KR970707350A - 장소타항의 항두처리구, 항두처리공법(抗頭處理工法) 및 장소타항공법(場所打抗工法) - Google Patents
장소타항의 항두처리구, 항두처리공법(抗頭處理工法) 및 장소타항공법(場所打抗工法) Download PDFInfo
- Publication number
- KR970707350A KR970707350A KR1019970702757A KR19970702757A KR970707350A KR 970707350 A KR970707350 A KR 970707350A KR 1019970702757 A KR1019970702757 A KR 1019970702757A KR 19970702757 A KR19970702757 A KR 19970702757A KR 970707350 A KR970707350 A KR 970707350A
- Authority
- KR
- South Korea
- Prior art keywords
- hole
- port
- cap body
- barrel
- concrete
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
콘크리트타설용 트레미관 16이 자유로이 삽통가능한 내부원통 2을 소정간격을 두고 외부원통 3으로 둘러싸는 동시에, 양 원통 2, 3의 상단을 환상의 천장판 1으로, 하단을 환상의 밑판 6으로 각각 계착하여 이중원통상의 켑본체 A를 형성하고, 또한, 이 캡본체 A의 상기 밑판 6에 소정간격을 두고 복수개의 항주근구멍 8을 뚫어 설치하는 동시에, 상기 천장판 1 및 밑판 6에 기액빼냄구멍 5(9)을 개구형성한 구성으로 한다.
Description
본 내용은 요부공개 건이므로 전문내용을 수록하지 않았음
제1도는 캡본체의 사시도이다. 제2도는 캡본체의 일부 절결사시도이다. 제3도는 외부 원통의 밑판의 절곡전평면도이다. 제4도는 캡본체의 일부 절결종단면도이다. 제5도는 캡본체의 사용상태의 설명도이다. 제7도는 내부 원통의 콘크리트를 제거하는 설명도이다. 제8도는 캡본체 A의 다른 실시예를 나타내는 일부 절결사시도이다. 제9도는 캡본체 A의 다른 실시예를 나타내는 일부 절결사시도이다. 제10도는 캡본체 A의 또 다른 실시예를 나타내는 일부 절결사시도이다. 제11도는 캡본체 A의 다른 실시예의 사시도이다.
Claims (8)
- 콘크리트타설용 트레미관 16이 자유로이 삽통가능한 내부원통 2을 소정간격을 두고 외부원통 3으로 둘러싸는 동시에, 양 원통 2, 3의 상단을 환상의 천장판 1으로, 하단을 환상의 밑판 6으로 각각 계착하여 이중원통상의 캡본체 A를 형성하고, 또한, 이 캡본체 A의 상기 밑판 6에 소정간격을 두고 복수개의 항주근구멍 8을 뚫어 설치하는 동시에, 상기 천장판 1 및 밑판 6에 기액누출구멍 5(9)을 개구형성한 것을 특징으로 하는 장소타항(場所打抗)의 항두처리구(抗頭處理具).
- 제1항에 있어서, 상기 내부원통 2과 외부원통 3은 동일한 길이로 천장판 1 및 밑판 6을 수평판상으로 상기 양 원통 2, 3의 상단 및 하단에 계착한 것을 특징으로 하는 장소타항의 항두처리구.
- 외부원통 3의 천정판 1의 외부주위가장자리쪽에, 복수개의 기액빼냄구멍 5을 뚫어설치하는 동시에, 상기 천정판 1의 중앙에 콘크리트타설용 트레미관 16이 자유로이 삽통가능한 상부 트레미구 4를 뚫어 설치하고, 이 상부 트레미구 4의 하측에 계착하고, 상기 외부원통 3보다 2% 내지 3% 짧은 상하면 개방형의 내부원통 2을 관설하고 이중원통을 형성하여 이루어지는 캡본체 A에 있어서, 상기 외부원통 3의 밑판 6의 외부주위가장 자리쪽으로의 평탄지역 6a에, 거의 같은 간격으로 복수개의 항주근구멍 8을 뚫어 설치하고, 또한 이 밑판 6의 중앙에 뚫어 설치한 하부트레미구 7의 주위가장자리에, 방사상르로 절입한 복수개의 슬릿 9을, 거의 같은 간격에 또한 상기 평탄지역 6a을 남겨서 형성하고, 또한 각 슬릿 9에 의하여 생긴 슬릿편 9a을 경사지게 윗쪽으로 절곡하고, 이 슬릿편 9a의 선단을 상기 내부원통 2의 아래가장자리에 고착하여 형성한 것을 특징으로 하는 장소타항의 항두처리구.
