CN110725308A - 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 - Google Patents
桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 Download PDFInfo
- Publication number
- CN110725308A CN110725308A CN201910874993.8A CN201910874993A CN110725308A CN 110725308 A CN110725308 A CN 110725308A CN 201910874993 A CN201910874993 A CN 201910874993A CN 110725308 A CN110725308 A CN 110725308A
- Authority
- CN
- China
- Prior art keywords
- reinforcement cage
- pile foundation
- pile
- limiting device
- limiting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种桩基钢筋笼安装平面位置精确定位施工方法及限位装置,它先是在桩基钢筋笼下放到钢护筒内节段时,先对准桩基钢筋笼的中心与设置桩的中心,再测量出桩基钢筋笼与钢护筒内壁的间隙并根据测量结果用不同长度的限位装置进行限位,从而达到精确限位的目的。本发明具有在桩基钢筋笼安装时能保证钢筋笼中心处于桩基钻孔桩的桩位中心、偏位控制在毫米级偏差范围内、安装平面位置能够精确定位、使用既有材料、制作方便、成本投入小、施工难度小、工程进度快、简单快捷、不影响钻孔桩质量、符合绿色建造与绿色施工要求的优点。
Description
技术领域
本发明涉及桥梁基础施工方法,尤其是涉及一种在设有钢护筒的情况下利用既有材料进行桥梁工程桩基施工的桩基钢筋笼安装精确定位的施工方法及限位装置。
背景技术
随着我国经济的迅速发展,交通基础装置的建设也得到迅猛发展,与此同时在我国江河湖面上修建的桥梁也随之增多。众所周知,修建桥梁首先要进行钻孔桩施工,而桩基作为桥梁的基础,其施工质量至关重要。
群桩基础的偏心控制范围为不超过100mm,超过了允许值,将对桩基、承台的受力产生影响。传统施工方法是直接利用吊挂系统调节和限位桩基钢筋笼,桩基钢筋笼在混凝土浇筑过程中容易受到扰动而发生偏位。为了更好的控制桩基钢筋笼的安装精度,需要一种装置固定桩基钢筋笼的平面位置,且不能对桩基的质量产生影响。
发明内容
本发明的第一个目的在于提供一种在桩基钢筋笼安装时能保证钢筋笼中心处于桩基钻孔桩的桩位中心、偏位控制在毫米级偏差范围内、安装平面位置能够精确定位的施工方法。
本发明的第二个目的在于提供一种使用既有材料、制作方便、简单快捷、不影响钻孔桩质量的限位装置。
本发明的第一个目的是这样实现的:
桩基钢筋笼安装平面位置精确定位的施工方法,特征是:具体步骤如下:
A、将桩基钢筋笼下放到钢护筒内节段时暂停下放,测量放出设计桩的中心位置并用十字线标识,十字线方向与即将安装的限位装置方向一致;
B、调整桩基钢筋笼的中心与设置桩的中心对中,用直尺测量限位点与钢护筒内壁之间的距离,在同一标高平面设置4个限位点,在钢护筒内设置有多道限位装置;
C、根据测量结果在限位点处焊接限位装置于钢筋笼的加劲箍上,保证限位装置上的混凝土垫块与钢护筒的内壁距离控制在2mm内;
D、下放钢筋笼到设计位置,完成桩基钢筋笼平面位置精确定位。
限位点设置在桩顶标高以下的加劲箍上,能保证桩基混凝土浇筑后限位装置完全包裹在桩基混凝土里面。
本发明的第二个目的是这样实现的:
桩基钢筋笼安装平面位置精确定位施工方法中的限位装置,特征是:限位装置由“U”型钢筋和保护层垫块两大部分组成,保护层垫块 的一端固定在钢护筒 的内壁上,“U”型钢筋穿过保护层垫块中间的安装孔后,使得“U”型钢筋和保护层垫块固定在一起;“U”型钢筋开口方向的两个端部与钢筋笼加劲箍焊接,使得“U”型钢筋与钢筋笼加劲箍固定在一起。
“U”型钢筋由直径Φ16的钢筋制作而成,保护层垫块采用与钢筋笼保护层垫块相同的垫块。
