab with a negative roof profile
- Figure 6 shows the board edge facing away from the track with mounting bracket.
- F Fiigguurr 77 shows a schematic top view and side view with mounting bracket.
- Figure 8 shows a schematic of an arc fitting.
- Figure 9 shows a schematic of a recess
- FIG. 10 shows schematically the connection of a mounting plate to the system plate for establishing a weather protection house
- FIG. 11 shows the systems II and III as a basic sketch
- Figure 12 shows the cross section of the platform system II.
- Figure 13 shows a longitudinal section of the platform system II.
- Figure 14 shows the cross section of the platform system III.
- F Fiigguurr 1155 shows the cross section of the System IV platform.
- Figure 16 shows the foundations and drainage (System IV).
- Figure 17 shows the height adjustability in System IV.
- Figure 18 shows a makeshift platform
- Figure 19 shows a perspective view of a central platform.
- Figure 1 shows a perspective view of a section of the platform according to the invention according to system I, which consists of two basic sections (platform slabs 1).
- the platform runs parallel to extend the rails, the upper edge of the platform must maintain a predetermined distance from the upper edge of the rails.
- the platform according to the invention is built on a cleanliness layer 5 or an old platform 5.
- the in-situ concrete foundations 4 are first laid at certain intervals. The spacing of these foundations corresponds to the length of the platform slabs 1.
- the spacer elements 3 are located in one piece on the foundations 4. These are each arranged at the two end points of the foundations 4.
- the spacer elements 3 on the one hand form a defined support surface towards the platform plate 1, on the other hand they are suitable as light and easily interchangeable elements, the height and
- Figure 2 shows the construction according to the invention schematically in a side view.
- longitudinal beams 2 can also be seen, which are formed on the underside of the platform slabs 1 and provide stability in the longitudinal direction there.
- Support beams arranged in the transverse direction cf. number 2 in FIGS. 1 and 3 likewise ensure the stability of the platform slabs in the transverse direction.
- the overhang that the platform slab 1 has over the support beams 2 is also clearly visible.
- the protrusion on the narrow side makes it possible to change the shape of the platform slab without changing the frame of the support beams (deviating from the rectangular shape) in such a way that the assembled platform slabs adapt to predetermined radii of curvature.
- the platform plates are preferably trapezoidal for this purpose.
- FIG. 2 shows two variants of the platform according to the invention in a front view.
- FIG. 3a relates to the version with one-piece in-situ concrete foundations 4.
- the structure of cleanliness layer 5, foundation 4, spacer elements 3 and platform slab 1 with (transverse) support beams 2 can be seen.
- empty pipes 6 can be seen, which run centrally below the platform slab 1 and e.g. can serve as cable protection tubes. On the front side of the platform slab, the empty tubes 6 penetrate the cross beam 2.
- Figure 3b shows a similar basic structure, but here the platform is built on a pile foundation with the piles 4 '. This construction method is preferable in difficult terrain and ground conditions, e.g. when the platform is built on a dam.
- the spacer elements 3 are located on the piles 4 'and can be designed as pile head beams.
- 3b shows the drainage channels 7 arranged on the side of the platform edge, a cable trough 8, empty pipes 6, a railing 9 mounted in plug holes and a service hatch 10.
- FIG. 4 shows the front view of an alternative platform.
- two platforms actually run parallel to one another and together form a platform of double width.
- Both platforms are each based on the known structure of cleanliness layer 5, foundation 4, spacer elements 3 and platform slabs 1.
- Structures are indicated on the platforms, e.g. Weather protection devices and lighting measures. These can preferably be connected to the platform plates 1 in preassembled mounting sleeves.
- the essentials of the construction according to FIG. 4 are the two-piece spacer elements 3a, 3b. These provide two support points in which the longitudinal beam beams 2a, 2b are placed. With the two-part division of the spacer elements 3, it is possible to cross-slope the To influence platform plate 1. For this purpose, spacer elements 3a, 3b of different heights can be selected. It is thus possible either to compensate for an inclination of the foundation 4 that deviates from the horizontal or to generate a corresponding inclination of the platform slab 1.
- the spacer elements 3a, 3b have depressions on their upper side, into which the longitudinal beam beams 2a, 2b are inserted.
