WO2017057305A1 - 遠隔操作装置 - Google Patents
遠隔操作装置 Download PDFInfo
- Publication number
- WO2017057305A1 WO2017057305A1 PCT/JP2016/078335 JP2016078335W WO2017057305A1 WO 2017057305 A1 WO2017057305 A1 WO 2017057305A1 JP 2016078335 W JP2016078335 W JP 2016078335W WO 2017057305 A1 WO2017057305 A1 WO 2017057305A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- lever switch
- mode
- selection means
- remote control
- control device
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/18—Control systems or devices
- B66C13/40—Applications of devices for transmitting control pulses; Applications of remote control devices
- B66C13/44—Electrical transmitters
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/18—Control systems or devices
- B66C13/40—Applications of devices for transmitting control pulses; Applications of remote control devices
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/52—Details of compartments for driving engines or motors or of operator's stands or cabins
- B66C13/54—Operator's stands or cabins
- B66C13/56—Arrangements of handles or pedals
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/36—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
- B66C23/42—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes with jibs of adjustable configuration, e.g. foldable
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/88—Safety gear
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C2700/00—Cranes
- B66C2700/08—Electrical assemblies or electrical control devices for cranes, winches, capstans or electrical hoists
- B66C2700/088—Remote control of electric cranes
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01H—ELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
- H01H9/00—Details of switching devices, not covered by groups H01H1/00 - H01H7/00
- H01H9/02—Bases, casings, or covers
- H01H9/0214—Hand-held casings
Definitions
- the present invention relates to a remote operation device for an actuator of a mobile crane.
- a remote operation device for remotely operating an actuator of a mobile crane has been proposed.
- the remote control device even if it is attempted to reproduce the lever arrangement of the driver's seat of the mobile crane as it is, the number of levers is large, so the device becomes large and not suitable for carrying.
- a vehicle-mounted crane has a relatively small number of operation inputs, a small remote control device that can be operated with one hand is realized.
- Patent Document 1 includes an initial mode and a work mode, and the initial mode includes a user setting mode, a service setting mode, and a manufacturer setting mode.
- a remote control transmitter is disclosed.
- the conventional remote control device is limited even when preparing for work peculiar to a large crane such as a rough terrain crane or an all terrain crane (for example, extending and storing a jib and operating four outriggers).
- a large crane such as a rough terrain crane or an all terrain crane (for example, extending and storing a jib and operating four outriggers).
- the number of operation means is difficult to operate and the number of operation inputs is insufficient.
- an object of the present invention is to provide a small remote control device that can be operated with one hand, and is easy to operate for work preparation specific to a large crane.
- a remote control device for an actuator of a mobile crane, and includes a gripping part to be gripped by a hand and an operation surface for operating the actuator.
- the plurality of selection means two selection means having the highest frequency of use in the work preparation step of the mobile crane are provided on the operation surface.
- Central is disposed adjacent to the neighborhood.
- the remote control device of the present invention includes a device main body and a plurality of selection means, each of which is arranged on the operation surface and selected by the movement from the neutral position in the first direction or the second direction.
- the selection means two selection means that are most frequently used in the work preparation process of the mobile crane are arranged adjacent to the vicinity of the center of the operation surface. Because of such a configuration, the remote control device can be operated with one hand and can be easily operated for work preparation specific to a large crane.
- the rough terrain crane 1 of the present embodiment includes a vehicle body 10 that is a main body portion of a vehicle having a traveling function, outriggers 11,... Provided at four corners of the vehicle body 10, and the vehicle body 10.
- a swivel base 12 is mounted so as to be horizontally swivelable, and a boom 14 is mounted on a bracket 13 erected on the swivel base 12.
- the outrigger 11 can be slid out / slidable outward in the width direction from the vehicle body 10 by extending / contracting the slide cylinder 52, and can also be jacked / jacked vertically from the vehicle body 10 by extending / contracting the jack cylinder 51. It can be stored.
- the swivel base 12 has a pinion gear to which the power of the turning motor is transmitted, and the pinion gear meshes with a circular gear provided on the vehicle body 10 to rotate around the turning axis.
- the swivel base 12 has a cockpit 18 disposed on the front right side, a bracket 13 disposed in the rear center, and a counterweight 19 disposed in the lower rear portion.
- the boom 14 is configured to be nested by a base end boom 141, an intermediate boom 142, and a front end boom 143, and can be expanded and contracted by a telescopic cylinder disposed therein.
- a sheave is arranged at the most advanced boom head of the tip boom 143, and a wire rope 16 is hung around the sheave and a hook block 17 is suspended.
- the outermost base boom 141 is pivotally attached to a support shaft that is installed horizontally on the bracket 13 so that the base boom 141 can be raised and lowered up and down around the support shaft. Furthermore, the raising / lowering cylinder 15 is spanned between the bracket 13 and the lower surface of the base end boom 141, and the boom 14 can be raised / lowered by extending / contracting the raising / lowering cylinder 15.
- the jib 30 and the tension rods 20 and 20 are stored in a sideways posture on the side surface of the base end boom 141.
- the jib 30 and the tension rods 20 and 20 are mounted / stored using a plurality of pins (not shown) and a side-up cylinder 31.
- the control system of the present embodiment has four jack cylinders 51,..., Four slide cylinders 52,..., A swing motor 53, a hoisting cylinder 54, a telescopic cylinder 55, and a main winch as actuators.
- a motor 56 and a sub winch motor 57 are provided. These actuators are controlled by a control valve 64 described later.
- the control system of the present embodiment includes, as a hydraulic circuit, a PTO 62 that extracts power from the transmission 61 of the engine 60, a hydraulic pump 63 that is rotationally driven by the PTO 62 and pressurizes hydraulic oil from the oil tank 65, and a hydraulic pump 63 And a control valve 64 for controlling the flow of discharged hydraulic oil.
- the control valve 64 includes a valve group corresponding to each actuator. Each valve is controlled by a controller 70.
- the controller 70 is a computer having a bus, an arithmetic device, a storage device, and the like.
- the controller 70 receives an operation signal from the turning lever 71, the hoisting lever 72, the telescopic lever 73, the main winch lever 74, or the like, or receives an operation signal from the remote operation device 40 via the communication unit 70a.
- the actuator is controlled by calculating the moving direction and moving amount of each valve and transmitting a signal to the control valve 64.
- the remote operation device 40 includes an operation surface 42 for operating the actuator, and a grip portion 41 that extends below the operation surface 42 and is gripped by hand.
- the remote control device 40 has a communication unit 40a, and commands the controller 70 via the communication unit 70a of the controller 70 by operating lever switches S1 to S4 and setting buttons F1 to F3 described below. Or obtain information from the controller 70.
- a trigger 45 that is operated with an index finger while holding the grip 41 is disposed on the back side of the grip 41. As will be described later, the trigger 45 drives the actuator selected by the selection unit in the selected direction (forward direction or reverse direction) at a speed corresponding to the operation amount.
- the trigger 45 can operate a plurality of actuators. However, since there is only one trigger 45, a separate operation amount cannot be associated with each actuator.
- the operation surface 42 includes a display unit 43 disposed at the upper part; a power switch 44 disposed on the right side of the display unit 43; a mode button 46 disposed on the lower left side of the display unit; The three setting buttons F1, F2, F3 arranged in the above; the turning lever switch S1 and the undulation lever switch S2 as four selection means arranged below corresponding to the mode button 46 and the setting buttons F1, F2, F3 A sub winch lever switch S3 and a main winch lever switch S4.
- the mode button 46 and the setting buttons F1 to F3 constitute mode switching means.
- the display unit 43 is a liquid crystal display, and switches to a setting screen by long-pressing the mode button 46. By pressing the setting buttons F1, F2, and F3 following the mode button 46, a crane mode (laying plate suspension process mode) is displayed. ), Outrigger extension / storage process mode, and jib attachment / detachment process mode.
