WO2021090439A1 PCT/JP2019/043674 JP2019043674W WO2021090439A1 WO 2021090439 A1 WO2021090439 A1 WO 2021090439A1 JP 2019043674 W JP2019043674 W JP 2019043674W WO 2021090439 A1 WO2021090439 A1 WO 2021090439A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel pipe
pile
road structure
eccentric
road
Prior art date
Application number
PCT/JP2019/043674
Other languages
English (en)
French (fr)
Inventor
仁志 尾添
聡 松永
啓介 塩田
Original Assignee
Jfeシビル株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jfeシビル株式会社 filed Critical Jfeシビル株式会社
Priority to PCT/JP2019/043674 priority Critical patent/WO2021090439A1/ja
Priority to JP2021554967A priority patent/JP7371113B2/ja
Priority to PCT/JP2020/041331 priority patent/WO2021090873A1/ja
Priority to PH12021550584A priority patent/PH12021550584A1/en
Publication of WO2021090439A1 publication Critical patent/WO2021090439A1/ja
Priority to JP2023179392A priority patent/JP7490128B2/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C1/00Design or layout of roads, e.g. for noise abatement, for gas absorption
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/24Bridges or similar structures, based on land or on a fixed structure and designed to give access to ships or other floating structures
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Definitions

  • the present invention relates to a road structure capable of securing the slope and width required for a road without being affected by the terrain when constructing a road in a mountainous area, a formwork jig used for construction of the road structure, and a road structure. Regarding the construction method.
  • a pile head block is joined on a steel pipe pile to be driven into the ground, a girder is installed on the pile head block, and a road slab is placed on the girder.
  • a road slab is placed on the girder.
  • superstructures such as girders and floor slabs are directly provided on the upper part of the steel pipe pile protruding from the slope, and the steel pipe pile protrudes for terrain where the slope depth is deep with respect to the planned road surface. The length becomes great. In this case, the error in the position of the pile head of the steel pipe pile becomes large due to the influence of the accuracy of driving the steel pipe pile and the accuracy of the steel pipe pile.
  • the pile head block and girder must be installed by adjusting the error of the position of each pile head of a plurality of steel pipe piles due to the influence of the terrain, so that the construction period for installing the road structure is prolonged. There was a problem that the cost also increased.
  • the present invention solves the above problems, and is a road structure capable of ensuring installation accuracy regardless of the terrain and suppressing the construction period and cost, a formwork jig used for the construction of the road structure, and a construction method of the road structure.
  • the purpose is to provide.
  • the road structure according to the present invention includes a steel pipe pile including a first steel pipe pile and a second steel pipe pile placed in parallel in the first direction in which the road extends and the second direction intersecting the first direction.
  • a girder member that connects a steel pipe column connected above the first steel pipe pile, an upper end grade steel pipe installed at the upper end of the second steel pipe pile or the steel pipe column, and two adjacent upper end grade steel pipes.
  • the first steel pipe pile the second steel pipe pile, the steel pipe strut, and the upper end grade steel pipe.
  • the joint portion between the lower member and the upper member is the central axis of the lower member and the upper member. It is joined by an eccentric joining member that can be joined in a state where the central axis of the member is eccentric.
  • the form jig according to the present invention is connected to a steel pipe pile placed in parallel in the first direction in which the road extends and the second direction intersecting the first direction, and above the steel pipe pile.
  • a steel pipe strut and a steel pipe pile or a graded steel pipe installed on the steel pipe strut are provided, and among the steel pipe pile, the steel pipe strut, and the graded steel pipe, a member located below is used as a lower member.
  • the member joined above the lower member is an upper member
  • the joint portion between the lower member and the upper member is in a state where the central axis of the lower member and the central axis of the upper member are eccentric.
  • the eccentric joining member includes a tubular body, and the tubular body is installed so as to surround the outer peripheral surface of the steel pipe pile or the steel pipe column, and the tubular body and the steel pipe pile or
  • the gap formed between the steel pipe column and the steel pipe column is a mold jig used when installing the eccentric joining member of the road structure, which is filled with a filler, and surrounds the outer peripheral surface of the lower member.
  • a mold plate installed in contact with the lower end of the cylinder, an adjustment bolt for adjusting and fixing the horizontal position of the cylinder, the mold plate and the adjustment bolt are supported and detachably attached to the lower member. It is provided with a bracket to be fixed.
  • the construction method of the road structure according to the present invention is connected to a steel pipe pile to be driven into the ground in parallel in a first direction in which the road extends and a second direction intersecting the first direction, and above the steel pipe pile.
  • a steel pipe strut and a steel pipe pile or a graded steel pipe installed on the steel pipe strut are provided, and a member located below the steel pipe pile, the steel pipe strut, and the graded steel pipe is used as a lower member.
  • the member joined above the lower member is an upper member
  • the joint portion between the lower member and the upper member is in a state in which the central axis of the lower member and the central axis of the upper member are eccentric.
  • the eccentric joining member improves the position accuracy of the pile head even in a pile having a large protrusion length from the ground, and can suppress the adjustment of the position accuracy of the upper end grade steel pipe and the girder member. Regardless of the construction period and cost, the road structure can be installed.
  • FIG. It is a schematic diagram of the road structure 100 which concerns on Embodiment 1.
  • FIG. It is explanatory drawing of the cross-sectional structure of the AA part of the road structure 100 of FIG. It is explanatory drawing of the cross-sectional structure of the BB part of the road structure 100 of FIG. It is explanatory drawing of the cross-sectional structure of the CC part of the road structure 100 of FIG. It is a layout drawing of the girder member 41 of the road structure 100 of FIG. It is explanatory drawing of the cross-sectional structure around the upper end grade point steel pipe 50a of the road structure 100 which concerns on Embodiment 1.
  • FIG. It is a top view of the upper end grade point steel pipe 50a of the road structure 100 which concerns on Embodiment 1.
  • FIG. 1 It is explanatory drawing of the cross-sectional structure around the intermediate grade steel pipe 50b of the road structure 100 which concerns on Embodiment 1.
  • FIG. It is a top view of the intermediate grade steel pipe 50b of the road structure 100 which concerns on Embodiment 1.
  • FIG. 1 It is explanatory drawing of the cross-sectional structure around the intermediate grade steel pipe 150b which is a modification of the intermediate grade steel pipe 50b of the road structure 100 which concerns on Embodiment 1.
  • FIG. It is explanatory drawing of the cross-sectional structure of an example of the intermediate grade steel pipe 150b which is a modification of the intermediate grade steel pipe 50b of the road structure 100 which concerns on Embodiment 1.
  • FIG. It is a schematic diagram of the road structure 100 and the road structure 1000 of the comparative example which concerns on Embodiment 1.
  • FIG. It is explanatory drawing of the cross-sectional structure around the upper end grade point steel pipe 250a of the road structure 200 which concerns on Embodiment 2.
  • FIG. It is a top view of the upper end grade point steel pipe 250a of the road structure 200 which concerns on Embodiment 2.
  • FIG. It is a side view of the structure around the intermediate grade steel pipe 250b of the road structure 200 which concerns on Embodiment 2.
  • FIG. It is explanatory drawing of the state in which the steel pipe pile 20 is built in the hole 95. It is explanatory drawing of the structure of the formwork jig 70 used in the temporary joining process of Embodiment 3.
  • FIG. 1 This is an example of a grade girder in which an upper end grade steel pipe 250a and a cross girder 41b are integrated.
  • FIG. 1 is a schematic view of the road structure 100 according to the first embodiment.
  • FIG. 2 is an explanatory view of a cross-sectional structure of a portion AA of the road structure 100 of FIG.
  • FIG. 3 is an explanatory view of the cross-sectional structure of the BB portion of the road structure 100 of FIG.
  • FIG. 4 is an explanatory view of the cross-sectional structure of the CC portion of the road structure 100 of FIG.
  • FIG. 5 is a layout diagram of the girder member 41 of the road structure 100 of FIG.
  • the road structure 100 is installed on a ground with large undulations such as a mountainous area.
  • the road structure 100 is used, for example, when a road is provided along a slope in a mountainous area, when an existing road provided along the slope is widened, or when a road is passed across a swamp in a mountainous area. It is a structure. In the first embodiment, the road structure 100 installed along the slope of the mountainous area will be described.
  • the road structure 100 includes a plurality of steel pipe piles 20 placed in the ground 90.
  • the steel pipe pile 20 is built in a hole provided in the ground 90 so that the pile head 12 projects from the surface 94 of the ground 90.
  • the ground 90 penetrates the sedimentary layer 92 by a down-the-hole hammer or the like, and is drilled to the support layer 93.
  • the steel pipe pile 20 is erected in the ground 90 by building the steel pipe pile 20 in the hole provided in the ground 90 and filling the hole with a filler such as mortar.
  • a plurality of steel pipe piles 20 are driven into the ground 90 in parallel with the first direction in which the road extends.
  • the girder member 41 is arranged so as to be bent along a slope or the like, and the road is configured by installing a road slab 99 on the girder member 41.
  • the first direction is the direction along this road.
  • the plurality of steel pipe piles 20 of the road structure 100 include a first steel pipe pile 20a and a second steel pipe pile 20b.
  • a steel pipe column 30 is connected to the first steel pipe pile 20a above. The steel pipe column 30 is joined to the upper end of the first steel pipe pile 20a according to the height from the surface 94 of the ground 90 on which the road slab 99 and the girder member 41 are installed.
  • the triangular symbol shown in FIG. 1 indicates the joint portion 11 between the first steel pipe pile 20a and the steel pipe column 30.
  • the eccentric joining member 60 (see FIGS. 6 and 8) joins the lower member located on the ground 90 side and the upper member joined above the lower member.
  • the columnar structure erected on the ground 90 may be referred to as a support pile 10.
  • the structure in which the above-mentioned first steel pipe pile 20a and the steel pipe column 30 are joined may be referred to as a support pile 10a.
  • the steel pipe column 30 is joined to the pile head 21a of the first steel pipe pile 20a and extends upward.
  • An upper end grade steel pipe 50a is joined to the pile head 12 of the steel pipe column 30.
  • the upper end grade point steel pipe 50a is joined to the pile head 12 of the steel pipe column 30 by using an eccentric joining member 60.
  • the upper end grade steel pipe 50a is connected to the upper end grade steel pipe 50a adjacent to each other in the first direction by a girder member 41.
  • the girder member 41 installed along the first direction is particularly referred to as a vertical girder 41a.
  • the upper end grade steel pipe 50a is connected to the adjacent upper end grade steel pipe 50a in parallel in the second direction intersecting the first direction by a girder member 41.
  • the girder member 41 installed along the second direction is particularly referred to as a cross girder 41b.
  • two steel pipe piles 20 are arranged along the second direction intersecting the first direction.
  • the cross girder 41b connects the pile heads 12 arranged in the second direction.
  • the girder member 41 is installed along the first direction and the second direction, and connects the pile heads 12 of the support piles 10 via the upper end grade point steel pipe 50a, respectively.
  • a floor slab fixing member 42 is installed on the upper surface of the girder member 41 and the upper end grade steel pipe 50a.
  • the road floor slab 99 is fixed to the girder member 41 and the upper end grade steel pipe 50a via the floor slab fixing member 42.