- the spacer elements 3a, 3b in turn engage with protrusions in corresponding recesses in the foundations 4. In this way it is ensured without further, permanent connection measures between the components that the corresponding arrangement is stable against a load with transverse forces.
- Figure 5 shows a perspective view of a platform slab 1, in which a depression is formed in the surface by a "negative roof profile", in the lowest point of which the waste water drain 13 is arranged.
- a depression is formed in the surface by a "negative roof profile", in the lowest point of which the waste water drain 13 is arranged.
- other shapes of the surface can also be realized depending on the needs and the desired waste water collection point.
- Figure 6 shows a section of the plate side facing away from the track. You can see a c-profile 14, which is used to reinforce the edges, and the on-site I-profile 15 (wide flange bracket of the HEA or HEB version).
- the non-positive connection with the plate 1 is made via threaded sleeves 16 with shaft anchors, for example of the PFEIFFER type, a threaded rod and a nut 25, which is easily accessible from the outside.
- Openings in the upper flange which are either manufactured beforehand in defined grid dimensions or on-site according to requirements, can be used, for example, to secure railing supports 17 in a torque-stable and easy-to-install manner. They are fastened in the lower area, for example in a base plate 21 with a screw thread.
- the assembly time can also be shortened if the equipment elements are already connected to the support 19 (screwed or welded) before they are screwed together with the system plate 1.
- the mounting bracket 19 can be flushed through a corresponding recess in the plate 1 to the concrete surface and connected with a permanently elastic joint 18.
- the support can also be installed so that the top of the flange is above the concrete surface.
- Figure 7 shows the c-profile and I-profile in a schematic plan view and a side view (side facing away from the track).
- FIG. 8 shows the adaptation of the plate edges 26 on the track side to predetermined radii. Since all plate edges are drawn over the supporting structure 27 (cantilever plates), the edges can be changed without endangering the load-bearing capacity of the plate.
- the edge 26 on the track side can be convex, concave or oblique.
- FIG. 9 shows the possibility of also changing the edge profile on the side facing away from the track, without thereby endangering the load-bearing capacity.
- Figure 10 shows the connection of a mounting plate 32 to the system plate 1, for example, to attach a weather protection house thereon. The transition of both plates is made by the mounting bracket 19.
- the mounting plate 32 can also be retrofitted to the system plates equipped with a mounting bracket.
- Figure 11 shows the systems II and III in plan as a schematic diagram.
- the part of a central platform is shown that tapers towards the end.
- System II consists of two or more panels 1 lying together in the platform width.
- the floor plan shows the continuous trough element 40 in the middle, the two edge elements 41 running through the length and the grid of e.g. Basic beam 42 running 9 m across the entire width of the platform.
- System III starts where the width of the platform allows a single slab.
- the criteria here are the weight and the transport size of the plate. It is shown e.g. a 7 m wide and 3 m long slab that tapers towards one side.
- the plates of system III rest on the two outer edge beams 41 and partially, in the example every 9 m, on the base beam 42.
- Figure 12 shows the cross section of the platform system II.
- a cavity in which supply lines 42 or other channels can be accommodated.
- a possible attachment or foundation of platform structures, such as platform roofs etc. is also indicated.
- the platform is raised or lowered via a spacer element 3 under the edge support 41. This spacer element is not continuous along the length, but rather is placed on the base beams 42 .
- a neoprene bearing 44 is located between the edge support 41 and the spacer element 3.
- the drainage takes place via a half-channel 45 in the middle between the two platform plates. The water can be discharged through a recess in the trough element 40.
- Figure 13 shows the longitudinal section of the same platform, namely System II. Occasionally required access to the interior of the trough channel 40, e.g. to change the drainage line is possible via a side entry 46. Access to the cavity between the trough channel and edge beams can be created via a manhole cover in the platform slab, the surface of which can be adapted in color.
- Figure 14 shows the cross section of the platform system III.
- the structure is similar to System I, but without a central trough and with only one plate 1 over the entire width of the platform.
- FIG. 15 shows the cross section of the system IV. It can be seen in the figure that an old existing platform 47 does not have to be completely removed.
