WO2005062145A1 - 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体 - Google Patents

生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体 Download PDF

Info

Publication number
WO2005062145A1
WO2005062145A1 PCT/JP2004/019405 JP2004019405W WO2005062145A1 WO 2005062145 A1 WO2005062145 A1 WO 2005062145A1 JP 2004019405 W JP2004019405 W JP 2004019405W WO 2005062145 A1 WO2005062145 A1 WO 2005062145A1
Authority
WO
WIPO (PCT)
Prior art keywords
logistics
production
distribution
simulator
period
Prior art date
Application number
PCT/JP2004/019405
Other languages
English (en)
French (fr)
Inventor
Yasuhito Yaji
Kenji Sugiyama
Tetsuaki Kurokawa
Masanori Shioya
Kuniharu Ito
Hirokazu Kobayashi
Original Assignee
Nippon Steel Corporation
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corporation filed Critical Nippon Steel Corporation
Priority to US10/584,423 priority Critical patent/US7676293B2/en
Priority to BRPI0418164-6A priority patent/BRPI0418164A/pt
Priority to JP2005516528A priority patent/JP4690893B2/ja
Priority to EP04807761.4A priority patent/EP1701232B1/en
Publication of WO2005062145A1 publication Critical patent/WO2005062145A1/ja
Priority to US12/655,847 priority patent/US7865260B2/en
Priority to US12/655,854 priority patent/US7860595B2/en

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32297Adaptive scheduling, feedback of actual proces progress to adapt schedule
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32301Simulate production, process stages, determine optimum scheduling rules
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Definitions