  • Two or more steel pipe piles 20 may be arranged in the second direction intersecting the first direction.
  • the cross girder 41b is provided with a connecting portion 43 at the center.
  • a vertical girder 41a is connected to the connecting portion 43.
  • the vertical girder 41a connected to the connecting portion 43 connects the connecting portions 43 of the horizontal girders 41b adjacent to each other in the first direction.
  • the upper end grade steel pipe 50a is connected to the upper side of the second steel pipe pile 20b.
  • the upper end grade point steel pipe 50a is joined to the pile head 12 of the second steel pipe pile 20b by using an eccentric joining member 60.
  • the upper end grade steel pipe 50a joined to the second steel pipe pile 20b is the same as the upper end grade steel pipe 50a joined to the support pile 10a with the upper end grade steel pipe 50a adjacent to each other in the first direction and the second direction. It is connected.
  • the second steel pipe pile 20b may be referred to as a support pile 10b.
  • the support pile 10a is provided with an intermediate grade steel pipe 50b.
  • the intermediate grade steel pipe 50b is installed in the central portion of the steel pipe column 30 of the support piles 10a. That is, the intermediate grade steel pipe 50b is provided on the support pile 10a having a large protrusion length from the ground 90 in the road structure 100.
  • the intermediate grade steel pipe 50b is connected to the intermediate grade steel pipe 50b provided on the adjacent steel pipe columns 30 by a beam member 40.
  • the beam member 40 installed along the first direction is particularly referred to as a vertical beam 40a.
  • the intermediate grade steel pipe 50b is connected to the intermediate grade steel pipe 50b installed on the supporting piles 10 adjacent to each other in the second direction intersecting the first direction by the beam member 40.
  • the beam member 40 installed along the second direction is particularly referred to as a cross beam 40b.
  • the beam member 40 may be installed at an angle as shown in FIGS. 1 and 3, or may be installed horizontally as shown in FIG. Further, the intermediate grade steel pipe 50b is not limited to the one installed on the steel pipe column 30 as shown in FIGS. 1 and 4, and may be installed on the second steel pipe pile 30b as shown in FIG. good.
  • FIG. 6 is an explanatory view of a cross-sectional structure around the upper end grade point steel pipe 50a of the road structure 100 according to the first embodiment.
  • FIG. 7 is a top view of the upper end grade point steel pipe 50a of the road structure 100 according to the first embodiment.
  • the upper end grade point steel pipe 50a and the support pile 10 are joined by an eccentric joining member 60a.
  • the eccentric joining member 60a is a part of the upper end grade steel pipe 50a and is for being combined with the pile head 12 of the support pile 10 so that the position of the upper end grade steel pipe 50a with respect to the pile head 12 can be adjusted. ..
  • the upper end grade point steel pipe 50a can be joined to the support pile 10 by the eccentric joining member 60a even when the positions of the support pile 10 and the central axis are deviated from each other.
  • the eccentric joining member 60a that joins the upper end grade steel pipe 50a and the pile head 12 may be particularly referred to as a first eccentric joining member.
  • the eccentric joint member 60a is composed of at least a steel pipe member 51a and a support member 55a, which are cylinders constituting the upper end grade steel pipe 50a.
  • the steel pipe member 51a has a cylindrical shape.
  • a support member 55a is installed above the inside of the steel pipe member 51a.
  • the support member 55a passes through the central axis C of the cylindrical steel pipe member 51a and is formed by combining plate-shaped members in a cross shape.
  • the steel pipe member 51a is not limited to a cylindrical shape, and may be a cylindrical body having a cross-sectional shape such as a rectangle or a polygon.
  • the upper end grade steel pipe 50a includes a vertical girder joint 52a and a horizontal girder joint 53a to which the girder member 41 is connected.
  • the vertical girder joint 52a, the horizontal girder joint 53a, and the girder member 41 sandwich the end of the vertical girder joint 52a or the horizontal girder joint 53a and the end of the girder member 41 with the splicing plate 44, and bolt. And nuts are used to fix and connect the splicing plate 44 and the ends of the respective members.
  • the upper end grade steel pipe 50a has a plate-shaped member attached to the upper part, and the upper surface 57a is flat.
  • the upper surface 57a may be inclined according to the inclination of the road.
  • a filling hole 56a that penetrates the plate-shaped member is opened in the upper surface 57a.
  • the filling hole 56a is a hole for injecting the filler 80 into the space between the pile head 12 and the steel pipe member 51a, and communicates the outside with the space inside the steel pipe member 51a.
  • the end surface 14 of the pile head 12 of the support pile 10a or 10b abuts on the lower surface of the support member 55a.
  • the position of the upper end grade steel pipe 50a in the central axis direction of the support pile 10, that is, the position in the height direction is determined.
  • the steel pipe member 51a surrounds the outer peripheral surface of the upper end portion of the support pile 10.
  • a gap is formed between the inner surface of the steel pipe member 51a and the outer surface of the support pile 10, and the upper end grade steel pipe 50a has the support pile 10 by the amount of the gap. On the other hand, it can be moved in the horizontal direction. As shown in FIGS.
  • the support member 55a is formed by combining plate-shaped members in a cross shape, but may take other forms.
  • the support member 55a can hold the upper end grade steel pipe 50a on the end surface 14 of the pile head 12, and may have another structure as long as it does not interfere with the injection of the filler 80.
  • the position of the pile head 12 of the support pile 10 may deviate from the assumed position.
  • the position error of the pile head 12 may increase due to the accuracy and joining accuracy of the steel pipe pile 20 and the steel pipe column 30 individually.
  • the steel pipe member 51a of the upper end grade steel pipe 50a has a cylindrical shape and the pile head 12 has a cylindrical shape
  • the inner diameter of the steel pipe member 51a is set to be 300 mm larger than the outer diameter of the pile head 12.
  • the upper end grade steel pipe 50a can be installed at the correct position even if the pile head 12 has a horizontal position error of 100 mm, and the filling property of the filler 80 can be ensured.
  • the filler 80 is filled in the gap between the steel pipe member 51a and the pile head 12 through the filling hole 56a opened in the upper surface 57a of the upper end grade steel pipe 50a.
  • the steel pipe member 51a is open at the bottom. Therefore, in the filling step of the filler 80, the formwork jig 70 (see FIG. 17) is brought into contact with the lower end surface of the steel pipe member 51a to close the opening so that the filler 80 does not leak from below.
  • the formwork jig 70 will be described separately.
  • Projections 54 and 13 are provided on the inner surface of the steel pipe member 51a forming a gap between the steel pipe member 51a filled with the filler 80 and the pile head 12 and the outer surface of the pile head 12.
  • the filler 80 Since the protrusions 54 and 13 mesh with the solidified filler 80, the filler 80 does not shift in the direction along the inner surface of the steel pipe member 51a and the outer surface of the pile head 12, and the upper end grade steel pipe 50a and the support pile.
  • the load transmission to and from 10 can be improved.
  • the protrusions 13 and 54 may be formed by bending a reinforcing bar or a steel bar and fixing them by welding.
  • the steel pipe member 51a and the support pile 10 may be formed of a steel plate material with protrusions.
  • a ribbed steel pipe formed of a striped steel plate having protrusions in the vertical and horizontal directions on the surface of the steel plate and a ribbed steel plate having protrusions having a height of about 2 mm arranged in parallel may be used.
  • the striped steel plate or the ribbed steel pipe it is possible to reduce the construction cost and the process for welding and joining the protrusion 54 to the steel pipe member 51a and the protrusion 13 to the support pile 10.
  • the protrusions 13 and 54 integrally formed in advance improve the fixing strength of the slip prevention protrusion, the steel pipe member 51a of the upper end grade steel pipe 50a can reduce the dimension in the height direction.
  • FIG. 8 is an explanatory view of a cross-sectional structure around an intermediate grade steel pipe 50b of the road structure 100 according to the first embodiment.
  • FIG. 9 is a top view of the intermediate grade steel pipe 50b of the road structure 100 according to the first embodiment.
  • the intermediate grade steel pipe 50b and the support pile 10 are joined by an eccentric joining member 60b.
  • the eccentric joint member 60b is a part of the intermediate grade steel pipe 50b, and is for being combined with the support pile 10 so that the position of the intermediate grade steel pipe 50b with respect to the support pile 10 can be adjusted. That is, the intermediate grade steel pipe 50b can be joined to the support pile 10 by the eccentric joining member 60b even when the positions of the support pile 10 and the central axis are deviated from each other.
  • the eccentric joint member 60b is composed of at least a steel pipe member 51b constituting an intermediate grade steel pipe 50b.
  • the steel pipe member 51b is a tubular body and has a cylindrical shape in the first embodiment.
  • the steel pipe member 51b is not limited to a cylindrical shape, and may be a cylindrical body having a cross-sectional shape such as a rectangle or a polygon.
  • the intermediate grade steel pipe 50b includes a vertical beam joint 52b and a horizontal beam joint 53b to which the beam member 40 is connected.
  • the vertical beam joint 52b, the horizontal beam joint 53b, and the beam member 40 are formed by using a splicing plate 44 to connect the end of the vertical beam joint 52b or the horizontal beam joint 53b and the end of the beam member 40 in the same manner as the girder member 41.
  • the splicing plate 44 and the end portions of the respective members are fixed and connected by sandwiching, bolts and nuts.
  • the steel pipe member 51b of the intermediate grade steel pipe 50b is a tubular body, its ends in the vertical direction are open. Therefore, the upper end of the gap between the steel pipe member 51b and the support pile 10 serves as a filling port 56b and serves as an opening for injecting the filler 80 into the space between the steel pipe member 51b and the support pile 10, and the outside and the steel pipe member 51a It communicates with the internal space.
  • the intermediate grade steel pipe 50b Before the filler 80 is filled, a gap is formed between the inner surface of the steel pipe member 51b and the outer surface of the support pile 10, and the intermediate grade steel pipe 50b has the support pile 10 by the amount of the gap. On the other hand, it can be moved in the horizontal direction.
  • the formwork is applied to the lower end surface of the intermediate grade steel pipe 50b when the intermediate grade steel pipe 50b is attached to the support pile 10.
  • the tool 70 (see FIG. 17) is brought into contact with the intermediate grade steel pipe 50b from below.
  • the formwork jig 70 also has a function of preventing the filler 80 from leaking from the lower opening when the filler 80 is filled.
  • the position of the support pile 10 may deviate from the expected position.
  • the positional error of the support pile 10 may increase due to the accuracy and joining accuracy of the steel pipe pile 20 and the steel pipe column 30 individually.
  • the steel pipe member 51b of the intermediate grade steel pipe 50b has a cylindrical shape and the support pile 10 has a cylindrical shape
  • the inner diameter of the steel pipe member 51b is set to be 300 mm larger than the outer diameter of the support pile 10.
  • Projections 54 and 13 are provided on the inner surface of the steel pipe member 51b and the outer surface of the support pile 10 that form a gap between the steel pipe member 51b filled with the filler 80 and the support pile 10. Since the protrusions 54 and 13 mesh with the solidified filler 80, the filler 80 does not shift in the direction along the inner surface of the steel pipe member 51b and the outer surface of the support pile 10, and the intermediate grade steel pipe 50b and the support pile do not shift. The load transmission to and from 10 can be improved.
  • the protrusions 13 and 54 may be formed by bending a reinforcing bar or a steel bar and fixing them by welding.
  • the steel pipe member 51b and the support pile 10 may be formed of a steel plate material with protrusions.
  • a ribbed steel pipe formed of a striped steel plate having protrusions in the vertical and horizontal directions on the surface of the steel plate and a ribbed steel plate having protrusions having a height of about 2 mm arranged in parallel may be used.