- 제1항 내지 제3항 중 어느 하나의 항에 있어서, 상기 천장판 1 또는 밑판 6을, 망체 또는 펑칭메탈에 의하여 형성한 것을 특징으로 하는 장소타항의 항두처리구.
- 제1항 내지 제4항중의 어느하나의 항에 있어서, 상기 철근농 14에 캡본체 A를 관착하는 동시에, 캡본체 A와 철근농 14을 자유로이 착탈하는 체인과 와이어, 끈 등의 색조 23로 묶어서 고착하고, 이 철근농 14을 굴삭구멍 17에 세워넣도록 한 것을 특징으로 하는 장소타항의 항두처리구를 사용하는 항두처리공법.
- 제1항 내지 제4항중 어느 하나의 항에 있어서, 상기 철근농 14에 캡본체 A를 스타트용접으로 관삽고착하여 굴삭구멍 17에 세워넣고, 뒤이어 상기 캡본체 A의 내부원통 2에 의해 트레미관 16을 굴삭구멍 17에 세워넣으며, 상기 굴삭구멍 17의 밑부로부터 상기 내부원통 2천정면에 이르기까지, 연속적으로 콘크리트타설을 행한 후, 곧 캐리바 19에 취부한 굴삭바켓트 18를 회전시키므로써, 내부원통에 충전된 슬라임혼합콘크리트를 제거하는 것을 특징으로 하는 장소타항의 항두처리구를 사용하는 항두처리공법.
- 굴삭한 구멍에 철근집을 세워 넣은 후, 굴삭구멍내에 콘크리트를 타설하는 장소 타항공법에 있어서, 시트재로 형성된 밑면이 있는 통상의 자루체내에 철근집을 넣은 후, 자루체체내에 콘크리트를 타설하는 것을 특징으로 하는 장소타항공법.
- 제7항에 있어서, 상기 시트재로 형성된 밑면이 있는 통상(有底筒狀)으로서, 통부를 옆쪽으로 개구하기 위한 절결부가 통부(筒部)의 세로방향으로 설치되고, 또한 이 절결부에 파스너가 취부된 자루체를 이용하여, 파스너의 슬라이더를 끌어내려서 통부를 개구시킨 자루체의 밑부를, 굴삭구멍의 구멍입구에 위치시키는 동시에, 굴삭구멍의 구멍입구에 파스너의 슬라이더를 고정하고, 철근집의 세워넣음에 의하여 자루체를 구멍내로 밀어넣는 동시에, 구멍내의 수분을 자루체의 통부의 절결부에서 자루체내로 도입하면서 자루체의 통부를 파스너로 닫도록 한 것을 특징으로 하는 장소타항공법.※ 참고사항 : 최초출원 내용에 의하여 공개하는 것임.