- the two platform slabs 1 (with a smaller width, e.g. ⁇ 7 m, a platform slab is also conceivable) are supported in the middle on a foundation with an overlying prefabricated part.
- An increase is possible with this system, the details of which are shown in FIG.
- the edge beams 41 can be clad with a sound-absorbing surface or made from a large-pore concrete on the surface.
- the foundation is so far from the threshold that it is not touched by the load spreading 48 below the threshold, which occurs at approximately 45 °, i.e. the operation of the track is not endangered during the laying of the foundations.
- the foundations are composed of a frost-free lean concrete layer 49, on which two precast foundations 50 are placed.
- Figure 16 shows how the foundations of System IV are arranged and how the drainage of the platform can be provided.
- each plate In the less wide parts of the platform, in which only one plate 1 is provided over the entire width, each plate has an inclination towards one point. These inclinations can already be provided in the plate in the precast plant. In the two- or multi-plate area, the drainage takes place in the middle between the two plates.
- FIG. 17 shows the detail of height adjustability in system IV.
- the anchor 52 is supported downwards on a base plate 55 (e.g. 120x120x12 mm) anchored in the concrete foundation.
- a base plate 56 e.g. 120x120x12 mm
- a nut 57 e.g. M20-M27
- the standpipe 51 is gripped by a lockable top ring 59 ground at the top.
- the height is adjusted by rotating the armature 52, which e.g. can be done by an electric screwdriver 60 with roller bearing management.
- the resulting space can be filled with concrete via the joint between the two panels.
- the adjustment is ensured by means of the sheet metal slide box 53 shown, the sealing by a neoprene lip seal 54.
- this system can no longer be lowered when filling with concrete.
- Figure 18 shows a makeshift platform which e.g. can be used in the following cases:
- the position of the provisional platform may or may not be the same as the final position of the platform.
- the platform is installed in advance at a provisional location. The same system is later installed in the final state and remains there.
- 3. As a temporary platform extension. This is necessary, for example, if a longer track is ordered from the station provider for a limited time.
- the dimensions of the makeshift platform are variable. Its width is preferably between 2.40 m and 3.00 m. The length is preferably between 6 and 9 m, so that even with this system the costs are minimized and simple equipment can be used. Since the
- Makeshift platform should be installed several times at different locations, usually only certain grids are used.
- the temporary platform consists of precast foundations 4 and a precast slab 1, which is supported on these foundations and is secured with stainless steel brackets 61 against unintentional lateral displacement.
- the overhanging part can be varied as in the other systems.
- the precast foundations sit on a ballast bed and a thin layer of sand.
- FIG. 19 shows a perspective view of a central platform of the type described above for better illustration.
- the system platform is assembled during the breaks during operation with two-way system vehicles or cranes and can be used immediately.
- the system enables preparatory work for the production of the platform, e.g. Civil engineering, foundation production, unless transport by rail is required, to be carried out outside the pressure range of the adjacent track. In this way, operational security costs and slow driving points can be minimized. If the horizontal and / or vertical position of the platform changes, all parts can be reused.
- the system platform is based on a modular pre-fabricated skeleton, with which a new, modern platform can be installed in a very short construction time over a defective platform or over the earth body adjoining the formation.
- the platform height between 38 cm above sea level (above the top of the rail) and 96 cm above sea level can be varied at any time without great effort.
- the color, structure and texture of the covering surface can be individually determined in consultation with the client and manufactured to a consistently high quality.
- Width and length parameters are tailored to the application and the available transport options, or to a predetermined grid dimension of the user.
- roofs or weather protection devices can also be integrated according to the user's specifications, either according to the detailed sketch by connecting the required foundations to the base beam or as an individual foundation through a recess in the system plate.
- Standard traffic loads of 5 kN / m 2 for passenger traffic and 5 kN / m 2 for a 3-t baggage vehicle according to DS 804 Para. 105, Vol. 29 of DB AG can be used as load factors.
- the introduction of point-shaped special loads, for example for supports for weather protection devices, etc. are possible and are permitted to a large extent without changing the planning.
- a special precast reinforced concrete element can be used, which is based on the design of the static system of a ⁇ plate.
- beam support can be dispensed with. Manufacturing costs and installation effort can be minimized.
- Panel thickness (or web height for system I) of the system panel are sufficiently dimensioned for all conceivable operating conditions.