  • Production / distribution schedule creation device and method Production / distribution process control device and method, computer program, and computer-readable recording medium
  • the present invention relates to a production / distribution schedule creation device and method, a production / distribution process control device and method, a computer program, and a computer-readable recording medium, and particularly, without depending on the skill of an operator. This is suitable for the case where the schedule of the target system is created accurately.
  • the present invention enables an optimal production / distribution simulation result to be obtained without repeating simulation, and can be actually used in a production / distribution process for which a schedule is to be created.
  • the purpose is to be able to create production and logistics schedules at high speed and with high accuracy.
  • Patent Document 1 JP-A-2002-366219
  • Patent Document 2 JP 2000-172745 A
  • the production / distribution schedule creation apparatus is a production / distribution process that expresses the distribution status and distribution constraints of a distribution process / production.
  • a mathematical expression model that expresses constraints and mathematical expressions, and holds a mathematical expression model created by capturing information related to creating a logistics schedule of interest; and a mathematical expression model holding device.
  • An optimization calculation device that performs an optimization calculation process using a predetermined evaluation function to calculate a physical distribution instruction to the production / distribution simulator, and stores the physical distribution instruction obtained by the optimization calculation device in the production
  • the simulation is given to the logistics simulator, and when a new event occurs, the production and logistics simulator Output the instruction to perform the optimization calculation to the above-mentioned optimization calculation device, and link the above-mentioned production / logistics simulator and the above-mentioned optimization calculation device in the above-mentioned production / logistics process. It has a feature in that a production and distribution schedule is created.
  • Another production logistics schedule creation device is a production logistics process logistics Production that expresses the state and logistics constraintsProduction that simulates a logistics processLogistics simulator
  • a mathematical model holding device that holds a mathematical model using a state equation created by taking in information related to creating a mathematical equation, and performing an optimization calculation process on the mathematical model using a predetermined evaluation function.
  • Another production device according to the present invention is a production scheduler for logistics, which is a production process that expresses the distribution status and distribution constraints of a distribution process.Production that simulates a distribution process.
  • a mathematical model holding device that holds a mathematical model created by fetching relevant information, performs optimization calculation processing on the mathematical model using a predetermined evaluation function, and issues a logistics instruction to the production / logistics simulator.
  • the calculation is given to the production logistics simulator, the simulation is performed for a preset period (simulation period), and the logistics plan is determined for the preset period (plan determination period).
  • the production / logistics schedule described above is created from the simulation results obtained by repeating the process of setting up the date / time immediately after as the new planning start date / time and creating a logistics plan, based on the simulation results obtained. Having.
  • the production / distribution schedule creation method includes the following: production / production expressing the distribution status and distribution constraints of the distribution process / production simulating the distribution process / distribution simulator A mathematical model that expresses the logistics state and logistics constraints of the production and logistics processes using mathematical formulas, and holds a mathematical model created by capturing information related to creating a logistics schedule of interest.
  • the production / distribution schedule creation apparatus includes an apparatus and an optimization calculation apparatus for performing an optimization calculation process on the mathematical expression model using a predetermined evaluation function to calculate a flow instruction for the production / distribution simulator. This is a method for creating a logistics schedule, which provides the logistics instructions obtained by the above-mentioned optimization computer to the production / logistics simulator to execute the simulation. ⁇ An instruction to perform optimization calculation from the logistics simulator to the optimization computer is output. Then, the production / distribution simulator is linked to the optimization calculation device to create a production / distribution schedule in the production / distribution process.
  • Another production method is a method for creating a logistics schedule, which includes production, a logistics process expressing logistics status and logistics constraints, a production simulating a logistics process, a logistics simulator, and the above-described production, a logistics status of a logistics process and logistics constraints.
  • a mathematical model model that holds a mathematical model using a state equation created by taking in information related to creating a logistics schedule of interest,
  • a production and distribution system that has an optimization calculation device that performs optimization calculation processing on the expression model using a predetermined evaluation function and calculates a distribution instruction to the production-logistics simulator.
  • a feedback gain is calculated by the above-described optimization calculation process, and the feedback gain is calculated.
  • a logistics instruction is calculated using the gain and the logistics state, and given to the above-mentioned production / logistics simulator to proceed with the simulation, obtain a new logistics state, and provide a new logistics instruction based on the new logistics state. It is characterized in that the simulation and the logistics schedule obtained by repeating the process of calculating the production and logistics schedule are created.
  • Another production method is a method for creating a logistics schedule, which includes production, a logistics process expressing logistics status and logistics constraints, a production simulating a logistics process, a logistics simulator, and the above-described production, a logistics status of a logistics process and logistics constraints.
  • an optimization calculation device that performs an optimization calculation process on the mathematical expression model using a predetermined evaluation function to calculate a distribution instruction to the production / distribution simulator.
  • the simulation is executed for the preset period (simulation period) and the preset period (plan confirmation period) From the simulation results obtained by repeating the process of determining the logistics plan, setting the date and time immediately after the determined period as a new planning start date and drafting the logistics plan, the above-mentioned production ⁇ Characterized by creating a logistics schedule.
  • the computer program of the present invention is a production program that expresses the logistics state and logistics constraints of the production logistics process.Production that simulates the logistics process.
  • a mathematical expression model holding device that holds the mathematical expression model, which is an expressed mathematical expression model, the information being related to creating a distribution schedule of interest, and a predetermined evaluation function for the mathematical expression model.
  • the computer implements the function of an optimization calculator that calculates the logistics instruction to the above-mentioned production and logistics simulator by performing optimization calculation processing using the above-mentioned production and distribution simulator. To run the simulation, and when a new event occurs, The emulator outputs an instruction for performing the optimization calculation to the optimization calculation device, and the production 'logistics simulator and the optimization calculation device are linked to each other to perform the optimization in the production' flow process.
  • Another computer program according to the present invention is a production that expresses the logistics state and logistics constraints of the production logistics processProduction simulating the logistics processLogistics simulator and the above-mentioned production
  • a mathematical model that expresses A mathematical model holding device that holds a mathematical model using a state equation created by taking in information related to creating a logistics schedule, and an optimal model using a predetermined evaluation function for the mathematical model
  • a computer performs the optimization calculation process to calculate the distribution instruction to the production and logistics simulator, and calculates the feedback gain by the optimization calculation process.
  • the logistics instruction is calculated using the status and given to the above-mentioned production and logistics simulator, the simulation is advanced, a new physical distribution state is obtained, and a new physical distribution instruction is calculated based on the new physical distribution state. From the simulation results obtained by repeating the processing, the above-mentioned production It has a feature in that so as to create a Le.
  • Another computer program according to the present invention is a production that expresses the logistics state and logistics constraints of the production logistics processProduction simulating the logistics processLogistics simulator and the above-mentioned production
  • This is a mathematical model model that captures information related to creating a logistics schedule of interest for a preset period (planning period) of the production and logistics process.
  • a mathematical model holding device that holds the created mathematical model, and an optimization calculating device that performs an optimization calculation process on the mathematical model using a predetermined evaluation function and calculates a logistics instruction to the production / logistics simulator.
  • the logistics instruction is calculated and given to the above-mentioned production and logistics simulator, the simulation is executed for the preset period (simulation period), and the logistics plan is determined for the preset period (planning confirmation period). From the simulation results obtained by repeating the process of setting the date and time immediately after the determined period as the new planning start date and time and drafting the logistics plan, the above-mentioned production It has a feature in that it is realized.
  • the production / distribution process control device is a production / production system that expresses the distribution status and distribution constraints of the distribution process / production simulating the distribution process / distribution simulator and the above-mentioned production •
  • the distribution status and distribution constraints of the distribution process Is a mathematical model that expresses
  • a mathematical model holding device that holds a mathematical model using a state equation created by capturing information related to creating a logistics schedule and a predetermined evaluation function for the mathematical model are used.
  • An optimization calculation device that calculates a distribution instruction to the production / distribution simulator by performing optimization calculation processing, calculates a feedback gain by the optimization calculation processing, and compares the feedback gain and the distribution state. Calculate the logistics instruction using this and give it to the above production logistics simulator to proceed with the simulation.
  • Control of the logistics process based on simulation results obtained by repeating the process of obtaining a new physical distribution state and calculating a new physical distribution instruction based on this new physical distribution state. It has features.
  • Another production process is a production process that expresses the distribution status and distribution constraints of the distribution process.Production that simulates the distribution process.The distribution simulator and the above production.The distribution status and the distribution constraints of the distribution process.
  • This is a mathematical model that expresses the above formulas, and the information related to creating a logistics schedule of interest for a predetermined period (planning period) for the production start logistics process.
  • a formula model holding device that holds the formula model created by taking in the data, and performs an optimization calculation process on the formula model using a predetermined evaluation function to calculate a distribution instruction to the production / logistics simulator.
  • a logistics instruction is calculated for a preset period (instruction calculation period) from the current time by the above-mentioned optimization calculation process.
  • the production and distribution process control method is a production process that expresses the distribution status and distribution constraints of the distribution process.
  • Production that simulates the distribution process.
  • the distribution simulator and the above-mentioned production. Is a mathematical model that expresses a mathematical formula, and was created by taking in information related to creating a logistics schedule.
  • a mathematical model holding device that holds a mathematical model using a state equation, and an optimal model that performs an optimization calculation process on the mathematical model using a predetermined evaluation function to calculate a logistics instruction to the production / logistics simulator.
  • the simulation is obtained by repeating the process of calculating and giving it to the above-mentioned production logistics simulator, performing the simulation, obtaining a new physical distribution state, and calculating a new physical distribution instruction based on this new physical distribution state.
  • the feature is that the production and logistics processes are controlled based on the results.
  • Another production control method is a production method that expresses the logistics state and logistics constraints of the production process.Production that simulates the logistics process. This is a mathematical model that expresses the above formulas, and the information related to creating a logistics schedule of interest for a predetermined period (planning period) for the production start logistics process. And a formula model holding device that holds the formula model created by taking in the data, and performs an optimization calculation process on the formula model using a predetermined evaluation function to calculate a distribution instruction to the production / logistics simulator.
  • a production and logistics process control method using a production and logistics process control device having an optimization calculation device From the present time, a logistics instruction is calculated for a preset period (instruction calculation period) from the present time and given to the production / distribution simulator, and a simulation is executed for the preset period (simulation period) for the preset period. Based on the simulation results obtained by repeating the process of determining the logistics plan for the period (plan determination period), setting the date and time immediately after the determined period as a new planning start date, and drafting the logistics plan It is characterized in that it controls the logistics of production and logistics processes.
  • the computer program according to the present invention expresses the logistics state of the production logistics process and the production logistics process.
  • a state model that is a mathematical model created by taking in information related to creating a logistics schedule of interest.
  • a formula model holding device that holds a formula model using a formula, and an optimization calculation that performs an optimization calculation process on the above formula model using a predetermined evaluation function to calculate a logistics instruction to the production / logistics simulator.
  • the function of the device is realized by a computer, a feedback gain is calculated by the above-mentioned optimization calculation process, a logistics instruction is calculated using the feedback gain and the logistics state, and given to the production / logistics simulator, thereby performing a simulation. Control of production and logistics processes based on simulation results obtained by repeating the process of obtaining a new logistics state and calculating a new logistics instruction based on this new logistics state.
  • the feature is that it is performed.
  • Another computer program according to the present invention is a production that expresses the logistics state and logistics constraints of the production logistics processProduction simulating the logistics processLogistics simulator and the above-mentioned production
  • This is a mathematical model model that captures information related to creating a logistics schedule of interest for a preset period (planning period) of the production and logistics process.
  • a mathematical model holding device that holds the created mathematical model, and an optimization calculating device that performs an optimization calculation process on the mathematical model using a predetermined evaluation function and calculates a logistics instruction to the production / logistics simulator.
  • the logistics instruction is calculated and given to the above-mentioned production and logistics simulator, the simulation is executed for the preset period (simulation period), and the logistics plan is determined for the preset period (planning confirmation period).
  • Production and logistics control based on the simulation results obtained by repeating the process of setting the date and time immediately after the determined period as a new planning start date and time and formulating a logistics plan. It has the characteristic that
  • a computer-readable recording medium is characterized in that the computer program according to the present invention is recorded.
  • FIG. 1 is a block diagram showing a first embodiment of the present invention and illustrating a schematic configuration of a production / distribution schedule creating apparatus.
  • FIG. 2 is a block diagram showing a second embodiment of the present invention and illustrating a schematic configuration of a production / distribution schedule creating apparatus.
  • FIG. 3 is a flowchart showing a processing procedure for creating a production / distribution schedule in the second embodiment.
  • FIG. 4 is a flowchart showing a processing procedure of model construction.
  • FIG. 5 is a flowchart showing a processing procedure of control rule construction.
  • FIG. 6 is a flowchart showing a simulation processing procedure.
  • FIG. 7 is a block diagram showing a third embodiment of the present invention and illustrating a schematic configuration of a production / distribution schedule creating apparatus.
  • FIG. 8 is a diagram showing a specific example to which the present invention is applied and explaining a production / distribution plan creation procedure.
  • FIG. 9 is a flowchart showing a processing procedure for creating a production / distribution schedule according to the fourth embodiment.
  • FIG. 10 is a flowchart showing a procedure of model construction.
  • FIG. 11 is a flowchart showing a processing procedure of control rule construction.
  • FIG. 12 is a flowchart showing a simulation processing procedure.
  • FIG. 13 is a diagram showing an example of a Petri net model.
  • FIG. 14 is a flowchart showing a processing procedure for creating a production / distribution schedule according to the fifth embodiment.
  • FIG. 15 is a flowchart showing a procedure of model construction.
  • FIG. 16 is a flowchart showing a control procedure construction processing procedure.
  • FIG. 17 is a flowchart showing a simulation procedure.
  • FIG. 18 is a flowchart showing a processing procedure for creating a production / distribution schedule according to the sixth embodiment.
  • FIG. 19 is a flowchart showing a procedure of model construction.
  • FIG. 20 is a flowchart showing a processing procedure of control rule construction.
  • FIG. 21 is a flowchart showing a simulation processing procedure.
  • FIG. 22 is a diagram showing an example of a Petri net model.
  • FIG. 23 is a diagram showing an example of a Petri net model.
  • FIG. 24 is a diagram showing an example of a Petri net model for product type No. 1.
  • FIG. 25 is a block diagram showing an eighth embodiment and illustrating a main part configuration of a production / distribution schedule creating apparatus in a manufacturing process.
  • FIG. 26 is a diagram for explaining an operation performed by the production / distribution schedule creation device (the production / distribution schedule creation method according to the present embodiment).
  • FIG. 27 is a diagram showing the position of a production / distribution schedule creation device in a weekly daily planning system.
  • FIG. 28 is a diagram for explaining a formula of a distribution model.
  • FIG. 29 is a block diagram showing an example of a combi- ter system that can constitute the production / distribution schedule creation device of the present invention.
  • FIG. 1 is a block diagram illustrating a first embodiment of the present invention and illustrating an example of a physical distribution schedule creating device.
  • the distribution schedule creation device of the present embodiment includes a distribution simulator 100, an optimization calculation device 120, and the like.
  • the distribution simulator 100 is a large-scale simulator simulating a factory, and is configured as a discrete system that moves an object for each event (simulator event).
  • the physical distribution simulator 100 is configured using a Petri net, and configured to output the mathematical model 110.
  • a distribution model (formula model) 110 is configured to correspond to the distribution simulator 100 described above.
  • the mathematical expression model 110 is created by taking in the elements related to the created distribution schedule from the distribution state and the distribution restrictions of the production / distribution process.
  • all of the physical distribution conditions and physical restrictions described in the physical distribution simulator 100 may be included, or only some of them may be included. Is also good.
  • the mathematical expression model 110 is a mathematical expression model holding means constituted by a semiconductor storage means and the like.
  • the distribution calculation instruction is performed by the above-described optimization calculation device 120 instead of being performed based on a predetermined rule as in the related art.
  • a distribution instruction based on the result of the optimal calculation can be output to the distribution simulator 100. As a result, it is possible to reliably issue an optimal distribution instruction according to the event at that time.
  • the time management unit 101 advances the event by one, and outputs a calculation instruction from the distribution simulator 100 to the mathematical model 110 and the optimization calculation device 120 to perform the calculation. Is done.
  • the optimization calculation device 120 executes the optimization calculation using the mathematical expression model 110 and the evaluation function S. As described above, an optimal production / distribution schedule can be created by once executing the detailed simulation in which the distribution simulator 100 and the optimization calculation device 120 are linked for each event.
  • a simulation is performed based on a result of performing an optimal calculation, which is different from a simulation based on a predetermined rule as in the related art. It is possible to reliably obtain the theoretical optimal solution by performing only one simulation, and to quickly and quickly evaluate the simulation results and eliminate the need to repeat the simulation many times. It can be created with high accuracy. Therefore, even if the schedule is created on a large scale, it can be created within practical hours.
  • the simulation result obtained as described above is output as a schedule.
  • the size of the logistics simulator 100 is set to an appropriate range, and optimization calculations can be performed within practical time. Can be done.
  • the physical distribution simulator 100 can describe all physical distribution conditions and physical distribution restrictions to be considered, it is guaranteed that a schedule created by performing a single simulation can be actually executed.
  • the physical distribution simulator 100, the mathematical expression model 110, and the optimization calculation device 120 are linked to create a physical distribution schedule. You can create a schedule without doing.
  • the logistics simulator 100 detects the physical distribution state and the physical distribution restriction information, and performs the optimization based on the detected information and the predetermined evaluation index. Since the optimal logistics instruction is calculated by the optimization method by the computer 120 and the detailed simulation is performed by the logistics simulator 100 based on the above calculation result, the schedule is created. (5) It is possible to create a schedule whose feasibility has been verified.
  • FIG. 2 is a block diagram illustrating a second embodiment of the present invention and illustrating an example of a physical distribution schedule creating device.
  • the distribution schedule creation device of the present embodiment includes a simulation control unit 200 including a distribution simulator 201, an optimization calculation device 212, and the like.
  • the logistics simulator 201 is a production and production that expresses the physical distribution state and physical distribution constraints of the physical distribution process.
  • the system is configured as a discrete system that moves an object for each event (simulator event) using a Petri net.
  • a mathematical model (formula model) 211 is configured to correspond to the physical distribution simulator 201.
  • the factors related to the logistics schedule to be created are fetched from the logistics status and the logistics constraints of the production / logistics process, and the above equation is obtained by using a state equation as shown in the following equation (a).
  • Model 211 has been created.
  • the mathematical expression model 211 is held by mathematical expression model holding means (not shown) constituted by semiconductor storage means and the like.
  • a state vector indicating the number of tokens present in each place at a certain discrete time k that is, the state quantity is represented by M (k), and the presence or absence of each transition firing is represented by “1" ”and“ 0 ⁇ ”.
  • the state vector M (k + 1) at the next time k + 1 can be expressed by the above equation (i) using the transition matrix a and the connection matrix b. it can.
  • the optimization calculation device 212 performs an optimization calculation process on the mathematical model 211 and calculates a feedback gain K.
  • the optimization calculation performed by the optimization calculation device 212 is performed using an evaluation function S as shown in the following equation (mouth).
  • Q and R are appropriate matrices set according to the control purpose, and ⁇ ′ and u ′ are transposition vectors of the state vector ⁇ and the operation vector u, respectively. Then, considering that the evaluation function S is controlled to be minimum,
  • the feedback gain K for performing the state feedback control can be obtained from the optimal control theory.
  • the optimal control policy unit 202 of the simulation control unit 200 calculates a distribution instruction (operation vector u) using the feedback gain ⁇ calculated by the optimization calculation unit 212 and the distribution state (state vector ⁇ ).
  • the process is given to the physical distribution simulator 201, the simulation is advanced, a new physical distribution state is obtained, and a process of calculating a new physical distribution instruction based on the new physical distribution state is repeated. Then, from the simulation result 220 obtained, Create a distribution schedule for the distribution process.
  • a Petri net model of the production and logistics processes As shown in Fig. 3, first, as a Petri net model of the production and logistics processes, a Petri net model that represents each process with a place where the processing time is input is constructed for each product type. Then, a transition matrix a and a connection matrix b are calculated according to a step time delay np proportional to the processing time Tp of each place of the constructed Petri net model, and the state equation is calculated using these two matrices a and b. Is created (step S31).
  • a feedback gain matrix K is obtained for each product type from the state equation created in step S31 and the set evaluation functions Q and R (step S32).
  • step S33 After calculating the operation level u (k) for the moving operation end of the product for each product type, a large positive operation amount is calculated for each moving operation end in the virtual production / distribution process.
  • a simulation of the production / distribution process for a predetermined period is executed by using a method of sequentially performing a moving operation as many times as possible in the order of the products obtained (step S33).
  • FIG. 4 shows a process of step S31 shown in FIG. 3, that is, as a Petri net model of a production / distribution process, a Petri net model representing each process in a place where a processing time is input is constructed for each product type.
  • 12 is a flowchart illustrating an example of a processing procedure for calculating a transition matrix a and a connection matrix b representing a step time delay in each step for each product type.
  • step S101 the discrete step time ⁇ is input (step S101), and then all the processing steps and the processing time Tp are input for each product type (step S102). Then, for each processing step, the processing time Tp is divided by the step time ⁇ to obtain an integer by dividing the processing time Tp by the step time ⁇ (steps S103 and S104), and according to the step time delay np, A transition matrix a and a connection matrix b are calculated for each product type in all processing steps (step S105).
  • step S106 returns from step S106 to step S102 until transition matrices a and connection matrices b are calculated for all products, and the above processes are repeated. Note that it is most effective to define the discrete step time ⁇ with the greatest common divisor of each product type and each process processing time. Although it is efficient, it may be set appropriately in consideration of the target control accuracy.
  • FIG. 5 shows a process of step S32 shown in FIG. 3, that is, a feedback gain matrix based on the state equation including the transition matrix a and the connection matrix b obtained as described above and the set evaluation functions Q and R. 9 is a flowchart illustrating an example of a processing procedure for obtaining K for each product type.
  • a transition matrix a and a connection matrix b expressing a step time delay np proportional to the processing time T p of each place of the Petri net model for each product type and the connection matrix b are first sent to the optimization calculation device 212.
  • matrices Q and R representing the evaluation function are input (step S202).
  • the input transition matrix a, connection matrix b, and evaluation matrices Q and R also calculate the feedback gain matrix K (step S203).
  • the process returns from step S204 to step S201 until this calculation is completed for all products, and the above process is repeated.
  • the transition matrix a and the connection matrix b representing the step time delay np proportional to the processing time Tp of each place of the Petri net model are input to the gain matrix calculation means 34, and all products are calculated at once. You may make it.
  • FIG. 6 shows the process of step S33 shown in FIG. 3, that is, the product of the product based on the feedback gain matrix K calculated as described above and the state vector M (K) representing the in-process product in-process state.
  • a product with a positive and large operation amount obtained for each moving operation end in the virtual production / distribution process 5 is a flowchart illustrating an example of a processing procedure for executing a simulation of a production / distribution process for a predetermined period by using a method of sequentially performing a moving operation by a number that can be sequentially moved.
  • an operation vector u (k) is calculated for each product type by multiplying the feedback gain matrix K calculated using the above-described method and the input state vector M (k) (step S303). Then, for each moving operation end, it is possible to move in the order of the products in which the positive and large operation amounts were obtained.
  • the moving operation is executed by the number (step S304).
  • step S 306 it is determined whether or not the simulation of each step has been completed. If the simulation has not been completed, the process returns to step S 302. On the other hand, when the process is completed, the production schedule is set using the order of the tokens conveyed from the input place as a result (step S307).
  • the optimal control is performed based on the instruction obtained as a result of performing the optimization calculation and the state of the event, the optimal control is performed for each event.
  • a schedule can be created based on the simulation result of the optimization calculation, and the schedule is a simulation result by a simulator expressing the constraints of the production and logistics processes. You can check it.
  • the schedule generation of the physical distribution state and the mathematical formula described in the physical distribution simulator 201 is not required.
  • the size of the logistics simulator 201 is set to an appropriate range, and the optimization calculation is performed within a practical time. be able to.
  • the physical distribution simulator 201 can describe all physical distribution conditions and physical distribution restrictions to be considered, it is assured that a schedule created by performing a single simulation can be actually executed.
  • the physical distribution simulator 201, the mathematical expression model 211, and the optimization calculating device 212 are linked to create a physical distribution schedule. You can create a schedule without doing. In addition, (2) the calculation time can be shortened by incorporating only important parts into the above-mentioned mathematical model 211, which has a large influence on the schedule creation, and (3) a large-scale problem can be solved. Meeting.
  • the calculation unit 212 calculates the optimal logistics instruction for the optimization method, and A detailed simulation is performed by the above-mentioned logistics simulator 201 based on the calculation result to create a schedule. Therefore, (4) schedule accuracy can be increased, and (5) a schedule that has been verified for feasibility is created. can do.
  • the processing in the simulation control unit 200 is online, the construction of a mathematical model (formula model) 211 corresponding to the logistics simulator 201 and the optimization calculation process for the above mathematical model 211 in the optimization calculator 212. It is also possible to divide the processing so that the processing is performed offline, so that the processing load on the simulation control unit 200 can be reduced and the processing capacity can be increased.
  • FIG. 7 is a block diagram illustrating a third embodiment of the distribution schedule creation device of the present invention.
  • the distribution schedule creation device 300 of the present embodiment includes a distribution simulator 310, a mathematical model holding device 320, an optimization calculation device 330, and the like.
  • the physical distribution simulator 310 is a large-scale simulator simulating a factory, and is configured as a discrete system that moves an object for each event (simulator event). In the present embodiment, the distribution simulator 310 is configured using a Petri net.
  • a distribution model (formula model) 321 is configured to correspond to the distribution simulator 310, and is stored in the mathematical model holding device 320.
  • the formula model 321 is created by taking in elements related to the created distribution schedule from the distribution status and the distribution constraints of the production / distribution process.
  • a mathematical model 321 is constructed for the relations and constraints of the work groups involved in the processing of products, moving bodies, and facilities.
  • the mathematical expression model 321 constructed as described above is held by the mathematical expression model holding device 320 constituted by semiconductor storage means and the like.
  • the optimization calculation is performed by the mathematical expression model 321 and the optimization calculation device 330.
  • the optimization calculation process is performed on the mathematical expression model 321 by using the evaluation function S, and A distribution instruction to the distribution simulator 310 is calculated.
  • the above formula model 321 is used to create a logistics schedule by focusing on a preset period (planning period) from the planning start time of the production / distribution process.
  • the relevant information is created and created, and the created mathematical model 321 is given to the optimization calculating device 330 to calculate the distribution instruction for the preset period (instruction calculation period) from the present time by the optimization calculation process.
  • the simulation is given to the above-mentioned production / distribution simulator, and the simulation is executed for a preset period (simulation period), and the distribution plan is fixed for the preset period (plan determination period).
  • this example is an example in which the simulation period and the confirmation period are the same period.
  • the optimization calculation device 330 calculates a solution for the target period from 0: 1 to 24:00 on the first day based on the mathematical model 321. Then, a simulation is performed by the distribution simulator 310 based on the solution results obtained by the optimization calculation processing, and the period A of the first distribution plan is determined for the first 8 hours.
  • the date and time immediately after the determined period are set as the new planning start date and time. And set up a logistics plan.
  • the planning start date which was initially 0:00 on the first day, was changed to the first day in the second loop. Update at 8 o'clock.
  • the optimization computer 330 based on the mathematical model 321 sets a target period of 24 hours from 8:00 on the first day to 8:00 on the second day. Perform a solution. Then, a simulation is performed by the logistics simulator 310 based on the solution results obtained by the optimization calculation processing, and for the first 8 hours, in this case, 8:16 on the first day, the second logistics plan The period B of is determined.
  • a date and time immediately after the determined second physical distribution plan period B is set as a new planning start date and time, and a physical distribution plan is drafted.
  • the planning start date which was 8:00 on the first day in the second loop, was updated at 16:00 on the first day in the third loop.
  • a solution is performed by the above-described optimization calculation device 330 based on the mathematical expression model 321 with a target period of 24 hours.
  • the distribution simulator 310 based on the solution results obtained by the optimization calculation process, and the distribution plan is determined for the first 8 hours.
  • the period from 16:00 to 24:00 on the first day is determined as period C of the third logistics plan.
  • it will be 0:00 on the planning start day.
  • the target period for which the optimization calculation device 330 performs a solution based on the mathematical expression model 321 is set to 48 hours from 0:00 on the second day to 0:00 on the fourth day.
  • the results of the solution performed for the above 48 hours are simulated by the logistics simulator 310, and in this fourth loop, the logistics plan is determined for the first 24 hours! In this case, the period from midnight on the second day to midnight on the second day (0:00 on the third day) is determined as period D of the fourth logistics plan.
  • a solution is performed by the mathematical model 321 with a 24-hour period from 0:00 on the fourth day to 24:00 on the fourth day as a target period.
  • 24 hours which is the entire target period, is decided as period F of the sixth logistics plan.
  • the production and distribution plans for four days are all created, and the processing is terminated.
  • the determination of the distribution plan may be performed every time an event requiring a distribution instruction occurs.
  • the calculation range is divided while moving the initial value, so that it is practically used even when calculating a schedule with a large calculation load. It is possible to calculate in time. Therefore, even when creating a production / distribution schedule of a large-scale factory having a large number of calculation elements, a schedule can be created in practical time.
  • the division processing is performed in conjunction with the optimization calculation device 330 and the distribution simulator 310, even if there is a slight deviation in each event, fine adjustment is made for each event. It will be possible to create an optimal schedule within practical time.
  • the above-mentioned logistics simulator 310 can describe all the logistics conditions and distribution restrictions to be considered, so it is guaranteed that the created schedule created by performing one simulation will be actually executable. Is done.
  • the physical distribution simulator 310, the mathematical expression model 321 and the optimization calculation device 330 are linked to create a physical distribution schedule. You can create a schedule without doing. Also, (2) import only important parts that have a large effect on schedule creation into the mathematical model 321. By doing so, the calculation time can be reduced, and (3) large-scale problems can be solved.
  • the physical distribution condition and physical restriction information of the physical distribution simulator 310 are detected, and the optimization is performed based on the detected information and a predetermined evaluation index.
  • the optimal logistics instruction is calculated by the optimization method by the computing device 330, and a detailed simulation is performed by the logistics simulator 310 based on the calculation result to create a schedule.
  • the schedule accuracy can be increased. (5) It is possible to create a schedule whose feasibility has been verified.
  • the fourth embodiment-the sixth embodiment described below is related to the above-described second embodiment.
  • the distribution schedule creation device of the present embodiment also includes a simulation control unit 200 having a distribution simulator 201, an optimization calculation device 212, and the like.
  • the logistics simulator 201 is a large-scale simulator that simulates the production and logistics processes expressing the logistics state and logistics constraints of the production and logistics processes.
  • a simulator is constructed using a graph model, and is configured as a discrete system that moves an object for each event (simulator event).
  • a mathematical model (formula model) 211 is configured to correspond to the physical distribution simulator 201.
  • the factors related to the logistics schedule to be created are taken in from the physical distribution status and physical distribution constraints of the production / logistics process, and the above equation is obtained by using the state equation as shown in the following equation (2).
  • Model 211 has been created.
  • the mathematical expression model 211 is held by mathematical expression model holding means (not shown) constituted by semiconductor storage means and the like.
  • M (k + 1) M (k) + b -u (k)... (2)
  • a state vector indicating the number of elements present at each point at a certain discrete time k in other words, the state quantity is represented by M (k), and the presence or absence of firing of each line is represented by ⁇ 1 ”and“ 0 ”. If the expressed operation vector is represented by u (k), the state vector M (k + 1) at the next time k + 1 can be represented by the above equation (2) using the connection matrix b.
  • the optimization calculation device 212 performs an optimization calculation process on the mathematical expression model 211 and calculates a feedback gain K.
  • the optimization calculation performed by the optimization calculation device 2 utilizes linear quadratic (LQ) control, and is performed using an evaluation function S as shown in the following equation (mouth).
  • Q and R are appropriate matrices set according to the control purpose, and ⁇ ′ and u ′ are transposition vectors of the state vector ⁇ and the operation vector u, respectively. Then, considering that the evaluation function S is controlled to be minimum,
  • the optimal control policy unit 202 of the simulation control unit 200 calculates a distribution instruction (operation vector u) using the feedback gain ⁇ calculated by the optimization calculation unit 212 and the distribution state (state vector ⁇ ). The process is given to the physical distribution simulator 201, the simulation is advanced, a new physical distribution state is obtained, and a process of calculating a new physical distribution instruction based on the new physical distribution state is repeated. Then, a logistics schedule in the production logistics process is created from the simulation result 220 obtained thereby.
  • a graph model representing each process in terms of a number proportional to the processing time ⁇ is constructed for each product type as a graph model of the production and logistics processes (step S91). .
  • step S92 the state equation of the constructed graph model and the set evaluation functions Q and R and the feedback gain matrix ⁇ are obtained for each product type (step S92).
  • step S93 After calculating the operation level u (k) for the moving operation end of the product for each product type, a large positive operation amount is calculated for each moving operation end in the virtual production / distribution process.
  • a simulation of the production / distribution process for a predetermined period is executed by using a method of sequentially performing a moving operation as many times as possible in the order of the products obtained (step S93).
  • FIG. 10 shows, as a graph model of the process of step S 91 shown in FIG. 9, ie, a production / distribution process, a graph model representing each process in terms of the number of processing times in proportion to each product type. It is a flowchart which shows the example of the processing procedure for construction.
  • step S 1001 a discrete step time ⁇ is input (step S 1001), and then all processing steps and processing time Tp are input for each product type (step S 1002). Then, for each processing step, the number of points ⁇ in each of the above processing steps is obtained by dividing the processing time ⁇ by the step time ⁇ and performing integer filtering (steps S 1003 and S 1004).
  • a graph model is constructed for each product type by connecting the lines (step S1005).
  • step S 1006 the process returns from step S 1006 to step S 1002 until a graph model is constructed for all products, and the above processes are repeated. It is most efficient to define the discrete step time ⁇ with the greatest common divisor of each product type and each process time, but it may be appropriately set in consideration of the desired control accuracy.
  • FIG. 11 shows the process of step S92 shown in FIG. 9, that is, the process procedure for obtaining the feedback gain matrix ⁇ for each product type from the state equation of the constructed graph model and the set evaluation function. It is a flowchart which shows an example. In addition, create a connection matrix b of the graph model for all products, input it to the optimization calculator 2, and calculate all products at once.