本发明采用制作钢筋笼箍筋的边角料,即直径Φ16的钢筋制作而成“U”型钢筋;采用与钢筋笼保护层垫块相同的垫块。“U”型钢筋穿过保护层垫块后,开口方向与钢筋笼加劲箍焊接。材料为既有材料,且利用了边角料,成本投入小、施工难度小、工效快,且符合绿色建造与绿色施工的要求。
因此,本发明具有在钢筋笼安装时能保证钢筋笼中心处于桩基钻孔桩的桩位中心、偏位控制在毫米级偏差范围内、安装平面位置能够精确定位、使用既有材料、制作方便、成本投入小、施工难度小、工程进度快、简单快捷、不影响钻孔桩质量、符合绿色建造与绿色施工要求的优点。
附图说明
图1 为本发明的限位装置安装的立面示意图;
图2 为图1中A-A向的剖视图;
图3 为限位装置的结构示意图。
具体实施方式
下面结合实施例对本发明作进一步详细说明。
桩基钢筋笼安装平面位置精确定位的施工方法,具体步骤如下:
A、主墩桩基直径为2.8m,采用3.0米钢护筒1;桩基钢筋笼2及限位装置3均提前制作完成;桩基钢筋笼2下放到钢护筒1内节段时暂停下放,测量放出设计桩的中心位置并用十字线标识;十字线方向与即将安装的限位装置3方向一致;
B、调整桩基钢筋笼2的中心与设置桩的中心对中,用直尺测量限位点与钢护筒1内壁之间的距离;在同一标高平面设置四个限位点,根据钢护筒1的长度在钢护筒1内设置多道限位装置,限位点设置在桩顶标高以下的加劲箍4上,能保证桩基混凝土浇筑后限位装置3完全包裹在桩基混凝土里面,以免出现耐久性问题;
C、根据测量结果在限位点焊接限位装置3于桩基钢筋笼上2上,保证限位装置3上的混凝土垫块与钢护筒1内壁距离控制在2mm内;
D、下放桩基钢筋笼2到设计位置,完成桩基钢筋笼2平面位置精确定位。
桩基钢筋笼安装平面位置精确定位施工方法中的限位装置,由“U”型钢筋5和保护层垫块6两大部分组成,采用制作钢筋笼箍筋的边角料,即直径Φ16的钢筋制作成“U”型钢筋5;保护层垫块6采用与钢筋笼保护层垫块相同的垫块;保护层垫块6 的一端固定在钢护筒1 的内壁上,“U”型钢筋5穿过保护层垫块6中间的安装孔7后,使得“U”型钢筋5和保护层垫块6固定在一起;“U”型钢筋5开口方向的两个端部与钢筋笼加劲箍4焊接,使得“U”型钢筋5与钢筋笼加劲箍4固定在一起。
Claims (4)
1.一种桩基钢筋笼安装平面位置精确定位的施工方法,其特征在于:具体步骤如下:
A、将桩基钢筋笼下放到钢护筒内节段时暂停下放,测量放出设计桩的中心位置并用十字线标识,十字线方向与即将安装的限位装置方向一致;
B、调整桩基钢筋笼的中心与设置桩的中心对中,用直尺测量限位点与钢护筒内壁之间的距离,在同一标高平面设置4个限位点,在钢护筒内设置有多道限位装置;
C、根据测量结果在限位点处焊接限位装置于钢筋笼的加劲箍上,保证限位装置上的混凝土垫块与钢护筒的内壁距离控制在2mm内;
D、下放钢筋笼到设计位置,完成桩基钢筋笼平面位置精确定位。
2.根据权利要求1所述的桩基钢筋笼安装平面位置精确定位的施工方法,其特征在于:限位点设置在桩顶标高以下的加劲箍上,能保证桩基混凝土浇筑后限位装置完全包裹在桩基混凝土里面。
3.桩基钢筋笼安装平面位置精确定位施工方法中的限位装置,其特征在于:限位装置由“U”型钢筋和保护层垫块两大部分组成,保护层垫块 的一端固定在钢护筒 的内壁上,“U”型钢筋穿过保护层垫块中间的安装孔后,使得“U”型钢筋和保护层垫块固定在一起;“U”型钢筋开口方向的两个端部与钢筋笼加劲箍焊接,使得“U”型钢筋与钢筋笼加劲箍固定在一起。
4.根据权利要求1所述的桩基钢筋笼安装平面位置精确定位施工方法中的限位装置,其特征在于:“U”型钢筋由直径Φ16的钢筋制作而成,保护层垫块采用与钢筋笼保护层垫块相同的垫块。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910874993.8A CN110725308A (zh) | 2019-09-17 | 2019-09-17 | 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910874993.8A CN110725308A (zh) | 2019-09-17 | 2019-09-17 | 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110725308A true CN110725308A (zh) | 2020-01-24 |
Family