Applications Claiming Priority (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30058394 | 1994-12-05 | ||
JP94-300583 | 1994-12-05 | ||
JP22821595A JPH0971933A (ja) | 1995-09-05 | 1995-09-05 | 場所打ちコンクリート杭工法 |
JP95-228215 | 1995-09-05 | ||
JP28364595A JPH08209686A (ja) | 1994-12-05 | 1995-10-31 | 場所打杭の杭頭処理具及び杭頭処理工法 |
JP95-283645 | 1995-10-31 |
Publications (2)
Publication Number | Publication Date |
---|---|
KR970707350A true KR970707350A (ko) | 1997-12-01 |
KR100428018B1 KR100428018B1 (ko) | 2004-09-10 |
Family
ID=27331373
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019970702757A KR100428018B1 (ko) | 1994-12-05 | 1995-11-27 | 현장치기콘크리트파일의파일헤드처리구,파일헤드처리공법및현장치기콘크리트파일공법 |
Country Status (6)
Country | Link |
---|---|
US (1) | US5961253A (ko) |
EP (1) | EP0796948B1 (ko) |
KR (1) | KR100428018B1 (ko) |
CN (1) | CN1077942C (ko) |
DE (1) | DE69528377D1 (ko) |
WO (1) | WO1996018001A1 (ko) |
Families Citing this family (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19746731A1 (de) * | 1997-10-13 | 1999-05-06 | Huang Chia Hsiung | C-Profil-Pfahl und Verfahren zum Einbringen von C-Profil-Pfählen |
JP3284110B2 (ja) * | 1998-12-17 | 2002-05-20 | 韓国道路公社 | 鋼管杭用蓋板 |
CN1189630C (zh) * | 2000-07-20 | 2005-02-16 | 斯马泰克工程技术株式会社 | 用于结合钢管桩的头部和混凝土基础的结合件和结合结构 |
KR200212743Y1 (ko) * | 2000-08-09 | 2001-02-15 | 배정효 | 기초공사용 강관의 상단부 보강구조 |
US6568881B2 (en) | 2001-10-15 | 2003-05-27 | Walter Daniel Long | Jet head device for sinking pilings |
GB2400880A (en) * | 2003-04-22 | 2004-10-27 | Cordek Ltd | Former for use in removing the tops of piles |
US6893598B1 (en) | 2003-09-05 | 2005-05-17 | Mark A. March | Finishing guide for concrete piers |
US8206064B2 (en) * | 2005-10-20 | 2012-06-26 | University Of South Florida | Voided drilled shafts |
US7735273B2 (en) * | 2006-01-17 | 2010-06-15 | Morton Buildings | Poured concrete column hole |
US7360315B2 (en) | 2006-01-17 | 2008-04-22 | Morton Buildings | Poured concrete column alignment and plumbing tool |
KR100742540B1 (ko) * | 2006-04-12 | 2007-07-25 | (주) 대호바콘텍 | 확대기초구조물용 콘크리트 말뚝의 헤드커버 |
US20080008539A1 (en) * | 2006-07-05 | 2008-01-10 | Con-Tech Systems Ltd. | Void form for constructing post-tensioned foundation piles |
US8109057B2 (en) * | 2008-03-03 | 2012-02-07 | Daniel Stark | Tower foundation system |
US20100257794A1 (en) * | 2009-04-10 | 2010-10-14 | Stark N Daniel W | Lateral support device |
US8381479B1 (en) * | 2009-09-28 | 2013-02-26 | Felix E. Ferrer | Pre-fabricated modular reinforcement cages for concrete structures |
CN101812844A (zh) * | 2010-02-10 | 2010-08-25 | 郭振国 | 一种桥梁桩基用护筒 |
US20120042605A1 (en) * | 2010-08-17 | 2012-02-23 | Turner Michael L | Removable Support Cage For Top Of Drilled Pier |