  • connection matrix b describing the state equation of the graph model for each product type is input to the optimization calculation device 2 (step S1101), and the matrices Q and R representing the evaluation function are input (step S1101). S 1102). Then, a feedback gain matrix K is calculated from the input connection matrix b and the evaluation matrices Q and R (step S1103). The process returns from step S1104 to step S1101 until this calculation is completed for all products, and the above processing is repeated.
  • FIG. 12 shows the process of step S93 shown in FIG. 9, that is, the process is performed from the feedback gain matrix K calculated as described above and the state vector M (K) representing the in-process product in-process state.
  • FIG. 5 is a flowchart showing an example of a processing procedure for executing a simulation of a production / distribution process for a predetermined period by using a method of sequentially performing a moving operation as many times as possible in a product order.
  • step S1201 state vectors M (k) of all product types at the current time (time: k) are input (step S1202).
  • the operation vector u (k) is calculated for each product type by multiplying the feedback gain matrix K calculated using the above-described method and the input state vector M (k) (step S1233). Then, for each moving operation end, the moving operation is executed by the movable number in the order of the product having the larger positive operation amount (step S1204).
  • step S1205 After advancing the time (step S1205), it is determined whether or not the simulation of each step has been completed (step S1206). If not, the process returns to step S1202. On the other hand, when the process is completed, the simulation result is used as a production schedule (step S1207).
  • a schedule can be created based on the simulation result of executing the optimization calculation.Since the schedule is a simulation result by a simulator that expresses the constraints of the production and logistics processes, it must be actually usable. Can be confirmed.
  • the physical distribution simulator 201 can describe all physical distribution states and physical distribution restrictions to be considered, so that it is guaranteed that a schedule created by performing a single simulation can be actually executed.
  • the physical distribution simulator 201, the mathematical expression model 211, and the optimization calculating device 212 are linked to create a physical distribution schedule. You can create a schedule without doing. In addition, (2) the calculation time can be shortened by incorporating only important parts into the above-mentioned mathematical model 211, which has a large influence on the schedule creation, and (3) a large-scale problem can be solved. Meeting.
  • the logistics simulator 201 detects the physical distribution state and the physical distribution restriction information, and performs the optimization based on the detected information and the predetermined evaluation index. Since the optimal logistics instruction is calculated by the computer 212 for the optimization method and the detailed simulation is performed by the logistics simulator 201 based on the calculation result to create a schedule, (4) schedule accuracy can be improved and (5) A schedule whose feasibility has been verified can be created.
  • the processing in the simulation control unit 200 is online, the construction of a mathematical model (formula model) 211 corresponding to the logistics simulator 201, and the optimization calculation process for the above mathematical model 211 in the optimization calculator 212. It is also possible to divide the processing so that the processing is performed offline, so that the processing load on the simulation control unit 200 can be reduced and the processing capacity can be increased.
  • the processing capacity in each process is controlled by software.
  • the virtual token for capacity setting initially set in the virtual place provided in each process is set. The number limits the number of products that can be processed simultaneously in each processing step.
  • the logistics schedule creation device of this embodiment also has a logistics simulator.
  • It comprises a simulation control unit 200 provided with 201, an optimization calculation device 212, and the like.
  • the logistics simulator 201 is a large-scale simulator that simulates a production-logistics process and a logistics process that expresses the logistics state and logistics constraints of a production / logistics process.
  • a simulator is constructed using a Petri net model, and is configured as a discrete system that moves an object for each event (simulator event).
  • a mathematical model (numerical model) 211 is configured to correspond to the physical distribution simulator 201 described above.
  • the factors related to the logistics schedule to be created are taken from the physical distribution status and physical restrictions of the production / logistics process, and are expressed by the following equation (2).
  • the mathematical model 211 is created using such a state equation.
  • the mathematical expression model 211 is held by mathematical expression model holding means (not shown) constituted by semiconductor storage means and the like.
  • a state vector indicating the presence / absence of a token at each place at a discrete time k in other words, the state quantity is represented by M (k), and the presence / absence of each transition firing is represented by “1” and “0”. If the obtained operation vector is represented by u (k), the state vector M (k + 1) at the next time k + 1 can be represented by the above equation (2) using the connection matrix b.
  • FIG. 13 shows an example of a Petri net model.
  • the Petri net model is represented by four elements: place ( ⁇ mark) (pi-p6 in the example), transition (I mark) (tl-t5 in the example), arc ( ⁇ mark), and token ('mark). Is done. In this case, if a plurality of place forces are input to one transition, arcs are input, and if all the places have products, that is, tokens, the operation of the transition cannot be performed. (Transition Ignition Shell IJ). If arcs are output in multiple places for one transition force, tokens are output in all of those places. The arc indicates the direction in which tokens move from transition to place, or from place to transition, and the number indicates the number of tokens moving. Operating the transition is called firing the transition.
  • a state vector indicating the presence or absence of the token tl-t5 at each place pi-p6 in other words, the state quantity is represented by M (k), and the presence or absence of each transition firing is represented by ⁇ 1 "and" If the operation vector expressed by 0 ⁇ is expressed by u (k), the state vector M (k + 1) at the next time k + 1 can be expressed by the following equation (1) using the connection matrix b. .
  • the optimization calculation device 212 performs an optimization calculation process on the mathematical expression model 211, and calculates the feedback gain K.
  • the optimization calculation performed by the optimization calculation device 212 uses linear quadratic (LQ) control, and is performed using an evaluation function S as shown in the following equation (mouth).
  • Q and R are appropriate matrices set according to the control purpose, and ⁇ ′ and u ′ are transposition vectors of the state vector ⁇ and the operation vector u, respectively. Then, considering that the evaluation function S is controlled to be minimum,
  • the feedback gain K for performing the state feedback control described above can be obtained from the optimal control theory.
  • the optimal control policy unit 202 of the simulation control unit 200 calculates a distribution instruction (operation vector u) using the feedback gain ⁇ calculated by the optimization calculation unit 212 and the distribution state (state vector ⁇ ). The process is given to the physical distribution simulator 201, the simulation is advanced, a new physical distribution state is obtained, and a process of calculating a new physical distribution instruction based on the new physical distribution state is repeated. Then, a logistics schedule in the production logistics process is created from the simulation result 220 obtained thereby.
  • a Petri net model of the production and logistics process a Petri net model that represents each step with places proportional to the processing time ⁇ is constructed for each product type (step S1401). ).
  • a feedback gain matrix K is obtained for each product type from the state equation of the constructed Petri net model and the set evaluation function (step S1402).
  • step S1403 After calculating the operation level u (k) for the moving operation end of the product for each product type, a large positive operation amount is calculated for each moving operation end in the virtual production / distribution process.
  • the simulation of the production / distribution process for a predetermined period is executed using a method of sequentially performing the moving operation as many times as possible in the order of the products obtained (step S1403).
  • FIG. 15 shows a Petri net model representing each process in places proportional to the processing time Tp as a Petri net model of the process of step S 1401 shown in FIG. 9 is a flowchart illustrating an example of a processing procedure for constructing each product type.
  • step S1501 discrete step time ⁇ is input (step S1501), and then all processing steps and processing time Tp are input for each product type (step SI502). Then, for each processing step, the processing time Tp is divided by the step time ⁇ and integers are calculated to determine the number np of the processing steps (steps S1503, SI 504), and the places of all the processing steps are connected. Then, a subnet model is constructed for each product type (step S1505).
  • step S1506 the process returns from step S1506 to step S1502 until a Petri net model is constructed for all products, and the above processes are repeated. It is most efficient to define the discrete step time ⁇ with the greatest common divisor of each product type and each process time, but it may be set appropriately in consideration of the target control accuracy.
  • FIG. 16 shows the process of step S1402 shown in FIG. 14, that is, a process procedure for obtaining a feedback gain matrix K for each product type from the state equation of the constructed Petri net model and the set evaluation function. It is a flowchart which shows an example.
  • connection matrix b describing the state equation of the Petri net model for each product type is input to the optimization calculator 2 (step S1601), and the matrices Q and R representing the evaluation function are input (step S1601). S1602). Then, a feedback gain matrix K is calculated from the input connection matrix b and the evaluation matrices Q and R (step S1603). This calculation The process returns from step S1604 to step S1601 until the product is completed, and the above process is repeated.
  • the connection matrix b of the Petri net model for all products may be input to the optimization calculation device 212, and all products may be calculated at once.
  • FIG. 17 shows the process of step S 1403 shown in FIG. 14, that is, the product of the feedback gain matrix K calculated as described above and the state vector M (K) representing the in-process product in-process state.
  • the operation vector u (K) for the moving operation end of each product type it moves to the moving operation end in the virtual production logistics process in the order of the product with the largest positive operation value.
  • 5 is a flowchart illustrating an example of a processing procedure for executing a simulation of a production / distribution process for a predetermined period by using a method of sequentially performing a moving operation as many times as possible.
  • step S1701 That is, first, the state vector M (0) in the initial state of the Petri net model is input, all the products to be introduced are input to the entry place, and the value of the time k is initialized to 0 (step S1701), state vectors M (k) of all product types at the present time (time: k) are input (step S1702).
  • the operation vector u (k) is calculated for each product type by multiplying the feedback gain matrix K calculated using the above-described method and the input state vector M (k) (step S17 03). Then, for each moving operation end, the moving operation is executed by a movable number in the order of the product having the larger positive operation amount (step S1704).
  • step S1705 After advancing the time (step S1705), it is determined whether or not the simulation of each step has been completed (step S1706), and if not, the process returns to step S1702. On the other hand, when the process is completed, the simulation result is used as a production schedule (step S1707).
  • a state vector representing the in-process product in-process state is expressed according to the presence or absence of a product in each place.
  • each element of the feedback gain row and the operation vector for which the state vector force is also calculated can directly reflect the size of each element of the feedback gain matrix, and a plurality of elements existing in the same place can be obtained.
  • products with larger gains can always be given priority and as a result, Optimal schedules that minimize the total processing time in the process can be easily created.
  • the state vector in each place can be selected.
  • a method of expressing the state vector if either a method according to the presence or absence of a product in each place or a method according to the number of products existing in each place can be selected, the state vector in each place can be selected.
  • the distribution schedule creation device of the present embodiment also includes a simulation control unit 200 having a distribution simulator 201, an optimization calculation device 212, and the like.
  • the logistics simulator 201 is a production simulator expressing the logistics state and logistics constraints of the production logistics process, a simulator simulating the logistics process, and a large simulator simulating a so-called factory.
  • a simulator is constructed using a Petri net model, and is configured as a discrete system that moves an object for each event (simulator event).
  • a mathematical model (formula model) 211 is configured to correspond to the physical distribution simulator 201.
  • the factors related to the logistics schedule to be created are fetched from the logistics status and the logistics constraints of the production / logistics process, and the above equation is obtained by using a state equation as shown in the following equation (a).
  • Model 211 has been created.
  • the mathematical expression model 211 is held by mathematical expression model holding means (not shown) constituted by semiconductor storage means and the like.
  • a state vector indicating the number of tokens present in each place at a discrete time k in other words, the state quantity is represented by M (k), and the presence or absence of each transition firing is represented by “1” and “0 ⁇ . If the expressed operation vector is represented by u (k), the state at the next time k + 1
  • the vector M (k + 1) can be represented by the above equation (a) using the transition matrix a and the connection matrix b.
  • the optimization calculation device 212 performs an optimization calculation process on the mathematical model 211 to calculate a feedback gain K.
  • the optimization calculation performed by the optimization calculation device 212 uses linear quadratic (LQ) control, and is performed using an evaluation function S as shown in the following equation (mouth).
  • Q and R are appropriate matrices set according to the control purpose, and ⁇ ′ and u ′ are transposition vectors of the state vector ⁇ and the operation vector u, respectively. Then, considering that the evaluation function S is controlled to be minimum,
  • the feedback gain K for performing the state feedback control described above can be obtained from the optimal control theory.
  • the optimal control strategy unit 202 of the simulation control unit 200 calculates a distribution instruction (operation vector u) using the feedback gain ⁇ calculated by the optimization calculation unit 212 and the distribution state (state vector ⁇ ). The process is given to the physical distribution simulator 201, the simulation is advanced, a new physical distribution state is obtained, and a process of calculating a new physical distribution instruction based on the new physical distribution state is repeated. Then, a logistics schedule in the production logistics process is created from the simulation result 220 obtained thereby.
  • a Petri net model of the production and logistics process a Petri net model that represents each process with a place where the processing time ⁇ is input is constructed for each product type. Then, the transition matrix a and the connection matrix b expressed according to the step time ⁇ that is proportional to the processing time ⁇ of each place of the constructed Petri net model are calculated, and the state is calculated using these two matrices a and b. Create an equation (step S1801).
  • a feedback gain matrix K is obtained for each product type from the state equation created in step S1801 and the set evaluation function (step S1802).
  • the obtained feedback gain matrix K and the state vector M (k) representing the in-process product in-process state From the above, the operation level U (k) for the moving operation end of the product is calculated for each product type, and the positive and large operation amount is calculated for each moving operation end in the virtual production and distribution process.
  • the simulation of the production / distribution process for a predetermined period is executed using a method of sequentially performing the moving operation as many times as possible in the order of the products obtained (step S1803).
  • FIG. 19 shows a process of step S 1801 shown in FIG. 18, that is, a Petri net model representing each process in a place where a processing time is input as a Petri net model of a production / distribution process for each product type.
  • 9 is a flowchart illustrating an example of a processing procedure for constructing and calculating a transition matrix a and a connection matrix b representing a step time delay in each process for each product type.
  • step S1901 the discrete step time ⁇ is input (step S1901), and then all the processing steps and the processing time Tp are input for each product type (step SI902). Then, for each processing step, the processing time Tp is divided by the step time ⁇ to form an integer and the step time delay np of each of the above processing steps is determined (steps S1903 and S1904), and according to the step time delay np Then, a transition matrix a and a connection matrix b for each product type in all the processing steps are calculated (step S1905).
  • step S1906 the process returns from step S1906 to step S1902 until transition matrices a and connection matrices b are calculated for all products, and the above processes are repeated. It is most efficient to define the discrete step time ⁇ with the greatest common divisor of each product type and each process time, but it may be set appropriately in consideration of the desired control accuracy.
  • Fig. 20 shows a process of step S1802 shown in Fig. 18, that is, a product of the feedback gain matrix K from the state equation composed of the transition matrix a and the connection matrix b obtained as described above and the set evaluation function.
  • 9 is a flowchart illustrating an example of a processing procedure for obtaining each type.
  • transition matrix a and the connection matrix b representing the step time delay np proportional to the processing time Tp of each place of the Petri net model for each product type are input to the optimization calculation device 212, and S2001), and input the matrices Q and R representing the evaluation function (step S2002). Then, a feedback gain matrix K is calculated from the input transition matrix a, connection matrix b, and evaluation matrices Q and R (step S2003). Until this calculation is completed for all products, step S2004 returns to step S2001, and the above processing is repeated. Return and do.
  • the transition matrix a and the connection matrix b representing the step time delay np proportional to the processing time Tp of each place of the Petri net model are input to the optimization calculator 212, and all products are calculated collectively. You may make it.
  • FIG. 21 shows the processing of step S1803 shown in FIG. 18, that is, the feedback gain matrix K calculated as described above and the state vector M (K) representing the in-process product in-process state, After calculating the operation vector u (K) for the moving operation end for each product type, it is possible to move to the moving operation end in the virtual production / logistics process in the order of the product with the largest positive operation value.
  • 7 is a flowchart illustrating an example of a processing procedure for executing a simulation of a production / distribution process for a predetermined period by using a method of sequentially performing a number of moving operations.
  • step S2101 state vectors M (k) of all product types at the present time (time: k) are input (step S2102).
  • the operation vector u (k) is calculated for each product type by multiplying the feedback gain matrix K calculated using the above-described method and the input state vector M (k) (step S2103). Then, for each moving operation end, the moving operation is executed by a movable number in the order of the product having the larger positive operation amount (Step S2104).
  • step S2105 After advancing the time (step S2105), it is determined whether or not the simulation of each step has been completed (step S2106). If not, the process returns to step S2102. On the other hand, when the process is completed, the simulation result is used as a production schedule (step S2107).
  • Step 1 Step 2 Step 3 Step 4 Processing time (min) 10 15 5 10
  • FIG. 22 shows a Petri net model of a process of manufacturing both products A and B with a discrete step time ⁇ of 5 minutes.
  • steps 1, 2, 3, and 4 have a step time delay of 2, 3, 1, and 2, respectively
  • steps 1, 2, 3, and 4 each have a step time of 2 , 2, 0, and 2 step delays.
  • the products A and B are put in via the moving operation end T1 (hereinafter, the moving operation end is also referred to as transition), and are carried out to the next process or warehouse via the transition T6. . That is, product A passes through places P1, P2, P3, and P4, and product B passes through places P1, P2, and P4.
  • the state vector indicating the number of tokens present in each place at a discrete time k that is, the state quantity is represented by M (k), and the presence or absence of each transition firing is represented by "1".
  • the operation vector expressed by “0” and “0k” is expressed by u (k)
  • the state vector M (k + 1) at the next time k + 1 is calculated by using the transition matrix a and the connection matrix b.
  • the moving operation end (transition) on the state equation (a) coincides with the moving operation end of the real process, that is, the signal of the operation vector u (k) is Process operation signal.
  • the vector in which the number of tokens present in places P1, P2, P3, and P4 are arranged is M, and whether transitions T1, T2, T3, T5, and T6 are fired is 1
  • the operation vector represented by "and ⁇ 0" is u
  • the transition matrix a and the connection matrix b expressed by the following equations (2) and (3) are used. Therefore, the vector M (k) force can also represent a state change to the vector M (k + 1).
  • the one-digit number in the column direction indicates a place number
  • the two-digit number in the row direction indicates the place number on the left side
  • the number on the right side indicates the place number.
  • a one-digit number in the column direction indicates a transition number
  • a two-digit number in the row direction indicates a place number on the left side
  • a right-side number indicates a place number.
  • the number of the existing state (step time delay) is shown.
  • Equation (4) when the state force existing in a certain process is, the submatrix of the part related to that process is represented by an n X n square matrix as shown in Equation (4). Is done.
  • the transition matrix a representing the transitions of all the processes corresponds to the sub-matrices for each of the above processes corresponding to the numbers in the row and column directions. It is represented by placing it in an appropriate position and setting all other elements to "0".
  • connection matrix b A general form for expressing the connection matrix b is shown in the following equation (5). That is, when the number of states existing in a certain process is 3 ⁇ 4, the submatrix of the part related to that process is represented by an nX 2 matrix as shown in Expression (5). (1,1) element number ⁇ 1 "indicates that a token is input to the corresponding place, and (n, 2) element number '1' indicates that a token is output from the corresponding place. It is shown that.
  • the connection matrix b for all the processes is represented by arranging the small matrices of the above processes at appropriate positions corresponding to the numbers in the row and column directions, and setting all other elements to "0". You.
  • a Petri net model is constructed by assigning a plurality of units of processing time (discrete step time) to one place, and the logistics model is formed only by two determinants of the transition matrix a and the connection matrix b. Since it can be expressed, it is not necessary to reconstruct a Petri net model for control with one place for each discrete step time. In addition, the number of control terminals can be reduced as compared with the Petri net model in which a place is provided for each discrete step time, and the model can be easily used in an actual process.
  • the feedback gain matrix K for controlling can be obtained from the optimal control theory.
  • a method for calculating the feedback gain matrix K is described in, for example, (Kazuaki Ando, et al., “Control System Design by Numerical Analysis Method,” published by the Society of Instrument and Control Engineers, ⁇ .126-130, first edition of 1993, second edition) There are several methods that have been done.
  • the evaluation matrices Q and R are square matrices having dimensions of the number of places and the number of transitions, respectively, for expressing the transient characteristics of control and the input energy of the transition operation as evaluation functions. And may be appropriately set according to the control purpose. For example, when emphasizing transient characteristics, a matrix Q having a large numerical value may be set. If it is desired to reduce the input energy required for the operation, a matrix R having a large numerical value may be set.
  • FIG. 23 shows an example of a Petri net model of a manufacturing process including a plurality of steps, and the discrete step time ⁇ is set to 5 minutes.
  • This manufacturing process is composed of a pre-processing step of steps 1, 2, 3, and 4 and a post-processing step of steps 5, 6, and a pre-processing step input buffer indicated by a place P1 (input place), It has a post-process input buffer shown in places P6 and P8 and an unloading place shown in place P10.
  • the product processed in pre-processing step 1 or 2 is processed in post-processing step 5, and the product processed in pre-processing step 3 or 4 is processed in post-processing step 6.
  • some products can be processed by any of a plurality of combinations of the pre-processing step 1-4 and the post-processing step 5-6, so there are a total of 15 product types.
  • Table 2 below shows which pre-treatment and post-treatment combinations can be used for each product type.
  • places P11, P12, P13, P14, P15, and P16 are virtual places for restricting the processing capacity of the process 1-16, and the capacity settings initially set for these virtual places are set.
  • the number of products that can be processed simultaneously in each processing step is limited by the number of virtual tokens for use.
  • the place P2 force is also configured, and one capacity setting virtual token is placed in the virtual place P11 as an initial state. Processing capacity is set to 1! RU
  • FIG. 23 shows the virtual place from step 1 to step 6.
  • the place P1 for product input and the place P10 for product output can accommodate up to 200 products, and the buffers of places P6 and P8 are both set to accommodate up to 20 products.
  • the part shown by the solid line in FIG. 24 shows the Petri net model for the product type No. 1 shown in Table 2. Similarly, by constructing Petri net models for all product types, the model construction shown in the flowchart of FIG. 18 is performed.
  • the process of obtaining the feedback gain matrix K will be described using the product type No. 1 as an example.
  • the transition matrix a in the state equation of equation (a) is expressed as a matrix of size 8 ⁇ 8 expressed by the following equation (6) for the Petri net model of product type No. 1 shown in FIG. Desired.
  • equation (6) the numbers in the column direction indicate the place numbers, and the numbers other than the last digit indicate the place numbers in the numbers in the row direction, and the last digit is the number in each place. Show the number of (step delay).
  • connection matrix b in the state equation of equation (a) is, for the Petri net model of product type No. 1 shown in FIG. 24, a size 8 expressed by the following equation (7). It is obtained as a matrix of X6.
  • equation (7) the numbers in the column direction indicate transition numbers, numbers in the row direction other than the last digit indicate place numbers, and the numbers in the last digit exist in each place. Show the number! / Puru.
  • the matrices Q and R in the evaluation function represented by the equation (mouth) are square matrices having dimensions of the step time delay number of each process and the number of transitions, respectively. Therefore, each is set for each product type of Petri net model.
  • Equation (8) and (9) I (n) is an n-th order unit matrix.
  • the feedback gain matrix K can be obtained by the optimal control theory in a discrete-time system.
  • (B T PB + R) -1 is the inverse matrix of the matrix (B T PB + R).
  • Step S2101 while inputting the state vector M (0) in the initial state of the Petri net model, inputting all products to be introduced into the introduction place, and initializing the value of time k to 0, (Step Step S2101), input the state vectors of all product types at the current time (time: k) (Step S2102), enter new products for each product type, and add them to the state vector.
  • the vector M (k) is determined. Furthermore, for each product type, the feedback gain matrix K and the state vector M (k)
  • the operation vector u (k) can be calculated (step S2103).
  • each element of the expression (13) is a state number of each place ⁇ 1, ⁇ 2, ⁇ 6, ⁇ 7, ⁇ 10
  • operation vectors u (k) are obtained for all product types. Then, for each moving operation end, that is, for each transition, the moving operation is executed by a movable number in the order of the product having the larger positive operation amount (step S2104).
  • the operation amount for the token of product type No. 1 for transition T10 was 0.300 according to equation (14).
  • the operation amount for the token of product type No. 8 is calculated in the same way.
  • the transition matrix a of product type No. 8 is expressed by equation (15), and the connection matrix 1 ⁇ is expressed by ( 16), and the matrices Q and R show (17) and (18).
  • the feedback gain matrix K is as shown in the following equation (19), and the manipulated variable of transition T10 is 0.361.
  • I (n) is an n-th order unit matrix.
  • the transition T10 can move one token to the place P7 by a moving operation, that is, firing.
  • a moving operation that is, firing.
  • the transition T10 can be fired only for the token of the product type No. 8 after all. Also, since the token of product type No. 8 did not exist in another place at time k, the transition T10
  • step S2105 it is determined whether or not the simulation of each step has been completed. If the simulation has not been completed, the process returns to step S2102. On the other hand, when the process is completed, the simulation result is used as the production schedule (step S2107).
  • a Petri net model is constructed such that one place includes a plurality of step delays, and a transition matrix and connection Since the mathematical model can be expressed only by the two determinants of the matrix, it is not necessary to reconstruct a Petri net model with one place for each time delay. In addition, the number of control ends can be reduced as compared with a Petri net model in which one place is provided for each step time delay, and it is easy to use in an actual process.
  • the present invention can be applied to the force or other Daraf model described using the Petri net model as an example, for example, a directed graph or an undirected graph.
  • a directed graph places in the Petri net model described above are represented by points, and transitions are represented by lines with arrows.
  • the line with the arrow is the moving operation end that moves the product, that is, the token, from point to point, and serves as a moving path.
  • the arrow indicates the direction in which the token moves from the line to the point or from the point to the line.
  • the number of products that can be processed simultaneously in each processing step is limited by the number of capacity setting virtual tokens initially set in the virtual place provided in each step.
  • there is no virtual place, and the processing capacity in each process is controlled by software.
  • a seventh embodiment described below is related to the above-described third embodiment (seventh embodiment).
  • the production / distribution schedule creation device of this embodiment is also a distribution simulation.
  • a mathematical model 321 and an optimization calculator 330 are also a distribution simulation.
  • the production / distribution schedule creation device of this embodiment in the production process from process A to process B, the process A operation plan that matches the process B Let us deal with optimization problems.
  • the operation plan here first aims at maximizing the throughput of the entire factory. Secondly, it aims at minimizing the residence time of semi-finished products in the process. In other words, the semi-finished product processed from Process A is transported to Process B by transport equipment, etc., and then stored in the depot until the semi-finished product currently in the intermediate buffer is completely completed. Where the waiting time occurs. If the waiting time is long, the temperature drop of the semi-finished product will increase, causing problems in product quality. Therefore, in order to suppress such a temperature drop, it is necessary to minimize the charging wait time on the storage site.
  • the processing time of each semi-finished product in the process B may be different for each semi-finished product.
  • the next semi-finished product must be put in before the contents of the intermediate buffer at the entrance of Process B are completely interrupted. Therefore, when preparing the operation plan for Process A, consider that the processing time differs for each semi-finished product and the necessity of continuation of each semi-finished product and minimization of the residence time, etc. It is necessary to accurately determine not only the processing order but also the processing time.
  • FIG. 25 is a block diagram illustrating a schematic configuration of a production / distribution schedule creating apparatus according to the present embodiment
  • FIG. 26 is a diagram illustrating an outline of processing performed by the production / distribution schedule creating apparatus according to the present embodiment.
  • FIG. 27 is a diagram showing the positioning of the processing plan creation device according to the present embodiment in the planning system. First of all, using FIG. The positioning of the production / distribution schedule creation device according to the embodiment will be described.
  • the input order creating unit 31 assigns each semi-finished product to the process B based on a preset weekly schedule 30. Determining the order of input, in this case, at least in which equipment of process A, and then in which equipment of process B the semi-finished product is to be processed and in which order.
  • the processing plan creation unit 32 is configured to execute the process B input order given by the input order creation unit 31 under the input order created by the input order creation unit 31 and various factory distribution restrictions. Obtain the operation plan in the information resource process A, that is, the processing order and the processing time in the process A.
  • the processing plan creation unit 32 uses a Petri net that graphically models the logistics structure (e.g., equipment layout and connection relations in the factory, equipment capacity, and semi-finished product passage routes).
  • the operation plan (information of the processing order and the processing time) in the process A obtained by the processing plan creation unit 32 is given to the display unit 33 and displayed in, for example, a Gantt chart format.
  • the evaluation section 34 evaluates the required operation plan from various viewpoints, and if the results are not satisfactory, corrects the input order of each semi-finished product as necessary. Then, the operation plan is created again by the treatment plan creation section 32.
  • Process A Units 1 and 2 and Process B Units 1, 2 and 3 are taken as examples.
  • the semi-finished products indicated by the letters “A, B, C, D, E” are processed in this order from the process A1 to the process B1 by the charging order creation unit 31 in FIG.
  • semi-finished products indicated by the numbers “1, 2, 3, 4, 5” are processed in this order in process B2
  • “0, P, Q, R, S” are processed in process A3 It is decided to process semi-finished products indicated by the alphabetical characters in this order.
  • the processing plan creation unit 32 performs the following order of input based on the concept of model predictive control. For each judgment of the processing time simulation (every time a processing event occurs), the waiting time of the semi-finished product on the yard, which is the future physical condition, and the deceleration amount of the semi-finished product processing speed are estimated. The processing order and the processing time of the process A that optimizes the predetermined evaluation function set for maximizing the overall throughput and minimizing the waiting time are determined. At this time, the estimated range of the future physical distribution state is one semi-finished product to be processed in each process B.
  • step S1 one semi-finished product is set for each process B as a predicted range of the future physical distribution state.
  • semi-finished product D is set for process B1, semi-finished product 5 for process B2, and semi-finished product S for process B3.
  • step S2 the processing completion desired time of each semi-finished product (D, 5, S) within the set prediction range is calculated, and a distribution model based on the distribution restrictions is formulated.
  • the processing completion desired time is a time indicating when the semi-finished product should be processed from process A and the semi-finished product exactly arrives at process B at the processing completion time of the previous semi-finished product. This is easily obtained by subtracting the transport time (including the secondary processing time) of the semi-finished product from the processing completion time of the previously processed semi-finished product.
  • the processing completion desired time of each semi-finished product (D, 5, S) within the current forecast range is indicated by an X in the upper diagram of FIG.
  • step S5 the semi-finished product D ⁇ semi-finished product 5 ⁇ semi Issue processing instructions in the order of product S.
  • the simulator proceeds with the simulation until the processing time t + At of the semi-finished product D in step S6.
  • This state is shown in the lower diagram of FIG. Since the processing event has occurred again in this way, in step S7, one semi-finished product for each process B is set as the predicted range of the future distribution state from the processing event occurrence time t + At of the semi-finished product D.
  • semi-finished product E is newly set as the forecast range for Process B1 and Process B1 in which the same force processing event occurred in Process B2 and Unit 3 as in the previous time.
  • the construction of the distribution model and the optimization calculation are performed in the same manner as the previous time.
  • step S8 it is assumed that a result that the order of semi-finished product S ⁇ semi-finished product 5 ⁇ semi-finished product E is optimal is obtained.
  • the simulation in the simulator is advanced to the processing time of the semi-finished product S by issuing a processing instruction to the simulator of the Petri net in the order of semi-finished product S ⁇ semi-finished product 5 ⁇ semi-finished product E.
  • the process of partially simulating (optimizing the processing order and processing time) by dividing the future prediction range by one semi-finished product of each process B is performed. I will repeat.
  • a result indicating the result of a simulation in which all the semi-finished products were processed at the desired processing time is not always obtained at the desired processing time. If the processing time is later than the desired processing time, the continuity of the semi-finished product in process B is interrupted, so the processing time of the previous semi-finished product is extended to maintain continuity (reduce the processing speed )There is a need. However, this tends to reduce the overall throughput.
  • reference numeral 11 denotes a discrete event simulator based on Petri nets, which is composed of a graphical distribution structure model based on Petri nets and a rule description that cannot be represented graphically.
  • rules include the earliest processing time indicating the time limit at which a semi-finished product can be processed at the earliest time, the processing latest time indicating the time limit at which a semi-finished product can be processed at the latest time, and interference between multiple processes A. There are conditions.
  • the processing speed of each semi-finished product in process B can be changed only within a certain narrow range, and the waiting time on the storage site has upper and lower limits.
  • the earliest and latest time points for the completion of the process A are set for each semi-finished product to satisfy the above conditions.
  • Reference numeral 12 denotes a logistics model construction unit, which includes information on the earliest processing end time, the latest time, and the logistics restriction set in the simulator 11, and the current logistics given as a result of the simulation performed by the simulator 11.
  • a logistics model construction unit which includes information on the earliest processing end time, the latest time, and the logistics restriction set in the simulator 11, and the current logistics given as a result of the simulation performed by the simulator 11.
  • a future prediction range for one semi-finished product is set for each process B, and Build a logistics model.
  • This logistics model is performed by formulas based on a mathematical model as described below.
  • FIG. 28 is a diagram showing an outline of the formulation of the distribution model.
  • a processing end event of process A of a semi-finished product occurs at time t on the simulation
  • one semi-finished product is set as the predicted range of the future logistics state, and from the current logistics state obtained from the simulator 11, the desired end time of the process A for each semi-finished product within the predicted range is determined. Calculate each.
  • X is a matrix representation of the processing end time of process A of each process B
  • a and B are predetermined determinants
  • xmin and xmax are the earliest time and the latest time of the processing end of process A for each process B, respectively. Is a matrix representation of.
  • FIG. 29 is a block diagram showing an example of a computer system that can constitute the production / distribution schedule creation device of each of the above-described embodiments.
  • reference numeral 1200 denotes a computer PC.
  • the PC 1200 includes a CPU 1201 and is stored in a ROM 1202 or a hard disk (HD) 1211 or supplied from a flexible disk drive (FD) 1212. Executing device control software to control each device connected to the system bus 1204 as a whole.
  • Each functional unit of this embodiment is configured by a program stored in the CPU 1201, ROM 1202, or hard disk (HD) 1211 of the PC 1200.
  • Reference numeral 1203 denotes a RAM, which functions as a main memory, a work area, and the like of the CPU 1201.
  • Reference numeral 1205 denotes a keyboard controller (KBC), which controls input of a signal input from the keyboard (KB) 1209 into the system main body.
  • KBC keyboard controller
  • a display controller (CRTC) 1206 controls display on a display device (CRT) 1210.
  • 1207 is a disk controller (DKC), which is a hard disk that stores a boot program (startup program: a program that starts execution (operation) of the hardware and software of a personal computer), multiple applications, edit files, user files, and a network management program.
  • HD 1211 and Flexible Disk (FD) 1212.
  • Reference numeral 1208 denotes a network interface card (NIC), which exchanges data bidirectionally with a network printer, another network device, or another PC via the LAN 1220.
  • NIC network interface card
  • the present invention may be applied to a system including a plurality of devices or to an apparatus including one device.
  • an object of the present invention is to supply a storage medium in which a program code of software for realizing the functions of the above-described embodiments is recorded to a system or an apparatus, and the computer (CPU or MPU) of the system or the apparatus stores the storage medium. It goes without saying that this is also achieved by reading and executing the program code stored in the medium.
  • the readout program code itself realizes the function of the above-described embodiment, and the storage medium storing the program code constitutes the present invention.
  • a storage medium for supplying the program code for example, a flexible disk, hard disk, optical disk, magneto-optical disk, CD-ROM, CD-R, magnetic tape, nonvolatile memory card, ROM, or the like is used. Can be.
  • the computer executes the readout program code to execute the above-described implementation.
  • the OS Operating System
  • the OS that runs on the computer performs some or all of the actual processing based on the instructions of the program code. It goes without saying that a case where the functions of the above-described embodiments are realized by the processing is also included.
  • the simulation result power described in the example of creating the production / distribution schedule in the production / distribution process described above is applicable to the case where the production / distribution process is controlled based on the simulation result.
  • the present invention applies.
  • the simulator power simulation detects the physical distribution state and the physical distribution restriction information at the current time, Calculate the optimal logistics instruction by the optimization method based on the predetermined evaluation index, and based on the above calculation results, proceed with the detailed simulation, and then when the event requiring the logistics instruction occurs The calculation of the optimal logistics instruction is repeated again, so that the detailed simulation itself can be performed only once to obtain the optimal physical distribution instruction.
  • the simulator, the mathematical model, and the optimization device are linked to calculate the optimal logistics instruction and simulate the calculation result to create a schedule. It can also create executable schedules.
  • a schedule that optimizes a desired evaluation index can be created, and a calculation time can be reduced to create a schedule within a practical time.
  • both optimality and feasibility can be ensured.
  • the time and effort required to create a schedule according to the status of the target production and logistics processes can be significantly reduced.
  • accurate production and logistics schedules can be created at high speed and with high accuracy. It can be created.