ID=69219021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910874993.8A Pending CN110725308A (zh) | 2019-09-17 | 2019-09-17 | 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110725308A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112663600A (zh) * | 2020-12-14 | 2021-04-16 | 中铁十六局集团第一工程有限公司 | 一种富水砂质地层钻孔灌注桩施工方法 |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1996018001A1 (fr) * | 1994-12-05 | 1996-06-13 | Shogen Okawa | Outil a traiter les tetes de pieux coules sur place, procede de traitement de tetes de pieux et procede de realisation de pieux coules sur place |
JP2008069577A (ja) * | 2006-09-14 | 2008-03-27 | Okumura Corp | 杭鉄筋籠の建て込み方法および杭鉄筋籠の建て込み装置 |
KR100832871B1 (ko) * | 2007-11-07 | 2008-05-28 | 노연식 | 피에이치씨 파일의 두부 보강장치 |
CN102767176A (zh) * | 2012-07-25 | 2012-11-07 | 中建三局第二建设工程有限责任公司 | 一种桩基钢筋笼吊装定位施工方法 |
CN203429623U (zh) * | 2013-08-27 | 2014-02-12 | 浙江大学城市学院 | 水上桩基钢筋笼结构 |
CN205502008U (zh) * | 2016-03-30 | 2016-08-24 | 上海城建市政工程(集团)有限公司 | 一种用于突变截面钻孔桩桩护筒上的定位结构 |
CN208563308U (zh) * | 2018-04-09 | 2019-03-01 | 中国一冶集团有限公司 | 钻孔灌注桩钢筋笼保护层厚度环形控制垫块 |
CN109610458A (zh) * | 2019-01-15 | 2019-04-12 | 五冶集团上海有限公司 | 一种人工挖孔灌注桩钢筋笼偏位预防装置及其使用方法 |
CN208856776U (zh) * | 2018-08-30 | 2019-05-14 | 中交二航局第二工程有限公司 | 便于大型钢筋笼下放及固定的装置 |
CN209293294U (zh) * | 2018-07-26 | 2019-08-23 | 中国一冶集团有限公司 | 一种多功能钢筋笼施工装置 |
-
2019
- 2019-09-17 CN CN201910874993.8A patent/CN110725308A/zh active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1996018001A1 (fr) * | 1994-12-05 | 1996-06-13 | Shogen Okawa | Outil a traiter les tetes de pieux coules sur place, procede de traitement de tetes de pieux et procede de realisation de pieux coules sur place |
JP2008069577A (ja) * | 2006-09-14 | 2008-03-27 | Okumura Corp | 杭鉄筋籠の建て込み方法および杭鉄筋籠の建て込み装置 |
KR100832871B1 (ko) * | 2007-11-07 | 2008-05-28 | 노연식 | 피에이치씨 파일의 두부 보강장치 |
CN102767176A (zh) * | 2012-07-25 | 2012-11-07 | 中建三局第二建设工程有限责任公司 | 一种桩基钢筋笼吊装定位施工方法 |