- the weight and dimensions of the element are matched to the work equipment in railway construction and the existing clearance profile.
- the plates are connected to one another in the middle of the plate in accordance with the cantilevered area, in order to permanently compensate for height differences caused by bending or production.
- Pre-fabricated parts made of reinforced concrete are also used as support elements, which ensure a gradual height adjustment from 38 cm above sea level to 96 cm above sea level.
- the actual foundation is made of in-situ concrete.
- the dimensions of the construction pits to be produced for this purpose are generally chosen so that the stability of the ballast bed is not endangered and no shoring is necessary.
- Removable connections guarantee a quick and easy conversion in the event of a future change in level.
- transport anchors usually arranged in the surface of finished parts are avoided here in order not to disturb the uniform appearance of the surface by moving the plates with bands.
- the foundations are dimensioned in such a way that the permissible soil pressure according to DIN 1054 or Eurocode 7 is observed. In the case of particularly poor geotechnical conditions, soil stabilization is required in individual cases or deep foundation is necessary.
- the covering side especially along the track side, must be equipped with a sure-footed, rough structure and a guide marking must be provided, which is indispensable as a visually and tactile orientation aid for special groups of people.
- a special surface quality which is characterized by a high abrasion value and insensitivity to environmental influences and the use of de-icing agents, is particularly preferred.
- no additional work step is required to manufacture the surface.
- Different colors, structures, grids and coverings can be individually manufactured in the precast plant according to the user's wishes.
- the necessary construction joints (eg to separate different colors) are poured with shrink-free mortar so that there is no loss of the statically required covering of the reinforcement of at least 3 cm. This is necessary in order to minimize the thickness of the panels and thus their weight.
- This version can be sanded in color, to match the colors of the surface.
- a 30-50 cm wide strip with a particularly non-slip structure e.g.
- a 25 cm wide guiding marking e.g.
- pavement structure for the platform: pavement structure, various variations possible.
- the drainage is collected in a drainage channel and either fed to the ground in a septic tank or discharged into the sewage system.
- a cross slope of 1-2% of the system platform to the side facing away from the track or (usually) to the center reliably ensures that the water flows off evenly.
- the plate widths can be varied so that a uniform gradient is maintained from both sides.
- the water can be collected centrally in one or more points by a special negative profiling of the plate surface and fed to a drain line.
- the platform system allows free access to the cavity under the platform at any point, e.g. via a manhole.
- the surface structure is continued in the manhole cover.
- the cables are routed via cable protection tubes integrated into the plate in System I, or through empty tubes arranged below the plate in the other systems. An uncomplicated supply of the platform equipment is guaranteed by cable connection boxes at regular intervals and the subsequent pulling in of cables is made possible.
- a cable trough can optionally be installed in the space under the plate, in which additional lines such as e.g. can be accommodated for the installation of a parallel communication network.
- the cavity under the platform slab can accommodate cable guides.
- the cavities can be made accessible through doors or openings in order to e.g. to use as storage space for winter service.