- the four lever switches S1 to S4 as selection means respectively set the operation direction of each actuator to the forward direction or the reverse direction by moving (tilting) from the neutral position in the first direction or the second direction.
- Each lever switch S1 (S2, S3, S4) is biased by a spring so as to return from the moved (tilted) position to the neutral position.
- the swing lever switch S1 selects an operation for extending the boom 14 when tilted upward, and selects an operation for contracting the boom 14 when tilted downward.
- the turning lever switch S1 corresponds to the operation of the left rear outrigger 11 in the outrigger extension / retraction mode.
- the raising / lowering lever switch S2 selects an operation in which the boom 14 rises when it is tilted upward, and an operation in which the boom 14 falls when it is tilted downward.
- the raising / lowering lever switch S2 selects an operation in which the boom 14 or the jib 30 is raised when it is tilted upward, and an operation in which the boom 14 or the jib 30 is tilted when it is tilted downward.
- pressing the setting button F1 switches the boom 14 and the jib 30 that are the operation targets.
- the hoisting lever switch S2 corresponds to the operation of the left front outrigger 11 in the outrigger extension / retraction mode.
- the sub winch lever switch S3 When the sub winch lever switch S3 is tilted upward in both the crane mode and the jib attachment / detachment process mode, the sub winch is selected to be lowered, and when it is tilted downward, the sub winch is selected to be wound. Further, the sub winch lever switch S3 corresponds to the operation of the right front outrigger 11 in the outrigger extension / retraction mode.
- the main winch lever switch S4 When the main winch lever switch S4 is tilted upward in the crane mode, the main winch winding is selected, and when the main winch lever switch S4 is tilted downward, the main winch winding is selected.
- the main winch lever switch S4 In the jib attachment / detachment process mode, when the main winch lever switch S4 is tilted upward, the main winch winding or the side-up cylinder 31 is selected to be lifted.
- the main winch lever switch S4 When the main winch lever switch S4 is tilted downward, the main winch is lowered or the side-up cylinder 31 is lowered. Is selected.
- pressing the setting button F3 switches between the main winch and the side-up cylinder 31 that are the operation targets. Further, the main winch lever switch S4 corresponds to the operation of the right rear outrigger 11 in the outrigger extension / retraction mode.
- the crane mode In the crane mode (laying plate suspension process mode), as shown in FIG. 7, the crane mode is displayed on the left in the display unit 43 by an icon, a turning brake ON warning, a hook-in enable icon, an overwind release icon Is displayed. The overwinding is released by pressing the setting button F2 in the crane mode.
- the operator operates the remote control device 40 by one person, so that the turning motor 53, the raising / lowering are performed by the turning lever switch S1, the raising / lowering lever switch S2, the sub winch lever switch S3, and the main winch lever switch S4.
- the cylinder 54, the sub winch motor 57, and the main winch motor 56 are driven to operate the boom 14 and the winch, and the floor plate is installed at a predetermined position corresponding to each outrigger 11.
- this laying plate hanging process unlike load hanging work, there are many cases where there is no auxiliary worker such as a slinger, and the operator has to get out of the cockpit 18 and hang the laying plate manually. For this reason, conventionally, even when returning to the cockpit 18 in order to install the floorboard in a predetermined position, the floorboard has to be moved out again and then manually placed, so that the work efficiency is poor. Therefore, when the remote control device 40 is used, the operator can operate the boom 14 and winch while being near the floorboard, so that it is not necessary to go up and down to the cockpit 18 for the operation.
- a jack-up confirmation screen is first displayed as shown in FIG.
- the setting button F2 is pressed to advance to the jib attachment / detachment screen.
- the setting button F3 is pressed to return to the mode selection screen.
- the telescopic cylinder 55, the hoisting cylinder 54 (or dibutyl) are turned by the turning lever switch S1, the hoisting lever switch S2, the sub winch lever switch S3, and the main winch lever switch S4.
- the cylinder 14), the sub winch motor 57, and the main winch motor 56 (or the side-up cylinder 31) are operated to operate the boom 14 and the jib 30, and the jib 30 is attached to and removed from the tip of the boom 14. Further, by pressing the setting button F1, the operation of the actuator corresponding to the hoisting lever switch S2 can be switched to boom hoisting or dibutylt.
- the remote control device 40 if the operator can operate the boom 14, the sub winch (not shown), the side up cylinder 31 and the like while being near the jib 30, it is not necessary to move up and down to the cockpit 18 and work efficiency. Will improve.
- the jib attachment / detachment procedure will be briefly described for easy understanding.
- the jib 30 is moved from the retracted state to the lower surface of the boom 14, the tension rod 20 is connected to the link at the tip of the boom 14, the jib set pin is inserted, the auxiliary rope is attached, and the jib 30 is swung from the boom 14.
- the jib 30 is swung out of the boom 14, the dibutylt cylinder is extended, and the jib 30 is swung up to the working state.
- the dibutylt cylinder is fully reduced to suspend the jib 30, and an auxiliary rope is attached to prepare to fix the jib 30 to the boom 14.
- the jib 30 is pulled into the lower surface of the boom 14.
- the boom 14 is fixed, the jib set pin is pulled out, the tension rod 20 is removed from the link at the tip of the boom 14, and the jib 30 is pulled from the bottom surface of the boom 14 to the side.
- the other end of the auxiliary rope is manually attached to the auxiliary winding hook, and the sub winch is wound up by pulling the trigger 45 with the index finger while tilting the sub winch lever S3 downward with the thumb so that the auxiliary rope is not over tensioned.
- the safety rope is manually removed from the tip of the jib 30, and the boom 14 is further raised by pulling the trigger 45 with the index finger while tilting the hoisting lever switch S2 downward with the thumb.
- the sub winch is lowered so that the jib 30 is perpendicular to the ground.
- the boom 14 is tilted and the auxiliary rope is manually removed.
- the trigger 45 is pulled with the index finger while tilting both the raising / lowering lever switch S2 and the sub winch lever switch S3 with the thumb. This is followed by further work.
- Outrigger extension / storage process mode In the outrigger extension / storage process mode, as shown in FIG. 9, the icon indicating that the outrigger extension / storage process mode is in the left of the display unit 43, and on the right side are four processes described below. Which process is selected is displayed. Then, by pressing the setting button F1, the slide extension / storage screen and the jack extension / storage screen are switched. On the slide overhang / storage screen, pressing the setting button F2 switches between slide overhang and slide storage. On the jack extension / storage screen, pressing the setting button F2 switches between jack extension and jack storage. Each outrigger 11 is operated by pulling the trigger 45 with the index finger while tilting the switches S1 to S4 corresponding to the four outriggers 11,.
- the remote operation device 40 for the actuator of the mobile crane includes a device body having a grip portion 41 to be gripped by a hand and an operation surface 42 for operating the actuator;
- Lever switches S1 to S4 as a plurality of selection means for selecting an actuator, each of which is arranged on the operation surface 42 and selected by the movement in the first direction or the second direction from the neutral position.
- the lever switches S1 to S4 as a plurality of selection means that are set in the forward direction or the reverse direction, and the actuator selected by the lever switches S1 to S4 in the forward direction or the reverse direction are arranged in the vicinity of the grip portion 41.
- the remote control device 40 can be easily operated with the thumb by holding the remote control device 40 with one hand and operating the lever switches S2 and S3, which are frequently used in the work preparation process.
- the remote control device 40 the operator can operate the actuator outside the cockpit 18, so that it is not necessary to go up and down to the cockpit 18 for the operation. Furthermore, by arranging the two lever switches S2 and S3 corresponding to the frequently used actuator closer to the center, the remote control device 40 is operated by the thumb of one hand to operate the actuator, while the other hand is used. You can also work. Furthermore, two actuators can be operated simultaneously by simultaneously operating the two lever switches S2 and S3.
