WO2020003376A1 - Module d'installation - Google Patents

Module d'installation Download PDF

Info

Publication number
WO2020003376A1
WO2020003376A1 PCT/JP2018/024169 JP2018024169W WO2020003376A1 WO 2020003376 A1 WO2020003376 A1 WO 2020003376A1 JP 2018024169 W JP2018024169 W JP 2018024169W WO 2020003376 A1 WO2020003376 A1 WO 2020003376A1
Authority
WO
WIPO (PCT)
Prior art keywords
scaffold
passage
unit
floor
plant module
Prior art date
Application number
PCT/JP2018/024169
Other languages
English (en)
Japanese (ja)
Inventor
佐藤 健二
尚子 岡本
Original Assignee
日揮グローバル株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日揮グローバル株式会社 filed Critical 日揮グローバル株式会社
Priority to PCT/JP2018/024169 priority Critical patent/WO2020003376A1/fr
Priority to SG11202005506QA priority patent/SG11202005506QA/en
Priority to CN201880078223.6A priority patent/CN111433424B/zh
Priority to KR1020207015558A priority patent/KR20210023792A/ko
Priority to KR1020237025789A priority patent/KR102653819B1/ko
Priority to BR112020012798-1A priority patent/BR112020012798B1/pt
Publication of WO2020003376A1 publication Critical patent/WO2020003376A1/fr

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B81/00Repairing or maintaining vessels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F02COMBUSTION ENGINES; HOT-GAS OR COMBUSTION-PRODUCT ENGINE PLANTS
    • F02CGAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS
    • F02C7/00Features, components parts, details or accessories, not provided for in, or of interest apart form groups F02C1/00 - F02C6/00; Air intakes for jet-propulsion plants
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B2035/4433Floating structures carrying electric power plants
    • B63B2035/444Floating structures carrying electric power plants for converting combustion energy into electric energy
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B2035/448Floating hydrocarbon production vessels, e.g. Floating Production Storage and Offloading vessels [FPSO]
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C5/00Equipment usable both on slipways and in dry docks
    • B63C5/02Stagings; Scaffolding; Shores or struts
    • B63C2005/025Stagings, or scaffolding, i.e. constructions providing temporary working platforms on slipways, in building or repair docks, or inside hulls