  • the striped steel plate or the ribbed steel pipe it is possible to reduce the construction cost and the process for welding and joining the protrusion 54 to the steel pipe member 51b and the protrusion 13 to the support pile 10.
  • the protrusions 13 and 54 integrally formed in advance improve the fixing strength of the slip prevention protrusion, the steel pipe member 51b of the intermediate grade steel pipe 50b can reduce the dimension in the height direction.
  • FIG. 10 is an explanatory view of a cross-sectional structure around an intermediate grade steel pipe 150b, which is a modification of the intermediate grade steel pipe 50b of the road structure 100 according to the first embodiment.
  • the intermediate grade steel pipe 50b for example, the first steel pipe pile 20a and the steel pipe column 30 can be joined by installing the support member 55b inside the steel pipe member 51b.
  • the intermediate grade steel pipe 150b of the modified example includes a support member 55b having the same structure as the support member 55a provided in the upper end grade steel pipe 50a inside the steel pipe member 51b.
  • the end surface 22a of the pile head 21a of the first steel pipe pile 20a abuts on the lower surface of the support member 55b.
  • the position of the intermediate grade steel pipe 150b in the central axis direction that is, the position in the height direction is determined.
  • a gap is formed between the inner surface of the steel pipe member 51b and the outer surface of the second steel pipe pile 20b, and the intermediate grade steel pipe 150b is formed by the amount of the gap. It can be moved in the horizontal direction with respect to the second steel pipe pile 20b. As shown in FIGS.
  • the support member 55a is formed by combining plate-shaped members in a cross shape, but may take other forms.
  • the support member 55a can hold the intermediate grade steel pipe 150b on the end surface 14 of the pile head 12, and may have another structure as long as it does not interfere with the injection of the filler 80.
  • the end surface 31 of the steel pipe column 30 is placed on the upper surface of the support member 55b.
  • the position of the steel pipe column 30 in the central axis direction that is, the position in the height direction is determined.
  • a gap is formed between the inner surface of the steel pipe member 51b and the outer surface of the steel pipe support column 30, and the steel pipe support column 30 has a gap with respect to the steel pipe member 51b by the amount of the gap. , Can be moved horizontally. From the above, in the intermediate grade steel pipe 150b, the first steel pipe pile 20a which is a lower member and the steel pipe column 30 which is an upper member can be joined in a state where the central axis is eccentric.
  • FIG. 11 is an explanatory view of a cross-sectional structure of an example of an intermediate grade steel pipe 150b, which is a modification of the intermediate grade steel pipe 50b of the road structure 100 according to the first embodiment.
  • the intermediate grade steel pipe 150b may include a bolt 57 screwed from the outside to the inside of the steel pipe member 51b.
  • the bolt 57 adjusts the positions of the lower member and the upper member constituting the support pile 10 with respect to the steel pipe member 51b, and temporarily fixes the bolt 57. After the filler 80 is filled and solidified inside the intermediate grade steel pipe 50b, the head of the bolt 57 may be removed.
  • the first steel pipe pile 20a and the second steel pipe pile 20a and the second steel pipe pile are driven into the ground 90 in parallel with the first direction in which the road extends and the second direction intersecting the first direction.
  • 20b a steel pipe column 30 connected above the first steel pipe pile 20a, an upper end grade steel pipe 50a installed at the upper end of the second steel pipe pile 20b or the steel pipe column 30, and two adjacent upper end grade steel pipes 50a.
  • a girder member 41 to be connected, an upper end grade steel pipe 50a, and a road slab 99 installed on the girder member 41 are provided.
  • the member located below is the lower member and the member joined above the lower member is the upper member among the first steel pipe pile 20a, the second steel pipe pile 20b, the steel pipe column 30, and the upper end grade steel pipe 50a.
  • the joint portion between the lower member and the upper member is joined by an eccentric joining member 60 that can be joined in a state where the central axis of the lower member and the central axis of the upper member are eccentric.
  • the central axis of the lower member located below and the upper member joined above the lower member is the amount of error.
  • the position can be adjusted by shifting it. Therefore, when the support pile 10 is erected on the ground 90, the accuracy of the position of the upper end grade steel pipe 50a can be easily ensured, and the road structure 100 can suppress the construction period and the cost while ensuring the accuracy.
  • the eccentric joining member 60 includes at least a first eccentric joining member 60a
  • at least one of the upper end grade steel pipes 50a includes a first eccentric joining member 60a including a tubular body.
  • the tubular body is larger than the outer shape of the steel pipe pile 20 and the outer shape of the steel pipe column 30, and is installed so as to surround the outer surface of the steel pipe pile 20 or the steel pipe column 30. Then, the gap formed between the tubular body and the steel pipe pile 20 or the steel pipe column 30 is filled with the filler 80. With this configuration, the position of the upper end grade steel pipe 50a can be easily adjusted even if there is an error in the position of the pile head 12 of the support pile 10.
  • a beam member connecting two intermediate grade steel pipes 50b adjacent to each other with the intermediate grade steel pipe 50b installed on the first steel pipe pile 20a, the second steel pipe pile 20b, or the steel pipe column 30. 40 and more are provided.
  • the eccentric joining member 60 includes at least the second eccentric joining member 60b, and is located below the first steel pipe pile 20a, the second steel pipe pile 20b, the steel pipe column 30, the upper end grade steel pipe 50a, and the intermediate grade steel pipe 50b.
  • the member to be joined is a lower member and the member joined above the lower member is an upper member, the joint portion between the lower member and the upper member is joined by the second eccentric joining member 60b.
  • the intermediate grade steel pipe 50b includes a second eccentric joint member 60b including a tubular body.
  • the tubular body is larger than the outer shape of the steel pipe pile 20 and the outer shape of the steel pipe column 30, and is installed so as to surround the outer surface of the steel pipe pile 20 or the steel pipe column 30.
  • the gap formed between the intermediate grade steel pipe 50b and the steel pipe pile 20 or the steel pipe column 30 is filled with the filler 80.
  • the installation position of the intermediate grade steel pipe 50b can be adjusted by the gap between the steel pipe member 51b and the support pile 10, so that the intermediate grade steel pipe 50b can be installed. It's easy.
  • FIG. 12 is a schematic view of the road structure 100 according to the first embodiment and the road structure 1000 of the comparative example.
  • the road structure 100 according to the first embodiment includes intermediate grade steel pipes 50b, and adjacent intermediate grade steel pipes 50b are connected to each other by a beam member 40. Therefore, as shown in FIG. 12A, the bending moment generated in the support pile 10a with respect to the input F due to the seismic force is suppressed by the intermediate grade steel pipe 50b, and the displacement ⁇ x is also suppressed.
  • the road structure 1000 of the comparative example neither the intermediate grade steel pipe 50b nor the beam member 40 is installed. Therefore, as shown in FIG. 12B, the bending moment generated in the support pile 10a with respect to the input F due to the seismic force is larger than that of the road structure 100 according to the first embodiment, and the displacement ⁇ x1 is also large.
  • the road structure 100 can improve the reliability.
  • superstructures such as a girder member 41 and a road slab 99 are directly provided on the upper part of the support pile 10 protruding from the ground 90. Therefore, when the depth of the slope is deep with respect to the planned road surface and the projecting length of the support pile 10 from the ground 90 becomes large, the road structure 1000 of the comparative example is opposed to the seismic force acting on the superstructure.
  • the road structure 1000 of the comparative example has a problem that it cannot be applied to a terrain in which the protruding height of the support pile 10 is larger than about 10 m.
  • the road structure 100 according to the first embodiment as described above, the bending moment and the displacement ⁇ x can be suppressed even if the protrusion length of the support pile 10 from the ground 90 is large. Therefore, the road structure 100 has an advantage that it can be installed regardless of the terrain.
  • the road structure 200 according to the second embodiment is a modification of the structure of at least a part of the eccentric joint members 60 with respect to the road structure 100 according to the first embodiment.
  • the changes to the first embodiment will be mainly described.
  • those having the same function in each drawing shall be indicated with the same reference numerals as those used in the description of the first embodiment.
  • FIG. 13 is an explanatory view of a cross-sectional structure around the upper end grade steel pipe 250a of the road structure 200 according to the second embodiment.
  • FIG. 14 is a top view of the upper end grade point steel pipe 250a of the road structure 200 according to the second embodiment.
  • the upper end grade steel pipe 250a of the road structure 200 according to the second embodiment includes a vertical girder joint 52a for connecting the steel pipe member 251a and the vertical girder 41a and a horizontal girder joint 53a for connecting the horizontal girder 41b, and has an upper surface 57a. Is flat.
  • An eccentric joining member 260 is joined to the end face 14 of the pile head 12 of the support pile 10.
  • the lower end surface of the eccentric joining member 260 is joined to the pile head 12 of the support pile 10, and the upper end surface is formed by the plate member 261.
  • the upper surface 262 of the plate member 261 is flat so that the lower end surface 254a of the steel pipe member 251a of the upper end grade steel pipe 250a can be placed.
  • the upper surface 262 of the plate member 261 is formed to be larger than the lower end surface 254a of the steel pipe member 251a. Therefore, the steel pipe member 251a of the upper end grade steel pipe 250a can be placed on the upper surface 262 of the eccentric joint member 260 so as to be displaced in the horizontal direction.
  • the support pile 10 and the upper end grade point steel pipe 250a can be joined in a state where the central axes are eccentric to each other by using the eccentric joining member 260.
  • the eccentric joining member 260 in the second embodiment may be referred to as a third eccentric joining member 260.
  • the upper surface 262 may be referred to as a joint surface.
  • FIG. 15 is a side view of the structure around the intermediate grade steel pipe 250b of the road structure 200 according to the second embodiment.
  • the eccentric joining member 260 may be used for joining the intermediate grade steel pipe 250b and the first steel pipe pile 20a.
  • the steel pipe member 251b of the intermediate grade steel pipe 250b has the same cross-sectional shape as the first steel pipe pile 20a.
  • the intermediate grade steel pipe 250b is composed of a steel pipe member 251b, a vertical beam joint 52b, and a horizontal beam joint 53b.
  • the intermediate grade steel pipe 250b may be integrated with the steel pipe column 30 in the first embodiment. With this configuration, the beam member 40 can be installed on the support pile 10a formed by joining using the eccentric joining member 260.
  • Embodiment 3 In the third embodiment, the construction method of the road structure 100 according to the first embodiment will be described.
  • steel pipe piles 20 are first driven into the ground 90 in parallel with the first direction in which the road extends and the second direction intersecting the first direction. This process is called a steel pipe pile driving process.
  • a hole is drilled in the ground 90 using a down-the-hole hammer or the like to form a hole 95 in which the steel pipe pile 20 is built.
  • the hole 95 penetrates the sedimentary layer 92 on the surface 94 side of the ground 90 and reaches the support layer 93.
  • FIG. 16 is an explanatory view of a state in which the steel pipe pile 20 is built in the hole 95.
  • the portion on the right side from the center line of FIG. 16 shows the structure in the cross section including the central axis of the steel pipe pile 20.