- the hoisting lever switch S2 and the sub winch lever switch S3, which are most frequently used in the work preparation process of the mobile crane, particularly in the laying plate hanging process and the jib attaching / detaching process, are adjacent to the center of the operation surface 42. Since it is arranged, the work preparation process can be carried out efficiently. That is, for example, in the jib attachment / detachment process, when the jib 30 is shaken out or pulled toward the boom 14, the boom 14 is often raised and lowered or the sub winch is wound up / down, and the corresponding lever switches S2, S3 are provided. It becomes easier to operate by placing it closer to the center. Furthermore, the simultaneous operation
- lever switches S1 to S4 are provided, and the four lever switches S1 to S4 are arranged in order from the left of the operation surface 42, the turning lever switch S1, the undulating lever switch S2, and the sub winch (supplementary winding).
- the lever switch S3 is the main winch (main winding) lever switch S4. This arrangement is almost the same as the lever arrangement in the cockpit 18 (in the order of turning, undulation, expansion / contraction, sub winch, main winch), so that the operator can easily learn the arrangement and prevent erroneous operation.
- the apparatus further includes mode switching means for switching the actuators assigned to the plurality of selection means, and the mode switching means switches between the plurality of setting buttons F1 to F3 corresponding to each mode and the setting buttons F1 to F3.
- a mode button 46 for enabling the state.
- the setting buttons F1 to F3 are the setting button F1 corresponding to the floor hanging process mode of the mobile crane, the setting button F3 corresponding to the jib attaching / detaching process mode, and the setting button F2 corresponding to the outrigger extension / retraction process mode. It consists of three. By switching the modes in this way, a large number of actuators can be remotely operated with a limited number of operation means. In the present embodiment, the case where switching to all three modes is described has been described. However, the present invention is not limited to this, and it is sufficient that at least any two modes can be switched.
- one lever switch can be used by switching between two actuators.
- the undulation switch S2 is switched to boom undulation or dibutyl.
- the overhanging / storing of the side-up cylinder 31 is switched to a main winch that is not frequently used in the jib attachment / detachment process mode.
- the setting buttons F1 and F3 are arranged on the same axis of the lever switches S2 and S4 to be switched, it is possible to prevent an erroneous operation together with the recognition of the operator.
- lever switches S1 to S4 are provided, and in the outrigger extension / retraction process mode, the rear left outrigger lever switch S1, in order from the left of the operation surface 42 to the four lever switches S1 to S4, A front left outrigger lever switch S2, a front right outrigger lever switch S3, and a rear right outrigger lever switch S4 are assigned. Therefore, simultaneous operation of only the two outriggers 11 and 11 on the front side, simultaneous operation of only the two outriggers 11 and 11 on the right side, and simultaneous operation of only the two outriggers 11 and 11 on the left side are possible. .
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Automation & Control Theory (AREA)
- Jib Cranes (AREA)
- Control And Safety Of Cranes (AREA)
Abstract
片手で操作可能な小型の遠隔操作装置であって、大型クレーン特有の操作がしやすい遠隔操作装置を提供する。移動式クレーン1のアクチュエータの遠隔操作装置40である。遠隔操作装置40は、装置本体と、複数の選択手段であって、それぞれ操作面42に配置され、中立位置から第1方向又は第2方向への移動によって選択されたアクチュエータの動作方向を正方向又は逆方向に設定する、複数の選択手段S1~S4と、選択手段S1~S4によって選択されたアクチュエータを、正方向又は逆方向に操作量に応じて動作させるトリガ45と、を備えており、複数の選択手段S1~S4のうち、移動式クレーン1の作業準備工程において使用頻度の最も高い2つの選択手段S2、S3が、操作面42の中央近傍に隣接して配置されている。
Description
本発明は、移動式クレーンのアクチュエータの遠隔操作装置に関するものである。
従来から、移動式クレーンのアクチュエータを遠隔操作するための遠隔操作装置が提案されている。遠隔操作装置では、移動式クレーンの運転席のレバー配置をそのまま再現しようとしても、レバーの数が多いため装置が大型化して持ち運びには適さなくなる。他方で、車両搭載型クレーンは比較的に操作入力数が少ないため、片手で操作できる小型の遠隔操作装置が実現されている。