- Support structure 60 Electric screwdriver 0 28 Track axis 61 Angle 29 Platform axis 30 Barrier 31 Cut-out 32 Attachment plate
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
- Transceivers (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Pressure Welding/Diffusion-Bonding (AREA)
- Train Traffic Observation, Control, And Security (AREA)
- Discharge Heating (AREA)
Description
Claims
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19641800 | 1996-10-10 | ||
DE19641800A DE19641800A1 (de) | 1996-10-10 | 1996-10-10 | Modularer Bahnsteigbausatz |
PCT/EP1997/005571 WO1998015691A1 (de) | 1996-10-10 | 1997-10-09 | Modularer bahnsteigbausatz |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0865540A1 true EP0865540A1 (de) | 1998-09-23 |
EP0865540B1 EP0865540B1 (de) | 2004-01-02 |
Family
ID=7808376
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP97945810A Expired - Lifetime EP0865540B1 (de) | 1996-10-10 | 1997-10-09 | Fertigbausatz zur erstellung eines veränderbaren bahnsteigs |
Country Status (7)
Country | Link |
---|---|
US (1) | US6173653B1 (de) |
EP (1) | EP0865540B1 (de) |
AT (1) | ATE257197T1 (de) |
AU (1) | AU5117998A (de) |
DE (2) | DE19641800A1 (de) |
PL (1) | PL190117B1 (de) |
WO (1) | WO1998015691A1 (de) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015177383A1 (fr) * | 2015-02-17 | 2015-11-26 | Metrolab | Procédé de déploiement modulaire de quais |
RU2725972C1 (ru) * | 2019-09-06 | 2020-07-08 | Общество с ограниченной ответственностью "Андромета" | Сборно-разборная железнодорожная платформа и способ её перемещения |
Families Citing this family (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU4917899A (en) * | 1998-07-15 | 2000-02-07 | Derek William Rea | Platform structure |
DE19855511A1 (de) * | 1998-10-17 | 2000-05-04 | Euka Gmbh Ingenieur Consulting | Fertigbausatz für die Erstellung einer Plattform, insbesondere eines Bahnsteiges |
NL1012567C2 (nl) * | 1999-07-12 | 2001-01-15 | Compatech B V | Stelrand voor keerwanden en werkwijze voor het aanbrengen en stellen van de rand. |
GB2378193A (en) * | 2001-08-03 | 2003-02-05 | Laing Rail Ltd | Railway platform construction |
ATE368771T1 (de) | 2002-06-10 | 2007-08-15 | Karl-Heinz Winter | Modulares bahnsteigsystem |
BE1015505A3 (nl) * | 2003-05-05 | 2005-05-03 | Composite Damping Material Nv | Tussen een trein en een platform te plaatsen boordelement. |
GB0310517D0 (en) * | 2003-05-07 | 2003-06-11 | Middleton Jonathan | Rail system |
FR2875463B1 (fr) * | 2004-09-17 | 2006-12-15 | Csm Chaudronnerie De Saint Mar | Dispositif pour creer un quai a usage temporaire, pour les usagers d'un moyen de transport |
US7779581B2 (en) * | 2007-05-09 | 2010-08-24 | Ada Solutions, Inc. | Replaceable wet-set tactile warning surface unit and method of installation and replacement |
FR2918339A1 (fr) * | 2007-07-02 | 2009-01-09 | Alstom Transport Sa | Vehicule ferroviaire et dispositif d'acces audit vehicule |
DE202009004754U1 (de) | 2009-04-29 | 2009-07-02 | Hering Bau Gmbh & Co. Kg | Modulares System zur Überdachung von Bahnsteigen |
EP2278071B1 (de) | 2009-06-18 | 2016-01-06 | Triple S GmbH | Modulare Bahnsteigkante mit demontierbarer Bahnsteigkantenplatte |
DE202009005016U1 (de) | 2009-07-14 | 2009-09-17 | Hering Bau Gmbh & Co. Kg | Modular aufgebauter Bahnsteig |
DE102010019891A1 (de) | 2010-05-07 | 2011-11-10 | Hsp Spengler Gmbh & Co.Kg | Bahnsteig in Fertigteilbauweise |
US8920066B1 (en) | 2011-01-12 | 2014-12-30 | Tuf-Tite, Inc. | Tactile sidewalk surface |
DE102013100228A1 (de) * | 2013-01-10 | 2014-07-10 | Triple S-Gmbh | Bahnsteiginstallationseinrichtung für einen Bahnsteig |
DE202013100857U1 (de) | 2013-02-28 | 2013-04-18 | Hering Bau Gmbh & Co. Kg | Bahnsteigaufhöhungs- und Sanierungssystem |
CN105778934A (zh) * | 2016-04-06 | 2016-07-20 | 中国五冶集团有限公司 | 基于焦炉炉体砌筑施工的三维控制砌筑方法 |