  • the steel pipe pile 20 is built in the hole 95 so that the tip reaches the bottom surface 96 of the hole 95.
  • the filler 80 is injected from the opening at the upper end of the steel pipe pile 20.
  • the filler 80 for example, mortar or cement is used.
  • the filler 80 passes through the hollow tubular steel pipe pile 20 and connects the hole 95 and the outer surface of the steel pipe pile 20 from the through hole 15 provided at the end of the steel pipe pile 20 on the bottom surface 96 side of the hole 95. It flows into the gap 97 between them.
  • the filler 80 that has flowed into the gap 97 rises in the gap 97 as the space inside the steel pipe pile 20 is filled with the filler 80. If it can be confirmed that the filler 80 flows out from the gap 97 from the surface 94 of the ground 90, it can be confirmed that the gap 97 between the steel pipe pile 20 and the hole 95 is filled with the filler 80. When the filler 80 is directly filled from the surface 94 of the ground 90 into the gap 97 between the steel pipe pile 20 and the hole 95, it is difficult to evenly fill the filler 80 around the steel pipe pile 20.
  • the surface of the hole 95 may not be smooth and earth and sand may be mixed in the filler 80, or the filler 80 may not be sufficiently filled up to the bottom surface 96. If the filling material 80 is insufficiently filled, the bearing capacity of the steel pipe pile 20 may not be able to secure the design value. However, according to the steel pipe pile driving step in the third embodiment, the steel pipe pile 20 is surely driven into the ground 90 by performing as described above.
  • a plurality of steel pipe piles 20 are used for road structures 100 and 200.
  • the plurality of steel pipe piles 20 are all driven into the ground 90 by the above-mentioned steel pipe pile driving step.
  • the steel pipe column 30 is temporarily joined to the first steel pipe pile 20a among the plurality of steel pipe piles 20, and the support pile 10a is temporarily assembled. Further, the upper end grade steel pipe 50a is temporarily joined to the pile head 12 of the support pile 10a and the pile head 21b of the second steel pipe pile 20b among the plurality of steel pipe piles 20.
  • Temporary joining is to temporarily install the steel pipe column 30, the upper end grade steel pipe 50a, and the intermediate grade steel pipe 50b on the steel pipe pile 20 by using the formwork jig 70. This is called a temporary joining process. The details of the temporary joining process will be described below.
  • FIG. 17 is an explanatory diagram of the structure of the formwork jig 70 used in the temporary joining step of the third embodiment.
  • FIG. 17 shows a diagram when the upper end grade steel pipe 50a is installed on the steel pipe pile 20, but the method of using the formwork jig 70 is the same even when the intermediate grade steel pipe 50b is installed.
  • the formwork jig 70 is used on the pile head 21 of the steel pipe pile 20.
  • the formwork jig 70 includes a bracket 71 that supports the formwork plate 74.
  • the bracket 71 is connected to the fixing band 73.
  • the fixing band 73 is detachably fixed to the steel pipe pile 20 so as to surround the outer surface of the steel pipe pile 20, and fixes the position of the bracket 71.
  • the process of installing the formwork jig 70 on the steel pipe pile 20 by the fixing band 73 is particularly called a formwork installation process.
  • the formwork installation process is included in the temporary joining process.
  • the intermediate grade steel pipe 50b is installed so as to bring the form plate 74 of the form jig 70 into contact with the lower end surface of the steel pipe member 51b.
  • This process is called a cylinder installation process.
  • the cylinder installation process is included in the joining process.
  • the formwork plate 74 is installed so that the filler 80 injected into the intermediate grade steel pipe 50b does not leak out.
  • the bracket 71 includes an adjustment bolt 75.
  • the tip of the adjusting bolt 75 comes into contact with the outer peripheral surface of the steel pipe member 51b of the intermediate grade steel pipe 50b placed on the form plate 74.
  • the adjusting bolt 75 is screwed with the nut member 76, so that the position of the tip can be adjusted with high accuracy and the position of the steel pipe member 51b of the intermediate grade steel pipe 50b can be temporarily fixed.
  • the step of adjusting and fixing the horizontal position of the steel pipe member 51b of the intermediate grade steel pipe 50b in this way is called a fixing step.
  • the fixing step is included in the temporary joining step.
  • the steel pipe column 30 is built in the intermediate grade steel pipe 50b. This is called the steel pipe support building process.
  • the steel pipe support building process is included in the temporary joining process.
  • the upper end grade steel pipe 50a is attached to the pile head 12 of the support pile 10a and the second steel pipe pile 20b to which the steel pipe column 30 is connected to the first steel pipe pile 20a.
  • the installation of the upper end grade steel pipe 50a is carried out by a formwork installation step, a cylinder installation step, and a fixing step in the same manner as the installation of the intermediate grade point steel pipe 50b at the pile head 21 of the steel pipe pile 20.
  • the beam member 40 is installed. This process is called a beam member installation process. Further, the girder member 41 is installed after the upper end grade point steel pipe 50a is installed. This process is called a girder member installation process.
  • the beam member installation process and the girder member installation process can be included in the temporary joining process.
  • the support piles 10a and 10b can be temporarily assembled by using the formwork jig 70 as described above without injecting the filler 80 into the grade steel pipe 50. .. Therefore, a lining plate (not shown) can be installed on the temporarily assembled support piles 10a and 10b, and the support piles 10a and 10b can be erected one after another in the first direction along the road. That is, the steel pipe placing process and the temporary joining process are alternately repeated until the support piles 10a and 10b for the entire length of the road or the predetermined length of the road are completed. The above steps are collectively called the support pile erection process.
  • the graded steel pipe 50 is a general term for the upper end graded steel pipe 50a and the intermediate graded steel pipe 50b.
  • the injection solidification step may be carried out for all the graded steel pipes 50 after the support piles 10a and 10b in the temporarily assembled state for the entire length of the road are erected.
  • the road structure 100 When the road structure 100 is installed without using the formwork jig 70, the first support pile 10 is erected in the first direction along the road, and the filler 80 injected into the grade steel pipe 50 is solidified and then covered. The formwork is installed on the support pile 10. Then, a heavy machine is placed on the installed lining plate, and the next support pile 10 is built. In the case of such a process, the injection and solidification step of the filler 80 is required every time the support pile 10 is built, so that the construction period becomes long. On the other hand, the road structure 100 has an advantage that the construction period can be shortened because the number of injection and solidification steps of the filler 80 can be suppressed by using the formwork jig 70.
  • the lining slab is removed after the injection solidification process is completed, and the road floor slab 99 is installed.
  • FIG. 18 is a side view showing an example of the lining plate.
  • the lining plate is placed on the support pile 10 temporarily assembled when the steel pipe pile driving process and the temporary joining process are repeated.
  • the lining plate 399 shown in FIG. 18 includes a temporary pile head block 350a. Therefore, the pile head block 350a is fitted into the pile head 12 without installing the upper end grade steel pipe 50a of the road structure 100 so that the lining plate 399 can be installed.
  • a lining plate 399 only the steel pipe pile driving process can be carried out collectively, so that the restraint time of the pile driver can be shortened.
  • Embodiment 4 a modification of the road structure 100 according to the first embodiment and the road structure 200 according to the second embodiment will be described.
  • FIG. 19 is an explanatory view of a cross-sectional structure of a modified example of the road structure 100 according to the first embodiment.
  • two support piles 10 are arranged in parallel in the second direction intersecting the first direction in which the road extends, but 2 More than one support pile 10 may be arranged in parallel.
  • the road structure 100 includes an oblique beam 48 that connects between the upper end grade steel pipe 50a and the intermediate grade steel pipe 50b or between two intermediate grade steel pipes 50b and is inclined with respect to the cross girder 41b. You may have.
  • the oblique beam 48 connects two graded steel pipes 50 located diagonally to a rectangular structure composed of a support pile 10 and a cross girder 41b or a cross beam 40b.
  • deformation of the frame is suppressed by the truss structure formed by the oblique beams 48, and the member stress can be reduced.
  • the road structure 100 shown in FIG. 19 may be configured by using the eccentric joining member 260 used in the road structure 200 of the second embodiment.
  • the upper end grade steel pipe 250a and the eccentric joint member 260 shown in the second embodiment are applied to the pile head 12 of the support pile 10, and the steel pipe column 30 is shown in FIG.
  • the double pipe type intermediate grade steel pipe 50b shown in is installed.
  • the upper end grade steel pipe 250a and the cross girder 41b are integrally manufactured in advance to form a grade girder.
  • the intermediate grade steel pipe 50b and the cross beam 40b are integrally manufactured in advance to form a grade beam.
  • the intermediate grade steel pipe 50b is also manufactured integrally with the cross beam 40b, and has the same effect. Further, the graded steel pipes 50 are joined to each other by diagonal members, and the truss structure of the diagonal beams 48 suppresses the deformation of the frame and reduces the member stress.
  • an eccentric joint member 260 is applied at the joint portion 11.
  • the lower end surface of the steel pipe column 30 is placed on the upper surface 262 of the eccentric joining member 260, and the horizontal position of the steel pipe column 30 is adjusted and joined.
  • 20 and 21 are examples of grade girders in which the upper end grade steel pipe 250a and the cross girder 41b are integrated.
  • the rating girder applied to the road structure 100 shown in FIG. 19 may be specifically in the form shown in FIGS. 20 and 21.
  • FIG. 22 and 23 are explanatory views of cross-sectional structures of modified examples of the road structure 100 according to the first embodiment and the road structure 200 according to the second embodiment.
  • the cross girders 41b of the road structures 100 and 200 may be formed so as to project to the slope side of the ground 90. This structure is applied when the slope slope is steep and it is difficult to install the steel pipe pile 20. Further, as shown in FIG. 23, the road structures 100 and 200 can be installed so as to widen the road provided by cutting the slope.
  • FIG. 24 is a side view of a modified example of the road structure 100 according to the first embodiment and the road structure 200 according to the second embodiment.
  • the seismic isolation member 5 may be provided on the pile head 12 of the support pile 10b having a small amount of protrusion from the ground 90. As a result, the load load on the road structures 100 and 200 as a whole is reduced.
  • the present invention has been described above based on the embodiment, the present invention is not limited to the configuration of the above-described embodiment.
  • the combination of the components is not limited to the combination in the embodiment, and the combination of the components described in each embodiment can be appropriately changed.
  • the gist (technical scope) of the present invention includes various changes, applications, and uses made by those skilled in the art as necessary.
  • Seismic isolation member 10 support pile, 10a support pile, 10b support pile, 11 joint, 12 pile head, 13 protrusion, 14 end face, 15 through hole, 20 steel pipe pile, 20a 1st steel pipe pile, 20b 2nd steel pipe pile , 21 pile head, 21a pile head, 21b pile head, 22a end face, 30 steel pipe column, 30b second steel pipe pile, 31 end face, 40 beam member, 40a vertical beam, 40b cross beam, 41 girder member, 41a vertical girder, 41b horizontal Girder, 42 floor slab fixing member, 43 connecting part, 44 splicing plate, 48 beam, 50 graded steel pipe, 50a upper end graded steel pipe, 50b intermediate graded steel pipe, 51a steel pipe member, 51b steel pipe member, 52a vertical girder joint , 52b vertical beam joint, 53a horizontal girder joint, 53b horizontal beam joint, 54 protrusion, 55a support member, 55b support member, 56a filling hole, 56b filling port, 57 bolt, 57a upper surface, 60 eccentric