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Manufacturing & Machinery (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Automation & Control Theory (AREA)
  • Quality & Reliability (AREA)
  • General Engineering & Computer Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Primary Health Care (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

 生産・物流プロセスの物流状態と物流制約を表現した生産・物流プロセスを模擬する生産・物流シミュレータ(100)と、上記生産・物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作成された数式モデル(110)を保持する数式モデル保持装置と、上記数式モデル(110)に対して所定の評価関数を用いて最適化計算処理を行って上記生産・物流シミュレータに対する物流指示を算出する最適化計算装置(120)とを設け、上記最適化計算装置(120)によって得られた物流指示を上記生産・物流シミュレータ(100)に与えてシミュレーションを実行させるようにして、1回のシミュレーションを行うだけで最適な解が得られるようにする。

Description

明 細 書
生産 ·物流スケジュール作成装置及び方法、生産 ·物流プロセス制御装 置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体 技術分野
[0001] 本発明は生産 ·物流スケジュール作成装置及び方法、生産 ·物流プロセス制御装 置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体に 関し、特に、操作者の熟練度に依存することなく対象システムのスケジュールを正確 に作成するような場合に用いて好適なものである。
背景技術
[0002] 従来、見込み生産を行わな!/、受注生産の形態では、受注した品目を製造オーダー に分割し、納期遵守率や設備稼働率、中間在庫量、コスト等の観点を考慮して生産- 物流スケジュールを作成して 、る。上記生産 ·物流スケジュールを作成する手法とし て、技術的に大別すると 2つの手法が用いられている。
[0003] すなわち、第 1の手法としては、例えば、特許文献 1の「生産計画評価方法及びシ ステム」に開示されているように、コンピュータ上に構築した工場を模したシミュレーシ ヨン上で、実機器と同じインタフェースカゝら取得した情報を使用して実機器の稼動を 予測し、稼動予測に基づいて、実機器より速い速度で仮想的な生産を行い、仮想的 な生産の過程及び結果を用いて、精度の高い指標を提示することによって、生産計 画の評価及び選択を可能にする手法である。
[0004] また、第 2の手法としては、特許文献 2の「物流計画作成装置」にて開示されて 、る ように、線形計画法、数理計画法等のように、最適性が保証される手法に基づいてス ケジュールを作成する手法である。
[0005] 特許文献 1に記載の「生産計画評価方法及びシステム」に開示されて!ヽるように、シ ミュレータを用いて生産 ·物流スケジュールを作成する手法は、満足できる結果が得 られるまでには、(1)条件を種々に変えながらシミュレーションを行い、その結果の評 価を何回も繰返し行う必要があった。したがって、(2)大規模工場では生産'物流ス ケジュールを作成するのに多くの時間が力かってしまう問題点があった。また、(3)高 精度な生産'物流スケジュールを得るためには、シミュレーション 'ルールを細力べ設 定しなければならない問題点があった。
[0006] また、特許文献 2の「物流計画作成装置」にて開示されて!、るように、線形計画法、 数理計画法等のように、最適性が保証される手法に基づ!/ヽてスケジュールを作成す る手法の場合には、(1)生産 ·物流スケジュールを作成する規模が大きくなると、実用 的な時間内に解くことが困難になってしまう問題点があった。また、(2)数式で記述で きない制約や条件に起因する誤差が生じるため、得られた生産 ·物流スケジュールが 実行可能であるかどうかは保証されていな力つた。
[0007] 本発明は上述の問題点にかんがみ、シミュレーションを繰り返し行うことなく最適な 生産 ·物流シミュレーション結果を得ることができるようにして、スケジュール作成対象 の生産 ·物流プロセスで実際に使用可能であることが保証された生産 ·物流スケジュ ールを高速に、且つ高精度に作成できるようにすることを目的とする。
[0008] 特許文献 1:特開 2002 - 366219号公報
特許文献 2 :特開 2000-172745号公報
発明の開示
[0009] 本発明による生産 ·物流スケジュール作成装置は、生産 ·物流プロセスの物流状態 と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記 生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって 、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作成され た数式モデルを保持する数式モデル保持装置と、上記数式モデルに対して所定の 評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレータに対する物 流指示を算出する最適化計算装置とを有し、上記最適化計算装置によって得られた 物流指示を上記生産'物流シミュレータに与えてシミュレーションを実行させるととも に、新たな事象が発生した場合には上記生産 ·物流シミュレータから上記最適化計 算装置に対して最適化計算を行うようにする指示を出力するようにして、上記生産 · 物流シミュレータと上記最適化計算装置とを連動させて、上記生産'物流プロセスに おける生産 ·物流スケジュールを作成するようにした点に特徴を有する。
本発明による他の生産 ·物流スケジュール作成装置は、生産 ·物流プロセスの物流 状態と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、 上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであ つて、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作成 された状態方程式を用いた数式モデルを保持する数式モデル保持装置と、上記数 式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 -物 流シミュレータに対する物流指示を算出する最適化計算装置とを有し、上記最適化 計算処理によりフィードバックゲインを算出し、そのフィードバックゲインと物流状態と を用いて物流指示を算出して上記生産'物流シミュレータに与えて、シミュレーション を進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算 出するという処理を繰り返すことにより得られたシミュレーション結果から上記生産 '物 流プロセスにおける生産 ·物流スケジュールを作成するようにした点に特徴を有する。 本発明による他の生産 ·物流スケジュール作成装置は、生産 ·物流プロセスの物流 状態と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、 上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであ つて、上記生産'物流プロセスの立案開始時間から予め設定した期間 (計画作成期 間)分を対象として、着目して 、る物流のスケジュールを作成するのに係わる情報を 取り込んで作成された数式モデルを保持する数式モデル保持装置と、上記数式モ デルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミ ユレータに対する物流指示を算出する最適化計算装置とを有し、上記最適化計算処 理により現時点力も予め設定した期間 (指示算出期間)分について物流指示を算出 して上記生産'物流シミュレータに与えて、予め設定した期間(シミュレーション期間) 分だけシミュレーションを実行して予め設定した期間 (計画確定期間)分だけ物流計 画を確定し、上記確定した期間の直後の日時を新たな立案開始日時として設定して 物流計画を立案するという処理を繰り返すことにより得られたシミュレーション結果か ら上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにした点に 特徴を有する。
本発明による生産 ·物流スケジュール作成方法は、生産 ·物流プロセスの物流状態 と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記 生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって 、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作成され た数式モデルを保持する数式モデル保持装置と、上記数式モデルに対して所定の 評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレータに対する物 流指示を算出する最適化計算装置とを有する生産'物流スケジュール作成装置によ り生産'物流スケジュールを作成する方法であって、上記最適化計算装置によって得 られた物流指示を上記生産 ·物流シミュレータに与えてシミュレーションを実行させる とともに、新たな事象が発生した場合には上記生産 ·物流シミュレータから上記最適 化計算装置に対して最適化計算を行うようにする指示を出力するようにして、上記生 産 ·物流シミュレータと上記最適化計算装置とを連動させて、上記生産 ·物流プロセ スにおける生産 ·物流スケジュールを作成するようにした点に特徴を有する。
本発明による他の生産 ·物流スケジュール作成方法は、生産 ·物流プロセスの物流 状態と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、 上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであ つて、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作成 された状態方程式を用いた数式モデルを保持する数式モデル保持装置と、上記数 式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 -物 流シミュレータに対する物流指示を算出する最適化計算装置とを有する生産 ·物流 スケジュール作成装置により生産'物流スケジュールを作成する方法であって、上記 最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲインと物流 状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シミュレ一 シヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示 を算出するという処理を繰り返すことにより得られたシミュレーション結果力 上記生 産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにした点に特徴を 有する。
本発明による他の生産 ·物流スケジュール作成方法は、生産 ·物流プロセスの物流 状態と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、 上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであ つて、上記生産'物流プロセスの立案開始時間から予め設定した期間 (計画作成期 間)分を対象として、着目して 、る物流のスケジュールを作成するのに係わる情報を 取り込んで作成された数式モデルを保持する数式モデル保持装置と、上記数式モ デルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミ ユレータに対する物流指示を算出する最適化計算装置とを有する生産 ·物流スケジ ユール作成装置により生産'物流スケジュールを作成する方法であって、上記最適化 計算処理により現時点力も予め設定した期間 (指示算出期間)分について物流指示 を算出して上記生産'物流シミュレータに与えて、予め設定した期間(シミュレーショ ン期間)分だけシミュレーションを実行して予め設定した期間 (計画確定期間)分だけ 物流計画を確定し、上記確定した期間の直後の日時を新たな立案開始日時として設 定して物流計画を立案するという処理を繰り返すことにより得られたシミュレーション 結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するように した点に特徴を有する。
本発明のコンピュータプログラムは、生産'物流プロセスの物流状態と物流制約を 表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 ·物流プ 口セスの物流状態と物流制約とを数式で表現した数式モデルであって、着目している 物流のスケジュールを作成するのに係わる情報を取り込んで作成された数式モデル を保持する数式モデル保持装置と、上記数式モデルに対して所定の評価関数を用 いて最適化計算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出 する最適化計算装置としての機能をコンピュータに実現させ、上記最適化計算装置 によって得られた物流指示を上記生産 ·物流シミュレータに与えてシミュレーションを 実行させるとともに、新たな事象が発生した場合には上記生産 ·物流シミュレータから 上記最適化計算装置に対して最適化計算を行うようにする指示を出力するようにして 、上記生産'物流シミュレータと上記最適化計算装置とを連動させて、上記生産'物 流プロセスにおける生産 ·物流スケジュールを作成するようにした点に特徴を有する。 本発明による他のコンピュータプログラムは、生産'物流プロセスの物流状態と物流 制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 · 物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、着目 している物流のスケジュールを作成するのに係わる情報を取り込んで作成された状 態方程式を用いた数式モデルを保持する数式モデル保持装置と、上記数式モデル に対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレ ータに対する物流指示を算出する最適化計算装置としての機能をコンピュータに実 現させ、上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバック ゲインと物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与え て、シミュレーションを進め、新たな物流状態を得て、この新たな物流状態をもとに新 たな物流指示を算出するという処理を繰り返すことにより得られたシミュレーション結 果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにした 点に特徴を有する。
本発明による他のコンピュータプログラムは、生産'物流プロセスの物流状態と物流 制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 · 物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、上記 生産 ·物流プロセスの立案開始時間力 予め設定した期間 (計画作成期間)分を対 象として、着目している物流のスケジュールを作成するのに係わる情報を取り込んで 作成された数式モデルを保持する数式モデル保持装置と、上記数式モデルに対し て所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレータに 対する物流指示を算出する最適化計算装置としての機能をコンピュータに実現させ 、上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作 成するようにした点に特徴を有する。
本発明による生産 ·物流プロセス制御装置は、生産 ·物流プロセスの物流状態と物 流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 •物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、着 目して 、る物流のスケジュールを作成するのに係わる情報を取り込んで作成された 状態方程式を用いた数式モデルを保持する数式モデル保持装置と、上記数式モデ ルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュ レータに対する物流指示を算出する最適化計算装置とを有し、上記最適化計算処 理によりフィードバックゲインを算出し、そのフィードバックゲインと物流状態とを用い て物流指示を算出して上記生産'物流シミュレータに与えて、シミュレーションを進め
、新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返すことにより得られたシミュレーション結果に基づいて生産.物流プ 口セスの制御を行う点に特徴を有する。
ことを特徴とする。
本発明による他の生産 ·物流プロセス制御装置は、生産 ·物流プロセスの物流状態 と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記 生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって 、上記生産'物流プロセスの立案開始時間力も予め設定した期間 (計画作成期間)分 を対象として、着目している物流のスケジュールを作成するのに係わる情報を取り込 んで作成された数式モデルを保持する数式モデル保持装置と、上記数式モデルに 対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレ一 タに対する物流指示を算出する最適化計算装置とを有し、上記最適化計算処理によ り現時点から予め設定した期間 (指示算出期間)分について物流指示を算出して上 記生産 ·物流シミュレータに与えて、予め設定した期間(シミュレーション期間)分だけ シミュレーションを実行して予め設定した期間 (計画確定期間)分だけ物流計画を確 定し、上記確定した期間の直後の日時を新たな立案開始日時として設定して物流計 画を立案するという処理を繰り返すことにより得られたシミュレーション結果に基づい て生産 ·物流プロセスの物流制御を行うようにした点に特徴を有する。
本発明による生産 ·物流プロセス制御方法は、生産 ·物流プロセスの物流状態と物 流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 •物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、着 目して 、る物流のスケジュールを作成するのに係わる情報を取り込んで作成された 状態方程式を用いた数式モデルを保持する数式モデル保持装置と、上記数式モデ ルに対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュ レータに対する物流指示を算出する最適化計算装置とを有する生産,物流プロセス 制御装置により生産'物流プロセスを制御する方法であって、上記最適化計算処理 によりフィードバックゲインを算出し、そのフィードバックゲインと物流状態とを用いて 物流指示を算出して上記生産'物流シミュレータに与えて、シミュレーションを進め、 新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返すことにより得られたシミュレーション結果に基づいて生産.物流プ 口セスの制御を行うようにした点に特徴を有する。
本発明による他の生産 ·物流プロセス制御方法は、生産 ·物流プロセスの物流状態 と物流制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記 生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって 、上記生産'物流プロセスの立案開始時間力も予め設定した期間 (計画作成期間)分 を対象として、着目している物流のスケジュールを作成するのに係わる情報を取り込 んで作成された数式モデルを保持する数式モデル保持装置と、上記数式モデルに 対して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレ一 タに対する物流指示を算出する最適化計算装置とを有する生産,物流プロセス制御 装置を用いた生産'物流プロセス制御方法であって、上記最適化計算処理により現 時点から予め設定した期間 (指示算出期間)分について物流指示を算出して上記生 産 ·物流シミュレータに与えて、予め設定した期間(シミュレーション期間)分だけシミ ユレーシヨンを実行して予め設定した期間 (計画確定期間)分だけ物流計画を確定し 、上記確定した期間の直後の日時を新たな立案開始日時として設定して物流計画を 立案するという処理を繰り返すことにより得られたシミュレーション結果に基づいて生 産 ·物流プロセスの物流制御を行うようにした点に特徴を有する。
本発明によるコンピュータプログラムは、生産'物流プロセスの物流状態と物流制約 を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 ·物流 プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、着目して いる物流のスケジュールを作成するのに係わる情報を取り込んで作成された状態方 程式を用いた数式モデルを保持する数式モデル保持装置と、上記数式モデルに対 して所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレータ に対する物流指示を算出する最適化計算装置としての機能をコンピュータに実現さ せ、上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイ ンと物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、 シミュレーションを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな 物流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果に 基づ 、て生産 ·物流プロセスの制御を行うようにした点に特徴を有する。
本発明による他のコンピュータプログラムは、生産'物流プロセスの物流状態と物流 制約を表現した生産 ·物流プロセスを模擬する生産 ·物流シミュレータと、上記生産 · 物流プロセスの物流状態と物流制約とを数式で表現した数式モデルであって、上記 生産 ·物流プロセスの立案開始時間力 予め設定した期間 (計画作成期間)分を対 象として、着目している物流のスケジュールを作成するのに係わる情報を取り込んで 作成された数式モデルを保持する数式モデル保持装置と、上記数式モデルに対し て所定の評価関数を用いて最適化計算処理を行って上記生産 ·物流シミュレータに 対する物流指示を算出する最適化計算装置としての機能をコンピュータに実現させ 、上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果に基づいて生産.物流プロセスの物流制御を行うようにした点に特 徴を有する。
本発明によるコンピュータ読み取り可能な記録媒体は、本発明によるコンピュータ プログラムを記録した点に特徴を有する。 図面の簡単な説明
[図 1]図 1は、本発明の第 1の実施形態を示し、生産'物流スケジュール作成装置の 概略構成を説明するブロック図である。 [図 2]図 2は、本発明の第 2の実施形態を示し、生産'物流スケジュール作成装置の 概略構成を説明するブロック図である。
[図 3]図 3は、第 2の実施形態における生産 ·物流スケジュール作成の処理手順を示 すフローチャートである。
[図 4]図 4は、モデル構築の処理手順を示すフローチャートである。
[図 5]図 5は、制御則構築の処理手順を示すフローチャートである。
[図 6]図 6は、シミュレーションの処理手順を示すフローチャートである。
[図 7]図 7は、本発明の第 3の実施形態を示し、生産'物流スケジュール作成装置の 概略構成を説明するブロック図である。
[図 8]図 8は、本発明を適用した具体例を示し、生産 ·物流計画作成手順を説明する 図である。
[図 9]図 9は、第 4の実施形態における生産 ·物流スケジュール作成の処理手順を示 すフローチャートである。
[図 10]図 10は、モデル構築の処理手順を示すフローチャートである。
[図 11]図 11は、制御則構築の処理手順を示すフローチャートである。
[図 12]図 12は、シミュレーションの処理手順を示すフローチャートである。
[図 13]図 13は、ペトリネットモデルの例を示す図である。
[図 14]図 14は、第 5の実施形態における生産 ·物流スケジュール作成の処理手順を 示すフローチャートである。
[図 15]図 15は、モデル構築の処理手順を示すフローチャートである。
[図 16]図 16は、制御則構築の処理手順を示すフローチャートである。
[図 17]図 17は、シミュレーションの処理手順を示すフローチャートである。
[図 18]図 18は、第 6の実施形態における生産 ·物流スケジュール作成の処理手順を 示すフローチャートである。
[図 19]図 19は、モデル構築の処理手順を示すフローチャートである。
[図 20]図 20は、制御則構築の処理手順を示すフローチャートである。
[図 21]図 21は、シミュレーションの処理手順を示すフローチャートである。
[図 22]図 22は、ペトリネットモデルの例を示す図である。 [図 23]図 23は、ペトリネットモデルの例を示す図である。
[図 24]図 24は、製品種 No.1に対するペトリネットモデルの例を示す図である。
[図 25]図 25は、第 8の実施の形態を示し、製造プロセスにおける生産.物流スケジュ ール作成装置の要部構成を示すブロック図である。
[図 26]図 26は、生産 ·物流スケジュール作成装置によって行われる動作 (本実施の 形態による生産 ·物流スケジュール作成方法)を説明するための図である。
[図 27]図 27は、生産 ·物流スケジュール作成装置の週間日別計画システム内での位 置づけを示す図である。
[図 28]図 28は、物流モデルの定式ィ匕について説明する図である。
[図 29]図 29は、本発明の生産'物流スケジュール作成装置を構成可能なコンビユー タシステムの一例を示すブロック図である。
発明を実施するための最良の形態
[0011] 以下、図面を参照しながら、本発明の生産'物流スケジュール作成装置、生産 '物 流スケジュール作成方法、コンピュータプログラム及びコンピュータ読み取り可能な 記録媒体の実施形態を説明する。
[0012] (第 1の実施形態)
図 1は、本発明の第 1の実施形態を示し、物流スケジュール作成装置の一例を説明 するブロック図である。図 1に示したように、本実施形態の物流スケジュール作成装置 は、物流シミュレータ 100、最適化計算装置 120等によって構成されている。
[0013] 上記物流シミュレータ 100は、工場を模擬した大型のシミュレータであり、事象 (シミ ユレータのイベント)毎に物を動かす離散系として構成されている。本実施形態にお いては、ペトリネットを用いて上記物流シミュレータ 100を構成し、数式モデル 110を 出力するように構成している。
[0014] また、上記物流シミュレータ 100に対応させて物流モデル (数式モデル) 110が構 成されている。本実施形態においては、生産'物流プロセスの物流状態及び物流制 約の中から、作成する物流スケジュールに関連する要素を取り込んで上記数式モデ ル 110を作成している。上記数式モデル 110には、上記物流シミュレータ 100に記載 された物流状態、物流制約の全てを盛り込んでも良いし、その一部だけを取り込んで も良い。
[0015] 上記数式モデル 110は、半導体記憶手段等により構成される数式モデル保持手段
(図示せず)によって保持されている。そして、上記数式モデル 110と最適化計算装 置 120によって最適化計算を行 、、上記物流シミュレータ 100に対する物流指示を 算出するようにしている。上記最適化計算装置 120によって行われる最適化計算は 評価関数 Sを用いて行われる。
[0016] したがって、本実施形態の物流スケジュール作成装置によれば、従来のように予め 決められたルールに基づ 、て物流指示が行われるのではなぐ上記最適化計算装 置 120により行われた最適計算の結果に基づいた物流指示を上記物流シミュレータ 100に出力することができる。これにより、そのときの事象に応じた最適な物流指示を 確実に行うことが可能となる。
[0017] また、新たな事象が発生すると、時刻管理部 101により事象が 1つ進められ、物流 シミュレータ 100から数式モデル 110及び最適化計算装置 120に対して計算を行う ようにする計算指示が出力される。上記計算指示が上記物流シミュレータ 100から与 えられると、上記最適化計算装置 120が数式モデル 110及び評価関数 Sを用いて最 適化計算を実行する。上述のように、上記物流シミュレータ 100と上記最適化計算装 置 120とを事象毎に連動させた詳細シミュレーションを一度実行することで、最適な 生産 ·物流スケジュールを作成することができる。
[0018] すなわち、本実施形態において行われるシミュレーションは、従来のような所定のル ールに基づくシミュレーションではなぐ最適計算を行った結果に基づ 、てシミュレ一 シヨンを行うようにしているので、 1回のシミュレーションを行うだけで理論的な最適解 を確実に得ることが可能となり、従来のようにシミュレーション結果を評価してシミュレ ーシヨンを何回も繰り返し行う必要がなぐシミュレーション結果を迅速に、且つ高精 度に作成することができる。したがって、スケジュールを作成する対象が大規模であ つても実用時間内に作成することが十分に可能である。上述のようにして得られたシ ミュレーシヨン結果をスケジュールとして出力する。
[0019] また、上記物流シミュレータ 100の規模が非常に大きい場合、或いは制約条件が 非常に多くて複雑な場合でも、上記物流シミュレータ 100に記載された物流状態、数 式のうち、スケジュール作成に影響が大きい重要な部分のみを上記数式モデル 110 に取り込むようにすることで、上記物流シミュレータ 100の規模を適切な範囲にして、 実用的な時間内で最適化計算を行うようにすることができる。