Definitions

  • the present invention relates to a plant module including a plurality of arrangement units in which devices are arranged.
  • module which is a machine block constituting one unit of a plant such as an FLNG facility (Floating Liquefied Natural Gas) (see, for example, Patent Document 1).
  • FLNG facility Floating Liquefied Natural Gas
  • a plurality of arrangement units in which a gas turbine and a generator for generating electric power by driving the gas turbine are arranged are arranged.
  • each arrangement unit 126 is arranged to be adjacent to each other with an interval.
  • a passage 128 is formed between adjacent arrangement units 126, and each arrangement unit 126 is provided with a dedicated scaffold 116.
  • the scaffold 116 is provided at a predetermined height to facilitate daily work.
  • a core which is a main component of the gas turbine 110, is pulled out from the gas turbine 110. Since the core is located at a predetermined height from the deck 104, the core passes over the scaffolds 116 and is lowered onto the passage 128 between the adjacent scaffolds 116. The unloaded core is carried out of the module 122 through a passage 128 formed between the scaffolds 116.
  • the module 122 constituting the FLNG equipment needs to be designed so that all the equipment is installed in the limited space while securing the space necessary for the maintenance of the equipment as described above.
  • the conventional module 122 can secure a space for carrying out the gas turbine 110 at the time of the periodic maintenance, the scaffold 116 is provided in each gas turbine 110 to secure the space. Is not fully considered and there is room for improvement.
  • the room for improvement described above is not limited to floating-type facilities such as FLNG facilities, but exists in all large-scale plants including modules, such as natural gas processing facilities constructed on the ground.
  • An object of the present invention is to provide a compact plant module while securing space for carrying out equipment during maintenance.
  • the present invention includes the following items.
  • a plurality of arrangement units in which devices are arranged A scaffold that is connected to the placement unit and allows an operator to work on the placement unit;
  • Evacuation means for evacuation of the scaffold from the passage A plant module, wherein the scaffold is installed between one of the arrangement units and the other of the arrangement units, and connects one of the arrangement units and the other of the arrangement units on the passage.
  • the scaffold has a transfer path scaffold located on a transfer path on which the device is transferred, and a transfer path outside scaffold located outside the transfer path, The transport path upper scaffold and the transport path outer scaffold are separated from each other, The plant module according to [1], wherein the scaffold on the transport path has the retreating means.
  • the scaffold is A floor portion having a floor surface on which an operator moves, A pillar for holding the floor at a predetermined height from the deck; A fixing portion for detachably fixing the pillar portion to the deck, A joint member for joining the fixing portion and the deck, The plant module according to [1] or [2], wherein the module is retracted from the passage when the joining member is removed.
  • the scaffold includes a roller disposed between the pillar and the deck; The plant module according to [3], wherein the retracting unit is the roller.
  • the scaffold is A floor portion having a floor surface on which an operator moves, A hinge portion for opening and closing at least a part of the floor portion, With The retracting means is the hinge portion, The plant module according to [1] or [2], wherein the scaffold retreats from the passage by rotating the floor via the hinge.
  • the scaffold is A floor portion having a floor surface on which an operator moves, A lift unit for vertically moving the floor, With The evacuation unit is the lift unit, The plant module according to [1] or [2], wherein the scaffold raises the floor section via the lift section and retreats from the passage.
  • the retreating means is the plant module of [1] or [2], which is the hanging part.
  • the plant module according to [9], wherein the floating equipment is FLNG equipment (Floating Liquefied Natural Gas).
  • FIG. 1 It is an outline perspective view showing the module for plants concerning an embodiment. It is the schematic diagram which looked at the principal part of the module for plants which concerns on embodiment from above. It is the schematic diagram which looked at the principal part of the module for plants which concerns on embodiment from the side (X direction of FIG. 2). It is the schematic diagram which looked at the principal part of the module for plants which concerns on embodiment from the side (Y direction of FIG. 2). It is an enlarged view of the pillar base part of the pillar part concerning embodiment. It is a figure showing the state where the scaffold concerning an embodiment was evacuated. It is an enlarged view of the column base part of the column part concerning other embodiments. It is a schematic diagram in the case where a hinge part is provided as a retreat means of the scaffold according to the embodiment. FIG.
  • FIG. 8A is a schematic view of a main part of the plant module as viewed from above, and FIG. 8B is a side view of the main part of the plant module from the side (the Z direction in FIG. 8A). It is the schematic diagram seen. It is a schematic diagram in the case where a hinge part is provided as a retreat means of the scaffold according to the embodiment.
  • FIG. 10A is a schematic diagram illustrating a case where a lift unit is provided
  • FIG. 10B is a schematic diagram illustrating a case where a suspension unit is provided as a scaffold retreating unit according to the embodiment. It is a principal part enlarged view of the conventional module for plants.
  • FIG. 1 is a perspective view of the module according to the embodiment as viewed from above.