この他、例えば、特許文献1には、初期モードと作業モードとを備え、初期モードには、ユーザ向け設定モード、サービス向け設定モード及びメーカ向け設定モードが含まれていることを特徴とするクレーンの遠隔操作用送信機が開示されている。
このように、従来の遠隔操作装置では、ラフテレーンクレーンやオールテレーンクレーンなどの大型クレーンに特有の作業準備(例えば、ジブの張出・格納やアウトリガ4本操作)をする際にも、限られた数の操作手段では操作がしにくく、操作入力数も不足する、といった問題があった。
そこで、本発明は、片手で操作可能な小型の遠隔操作装置であって、大型クレーン特有の作業準備の操作がしやすい遠隔操作装置を提供することを目的としている。
前記目的を達成するために、本発明の遠隔操作装置は、移動式クレーンのアクチュエータの遠隔操作装置であって、手で把持される把持部と前記アクチュエータを操作するための操作面とを有する装置本体と、前記アクチュエータを選択するための複数の選択手段であって、それぞれ前記操作面に配置され、中立位置から第1方向又は第2方向への移動によって選択された前記アクチュエータの動作方向を正方向又は逆方向に設定する、複数の選択手段と、前記把持部の近傍に配置され、前記選択手段によって選択されたアクチュエータを、正方向又は逆方向に操作量に応じて動作させるトリガ手段と、を備え、複数の前記選択手段のうち、前記移動式クレーンの作業準備工程において使用頻度の最も高い2つの選択手段が、前記操作面の中央近傍に隣接して配置されている。
このように、本発明の遠隔操作装置は、装置本体と、複数の選択手段であって、それぞれ操作面に配置され、中立位置から第1方向又は第2方向への移動によって選択されたアクチュエータの動作方向を正方向又は逆方向に設定する、複数の選択手段と、選択手段によって選択されたアクチュエータを、正方向又は逆方向に操作量に応じて動作させるトリガ手段と、を備えており、複数の選択手段のうち、移動式クレーンの作業準備工程において使用頻度の最も高い2つの選択手段が、操作面の中央近傍に隣接して配置されていることを特徴とする。このような構成であるため、片手で操作可能であるうえ、大型クレーン特有の作業準備の操作がしやすい遠隔操作装置となる。
以下、本発明の実施の形態について図面を参照して説明する。ただし、以下の実施の形態に記載されている構成要素は例示であり、本発明の技術範囲をそれらのみに限定する趣旨のものではない。
(構成)
まず、図1を用いて本実施例のアクチュエータの遠隔操作装置40を備える移動式クレーンとしてのラフテレーンクレーン1の全体構成について説明する。以下の実施例では、ラフテレーンクレーン1を例にして説明するが、これに限定されるものではなく、オールテレーンクレーンなどの移動式クレーンに広く本発明を適用できる。
まず、図1を用いて本実施例のアクチュエータの遠隔操作装置40を備える移動式クレーンとしてのラフテレーンクレーン1の全体構成について説明する。以下の実施例では、ラフテレーンクレーン1を例にして説明するが、これに限定されるものではなく、オールテレーンクレーンなどの移動式クレーンに広く本発明を適用できる。
(クレーンの全体構成)
本実施例のラフテレーンクレーン1は、図1に示すように、走行機能を有する車両の本体部分となる車体10と、車体10の四隅に設けられたアウトリガ11,・・・と、車体10に水平旋回可能に取り付けられた旋回台12と、旋回台12に立設されたブラケット13に取り付けられたブーム14と、を備えている。
本実施例のラフテレーンクレーン1は、図1に示すように、走行機能を有する車両の本体部分となる車体10と、車体10の四隅に設けられたアウトリガ11,・・・と、車体10に水平旋回可能に取り付けられた旋回台12と、旋回台12に立設されたブラケット13に取り付けられたブーム14と、を備えている。
アウトリガ11は、スライドシリンダ52を伸縮させることによって、車体10から幅方向外側にスライド張出/スライド格納可能であるとともに、ジャッキシリンダ51を伸縮させることによって車体10から上下方向にジャッキ張出/ジャッキ格納可能である。
旋回台12は、旋回用モータの動力を伝達されるピニオンギヤを有しており、このピニオンギヤが車体10に設けた円形状のギヤに噛み合うことで旋回軸を中心に回動する。旋回台12は、前方右側に配置された操縦席18と、後方中央に配置されたブラケット13と、後方下部に配置されたカウンタウェイト19と、を有している。
ブーム14は、基端ブーム141と中間ブーム142と先端ブーム143とによって入れ子式に構成されており、内部に配置された伸縮シリンダによって伸縮できるようになっている。先端ブーム143の最先端のブームヘッドにはシーブが配置され、シーブにワイヤロープ16が掛け回されてフックブロック17が吊下げられている。
最も外側の基端ブーム141は、付け根部がブラケット13に水平に設置された支持軸に回動自在に取り付けられており、支持軸を回転中心として上下に起伏できるようになっている。さらに、ブラケット13と基端ブーム141の下面との間には、起伏シリンダ15が架け渡されており、起伏シリンダ15を伸縮することでブーム14全体を起伏することができる。
さらに、本実施例のラフテレーンクレーン1では、基端ブーム141の側面に、ジブ30及びテンションロッド20、20が横抱姿勢にて格納されている。ジブ30及びテンションロッド20、20は、複数のピン(不図示)とサイドアップシリンダ31とを用いて、装着/格納される。
(制御系の構成)
次に、図2を用いて本実施例の遠隔操作装置40を含む制御系の構成について説明する。本実施例の制御系は、アクチュエータとして、4つのジャッキシリンダ51、・・・と、4つのスライドシリンダ52、・・・と、旋回モータ53と、起伏シリンダ54と、伸縮シリンダ55と、メインウインチモータ56と、サブウインチモータ57と、を備えている。これらのアクチュエータは、後述するコントロールバルブ64によって制御される。
次に、図2を用いて本実施例の遠隔操作装置40を含む制御系の構成について説明する。本実施例の制御系は、アクチュエータとして、4つのジャッキシリンダ51、・・・と、4つのスライドシリンダ52、・・・と、旋回モータ53と、起伏シリンダ54と、伸縮シリンダ55と、メインウインチモータ56と、サブウインチモータ57と、を備えている。これらのアクチュエータは、後述するコントロールバルブ64によって制御される。
そして、本実施例の制御系は、油圧回路として、エンジン60のトランスミッション61から動力を取り出すPTO62と、PTO62によって回転駆動され油タンク65からの作動油を加圧する油圧ポンプ63と、油圧ポンプ63から吐出される作動油の流れを制御するコントロールバルブ64と、を備えている。コントロールバルブ64は、各アクチュエータに対応するバルブ群から構成される。各バルブはコントローラ70によって制御される。
コントローラ70は、バス、演算装置、記憶装置などを有するコンピュータである。コントローラ70は、旋回レバー71、起伏レバー72、伸縮レバー73、メインウインチレバー74などからの操作信号を受信して、又は、通信部70aを介して遠隔操作装置40からの操作信号を受信して、各バルブの移動方向及び移動量を演算し、コントロールバルブ64に信号を送信することによってアクチュエータを制御する。
遠隔操作装置40は、図3~図5に示すように、アクチュエータを操作するための操作面42と、操作面42の下方に延びて手で把持される把持部41と、を有する。また、遠隔操作装置40は通信部40aを有しており、以下に説明するレバースイッチS1~S4や設定ボタンF1~F3等を操作することでコントローラ70の通信部70aを介してコントローラ70に指示を出したり、コントローラ70から情報を取得したりする。把持部41の背面側には把持部41を握った状態で人差し指で操作されるトリガ45が配置されている。トリガ45は、後述するように、選択手段によって選択されたアクチュエータを、選択された方向(正方向又は逆方向)に、操作量に応じた速度で駆動させる。すなわち、トリガ45を大きく引くとアクチュエータが速く駆動し、小さく引くとアクチュエータがゆっくり駆動する。トリガ45は、複数のアクチュエータを操作可能であるが、トリガ45は1つしかないため各アクチュエータに対して別個の操作量を対応させることはできない。
操作面42は、上部に配置される表示部43と;表示部43の右に配置される電源スイッチ44と;表示部の下左に配置されるモードボタン46と;モードボタン46の右に並んで配置される3つの設定ボタンF1、F2、F3と;モードボタン46及び設定ボタンF1、F2、F3に対応して下方に配置される4つの選択手段としての旋回レバースイッチS1、起伏レバースイッチS2、サブウインチレバースイッチS3、及びメインウインチレバースイッチS4と;を備えている。そして、モードボタン46と設定ボタンF1~F3によって、モード切替手段が構成される。
表示部43は、液晶ディスプレイであり、モードボタン46を長押しすることで設定画面に切り替わり、モードボタン46に続いて設定ボタンF1、F2、F3を押すことによって、それぞれクレーンモード(敷板吊工程モード)、アウトリガ張出・格納工程モード、ジブ着脱工程モードに切り替わる。
選択手段としての4つのレバースイッチS1~S4は、それぞれ中立位置から第1方向又は第2方向への移動(傾倒)によって、各アクチュエータの動作方向を正方向又は逆方向に設定する。各レバースイッチS1(S2、S3、S4)は、移動(傾倒)した位置から中立位置に戻るようにバネによって付勢されている。