[0020] 上記物流シミュレータ 100は、考慮すべき物流状態、物流制約を全て記載すること ができるので、 1回のシミュレーションを行って作成されたスケジュールは現実に実行 可能となることが保証される。
[0021] 上述したように、本実施形態においては、物流シミュレータ 100と、数式モデル 110 と、最適化計算装置 120とを連動させて物流スケジュールを作成するようにしたので 、(1)シミュレーションの繰り返しをしないでスケジュールを作成することができる。また 、(2)スケジュール作成に影響が大きい重要な部分のみを上記数式モデル 110に取 り込むようにすることで計算時間を短縮することができるとともに、(3)大規模問題を 解くことが可能になる。
[0022] また、物流指示が必要な事象が発生するたびに上記物流シミュレータ 100の物流 状態及び物流制約の情報を検出し、上記検出した検出情報と予め定めた評価指標 を元に、上記最適化計算装置 120により最適化手法によって最適物流指示を計算し 、上記計算結果に基づ 、て上記物流シミュレータ 100で詳細シミュレーションを行つ てスケジュールを作成するので、(4)スケジュール精度を高くすることができるとともに 、 (5)実行可能性の検証が取れているスケジュールを作成することができる。
[0023] また、数式モデル 110を導入したので、スケジュール作成に影響が大き 、重要な部 分に変更が生じた場合でも迅速に対処することが可能となり、メンテナンス性の高い スケジュール作成装置を構築できる。
[0024] (第 2の実施形態)
図 2は、本発明の第 2の実施形態を示し、物流スケジュール作成装置の一例を説明 するブロック図である。図 2に示したように、本実施形態の物流スケジュール作成装置 は、物流シミュレータ 201を備えたシミュレーション制御部 200、最適化計算装置 21 2等によって構成されて 、る。
[0025] 物流シミュレータ 201は生産 ·物流プロセスの物流状態と物流制約を表現した生産
'物流プロセスを模擬したシミュレータ、いわば工場を模擬した大型のシミュレータで あり、本実施形態においては、ペトリネットを用いて、事象 (シミュレータのイベント)毎 に物を動かす離散系として構成されている。
[0026] また、上記物流シミュレータ 201に対応させて数学モデル (数式モデル) 211が構 成されている。本実施形態においては、生産'物流プロセスの物流状態及び物流制 約の中から、作成する物流スケジュールに関連する要素を取り込んで、下式 (ィ)に示 すような状態方程式を用いて上記数式モデル 211が作成されて ヽる。上記数式モデ ル 211は、半導体記憶手段等により構成される数式モデル保持手段(図示せず)に よって保持されている。
M(k+1) =a-M(k) +b -u(k)…(ィ)
すなわち、離散化したある時間 kにおいて各プレースに存在するトークンの数を示 す状態ベクトル、すなわち状態量を M(k)で表し、各トランジシヨン発火の有無を" 1〃 及び" 0〃で表現した操作ベクトルを u(k)で表わすと、次の時間 k+1における状態べク トル M(k+1)は、遷移行列 a、接続行列 bを用いて上式 (ィ)で表すことができる。
[0027] 最適化計算装置 212では、上記数式モデル 211に対して最適化計算処理を行!、 、フィードバックゲイン Kを算出するようにしている。上記最適化計算装置 212によつ て行われる最適化計算は、下式 (口)に示すような評価関数 Sを用いて行われる。
S=∑{M'QM+u'Ru} …(口)
評価関数 Sにおいて、 Q, Rは制御目的にあわせて設定された適当な行列であり、 Μ', u'は、それぞれ状態ベクトル Μ、操作ベクトル uの転置ベクトルである。そして、 評価関数 Sが最小となるように制御することを考えれば、
u(k) =-K-M(k)•••( )
とした状態フィードバック制御を行うフィードバックゲイン Kを最適制御理論より求める ことができる。
[0028] シミュレーション制御部 200の最適制御方策部 202では、最適化計算装置 212で 算出されるフィードバックゲイン Κと物流状態 (状態ベクトル Μ)とを用いて物流指示( 操作ベクトル u)を算出して物流シミュレータ 201に与えて、シミュレーションを進め、 新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返す。そして、これにより得られたシミュレーション結果 220から生産' 物流プロセスにおける物流スケジュールを作成する。
[0029] 以下に、第 2の実施形態の具体例を、図 3— 6を参照しながら説明する。
図 3に示したように、第 1に、生産 ·物流プロセスのペトリネットモデルとして、処理時 間を入力したプレースで各工程を表したペトリネットモデルを製品種ごとに構築する。 そして、構築したペトリネットモデルの各プレースの処理時間 Tpに比例したきざみ時 間遅れ npに従って表される遷移行列 aと接続行列 bとを算出し、これら 2つの行列 a, bを用いて状態方程式を作成する (ステップ S31)。
[0030] 第 2に、上記ステップ S31で作成した状態方程式と、設定した評価関数 Q, Rとから フィードバックゲイン行列 Kを製品種ごとに求める (ステップ S32)。
[0031] 第 3に、この求めたフィードバックゲイン行列 Kと工程内製品仕掛状態を表す状態 ベクトル M(k)
とから、製品の移動操作端に対する操作べ外ル u(k)を製品種ごとに求めたのち、仮 想的な生産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得ら れた製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間 の生産'物流プロセスのシミュレーションを実行する(ステップ S33)。
[0032] 図 4は、図 3に示したステップ S31の処理、すなわち、生産 ·物流プロセスのペトリネ ットモデルとして、処理時間を入力したプレースで各工程を表したペトリネットモデル を製品種ごとに構築し、製品種ごとに各工程でのきざみ時間遅れを表した遷移行列 a と接続行列 bとを算出するための処理手順の例を示すフローチャートである。
[0033] すなわち、まず最初に離散きざみ時間 ΔΤを入力し (ステップ S101)、次に製品種 ごとに全ての処理工程と処理時間 Tpとを入力する(ステップ S102)。そして、処理工 程ごとに処理時間 Tpをきざみ時間 ΔΤで除して整数化することにより上記各処理工 程のきざみ時間遅れ npを求め(ステップ S103、 S104)、そのきざみ時間遅れ npに 従って、全処理工程の製品種ごとの遷移行列 aと接続行列 bとを算出する (ステップ S 105)。
[0034] そして、全ての製品について遷移行列 aと接続行列 bとを算出するまでステップ S 10 6からステップ S 102の処理に戻り、以上の処理を繰り返して行う。なお、離散きざみ 時間 ΔΤは、各製品種各工程処理時間の最大公約数をもって定義するのが最も効 率的であるが、目的とする制御精度を勘案して適宜設定すればよい。
[0035] 図 5は、図 3に示したステップ S32の処理、すなわち、上記のようにして求めた遷移 行列 a及び接続行列 bから成る状態方程式と設定した評価関数 Q, Rとからフィードバ ックゲイン行列 Kを製品種ごとに求めるための処理手順の例を示すフローチャートで ある。
[0036] すなわち、まず最初に、製品種ごとにペトリネットモデルの各プレースの処理時間 T pに比例したきざみ時間遅れ npを表した遷移行列 aと接続行列 bとを最適化計算装 置 212に入力するとともに (ステップ S 201)、評価関数を表す行列 Q, Rを入力する( ステップ S202)。そして、上記入力した遷移行列 a、接続行列 b及び評価行列 Q, R 力もフィードバックゲイン行列 Kを計算する (ステップ S 203)。この計算を全ての製品 について完了するまでステップ S204からステップ S201の処理に戻り、以上の処理 を繰り返して行う。なお、全製品についてペトリネットモデルの各プレースの処理時間 Tpに比例したきざみ時間遅れ npを表した遷移行列 aと接続行列 bとをゲイン行列算 出手段 34に入力し、全製品を一括で計算するようにしてもよい。
[0037] 図 6は、図 3に示したステップ S33の処理、すなわち、上述のようにして計算したフィ ードバックゲイン行列 Kと工程内製品仕掛状態を表す状態ベクトル M(K)とから、製 品の移動操作端に対する操作べ外ル u(K)を製品種ごとに求めたのち、仮想的な生 産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得られた製品 順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間の生産 · 物流プロセスのシミュレーションを実行するための処理手順の例を示すフローチヤ一 トである。
[0038] すなわち、ペトリネットモデルの初期状態における状態ベクトル M(0)を入力するとと もに、投入予定の全製品を投入プレースに入力し、時間 kの値を 0に初期化したのち (ステップ S301)、現時点(時間: k )における全製品種の状態ベクトル M(k)を入力 する(ステップ S 302)。
[0039] そして、上述の方法を用いて計算されたフィードバックゲイン行列 Kと上記入力した 状態ベクトル M(k)とをかけて製品種ごとに操作ベクトル u(k)を計算し (ステップ S30 3)、次に移動操作端ごとに、正値で大きい操作量が得られた製品順に、移動可能な 数だけ移動操作を実行する (ステップ S 304)。
[0040] 次に、時間を進めたのち(ステップ S305)、各ステップのシミュレーションが終了した かどうかを判断し (ステップ S306)、終了していないときはステップ S302の処理に戻 る。一方、終了したときは、その結果として投入プレースより搬出されたトークン順をも つて生産スケジュールとする(ステップ S307)。
[0041] 上述したように、この第 2の実施形態においては、最適化計算を行った結果得られ た指示と、その事象における状態とに基づいた最適制御を行うので、それぞれの事 象毎に最適化計算を実行したシミュレーション結果に基づいてスケジュールを作成 することができ、しかも、そのスケジュールは生産 ·物流プロセスの制約を表現したシミ ユレータによるシミュレーション結果であるから、実際に使用可能であることを確認す ることがでさる。
[0042] これにより、上記物流シミュレータ 201の規模が非常に大きい場合、或いは制約条 件が非常に多くて複雑な場合でも、上記物流シミュレータ 201に記載された物流状 態、数式のうち、スケジュール作成に影響が大きい重要な部分のみを上記数式モデ ル 211に取り込むよう〖こすることで、上記物流シミュレータ 201の規模を適切な範囲 にして、実用的な時間内で最適化計算を行うようにすることができる。
[0043] 上記物流シミュレータ 201は、考慮すべき物流状態、物流制約を全て記載すること ができるので、 1回のシミュレーションを行って作成されたスケジュールは現実に実行 可能となることが保証される。
[0044] 上述したように、本実施形態においては、物流シミュレータ 201と、数式モデル 211 と、最適化計算装置 212とを連動させて物流スケジュールを作成するようにしたので 、(1)計算の繰り返しをしないでスケジュールを作成することができる。また、(2)スケ ジュール作成に影響が大き 、重要な部分のみを上記数式モデル 211に取り込むよう にすることで計算時間を短縮することができるとともに、 (3)大規模問題を解くことが 可會 になる。
[0045] また、物流指示が必要な事象が発生するたびに上記物流シミュレータ 201の物流 状態及び物流制約の情報を検出し、上記検出した検出情報と予め定めた評価指標 を元に、上記最適化計算装置 212により最適化手法に最適物流指示を計算し、上記 計算結果に基づいて上記物流シミュレータ 201で詳細シミュレーションを行ってスケ ジュールを作成するので、(4)スケジュール精度を高くすることができるとともに、 (5) 実行可能性の検証が取れているスケジュールを作成することができる。
[0046] また、数式モデル 211を導入したので、スケジュール作成に影響が大き 、重要な部 分に変更が生じた場合でも迅速に対処することが可能となり、メンテナンス性が高い スケジュール作成装置を構築できる。
[0047] さらに、シミュレーション制御部 200での処理はオンラインで、物流シミュレータ 201 に対応させて数学モデル (数式モデル) 211の構築や最適化計算装置 212での上 記数式モデル 211に対する最適化計算処理はオフラインで行うように分けることも可 能であり、シミュレーション制御部 200での処理負荷を軽くして処理能力を高めること ができる。
[0048] (第 3の実施形態)
図 7は、本発明の物流スケジュール作成装置の第 3の実施形態を説明するブロック 図である。図 7に示したように、本実施形態の物流スケジュール作成装置 300は、物 流シミュレータ 310、数式モデル保持装置 320、最適化計算装置 330等によって構 成されている。
[0049] 上記物流シミュレータ 310は、工場を模擬した大型のシミュレータであり、事象 (シミ ユレータのイベント)毎に物を動かす離散系として構成されている。本実施形態にお V、ては、ペトリネットを用いて上記物流シミュレータ 310を構成して 、る。
[0050] また、上記物流シミュレータ 310に対応させて物流モデル (数式モデル) 321が構 成されて数式モデル保持装置 320に保持されている。本実施形態においては、生産 •物流プロセスの物流状態及び物流制約の中から、作成する物流スケジュールに関 連する要素を取り込んで上記数式モデル 321を作成している。
[0051] 本実施形態においては、製造プロセス '搬送における製品受入計画、製品出荷計 画、在庫計画、設備使用計画、設備修理計画、設備能力、設備現況、工程現況、設 備現況、在庫現況、設備稼働'故障現況、及び操業者からの操業前提条件の全て 或いは一部を表わす入力データに基づいて、上記生産'物流計画の立案開始日時 力もあらかじめ設定された対象期間分を対象として、あらかじめ設定した精度に基づ いて、製品、移動体、設備の処理に伴う作業群の関係、制約に対して数式モデル 32 1を構築するようにしている。上記のように構築された数式モデル 321は、半導体記 憶手段等により構成される数式モデル保持装置 320によって保持されている。
[0052] 上記数式モデル 321と最適化計算装置 330によって最適化計算を行うのであるが 、本実施形態においては、上記数式モデル 321に対して評価関数 Sを用いて最適化 計算処理を行って上記物流シミュレータ 310に対する物流指示を算出するようにして いる。
[0053] そして、上記数式モデル 321を、記生産 ·物流プロセスの立案開始時間から予め設 定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを作 成するのに係わる情報を取り込んで作成し、上記作成した数式モデル 321を上記最 適化計算装置 330に与えて、上記最適化計算処理により現時点から予め設定した 期間分 (指示算出期間)について物流指示を算出して上記生産 ·物流シミュレータに 与えて、予め設定した期間(シミュレーション期間)分だけシミュレーションを実行して 予め設定した期間分 (計画確定期間)だけ物流計画を確定する。
[0054] 次に、上記確定した期間の直後の日時を新たな立案開始日時として設定して物流 計画を立案する、という処理を繰り返すことにより得られたシミュレーション結果から生 産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにして 、る。
[0055] 以下に、第 3の実施形態の具体例を、図 8を参照しながら説明する。なお、本例は、 シミュレーション期間と確定期間が同じ期間であるとした例である。
図 8に示したように、計画作成期間の 1日目は作成した生産 ·物流計画の最初の 8 時間分を確定し、 2日目以降は生産'物流計画の最初の 1日分を確定する。作成した 生産 ·物流計画の内で上記確定期間に入らな力つた部分については、その計画は 確定せずに破棄する。
[0056] すなわち、第 1ループでは 1日目の 0時一 24時の対象期間について数式モデル 32 1をもとに上記最適化計算装置 330で求解を行う。そして、最適化計算処理により得 られた求解結果を元に物流シミュレータ 310によるシミュレーションを行い、最初の 8 時間について第 1の物流計画の期間 Aを確定する。
[0057] 次に、第 2ループでは、上記確定した期間の直後の日時を新たな立案開始日時と して設定して物流計画を立案する。この例の場合は、第 1の物流計画の期間 Aとして 、 1日目の 8時まで確定したので、当初 1日目の 0時であった立案開始日を、第 2ルー プでは 1日目の 8時に更新する。
[0058] 第 2ループにおいても第 1ループと同様に、 1日目の 8時一 2日目の 8時までの 24 時間を対象期間として数式モデル 321をもとに上記最適化計算装置 330で求解を行 う。そして、最適化計算処理により得られた求解結果を元に物流シミュレータ 310によ るシミュレーションを行い、最初の 8時間について、この場合は 1日目の 8時一 16時に ついて、第 2の物流計画の期間 Bを確定する。
[0059] 次に、第 3ループにおいても、上記確定した第 2の物流計画の期間 Bの直後の日時 を新たな立案開始日時として設定して物流計画を立案する。この場合は、 1日目の 1 6時まで確定したので、第 2ループにおいては 1日目の 8時であった立案開始日を、 第 3ループでは 1日目の 16時に更新し、その後の 24時間を対象期間として数式モデ ル 321をもとに上記最適化計算装置 330で求解を行う。
[0060] そして、最適化計算処理により得られた求解結果を元に物流シミュレータ 310によ るシミュレーションを行い、最初の 8時間について物流計画を確定する。この場合は、 1日目の 16時一 24時について第 3の物流計画の期間 Cとして確定する。この結果、 次の第 4ループでは、立案開始日力 日目の 0時となる。
[0061] 第 4ループでは、数式モデル 321をもとに上記最適化計算装置 330で求解を行う 対象期間を、 2日目の 0時一 4日目の 0時までの 48時間としている。上記 48時間につ いて行った求解の結果を物流シミュレータ 310によるシミュレーションを行い、この第 4ループにぉ 、ては最初の 24時間につ 、て物流計画を確定するようにして!/、る。こ の場合、 2日目の 0時力ら 2日目の 24時(3日目の 0時)までの期間を第 4の物流計画 の期間 Dとして確定する。
[0062] 次に、第 5ループにおいては、上記確定した期間の直後の日時である、 3日目の 0 時を新たな立案開始日時として設定して、 4日目の 24時までの 48時間を対象期間と して数式モデル 321をもとに上記最適化計算装置 330で求解を行う。そして、上記 4 8時間について行った求解の結果を元にして、物流シミュレータ 310によるシミュレ一 シヨンを行う。この第 5ループにおいても、求解を行った 48時間のうち、最初の 24時 間について物流計画を確定するようにしている。この場合、 2日目の 0時力 3日目の 24時 (4日目の 0時)までについて第 5の物流計画の期間 Eを確定する。
[0063] 次に、第 6ループにおいては、 4日目の 0時から 4日目の 24時までの 24時間を対象 期間として数式モデル 321による求解を行う。この場合、対象期間の全てである 24時 間につ 、て第 6の物流計画の期間 Fとして確定するようにして 、る。本具体例では、 第 6ループが終了した時点で 4日分の生産 ·物流計画が全て作成されるので、処理 を終了する。また、物流計画の確定は、物流指示を必要とする事象が発生する毎に 行ってもよい。
[0064] 上述したように、この第 3の実施形態においては、初期値を移動させながら計算範 囲を分割するようにして 、るので、計算負荷が大きなスケジュールを計算する場合に おいても実用時間内で計算することが可能となる。したがって、計算要素が莫大な大 規模工場の生産 ·物流スケジュールを作成する場合にぉ ヽても実用時間でスケジュ ールを作成することができる。特に、本実施形態においては、最適化計算装置 330と 物流シミュレータ 310とを連動させて分割処理を行っているので、各々の事象におい て多少のずれが生じた場合でも、事象毎に微調整を行うことが可能となり、最適なス ケジュールを実用時間内で作成することができるようになる。
[0065] これにより、上記物流シミュレータ 310の規模が非常に大きい場合、或いは制約条 件が非常に多くて複雑な場合でも、上記物流シミュレータ 310に記載された物流状 態、数式のうち、スケジュール作成に影響が大きい重要な部分のみを上記数式モデ ル 321〖こ取り込むよう〖こすることで、上記数式モデル 321の規模を適切な範囲にして 、実用的な時間内で最適化計算を行うようにすることができる。
[0066] 上記物流シミュレータ 310は、考慮すべき物流状態、物流制約を全て記載すること ができるので、 1回のシミュレーションを行って作成された作成されたスケジュールは 現実に実行可能となることが保証される。
[0067] 上述したように、本実施形態においては、物流シミュレータ 310と、数式モデル 321 と、最適化計算装置 330とを連動させて物流スケジュールを作成するようにしたので 、(1)計算の繰り返しをしないでスケジュールを作成することができる。また、(2)スケ ジュール作成に影響が大きい重要な部分のみを上記数式モデル 321に取り込むよう にすることで計算時間を短縮することができるとともに、 (3)大規模問題を解くことが 可會 になる。
[0068] また、物流指示が必要な事象が発生するたびに上記物流シミュレータ 310の物流 状態及び物流制約の情報を検出し、上記検出した検出情報と予め定めた評価指標 を元に、上記最適化計算装置 330により最適化手法によって最適物流指示を計算し 、上記計算結果に基づ 、て上記物流シミュレータ 310で詳細シミュレーションを行つ てスケジュールを作成するので、(4)スケジュール精度を高くすることができるとともに 、 (5)実行可能性を検証が取れているスケジュールを作成することができる。
[0069] また、数式モデル 321を導入したので、スケジュール作成に影響が大き 、重要な部 分に変更が生じた場合でも迅速に対処することが可能となり、メンテナンス性が高い スケジュール作成装置を構築できる。
[0070] 以下に説明する第 4の実施形態一第 6の実施形態は、上述した第 2の実施形態に 関連するものである。
(第 4の実施形態)
図 2に示したように、本実施形態の物流スケジュール作成装置も、物流シミュレータ 201を備えたシミュレーション制御部 200、最適化計算装置 212等によって構成され ている。
[0071] 本実施形態では、物流シミュレータ 201は生産 ·物流プロセスの物流状態と物流制 約を表現した生産 ·物流プロセスを模擬したシミュレータ、 V、わば工場を模擬した大 型のシミュレータであり、本実施形態においては、グラフモデルを用いてシミュレータ を構築するもので、事象 (シミュレータのイベント)毎に物を動かす離散系として構成さ れている。
[0072] また、上記物流シミュレータ 201に対応させて数学モデル (数式モデル) 211が構 成されている。本実施形態においては、生産'物流プロセスの物流状態及び物流制 約の中から、作成する物流スケジュールに関連する要素を取り込んで、下式 (二)に示 すような状態方程式を用いて上記数式モデル 211が作成されて ヽる。上記数式モデ ル 211は、半導体記憶手段等により構成される数式モデル保持手段(図示せず)に よって保持されている。 M(k+1) =M(k) +b -u(k)…(二)
すなわち、離散化したある時刻 kにおいて各点に存在する要素の数を示す状態べ タトル、言い換えれば状態量を M(k)で表し、各線の発火の有無を〃 1 "及び "0 "で表 現した操作ベクトルを u(k)で表わすと、次の時刻 k+1における状態ベクトル M(k+1) は、接続行列 bを用いて上式 (二)で表わすことができる。
[0073] 最適化計算装置 212では、上記数式モデル 211に対して最適化計算処理を行!、 、フィードバックゲイン Kを算出するようにしている。上記最適化計算装置 2によって行 われる最適化計算は線形二次 (LQ)制御を利用するものであり、下式 (口)に示すよう な評価関数 Sを用いて行われる。
S=∑{M'QM+u'Ru} …(口)
評価関数 Sにおいて、 Q, Rは制御目的にあわせて設定された適当な行列であり、 Μ', u'は、それぞれ状態ベクトル Μ、操作ベクトル uの転置ベクトルである。そして、 評価関数 Sが最小となるように制御することを考えれば、
u(k) =-K-M(k)•••( )
とした状態フィードバック制御を行うフィードバックゲイン Kを最適制御理論より求める ことができる。
[0074] シミュレーション制御部 200の最適制御方策部 202では、最適化計算装置 212で 算出されるフィードバックゲイン Κと物流状態 (状態ベクトル Μ)とを用いて物流指示( 操作ベクトル u)を算出して物流シミュレータ 201に与えて、シミュレーションを進め、 新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返す。そして、これにより得られたシミュレーション結果 220から生産' 物流プロセスにおける物流スケジュールを作成する。
[0075] 以下に、第 4の実施形態の具体例を、図 9一 12を参照しながら説明する。図 9に示 したように、第 1に、生産'物流プロセスのグラフモデルとして、処理時間 Τρに比例し た数の点で各工程を表わしたグラフモデルを製品種ごとに構築する (ステップ S91)。
[0076] 第 2に、構築したグラフモデルの状態方程式と、設定した評価関数 Q, Rと力らフィ ードバックゲイン行列 Κを製品種ごとに求める (ステップ S92)。
[0077] 第 3に、この求めたフィードバックゲイン行列 Κと工程内製品仕掛状態を表す状態 ベクトル M(k)
とから、製品の移動操作端に対する操作べ外ル u(k)を製品種ごとに求めたのち、仮 想的な生産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得ら れた製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間 の生産'物流プロセスのシミュレーションを実行する(ステップ S93)。
[0078] 図 10は、図 9に示したステップ S 91の処理、すなわち、生産'物流プロセスのグラフ モデルとして、処理時間を比例した数の点で各工程を表したグラフモデルを製品種 ごとに構築するための処理手順の例を示すフローチャートである。
[0079] すなわち、まず離散きざみ時間 ΔΤを入力し (ステップ S 1001)、次に製品種ごとに 全ての処理工程と処理時間 Tpとを入力する(ステップ S 1002)。そして、処理工程ご とに処理時間 Τρをきざみ時間 ΔΤで除して整数ィ匕することにより上記各処理工程の 点の数 ηρを求め(ステップ S 1003、 S 1004)、全処理工程の点を線で連結して製品 種ごとのグラフモデルを構築する(ステップ S 1005)。
[0080] そして、全ての製品につ 、てグラフモデルを構築するまでステップ S 1006からステ ップ S1002の処理に戻り、以上の処理を繰り返して行う。なお、離散きざみ時間 ΔΤ は、各製品種各工程処理時間の最大公約数をもって定義するのが最も効率的であ るが、目的とする制御精度を勘案して適宜設定すればよい。
[0081] 図 11は、図 9に示したステップ S92の処理、すなわち、構築したグラフモデルの状 態方程式と設定した評価関数とからフィードバックゲイン行列 Κを製品種ごとに求め るための処理手順の例を示すフローチャートである。なお、全製品についてグラフモ デルの接続行列 b作成し、それを最適化計算装置 2に入力し、全製品を一括で計算 するようにしてちょい。
[0082] すなわち、まず製品種ごとにグラフモデルの状態方程式を記述する接続行列 bを最 適化計算装置 2に入力するとともに (ステップ S1101)、評価関数を表す行列 Q, Rを 入力する (ステップ S 1102)。そして、上記入力した接続行列 b及び評価行列 Q, Rか らフィードバックゲイン行列 Kを計算する (ステップ S1103)。この計算を全ての製品 について完了するまでステップ S1104からステップ S1101の処理に戻り、以上の処 理を繰り返して行う。 [0083] 図 12は、図 9に示したステップ S93の処理、すなわち、上述のようにして計算したフ イードバックゲイン行列 Kと工程内製品仕掛状態を表す状態ベクトル M(K)とから、製 品の移動操作端に対する操作べ外ル u(K)を製品種ごとに求めたのち、仮想的な生 産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得られた製品 順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間の生産 · 物流プロセスのシミュレーションを実行するための処理手順の例を示すフローチヤ一 トである。
[0084] すなわち、まずグラフモデルの初期状態における状態ベクトル M(0)を入力するとと もに、投入予定の全製品(要素)を投入点に入力し、時刻 kの値を 0に初期化したの ち(ステップ S1201)、現時点(時刻: k )における全製品種の状態ベクトル M(k)を入 力する(ステップ S 1202)。
[0085] そして、上述の方法を用いて計算されたフィードバックゲイン行列 Kと上記入力した 状態ベクトル M(k)とをかけて製品種ごとに操作ベクトル u(k)を計算し (ステップ S12 03)、次に移動操作端ごとに、正値で大きい操作量が得られた製品順に、移動可能 な数だけ移動操作を実行する (ステップ S 1204)。
[0086] 次に、時刻を進めたのち(ステップ S1205)、各ステップのシミュレーションが終了し たかどうかを判断し (ステップ S 1206)、終了していないときはステップ S1202の処理 に戻る。一方、終了したときは、そのシミュレーション結果をもって生産スケジュールと する(ステップ S 1207)。
[0087] 上述したように、本実施形態にお!ヽては、最適化計算を行った結果得られた指示と 、その事象における状態とに基づいた最適制御を行うので、それぞれの事象毎に最 適化計算を実行したシミュレーション結果に基づいてスケジュールを作成することが でき、し力も、そのスケジュールは生産'物流プロセスの制約を表現したシミュレータ によるシミュレーション結果であるから、実際に使用可能であることを確認することが できる。
[0088] これにより、上記物流シミュレータ 201の規模が非常に大きい場合、或いは制約条 件が非常に多くて複雑な場合でも、上記物流シミュレータ 201に記載された物流状 態、数式のうち、スケジュール作成に影響が大きい重要な部分のみを上記数式モデ ル 211に取り込むよう〖こすることで、上記物流シミュレータ 201の規模を適切な範囲 にして、実用的な時間内で最適化計算を行うようにすることができる。