IT1402942B1 (it) * | 2010-12-10 | 2013-09-27 | Fondazioni Speciali S P A | Palo di fondazione, particolarmente del tipo trivellato |
CN102444117A (zh) * | 2011-09-16 | 2012-05-09 | 中铁第四勘察设计院集团有限公司 | 黄土地区钢筋混凝土防护桩施工方法 |
JP6153764B2 (ja) * | 2013-04-23 | 2017-06-28 | 株式会社サンエイ | スライム除去バケットおよびこれを用いた杭頭処理工法 |
CN104234038A (zh) * | 2014-03-03 | 2014-12-24 | 王磊 | 一种灌注桩免破碎桩头施工工艺 |
TWI609117B (zh) * | 2014-04-07 | 2017-12-21 | Centrifugal pre-tensioned concrete pile with exhaust function | |
CN104695424B (zh) * | 2015-03-18 | 2016-08-31 | 建华建材(莱阳)有限公司 | 复合地基用预制空心桩桩帽及其固定方法 |
CN106400783B (zh) * | 2016-08-12 | 2018-07-03 | 武汉志和岩土工程有限公司 | 采用展开式钢筋笼制成灌注桩的施工方法 |
JP6909607B2 (ja) * | 2017-03-28 | 2021-07-28 | 大成建設株式会社 | 場所打ち杭および基礎の構築方法 |
CN106996107A (zh) * | 2017-05-26 | 2017-08-01 | 中交第二航务工程局有限公司 | 一种灌注桩桩头的破除装置及其施工方法 |
CN107268627B (zh) * | 2017-07-14 | 2019-08-23 | 中国一冶集团有限公司 | 一种适用于大型钻孔灌注桩桩头破除方法 |
US10808412B2 (en) * | 2017-07-31 | 2020-10-20 | Mohammad Reza Ehsani | Spacers for repair of columns and piles |
US20190311594A1 (en) * | 2018-04-10 | 2019-10-10 | Kidde Technologies, Inc. | Container for lithium battery |
WO2020000714A1 (zh) | 2018-06-28 | 2020-01-02 | 北京金风科创风电设备有限公司 | 阻尼器以及具有该阻尼器的承载围护结构 |
CN110630680B (zh) * | 2018-06-28 | 2020-12-18 | 北京金风科创风电设备有限公司 | 阻尼器以及具有该阻尼器的承载围护结构 |
CN109235437A (zh) * | 2018-10-30 | 2019-01-18 | 中铁北京工程局集团有限公司 | 一种破除桩头方法 |
KR102016366B1 (ko) * | 2019-04-12 | 2019-10-21 | 정훈식 | 현장타설 콘크리트파일의 두부정리장치 및 두부정리방법 |
CN110344389A (zh) * | 2019-07-03 | 2019-10-18 | 深圳市工勘岩土集团有限公司 | 塔式地下水压力回灌设备 |
CN110725308A (zh) * | 2019-09-17 | 2020-01-24 | 中铁大桥局集团第五工程有限公司 | 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 |
WO2023080774A1 (en) * | 2021-11-05 | 2023-05-11 | Will N Well Property Sdn Bhd | A system for guiding tremie pipe placement and a method for using thereof |
CN115075224B (zh) * | 2022-07-12 | 2023-07-07 | 中建八局第一建设有限公司 | 一种钢柔结合的预制管桩多功能挡板及实现方法 |
Family Cites Families (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2571549A (en) * | 1949-06-20 | 1951-10-16 | Luther T Dunning | Method of erecting reinforced concrete structures |
DE1298459B (de) * | 1965-09-08 | 1969-06-26 | Pleuger Friedrich Wilhelm | Schlauchschalung zum Herstellen von Ortbetonpfaehlen |
US3487646A (en) * | 1968-08-19 | 1970-01-06 | Paul Henri Gatien | Load bearing pile |
JPS491007A (ko) * | 1972-04-19 | 1974-01-08 | ||
CA1041780A (en) * | 1975-03-26 | 1978-11-07 | Pynford Limited | Pile |
JPS5880020A (ja) * | 1981-11-02 | 1983-05-14 | Hasegawa Komuten Co Ltd | 場所打ち杭の杭頭処理工法 |
US4472085A (en) * | 1981-12-14 | 1984-09-18 | The Union Metal Manufacturing Co. | Caisson cap |
JPS6030714A (ja) * | 1983-07-27 | 1985-02-16 | Komatsu Ltd | 場所打ち杭の杭頭処理装置 |