具体的には、旋回レバースイッチS1は、クレーンモードにおいて、上方向に倒すと左旋回が選択され、下方向に倒すと右旋回が選択される。旋回レバースイッチS1は、ジブ着脱工程モードにおいて、上方向に倒すとブーム14が伸びる動作が選択され、下方向に倒すとブーム14が縮む動作が選択される。さらに、旋回レバースイッチS1は、アウトリガ張出・格納モードでは、左後方のアウトリガ11の操作に対応する。
起伏レバースイッチS2は、クレーンモードにおいて、上方向に倒すとブーム14が起仰する動作が選択され、下方向に倒すとブーム14が倒伏する動作が選択される。起伏レバースイッチS2は、ジブ着脱工程モードでは、上方向に倒すとブーム14又はジブ30が起仰する動作が選択され、下方向に倒すとブーム14又はジブ30が倒伏する動作が選択される。ジブ着脱工程モードでは、設定ボタンF1を押すことで、操作対象であるブーム14とジブ30が切り換わる。さらに、起伏レバースイッチS2は、アウトリガ張出・格納モードでは、左前方のアウトリガ11の操作に対応する。
サブウインチレバースイッチS3は、クレーンモード及びジブ着脱工程モードの両方のモードにおいて、上方向に倒すとサブウインチの巻下げが選択され、下方向に倒すとサブウインチの巻上げが選択される。さらに、サブウインチレバースイッチS3は、アウトリガ張出・格納モードでは、右前方のアウトリガ11の操作に対応する。
メインウインチレバースイッチS4は、クレーンモードにおいて、上方向に倒すとメインウインチの巻下げが選択され、下方向に倒すとメインウインチの巻上げが選択される。メインウインチレバースイッチS4は、ジブ着脱工程モードでは、上方向に倒すとメインウインチの巻上げ又はサイドアップシリンダ31のアップが選択され、下方向に倒すとメインウインチの巻下げ又はサイドアップシリンダ31のダウンが選択される。ジブ着脱工程モードでは、設定ボタンF3を押すことで、操作対象であるメインウインチとサイドアップシリンダ31が切り換わる。さらに、メインウインチレバースイッチS4は、アウトリガ張出・格納モードでは、右後方のアウトリガ11の操作に対応する。
(作用)
次に、図6~図10を参照しつつ、本実施例のラフテレーンクレーン1のアクチュエータの遠隔操作装置40の作用について説明する。まず、図6のモードセレクト画面(初期画面)において、モードボタン46に続いて、表示部43のアイコンに対応して、設定ボタンF1を押すとクレーンモード(敷板吊工程モード)となり、設定ボタンF2を押すとアウトリガ張出・格納工程モードとなり、設定ボタンF3を押すとジブ着脱工程モードとなる。このように、モード切替手段として、モードボタン46と設定ボタンF1~F3の2種類のボタンを用いて2段階の操作を必要とすることで、誤ってモードが切り替わってしまうことを防止している。
次に、図6~図10を参照しつつ、本実施例のラフテレーンクレーン1のアクチュエータの遠隔操作装置40の作用について説明する。まず、図6のモードセレクト画面(初期画面)において、モードボタン46に続いて、表示部43のアイコンに対応して、設定ボタンF1を押すとクレーンモード(敷板吊工程モード)となり、設定ボタンF2を押すとアウトリガ張出・格納工程モードとなり、設定ボタンF3を押すとジブ着脱工程モードとなる。このように、モード切替手段として、モードボタン46と設定ボタンF1~F3の2種類のボタンを用いて2段階の操作を必要とすることで、誤ってモードが切り替わってしまうことを防止している。
(クレーンモード)
クレーンモード(敷板吊工程モード)では、図7に示すように、表示部43内の左にクレーンモードであることがアイコンによって表示される他、旋回ブレーキON警告、フックイン可能アイコン、過巻解除アイコンが表示される。クレーンモードにおいて設定ボタンF2を押すことで過巻解除される。そして、敷板吊工程では、オペレータが1人で遠隔操作装置40を操作することで、旋回レバースイッチS1、起伏レバースイッチS2、サブウインチレバースイッチS3、メインウインチレバースイッチS4によって、旋回モータ53、起伏シリンダ54、サブウインチモータ57、メインウインチモータ56を駆動してブーム14やウインチを操作して、敷板を各アウトリガ11に対応する所定位置に設置する。この敷板吊工程では、荷吊作業とは異なり玉掛け者などの補助作業員がいないことも多く、オペレータが操縦席18から出て手作業で敷板を玉掛けしなければならない。このため、従来は、敷板を所定位置に設置するために操縦席18に戻っても、その後、また外に出て手作業で敷板を玉掛けしなければならず、作業効率が悪かった。そこで、遠隔操作装置40を用いると、オペレータは敷板の近くにいながらにしてブーム14やウインチを操作できるため、操作のためにわざわざ操縦席18に昇降する必要がなくなる。
クレーンモード(敷板吊工程モード)では、図7に示すように、表示部43内の左にクレーンモードであることがアイコンによって表示される他、旋回ブレーキON警告、フックイン可能アイコン、過巻解除アイコンが表示される。クレーンモードにおいて設定ボタンF2を押すことで過巻解除される。そして、敷板吊工程では、オペレータが1人で遠隔操作装置40を操作することで、旋回レバースイッチS1、起伏レバースイッチS2、サブウインチレバースイッチS3、メインウインチレバースイッチS4によって、旋回モータ53、起伏シリンダ54、サブウインチモータ57、メインウインチモータ56を駆動してブーム14やウインチを操作して、敷板を各アウトリガ11に対応する所定位置に設置する。この敷板吊工程では、荷吊作業とは異なり玉掛け者などの補助作業員がいないことも多く、オペレータが操縦席18から出て手作業で敷板を玉掛けしなければならない。このため、従来は、敷板を所定位置に設置するために操縦席18に戻っても、その後、また外に出て手作業で敷板を玉掛けしなければならず、作業効率が悪かった。そこで、遠隔操作装置40を用いると、オペレータは敷板の近くにいながらにしてブーム14やウインチを操作できるため、操作のためにわざわざ操縦席18に昇降する必要がなくなる。
(ジブ着脱工程モード)
ジブ着脱工程モードでは、はじめに図8(a)に示すように、ジャッキアップ確認画面が表示される。ジャッキアップ確認画面において、ジャッキアップが完了していれば設定ボタンF2を押してジブ着脱画面に進み、ジャッキアップが完了していなければ設定ボタンF3を押してモードセレクト画面に戻る。そして、ジブ着脱工程では、図8(b)に示すように、旋回レバースイッチS1、起伏レバースイッチS2、サブウインチレバースイッチS3、メインウインチレバースイッチS4によって、伸縮シリンダ55、起伏シリンダ54(又はジブチルトシリンダ)、サブウインチモータ57、メインウインチモータ56(又はサイドアップシリンダ31)を駆動することによってブーム14やジブ30を操作して、ジブ30をブーム14の先端に取り付けたり、取り外したりする。また、設定ボタンF1を押すことで、起伏レバースイッチS2に対応するアクチュエータの動作を、ブーム起伏又はジブチルトに切換えることができる。さらに、設定ボタンF3を押すことで、メインウインチレバースイッチS4に対応するアクチュエータの動作を、メインウインチ又はサイドアップ/ダウンに切換えることができる。このジブ着脱工程は手順が複雑で、着脱作業に不慣れな作業員が作業することは困難であるため、クレーンのオペレータが操縦席18から出て手作業で準備をしなければならない。ところが、ラフテレーンクレーン1やオールテレーンクレーンでは、操縦席18の昇降に時間がかかるため、作業効率が悪くなっていた。そこで、遠隔操作装置40を用いることによって、オペレータはジブ30の近くにいながらにしてブーム14、サブウインチ(不図示)、サイドアップシリンダ31などを操作できれば、操縦席18に昇降する必要がなくなって作業効率が向上する。
ジブ着脱工程モードでは、はじめに図8(a)に示すように、ジャッキアップ確認画面が表示される。ジャッキアップ確認画面において、ジャッキアップが完了していれば設定ボタンF2を押してジブ着脱画面に進み、ジャッキアップが完了していなければ設定ボタンF3を押してモードセレクト画面に戻る。そして、ジブ着脱工程では、図8(b)に示すように、旋回レバースイッチS1、起伏レバースイッチS2、サブウインチレバースイッチS3、メインウインチレバースイッチS4によって、伸縮シリンダ55、起伏シリンダ54(又はジブチルトシリンダ)、サブウインチモータ57、メインウインチモータ56(又はサイドアップシリンダ31)を駆動することによってブーム14やジブ30を操作して、ジブ30をブーム14の先端に取り付けたり、取り外したりする。また、設定ボタンF1を押すことで、起伏レバースイッチS2に対応するアクチュエータの動作を、ブーム起伏又はジブチルトに切換えることができる。さらに、設定ボタンF3を押すことで、メインウインチレバースイッチS4に対応するアクチュエータの動作を、メインウインチ又はサイドアップ/ダウンに切換えることができる。このジブ着脱工程は手順が複雑で、着脱作業に不慣れな作業員が作業することは困難であるため、クレーンのオペレータが操縦席18から出て手作業で準備をしなければならない。ところが、ラフテレーンクレーン1やオールテレーンクレーンでは、操縦席18の昇降に時間がかかるため、作業効率が悪くなっていた。そこで、遠隔操作装置40を用いることによって、オペレータはジブ30の近くにいながらにしてブーム14、サブウインチ(不図示)、サイドアップシリンダ31などを操作できれば、操縦席18に昇降する必要がなくなって作業効率が向上する。