  • the plant module 2 (hereinafter abbreviated as module 2) includes FLNG equipment (Floating Liquefied Natural Gas: Floating Liquefied Natural Gas Production Equipment) and FPSO equipment (Floating Production, Storage and Offloading System: Floating Offshore Oil and Gas Production). It is a machine block that constitutes one unit of a plant mounted on a floating facility such as a storage and unloading facility, and a plurality of stories are formed by the deck 4.
  • FLNG equipment Floating Liquefied Natural Gas: Floating Liquefied Natural Gas Production Equipment
  • FPSO equipment Floating Production, Storage and Offloading System: Floating Offshore Oil and Gas Production
  • FIGS. 2 to 4 are schematic diagrams of the arrangement unit 6 which is a unit section for arranging devices in the module 2.
  • FIG. 2 is a diagram of the arrangement unit 6 as viewed from above
  • FIG. 3 is a diagram of these as viewed from the X direction shown in FIG.
  • FIG. 4 is a diagram of these as viewed from the Y direction shown in FIG.
  • the plurality of arrangement units 6 arranged in the module 2 only two arrangement units 6 are displayed.
  • the module 2 includes a plurality of arrangement units 6 on which devices are arranged, and a scaffold 7 connected to the arrangement units 6 for the worker H to work on the arrangement units 6.
  • devices such as the gas turbine 10 and the generator 12 are mounted on the arrangement unit 6.
  • the generator 12 is a device that generates power by driving the gas turbine 10.
  • the arrangement unit 6 is formed in a rectangular shape.
  • the gas turbine 10 is arranged such that the longitudinal direction of a shaft (not shown) matches the long side direction of the arrangement unit 6.
  • Adjacent arrangement units 6 are arranged such that long sides face each other. Adjacent arrangement units 6 are arranged so that the gas turbine 10 faces in the same direction.
  • the passage 8 is formed between two adjacent placement units 6 and also has a role as a transfer path for transferring the gas turbine 10 and the generator 12.
  • the scaffold 7 is installed between the one arrangement unit 6a and the other arrangement unit 6b, and connects the one arrangement unit 6a and the other arrangement unit 6b on the passage 8.
  • the scaffold 7 is a work floor on which the worker H works on the placement unit 6, and is connected to the placement unit 6.
  • the work includes, for example, daily work such as maintenance and management of the gas turbine 10 and the generator 12 and periodic work such as periodic maintenance of the gas turbine 10 and the generator 12.
  • the scaffold 7 of the present embodiment includes a floor 18 and a pillar 20.
  • the floor portion 18 is formed in a rectangular plate shape, and a floor surface on which the worker H moves is formed on the upper surface.
  • the pillar portion 20 is detachably fixed to the deck 4, and holds the floor portion 18 at a predetermined height from the deck 4.
  • the scaffold 7 of the present embodiment connects one arrangement unit 6a and the other arrangement unit 6b, which are located on the passage 8 and on both sides in the width direction of the passage 8, with each other. Therefore, the worker H can easily move to the other placement unit 6b across the scaffold 7 and perform the work without going down to the passage 8 after finishing the work in one placement unit 6a. For this reason, the burden of daily work on the worker is reduced.
  • FIG. 5 is an enlarged view of a pillar portion of the pillar portion 20.
  • the scaffold 7 includes the evacuation unit 9.
  • the scaffold 7 includes a roller 22 as the retracting means 9 between the pillar portion 20 and the deck 4.
  • the roller 22 is arranged between the lower end of the pillar 20 and the deck 4. The roller 22 is used when the scaffold 7 is retracted (moved) from the passage 8.
  • plates 24 as fixing portions for detachably fixing the pillar portion 20 to the deck 4 are arranged.
  • the plate 24 and the deck 4 and the plate 24 and the column 20 are respectively joined by bolts 26 as joining members via flanges 24a and 24b.
  • the plate 24 is provided on the column 20 to which the roller 22 is attached, and the column 20 is fixed to the deck 4. As described above, by disposing the plate 24 with the roller 22 serving as a movable part therebetween and fixing the pillar portion 20 to which the roller 22 is attached directly to the deck 4, the scaffold 7 that is resistant to shaking particularly at sea is realized. Can be.
  • the scaffold 7 (a scaffold 7a on a transport route to be described later) located on the unloading route of the core 11 of the gas turbine 10 to be maintained can be retracted, thereby performing maintenance. At times, the scaffold 7 can be moved to form a carry-out path for the core 11. Specifically, by retreating the scaffold 7, it is possible to secure a space that extends in the vertical direction for pulling out the core 11 from the gas turbine 10 and lowering it on the deck 4, and moving the lowered core 11 out of the module 2. A space extending in the horizontal direction for carrying out can be secured. For this reason, an independent scaffold is not required for each arrangement unit 6, and a compact module 2 in which the arrangement units 6 are installed close to each other can be realized, and the core 11 of the gas turbine 10 is easily carried out during maintenance. It becomes possible.
  • the width of the module 2 can be reduced and the scaffold 7 can be retracted from the passage 8 by the shared use of the scaffolds 7 and the arrangement units 6 can be installed close to each other, so that the core 11 of the gas turbine 10 is carried out during maintenance. Space can be secured. Further, when the scaffold 7 is retracted out of the passage 8, the roller 22 is moved while running on the passage 8, so that the evacuation operation is easy.
  • the scaffold 7 is installed so as to connect the adjacent placement units 6, so that the common work can be performed on both placement units 6 using the common scaffold 7. It can be performed.
  • the module 2 of the present invention is not limited to the above-described embodiment, and it is needless to say that various modifications can be made without departing from the scope of the present invention.
  • an L-shaped plate having an L-shaped cross section is provided on both sides of the pillar portion 20 with the roller 22 therebetween, as a fixing portion for detachably fixing the pillar portion 20 to the deck 4. 25 may be arranged. Also in this case, it is possible to realize the scaffold 7 that is resistant to shaking on the sea.