CN106703449A (zh) * | 2017-01-24 | 2017-05-24 | 北京交通大学 | 一种基于装配式技术的单轨交通车站 |
GB2562305B (en) * | 2017-05-12 | 2020-01-15 | Geoffrey Osborne Ltd | A coper unit for an edge of a platform |
CN107190658B (zh) * | 2017-07-27 | 2023-07-11 | 四川睿铁科技有限责任公司 | 一种钢制自由框拼装式铁路疏散救援站台 |
US10920378B2 (en) | 2018-01-19 | 2021-02-16 | Tuf-Tite, Inc. | Stamped steel detectable warning tile and method of manufacture |
JP2019137213A (ja) * | 2018-02-09 | 2019-08-22 | 有限会社弘栄工業 | ホーム柵 |
CN110196568B (zh) * | 2018-02-26 | 2022-06-24 | 宝山钢铁股份有限公司 | 行车抓取板坯的方法 |
US10954679B2 (en) | 2018-06-11 | 2021-03-23 | International Business Machines Corporation | Dynamic platform creation |
CN111794040B (zh) * | 2020-06-30 | 2022-05-17 | 中铁二院工程集团有限责任公司 | 一种支撑站台板的异形支挡结构及施工方法 |
CN112942153A (zh) * | 2021-01-26 | 2021-06-11 | 哈尔滨工业大学 | 道路安全岛及其施工方法 |
IT202100031037A1 (it) * | 2021-12-10 | 2023-06-10 | Alfio Giovanni Torrisi | Struttura prefabbricata modulare integrata in cemento armato per l’adeguamento dell’altezza del piano di calpestio di banchine ferroviarie |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE148132C (de) * | ||||
US2652783A (en) * | 1949-06-02 | 1953-09-22 | Whiting Corp | Crossover bridge and operating mechanism |
EP0357161B1 (de) * | 1988-08-01 | 1992-10-28 | Otto Frenzel Bauunternehmen | Bahnsteig |
DE3826096A1 (de) * | 1988-08-01 | 1990-02-15 | Frenzel Otto Bauunternehmen | Bausatz fuer bahnsteig |
DE4205192C2 (de) * | 1992-02-20 | 1995-10-12 | Euka Bauelemente Verkaufsgesel | Bahnsteig |
DE4316203A1 (de) * | 1992-05-20 | 1993-11-25 | Stewing Beton & Fertigteilwerk | Bausatz zum Erstellen eines Bahnsteiges in Fertigteilbauweise |
DE9304059U1 (de) * | 1993-03-19 | 1993-09-16 | Schreck-Mieves GmbH, 50226 Frechen | Bahnsteig |
DE4431470A1 (de) * | 1994-09-03 | 1996-03-07 | Mannheimer Verkehrs Ag Mvg | Bahnsteig für eine Haltestelle für Personenbeförderungsfahrzeuge |
DE29503328U1 (de) * | 1995-02-17 | 1995-04-13 | Otto Frenzel, Bauunternehmen, 31084 Freden | Bahnsteig |
-
1996
- 1996-10-10 DE DE19641800A patent/DE19641800A1/de not_active Withdrawn
-
1997
- 1997-10-09 AU AU51179/98A patent/AU5117998A/en not_active Abandoned
- 1997-10-09 AT AT97945810T patent/ATE257197T1/de active
- 1997-10-09 DE DE59711169T patent/DE59711169D1/de not_active Expired - Lifetime
- 1997-10-09 US US09/091,206 patent/US6173653B1/en not_active Expired - Lifetime
- 1997-10-09 PL PL97327189A patent/PL190117B1/pl not_active IP Right Cessation
- 1997-10-09 EP EP97945810A patent/EP0865540B1/de not_active Expired - Lifetime
- 1997-10-09 WO PCT/EP1997/005571 patent/WO1998015691A1/de active IP Right Grant
Non-Patent Citations (1)
Title |
---|
See references of WO9815691A1 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015177383A1 (fr) * | 2015-02-17 | 2015-11-26 | Metrolab | Procédé de déploiement modulaire de quais |
FR3032728A1 (fr) * | 2015-02-17 | 2016-08-19 | Metrolab | Procede de deploiement modulaire de quais |
RU2725972C1 (ru) * | 2019-09-06 | 2020-07-08 | Общество с ограниченной ответственностью "Андромета" | Сборно-разборная железнодорожная платформа и способ её перемещения |
Also Published As
Publication number | Publication date |
---|---|
US6173653B1 (en) | 2001-01-16 |
PL190117B1 (pl) | 2005-11-30 |
DE59711169D1 (de) | 2004-02-05 |
AU5117998A (en) | 1998-05-05 |
EP0865540B1 (de) | 2004-01-02 |
PL327189A1 (en) | 1998-11-23 |
DE19641800A1 (de) | 1998-04-23 |
WO1998015691A1 (de) | 1998-04-16 |
ATE257197T1 (de) | 2004-01-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0865540B1 (de) | Fertigbausatz zur erstellung eines veränderbaren bahnsteigs | |
EP3521557B1 (de) | Multifunktionsrahmen für röhrenartige bauwerke | |
DE2233518A1 (de) | Brueckenkonstruktion | |
EP2088244B1 (de) | Stahlbeton oder Verbundbrücke und Verfahren zu ihrer Herstellung | |
AT391499B (de) | Eisenbahnoberbau, insbesondere fuer schienenfahrzeuge mit sehr hohen fahrgeschwindigkeiten | |