ここにおいて、理解を容易にするためにジブ着脱手順について簡単に説明する。まずジブ装着では、ジブ30を格納状態からブーム14下面へ移動し、ブーム14先端のリンクにテンションロッド20を接続してジブセットピンを挿しこみ、補助ロープを取り付けてジブ30をブーム14から振り出す準備をし、ジブ30をブーム14から振り出し、ジブチルトシリンダを伸長してジブ30を作業状態まで振り上げる。次に、ジブ格納では、ジブチルトシリンダを全縮小してジブ30を吊り下がった状態とし、補助ロープを取り付けてジブ30をブーム14に固定する準備をし、ジブ30をブーム14下面に引き込んでブーム14に固定し、ジブセットピンを抜いてブーム14先端のリンクからテンションロッド20を取り外し、ジブ30をブーム14下面から側面に引き寄せる。
上述したジブ装着においては、手作業、ブーム14の起伏、サブウインチの巻上/巻下が実施される。例えば、ジブ30をブーム14から振り出す手順では、起伏レバースイッチS2を親指で下に倒しつつトリガ45を人差し指で引くことでブーム14を起こし、次に手作業で補助ロープの一端をジブ30先端に通してブーム14基端寄りの位置に掛止する。そして、手作業で補助ロープの他端を補巻フックに取り付け、補助ロープが張り過ぎない程度に、サブウインチレバーS3を親指で下に倒しつつトリガ45を人差し指で引くことでサブウインチを巻き上げる。次に、手作業で安全ロープをジブ30先端から外し、起伏レバースイッチS2を親指で下に倒しつつトリガ45を人差し指で引くことでブーム14をさらに起こす。その後、ブーム14を少し伸ばしたうえで、サブウインチを巻き下げてジブ30が地面と垂直になるようにする。さらに、サブウインチを巻き下げながら、ブーム14を倒して手作業で補助ロープを外す。なお、この際には、親指で起伏レバースイッチS2とサブウインチレバースイッチS3の両方を上に倒しつつトリガ45を人差し指で引く。この後、さらに作業が続く。
(アウトリガ張出・格納工程モード)
アウトリガ張出・格納工程モードでは、図9に示すように、表示部43内の左にアウトリガ張出・格納工程モードであることがアイコンによって表示され、その右には以下で説明する4つの工程のどの工程が選択されているか表示される。そして、設定ボタンF1を押すことで、スライド張出・格納画面とジャッキ張出・格納画面とが切り替わる。スライド張出・格納画面では、設定ボタンF2を押すことでスライド張出とスライド格納とが切り替わる。ジャッキ張出・格納画面では、設定ボタンF2を押すことでジャッキ張出とジャッキ格納とが切り替わる。そして、4本のアウトリガ11、・・・に対応するスイッチS1~S4を親指で倒しつつトリガ45を人差し指で引くことによって、各アウトリガ11を操作する。ジャッキ張出手順では、例えば、狭い場所で右側のみアウトリガ11を使用する場合には、図10(a)に示すように、親指で右側の2つのレバースイッチS3、S4を同時に倒すことで右前のアウトリガ11及び右後のアウトリガ11を伸ばすことができる。同様に、前側のみアウトリガ11を伸縮させる場合には、図10(b)に示すように、親指で中央の2つのレバースイッチS2、S3を同時に倒すことで右前のアウトリガ11及び左前のアウトリガ11を伸縮させることができる。
アウトリガ張出・格納工程モードでは、図9に示すように、表示部43内の左にアウトリガ張出・格納工程モードであることがアイコンによって表示され、その右には以下で説明する4つの工程のどの工程が選択されているか表示される。そして、設定ボタンF1を押すことで、スライド張出・格納画面とジャッキ張出・格納画面とが切り替わる。スライド張出・格納画面では、設定ボタンF2を押すことでスライド張出とスライド格納とが切り替わる。ジャッキ張出・格納画面では、設定ボタンF2を押すことでジャッキ張出とジャッキ格納とが切り替わる。そして、4本のアウトリガ11、・・・に対応するスイッチS1~S4を親指で倒しつつトリガ45を人差し指で引くことによって、各アウトリガ11を操作する。ジャッキ張出手順では、例えば、狭い場所で右側のみアウトリガ11を使用する場合には、図10(a)に示すように、親指で右側の2つのレバースイッチS3、S4を同時に倒すことで右前のアウトリガ11及び右後のアウトリガ11を伸ばすことができる。同様に、前側のみアウトリガ11を伸縮させる場合には、図10(b)に示すように、親指で中央の2つのレバースイッチS2、S3を同時に倒すことで右前のアウトリガ11及び左前のアウトリガ11を伸縮させることができる。
(効果)
次に、本実施例のアクチュエータの遠隔操作装置1の奏する効果を列挙して説明する。
次に、本実施例のアクチュエータの遠隔操作装置1の奏する効果を列挙して説明する。
(1)上述してきたように、本実施例の移動式クレーンのアクチュエータの遠隔操作装置40は、手で把持される把持部41とアクチュエータを操作するための操作面42とを有する装置本体と、アクチュエータを選択するための複数の選択手段としてのレバースイッチS1~S4であって、それぞれ操作面42に配置され、中立位置から第1方向又は第2方向への移動によって選択されたアクチュエータの動作方向を正方向又は逆方向に設定する、複数の選択手段としてのレバースイッチS1~S4と、把持部41の近傍に配置され、レバースイッチS1~S4によって選択されたアクチュエータを、正方向又は逆方向に操作量に応じた速度で動作させるトリガ45と、を備え、複数のレバースイッチS1~S4のうち、移動式クレーンの作業準備工程において使用頻度の最も高いアクチュエータに対応する2つのレバースイッチS2、S3が、操作面42の中央近傍に隣接して配置されている。このため、遠隔操作装置40を片手で持って、作業準備工程において使用頻度の高いレバースイッチS2、S3を、親指で操作しやすい遠隔操作装置40となる。
つまり、作業準備工程では、オペレータは操縦席18から出て手作業で準備しなければならない。このため、従来は、アクチュエータを操作するために操縦席18に戻っても、その後、またすぐに外に出て手作業で準備しなければならず、作業効率が悪かった。そこで、遠隔操作装置40を用いることで、オペレータは操縦席18の外でアクチュエータを操作できるため、操作のためにわざわざ操縦席18に昇降する必要がなくなる。さらに、使用頻度の高いアクチュエータに対応する2つのレバースイッチS2、S3を中央寄りに配置することで、一方の手の親指で遠隔操作装置40を操作してアクチュエータを動作させつつ、他方の手で作業することもできる。さらに、2つのレバースイッチS2、S3の同時操作によって、2つのアクチュエータを同時に動作させることもできる。
(2)また、移動式クレーンの作業準備工程、特に敷板吊工程とジブ着脱工程、において使用頻度の最も高い、起伏レバースイッチS2とサブウインチレバースイッチS3が操作面42の中央近傍に隣接して配置されているため、作業準備工程を効率よく実施できる。すなわち、例えばジブ着脱工程においては、ジブ30を振出したり、ブーム14に引き寄せる際に、ブーム14を起伏させたりサブウインチを巻上げ/巻下げることが多いところ、これらに対応するレバースイッチS2、S3を中央寄りに配置することで操作しやすくなる。さらに、ジブ30の振出手順において、ブーム14を倒伏させつつウインチを巻下げる同時作業を実現できる。
(3)さらに、4つのレバースイッチS1~S4を備えており、4つのレバースイッチS1~S4は、操作面42の左から順に、旋回レバースイッチS1、起伏レバースイッチS2、サブウインチ(補巻)レバースイッチS3、メインウインチ(主巻)レバースイッチS4とされている。この配置は、操縦席18内のレバー配置(旋回、起伏、伸縮、サブウインチ、メインウインチの順)とほぼ共通しているため、操作者が配列を覚えやすくなり、誤操作を防止できる。
(4)また、複数の選択手段に割り当てられるアクチュエータを切り替えるモード切替手段をさらに備え、モード切替手段は、各モードに対応する複数の設定ボタンF1~F3と、設定ボタンF1~F3によるモード切替えを可能な状態とするモードボタン46と、から構成されている。このうち、設定ボタンF1~F3は、移動式クレーンの敷板吊工程モードに対応する設定ボタンF1、ジブ着脱工程モードに対応する設定ボタンF3、アウトリガ張出・格納工程モードに対応する設定ボタンF2の3つから構成される。このようにモードを切り替えることで、限られた数の操作手段で多数のアクチュエータを遠隔操作することができる。なお、本実施例では、3つのモードすべてに切替え可能な場合について説明したが、これに限定されるものではなく、少なくともいずれか2つのモードを切替え可能であればよい。
加えて、各準備工程において、1つのレバースイッチを2通りのアクチュエータに切換えて使用できるようになっている。例えば、ジブ着脱工程モードでは、設定ボタンF1を押すことで、起伏スイッチS2が、ブーム起伏又はジブチルトに切り替わる。また、サイドアップシリンダ31の張出・格納は、ジブ着脱工程モードにおいて使用頻度の低いメインウインチとの切り換えとなっている。さらに、切り替わるレバースイッチS2、S4の同軸上に設定ボタンF1、F3が配置されていることによって、操作者の認識を合わせて誤操作を防止できる。