  • the bolts 26 and the rollers 22 function as the retreating means 9 for the scaffold 7, remove the bolts 26 from the deck 4 and the plate 24, and roll the rollers 22 disposed below the pillars 20.
  • the scaffold 7 is retracted out of the passage 8, but the retracting means 9 of the scaffold 7 may be other than the bolt 26 and the roller 22.
  • the scaffold 7 is provided with a hinge 30 as a retreating means 9 for the scaffold 7, and the floor 18 is opened and closed with the hinge 30 as an axis, thereby retreating the scaffold 7 from above the passage 8. You may let it. Specifically, when unloading the core 11 of the gas turbine 10, as shown in FIG.
  • the floor 18 is rotated upward about the hinge 30 and the floor 18 is rotated.
  • the scaffold 7 may be retracted by being folded toward the gas turbine 10 located on the opposite side to the gas turbine 10 from which the core 11 is pulled out. Then, the core 11 may be pulled out from the other arrangement unit 6b, lowered on the passage 8 (see the broken line arrow in FIG. 8B), and carried out. Also in this case, the core 11 of the gas turbine 10 can be easily carried out at the time of maintenance while reducing the burden of daily work.
  • FIG. 8A shows a case where the hinge unit 30 is provided on one of the arrangement units 6a, but the hinge unit 30 may be provided on the other arrangement unit 6b. . Further, the hinge portion 30 may be provided on both the one arrangement unit 6a and the other arrangement unit 6b, and may be folded on either arrangement unit 6 side.
  • the entire floor 18 is rotated around the hinge 30. However, only a part of the floor 18 may be rotated. For example, as shown in FIG. 9, the floor 18 may be bisected at the center, and only the floor 18 located on the side opposite to the side where the core 11 of the gas turbine 10 is carried out may be folded. Then, the core 11 may be pulled out from the other arrangement unit 6b, passed over the floor 18, and then lowered onto the passage 8 (see the dashed arrow in FIG. 9).
  • the scaffold 7 may include, as the evacuation unit 9, a lift unit 32 that moves the floor 18 up and down in the vertical direction.
  • the lift 32 is raised to retreat the scaffold 7 upward.
  • the core 11 can be easily carried out at the time of maintenance while reducing the burden of daily work.
  • the module 2 is provided with, for example, a hanging portion for hanging the scaffold 7 and vertically moving the deck 4 on the deck 4 located above the ceiling 8 (on the ceiling side).
  • the suspension may be a winch 33 that has a pulley 34 and a chain 36 that is connected to the pulley 34 so as to be wound up.
  • a hook portion such as a hook (not shown) may be provided on the scaffold 7, and the chain 36 hooked on the hook portion may be wound or unwound by the pulley 34 to raise and lower the floor portion 18 in the vertical direction.
  • the winch 33 functions as the evacuation means 9 for the scaffold 7.
  • the pulley 34 may have a function of moving the deck 4 on the ceiling side in the horizontal direction.
  • the pulley 34 moves the suspended scaffold 7 in the horizontal direction along the passage 8 and retreats from the passage 8.
  • You may.
  • the hanging portion may be a permanent crane fixed to the ceiling, or may be a crane carried in as needed.
  • the path 8 includes a transport path 8a serving as a path on which the core 11 as a device is transported, and a non-transport path 8b other than the transport path 8a. May be provided. That is, the non-transport path 8b is a portion of the passage 8 through which the core 11 does not pass.
  • the scaffold 7 may include a transport path upper scaffold 7a located on the transport path 8a and a transport path outer scaffold 7b located outside the transport path 8a (non-transport path 8b).
  • the transport path upper scaffold 7a and the transport path outer scaffold 7b are separated from each other and independent of each other.
  • the transport path upper scaffold 7a located on the path 8 serving as the path 8a has a retracting means 9 for retracting the transport path upper scaffold 7a.
  • the module 2 is mounted on a floating facility such as an FLNG facility or an FPSO facility is described as an example, but the module 2 may be arranged on the ground.
  • the embodiment according to the present invention can also be applied to a module 2 configuring a large plant such as a natural gas processing facility constructed on the ground.
  • the case where the gas turbine 10 is mounted on the arrangement unit 6 and the core 11 of the gas turbine 10 is carried out is taken as an example, but devices other than the core 11 of the gas turbine 10 are arranged. It may be mounted on the unit 6 and carried out.
  • the present invention is not limited to this.
  • Different devices may be placed on adjacent placement units 6.
  • the gas turbine 10 may be installed in one arrangement unit 6a
  • the pump may be installed in the other arrangement unit 6b
  • the passage 8 may be formed between the one arrangement unit 6a and the other arrangement unit 6b.
  • the equipment installed in one of the adjacent arrangement units 6a is drawn out to the passage 8 and carried out during maintenance, and the equipment installed in the other arrangement unit 6b is carried out during maintenance.
  • maintenance may be performed in the other arrangement unit 6b.
  • the pair of plates 24 are provided on both sides of the column 20 in a direction intersecting (orthogonal to) the moving direction of the roller 22 (see FIGS. 5 and 7).
  • the pair of plates 24 may be provided on both sides of the column 20 in the moving direction of the roller 22.
  • the case where at least two arrangement units 6 are mounted on the deck 4 has been described, but the present invention is not limited to this. Three or more arrangement units 6 may be placed adjacent to the deck 4. In this case, three or more arrangement units 6 may be arranged in a line, and a passage 8 may be formed between adjacent arrangement units 6.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • General Factory Administration (AREA)
  • Wind Motors (AREA)