DE4316203A1 (de) | Bausatz zum Erstellen eines Bahnsteiges in Fertigteilbauweise | |
EP0609297B1 (de) | Bahnsteigkante | |
EP1371781B1 (de) | Modulares Bahnsteigsystem | |
EP2088245A1 (de) | Stahlbeton oder Verbundbrücke mit horizontaler Verbundfuge und Verfahren zu ihrer Herstellung | |
DE29723956U1 (de) | Modularer Bahnsteigbausatz | |
DE102011107918B4 (de) | Überbaudeckel, Anordnung aus Überbaudeckel, Bohrpfahl und Steckträger sowie behelfsbrückenfreies Verfahren zum zügigen Verkehrswegkorper-und Verkehrsweganschluss eines Brücken- oder Unterführungstragwerkes in Deckelbauweise | |
DE4325476A1 (de) | Verfahren zur Herstellung eines Unterbaus für ein Gleis für Schienenfahrzeuge | |
EP2166149B2 (de) | Gleiskörperformteileinheit | |
DE29912398U1 (de) | Bahnsteigsystem aus Betonfertigteilen | |
DE10140318A1 (de) | Bahnsteig | |
DE19854246A1 (de) | Verfahren und System zum Bau und Umbau von Bahnsteigen mit veränderbaren Höhen | |
DE19818338C1 (de) | Bahnsteigsystem und Verfahren zur Erstellung eines Bahnsteiges | |
DE102017131351A1 (de) | Trogförmiger Überbau für eine Brücke, Brücke, Fertigteil für eine Trogwange einer Brücke sowie Verfahren zur Herstellung einer Brücke | |
DE29922297U1 (de) | Stahl-Beton-Decke | |
DE19944783A1 (de) | Feste-Fahrbahn-System | |
DE1434752B1 (de) | Mehrere Arbeitsstaende einer Fahrzeugwerkstaette umfassende,durchgehende Arbeitsgrube | |
DE3100740A1 (de) | "schallschutzwand" | |
DE1434752C (de) | Mehrere Arbeitsstande einer Fahr zeugwerkstatte umfassende, durchgehende Arbeits grube | |
DE10225752A1 (de) | Modulares Bahnsteigsystem | |
DE19650105A1 (de) | Tragkonstruktion |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 19980604 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE FR LI NL |
|
17Q | First examination report despatched |
Effective date: 20020129 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
RTI1 | Title (correction) |
Free format text: CONSTRUCTION KIT FOR THE CONSTRUCTION OF A MODULAR STATION PLATFORM |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH DE FR LI NL |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REF | Corresponds to: |
Ref document number: 59711169 Country of ref document: DE Date of ref document: 20040205 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: R. A. EGLI & CO. PATENTANWAELTE |
|
ET | Fr: translation filed | ||
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20041005 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20080630 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20061010 Year of fee payment: 10 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20071031 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20121129 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20121024 Year of fee payment: 16 |
|
BERE | Be: lapsed |
Owner name: *HERING G.M.B.H. & CO. K.G. VERWALTUNGSGESELLSCHAF Effective date: 20131031 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: V1 Effective date: 20140501 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140501 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131031 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20141027 Year of fee payment: 18 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20141028 Year of fee payment: 18 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 257197 Country of ref document: AT Kind code of ref document: T Effective date: 20151009 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20151031 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20151031 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20151009 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20160922 Year of fee payment: 20 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R071 Ref document number: 59711169 Country of ref document: DE |