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)
  • Foundations (AREA)

Abstract

地形によらず設置の精度を確保し、工期及びコストを抑制できる道路構造、道路構造の施工に用いる型枠治具、及び道路構造の施工方法を提供することを目的とする。 本発明に係る道路構造は、道路が延びる第1方向及び第1方向に交差する第2方向に並列して地盤に打設される第1鋼管杭及び第2鋼管杭を含む鋼管杭と、第1鋼管杭の上方に接続される鋼管支柱と、第2鋼管杭又は鋼管支柱の上端に設置される上端格点鋼管と、隣り合う2つの上端格点鋼管を連結する桁部材と、上端格点鋼管及び桁部材の上に設置される道路床版と、を備え、第1鋼管杭、第2鋼管杭、鋼管支柱、及び上端格点鋼管のうち、下方に位置する部材を下方部材とし、下方部材の上方に接合される部材を上方部材としたときに、下方部材と上方部材との接合部は、下方部材の中心軸と上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合される。

Description

道路構造、型枠治具、及び道路構造の施工方法
 本発明は、山間部などにおいて道路を構築する際に、地形の影響を受けずに道路に必要な傾斜及び幅員を確保できる道路構造、道路構造の施工に用いる型枠治具、及び道路構造の施工方法に関する。
 山間部に道路を構築する場合は、既存の斜面の道路面計画高さより高い部分は切土を行い、また、低い部分には盛土を行い、路面を平坦に成形した構造が用いられる。この場合、既存の斜面を改変するため、植栽及び生物の居住環境に及ぼす影響が大きく、環境保全の面で好ましくない場合が多い。また、谷合に橋梁を設置する場合には、大規模な橋脚を斜面に構築する必要があり、大規模な掘削及び基礎工事が必要である。この場合、環境に対する影響が大きいうえ、工期が長くなりコストも大きくなる。そこで、斜面に杭を設置し、その上に桁及び道路床版を設置する桟橋形式の道路構造が考案されている(例えば、特許文献1参照)。
特開2002-256504号公報
 特許文献1に開示されているところによれば、地盤に打設される鋼管杭の上に杭頭ブロックが接合され、杭頭ブロックの上に桁材が設置され、桁材上に道路床版が構築されている。この道路構造は、斜面から突出した鋼管杭の上部に桁及び床版等の上部工を直接設けており、計画道路面に対して斜面の深さが深い地形に対しては、鋼管杭の突出長が多大になる。この場合、鋼管杭の打設の精度及び鋼管杭の精度の影響により、鋼管杭の杭頭の位置の誤差が大きくなる。従って、杭頭ブロック及び桁材は、地形の影響を受けて複数の鋼管杭のそれぞれの杭頭の位置の誤差を調整して設置される必要があるため、道路構造の設置の工期が長期化し、コストも増大するという課題があった。
 本発明は上記課題を解決するものであって、地形によらず設置の精度を確保し、工期及びコストを抑制できる道路構造、道路構造の施工に用いる型枠治具、及び道路構造の施工方法を提供することを目的とする。
 本発明に係る道路構造は、道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される第1鋼管杭及び第2鋼管杭を含む鋼管杭と、前記第1鋼管杭の上方に接続される鋼管支柱と、前記第2鋼管杭又は前記鋼管支柱の上端に設置される上端格点鋼管と、隣り合う2つの前記上端格点鋼管を連結する桁部材と、前記上端格点鋼管及び前記桁部材の上に設置される道路床版と、を備え、前記第1鋼管杭、前記第2鋼管杭、前記鋼管支柱、及び前記上端格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、前記下方部材と前記上方部材との接合部は、前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合される。
 本発明に係る型枠治具は、道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される鋼管杭と、前記鋼管杭の上方に接続される鋼管支柱と、前記鋼管杭又は前記鋼管支柱に設置される格点鋼管と、を備え、前記鋼管杭、前記鋼管支柱、及び前記格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、前記下方部材と前記上方部材との接合部は、前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合され、前記偏心接合部材は、筒体を備え、前記筒体は、前記鋼管杭又は前記鋼管支柱の外周面を包囲して設置され、前記筒体と前記鋼管杭又は前記鋼管支柱との間に形成される間隙は、充填材が充填される、道路構造の前記偏心接合部材を設置する際に用いる型枠治具であって、前記下方部材の外周面を包囲し前記筒体の下端に接して設置される型枠板と、前記筒体の水平位置を調整し固定する調整ボルトと、前記型枠板及び前記調整ボルトを支持し、前記下方部材に着脱自在に固定されるブラケットと、を備える。
 本発明に係る道路構造の施工方法は、道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される鋼管杭と、前記鋼管杭の上方に接続される鋼管支柱と、前記鋼管杭又は前記鋼管支柱に設置される格点鋼管と、を備え、前記鋼管杭、前記鋼管支柱、及び前記格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、前記下方部材と前記上方部材との接合部は、前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合される、道路構造の施工方法であって、前記下方部材と前記上方部材を接合する仮接合工程を備え、前記仮接合工程は、前記偏心接合部材が備える筒体を前記下方部材の上端部の外周面を包囲して設置する筒体設置工程と、型枠治具が備える型枠板を前記下方部材の外周面を包囲し前記筒体の下端に接するように設置する型枠設置工程と、調整ボルトにより前記筒体の水平位置を調整し固定する固定工程と、を備える。
 本発明によれば、偏心接合部材により、地盤からの突出長さが多大な杭においても杭頭の位置精度が向上し、上端格点鋼管及び桁部材の位置精度の調整を抑制できるため、地形によらず工期及びコストを抑えて道路構造を設置できる。
実施の形態1に係る道路構造100の模式図である。 図1の道路構造100のA-A部の断面構造の説明図である。 図1の道路構造100のB-B部の断面構造の説明図である。 図1の道路構造100のC-C部の断面構造の説明図である。 図1の道路構造100の桁部材41の配置図である。 実施の形態1に係る道路構造100の上端格点鋼管50a周辺の断面構造の説明図である。 実施の形態1に係る道路構造100の上端格点鋼管50aの上面図である。 実施の形態1に係る道路構造100の中間格点鋼管50b周辺の断面構造の説明図である。 実施の形態1に係る道路構造100の中間格点鋼管50bの上面図である。 実施の形態1に係る道路構造100の中間格点鋼管50bの変形例である中間格点鋼管150b周辺の断面構造の説明図である。 実施の形態1に係る道路構造100の中間格点鋼管50bの変形例である中間格点鋼管150bの一例の断面構造の説明図である。 実施の形態1に係る道路構造100及び比較例の道路構造1000の模式図である。 実施の形態2に係る道路構造200の上端格点鋼管250a周辺の断面構造の説明図である。 実施の形態2に係る道路構造200の上端格点鋼管250aの上面図である。 実施の形態2に係る道路構造200の中間格点鋼管250b周辺の構造の側面図である。 孔95に鋼管杭20を建て込んだ状態の説明図である。 実施の形態3の仮接合工程に用いられる型枠治具70の構造の説明図である。 覆工版の一例を示す側面図である。 実施の形態1に係る道路構造100の変形例の断面構造の説明図である。 上端格点鋼管250aと横桁41bとを一体化した格点桁の一例である。 上端格点鋼管250aと横桁41bとを一体化した格点桁の一例である。 実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例の断面構造の説明図である。 実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例の断面構造の説明図である。 実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例の側面図である。
 以下、本発明の実施の形態を図面に基づいて説明する。なお、以下に説明する実施の形態によって本発明が限定されるものではない。各図は模式的に示すものであって、各部材の相対的な大きさや板厚等は図示する寸法に限定されるものではない。また、以下の図面では各構成部材の大きさの関係が実際のものとは異なる場合がある。
 実施の形態1.
 図1は、実施の形態1に係る道路構造100の模式図である。図2は、図1の道路構造100のA-A部の断面構造の説明図である。図3は、図1の道路構造100のB-B部の断面構造の説明図である。図4は、図1の道路構造100のC-C部の断面構造の説明図である。図5は、図1の道路構造100の桁部材41の配置図である。道路構造100は、山間部等の起伏が大きい地盤に設置されるものである。道路構造100は、例えば、山間部の斜面に沿って道路を設ける場合、斜面に沿って設けられた既設道路を拡幅する場合、又は山間部の沢部を跨いで道路を通す場合等に用いられる構造である。実施の形態1においては、山間部の斜面に沿って設置された道路構造100について説明する。
 道路構造100は、地盤90に打設された複数の鋼管杭20を備える。鋼管杭20は、地盤90に設けられた孔に、杭頭12が地盤90の表面94から突出するように建てられる。地盤90は、ダウンザホールハンマ等によって堆積層92を貫通し、支持層93まで削孔されている。地盤90に設けられた孔に鋼管杭20を建て込み、孔にモルタル等の充填材が充填されることにより、鋼管杭20は、地盤90に立設される。
 鋼管杭20は、道路が延びる方向である第1方向に並列して地盤90に複数打設される。図5に示される様に、桁部材41が例えば斜面などに沿って曲がって配置されており、道路は、その桁部材41の上に道路床版99を設置して構成される。第1方向は、この道路に沿った方向である。道路構造100の複数の鋼管杭20は、第1鋼管杭20aと第2鋼管杭20bとを含む。第1鋼管杭20aは、上方に鋼管支柱30が接続される。鋼管支柱30は、道路床版99及び桁部材41が設置される地盤90の表面94からの高さに応じて、第1鋼管杭20aの上端に接合される。図1中に示されている三角形の記号は、第1鋼管杭20aと鋼管支柱30との接合部11を示している。接合部11においては、偏心接合部材60(図6、図8参照)が、地盤90側に位置する下方部材と下方部材の上方に接合される上方部材とを接合している。なお、地盤90に立設された柱状の構造を支持杭10と称する場合がある。特に、上述した第1鋼管杭20aと鋼管支柱30とを接合した構造は、支持杭10aと称する場合がある。
 鋼管支柱30は、第1鋼管杭20aの杭頭21aと接合され上方に延びている。鋼管支柱30の杭頭12には上端格点鋼管50aが接合されている。上端格点鋼管50aは、偏心接合部材60を用いて鋼管支柱30の杭頭12と接合されている。
 上端格点鋼管50aは、第1方向において隣り合う上端格点鋼管50aと桁部材41により連結されている。第1方向に沿って設置されている桁部材41を特に縦桁41aと呼ぶ。
 図2~図4に示される様に、上端格点鋼管50aは、第1方向に交差する第2方向に並列して隣り合う上端格点鋼管50aと桁部材41により連結されている。第2方向に沿って設置されている桁部材41を特に横桁41bと呼ぶ。
 実施の形態1においては、図2~図4に示される様に、鋼管杭20は、第1方向に交差する第2方向に沿って2本並べられている。横桁41bは、第2方向に並べられた杭頭12を連結している。桁部材41は、第1方向及び第2方向に沿って設置され、それぞれ支持杭10の杭頭12を上端格点鋼管50aを介して連結している。桁部材41及び上端格点鋼管50aの上面には、床版固定部材42が設置されている。道路床版99は、床版固定部材42を介して桁部材41及び上端格点鋼管50aに固定される。なお、鋼管杭20は、第1方向に交差する第2方向に2本以上並べられていても良い。
 横桁41bは、中央部に連結部43を備える。連結部43には縦桁41aが接続されている。連結部43に接続されている縦桁41aは、第1方向において隣り合う横桁41bの連結部43同士を接続している。
 図1に戻り、第2鋼管杭20bは、上方に上端格点鋼管50aが接続されている。上端格点鋼管50aは、偏心接合部材60を用いて第2鋼管杭20bの杭頭12と接合されている。第2鋼管杭20bに接合されている上端格点鋼管50aは、支持杭10aに接合されている上端格点鋼管50aと同様に、第1方向及び第2方向に隣り合う上端格点鋼管50aと連結されている。なお、第2鋼管杭20bは、支持杭10bと称する場合がある。
 図1に示される様に、支持杭10aには中間格点鋼管50bが設けられている。実施の形態1において、中間格点鋼管50bは、支持杭10aのうち鋼管支柱30の中央部に設置されている。つまり、中間格点鋼管50bは、道路構造100のうち、地盤90からの突出長さが多大な支持杭10aに設けられている。中間格点鋼管50bは、隣り合う鋼管支柱30に設けられた中間格点鋼管50bと梁部材40により連結されている。第1方向に沿って設置されている梁部材40を、特に縦梁40aと呼ぶ。
 図4に示される様に、中間格点鋼管50bは、第1方向に交差する第2方向において隣り合う支持杭10に設置された中間格点鋼管50bと梁部材40により連結されている。第2方向に沿って設置されている梁部材40を、特に横梁40bと呼ぶ。
 梁部材40は、図1及び図3に示される様に傾斜して設置されていても良いし、図4に示される様に水平に設置されていても良い。また、中間格点鋼管50bは、図1及び図4に示される様に鋼管支柱30に設置されるものに限定されず、図3に示される様に第2鋼管杭30bに設置されていても良い。
 (上端格点鋼管50aの構造)
 図6は、実施の形態1に係る道路構造100の上端格点鋼管50a周辺の断面構造の説明図である。図7は、実施の形態1に係る道路構造100の上端格点鋼管50aの上面図である。上端格点鋼管50aと支持杭10とは、偏心接合部材60aにより接合される。偏心接合部材60aは、上端格点鋼管50aの一部であり、支持杭10の杭頭12と組み合わさり、杭頭12に対する上端格点鋼管50aの位置を調整できるようにするためのものである。即ち、上端格点鋼管50aは、偏心接合部材60aにより、支持杭10と中心軸の位置がずれた状態であっても、支持杭10に接合することができる。上端格点鋼管50aと杭頭12とを接合する偏心接合部材60aを、特に第1偏心接合部材と称する場合がある。
 実施の形態1において、偏心接合部材60aは、少なくとも上端格点鋼管50aを構成する筒体である鋼管部材51aと支持部材55aとから構成される。実施の形態1においては、鋼管部材51aは、円筒形状になっている。鋼管部材51aの内部の上部には支持部材55aが設置されている。支持部材55aは、円筒形状である鋼管部材51aの中心軸Cを通り、板状の部材を十字形状に組み合わせて形成されている。なお、鋼管部材51aは、円筒形状に限定されるものではなく、矩形又は多角形等の断面形状の筒体であってもよい。