[0089] 上記物流シミュレータ 201は、考慮すべき物流状態、物流制約を全て記載すること ができるので、 1回のシミュレーションを行って作成されたスケジュールは現実に実行 可能となることが保証される。
[0090] 上述したように、本実施形態においては、物流シミュレータ 201と、数式モデル 211 と、最適化計算装置 212とを連動させて物流スケジュールを作成するようにしたので 、(1)計算の繰り返しをしないでスケジュールを作成することができる。また、(2)スケ ジュール作成に影響が大き 、重要な部分のみを上記数式モデル 211に取り込むよう にすることで計算時間を短縮することができるとともに、 (3)大規模問題を解くことが 可會 になる。
[0091] また、物流指示が必要な事象が発生するたびに上記物流シミュレータ 201の物流 状態及び物流制約の情報を検出し、上記検出した検出情報と予め定めた評価指標 を元に、上記最適化計算装置 212により最適化手法に最適物流指示を計算し、上記 計算結果に基づいて上記物流シミュレータ 201で詳細シミュレーションを行ってスケ ジュールを作成するので、(4)スケジュール精度を高くすることができるとともに、 (5) 実行可能性の検証が取れているスケジュールを作成することができる。
[0092] また、数式モデル 211を導入したので、スケジュール作成に影響が大き 、重要な部 分に変更が生じた場合でも迅速に対処することが可能となり、メンテナンス性が高い スケジュール作成装置を構築できる。
[0093] さらに、シミュレーション制御部 200での処理はオンラインで、物流シミュレータ 201 に対応させて数学モデル (数式モデル) 211の構築や最適化計算装置 212での上 記数式モデル 211に対する最適化計算処理はオフラインで行うように分けることも可 能であり、シミュレーション制御部 200での処理負荷を軽くして処理能力を高めること ができる。
[0094] なお、本実施形態では、一般的なグラフ理論に基づく例を説明したが、ペトリネット モデルやその他のグラフモデルに本発明を適用することも可能である。ペトリネットモ デルでは、上述したグラフモデルにおける点はプレースで表現され、線はトランジショ ンで表現される。トランジシヨンは、プレースからプレースへ製品すなわちトークンを移 動させる移動操作端である。
[0095] 一般に、ペトリネットモデルでは、 1つのトランジシヨンに複数のプレースからアーク が入力して 、る場合には、それらのプレースの全てにトークンが存在して ヽな 、とトラ ンジシヨンの操作ができない。これをトランジシヨンの発火則と言う。また、 1つのトラン ジシヨン力も複数のプレースにアークが出力している場合には、それらのプレースの 全てにトークンが出力される。なお、アークとは、トランジシヨンからプレース、或いは プレースからトランジシヨンへトークンが移動する方向を示すものであり、その数は移 動するトークンの数を示している。また、トランジシヨンを操作することを、トランジシヨン を発火させると言う。
[0096] また、グラフモデルでは、各工程内における処理容量をソフトウェア上で制御してい た力 ペトリネットモデルでは、各工程内に設けられている仮想プレースに初期設定 された容量設定用仮想トークンの数により、各処理工程で同時に処理できる製品の 数を制限している。
[0097] このような特徴を有するペトリネットモデルに本発明を適用する場合も、一連の動作 は上述したグラフモデルにおける動作と同様である。
[0098] (第 5の実施形態)
本実施形態の物流スケジュール作成装置も、図 2に示したように、物流シミュレータ
201を備えたシミュレーション制御部 200、最適化計算装置 212等によって構成され ている。
[0099] 本実施形態では、物流シミュレータ 201は生産 ·物流プロセスの物流状態と物流制 約を表現した生産 ·物流プロセスを模擬したシミュレータ、 V、わば工場を模擬した大 型のシミュレータであり、本実施形態においては、ペトリネットモデルを用いてシミュレ ータを構築するもので、事象 (シミュレータのイベント)毎に物を動かす離散系として 構成されている。
[0100] また、上記物流シミュレータ 201に対応させて数学モデル (数式モデル) 211が構 成されている。本実施形態においては、生産'物流プロセスの物流状態及び物流制 約の中から、作成する物流スケジュールに関連する要素を取り込んで、下式 (二)に示 すような状態方程式を用いて上記数式モデル 211が作成されて ヽる。上記数式モデ ル 211は、半導体記憶手段等により構成される数式モデル保持手段(図示せず)に よって保持されている。
M(k+1) =M(k) +b -u(k)…(二)
すなわち、離散化したある時刻 kにおいて各プレースでのトークンの有無を示す状 態ベクトル、言い換えれば状態量を M(k)で表し、各トランジシヨン発火の有無を" 1〃 及び" 0〃で表現した操作ベクトルを u(k)で表わすと、次の時刻 k+1における状態べク トル M(k+1)は、接続行列 bを用いて上式 (二)で表わすことができる。
[0101] ここで、図 13にペトリネットモデルの一例を示す。ペトリネットモデルは、プレース(〇 印)(図示例では pi— p6)、トランジシヨン( I印)(図示例では tl一 t5)、アーク (→印) 、トークン('印)の 4要素で表現される。この場合に、 1つのトランジシヨンに複数のプ レース力もアークが入力して 、る場合には、それらのプレースの全てに製品すなわち トークンが存在して ヽな 、とトランジシヨンの操作ができな ヽ(トランジシヨンの発火貝 IJ) 。また、 1つのトランジシヨン力も複数のプレースにアークが出力している場合には、そ れらのプレースの全てにトークンが出力される。なお、アークとは、トランジシヨンから プレース、或いは、プレースからトランジシヨンへトークンが移動する方向を示すもの であり、その数は移動するトークンの数を示している。また、トランジシヨンを操作する ことを、トランジシヨンを発火させると言う。
[0102] 図 13に示すようにトランジシヨン tlを発火させる場合を例にすると、離散化したある 時刻 k
にお 、て各プレース pi— p6でのトークン tl一 t5の有無を示す状態ベクトル、言!、換え れば状態量を M(k)で表し、各トランジシヨン発火の有無を〃 1 "及び" 0〃で表現した操 作ベクトルを u(k)で表わすと、次の時刻 k+1における状態ベクトル M(k+1)は、接続 行列 bを用いて下式(1)で表わすことができる。
[0103] [数 1]
Figure imgf000031_0001
[0104] 最適化計算装置 212では、上記数式モデル 211に対して最適化計算処理を行!、 、フィードバックゲイン Kを算出するようにしている。上記最適化計算装置 212によつ て行われる最適化計算は線形二次 (LQ)制御を利用するものであり、下式 (口)に示す ような評価関数 Sを用いて行われる。
S=∑{M'QM+u'Ru} …(口)
評価関数 Sにおいて、 Q, Rは制御目的にあわせて設定された適当な行列であり、 Μ', u'は、それぞれ状態ベクトル Μ、操作ベクトル uの転置ベクトルである。そして、 評価関数 Sが最小となるように制御することを考えれば、
u(k) =-K-M(k)•••( )
とした状態フィードバック制御を行うフィードバックゲイン Kを最適制御理論より求める ことができる。
[0105] シミュレーション制御部 200の最適制御方策部 202では、最適化計算装置 212で 算出されるフィードバックゲイン Κと物流状態 (状態ベクトル Μ)とを用いて物流指示( 操作ベクトル u)を算出して物流シミュレータ 201に与えて、シミュレーションを進め、 新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返す。そして、これにより得られたシミュレーション結果 220から生産' 物流プロセスにおける物流スケジュールを作成する。
[0106] 以下に、第 5の実施形態の具体例を、図 14一 17を参照しながら説明する。図 14に 示したように、第 1に、生産 ·物流プロセスのペトリネットモデルとして、処理時間 Τρに 比例した数のプレースで各工程を表したペトリネットモデルを製品種ごとに構築する( ステップ S1401)。 [0107] 第 2に、構築したペトリネットモデルの状態方程式と、設定した評価関数とからフィー ドバックゲイン行列 Kを製品種ごとに求める (ステップ S1402)。
[0108] 第 3に、この求めたフィードバックゲイン行列 Kと工程内製品仕掛状態を表す状態 ベクトル M(k)
とから、製品の移動操作端に対する操作べ外ル u(k)を製品種ごとに求めたのち、仮 想的な生産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得ら れた製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間 の生産 ·物流プロセスのシミュレーションを実行する(ステップ S 1403)。
[0109] 図 15は、図 14に示したステップ S 1401の処理、すなわち、生産'物流プロセスのぺ トリネットモデルとして、処理時間 Tpに比例した数のプレースで各工程を表したペトリ ネットモデルを製品種ごとに構築するための処理手順の例を示すフローチャートであ る。
[0110] すなわち、まず離散きざみ時間 ΔΤを入力し (ステップ S1501)、次に製品種ごとに 全ての処理工程と処理時間 Tpとを入力する(ステップ SI 502)。そして、処理工程ご とに処理時間 Tpをきざみ時間 ΔΤで除して整数ィ匕することにより各処理工程のプレ ース数 npを求め(ステップ S1503、 SI 504)、全処理工程のプレースを連結してぺト リネットモデルを製品種ごとに構築する (ステップ S 1505)。
[0111] そして、全ての製品についてペトリネットモデルを構築するまでステップ S 1506から ステップ S 1502の処理に戻り、以上の処理を繰り返して行う。なお、離散きざみ時間 ΔΤは、各製品種各工程処理時間の最大公約数をもって定義するのが最も効率的 であるが、 目的とする制御精度を勘案して適宜設定すればよい。
[0112] 図 16は、図 14に示したステップ S 1402の処理、すなわち、構築したペトリネットモ デルの状態方程式と設定した評価関数とからフィードバックゲイン行列 Kを製品種ご とに求めるための処理手順の例を示すフローチャートである。
[0113] すなわち、まず製品種ごとにペトリネットモデルの状態方程式を記述する接続行列 bを最適化計算装置 2に入力するとともに (ステップ S1601)、評価関数を表す行列 Q , Rを入力する (ステップ S1602)。そして、上記入力した接続行列 b及び評価行列 Q , Rからフィードバックゲイン行列 Kを計算する(ステップ S 1603)。この計算を全ての 製品について完了するまでステップ S1604からステップ S1601の処理に戻り、以上 の処理を繰り返して行う。なお、全製品についてペトリネットモデルの接続行列 bを最 適化計算装置 212に入力し、全製品を一括で計算するようにしてもよい。
[0114] 図 17は、図 14に示したステップ S 1403の処理、すなわち、上述のようにして計算し たフィードバックゲイン行列 Kと工程内製品仕掛状態を表す状態ベクトル M(K)とから 、製品の移動操作端に対する操作ベクトル u(K)を製品種ごとに求めたのち、仮想的 な生産'物流プロセス内の各移動操作端に対して、正値で大きい操作量が得られた 製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間の生 産'物流プロセスのシミュレーションを実行するための処理手順の例を示すフローチ ヤートである。
[0115] すなわち、まずペトリネットモデルの初期状態における状態ベクトル M(0)を入力す るとともに、投入予定の全製品を投入プレースに入力し、時刻 kの値を 0に初期化した のち (ステップ S1701)、現時点(時刻: k )における全製品種の状態ベクトル M(k)を 入力する(ステップ S 1702)。
[0116] そして、上述の方法を用いて計算されたフィードバックゲイン行列 Kと上記入力した 状態ベクトル M(k)とをかけて製品種ごとに操作ベクトル u(k)を計算し (ステップ S17 03)、次に移動操作端ごとに、正値で大きい操作量が得られた製品順に、移動可能 な数だけ移動操作を実行する (ステップ S 1704)。
[0117] 次に、時刻を進めたのち(ステップ S1705)、各ステップのシミュレーションが終了し たかどうかを判断し (ステップ S 1706)、終了していないときはステップ S1702の処理 に戻る。一方、終了したときは、そのシミュレーション結果をもって生産スケジュールと する(ステップ S 1707)。
[0118] 上述したように、本実施形態においては、上述した第 4の実施形態の効果に加えて 、工程内製品仕掛状態を表わす状態ベクトルを各プレースにおける製品の有無に従 つて表現するようにしたので、フィードバックゲイン行例と上記状態ベクトル力も算出さ れる操作ベクトルの各要素を、フォードバックゲイン行列の各要素の大きさをそのまま 反映したものとすることができ、同じプレース内に存在する複数種類の製品のうち、ゲ インがより大きいものを常に優先して処理するようにすることができ、その結果、各処 理工程での総処理時間を最短にする最適なスケジュールを簡単に作成することがで きる。
[0119] また、状態ベクトルを表現する方法として、各プレースにおける製品の有無に従う手 法と、各プレースに存在する製品の数に従う手法とのいずれかを選択できるようにす れば、各プレースにおける製品の有無に従って状態ベクトルを表現する場合には、 上述のように総処理時間を最短にするスケジュールを簡単に作成することができる一 方、各プレースに存在する製品の数に従って状態ベクトルを表現する場合には、 1つ のプレース内にある製品が溜まってしまうという不都合を防止しつつ総処理時間をあ る程度短くするスケジュールを簡単に作成することができる。
[0120] (第 6の実施形態)
本実施形態の物流スケジュール作成装置も、図 2に示したように、物流シミュレータ 201を備えたシミュレーション制御部 200、最適化計算装置 212等によって構成され ている。
[0121] 本実施形態では、物流シミュレータ 201は生産 ·物流プロセスの物流状態と物流制 約を表現した生産 ·物流プロセスを模擬したシミュレータ、 V、わば工場を模擬した大 型のシミュレータであり、本実施形態においては、ペトリネットモデルを用いてシミュレ ータを構築するもので、事象 (シミュレータのイベント)毎に物を動かす離散系として 構成されている。
[0122] また、上記物流シミュレータ 201に対応させて数学モデル (数式モデル) 211が構 成されている。本実施形態においては、生産'物流プロセスの物流状態及び物流制 約の中から、作成する物流スケジュールに関連する要素を取り込んで、下式 (ィ)に示 すような状態方程式を用いて上記数式モデル 211が作成されて ヽる。上記数式モデ ル 211は、半導体記憶手段等により構成される数式モデル保持手段(図示せず)に よって保持されている。
M(k+1) =a-M(k) +b -u(k)…(ィ)
すなわち、離散化したある時刻 kにおいて各プレースに存在するトークンの数を示 す状態ベクトル、言い換えれば状態量を M(k)で表し、各トランジシヨン発火の有無を "1"及び" 0〃で表現した操作ベクトルを u(k)で表わすと、次の時刻 k+1における状態 ベクトル M(k+1)は、遷移行列 a、接続行列 bを用いて上式 (ィ)で表わすことができる。
[0123] 最適化計算装置 212では、上記数式モデル 211に対して最適化計算処理を行い 、フィードバックゲイン Kを算出するようにしている。上記最適化計算装置 212によつ て行われる最適化計算は線形二次 (LQ)制御を利用するものであり、下式 (口)に示す ような評価関数 Sを用いて行われる。
S=∑{M'QM+u'Ru} …(口)
評価関数 Sにおいて、 Q, Rは制御目的にあわせて設定された適当な行列であり、 Μ', u'は、それぞれ状態ベクトル Μ、操作ベクトル uの転置ベクトルである。そして、 評価関数 Sが最小となるように制御することを考えれば、
u(k) =-K-M(k)•••( )
とした状態フィードバック制御を行うフィードバックゲイン Kを最適制御理論より求める ことができる。
[0124] シミュレーション制御部 200の最適制御方策部 202では、最適化計算装置 212で 算出されるフィードバックゲイン Κと物流状態 (状態ベクトル Μ)とを用いて物流指示( 操作ベクトル u)を算出して物流シミュレータ 201に与えて、シミュレーションを進め、 新たな物流状態を得て、この新たな物流状態をもとに新たな物流指示を算出すると いう処理を繰り返す。そして、これにより得られたシミュレーション結果 220から生産' 物流プロセスにおける物流スケジュールを作成する。
[0125] 以下に、第 6の実施形態の具体例を、図 18— 21を参照しながら説明する。図 18に 示したように、第 1に、生産 ·物流プロセスのペトリネットモデルとして、処理時間 Τρを 入力したプレースで各工程を表したペトリネットモデルを製品種ごとに構築する。そし て、構築したペトリネットモデルの各プレースの処理時間 Τρに比例したきざみ時間遅 れ ηρに従って表される遷移行列 aと接続行列 bとを算出し、これら 2つの行列 a, bを 用いて状態方程式を作成する (ステップ S1801)。
[0126] 第 2に、上記ステップ S1801で作成した状態方程式と、設定した評価関数とからフ イードバックゲイン行列 Kを製品種ごとに求める (ステップ S 1802)。
[0127] 第 3に、この求めたフィードバックゲイン行列 Kと工程内製品仕掛状態を表す状態 ベクトル M(k) とから、製品の移動操作端に対する操作べ外ル U(k)を製品種ごとに求めたのち、仮 想的な生産 ·物流プロセス内の各移動操作端に対して、正値で大きい操作量が得ら れた製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間 の生産 ·物流プロセスのシミュレーションを実行する(ステップ S 1803)。
[0128] 図 19は、図 18に示したステップ S 1801の処理、すなわち、生産'物流プロセスのぺ トリネットモデルとして、処理時間を入力したプレースで各工程を表したペトリネットモ デルを製品種ごとに構築し、製品種ごとに各工程でのきざみ時間遅れを表した遷移 行列 aと接続行列 bとを算出するための処理手順の例を示すフローチャートである。
[0129] すなわち、まず離散きざみ時間 ΔΤを入力し (ステップ S1901)、次に製品種ごとに 全ての処理工程と処理時間 Tpとを入力する(ステップ SI 902)。そして、処理工程ご とに処理時間 Tpをきざみ時間 ΔΤで除して整数ィ匕することにより上記各処理工程の きざみ時間遅れ npを求め(ステップ S1903、 S1904)、そのきざみ時間遅れ npに従 つて、全処理工程の製品種ごとの遷移行列 aと接続行列 bとを算出する (ステップ S 19 05)。
[0130] そして、全ての製品について遷移行列 aと接続行列 bとを算出するまでステップ S 19 06からステップ S 1902の処理に戻り、以上の処理を繰り返して行う。なお、離散きざ み時間 ΔΤは、各製品種各工程処理時間の最大公約数をもって定義するのが最も 効率的であるが、目的とする制御精度を勘案して適宜設定すればよい。
[0131] 図 20は、図 18に示したステップ S1802の処理、すなわち、上記のようにして求めた 遷移行列 a及び接続行列 bから成る状態方程式と設定した評価関数とからフィードバ ックゲイン行列 Kを製品種ごとに求めるための処理手順の例を示すフローチャートで ある。
[0132] すなわち、まず製品種ごとにペトリネットモデルの各プレースの処理時間 Tpに比例 したきざみ時間遅れ npを表した遷移行列 aと接続行列 bとを最適化計算装置 212に 入力するとともに (ステップ S2001)、評価関数を表す行列 Q, Rを入力する (ステップ S2002)。そして、上記入力した遷移行列 a、接続行列 b及び評価行列 Q, Rからフィ ードバックゲイン行列 Kを計算する (ステップ S 2003)。この計算を全ての製品につい て完了するまでステップ S2004力もステップ S2001の処理に戻り、以上の処理を繰り 返して行う。なお、全製品についてペトリネットモデルの各プレースの処理時間 Tpに 比例したきざみ時間遅れ npを表した遷移行列 aと接続行列 bとを最適化計算装置 21 2に入力し、全製品を一括で計算するようにしてもよい。
[0133] 図 21は、図 18に示したステップ S1803の処理、すなわち、上述のようにして計算し たフィードバックゲイン行列 Kと工程内製品仕掛状態を表す状態ベクトル M(K)とから 、製品の移動操作端に対する操作ベクトル u(K)を製品種ごとに求めたのち、仮想的 な生産'物流プロセス内の各移動操作端に対して、正値で大きい操作量が得られた 製品順に移動可能な数だけ移動操作を順次行うという方法を用いて、所定期間の生 産'物流プロセスのシミュレーションを実行するための処理手順の例を示すフローチ ヤートである。
[0134] すなわち、まずペトリネットモデルの初期状態における状態ベクトル M(0)を入力す るとともに、投入予定の全製品を投入プレースに入力し、時刻 kの値を 0に初期化し たのち (ステップ S2101)、現時点(時刻: k )における全製品種の状態ベクトル M(k) を入力する(ステップ S2102)。
[0135] そして、上述の方法を用いて計算されたフィードバックゲイン行列 Kと上記入力した 状態ベクトル M(k)とをかけて製品種ごとに操作ベクトル u(k)を計算し (ステップ S21 03)、次に移動操作端ごとに、正値で大きい操作量が得られた製品順に、移動可能 な数だけ移動操作を実行する (ステップ S2104)。
[0136] 次に、時刻を進めたのち(ステップ S2105)、各ステップのシミュレーションが終了し たかどうかを判断し (ステップ S2106)、終了していないときはステップ S2102の処理 に戻る。一方、終了したときは、そのシミュレーション結果をもって生産スケジュールと する(ステップ S2107)。
[0137] 次に、第 6の実施形態の作用を以下に示す例に即して説明する。ここでは、異なる 複数の工程で複数の製品を処理して製造するプロセスの例として、 2種類の製品、す なわち製品 Aと製品 Bとを 4つの工程で処理して製造する場合を考え、各製品に対す る各工程の処理時間が表 1のように与えられて 、るものとする。
[0138] [表 1] 工程 1 工程 2 工程 3 工程 4 処理時間 (分) 10 15 5 10
製品 A
時間きざみ 2 3 1 2
遅れ数 処理時間 (分) 10 10 —- 10
製品 B
時間きざみ 2
遅れ数 2 0 2
[0139] また、離散きざみ時間 ΔΤを 5分として両製品 A, Bを製造するプロセスのペトリネッ トモデルを示したもの力 図 22である。上記した表 1は、処理時間を離散きざみ時間 ΔΤ( = 5分)で除して得られた各工程 1、 2、 3、 4のきざみ時間遅れを表している。こ の例では、製品 Αについては工程 1、 2、 3、 4がそれぞれ 2、 3、 1、 2のきざみ時間遅 れを有し、製品 Bについては工程 1、 2、 3、 4がそれぞれ 2、 2、 0、 2のきざみ時間遅 れを有している。この例において製品 A, Bは、移動操作端 T1 (以降、移動操作端を トランジシヨンとも称する)を経由して投入され、トランジシヨン T6を経由して次工程或 いは倉庫等へ搬出される。すなわち、製品 Aはプレース P1,P2,P3,P4を通り、製品 B はプレース P1,P2,P4を通る。
[0140] 上述のように、離散化したある時刻 kにおいて各プレースに存在するトークンの数を 示す状態ベクトル、言い換えれば状態量を M(k)で表し、各トランジシヨン発火の有無 を" 1 "及び" 0〃で表現した操作ベクトルを u(k)で表わすと、次の時刻 k+1における状 態ベクトル M(k+1)は、遷移行列 a、接続行列 bを用いて上式 (ィ)で表わすことができ る。状態方程式 (ィ)上の移動操作端 (トランジシヨン)と、実プロセスの移動操作端と は一致している。すなわち、操作ベクトル u(k)の信号は、実プロセスの操作信号であ る。
[0141] 例えば、製品 Aに対してプレース P1,P2,P3,P4に存在するトークンの数を並べたベ タトルを M、トランジシヨン T1,T2,T3,T5,T6の発火の有無を〃 1 "及び〃0 "で表した操作 ベクトルを uとすれば、以下の式(2)、 (3)で示される遷移行列 aと接続行列 bとを用い て、ベクトル M(k)力もベクトル M(k+1)への状態変化を表現することができる。
[0142] [数 2]
Figure imgf000039_0001
1 2 3 5 6
1 0; 0 0 ϋ ) 1 1
0 - lj 0 0 0 1 2
0 I 0: 0 0 2 1
0 0 0; ϋ 0 22
0 0 - 1: 0 0 23
0 0 1 - 1 () 3 1
0 0 0 ; 1 0 4 1
0 0 0 io - 1 A 2
[0143] ただし、上記式(2)において、列方向の 1桁の番号はプレース番号を示し、行方向 の 2桁の番号のうち、左側の数字はプレース番号を示し、右側の数字は各プレースに 存在する状態 (きざみ時間遅れ)の番号を示している。また、上記式(3)において、列 方向の 1桁の番号はトランジシヨン番号を示し、行方向の 2桁の番号のうち、左側の数 字はプレース番号を示し、右側の数字は各プレースに存在する状態 (きざみ時間遅 れ)の番号を示している。
[0144] 上記遷移行列 aを表現するときの一般形を、次の式 (4)に示す。この式 (4)から明ら かなように、ある工程に存在する状態数力 のとき、その工程に関する部分の小行列 は、式 (4)中に示したような n X nの正方行列で表される。そして、全工程の遷移を表 した遷移行列 aは、上記各工程に関する小行列を行方向及び列方向の番号に対応 した適当な位置に配置するとともに、その他の要素を全て" 0"とすることによって表さ れる。
[0145] [数 3]
a 二 o o o o o 1 1 o ϋ o o o 1:■ 表現
Figure imgf000040_0001
[0146] また、上記接続行列 bを表現するときの一般形を、次の式(5)に示す。すなわち、あ る工程に存在する状態数力 ¾のとき、その工程に関する部分の小行列は、式(5)に 示すような nX 2の行列で表される。(1,1)要素の数〃 1 "は、該当するプレースにトーク ンが入力されることを示し、 (n,2)要素の数'し 1 "は、該当するプレースからトークンが 出力されることを示している。そして、全工程に関する接続行列 bは、上記各工程の 小行列を行方向及び列方向の番号に対応した適当な位置に配置するとともに、その 他の要素を全て" 0"とすることによって表される。
[0147] [数 4]
η時間遅れの表現 )
Figure imgf000040_0002
[0148] 製品 Aにつ 、て上記式(2)、 (3)で示される遷移行列 aと接続行列 bとを用いてベタ トル M(k)力 ベクトル M(k+1)への状態変化を表現したのと同様のことが製品 Bにつ いても表現できる。
[0149] このように、製品ごとに、処理時間を入力したプレースを持つペトリネットモデルを用 V、、製品ごとに各工程でのきざみ時間遅れを表した遷移行列 aと接続行列 bとで各ェ 程を表すことにより、離散時刻 k力 ^進むたびに複数の離散きざみ時間を要するプレ ースでトークンが移動していくことを表現でき、その結果、離散時間系の最適制御理 論を適用できる形にすることができる。
[0150] この場合、 1つのプレースに複数単位の処理時間(離散きざみ時間)を割り当てるよ うにしてペトリネットモデルを構築し、遷移行列 a及び接続行列 bの 2つの行列式だけ で物流モデルを表現できるようにしているので、 1つの離散きざみ時間ごとに 1つのプ レースを設けた制御用のペトリネットモデルを再構築しなくても済む。また、上記 1つ の離散きざみ時間ごとにプレースを設けたペトリネットモデルに比べて制御端の数を 少なくすることができ、実際のプロセスに使いやすいモデルとすることができる。
[0151] これにより、制御の目的にあわせて適当な行列 Q, Rを設定して、評価関数 (口)が 最小になるように制御することを考えれば、上式 (ハ)とした状態フィードバック制御を 行うフィードバックゲイン行列 Kを最適制御理論より求めることができる。フィードバック ゲイン行列 Kの計算法としては、例えば (安藤和昭、他編著「数値解析手法による制 御系設計」計測自動制御学会発行、 ρρ.126-130、平成 5年初版第 2刷)に記載され たいくつかの方法がある。
[0152] また、評価行列 Q, Rは、それぞれプレースの数及びトランジシヨンの数の次元を有 する正方行列で、それぞれ制御の過渡特性とトランジシヨン操作の入力エネルギーと を評価関数として表すためのものであり、制御目的に応じて適宜設定すればよい。例 えば、過渡特性を重視する場合は、大きな数値をもつ行列 Qを設定すればよい。また 、操作に要する入力エネルギーを小さく抑えたい場合は、大きな数値をもつ行列 Rを 設定すればよい。
[0153] 次に、第 6の一実施形態の具体例を、モデル構築、制御則構築、シミュレーション、 実施結果例に分けて以下に説明する。 〔モデル構築〕
図 23は、複数工程よりなる製造プロセスのペトリネットモデルの一例を示したもので あり、離散きざみ時間 ΔΤは 5分に設定してある。この製造プロセスは、工程 1、 2、 3、 4力もなる前処理工程と工程 5、 6からなる後処理工程とから構成され、プレース P1 ( 投入プレース)で示した前処理工程入側バッファと、プレース P6,P8で示した後処理 工程入側バッファと、プレース P10で示した搬出用プレースとを具備している。
[0154] この製造プロセスでは、前処理工程 1又は 2で処理された製品は後処理工程 5で処 理され、また、前処理工程 3又は 4で処理された製品は後処理工程 6で処理されるが 、製品によっては前処理工程 1一 4と後処理工程 5— 6の複数の組合せのいずれか で処理し得るものがあるため、全体で 15の製品種類がある。次の表 2は、それぞれの 製品種がどの前処理工程と後処理工程との組合せで処理可能かを示したものである
[0155] [表 2]
Figure imgf000042_0001
[0156] 図 23において、プレース P11,P12,P13,P14,P15,P16は、それぞれ工程 1一 6の処理 容量を制限するための仮想プレースであり、これらの仮想プレースに初期設定された 容量設定用仮想トークンの数により、各処理工程で同時に処理できる製品の数を制 限している。例えば、工程 1は、プレース P2力も構成されるとともに、仮想プレース P11 に初期状態として 1個の容量設定用仮想トークンが置かれることにより、この工程 1で の処理容量が 1に設定されて!、る。