(5)また、4つのレバースイッチS1~S4を備えており、アウトリガ張出・格納工程モードにおいては、4つのレバースイッチS1~S4に操作面42の左から順に、後左アウトリガレバースイッチS1、前左アウトリガレバースイッチS2、前右アウトリガレバースイッチS3、後右アウトリガレバースイッチS4が割り当てられている。このため、前側にある2つのアウトリガ11、11のみの同時操作や、右側にある2つのアウトリガ11、11のみの同時操作や、左側にある2つのアウトリガ11、11のみの同時操作が可能となる。
以上、図面を参照して、本発明の実施例を詳述してきたが、具体的な構成は、この実施例に限らず、本発明の要旨を逸脱しない程度の設計的変更は、本発明に含まれる。
例えば、実施例では、クレーンモードと、ジブ着脱工程モードと、アウトリガ張出・格納工程モードと、を備える場合について説明したが、これに限定されるものではなく、クレーンモードとジブ着脱工程モードの2つのみを切り替える構成にすることもできる。
1:ラフテレーンクレーン(移動式クレーン);
10:車体;11:アウトリガ;12:旋回台;14:ブーム;15:起伏シリンダ;
30:ジブ;20:テンションロッド;31:サイドアップシリンダ;
40:遠隔操作装置;41:把持部;42:操作面;43:表示部;45:トリガ;
46:モードボタン;
F1~F3:ボタン;S1:旋回レバースイッチ;S2:起伏レバースイッチ;S3:伸縮レバースイッチ;S4:メインウインチレバースイッチ;
51:ジャッキシリンダ;52:スライドシリンダ;53:旋回モータ;54:起伏シリンダ;55:伸縮シリンダ;56:メインウインチモータ;57:サブウインチモータ;
71:旋回レバー;72:起伏レバー;73:伸縮レバー;74:メインウインチレバー
10:車体;11:アウトリガ;12:旋回台;14:ブーム;15:起伏シリンダ;
30:ジブ;20:テンションロッド;31:サイドアップシリンダ;
40:遠隔操作装置;41:把持部;42:操作面;43:表示部;45:トリガ;
46:モードボタン;
F1~F3:ボタン;S1:旋回レバースイッチ;S2:起伏レバースイッチ;S3:伸縮レバースイッチ;S4:メインウインチレバースイッチ;
51:ジャッキシリンダ;52:スライドシリンダ;53:旋回モータ;54:起伏シリンダ;55:伸縮シリンダ;56:メインウインチモータ;57:サブウインチモータ;
71:旋回レバー;72:起伏レバー;73:伸縮レバー;74:メインウインチレバー
Claims (5)
- 移動式クレーンのアクチュエータの遠隔操作装置であって、
手で把持される把持部と前記アクチュエータを操作するための操作面とを有する装置本体と、
前記アクチュエータを選択するための複数の選択手段であって、それぞれ前記操作面に配置され、中立位置から第1方向又は第2方向への移動によって選択された前記アクチュエータの動作方向を正方向又は逆方向に設定する、複数の選択手段と、
前記把持部の近傍に配置され、前記選択手段によって選択されたアクチュエータを、正方向又は逆方向に操作量に応じて動作させるトリガ手段と、を備え、
複数の前記選択手段のうち、前記移動式クレーンの作業準備工程において使用頻度の最も高い2つの選択手段が、前記操作面の中央近傍に隣接して配置されている、遠隔操作装置。 - 前記移動式クレーンの作業準備工程において使用頻度の最も高い、起伏レバースイッチと補巻レバースイッチが前記操作面の中央近傍に隣接して配置されている、請求項1に記載された遠隔操作装置。
- 4つの前記選択手段を備えており、
4つの前記選択手段は、前記操作面の左から順に、旋回レバースイッチ、起伏レバースイッチ、補巻レバースイッチ、主巻レバースイッチである、請求項2に記載された遠隔操作装置。 - 複数の前記選択手段に割り当てられるアクチュエータを切り換えるモード切替手段をさらに備え、
前記モード切替手段は、各モードに対応する複数の設定ボタンと、前記設定ボタンによるモード切替えを可能な状態とするモードボタンと、から構成され、
前記設定ボタンは、前記移動式クレーンの敷板吊工程モード、ジブ着脱工程モード、アウトリガ張出・格納工程モードの3つのモードのうち少なくとも2つのモードに対応するようにされている、請求項1乃至請求項3のいずれか一項に記載された遠隔作装置。 - 4つの前記選択手段を備えており、
アウトリガ張出・格納工程モードにおいては、4つの前記選択手段に前記操作面の左から順に、後左アウトリガレバースイッチ、前左アウトリガレバースイッチ、前右アウトリガレバースイッチ、後右アウトリガレバースイッチが割り当てられている、請求項4に記載された遠隔操作装置。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201680031257.0A CN108025895B (zh) | 2015-10-01 | 2016-09-27 | 远程操作装置 |
EP16851476.8A EP3357855B1 (en) | 2015-10-01 | 2016-09-27 | Remote control device |
US15/574,733 US20180148302A1 (en) | 2015-10-01 | 2016-09-27 | Remote control device |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2015196269A JP6672681B2 (ja) | 2015-10-01 | 2015-10-01 | 遠隔操作装置 |
JP2015-196269 | 2015-10-01 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2017057305A1 true WO2017057305A1 (ja) | 2017-04-06 |
Family
ID=58423590
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2016/078335 WO2017057305A1 (ja) | 2015-10-01 | 2016-09-27 | 遠隔操作装置 |
Country Status (5)
Country | Link |
---|---|
US (1) | US20180148302A1 (ja) |
EP (1) | EP3357855B1 (ja) |
JP (1) | JP6672681B2 (ja) |
CN (1) | CN108025895B (ja) |
WO (1) | WO2017057305A1 (ja) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2021246240A1 (ja) * | 2020-06-02 | 2021-12-09 | コベルコ建機株式会社 | クレーンの制御装置 |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP3284869A4 (en) * | 2015-04-13 | 2019-01-09 | Volvo Construction Equipment AB | HYDRAULIC DEVICE FOR A CONSTRUCTION MACHINE AND CONTROL PROCESS THEREFOR |
USD916418S1 (en) * | 2018-02-28 | 2021-04-13 | Tadano Ltd. | Operation device for crane |
JP7047538B2 (ja) * | 2018-03-29 | 2022-04-05 | 株式会社タダノ | 遠隔操作端末および遠隔操作端末を備える作業車両 |
JP7059703B2 (ja) * | 2018-03-09 | 2022-04-26 | 株式会社タダノ | 遠隔操作端末および遠隔操作端末を備える作業車両 |
JP7010072B2 (ja) | 2018-03-09 | 2022-01-26 | 株式会社タダノ | 作業車両 |
EP3763660B1 (en) * | 2018-03-09 | 2023-10-18 | Tadano Ltd. | Remote operation terminal and work vehicle comprising remote operation terminal |
WO2019189320A1 (ja) | 2018-03-28 | 2019-10-03 | 株式会社タダノ | 作業車両 |
CN111689398A (zh) * | 2020-06-15 | 2020-09-22 | 浙江三一装备有限公司 | 交互方法、装置及智能终端 |
CN112919328A (zh) * | 2021-01-22 | 2021-06-08 | 浙江三一装备有限公司 | 起重机的操控部件控制方法及装置 |
USD1023981S1 (en) * | 2022-03-15 | 2024-04-23 | Stellar Industries, Inc. | Crane remote control device |
USD1026393S1 (en) * | 2022-04-19 | 2024-05-07 | Stellar Industries, Inc. | Crane remote control device |
USD1026045S1 (en) * | 2022-05-06 | 2024-05-07 | Stellar Industries | Crane remote control device |