JPS60119815A (ja) * | 1983-12-03 | 1985-06-27 | Hasegawa Komuten Co Ltd | 余盛コンクリ−ト除去用バケツト |
JPH01219214A (ja) * | 1988-02-26 | 1989-09-01 | Shuzo Tamoto | 場所打ちコンクリートぐいのくい頭処理方法 |
JPH01322020A (ja) * | 1988-06-23 | 1989-12-27 | Masaharu Ookawa | 場所打杭の杭頭処理用キャップ |
JP2844016B2 (ja) * | 1990-10-11 | 1999-01-06 | 大成建設株式会社 | 場所打ち杭構築工法 |
CH683197A5 (de) * | 1990-12-19 | 1994-01-31 | Eggstein Ag | Länglicher Stützkorb, zur Herstellung eines Betonpfahles. |
US5359829A (en) * | 1992-12-07 | 1994-11-01 | Voita John M | Fabrication and installation of steel reinforcement cages for pier foundations |
US5423633A (en) * | 1993-12-23 | 1995-06-13 | Beheersmaatschappij Verstraeten B.V. | Piling apparatus adapted to be provided in a tube |
-
1995
- 1995-11-27 DE DE69528377T patent/DE69528377D1/de not_active Expired - Lifetime
- 1995-11-27 KR KR1019970702757A patent/KR100428018B1/ko not_active IP Right Cessation
- 1995-11-27 US US08/836,696 patent/US5961253A/en not_active Expired - Fee Related
- 1995-11-27 CN CN95196621A patent/CN1077942C/zh not_active Expired - Fee Related
- 1995-11-27 EP EP95938611A patent/EP0796948B1/en not_active Expired - Lifetime
- 1995-11-27 WO PCT/JP1995/002438 patent/WO1996018001A1/ja active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
WO1996018001A1 (fr) | 1996-06-13 |
CN1077942C (zh) | 2002-01-16 |
EP0796948A1 (en) | 1997-09-24 |
CN1168707A (zh) | 1997-12-24 |
KR100428018B1 (ko) | 2004-09-10 |
US5961253A (en) | 1999-10-05 |
EP0796948A4 (en) | 1999-05-06 |
EP0796948B1 (en) | 2002-09-25 |
DE69528377D1 (de) | 2002-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR970707350A (ko) | 장소타항의 항두처리구, 항두처리공법(抗頭處理工法) 및 장소타항공법(場所打抗工法) | |
GB2158493A (en) | Method of installing a pile | |
EP0902129A3 (de) | Verfahren und Vorrichtung für den Rohreinbau | |
JP2000144719A (ja) | コンクリート矢板及びその打込み方法 | |
DE10025966A1 (de) | Stützschlauch-Säulen | |
JPH05230823A (ja) | 超軟弱地盤改良用水平ドレーン材敷設方法 | |
DE1784739A1 (de) | Verfahren und Vorrichtung zur Herstellung von Schaechten,Revisionskammern und Roehrenverbindungen | |
JP7252608B2 (ja) | 立坑用ケーシングおよび土留工法 | |
JPH0673727A (ja) | ソイル杭柱列山留め壁の構築方法と特殊h型鋼 | |
JPS6044452B2 (ja) | 地中埋設管の基礎定着方法 | |
JPS6032200Y2 (ja) | 砂杭案内管 | |
JPS6233772Y2 (ko) | ||
JPH09195267A (ja) | 地盤の液状化防止装置 | |
JPS60364Y2 (ja) | 水中コンクリ−ト打設装置 | |
JPH0411110A (ja) | 浸透管及び浸透管の推進埋設工法 | |
JPH11270130A (ja) | コンクリ―ト成形型枠 | |
KR100358994B1 (ko) | 수로장치 | |
JPS6133072Y2 (ko) | ||
JPH0447247Y2 (ko) | ||
JP2652567B2 (ja) | トンネル等構築方法及び装置 | |
JPH0771039A (ja) | 法面用スペーサー | |
JP2858050B2 (ja) | 立坑掘削工法 | |
JP3014481U (ja) | 水抜パイプインナー保持具 | |
JPH0535175Y2 (ko) | ||
JPS6178915A (ja) | 地中連続壁の造成工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20070327 Year of fee payment: 4 |
|
LAPS | Lapse due to unpaid annual fee |