 上端格点鋼管50aは、桁部材41が接続される縦桁仕口52a及び横桁仕口53aを備える。縦桁仕口52a及び横桁仕口53aと桁部材41とは、添接板44により縦桁仕口52a又は横桁仕口53aの端部と桁部材41の端部とを挟みこみ、ボルト及びナットを用いて添接板44とそれぞれの部材の端部とを固定して接続される。
 上端格点鋼管50aは、上部に板状の部材が取り付けられており、上面57aが平坦になっている。上面57aは、道路の傾斜に合わせて傾斜していてもよい。上面57aには、板状の部材を貫通する充填孔56aが開口されている。充填孔56aは、杭頭12と鋼管部材51aとの間の空間に充填材80を注入するための孔であり、外部と鋼管部材51aの内部の空間とを連通する。
 支持部材55aは、下面に支持杭10a又は10bの杭頭12の端面14が当接する。支持部材55aの下面と杭頭12の端面14とが当接することにより、上端格点鋼管50aは、支持杭10の中心軸方向の位置、即ち高さ方向の位置が決まる。鋼管部材51aは、支持杭10の上端部の外周面を包囲している。充填材80が充填される前においては、鋼管部材51aの内側面と支持杭10の外側面と間には隙間が形成されており、上端格点鋼管50aは、その隙間の分だけ支持杭10に対し、水平方向に移動させることができる。図6及び図7に示されるように、支持部材55aは、板状の部材を十字に組み合わせて形成されているが、その他の形態をとることもできる。支持部材55aは、上端格点鋼管50aを杭頭12の端面14上に保持できることができ、充填材80の注入の際に障害にならなければその他の構造であってもよい。
 支持杭10は、杭頭12の位置が想定した位置からずれる場合がある。地盤90の表面94からの突出量が多大である場合には、鋼管杭20及び鋼管支柱30の単品の精度及び接合精度により、杭頭12の位置誤差が大きくなる場合がある。例えば、上端格点鋼管50aの鋼管部材51aが円筒形状であり、杭頭12が円柱形状である場合、鋼管部材51aの内径を杭頭12の外径より300mm大きく設定する。これにより、上端格点鋼管50aは、杭頭12に100mmの水平方向の位置の誤差があっても正しい位置に設置でき、充填材80の充填性も確保することができる。
 充填材80は、上端格点鋼管50aの上面57aに開口している充填孔56aから鋼管部材51aと杭頭12との隙間に充填される。鋼管部材51aは、下方が開口されている。そのため、充填材80の充填工程において、下方から充填材80が漏れ出ないように、型枠治具70(図17参照)を鋼管部材51aの下端面に当接させて開口を塞ぐ。型枠治具70については、別途説明する。充填材80が充填される鋼管部材51aと杭頭12との隙間を形成する鋼管部材51aの内側面及び杭頭12の外側面は、突起54及び13が設けられている。突起54及び13が固化した充填材80と噛み合うため、充填材80は、鋼管部材51aの内側面及び杭頭12の外側面に沿った方向にずれることがなく、上端格点鋼管50aと支持杭10との間の荷重伝達を向上させることができる。
 突起13及び54は、鉄筋や棒鋼を曲げて溶接にて固定することにより形成してもよい。又は、鋼管部材51a及び支持杭10は、突起付き鋼板材により形成されていてもよい。例えば、鋼管部材51a及び支持杭10は、鋼板表面に縦横に突起を有する縞鋼板、高さ2mm程度の突起が並行して並ぶリブ付き鋼板により形成されたリブ付き鋼管を用いてもよい。縞鋼板又はリブ付き鋼管を使用することによって、鋼管部材51aに突起54を、及び支持杭10に突起13を溶接接合するための工費や工程を削減することができる。また、あらかじめ一体に形成されている突起13及び54がずれ止め突起の固定強度を向上させるため、上端格点鋼管50aの鋼管部材51aは、高さ方向の寸法を縮小することが可能である。
 (中間格点鋼管50bの構造)
 図8は、実施の形態1に係る道路構造100の中間格点鋼管50b周辺の断面構造の説明図である。図9は、実施の形態1に係る道路構造100の中間格点鋼管50bの上面図である。中間格点鋼管50bと支持杭10とは、偏心接合部材60bにより接合される。偏心接合部材60bは、中間格点鋼管50bの一部であり、支持杭10と組み合わさり、支持杭10に対する中間格点鋼管50bの位置を調整できるようにするためのものである。即ち、中間格点鋼管50bは、偏心接合部材60bにより、支持杭10と中心軸の位置がずれた状態であっても、支持杭10に接合することができる。
 実施の形態1において、偏心接合部材60bは、少なくとも中間格点鋼管50bを構成する鋼管部材51bから構成される。鋼管部材51bは、筒体であり、実施の形態1においては円筒形状になっている。ただし、鋼管部材51bは、円筒形状に限定されるものではなく、矩形又は多角形等の断面形状の筒体であってもよい。
 中間格点鋼管50bは、梁部材40が接続される縦梁仕口52b及び横梁仕口53bを備える。縦梁仕口52b及び横梁仕口53bと梁部材40とは、桁部材41と同様に添接板44により縦梁仕口52b又は横梁仕口53bの端部と梁部材40の端部とを挟みこみ、ボルト及びナットを用いて添接板44とそれぞれの部材の端部とを固定して接続される。
 中間格点鋼管50bの鋼管部材51bは、筒体であるため上下方向の端部は開口されている。従って、鋼管部材51bと支持杭10との隙間の上端が、充填口56bとなり鋼管部材51bと支持杭10との間の空間に充填材80を注入するための開口となり、外部と鋼管部材51aの内部の空間とを連通している。
 充填材80が充填される前においては、鋼管部材51bの内側面と支持杭10の外側面と間には隙間が形成されており、中間格点鋼管50bは、その隙間の分だけ支持杭10に対し、水平方向に移動させることができる。図8に示される構造の場合、中間格点鋼管50bを上下方向に支持する構造が無いため、中間格点鋼管50bを支持杭10に取り付ける際に中間格点鋼管50bの下端面に型枠治具70(図17参照)を当接させて下側から中間格点鋼管50bを支持する。型枠治具70は、充填材80を充填する際に下側の開口から充填材80が漏れ出ないようにする機能も有する。
 支持杭10は、位置が想定した位置からずれる場合がある。地盤90の表面94からの突出量が多大である場合には、鋼管杭20及び鋼管支柱30の単品の精度及び接合精度により、支持杭10の位置誤差が大きくなる場合がある。例えば、中間格点鋼管50bの鋼管部材51bが円筒形状であり、支持杭10が円柱形状である場合、鋼管部材51bの内径を支持杭10の外径より300mm大きく設定する。これにより、中間格点鋼管50bは、支持杭10が100mmの水平方向の位置の誤差を持っていても正しい位置に設置でき、充填材80の充填性も確保することができる。
 充填材80が充填される鋼管部材51bと支持杭10との隙間を形成する鋼管部材51bの内側面及び支持杭10の外側面は、突起54及び13が設けられている。突起54及び13が固化した充填材80と噛み合うため、充填材80は、鋼管部材51bの内側面及び支持杭10の外側面に沿った方向にずれることがなく、中間格点鋼管50bと支持杭10との間の荷重伝達を向上させることができる。
 突起13及び54は、鉄筋や棒鋼を曲げて溶接にて固定することにより形成してもよい。又は、鋼管部材51b及び支持杭10は、突起付き鋼板材により形成されていてもよい。例えば、鋼管部材51b及び支持杭10は、鋼板表面に縦横に突起を有する縞鋼板、高さ2mm程度の突起が並行して並ぶリブ付き鋼板により形成されたリブ付き鋼管を用いてもよい。縞鋼板又はリブ付き鋼管を使用することによって、鋼管部材51bに突起54を、及び支持杭10に突起13を溶接接合するための工費や工程を削減することができる。また、あらかじめ一体に形成されている突起13及び54がずれ止め突起の固定強度を向上させるため、中間格点鋼管50bの鋼管部材51bは、高さ方向の寸法を縮小することが可能である。
 (中間格点鋼管50bの構造の変形例)
 図10は、実施の形態1に係る道路構造100の中間格点鋼管50bの変形例である中間格点鋼管150b周辺の断面構造の説明図である。中間格点鋼管50bは、鋼管部材51bの内部に支持部材55bを設置することにより、例えば第1鋼管杭20aと鋼管支柱30とを接合することができる。変形例の中間格点鋼管150bは、鋼管部材51bの内部に上端格点鋼管50aが備える支持部材55aと同様の構造の支持部材55bを備える。
 支持部材55bは、下面に第1鋼管杭20aの杭頭21aの端面22aが当接する。支持部材55aの下面と杭頭21aの端面22aとが当接することにより、中間格点鋼管150bは、支持杭10の中心軸方向の位置、即ち高さ方向の位置が決まる。充填材80が充填される前においては、鋼管部材51bの内側面と第2鋼管杭20bの外側面との間には隙間が形成されており、中間格点鋼管150bは、その隙間の分だけ第2鋼管杭20bに対し、水平方向に移動させることができる。図6及び図7に示されるように、支持部材55aは、板状の部材を十字に組み合わせて形成されているが、その他の形態をとることもできる。支持部材55aは、中間格点鋼管150bを杭頭12の端面14上に保持できることができ、充填材80の注入の際に障害にならなければその他の構造であってもよい。
 支持部材55bは、上面に鋼管支柱30の端面31が載置される。支持部材55aの上面と鋼管支柱30の端面31とが当接することにより、鋼管支柱30は、支持杭10の中心軸方向の位置、即ち高さ方向の位置が決まる。充填材80が充填される前においては、鋼管部材51bの内側面と鋼管支柱30の外側面と間には隙間が形成されており、鋼管支柱30は、その隙間の分だけ鋼管部材51bに対し、水平方向に移動させることができる。以上より、中間格点鋼管150bは、下方部材である第1鋼管杭20aと上方部材である鋼管支柱30とを中心軸を偏心させた状態で接合させることができる。
 図11は、実施の形態1に係る道路構造100の中間格点鋼管50bの変形例である中間格点鋼管150bの一例の断面構造の説明図である。中間格点鋼管150bは、図11に示される様に、鋼管部材51bの外側から内部に向かってねじ込まれるボルト57を備えていても良い。ボルト57は、支持杭10を構成する下方部材及び上方部材の鋼管部材51bに対する位置を調整し、仮固定するものである。中間格点鋼管50bの内部に充填材80が充填され固化した後は、ボルト57の頭は除去しても良い。
 (実施の形態1に係る道路構造100の効果)
 実施の形態1に係る道路構造100によれば、道路が延びる第1方向及び第1方向に交差する第2方向に並列して地盤90に打設される第1鋼管杭20a及び第2鋼管杭20bと、第1鋼管杭20aの上方に接続される鋼管支柱30と、第2鋼管杭20b又は鋼管支柱30の上端に設置される上端格点鋼管50aと、隣り合う2つの上端格点鋼管50aのうち連結する桁部材41と、上端格点鋼管50a及び桁部材41の上に設置される道路床版99と、を備える。第1鋼管杭20a、第2鋼管杭20b、鋼管支柱30、及び上端格点鋼管50aのうち、下方に位置する部材を下方部材とし、下方部材の上方に接合される部材を上方部材としたときに、下方部材と上方部材との接合部は、下方部材の中心軸と上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材60により接合される。
 このように構成されることにより、道路構造100は、地盤90からの突出長さが多大な支持杭10においても、杭頭12の位置が調整でき、また、杭頭12に接合される上端格点鋼管50aの位置及び桁部材41の位置の調整ができる。つまり、道路構造100を構成する鋼管杭20、鋼管支柱30、及び上端格点鋼管50aのうち、下方に位置する下方部材と下方部材の上方に接合される上方部材との中心軸を誤差の分だけずらして位置調整ができる。そのため、支持杭10を地盤90に立設するにあたり、上端格点鋼管50aの位置の精度を容易に確保でき、道路構造100は、精度を確保しつつ工期及びコストを抑制できる。
 また、道路構造100によれば、偏心接合部材60は、少なくとも第1偏心接合部材60aを含み、上端格点鋼管50aのうち少なくとも1つは、筒体を含む第1偏心接合部材60aを備える。筒体は、鋼管杭20の外形及び鋼管支柱30の外形よりも大きく、鋼管杭20又は鋼管支柱30の外側面を包囲して設置される。そして、筒体と鋼管杭20又は鋼管支柱30との間に形成される隙間は、充填材80が充填される。
 このように構成されることにより、上端格点鋼管50aは、支持杭10の杭頭12の位置に誤差があっても、位置調整を容易に行うことができる。
 また、道路構造100によれば、第1鋼管杭20a、第2鋼管杭20b、又は鋼管支柱30に設置される中間格点鋼管50bと、隣り合う2つの中間格点鋼管50bを連結する梁部材40と、をさらに備える。偏心接合部材60は、少なくとも第2偏心接合部材60bを含み、第1鋼管杭20a、第2鋼管杭20b、鋼管支柱30、上端格点鋼管50a、及び中間格点鋼管50bのうち、下方に位置する部材を下方部材とし、下方部材の上方に接合される部材を上方部材としたときに、下方部材と上方部材との接合部は、第2偏心接合部材60bにより接合される。中間格点鋼管50bは、筒体を含む第2偏心接合部材60bを備える。筒体は、鋼管杭20の外形及び鋼管支柱30の外形よりも大きく、鋼管杭20又は鋼管支柱30の外側面を包囲して設置される。中間格点鋼管50bと鋼管杭20又は鋼管支柱30との間に形成される隙間は、充填材80が充填される。
 このように構成されることにより、中間格点鋼管50bは、支持杭10の位置に誤差があっても、支持杭10に対し中心軸をずらして設置することができる。そのため、異なる支持杭10に設置された2つの中間格点鋼管50b同士を不都合なく梁部材40で連結することができる。また、道路構造100は、支持杭10の位置に誤差があっても中間格点鋼管50bの設置位置を鋼管部材51bと支持杭10との隙間で調整できるため、中間格点鋼管50bの設置が容易である。
 図12は、実施の形態1に係る道路構造100及び比較例の道路構造1000の模式図である。実施の形態1に係る道路構造100は、中間格点鋼管50bを備え、隣り合う中間格点鋼管50b同士を梁部材40で接続している。そのため、図12(a)に示される様に、地震力による入力Fに対する支持杭10aに発生する曲げモーメントは、中間格点鋼管50bにより抑えられ、変位Δxも抑えられる。一方、比較例の道路構造1000は、中間格点鋼管50bも梁部材40も設置されていない。そのため、図12(b)に示される様に、地震力による入力Fに対する支持杭10aに発生する曲げモーメントは、実施の形態1に係る道路構造100よりも大きくなり、変位Δx1も大きくなる。
 以上のように、実施の形態1に係る道路構造100によれば、設置が容易で工期及びコストを抑えるだけでなく、地震力などによる入力Fに対して発生する曲げモーメント及び変位Δxを抑えることができる。そのため、道路構造100は、信頼性を向上させることができる。特に、実施の形態1に係る道路構造100は、地盤90から突出した支持杭10の上部に桁部材41及び道路床版99等の上部工を直接設けている。そのため、計画道路面に対して斜面の深さが深く、支持杭10の地盤90からの突出長が多大になる場合には、上部工に作用する地震力に対して、比較例の道路構造1000のように支持杭10の変形量及び応力が多大となる。従って、比較例の道路構造1000は、支持杭10の突出高さが10m程度より大きくなってしまうような地形に対して適用できないという課題があった。しかし、実施の形態1に係る道路構造100によれば、上記のように、支持杭10の地盤90からの突出長が多大であっても曲げモーメント及び変位Δxを抑えることができる。そのため、道路構造100は、地形に拘わらず設置ができるという利点がある。