[0157] すなわち、工程 1に製品がな力つた状態からトランジシヨン T2を経由して製品が入 力されるときに、仮想プレース P11に置かれた容量設定用仮想トークンが同時に入 力され、製品を表すトークンがプレース P1力もプレース P2に移動する。その後、そのト 一クンがトランジシヨン T3を経由してプレース P6に移動すると同時に容量設定用仮想 トークンがプレース P11に復帰して、再び工程 1が待ち状態になる。
[0158] このように、複数のプレースで表される工程に対して仮想プレースを適宜利用する ことにより、各工程の処理容量を設定して製造プロセスのペトリネットモデルを構築す ることは周知の手法である。
[0159] なお、この図 23の例は、工程 1から工程 6までの仮想プレース
P11,P12,P13,P14,P15,P16
の容量が全て 1のプロセスである。また、製品入力用のプレース P1と製品出力用のプ レース P10は最大 200個の製品を収容可能で、プレース P6,P8のバッファはともに最 大 20個の製品を収容可能と設定してある。
[0160] 図 24に実線で示された部分は、表 2に記載した製品種 No.lに対するペトリネットモ デルを示したものである。同様に、全ての製品種に対してもペトリネットモデルを構築 することにより、図 18のフローチャートに示したモデル構築が行われる。
[0161] 〔制御則構築〕
引き続き製品種 No.lを例にとり、フィードバックゲイン行列 Kを求める過程を説明す る。式 (ィ)の状態方程式における遷移行列 aは、図 24に示された製品種 No.lのペトリ ネットモデルに対しては、次の式(6)で表現されるサイズ 8 X 8の行列として求められ る。ただし、式(6)において、列方向の番号はプレース番号を示し、行方向の番号の うち、下 1桁以外の数字はプレース番号を示し、下 1桁の数字は各プレースに存在す る状態 (きざみ時間遅れ)の番号を示して 、る。
[0162] [数 5]
Figure imgf000044_0001
[0163] また、式 (ィ)の状態方程式における接続行列 bは、図 24に示された製品種 No.1の ペトリネットモデルに対しては、次の式(7)で表現されるサイズ 8 X 6の行列として求め られる。ただし、式(7)において、列方向の番号はトランジシヨン番号を示し、行方向 の番号のうち、下 1桁以外の数字はプレース番号を示し、下 1桁の数字は各プレース に存在する状態の番号を示して!/ヽる。
[0164] [数 6]
1 2 3 1011 14
1 -1 0 0 .0 0 11
0 1 0 0 0 ϋ 21
0 0 -1 0 0 0 22
0 0 1 -\ 0 0 61 (7)
0 () 0 し 0 () 71
(I 0 0 ;0 0 io Ί1
0 0 0 :() Λ : 0 73
0 0 0 0 1 -1: 101
[0165] また、式 (口)で表される評価関数中における行列 Q, Rは、上述したように、それぞ れ各工程のきざみ時間遅れ数及びトランジシヨンの数の次元を有する正方行列であ るから、それぞれペトリネットモデルの製品種ごとに設定される。
[0166] 製品種 No.lに対しては、この製造プロセスにおける標準的な値として、
Q = 20X1(8) ·'·(8)
及び
R=I(6) ·'·(9) を設定した。ただし、式 (8)、(9)において I(n)は n次の単位行列である。
[0167] このようにして遷移行列 a及び接続行列 bと、評価関数を定義する行列 Q, Rとが定 まれば、離散時間系における最適制御理論によりフィードバックゲイン行列 Kを求め ることがでさる。
[0168] すなわち、代数リツカチ方程式(10)
o
P=ATPA-ATPB(BTPB+R)_1BTPA+Q - · -(10)
ο
ο
を満足する解 Pを求めれば、フィードバックゲイン行列 Kは、
K=-(BTPB+R)_1BTPA
•••(11)
により計算することができる。ここで、(BTPB+R)— 1は行列 (BTPB+R)の逆行列である。な お、リツカチ方程式の解法は、上述した参考文献にも詳述されているように既知の方 法が多々知られている。
[0169] このようにして計算した製品種 No.lのペトリネットモデルに対するフィードバックゲイ ン行列 Kは、次の式(12)で与えられる。ただし、この式(12)において、列方向の番 号及び行方向の番号は、それぞれ式(7)における行方向の番号及び列方向の番号 に対応するものである。
[0170] [数 7]
11 21 22 61 71 72 73 101
-0. 927 -0. 252 -0. 252 -0. 249 -0. 001 0. 000 0. 000 0. 000 1
0. 029 -0. 259 -0. 259 -0. 255 -0. 001 0. 000 0. 000 0. 000 2
0. 003 0, 629 0. 629 -0. 343 -0. 001 0. 000 0. 000 0. 000 3 (12)
0. 006 0. 292 0. 292 0. 300 -0. 003 0. 000 0. 000 0. 000 10
0. 000 0. 002 0. 002 0. 002 0. 073 0. 919 0. 919 -0. 039 11
0. 000 0. 004 0. 880 0. 880 0. 919 14
[0171] 同様にして全ての製品種に対してもフィードバックゲイン行列 Kを計算することによ り、図 11のフローチャートに示した制御則の構築が行われる。
[0172] 〔シミュレーション〕
次に、シミュレーションについて、図 21に示したフローチャートに沿って説明する。 まず、ペトリネットモデルの初期状態における状態ベクトル M(0)を入力するとともに、 投入予定の全製品を投入プレースに入力し、時刻 kの値を 0に初期化したのち (ステ ップ S2101)、現時点(時刻: k )における全製品種の状態ベクトルを入力し (ステップ S2102)、新規投入製品を製品種ごとに入力して状態ベクトルに加えると、現時点に おける最終的な状態ベクトル M(k)が定まる。さらに、製品種ごとに、フィードバックゲ イン行列 Kと状態ベクトル M(k)
とをかければ、操作ベクトル u(k)が計算できる (ステップ S2103)。
[0173] 例えば、ある時刻 kにおいて製品種 No.lのトークンがプレース P6のみに 1個あり、さ らに同品種の新規投入製品は無力つたとすると、製品種 No.1に対する最終的な状態 ベクトル M(k)は、
M(k) = [ 0 0 0 1
0 0 0 0 ]' · ' ·(13)
となる。ただし、式( 13)にお 、て記号' は転置ベクトルであることを表す。また、式( 1 3)の各要素は、それぞれ各プレース Ρ1,Ρ2,Ρ6,Ρ7,Ρ10の状態番号
11,21,22,61,71,72,73,101〖こ対応する製品種 No.lのトークン数を表す。
[0174] 次に、式(12)で与えられたフィードバックゲイン行列 Kと式(13)の状態ベクトル M (k)
とを式 (ハ)に従ってかければ、操作ベクトル u(k)は、
u(k) = [-0.249
-0.255 -0.3430 0.300 0.002 0.004 ]' · · · (14)
と求められる。ただし、式 (14)の各要素は、それぞれトランジシヨン
T1,T2,T3,T10,T11,T14に対する操作量である。
[0175] 同様にして全ての製品種に対しても操作ベクトル u(k)を求める。そして、移動操作 端すなわちトランジシヨンごとに、正値で大きい操作量が得られた製品順に、移動可 能な数だけ移動操作を実行する (ステップ S2104)。
[0176] 例えば、時刻 kにおいて製品種 No.lのトークンがプレース P6に 1個あり、このとき同 時に製品種 No.8のトークンもプレース P6に 1個あり、他の製品種のトークンはプレース P6にはなかったとする。この場合、トランジシヨン T10に関して製品種 No.lのトークン に対する操作量は、式(14)より 0.300であった。一方、製品種 No.8のトークンに対す る操作量を同様にして計算する。製品種 No.8の遷移行列 aを式(15)、接続行列 1^を( 16)、行列 Q、 Rを(17)、(18)を示す。フィードバックゲイン行列 Kは次の式(19)の ようになり、トランジシヨン T10の操作量は 0.361となる。
[数 8]
Figure imgf000047_0001
[0178] [数 9]
Figure imgf000047_0002
[0179] Q = 20XI(16) ---(17)
R=I(10) ,··(18)
ただし、式(17)、(18)において I(n)は n次の単位行列である。 [0180] [数 10]
Figure imgf000048_0001
(19)
[0181] ここで、トランジシヨン T10は、移動操作すなわち発火によって 1個のトークンをプレ ース P7に移動させることができるものであるとする。この場合、時刻 kにおいては仮想 プレース P15に容量設定用仮想トークンが 1個存在しているため、結局製品種 No.8 のトークンに対してのみトランジシヨン T10を発火させることが可能になる。また、製品 種 No.8のトークンは時刻 kにおいて他のプレースには存在していなかつたから、操作 量の正負に関わらずトランジシヨン T10
以外のトランジシヨンは発火できな 、。
[0182] したがって、製品種 No.8に対する最終的な操作ベクトル u(k)は、
u(k) = [ 0000
010000 ]' ---(20)
となり、トランジシヨン T10のみが発火する。その結果、製品種 No.8に対する時刻 kに おける状態ベクトルが
M(k) = [ 0000
000010000000 ]' ---(21)
から時刻 k+1における状態ベクトルへ
M(k+1) = [000
0000001000000 "'{22)
と更新される。
[0183] 同様の計算を全製品種、全トランジシヨンについて行えば、全製品種に対する時刻 k+1における状態ベクトル M(k+1)が計算されることになる。その後は、時間を進めた のち(ステップ S2105)、各ステップのシミュレーションが終了したかどうかを判断し (ス テツプ S2106)、終了していないときはステップ S2102の処理に戻る。一方、終了し たときは、そのシミュレーション結果をもって生産スケジュールとする(ステップ S2107
) o
[0184] 上述したように、本実施形態においては、上述した第 4の実施形態の効果に加えて 、 1つのプレースに複数のきざみ時間遅れを含むようにしてペトリネットモデルを構築 し、遷移行列及び接続行列の 2つの行列式だけで数式モデルを表現できるようにし たので、 1つのきざみ時間遅れごとに 1つのプレースを設けたペトリネットモデルを再 構築しなくても済む。また、 1つのきざみ時間遅れごとに 1つのプレースを設けたペトリ ネットモデルに比べて制御端の数を少なくすることができ、実プロセスに使 、やす ヽ ちのとすることがでさる。
[0185] なお、本実施形態では、ペトリネットモデルを例に挙げて説明した力 その他のダラ フモデル、例えば有向グラフや無向グラフに本発明を適用することも可能である。例 えば有向グラフでは、上述したペトリネットモデルにおけるプレースは点で表現され、 トランジシヨンは矢印付きの線で表現される。矢印付きの線は、点から点へ製品すな わちトークンを移動させる移動操作端であり、移動路の役目をする。また、矢印は、線 から点、或いは、点から線へトークンが移動する方向を示すものである。
[0186] また、ペトリネットモデルでは、各工程内に設けられている仮想プレースに初期設定 された容量設定用仮想トークンの数により、各処理工程で同時に処理できる製品の 数を制限していた力 通常のグラフモデルでは仮想プレースは存在せず、各工程内 における処理容量をソフトウェア上で制御される。
[0187] このような特徴を有する通常のグラフモデルに本発明を適用する場合も、一連の動 作は上述したペトリネットモデルにおける動作と同様であり、ここでは、その詳細な説 明は省略する。
[0188] 以下に説明する第 7の実施形態は、上述した第 3の実施形態に関連するものである (第 7の実施形態)
図 3に示したように、本実施形態の生産'物流スケジュール作成装置も、物流シミュ レータ 300、数式モデル 321、最適化計算装置 330等によって構成されている。
[0189] 以下に、第 7の実施形態を、図 25— 27を参照しながら説明する。
本実施形態の生産 ·物流スケジュール作成装置では、プロセス Aからプロセス Bま での製造プロセスにおいて、与えられた投入順と工場物流制約の下で、プロセス B操 業計画にマッチしたプロセス A操業計画の最適化問題を扱うものとする。ただし、これ はあくまでも一例であり、本実施形態の生産'物流スケジュール作成装置は、下工程 の方に課せられた多くの制約を守りつつ上工程での操業計画を作成する際には適 用することが可能であり、また特に有効である。
[0190] ここでの操業計画では、まず第 1に、工場全体のスループットを最大にすることを目 的とする。第 2に、途中工程での半製品滞留時間を最小にすることを目的とする。す なわち、プロセス Aより処理された半製品は、搬送機器等によりプロセス Bの所まで運 ばれてきた後、現在中間バッファーに投入中の半製品が完全に終了するまで、置き 場に予備的に置かれ、ここで待ち時間が生じる。この待ち時間が長くなると、半製品 の温度低下が大きくなり製品の品質上問題が生じる。よって、このような温度低下を 抑制するためにも、置場上での投入待ち時間を最小化する必要がある。
[0191] なお、プロセス Aより処理された半製品が搬送機器よつてプロセス Bまで運ばれてく るのには時間がかかる。その際、製品の種類によっては、プロセス Aからプロセス Bま での途中過程で、 2次処理の処理が施される場合もある。
[0192] また、プロセス B内での各半製品の処理時間が各半製品毎に異なることもある。そ の一方で、上述したように、プロセス Bの入口にある中間バッファの中身が完全に途 切れる前に次の半製品を投入必要がある。よって、プロセス Aの操業計画を作成する 際には、各半製品毎に処理時間が異なること、及び各半製品の連続化や滞留時間 の最小化の必要性等を考慮して、プロセス Aでの処理順だけでなく処理時刻まで正 確に決定する必要がある。
[0193] 図 25は、本実施形態による生産'物流スケジュール作成装置の概略的構成を示す ブロック図、図 26は、本実施形態による生産 ·物流スケジュール作成装置によって行 われる処理の概要を説明するための図、図 27は、計画システム内での本実施形態 による処理計画作成装置の位置づけを示す図である。最初に、図 27を用いて本実 施形態による生産 ·物流スケジュール作成装置の位置づけを説明する。
[0194] 図 27に示すように、日毎操業計画を作成する際には、まず、投入順作成部 31で、 あらかじめ設定された週間スケジュール 30をもとにして、各半製品のプロセス Bへの 投入順を決定する、ここでは少なくとも、プロセス Aのどの装置で処理されたあと、半 製品をプロセス Bのどの装置でどの順序で処理するかを決定する。
[0195] 本実施形態の処理計画作成部 32は、投入順作成部 31により作成された投入順や 様々な工場物流制約の下で、投入順作成部 31より与えられたプロセス Bの投入順の 情報カゝらプロセス Aでの操業計画、すなわち、プロセス Aでの処理順と処理時刻とを 求める。
[0196] この処理計画作成部 32では、以下に詳しく述べるように、物流構造(工場内の設備 配置やその接続関係、設備容量、半製品の通過ルート等)をグラフィカルにモデリン グしたペトリネットによる離散事象シミュレータと、静的な計画問題の解法としてよく用 いられる LP (線形計画法)との従来にはない全く新たな組み合わせにより、いわゆる モデル予測制御の考え方に基づきプロセス Aでの処理順及び処理時刻の最適化を 図る。
[0197] 処理計画作成部 32で求められたプロセス Aでの操業計画 (処理順及び処理時間 の情報)は、表示部 33に与えられ、例えばガントチャートの形式で表示される。各種 評価部 34では、求められた操業計画を様々な観点力 評価し、満足のいく結果でな ければ必要に応じて各半製品の投入順を修正する。そして、処理計画作成部 32で もう一度操業計画を作成し直す。
[0198] 次に、上記処理計画作成部 32によって行われる処理の概要を、図 26を用いて説 明する。なお、この図 26の例では、プロセス A1号機及び 2号機、プロセス B1号機, 2 号機及び 3号機を例にとっている。また、この図 26の例では、図 27の投入順作成部 31により、プロセス A1号機からプロセス B1号機に「A, B, C, D, E」の英字で示す 半製品をこの順番で処理すると共に、プロセス B2号機に「1, 2, 3, 4, 5」の数字で 示す半製品をこの順番で処理し、プロセス A2号機カゝらプロセス B3号機に「0, P, Q , R, S」の英字で示す半製品をこの順番で処理することが決められている。
[0199] 処理計画作成部 32は、このような投入順の下、モデル予測制御の考え方に基づき 、処理時刻のシミュレーションの各判断時毎に (処理事象が発生する毎に)将来の物 流状態である置場上での半製品の待ち時間や半製品処理速度の減速量を推定した 上で、全体のスループットの最大化や待ち時間の最小化のために設定した所定の評 価関数を最良にするプロセス Aの処理順と処理時刻とを決定する。このとき、将来の 物流状態の推定範囲は、各プロセス Bの処理予定の 1半製品分とする。
[0200] すなわち、例えば図 26の上図のように、シミュレーション上の時刻 tにおいて半製品 Rの処理事象が発生したとする。この半製品 Rは、プロセス A2号機で処理された後、 搬送機器で運ばれ、時間 tl後に(この時間 tlの中には 2次処理での処理時間も含ま れているものとする)プロセス B3号機に到着する。そして、このプロセス B3号機内で 時間 tをカゝけて連続処理の処理が行われる。このような半製品 Rの処理事象が発生し たとき、まずステップ S1で、将来の物流状態の予測範囲として各プロセス B毎に 1半 製品分を設定する。ここでは、プロセス B1号機に関して半製品 D、プロセス B2号機 に関して半製品 5、プロセス B3号機に関して半製品 Sを予測範囲として設定する。
[0201] 次に、ステップ S2では、設定した予測範囲内の各半製品(D, 5, S)の処理完了希 望時刻をそれぞれ算出するとともに、物流制約に基づく物流モデルを定式ィ匕する。こ こで処理完了希望時刻とは、当該半製品をプロセス Aから何時に処理すれば前の半 製品の処理完了時刻に当該半製品がプロセス Bにぴったり到着するかを示す時刻で ある。これは、既に処理された前の半製品の処理完了時刻から半製品の運搬時間( 2次処理処理時間を含む)を減算することによって簡単に求められる。現在の予測範 囲内の各半製品(D, 5, S)の処理完了希望時刻は、図 26の上図中に X印で示して ある。
[0202] このようにして、ある時刻 tで処理事象が発生したときに、そこ力も各プロセス B毎に 1半製品分の予測範囲を設定して物流モデルを構築したら、続くステップ S3で、その 構築した物流モデルと、あらかじめ設定した所定の評価関数とを用いて、予測範囲 内の 3つ半製品(D, 5, S)を対象として処理時刻の最適化計算を行う。ここではこの 最適化計算により、ステップ S4で、半製品 D→半製品 5→半製品 Sの順が最適であ るとの結果が得られたとする。
[0203] そこで、次のステップ S5では、ペトリネットのシミュレータに半製品 D→半製品 5→半 製品 Sの順で処理指示を出す。これに応じてシミュレータは、ステップ S6で、半製品 Dの処理時刻 t+ Atまでシミュレーションを進める。この状態が図 26の下図に示して ある。このようにして再び処理事象が発生したので、ステップ S7で、その半製品 Dの 処理事象発生時刻 t + Atから各プロセス B毎に 1半製品分を将来の物流状態の予 測範囲として設定する。ここでは、プロセス B2号機及び 3号機に関しては前回と同様 である力 処理事象の発生したプロセス B1号機に関しては半製品 Eが新たに予測範 囲として設定されている。
[0204] この新たに設定した予測範囲についても前回と同様に、物流モデルの構築及び最 適化計算を行う。物流モデルの構築で半製品 Eの希望処理時刻を求める際に、その 直前の半製品 Dについては既に処理されてシミュレーションが済んでいるので、半製 品 Dでの処理完了時刻はペトリネットのシミュレータ力も得ることができる。よって半製 品 Eの希望処理時刻は、この半製品 Dの処理完了時刻から半製品 Eの運搬時間を 減算することによって求められる。
[0205] なお、ここでの最適化計算では、ステップ S8に示すように、半製品 S→半製品 5→ 半製品 Eの順が最適であるとの結果が得られたとする。この場合は、ペトリネットのシミ ユレータに半製品 S→半製品 5→半製品 Eの順で処理指示を出すことによって、シミ ユレータにおけるシミュレーションを半製品 Sの処理時刻まで進める。以下、同様にし て、処理事象が発生する毎に、そこ力 将来の予測範囲を各プロセス Bの 1半製品分 で区切って部分的にシミュレーション (処理順及び処理時刻の最適化)を行う処理を 繰り返していく。
[0206] なお、図 26の例では、全ての半製品が希望処理時刻どおりに処理されたシミュレ ーシヨンの結果を示している力 必ずしも希望処理時刻に処理される結果が得られる とは限らない。希望処理時刻よりも処理時刻が遅れると、プロセス B内での半製品の 連続性が断たれるので、連続性を維持するために前の半製品の処理時間を長くする (処理速度を減速させる)必要がある。しかし、これは全体のスループットを低下させ る方向に働くものである。
[0207] 一方、希望処理時刻よりも処理時刻が早まると、全体のスループットを向上させるこ とは可能であるが、置場上での半製品の滞留時間が長くなる方向に働き、待ち時間 の間に半製品の温度低下を招いてしまう。そこで実際には、これらの全体のスループ ットゃ滞留時間の両方を考慮した評価関数を用い、最適化計算の結果得られる評価 値が最良になる処理時刻を選ぶことにより、両者の最適なトレードオフを図っている。
[0208] 次に、図 26に示したような処理を行う処理計画作成部 32の概略的な構成について 、図 25を用いて説明する。図 25において、 11はペトリネットによる離散事象シミュレ ータであり、ペトリネットによるグラフィカルな物流構造モデルと、グラフィカルに表現 できないルール記述とによって構成される。ここで、ルールの例としては、半製品を最 も早く処理できる時刻の限界を示す処理最早時刻、半製品を最も遅く処理できる時 刻の限界を示す処理最遅時刻、及び複数プロセス Aの干渉条件等がある。
[0209] 以下に、数式モデルの具体例を説明する。上述したように、プロセス B内での各半 製品の処理速度はある狭い範囲内でのみ変更が許されており、且つ置場上での待 ち時間にも上下限があるため、これらをすベて満たすようにプロセス Aの処理終了最 早、最遅時刻が各半製品毎に設定される。
[0210] また、プロセス Aの同一の号機で連続して処理するためには、少なくともプロセス A の処理時間だけは間隔を確保する必要があり、プロセス Aの別の号機で処理するた めには、プロセス Aへの原料装入用搬送機器能力等の制約から必要な時間間隔を 確保する必要がある。そのため、同一の号機に関しては例えば 45分、別の号機に関 しては例えば 20分の間隔をおかなければならな ヽと 、う条件が物流制約として課さ れる。
[0211] 12は物流モデル構築部であり、上記シミュレータ 11に設定されている処理終了最 早、最遅時刻及び物流制約の情報と、シミュレータ 11によってシミュレーションが行 われた結果として与えられる現在の物流状況 (過去に処理を開始したものがどの半 製品で、その処理完了時刻がいっかという情報)とを組み合わせて、各プロセス B毎 に 1半製品分の将来予測範囲を設定してその範囲内の物流モデルを構築する。この 物流モデルは、以下に説明するように数学モデルによる定式ィ匕によって行う。
[0212] ここで、物流モデルの定式ィ匕について説明する。上述したように、図 28は、物流モ デルの定式化の概要を示す図である。図 28に示すように、シミュレーション上の時刻 tにおいてある半製品のプロセス Aの処理終了事象が発生したときに、その時刻から 各プロセス B毎に 1半製品分を将来の物流状態の予測範囲として設定し、シミュレ一 タ 11より得られる現状の物流状態から、予測範囲内の各半製品のプロセス Aの処理 終了希望時刻をそれぞれ算出する。シミュレータ 11より得られる前半製品の処理完 了時刻を a、予測している半製品のプロセス Aの処理終了からプロセス Bの処理開始 までの時間を bとすると、プロセス Aの処理終了希望時刻は、 c = a— bなる演算により 簡単に求まる。
[0213] 次に、シミュレータ 11よりプロセス Aの処理終了最早、最遅時刻及びプロセス B物流 制約の情報を取り込み、これを定式化する。図 28の例で、プロセス B1号機へのプロ セス Aの処理終了時刻を C 1 ,プロセス B2号機へのプロセス Aの処理終了時刻を C2 ,プロセス B3号機へのプロセス Aの処理終了時刻を C3とすると、プロセス Bの物流制 約は、
I cl-c2 I ≥45, I c2-c3 | ≥20
と表され、プロセス Aの処理終了最早時刻及び最遅時刻の条件は、
cl最早≤cl≤cl最遅
c2最早≤c2≤c2最遅
c3最早≤c3≤c3最遅
と表される。
[0214] さらに、これらの式を変形すると、物流モデルは、
Ax≤B
Xmin Xmax
という簡単な線形式で表すことができる。なお、 Xは各プロセス Bのプロセス Aの処理 終了時刻を行列表現したもの、 A, Bは所定の行列式、 xmin及び xmaxはそれぞれ 各プロセス Bへのプロセス Aの処理終了最早時刻及び最遅時刻を行列表現したもの である。
[0215] 図 29は、上述した各実施形態の生産'物流スケジュール作成装置を構成可能なコ ンピュータシステムの一例を示すブロック図である。同図において、 1200はコンビュ ータ PCである。 PC1200は、 CPU1201を備え、 ROM1202又はハードディスク(H D) 1211に記憶された、或いはフレキシブルディスクドライブ (FD) 1212より供給され るデバイス制御ソフトウェアを実行し、システムバス 1204に接続される各デバイスを 総括的に制御する。
[0216] 上記 PC1200の CPU1201、 ROM1202又はハードディスク(HD) 1211に記憶さ れたプログラムにより、本実施形態の各機能手段が構成される。
[0217] 1203は RAMで、 CPU1201の主メモリ、ワークエリア等として機能する。 1205は キーボードコントローラ (KBC)であり、キーボード (KB) 1209から入力される信号を システム本体内に入力する制御を行う。 1206は表示コントローラ(CRTC)であり、表 示装置(CRT) 1210上の表示制御を行う。 1207はディスクコントローラ(DKC)で、 ブートプログラム (起動プログラム:パソコンのハードやソフトの実行 (動作)を開始する プログラム)、複数のアプリケーション、編集ファイル、ユーザファイルそしてネットヮー ク管理プログラム等を記憶するハードディスク (HD) 1211、及びフレキシブルデイス ク(FD) 1212とのアクセスを制御する。
[0218] 1208はネットワークインタフェースカード(NIC)で、 LAN1220を介して、ネットヮ ークプリンタ、他のネットワーク機器、或いは他の PCと双方向のデータのやり取りを行
[0219] なお、本発明は複数の機器カゝら構成されるシステムに適用しても、一つの機器から なる装置に適用してもよい。
[0220] また、本発明の目的は前述した実施形態の機能を実現するソフトウェアのプロダラ ムコードを記録した記憶媒体を、システム或いは装置に供給し、そのシステム或いは 装置のコンピュータ (CPU若しくは MPU)が記憶媒体に格納されたプログラムコード を読出し実行することによつても、達成されることは言うまでもない。
[0221] この場合、記憶媒体力 読出されたプログラムコード自体が前述した実施形態の機 能を実現することになり、そのプログラムコードを記憶した記憶媒体は本発明を構成 すること〖こなる。
[0222] プログラムコードを供給するための記憶媒体としては、例えばフレキシブルディスク 、ハードディスク、光ディスク、光磁気ディスク、 CD-ROM, CD-R,磁気テープ、不 揮発性のメモリカード、 ROM等を用いることができる。
[0223] また、コンピュータが読出したプログラムコードを実行することにより、前述した実施 形態の機能が実現されるだけでなぐそのプログラムコードの指示に基づき、コンビュ ータ上で稼働して!/、る OS (オペレーティングシステム)等が実際の処理の一部又は 全部を行 ヽ、その処理によって前述した実施形態の機能が実現される場合も含まれ ることは言うまでもない。
[0224] 更に、記憶媒体力も読出されたプログラムコードが、コンピュータに挿入された機能 拡張ボードやコンピュータに接続された機能拡張ユニットに備わるメモリに書込まれ た後、そのプログラムコードの指示に基づき、その機能拡張ボードや機能拡張ュ-ッ トに備わる CPU等が実際の処理の一部又は全部を行い、その処理によって前述した 実施形態の機能が実現される場合も含まれることは言うまでもない。
[0225] 以上述べた各実施形態では、シミュレーション結果力 上記生産 ·物流プロセスに おける生産'物流スケジュールを作成する例を説明した力 シミュレーション結果に基 づいて生産 ·物流プロセスの制御を行う場合にも本発明は適用される。
産業上の利用可能性
[0226] 本発明によれば、詳細シミュレーションを実行中に物流指示が必要な事象が発生 するたびにシミュレータ力 シミュレーション現時点での物流状態及び物流制約の情 報を検出し、上記検出した検出情報と予め定めた評価指標を元に最適化手法によつ て最適物流指示を計算し、上記計算結果に基づ!、て以後の詳細シミュレーションを 進め、次に物流指示が必要な事象が発生した時点で最適物流指示を再度計算する ことを繰り返し行うようにしたので、詳細シミュレーション自体は一度行うだけで最適物 流指示を得ることができる。また、シミュレータと、数式モデルと、最適化装置とを連動 させて最適物流指示を計算し、上記計算結果のシミュレーションを行ってスケジユー ルを作成するようにしたので、物流制約条件が複雑であっても実行可能なスケジユー ルを作成することができる。また、所望の評価指標を最良にするスケジュールを作成 することができるとともに、計算時間を短縮して実用的な時間内にスケジュールを作 成することができる。これらにより、最適性と実行可能性の両方を確保できる。また、 対象とする生産 ·物流プロセスの状態に応じたスケジュールを作成する際の手間及 び時間を大幅に削減することができる。さらに、スケジュールを作成する対象の規模 が大きい場合においても、正確な生産 ·物流スケジュールを高速に、且つ高精度に 作成することが可能となる。