Abstract

La présente invention vise à fournir un module d'installation compact qui permet à un équipement d'être facilement retiré pendant l'entretien tout en maintenant l'efficacité de travail. À cet effet, l'invention concerne un module d'installation qui comprend : une pluralité d'unités d'équipement dans lesquelles un équipement est disposé ; un échafaudage qui est relié aux unités d'équipement et qui permet à un travailleur d'effectuer un travail sur les unités d'équipement ; un pont sur lequel les unités d'équipement et l'échafaudage sont placés ; un passage qui est formé entre deux unités d'équipement et qui est destiné à transporter l'équipement ; et un moyen de rétractation pour rétracter l'échafaudage à partir du passage. L'échafaudage est installé entre une unité d'équipement et une autre unité d'équipement et relie l'unité d'équipement à l'autre unité d'équipement sur le passage.
PCT/JP2018/024169 2018-06-26 2018-06-26 Module d'installation WO2020003376A1 (fr)

Priority Applications (6)

Application Number Priority Date Filing Date Title
PCT/JP2018/024169 WO2020003376A1 (fr) 2018-06-26 2018-06-26 Module d'installation
SG11202005506QA SG11202005506QA (en) 2018-06-26 2018-06-26 Plant module
CN201880078223.6A CN111433424B (zh) 2018-06-26 2018-06-26 工厂用模块
KR1020207015558A KR20210023792A (ko) 2018-06-26 2018-06-26 플랜트용 모듈
KR1020237025789A KR102653819B1 (ko) 2018-06-26 2018-06-26 플랜트용 모듈
BR112020012798-1A BR112020012798B1 (pt) 2018-06-26 2018-06-26 Módulo de planta

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2018/024169 WO2020003376A1 (fr) 2018-06-26 2018-06-26 Module d'installation

Publications (1)

Publication Number Publication Date
WO2020003376A1 true WO2020003376A1 (fr) 2020-01-02

Family

ID=68986880

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2018/024169 WO2020003376A1 (fr) 2018-06-26 2018-06-26 Module d'installation

Country Status (5)

Country Link
KR (2) KR102653819B1 (fr)
CN (1) CN111433424B (fr)
BR (1) BR112020012798B1 (fr)
SG (1) SG11202005506QA (fr)
WO (1) WO2020003376A1 (fr)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5443827U (fr) * 1977-09-02 1979-03-26
JPS62129064A (ja) * 1985-11-29 1987-06-11 前澤工業株式会社 高層建築物用緊急避難装置
JPS62299797A (ja) * 1986-06-20 1987-12-26 株式会社日立製作所 高圧タ−ビン点検分解用架台
JPH09310484A (ja) * 1996-05-21 1997-12-02 Takenaka Komuten Co Ltd 大空間対応吊り足場構築システム
JP2009281029A (ja) * 2008-05-21 2009-12-03 Ohbayashi Corp 作業方法及び作業足場
JP2015068102A (ja) * 2013-09-30 2015-04-13 株式会社Ihiインフラシステム 渡り通路装置
JP2016049929A (ja) * 2014-09-02 2016-04-11 三井造船株式会社 浮体式洋上設備、及び、浮体式洋上設備の電力供給方法
US20170045026A1 (en) * 2015-08-10 2017-02-16 Zupeng Fang Deep water power generation station, power station, marine power plant and offshore floating city thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06135520A (ja) * 1992-07-21 1994-05-17 Daifuku Koei Kk 枠組棚構築装置
JP5403358B2 (ja) 2009-12-10 2014-01-29 株式会社ダイフク 物品保管設備
KR20130000129U (ko) * 2011-06-27 2013-01-04 대우조선해양 주식회사 곡외판 작업용 승강대
JP5713203B2 (ja) * 2012-03-27 2015-05-07 株式会社ダイフク 物品収納設備
ITFI20120114A1 (it) 2012-06-08 2013-12-09 Nuovo Pignone Srl "modular gas turbine plant with a heavy duty gas turbine"