 実施の形態2.
 実施の形態2に係る道路構造200は、実施の形態1に係る道路構造100に対し、少なくとも一部の偏心接合部材60の構造を変更したものである。実施の形態2に係る道路構造200においては、実施の形態1に対する変更点を中心に説明する。実施の形態2に係る道路構造200の各部については、各図面において同一の機能を有するものは実施の形態1の説明で使用した図面と同一の符号を付して表示するものとする。
 図13は、実施の形態2に係る道路構造200の上端格点鋼管250a周辺の断面構造の説明図である。図14は、実施の形態2に係る道路構造200の上端格点鋼管250aの上面図である。実施の形態2に係る道路構造200の上端格点鋼管250aは、鋼管部材251aと縦桁41aを接続する縦桁仕口52aと横桁41bを接続する横桁仕口53aとを備え、上面57aが平坦になっている。
 支持杭10の杭頭12の端面14には偏心接合部材260が接合されている。偏心接合部材260は、下端面が支持杭10の杭頭12に接合され、上端面が板部材261により形成されている。板部材261は、上面262が平坦になっており、上端格点鋼管250aの鋼管部材251aの下端面254aを載置できる様に構成されている。板部材261は、上面262が鋼管部材251aの下端面254aよりも大きく形成されている。従って、上端格点鋼管250aの鋼管部材251aは、偏心接合部材260の上面262上において水平方向にずらして載置することができる。つまり、支持杭10と上端格点鋼管250aとは、偏心接合部材260を用いて互いに中心軸を偏心させた状態で接合することができる。なお、実施の形態2における偏心接合部材260を第3偏心接合部材260と呼ぶ場合がある。また、上面262を接合面と呼ぶ場合がある。
 図15は、実施の形態2に係る道路構造200の中間格点鋼管250b周辺の構造の側面図である。偏心接合部材260は、中間格点鋼管250bと第1鋼管杭20aとの接合に用いても良い。実施の形態2に係る道路構造200は、中間格点鋼管250bの鋼管部材251bが第1鋼管杭20aと同じ断面形状になっている。中間格点鋼管250bは、鋼管部材251bと縦梁仕口52bと横梁仕口53bとから構成されている。実施の形態2においては、中間格点鋼管250bは、実施の形態1における鋼管支柱30と一体化されていても良い。このように構成されることにより、偏心接合部材260を用いて接合して形成された支持杭10aに梁部材40を設置することができる。
 実施の形態3.
 実施の形態3においては、実施の形態1に係る道路構造100の施工方法について説明する。
 道路構造100及び200は、まず道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤90に鋼管杭20が打設される。この工程を鋼管杭打設工程と呼ぶ。鋼管杭打設工程は、まず地盤90にダウンザホールハンマなどを用いて削孔し、鋼管杭20を建て込む孔95を形成する。孔95は、地盤90の表面94側にある堆積層92を貫通し、支持層93に達している。
 図16は、孔95に鋼管杭20を建て込んだ状態の説明図である。図16の中心線から右側の部分は、鋼管杭20の中心軸を含む断面における構造を示している。鋼管杭20は、孔95の底面96に先端が達するように孔95に建て込まれる。そして、鋼管杭20の位置を決めた状態で、鋼管杭20の上端の開口から充填材80が注入される。充填材80は、例えばモルタル又はセメント等が用いられる。充填材80は、中空の筒形状である鋼管杭20を通り、孔95の底面96側の鋼管杭20の端部に設けられている貫通孔15から孔95と鋼管杭20の外側面との間の隙間97に流れ込む。
 隙間97に流れ込んだ充填材80は、鋼管杭20の内部の空間が充填材80に満たされるに従い、隙間97を上昇する。充填材80が隙間97から地盤90の表面94から流出するのが確認できれば、鋼管杭20と孔95との間の隙間97が充填材80で満たされたことが確認できる。鋼管杭20と孔95との間の隙間97に地盤90の表面94から充填材80を直接充填した場合、鋼管杭20の周りに均等に充填材80を充填するのが困難である。また、地盤90の条件によっては、孔95の表面が円滑ではなく充填材80に土砂が混入したり、底面96まで十分に充填材80が充填されない場合がある。充填材80の充填が不十分な場合、鋼管杭20の支持力が設計値を確保できないおそれがある。しかし、実施の形態3における鋼管杭打設工程によれば、以上のように行うことで、鋼管杭20が地盤90に確実に打設される。
 鋼管杭20は、道路構造100及び200に複数用いられる。複数の鋼管杭20は、全て上記の鋼管杭打設工程により地盤90に打設される。
 次に、複数の鋼管杭20のうち第1鋼管杭20aに鋼管支柱30が仮接合され、支持杭10aが仮組立される。また、支持杭10aの杭頭12及び複数の鋼管杭20のうち第2鋼管杭20bの杭頭21bに上端格点鋼管50aが仮接合される。仮接合は、型枠治具70を用いることにより、一時的に鋼管支柱30、上端格点鋼管50a、及び中間格点鋼管50bを、鋼管杭20に設置することである。これを仮接合工程と呼ぶ。以下に仮接合工程の詳細について説明する。
 図17は、実施の形態3の仮接合工程に用いられる型枠治具70の構造の説明図である。図17においては、上端格点鋼管50aを鋼管杭20に設置する場合の図を示しているが、中間格点鋼管50bを設置する場合においても型枠治具70の使用方法は同じである。鋼管杭20の杭頭21に中間格点鋼管50bを設置する際に、鋼管杭20の杭頭21に型枠治具70を用いる。
 型枠治具70は、型枠板74を支持するブラケット71を備える。ブラケット71は、固定バンド73に接続されている。固定バンド73は、鋼管杭20の外側面を包囲する様にして鋼管杭20に着脱自在に固定され、ブラケット71の位置を固定する。固定バンド73により型枠治具70を鋼管杭20に設置する工程を特に型枠設置工程と呼ぶ。型枠設置工程は、仮接合工程に含まれる。
 中間格点鋼管50bは、鋼管部材51bの下端面に型枠治具70の型枠板74を当接させるように設置される。この工程を筒体設置工程と呼ぶ。筒体設置工程は、接合工程に含まれる。型枠板74は、中間格点鋼管50bの内部に注入される充填材80が漏れ出ないように設置される。
 ブラケット71は、調整ボルト75を備える。調整ボルト75の先端は、型枠板74の上に載置される中間格点鋼管50bの鋼管部材51bの外周面に当接する。調整ボルト75は、ナット部材76と螺合しており、先端の位置を精度良く調整できるとともに、中間格点鋼管50bの鋼管部材51bの位置を仮固定することができる。このように中間格点鋼管50bの鋼管部材51bの水平位置を調整し固定する工程を固定工程と呼ぶ。固定工程は、仮接合工程に含まれる。
 中間格点鋼管50bが第1鋼管杭20aの杭頭21aに取り付けられた後に、中間格点鋼管50bに鋼管支柱30が建て込まれる。これを鋼管支柱建て込み工程と呼ぶ。鋼管支柱建て込み工程は、仮接合工程に含まれる。
 次に、第1鋼管杭20aに鋼管支柱30が接続されている支持杭10a及び第2鋼管杭20bの杭頭12に上端格点鋼管50aが取り付けられる。上端格点鋼管50aの設置は、中間格点鋼管50bを鋼管杭20の杭頭21に設置するのと同様に、型枠設置工程、筒体設置工程、及び固定工程により行われる。
 中間格点鋼管50bが設置された後に、梁部材40が設置される。この工程を梁部材設置工程と呼ぶ。また、上端格点鋼管50aが設置された後に、桁部材41が設置される。この工程を桁部材設置工程と呼ぶ。梁部材設置工程及び桁部材設置工程は、仮接合工程に含めることができる。
 実施の形態1に係る道路構造100は、上記のように型枠治具70を用いることにより、格点鋼管50に充填材80を注入しない状態で支持杭10a及び10bを仮組立することができる。そのため、仮組立した支持杭10a及び10bの上に覆工版(図示せず)を設置し、道路に沿った第1方向に次々に支持杭10a及び10bを立設することができる。つまり、鋼管打設工程と仮接合工程とは、交互に繰り返され、道路全長分又は所定の道路の長さの分の支持杭10a及び10bが建て終わるまで繰り返される。以上の工程をまとめて、支持杭立設工程と呼ぶ。
 支持杭立設工程により、支持杭10a及び10bが建てられ、支持杭10a及び10aの杭頭12に上端格点鋼管50aが仮固定された状態になったら、格点鋼管50の内部に充填材80が注入される。この工程を注入固化工程と呼ぶ。なお、格点鋼管50は、上端格点鋼管50a及び中間格点鋼管50bを総称したものである。注入固化工程は、道路全長分の仮組立状態の支持杭10a及び10bを立設した後に、全ての格点鋼管50について実施すると良い。
 型枠治具70を用いないで道路構造100を設置する場合、道路に沿った第1方向に最初の支持杭10を建て、格点鋼管50に注入された充填材80を固化させた後に覆工版を支持杭10の上に設置する。そして、設置された覆工版の上に重機を載せ、次の支持杭10を建てる。このような工程の場合、支持杭10を建てるごとに充填材80の注入固化工程が必要となるため、工期が長くなってしまう。一方、道路構造100は、型枠治具70を用いることにより、充填材80の注入固化工程の回数を抑えることができるため、工期を短縮することができるという利点がある。
 道路構造100は、注入固化工程が完了した後に覆工版が撤去され、道路床版99が設置される。
 図18は、覆工版の一例を示す側面図である。覆工版は、鋼管杭打設工程と仮接合工程とを繰り返している際に仮組立てされた支持杭10の上に載置されるものである。図18に示される覆工版399は、仮設の杭頭ブロック350aを備えている。そのため、道路構造100の上端格点鋼管50aを設置せずに杭頭ブロック350aを杭頭12にはめ込み、覆工版399を設置できる様にしたものである。このような覆工版399を用いることにより、鋼管杭打設工程のみをまとめて実施することができるため、杭打機の拘束時間を短縮することができる。
 実施の形態4.
 実施の形態4においては、実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例について説明する。
 図19は、実施の形態1に係る道路構造100の変形例の断面構造の説明図である。図2~図4に示されている様に、実施の形態1の道路構造100は、道路が延びる第1方向に交差する第2方向に2本の支持杭10が並列されているが、2本以上の支持杭10が並列されていても良い。また、道路構造100は、上端格点鋼管50aと中間格点鋼管50bとの間、又は2つの中間格点鋼管50bの間を連結し、横桁41bに対し傾斜している斜め梁48を備えていても良い。斜め梁48は、支持杭10及び横桁41b又は横梁40bにより構成される矩形の構造の対角に位置する2つの格点鋼管50を連結するものである。道路構造100は、斜め梁48によるトラス構造によって架構の変形が抑止され、部材応力が低減できる。
 また、図19に示されている道路構造100は、実施の形態2の道路構造200で用いられている偏心接合部材260を用いて構成されていても良い。図19に示されている道路構造100は、支持杭10の杭頭12に実施の形態2に示されている上端格点鋼管250a及び偏心接合部材260が適用され、鋼管支柱30には図8に示されている二重管型の中間格点鋼管50bが設置されている。上端格点鋼管250aと横桁41bは、予め一体に製作されており、格点桁となっている。また、中間格点鋼管50bと横梁40bとは、予め一体に製作されており、格点梁となっている。これにより、格点鋼管50は、個別に測量心出し設置する手間が省け、省力化、工程短縮が図れる。また、上端格点鋼管250aは、横桁41bにより複数が一体化されているため、偏心接合部材260の上部に安定して設置できる。中間格点鋼管50bも横梁40bと一体に製造されており、同様な効果をもつ。また、格点鋼管50は斜材によって互いに接合されており、斜め梁48によるトラス構造によって架構の変形が抑止され、部材応力が低減できる。
 また、図19に示されている道路構造100は、接合部11において偏心接合部材260が適用されている。偏心接合部材260の上面262には鋼管支柱30の下側の端面が載置され、鋼管支柱30の水平方向位置が調整されて接合されている。
 図20及び図21は、上端格点鋼管250aと横桁41bとを一体化した格点桁の一例である。図19に示された道路構造100に適用されている格点桁は、具体的には図20及び図21に示されるような形態としても良い。
 図22及び図23は、実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例の断面構造の説明図である。図22に示される様に、道路構造100及び200の横桁41bは、地盤90の斜面側に張り出して形成されていても良い。この構造は、斜面勾配が急で鋼管杭20の設置が困難な場合に適用される。また、図23に示される様に、斜面を削って設けられた道路を拡幅する様に道路構造100及び200を設置することもできる。
 図24は、実施の形態1に係る道路構造100及び実施の形態2に係る道路構造200の変形例の側面図である。図24に示される様に、例えば地盤90からの突出量が少ない支持杭10bの杭頭12に免震部材5を設けても良い。これにより、道路構造100及び200は、全体に掛かる荷重負担が軽減する。
 以上に本発明を実施の形態に基づいて説明したが、本発明は上述した実施の形態の構成のみに限定されるものではない。特に構成要素の組み合わせは、実施の形態における組み合わせのみに限定するものではなく、各実施の形態に記載した構成要素の組み合わせは適宜変更することができる。また、いわゆる当業者が必要に応じてなす種々なる変更、応用、利用の範囲をも本発明の要旨(技術的範囲)に含むことを念のため申し添える。
 5 免震部材、10 支持杭、10a 支持杭、10b 支持杭、11 接合部、12 杭頭、13 突起、14 端面、15 貫通孔、20 鋼管杭、20a 第1鋼管杭、20b 第2鋼管杭、21 杭頭、21a 杭頭、21b 杭頭、22a 端面、30 鋼管支柱、30b 第2鋼管杭、31 端面、40 梁部材、40a 縦梁、40b 横梁、41 桁部材、41a 縦桁、41b 横桁、42 床版固定部材、43 連結部、44 添接板、48 梁、50 格点鋼管、50a 上端格点鋼管、50b 中間格点鋼管、51a 鋼管部材、51b 鋼管部材、52a 縦桁仕口、52b 縦梁仕口、53a 横桁仕口、53b 横梁仕口、54 突起、55a 支持部材、55b 支持部材、56a 充填孔、56b 充填口、57 ボルト、57a 上面、60 偏心接合部材、60a (第1)偏心接合部材、60b (第2)偏心接合部材、70 型枠治具、71 ブラケット、73 固定バンド、74 型枠板、75 調整用ボルト、76 ナット部材、80 充填材、90 地盤、92 堆積層、93 支持層、94 表面、95 孔、96 底面、97 隙間、99 道路床版、100 道路構造、150b 中間格点鋼管、200 道路構造、250a 上端格点鋼管、250b 中間格点鋼管、251a 鋼管部材、251b 鋼管部材、254a 下端面、260 (第3)偏心接合部材、261 板部材、262 上面、350a 杭頭ブロック、399 覆工版、1000 道路構造、C 中心軸、F 入力、Δx 変位、Δx1 変位。