Claims

請求の範囲
[1] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、
上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルで あって、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作 成された数式モデルを保持する数式モデル保持装置と、
上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記 生産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有し、 上記最適化計算装置によって得られた物流指示を上記生産'物流シミュレータに 与えてシミュレーションを実行させるとともに、新たな事象が発生した場合には上記生 産 ·物流シミュレータ力 上記最適化計算装置に対して最適化計算を行うようにする 指示を出力するようにして、上記生産'物流シミュレータと上記最適化計算装置とを 連動させて、上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するよう にしたことを特徴とする生産 ·物流スケジュール作成装置。
[2] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、
上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルで あって、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作 成された状態方程式を用いた数式モデルを保持する数式モデル保持装置と、 上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記 生産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有し、 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果から 上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにしたことを 特徴とする生産 ·物流スケジュール作成装置。
[3] 上記生産 ·物流シミュレータは離散系の生産 ·物流シミュレータであることを特徴と する請求項 2に記載の生産 ·物流スケジュール作成装置。
[4] 上記離散系の生産 ·物流シミュレータはグラフモデルを用いてシミュレータを構築す るものであり、上記状態方程式はグラフモデルの状態方程式であることを特徴とする 請求項 3に記載の生産 ·物流スケジュール作成装置。
[5] 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出する場合に、フィードバックゲインと工程内製 品仕掛状態を表わす状態ベクトルとから、製品の移動操作端に対する操作ベクトル を求めたのち、各移動操作端に対して、上記求めた操作ベクトルの中で正値の大き
V、操作量が得られる製品順に各製品を移動可能な数だけ移動させるように操作する ことを特徴とする請求項 4に記載の生産 ·物流スケジュール作成装置。
[6] 上記離散系の生産 ·物流シミュレータはグラフモデルを用いてシミュレータを構築す るものであり、上記状態方程式は処理時間に比例したきざみ時間遅れに従って表わ される接続行列と遷移行列とを用いた状態方程式であることを特徴とする請求項 3に 記載の生産 ·物流スケジュール作成装置。
[7] 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出する場合に、フィードバックゲインと工程内製 品仕掛状態を表わす状態ベクトルとから、製品の移動操作端に対する操作ベクトル を求めたのち、各移動操作端に対して、上記求めた操作ベクトルの中で正値の大き
V、操作量が得られる製品順に各製品を移動可能な数だけ移動させるように操作する ことを特徴とする請求項 6に記載の生産 ·物流スケジュール作成装置。
[8] 上記離散系の生産'物流シミュレータはペトリネットモデルを用いてシミュレータを構 築するものであり、上記状態方程式はペトリネットモデルの状態方程式であることを特 徴とする請求項 3に記載の生産 ·物流スケジュール作成装置。
[9] 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出する場合に、フィードバックゲインと工程内製 品仕掛状態を表わす状態ベクトルとから、製品の移動操作端に対する操作ベクトル を求めたのち、各移動操作端に対して、上記求めた操作ベクトルの中で正値の大き
V、操作量が得られる製品順に各製品を移動可能な数だけ移動させるように操作する ことを特徴とする請求項 8に記載の生産 ·物流スケジュール作成装置。
[10] 上記離散系の生産'物流シミュレータはペトリネットモデルを用いてシミュレータを構 築するものであり、上記状態方程式は処理時間に比例したきざみ時間遅れに従って 表わされる接続行列と遷移行列とを用いた状態方程式であることを特徴とする請求 項 3に記載の生産 ·物流スケジュール作成装置。
[11] 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出する場合に、フィードバックゲインと工程内製 品仕掛状態を表わす状態ベクトルとから、製品の移動操作端に対する操作ベクトル を求めたのち、各移動操作端に対して、上記求めた操作ベクトルの中で正値の大き V、操作量が得られる製品順に各製品を移動可能な数だけ移動させるように操作する ことを特徴とする請求項 10に記載の生産 ·物流スケジュール作成装置。
[12] 上記最適化計算処理は線形二次制御を利用するものであり、所定の評価行列を用 いて表わされる評価関数を最小とするように前記フィードバックゲインを算出すること を特徴とする請求項 2に記載の生産 ·物流スケジュール作成装置。
[13] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、
上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルで あって、上記生産 ·物流プロセスの立案開始時間から予め設定した期間 (計画作成 期間)分を対象として、着目して 、る物流のスケジュールを作成するのに係わる情報 を取り込んで作成された数式モデルを保持する数式モデル保持装置と、
上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記 生産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有し、 上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作 成するようにしたことを特徴とする生産 ·物流スケジュール作成装置。
[14] 上記生産 ·物流シミュレータは離散系の生産 ·物流シミュレータであることを特徴と する請求項 2に記載の生産 ·物流スケジュール作成装置。
[15] 上記離散系の生産 ·物流シミュレータは、上記生産'物流プロセスを離散事象モデ ルで表したシミュレータであり、事象が発生したときに上記シミュレータ力も現在の物 流状態及び物流制約を検出することを特徴とする請求項 14に記載の生産'物流スケ ジュール作成装置。
[16] 上記立案開始時間力も予め設定した期間は、あらかじめ設定された対象期間分で あることを特徴とする請求項 13に記載の生産'物流スケジュール作成装置。
[17] 上記立案開始時間力も予め設定した期間は、将来の物流状態の予測範囲として、 上記事象発生の時刻から所定の区切られた範囲で設定された期間であることを特徴 とする請求項 13に記載の生産 ·物流スケジュール作成装置。
[18] 上記着目して 、る物流のスケジュールを作成するのに係わる情報を取り込んで作 成された数式モデルは、製品、移動体、設備の処理に伴う作業群の関係、制約に対 して構築されることを特徴とする請求項 13に記載の生産 ·物流スケジュール作成装 置。
[19] 上記着目して 、る物流のスケジュールを作成するのに係わる情報を取り込んで作 成された数式モデルは、上記検出した現在の物流状態及び物流制約で成る数式モ デルであることを特徴とする請求項 13に記載の生産'物流スケジュール作成装置。
[20] 上記最適化計算装置は、あらかじめ設定した評価関数を用いて最適化計算処理を 行うことを特徴とする請求項 13に記載の生産'物流スケジュール作成装置。
[21] 上記最適化計算装置は、あらかじめ設定した線形の評価関数を用いて最適化計算 処理を行うことを特徴とする請求項 13に記載の生産'物流スケジュール作成装置。
[22] 上記最適化計算装置は、最適化或いは準最適化問題として上記生産 ·物流スケジ ユールを作成することを特徴とする請求項 13に記載の生産 ·物流スケジュール作成 装置。
[23] 上記最適化計算装置は、上記設定した予測範囲内で少なくとも最適な発生事象及 びその発生時刻を求めることを特徴とする請求項 13に記載の生産 ·物流スケジユー ル作成装置。
[24] 上記最適化計算装置の計算結果に基づいて、上記製品、移動体、設備の処理に 伴う作業群の関係、制約の全部或いは一部動作 ·状況をシミュレートする生産 '物流 シミュレート処理と、
上記生産 ·物流シミュレート処理により求めた生産 ·物流計画の内で計画をあらかじ め設定した確定期間分だけ採用して確定する生産 ·物流計画確定処理とを行って上 記予め設定した期間 (計画確定期間)分だけ物流計画を確定することを特徴とする請 求項 13に記載の生産 ·物流スケジュール作成装置。
[25] 上記生産'物流シミュレータがシミュレーションを進めて、上記予め設定した期間( 計画作成期間)分だけ物流計画を確定することを特徴とする請求項 13に記載の生産 •物流スケジュール作成装置。
[26] 上記事象の発生事象力 将来の予測範囲を区切って最適化計算を行 、、その結 果を上記シミュレータに供給して事象発生時刻を進める処理を事象発生毎に繰り返 し行い、この繰り返し演算の結果力 上記予測範囲毎に求めた一連の事象発生順及 びその事象発生時刻を生産 ·物流スケジュールとして決定することを特徴とする請求 項 13に記載の生産 ·物流スケジュール作成装置。
[27] 上記生産 ·物流計画確定処理により確定した生産 ·物流計画の確定期間が経過し た直後の日時を新たな立案開始日時として設定し、上記生産 ·物流計画確定処理に より既に確定した生産'物流計画に基づき上記数式モデルを構築する処理により構 築した新たな数式モデルに基づ 、て、数式モデルに対する解を求める数式モデル 求解処理と、
上記数式モデル求解処理により求めた数式モデルに対する解に基づいて製造プ ロセス ·搬送の動作 ·状況をシミュレートする生産 ·物流シミュレート処理と、
上記生産 ·物流シミュレート処理により求めた生産 ·物流計画のうち、あら力じめ設 定した確定期間分の生産 ·物流計画だけを採用して生産 ·物流計画を確定する生産 •物流計画確定処理とにより、上記新たな立案開始日時力 新たな確定期間分の生 産'物流計画を確定する一連の処理を、順次設定する新たな立案開始日時につい てそれぞれ行うことを特徴とする請求項 23に記載の生産 ·物流スケジュール作成装 置。
[28] 上記離散系の生産 ·物流シミュレータは、ペトリネットモデルを使用して構成されて いることを特徴とする請求項 14に記載の生産'物流スケジュール作成装置。
[29] 上記最適化計算装置は、 LP (線形計画法)を使用することを特徴とする請求項 13 に記載の生産 ·物流スケジュール作成装置。
[30] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された数式モデルを保持する数式モデル保持装置と、 上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記生 産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有する生産 · 物流スケジュール作成装置により生産'物流スケジュールを作成する方法であって、 上記最適化計算装置によって得られた物流指示を上記生産'物流シミュレータに 与えてシミュレーションを実行させるとともに、新たな事象が発生した場合には上記生 産 ·物流シミュレータ力 上記最適化計算装置に対して最適化計算を行うようにする 指示を出力するようにして、上記生産'物流シミュレータと上記最適化計算装置とを 連動させて、上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するよう にしたことを特徴とする生産 ·物流スケジュール作成方法。
[31] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置とを有する生産 ·物流スケジュール作成装置により生産 ·物流スケジュールを 作成する方法であって、
上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果から 上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにしたことを 特徴とする生産 ·物流スケジュール作成方法。
[32] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と を有する生産 ·物流スケジュール作成装置により生産'物流スケジュールを作成する 方法であって、
上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作 成するようにしたことを特徴とする生産 ·物流スケジュール作成方法。
[33] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された数式モデルを保持する数式モデル保持装置と、 上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記生 産 ·物流シミュレータに対する物流指示を算出する最適化計算装置としての機能をコ ンピュータに実現させ、
上記最適化計算装置によって得られた物流指示を上記生産'物流シミュレータに 与えてシミュレーションを実行させるとともに、新たな事象が発生した場合には上記生 産 ·物流シミュレータ力 上記最適化計算装置に対して最適化計算を行うようにする 指示を出力するようにして、上記生産'物流シミュレータと上記最適化計算装置とを 連動させて、上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するよう にしたことを特徴とするコンピュータプログラム。
[34] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された数式モデルを保持する数式モデル保持装置と、 上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記生 産 ·物流シミュレータに対する物流指示を算出する最適化計算装置としての機能をコ ンピュータに実現させ、
上記最適化計算装置によって得られた物流指示を上記生産'物流シミュレータに 与えてシミュレーションを実行させるとともに、新たな事象が発生した場合には上記生 産 ·物流シミュレータ力 上記最適化計算装置に対して最適化計算を行うようにする 指示を出力するようにして、上記生産'物流シミュレータと上記最適化計算装置とを 連動させて、上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するよう にしたコンピュータプログラムを記録したことを特徴とするコンピュータ読み取り可能な 記録媒体。
[35] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置としての機能をコンピュータに実現させ、
上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果から 上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにしたことを 特徴とするコンピュータプログラム。
[36] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置としての機能をコンピュータに実現させ、
上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果から 上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作成するようにしたコンビ ユータプログラムを記録したことを特徴とするコンピュータ読み取り可能な記録媒体。
[37] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と しての機能をコンピュータに実現させ、
上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作 成するようにしたことを特徴とするコンピュータプログラム。
[38] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と しての機能をコンピュータに実現させ、
上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果から上記生産 ·物流プロセスにおける生産 ·物流スケジュールを作 成するようにしたコンピュータプログラムを記録したことを特徴とするコンピュータ読み 取り可能な記録媒体。
[39] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、
上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルで あって、着目している物流のスケジュールを作成するのに係わる情報を取り込んで作 成された状態方程式を用いた数式モデルを保持する数式モデル保持装置と、 上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記 生産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有し、 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果に基 づ 、て生産 ·物流プロセスの制御を行うことを特徴とする生産 ·物流プロセス制御装 置。
[40] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、
上記生産 ·物流プロセスの物流状態と物流制約とを数式で表現した数式モデルで あって、上記生産 ·物流プロセスの立案開始時間から予め設定した期間 (計画作成 期間)分を対象として、着目して 、る物流のスケジュールを作成するのに係わる情報 を取り込んで作成された数式モデルを保持する数式モデル保持装置と、
上記数式モデルに対して所定の評価関数を用いて最適化計算処理を行って上記 生産 ·物流シミュレータに対する物流指示を算出する最適化計算装置とを有し、 上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果に基づ 、て生産 ·物流プロセスの物流制御を行うようにしたことを 特徴とする生産 ·物流プロセス制御装置。
[41] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置とを有する生産 ·物流プロセス制御装置により生産 ·物流プロセスを制御する 方法であって、 上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果に基 づ 、て生産 ·物流プロセスの制御を行うようにしたことを特徴とする生産 ·物流プロセ ス制御方法。
[42] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と を有する生産 ·物流プロセス制御装置を用いた生産 ·物流プロセス制御方法であって 上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果に基づ 、て生産 ·物流プロセスの物流制御を行うようにしたことを 特徴とする生産 ·物流プロセス制御方法。
[43] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置としての機能をコンピュータに実現させ、
上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果に基 づいて生産'物流プロセスの制御を行うようにしたことを特徴とするコンピュータプログ ラム。
[44] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、着目している物流のスケジュールを作成するのに 係わる情報を取り込んで作成された状態方程式を用いた数式モデルを保持する数 式モデル保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計 算処理を行って上記生産 ·物流シミュレータに対する物流指示を算出する最適化計 算装置としての機能をコンピュータに実現させ、
上記最適化計算処理によりフィードバックゲインを算出し、そのフィードバックゲイン と物流状態とを用いて物流指示を算出して上記生産 ·物流シミュレータに与えて、シ ミュレーシヨンを進め、新たな物流状態を得て、この新たな物流状態をもとに新たな物 流指示を算出するという処理を繰り返すことにより得られたシミュレーション結果に基 づ 、て生産 ·物流プロセスの制御を行うようにしたコンピュータプログラムを記録したこ とを特徴とするコンピュータ読み取り可能な記録媒体。
[45] 生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と しての機能をコンピュータに実現させ、 上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果に基づ 、て生産 ·物流プロセスの物流制御を行うようにしたことを 特徴とするコンピュータプログラム。
生産 ·物流プロセスの物流状態と物流制約を表現した生産 ·物流プロセスを模擬す る生産 ·物流シミュレータと、上記生産 ·物流プロセスの物流状態と物流制約とを数式 で表現した数式モデルであって、上記生産'物流プロセスの立案開始時間から予め 設定した期間 (計画作成期間)分を対象として、着目して 、る物流のスケジュールを 作成するのに係わる情報を取り込んで作成された数式モデルを保持する数式モデル 保持装置と、上記数式モデルに対して所定の評価関数を用いて最適化計算処理を 行って上記生産'物流シミュレータに対する物流指示を算出する最適化計算装置と しての機能をコンピュータに実現させ、
上記最適化計算処理により現時点から予め設定した期間 (指示算出期間)分につ いて物流指示を算出して上記生産 ·物流シミュレータに与えて、予め設定した期間( シミュレーション期間)分だけシミュレーションを実行して予め設定した期間 (計画確 定期間)分だけ物流計画を確定し、上記確定した期間の直後の日時を新たな立案開 始日時として設定して物流計画を立案するという処理を繰り返すことにより得られたシ ミュレーシヨン結果に基づ 、て生産 ·物流プロセスの物流制御を行うようにしたコンビ ユータプログラムを記録したことを特徴とするコンピュータ読み取り可能な記録媒体。
PCT/JP2004/019405 2003-12-24 2004-12-24 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体 WO2005062145A1 (ja)

Priority Applications (6)

Application Number Priority Date Filing Date Title
US10/584,423 US7676293B2 (en) 2003-12-24 2004-12-24 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
BRPI0418164-6A BRPI0418164A (pt) 2003-12-24 2004-12-24 dispositivo e método de criação de escalonamento de produção, dispositivo e método de controle de processo de produção, programa de computador e meio de gravação legìvel em computador
JP2005516528A JP4690893B2 (ja) 2003-12-24 2004-12-24 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体
EP04807761.4A EP1701232B1 (en) 2003-12-24 2004-12-24 Manufacturing/distribution schedule creation device and method, manufacturing/distribution process control device and method, computer program, and computer-readable recording medium
US12/655,847 US7865260B2 (en) 2003-12-24 2010-01-08 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
US12/655,854 US7860595B2 (en) 2003-12-24 2010-01-08 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium

Applications Claiming Priority (6)

Application Number Priority Date Filing Date Title
JP2003-427914 2003-12-24
JP2003427914 2003-12-24
JP2004-106121 2004-03-31
JP2004106121 2004-03-31
JP2004-114637 2004-04-08
JP2004114637 2004-04-08

Related Child Applications (3)

Application Number Title Priority Date Filing Date
US10/584,423 A-371-Of-International US7676293B2 (en) 2003-12-24 2004-12-24 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
US12/655,854 Division US7860595B2 (en) 2003-12-24 2010-01-08 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
US12/655,847 Division US7865260B2 (en) 2003-12-24 2010-01-08 Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium

Publications (1)

Publication Number Publication Date
WO2005062145A1 true WO2005062145A1 (ja) 2005-07-07

Family

ID=34714153

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2004/019405 WO2005062145A1 (ja) 2003-12-24 2004-12-24 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体

Country Status (7)

Country Link
US (3) US7676293B2 (ja)
EP (1) EP1701232B1 (ja)
JP (1) JP4690893B2 (ja)
KR (1) KR100831108B1 (ja)
BR (1) BRPI0418164A (ja)
TW (1) TW200532519A (ja)
WO (1) WO2005062145A1 (ja)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005342787A (ja) * 2004-05-06 2005-12-15 Nippon Steel Corp 熱間圧延工場の加熱・圧延スケジュール作成装置、加熱・圧延スケジュール作成方法、コンピュータプログラム、及び読取可能な記憶媒体
JP2007206877A (ja) * 2006-01-31 2007-08-16 Nippon Steel Corp 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体
JP2008117309A (ja) * 2006-11-07 2008-05-22 Nippon Steel Corp 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、並びにコンピュータ読み取り可能な記録媒体
JP2018519590A (ja) * 2015-07-01 2018-07-19 シーメンス アクチエンゲゼルシヤフトSiemens Aktiengesellschaft 生産モジュールのための制御装置、制御装置を有する生産モジュールならびに制御装置を操作するための方法
WO2018179273A1 (ja) * 2017-03-30 2018-10-04 日本電気株式会社 フロー制御システム及びその制御方法
CN110442935A (zh) * 2019-07-22 2019-11-12 武汉理工大学 自动化装备生产节拍设计与优化方法
US10656628B2 (en) 2015-05-12 2020-05-19 Siemens Aktiengesellschaft Control device for a production module and a method for operating the control device

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007004391A (ja) * 2005-06-22 2007-01-11 Nippon Steel Corp 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、並びにコンピュータ読み取り可能な記録媒体
KR100932262B1 (ko) * 2007-09-28 2009-12-16 한국전자통신연구원 물류 센터의 운영 관리 시스템 및 그 방법
TWI394089B (zh) * 2009-08-11 2013-04-21 Univ Nat Cheng Kung 虛擬生產管制系統與方法及其電腦程式產品
DK2354541T3 (da) * 2010-01-20 2014-10-20 Siemens Ag Vindparkeffektstyring på basis af en matriks, som viser en effektbelastningsfordeling mellem individuelle vindmøller
US20110313736A1 (en) * 2010-06-18 2011-12-22 Bioproduction Group, a California Corporation Method and Algorithm for Modeling and Simulating A Discrete-Event Dynamic System
JP2012248072A (ja) * 2011-05-30 2012-12-13 Sony Corp 情報処理装置、情報処理方法、及びプログラム
DE102011080769A1 (de) * 2011-08-10 2013-02-14 Mall + Herlan Gmbh Effektive Produktionslinie für Aerosoldosen
US20130111430A1 (en) * 2011-10-27 2013-05-02 Yin Wang Providing goods or services
JP5627625B2 (ja) * 2012-03-22 2014-11-19 株式会社東芝 スケジューリング装置およびその方法
JP6002532B2 (ja) * 2012-10-10 2016-10-05 株式会社日立ハイテクノロジーズ 真空処理装置及び真空処理方法
DE102015211941A1 (de) * 2015-06-26 2016-12-29 Zf Friedrichshafen Ag Verfahren und Vorrichtung zur Reduzierung eines Energiebedarfs einer Werkzeugmaschine und Werkzeugmaschinensystem
JP6712934B2 (ja) * 2016-08-31 2020-06-24 株式会社日立ソリューションズ データ分析装置及びデータ分析方法
CN108268987B (zh) * 2016-12-30 2021-08-06 郑芳田 多样式产品的品质推估方法
TWI614699B (zh) * 2016-12-30 2018-02-11 國立成功大學 大量客製化產品的品質預測方法
JP6517845B2 (ja) * 2017-01-17 2019-05-22 株式会社荏原製作所 スケジューラ、基板処理装置、及び基板搬送方法
DE102017213583A1 (de) * 2017-08-04 2019-02-07 Siemens Aktiengesellschaft Verfahren zur Produktionsplanung
US10459432B2 (en) * 2017-10-27 2019-10-29 General Electric Company Slicing and merging production events
KR102251328B1 (ko) * 2019-06-28 2021-05-12 (주)브이엠에스 솔루션스 시뮬레이션 기반의 공장 내 자원 플래닝 방법 및 그 장치와, 컴퓨터 판독 가능한 기록 매체
EP3805993A1 (en) * 2019-10-10 2021-04-14 Siemens Aktiengesellschaft Generation of graph-structured representations of brownfield systems
CN115903707B (zh) * 2022-12-01 2024-02-06 苏州连讯电子有限公司 一种基于工位监测的连接线生产优化方法及系统

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05225205A (ja) * 1992-02-14 1993-09-03 Mitsubishi Electric Corp 順次確定生産計画システム
JPH10161708A (ja) * 1996-11-29 1998-06-19 Nec Corp 生産制御装置
JP2002229635A (ja) * 2001-02-06 2002-08-16 Nippon Steel Corp 製造・搬送プロセスにおける処理計画作成方法及び装置、物流制御方法及び装置、コンピュータ読み取り可能な記憶媒体、並びにコンピュータプログラム
JP2002288277A (ja) * 2001-03-27 2002-10-04 Mitsubishi Heavy Ind Ltd 離散事象制御システムと離散事象制御システムを用いた生産工程シミュレーション方法
JP2002298066A (ja) * 2001-03-29 2002-10-11 Toyota Motor Corp 輸送計画立案装置
JP2002373018A (ja) * 2001-06-14 2002-12-26 Ntn Corp 仮想工場システムおよび仮想工場・遠隔監視連携システム

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU560995B2 (en) * 1984-02-07 1987-04-30 Toshiba, Kabushiki Kaisha Process control apparatus
US5216593A (en) * 1991-01-24 1993-06-01 International Business Machines Corporation Method and apparatus for discrete activity resourse allocation through cardinality constraint generation
JPH05108649A (ja) * 1991-10-16 1993-04-30 Kobe Steel Ltd 生産・物流スケジユール作成装置
US5315521A (en) * 1992-07-29 1994-05-24 Praxair Technology, Inc. Chemical process optimization method
JP3386160B2 (ja) * 1992-11-27 2003-03-17 株式会社神戸製鋼所 稼動スケジュール作成装置
JPH0741114A (ja) * 1993-07-30 1995-02-10 Kobe Steel Ltd 物流シミュレーション装置
JPH07200675A (ja) * 1993-12-28 1995-08-04 Kobe Steel Ltd 生産工程シミュレーション装置
JP3400851B2 (ja) * 1994-04-22 2003-04-28 新日本製鐵株式会社 物流制御方法
JPH082648A (ja) * 1994-06-20 1996-01-09 Hitachi Ltd 物流オンライン制御方法とそのシステム、及び、かかるシステムに使用する物流量予測制御シミュレーション装置
JP3345203B2 (ja) * 1995-01-12 2002-11-18 株式会社日立製作所 物流オンライン制御方法とその装置
JP3333674B2 (ja) * 1995-12-01 2002-10-15 株式会社日立製作所 プラント運転計画作成方法および装置
JPH09231271A (ja) * 1996-02-22 1997-09-05 Nippon Steel Corp 自動搬送設備運行計画方法
JPH113101A (ja) * 1997-06-11 1999-01-06 Hitachi Ltd ロジスティクスチェーンシミュレーションシステム
US6405157B1 (en) 1998-05-13 2002-06-11 Nec Corporation Evaluation value computing system in production line simulator
JP2000172745A (ja) 1998-12-08 2000-06-23 Taiheiyo Cement Corp 物流計画作成装置
US6606527B2 (en) * 2000-03-31 2003-08-12 International Business Machines Corporation Methods and systems for planning operations in manufacturing plants
JP2002023823A (ja) * 2000-07-12 2002-01-25 Mitsubishi Electric Corp 生産管理システム
JP2002269192A (ja) * 2001-03-07 2002-09-20 Mitsubishi Heavy Ind Ltd 物流最適化システム
JP5023414B2 (ja) 2001-06-08 2012-09-12 大日本印刷株式会社 生産計画評価方法およびシステム
JP2003131719A (ja) * 2001-10-24 2003-05-09 Mitsubishi Heavy Ind Ltd 加工品製造日程最適化システム

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05225205A (ja) * 1992-02-14 1993-09-03 Mitsubishi Electric Corp 順次確定生産計画システム
JPH10161708A (ja) * 1996-11-29 1998-06-19 Nec Corp 生産制御装置
JP2002229635A (ja) * 2001-02-06 2002-08-16 Nippon Steel Corp 製造・搬送プロセスにおける処理計画作成方法及び装置、物流制御方法及び装置、コンピュータ読み取り可能な記憶媒体、並びにコンピュータプログラム
JP2002288277A (ja) * 2001-03-27 2002-10-04 Mitsubishi Heavy Ind Ltd 離散事象制御システムと離散事象制御システムを用いた生産工程シミュレーション方法
JP2002298066A (ja) * 2001-03-29 2002-10-11 Toyota Motor Corp 輸送計画立案装置
JP2002373018A (ja) * 2001-06-14 2002-12-26 Ntn Corp 仮想工場システムおよび仮想工場・遠隔監視連携システム

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP1701232A4 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005342787A (ja) * 2004-05-06 2005-12-15 Nippon Steel Corp 熱間圧延工場の加熱・圧延スケジュール作成装置、加熱・圧延スケジュール作成方法、コンピュータプログラム、及び読取可能な記憶媒体
JP2007206877A (ja) * 2006-01-31 2007-08-16 Nippon Steel Corp 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体
JP2008117309A (ja) * 2006-11-07 2008-05-22 Nippon Steel Corp 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、並びにコンピュータ読み取り可能な記録媒体
US10656628B2 (en) 2015-05-12 2020-05-19 Siemens Aktiengesellschaft Control device for a production module and a method for operating the control device
JP2018519590A (ja) * 2015-07-01 2018-07-19 シーメンス アクチエンゲゼルシヤフトSiemens Aktiengesellschaft 生産モジュールのための制御装置、制御装置を有する生産モジュールならびに制御装置を操作するための方法
US10671035B2 (en) 2015-07-01 2020-06-02 Siemens Aktiengesellshaft Control device for a production module, production module having a control device, and method for operating the control device
WO2018179273A1 (ja) * 2017-03-30 2018-10-04 日本電気株式会社 フロー制御システム及びその制御方法
JPWO2018179273A1 (ja) * 2017-03-30 2019-11-21 日本電気株式会社 フロー制御システム及びその制御方法
US11385625B2 (en) 2017-03-30 2022-07-12 Nec Corporation Flow control system and control method therefor
CN110442935A (zh) * 2019-07-22 2019-11-12 武汉理工大学 自动化装备生产节拍设计与优化方法
CN110442935B (zh) * 2019-07-22 2022-11-18 武汉理工大学 自动化装备生产节拍设计与优化方法

Also Published As

Publication number Publication date
BRPI0418164A (pt) 2007-06-19
EP1701232A4 (en) 2014-03-05
US20100138023A1 (en) 2010-06-03
JPWO2005062145A1 (ja) 2007-07-19
US7860595B2 (en) 2010-12-28
KR20060105027A (ko) 2006-10-09
JP4690893B2 (ja) 2011-06-01
US7676293B2 (en) 2010-03-09
TWI312490B (ja) 2009-07-21
EP1701232A1 (en) 2006-09-13
KR100831108B1 (ko) 2008-05-20
EP1701232B1 (en) 2016-03-02
TW200532519A (en) 2005-10-01
US7865260B2 (en) 2011-01-04
US20100168893A1 (en) 2010-07-01
US20070168067A1 (en) 2007-07-19

Similar Documents

Publication Publication Date Title
JP4690893B2 (ja) 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体
Bektur et al. A mathematical model and heuristic algorithms for an unrelated parallel machine scheduling problem with sequence-dependent setup times, machine eligibility restrictions and a common server
Gupta et al. From rescheduling to online scheduling
Yang et al. Optimized flowshop scheduling of multiple production lines for precast production
Faghihi et al. Construction scheduling using genetic algorithm based on building information model
Ye et al. A computationally efficient simulation-based optimization method with region-wise surrogate modeling for stochastic inventory management of supply chains with general network structures
Bertsekas Dynamic programming and optimal control: Volume I
Li et al. A multi-objective TLBO algorithm for balancing two-sided assembly line with multiple constraints
Higle et al. Production planning under supply and demand uncertainty: A stochastic programming approach
Hu et al. A simulation-based method for effective workface planning of industrial construction projects
JP2008117309A (ja) 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、並びにコンピュータ読み取り可能な記録媒体
Khayyati et al. Data-driven control of a production system by using marking-dependent threshold policy
CN116157812A (zh) 系统范围的工厂优化的优化模型的自动生成
JP4746334B2 (ja) 製造プロセスの生産計画立案方法、装置、及びコンピュータプログラム
Barik et al. Two-stage stochastic programming problems involving multi-choice parameters
Tissot et al. A hybrid simulation/optimization architecture for developing a digital twin
JP2016110592A (ja) 生産・物流スケジュール作成方法、装置及びプログラム
JP4846376B2 (ja) 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、及びコンピュータ読み取り可能な記録媒体
Ferro et al. Dynamic modeling of discrete event simulation
Ebrahimi et al. Benders decomposition algorithm for a build-to-order supply chain problem under uncertainty
JP2007004391A (ja) 生産・物流スケジュール作成装置及び方法、生産・物流プロセス制御装置及び方法、コンピュータプログラム、並びにコンピュータ読み取り可能な記録媒体
Bodi et al. Virtual Quality Management elements in optimized new product development using genetic algorithms
Bazargan-Lari et al. Intra-cell and inter-cell layout designs for cellular manufacturing
JP2006072851A (ja) 生産・物流スケジュール作成装置、生産・物流スケジュール作成方法、生産・物流プロセス制御装置、生産・物流プロセス制御方法、コンピュータプログラム及びコンピュータ読み取り可能な記録媒体
JP2006072852A (ja) 生産・物流スケジュール作成装置、生産・物流スケジュール作成方法、生産・物流プロセス制御装置、生産・物流プロセス制御方法、コンピュータプログラムおよびコンピュータ読み取り可能な記録媒体

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): BW GH GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LT LU MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DPEN Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed from 20040101)
WWE Wipo information: entry into national phase

Ref document number: 2007168067

Country of ref document: US

Ref document number: 10584423

Country of ref document: US

WWE Wipo information: entry into national phase

Ref document number: 1020067012565

Country of ref document: KR

Ref document number: 2005516528

Country of ref document: JP

NENP Non-entry into the national phase

Ref country code: DE

WWW Wipo information: withdrawn in national office

Country of ref document: DE

WWE Wipo information: entry into national phase

Ref document number: 2004807761

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 2004807761

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 1020067012565

Country of ref document: KR

ENP Entry into the national phase

Ref document number: PI0418164

Country of ref document: BR

WWP Wipo information: published in national office

Ref document number: 10584423

Country of ref document: US