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5443827U (fr) * 1977-09-02 1979-03-26
JPS62129064A (ja) * 1985-11-29 1987-06-11 前澤工業株式会社 高層建築物用緊急避難装置
JPS62299797A (ja) * 1986-06-20 1987-12-26 株式会社日立製作所 高圧タ−ビン点検分解用架台
JPH09310484A (ja) * 1996-05-21 1997-12-02 Takenaka Komuten Co Ltd 大空間対応吊り足場構築システム
JP2009281029A (ja) * 2008-05-21 2009-12-03 Ohbayashi Corp 作業方法及び作業足場
JP2015068102A (ja) * 2013-09-30 2015-04-13 株式会社Ihiインフラシステム 渡り通路装置
JP2016049929A (ja) * 2014-09-02 2016-04-11 三井造船株式会社 浮体式洋上設備、及び、浮体式洋上設備の電力供給方法
US20170045026A1 (en) * 2015-08-10 2017-02-16 Zupeng Fang Deep water power generation station, power station, marine power plant and offshore floating city thereof

Also Published As

Publication number Publication date
CN111433424B (zh) 2022-03-08
BR112020012798B1 (pt) 2023-11-28
KR102653819B1 (ko) 2024-04-02
KR20210023792A (ko) 2021-03-04
CN111433424A (zh) 2020-07-17
SG11202005506QA (en) 2020-07-29
KR20230117474A (ko) 2023-08-08
BR112020012798A2 (pt) 2020-11-24

Similar Documents

Publication Publication Date Title
US4546578A (en) Transportable holding assembly for rapid erection of buildings
JP2006348691A (ja) 建物の外壁部の施工システム
WO2020003376A1 (fr) Module d'installation
KR20140098362A (ko) 윈치 가이드 장치
US20220306431A1 (en) Construction System
CN109812027A (zh) 一种卸料平台及其安装方法
CN106365030A (zh) 一种吊篮
CN111017695A (zh) 履带吊配合吊排系统吊装大型船体总段的工艺
CN106477350B (zh) 桥式装卸船机的拆除方法
JPH05147884A (ja) 分解型ジブクレーン
JP2006348692A (ja) 建物外壁部施工用の資材搬送システム
JP2012189078A (ja) トルクコンバータ及び始動モータをガスタービンの補助コンパートメントから取り外す方法
WO2020224048A1 (fr) Système d'enroulement de câble de levage et mécanisme de levage pour chariot inférieur externe de grue de quai classique
JP5365958B2 (ja) プラント施設建設におけるモジュール工法およびモジュール工法用定盤
JP4502162B2 (ja) 給排水ポンプユニット
JP7430400B2 (ja) トランスファークレーンの嵩上げ工事方法、及び嵩上げ用ポスト
JP2001071912A (ja) ジャッキング装置を用いた運搬装置及び運搬装置の使用方法
JP2736735B2 (ja) 新燃料搬入検査作業方法
CN117246470A (zh) 一种mark-ⅲ型围护系统平台模块及拆除方法
CN211642261U (zh) 一种土木用木材搬运装置
KR200373696Y1 (ko) 크린룸 바닥 구조물 설치용 자재 운반장치
JP3152380B2 (ja) 外壁パネルの施工方法
JPH05113026A (ja) 仮設足場構造体
CN205973454U (zh) 吊具
JP3576399B2 (ja) ガスタービン用燃料制御弁の点検方法及び点検用装置

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18924884

Country of ref document: EP

Kind code of ref document: A1

REG Reference to national code

Ref country code: BR

Ref legal event code: B01A

Ref document number: 112020012798

Country of ref document: BR

ENP Entry into the national phase

Ref document number: 112020012798

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20200623

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18924884

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: JP