Claims (18)

  1.  道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される第1鋼管杭及び第2鋼管杭を含む鋼管杭と、
     前記第1鋼管杭の上方に接続される鋼管支柱と、
     前記第2鋼管杭又は前記鋼管支柱の上端に設置される上端格点鋼管と、
     隣り合う2つの前記上端格点鋼管を連結する桁部材と、
     前記上端格点鋼管及び前記桁部材の上に設置される道路床版と、を備え、
     前記第1鋼管杭、前記第2鋼管杭、前記鋼管支柱、及び前記上端格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、
     前記下方部材と前記上方部材との接合部は、
     前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合される、道路構造。
  2.  前記偏心接合部材は、
     少なくとも第1偏心接合部材を含み、
     前記上端格点鋼管は、
     筒体を含む前記第1偏心接合部材を備え、
     前記筒体は、
     前記鋼管杭又は前記鋼管支柱の外形よりも大きく、
     前記鋼管杭又は前記鋼管支柱の外側面を包囲して設置され、
     前記筒体と前記鋼管杭又は前記鋼管支柱との間に形成される隙間は、
     充填材が充填される、請求項1に記載の道路構造。
  3.  前記筒体の内側面は、
     突起が設けられている、請求項2に記載の道路構造。
  4.  前記筒体は、
     縞鋼板又はリブ付き鋼板により形成される、請求項3に記載の道路構造。
  5.  前記桁部材は、
     前記第1方向に並列された2つの前記鋼管杭又は前記鋼管支柱の間に設置される縦桁を含む、請求項1~4の何れか1項に記載の道路構造。
  6.  前記桁部材は、
     前記第2方向に並列された2つの前記鋼管杭又は前記鋼管支柱の間に設置される横桁を含む、請求項1~5の何れか1項に記載の道路構造。
  7.  前記第1鋼管杭、前記第2鋼管杭、又は前記鋼管支柱に設置される中間格点鋼管と、
     隣り合う2つの前記中間格点鋼管を連結する梁部材と、をさらに備え、
     前記偏心接合部材は、
     少なくとも第2偏心接合部材を含み、
     前記第1鋼管杭、前記第2鋼管杭、前記鋼管支柱、前記上端格点鋼管、及び前記中間格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、前記下方部材と前記上方部材との接合部は、前記第2偏心接合部材により接合され、
     前記中間格点鋼管は、
     筒体を含む前記第2偏心接合部材を備え、
     前記筒体は、
     前記鋼管杭又は前記鋼管支柱の外形よりも大きく、
     前記鋼管杭又は前記鋼管支柱の外側面を包囲して設置され、
     前記筒体と前記鋼管杭又は前記鋼管支柱との間に形成される隙間は、
     充填材が充填される、請求項1~6の何れか1項に記載の道路構造。
  8.  前記筒体の内側面は、
     突起が設けられている、請求項7に記載の道路構造。
  9.  前記筒体は、
     縞鋼板又はリブ付き鋼板により形成される、請求項8に記載の道路構造。
  10.  前記偏心接合部材は、
     前記接合部において前記上方部材及び前記下方部材の両方の端部にまたがって配置される前記中間格点鋼管を含む、請求項7~9の何れか1項に記載の道路構造。
  11.  前記梁部材は、
     前記第1方向に並列された2つの前記鋼管杭又は前記鋼管支柱の間に設置される縦梁を含む、請求項7~10の何れか1項に記載の道路構造。
  12.  前記梁部材は、
     前記第2方向に並列された2つの前記鋼管杭又は前記鋼管支柱の間に設置される横梁を含む、請求項7~11の何れか1項に記載の道路構造。
  13.  前記横梁は、
     前記中間格点鋼管と一体に形成されている、請求項12に記載の道路構造。
  14.  前記上端格点鋼管と前記中間格点鋼管との間、又は2つの前記中間格点鋼管の間を連結し、前記横桁に対し傾斜している斜め梁をさらに備える、請求項7~13の何れか1項に記載の道路構造。
  15.  前記偏心接合部材は、
     少なくとも第3偏心接合部材を含み、
     前記第3偏心接合部材は、
     上面に前記上方部材が接合される接合面を備え、前記下方部材の上端に接合され、
     前記接合面の外形は、
     前記上方部材の外形よりも大きい、請求項1~14の何れか1項に記載の道路構造。
  16.  前記鋼管杭は、
     中空の筒形状であり前記地盤の中に位置する側の端部の外周に開口された貫通孔を備える、請求項1~15の何れか1項に記載の道路構造。
  17.  道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される鋼管杭と、
     前記鋼管杭の上方に接続される鋼管支柱と、
     前記鋼管杭又は前記鋼管支柱に設置される格点鋼管と、を備え、
     前記鋼管杭、前記鋼管支柱、及び前記格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、
     前記下方部材と前記上方部材との接合部は、
     前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合され、
     前記偏心接合部材は、
     筒体を備え、
     前記筒体は、
     前記鋼管杭又は前記鋼管支柱の外周面を包囲して設置され、
     前記筒体と前記鋼管杭又は前記鋼管支柱との間に形成される間隙は、
     充填材が充填される、道路構造の前記偏心接合部材を設置する際に用いる型枠治具であって、
     前記下方部材の外周面を包囲し前記筒体の下端に接して設置される型枠板と、
     前記筒体の水平位置を調整し固定する調整ボルトと、
     前記型枠板及び前記調整ボルトを支持し、前記下方部材に着脱自在に固定されるブラケットと、を備える、型枠治具。
  18.  道路が延びる第1方向及び前記第1方向に交差する第2方向に並列して地盤に打設される鋼管杭と、
     前記鋼管杭の上方に接続される鋼管支柱と、
     前記鋼管杭又は前記鋼管支柱に設置される格点鋼管と、を備え、
     前記鋼管杭、前記鋼管支柱、及び前記格点鋼管のうち、下方に位置する部材を下方部材とし、前記下方部材の上方に接合される部材を上方部材としたときに、
     前記下方部材と前記上方部材との接合部は、
     前記下方部材の中心軸と前記上方部材の中心軸とを偏心させた状態で接合できる偏心接合部材により接合される、道路構造の施工方法であって、
     前記下方部材と前記上方部材を接合する仮接合工程を備え、
     前記仮接合工程は、
     前記偏心接合部材が備える筒体を前記下方部材の上端部の外周面を包囲して設置する筒体設置工程と、
     型枠治具が備える型枠板を前記下方部材の外周面を包囲し前記筒体の下端に接するように設置する型枠設置工程と、
     調整ボルトにより前記筒体の水平位置を調整し固定する固定工程と、を備える、道路構造の施工方法。
PCT/JP2019/043674 2019-11-07 2019-11-07 道路構造、型枠治具、及び道路構造の施工方法 WO2021090439A1 (ja)

Priority Applications (5)

Application Number Priority Date Filing Date Title
PCT/JP2019/043674 WO2021090439A1 (ja) 2019-11-07 2019-11-07 道路構造、型枠治具、及び道路構造の施工方法
JP2021554967A JP7371113B2 (ja) 2019-11-07 2020-11-05 道路構造、型枠治具、及び道路構造の施工方法
PCT/JP2020/041331 WO2021090873A1 (ja) 2019-11-07 2020-11-05 道路構造、型枠治具、及び道路構造の施工方法
PH12021550584A PH12021550584A1 (en) 2019-11-07 2021-03-16 Road structure, formwork jig, and method for constructing road structure
JP2023179392A JP7490128B2 (ja) 2019-11-07 2023-10-18 道路構造

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2019/043674 WO2021090439A1 (ja) 2019-11-07 2019-11-07 道路構造、型枠治具、及び道路構造の施工方法

Publications (1)

Publication Number Publication Date
WO2021090439A1 true WO2021090439A1 (ja) 2021-05-14

Family

ID=75848218

Family Applications (2)

Application Number Title Priority Date Filing Date
PCT/JP2019/043674 WO2021090439A1 (ja) 2019-11-07 2019-11-07 道路構造、型枠治具、及び道路構造の施工方法
PCT/JP2020/041331 WO2021090873A1 (ja) 2019-11-07 2020-11-05 道路構造、型枠治具、及び道路構造の施工方法

Family Applications After (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/041331 WO2021090873A1 (ja) 2019-11-07 2020-11-05 道路構造、型枠治具、及び道路構造の施工方法

Country Status (3)

Country Link
JP (2) JP7371113B2 (ja)
PH (1) PH12021550584A1 (ja)
WO (2) WO2021090439A1 (ja)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7346770B1 (ja) * 2022-08-05 2023-09-19 Jfeシビル株式会社 人工地盤構造物

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7463331B2 (ja) 2021-11-09 2024-04-08 Jfeスチール株式会社 仮設治具、該仮設治具を用いた人工地盤の構築方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60144427A (ja) * 1984-01-09 1985-07-30 Nippon Kokan Kk <Nkk> 海洋構造物支持鋼管杭の防食加工方法及び防食加工用型枠
JPH10227002A (ja) * 1996-12-11 1998-08-25 Kawasaki Steel Corp 拡幅道路およびその施工方法
JP2001303604A (ja) * 2000-04-25 2001-10-31 Nippon Steel Corp 鋼管杭と上部構造との接合構造
JP2011117274A (ja) * 2009-10-27 2011-06-16 Jfe Civil Engineering & Construction Corp 道路等の人工地盤及びその構築方法
JP2017115552A (ja) * 2015-12-25 2017-06-29 清水建設株式会社 ブレースバンドおよび構台の設置方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282403A (ja) 1999-03-30 2000-10-10 Kawasaki Steel Corp 道路用人工地盤およびその構築方法
JP3978642B2 (ja) * 2000-11-14 2007-09-19 Jfeシビル株式会社 杭と桁の結合構造体
JP4677690B2 (ja) * 2001-07-23 2011-04-27 Jfeスチール株式会社 杭の摩擦力増大方法
KR101181678B1 (ko) * 2011-10-25 2012-09-19 (주)에이치앤디건설 법면 확장 보도
CN106536825B (zh) 2014-06-30 2019-11-01 株式会社高知丸高 桥梁施工方法及桥梁结构

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60144427A (ja) * 1984-01-09 1985-07-30 Nippon Kokan Kk <Nkk> 海洋構造物支持鋼管杭の防食加工方法及び防食加工用型枠
JPH10227002A (ja) * 1996-12-11 1998-08-25 Kawasaki Steel Corp 拡幅道路およびその施工方法
JP2001303604A (ja) * 2000-04-25 2001-10-31 Nippon Steel Corp 鋼管杭と上部構造との接合構造
JP2011117274A (ja) * 2009-10-27 2011-06-16 Jfe Civil Engineering & Construction Corp 道路等の人工地盤及びその構築方法
JP2017115552A (ja) * 2015-12-25 2017-06-29 清水建設株式会社 ブレースバンドおよび構台の設置方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7346770B1 (ja) * 2022-08-05 2023-09-19 Jfeシビル株式会社 人工地盤構造物
WO2024029070A1 (ja) * 2022-08-05 2024-02-08 Jfeシビル株式会社 人工地盤構造物
JP7430842B1 (ja) 2022-08-05 2024-02-13 Jfeシビル株式会社 人工地盤構造物

Also Published As

Publication number Publication date
WO2021090873A1 (ja) 2021-05-14
JP7490128B2 (ja) 2024-05-24
JPWO2021090873A1 (ja) 2021-05-14
JP7371113B2 (ja) 2023-10-30
JP2023174870A (ja) 2023-12-08
PH12021550584A1 (en) 2021-10-25

Similar Documents

Publication Publication Date Title
JP7490128B2 (ja) 道路構造
JP2000248526A (ja) 桟橋構造およびその構築方法
JP7103962B2 (ja) 土留め構造及び土留め方法
JP5456626B2 (ja) 杭と鉄骨柱との接合構造および接合方法
KR102462488B1 (ko) 인터러킹 전단연결재를 이용한 프리캐스트 슬래브 및 이를 이용한 교량시공방법
JP4912030B2 (ja) 橋脚と杭との接合部構造
JP2003090052A (ja) 基礎構築方法及びフーチング基礎並びに高架式交通路の基礎構造
KR102254227B1 (ko) Pc 말뚝캡이 구비된 고강도 콘크리트 말뚝 구조체 및 이의 시공 방법
JP7158231B2 (ja) 合成柱及びそれを用いた橋脚、施工方法
JP5456627B2 (ja) 杭と鉄骨柱との接合構造および接合方法
KR101198286B1 (ko) 지하외벽의 연속시공을 위한 역타지지공법용 논웨일 스트러트 시스템 및 이에 의한 지하구조물의 역타 시공방법
CN106812359A (zh) 一种装配式地下车库及其建造方法
JP3671344B2 (ja) 基礎杭と柱脚部との接合構造およびその構築方法
KR102233513B1 (ko) 플랜지-웨브 보강 형강
JP6985037B2 (ja) 橋脚基礎構造
JP2004324340A (ja) フーチング基礎用鋼殻、橋梁の構造、橋梁の構築方法、及び立体交差橋の構築方法
JP6869825B2 (ja) 橋脚基礎構造
JP2021063340A (ja) 杭基礎構造
JP7138146B2 (ja) 基礎構造物、環状体、鋼製セグメントの連結機構及び基礎構造物の施工方法
JP2020094421A (ja) 杭と上部構造との接合構造、接合構造の施工方法、及び構造物
JP7481208B2 (ja) 土留め構造
KR20130066300A (ko) 고강도 대구경 피에이치씨 파일과 철골부재의 연결구조 및 이를 이용한 역타공법
JP3988612B2 (ja) 立体交差道路の施工方法および立体交差道路
JP7346770B1 (ja) 人工地盤構造物
JPH08246436A (ja) 鋼管杭と鋼製上部構造よりなる構造物の構築方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19951982

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19951982

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: JP