WO2024043852A1 (en) * | 2023-04-24 | 2024-02-29 | Elfatek Elektroni̇k Maki̇na Ve Otomasyonu Sanayi̇ Ti̇caret Li̇mi̇ted Şi̇rketi̇ | An authorizable industrial control handle with operator feedback feature |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4508014A (en) * | 1982-06-08 | 1985-04-02 | U.S. Truck Cranes, Inc. | Remote control apparatus for a machine such as a crane |
JPH0522472U (ja) * | 1991-08-30 | 1993-03-23 | 株式会社タダノ | 移動式クレーン |
JP2740035B2 (ja) * | 1990-03-16 | 1998-04-15 | 株式会社神戸製鋼所 | ホイール式クレーンの操作装置 |
JP2000296985A (ja) * | 1999-02-12 | 2000-10-24 | Maeda Seisakusho Co Ltd | 産業機械の遠隔操作用送信機 |
JP2003073073A (ja) * | 2001-08-31 | 2003-03-12 | Furukawa Co Ltd | 油圧アクチュエータの遠隔制御装置 |
JP2003204583A (ja) * | 2002-01-08 | 2003-07-18 | Fuji Heavy Ind Ltd | ナビゲーション用リモコン |
JP2011063379A (ja) * | 2009-09-17 | 2011-03-31 | Furukawa Unic Corp | クレーンの状態表示装置 |
JP2012156684A (ja) * | 2011-01-25 | 2012-08-16 | Panasonic Corp | 照明器具用リモコン |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11171473A (ja) * | 1997-12-09 | 1999-06-29 | Matsushita Electric Ind Co Ltd | クレーン用無線操縦装置 |
JPH11228074A (ja) * | 1998-02-16 | 1999-08-24 | Tadano Ltd | 移動式クレーンの携帯型操作入力部の操作内容報知装置 |
JP4116139B2 (ja) * | 1998-03-13 | 2008-07-09 | 株式会社タダノ | クレーン車の遠隔操作装置 |
JP2000296958A (ja) * | 1999-04-09 | 2000-10-24 | Dainippon Screen Mfg Co Ltd | 無版デジタル印刷装置 |
JP2008019062A (ja) * | 2006-07-13 | 2008-01-31 | Tadano Ltd | クレーンの自動格納制御装置 |
CN201338914Y (zh) * | 2009-01-20 | 2009-11-04 | 廊坊市管道人机械设备有限公司 | 一种基于遥控技术的吊管机 |
CN203529759U (zh) * | 2013-09-27 | 2014-04-09 | 徐州重型机械有限公司 | 一种起重机通讯系统 |
-
2015
- 2015-10-01 JP JP2015196269A patent/JP6672681B2/ja active Active
-
2016
- 2016-09-27 US US15/574,733 patent/US20180148302A1/en not_active Abandoned
- 2016-09-27 EP EP16851476.8A patent/EP3357855B1/en active Active
- 2016-09-27 WO PCT/JP2016/078335 patent/WO2017057305A1/ja active Application Filing
- 2016-09-27 CN CN201680031257.0A patent/CN108025895B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4508014A (en) * | 1982-06-08 | 1985-04-02 | U.S. Truck Cranes, Inc. | Remote control apparatus for a machine such as a crane |
JP2740035B2 (ja) * | 1990-03-16 | 1998-04-15 | 株式会社神戸製鋼所 | ホイール式クレーンの操作装置 |
JPH0522472U (ja) * | 1991-08-30 | 1993-03-23 | 株式会社タダノ | 移動式クレーン |
JP2000296985A (ja) * | 1999-02-12 | 2000-10-24 | Maeda Seisakusho Co Ltd | 産業機械の遠隔操作用送信機 |
JP2003073073A (ja) * | 2001-08-31 | 2003-03-12 | Furukawa Co Ltd | 油圧アクチュエータの遠隔制御装置 |
JP2003204583A (ja) * | 2002-01-08 | 2003-07-18 | Fuji Heavy Ind Ltd | ナビゲーション用リモコン |
JP2011063379A (ja) * | 2009-09-17 | 2011-03-31 | Furukawa Unic Corp | クレーンの状態表示装置 |
JP2012156684A (ja) * | 2011-01-25 | 2012-08-16 | Panasonic Corp | 照明器具用リモコン |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2021246240A1 (ja) * | 2020-06-02 | 2021-12-09 | コベルコ建機株式会社 | クレーンの制御装置 |
Also Published As
Publication number | Publication date |
---|---|
EP3357855A4 (en) | 2019-06-19 |
JP6672681B2 (ja) | 2020-03-25 |
US20180148302A1 (en) | 2018-05-31 |
JP2017065911A (ja) | 2017-04-06 |
CN108025895B (zh) | 2020-03-03 |
CN108025895A (zh) | 2018-05-11 |
EP3357855A1 (en) | 2018-08-08 |
EP3357855B1 (en) | 2021-05-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2017057305A1 (ja) | 遠隔操作装置 | |
EP3363763B1 (en) | Remote operation device and guidance system | |
JP6231727B1 (ja) | 遠隔操作端末および移動式クレーンの遠隔操作システム | |
EP3763661A1 (en) | Crane | |
WO2017061573A1 (ja) | 作業機 | |
JP5546821B2 (ja) | クレーンの状態表示装置 | |
JP2008019062A (ja) | クレーンの自動格納制御装置 | |
JP3614498B2 (ja) | 作業車の作業状態模擬確認装置 | |
JP6784103B2 (ja) | 画像表示装置 | |
WO2017183576A1 (ja) | 移動式クレーンの緊急停止装置 | |
JP4102061B2 (ja) | クレーンのフック格納装置 | |
JP5809082B2 (ja) | クレーンの携帯式遠隔操作装置 | |
JP4988990B2 (ja) | クレーンのジブ起伏制御装置 | |
JP5805370B2 (ja) | 車両搭載型クレーン | |
JP4447107B2 (ja) | 車載式クレーンのブーム制御装置 | |
JP4116338B2 (ja) | 車載式クレーンのジブ駆動制御装置 | |
JP2023075793A (ja) | クレーン装置及び制御プログラム | |
JP2023026963A (ja) | 携帯型の遠隔操作機 | |
JP2019043690A (ja) | 作業車両 | |
JP2019001600A (ja) | 作業車両 | |
JPH11157800A (ja) | 作業台ユニット |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 16851476 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 15574733 Country of ref document: US |
|
NENP | Non-entry into the national phase |
Ref country code: DE |