CN203429623U (zh) * | 2013-08-27 | 2014-02-12 | 浙江大学城市学院 | 水上桩基钢筋笼结构 |
CN205502008U (zh) * | 2016-03-30 | 2016-08-24 | 上海城建市政工程(集团)有限公司 | 一种用于突变截面钻孔桩桩护筒上的定位结构 |
CN208563308U (zh) * | 2018-04-09 | 2019-03-01 | 中国一冶集团有限公司 | 钻孔灌注桩钢筋笼保护层厚度环形控制垫块 |
CN209293294U (zh) * | 2018-07-26 | 2019-08-23 | 中国一冶集团有限公司 | 一种多功能钢筋笼施工装置 |
CN208856776U (zh) * | 2018-08-30 | 2019-05-14 | 中交二航局第二工程有限公司 | 便于大型钢筋笼下放及固定的装置 |
CN109610458A (zh) * | 2019-01-15 | 2019-04-12 | 五冶集团上海有限公司 | 一种人工挖孔灌注桩钢筋笼偏位预防装置及其使用方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112663600A (zh) * | 2020-12-14 | 2021-04-16 | 中铁十六局集团第一工程有限公司 | 一种富水砂质地层钻孔灌注桩施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111455855B (zh) | 一种双塔单索面矮塔斜拉桥主桥的施工工艺 | |
CN214740055U (zh) | 一种钢管柱高精度调垂装置 | |
CN100516378C (zh) | 采用横隔式预应力混凝土管桩对建筑基坑进行支护的方法 | |
CN110725308A (zh) | 桩基钢筋笼安装平面位置精确定位的施工方法及限位装置 | |
CN111549815A (zh) | 一种钢结构基础地脚螺栓预埋施工工法 | |
CN105735228A (zh) | 高扬程齿爬式升船机齿条系统施工方法及安装精度控制方法 | |
CN105971028B (zh) | 托换柱粘结滑移试验装置及方法 | |
CN215760524U (zh) | 一种主体结构楼板厚度控制块 | |
CN205742129U (zh) | 一种垂直升船机平衡重轨道快速安装调整装置 | |
CN115058977A (zh) | 城市桥梁预制装配式墩柱施工方法 | |
CN115256615A (zh) | 一种高速公路预制箱梁智能沐淋养护标准施工系统 | |
CN109443328B (zh) | 一种预应力管道坐标定位尺及其使用方法 | |
CN210636480U (zh) | 一种快速准确测量管桩桩位的测量装置 | |
CN210221357U (zh) | 一种埋入式应力传感器固定装置 | |
CN111335305A (zh) | 基于抗拔桩的双护筒零摩擦静载检测施工方法 | |
CN206916632U (zh) | 悬臂t型刚构线型监测点安装结构 | |
CN113048961A (zh) | 一种用于独立基础定位的测量工具及使用方法 | |
CN108709588B (zh) | 一种用于巷道围岩的多参数监测装置及其制备方法 | |
CN111005382A (zh) | 一种控制预应力混凝土管桩垂直度的装置 | |
CN220704604U (zh) | 一种快速测量预应力高强混凝土管桩垂直度的装置 | |
CN205742165U (zh) | 钢筋笼主筋检查尺 | |
CN214783319U (zh) | 装配式桥梁系梁顶预埋钢筋定位装置 | |
CN214034848U (zh) | 一种装配式建筑基础柱筋精准定位工具 | |
CN219211466U (zh) | 预制t梁钢筋胎架装置 | |
CN214583263U (zh) | 一种用于独立基础定位的测量工具 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200124 |
|
WD01 | Invention patent application deemed withdrawn after publication |