CN102808465B - Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination - Google Patents

Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination Download PDF

Info

Publication number
CN102808465B
CN102808465B CN201210281096.4A CN201210281096A CN102808465B CN 102808465 B CN102808465 B CN 102808465B CN 201210281096 A CN201210281096 A CN 201210281096A CN 102808465 B CN102808465 B CN 102808465B
Authority
CN
China
Prior art keywords
precast
shear wall
post
prefabricated
node
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210281096.4A
Other languages
Chinese (zh)
Other versions
CN102808465A (en
Inventor
赵唯坚
孙长征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201210281096.4A priority Critical patent/CN102808465B/en
Publication of CN102808465A publication Critical patent/CN102808465A/en
Application granted granted Critical
Publication of CN102808465B publication Critical patent/CN102808465B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention relates to the field of assembled concrete structures, in particular to an assembly connecting structure and an assembly connecting method of an assembled concrete frame and shear wall combination. A cast-in-place strip is disposed between precast columns and precast shear walls to connect column-wall embedded rebars. Vertical through holes are reserved in a precast node-precast beam integrated component to achieve communicated connection of vertical rebars for the upper and lower columns and the upper and lower shear walls. Embedded steel sleeves at the lower ends of the precast columns and the precast shear walls are mutually embedded with projecting rebar segments extending up out of the lower columns and the lower walls, and are integrated with the lower columns and the lower walls through cast mortar. The projecting straight rebars at the upper ends of the precast columns and the precast walls penetrate through the through holes reserved in the precast node-precast beam integrated component and protrude a floor slab, and the precast columns and the precast nodes are firmly integrated with the precast shear walls precast beams by cast mortar. Wet operations such as in-place casting of concrete are reduced to the maximum extent, building quality is improved, construction period is shortened, and energy conservation and emission reduction are achieved.

Description

The assembled syndeton of assembly concrete Frame-Shear Wall and assembled method of attachment
[technical field]
The present invention relates to prefabricated concrete structure field, be specially a kind of assembled system of fractionation of prefabricated assembled or assembled integral (hereinafter to be referred as the assembling) concrete frame-shear wall structure being formed by prefabricated post, precast wall body, prefabricated node and precast beam, member connects structure, by this assembled system and the works that is connected structure construction, and assembled method of attachment.
[background technology]
The prior art of prefabricated concrete structure only limits to pure frame structure and shear wall structure, and the assembly concrete frame shear wall structure being made up of prefabricated post, precast wall body, prefabricated node and precast beam there is not yet work literary composition.Compared with pure frame structure or shear wall structure, because concrete frame-shear wall structure is the combination of wire rod and plane materiel, particularly shear wall is cut off by beam and column, causes the steel bar stress assembling difficulty that continues large, there is no at present effective solution.Up to the present, concrete frame-shear wall structure is mainly to build by complete cast-in-place engineering method.The conventional way of assembling frame structure is that beam and column is prefabricated, and node is cast-in-place, and its subject matter is that the interspersed connection that crosses of the reinforcing bar of all directions beam and column is anchored in joint cores, causes arrangement of reinforcement constructional difficulties, is difficult to guarantee node construction quality.The current practice of fabricated shear wall structure is, upper and lower wall vertical reinforcement adopts preformed hole reinforcing bar slurry anchor overlap joint, and left and right wall horizontal reinforcement adopts cast-in-place band overlap joint, its subject matter is that vertical reinforcement is generally double-sided ribs, its radical is too much, and lap length is longer, is not easy to construction.
[summary of the invention]
The object of the present invention is to provide a kind of assembled syndeton of assembling and construction method of concrete frame-shear wall structure, rationally effectively split assembled system and member connected mode by adopting, reduce to greatest extent the wet trades such as cast-in-place concrete, improve assemblingization degree, realize energy-saving and emission-reduction, raise labour productivity, improve construction quality, the reduction of erection time.
technical scheme of the present invention:
The assembled syndeton of a kind of assembly concrete Frame-Shear Wall, form structure by prefabricated or partial precast post, prefabricated or partial precast shear wall, prefabricated or partial precast beam column node core area and prefabricated or partial precast beam and split assembled system, wherein: prefabricated or partial precast post, hereinafter to be referred as prefabricated post; Prefabricated or partial precast shear wall, hereinafter to be referred as dry wall; Prefabricated or partial precast beam column node core area, hereinafter to be referred as prefabricated node; Prefabricated or partial precast beam, hereinafter to be referred as precast beam; Joint cores and beam adopt integrated prefabricated mode, hereinafter to be referred as prefabricated node precast beam integrated component, the reserved through hole of the interspersed main muscle of post and shear wall vertical reinforcement are set in prefabricated node precast beam integrated component;
The lower end embedded bar sleeve of prefabricated post, mutually chimeric with the reinforcing bar nose section that lower floor post is stretched up, by note mortar in sleeve and connected horizontal joint, be connected to entirety with lower floor post;
The lower end embedded bar sleeve of precast shear wall, mutually chimeric with the reinforcing bar nose section that lower floor wall is stretched up, by perfusion mortar in sleeve and connected horizontal joint, be connected to entirety with lower floor precast shear wall;
Cast-in-place band is set between prefabricated post and precast shear wall, and coupled columns side embedded bar and precast shear wall end face embedded bar carry out level connection joint in cast-in-place band, make post and precast shear wall be connected to entirety by cast-in-place concrete;
The upper end of prefabricated post is outstanding straight reinforcing bar, run through the reserved through hole of the node area arranging in prefabricated node precast beam integrated component and protrude from floor face, perfusion mortar in horizontal joint between reserved through hole and post upper end and node, making post and node fixed is entirety;
The upper end of precast shear wall is outstanding straight reinforcing bar, run through and the reserved through hole in Liang district is set in prefabricated node precast beam integrated component and protrudes from floor face, perfusion mortar in horizontal joint between reserved through hole and precast shear wall upper end and precast beam, making precast shear wall and precast beam fixed is entirety.
The described assembled syndeton of assembly concrete Frame-Shear Wall, arranges horizontal fractionation and at this place, precast beam longitudinal reinforcement is carried out to level connection joint at described precast beam span centre, makes precast beam left and right be connected to entirety by cast-in-place concrete.
The described assembled syndeton of assembly concrete Frame-Shear Wall, the fractionation connection arranging in the optional position of described precast shear wall horizontal direction between precast shear wall and adjacent pillars is connected with the fractionation of setting up precast shear wall self.
The described assembled syndeton of assembly concrete Frame-Shear Wall, adopts the structure that is connected of U-shaped muscle level overlap joint and vertical muscle bolt anchor between described post and described precast shear wall, make post and precast shear wall be connected to entirety by cast-in-place concrete.
The described assembled syndeton of assembly concrete Frame-Shear Wall, between described precast shear wall and adjacent pillars, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall and adjacent pillars are outstanding separately, when assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement from top to bottom; At precast shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector is set on precast shear wall, post groove shear connector is set on post; By cast-in-place band portion formwork poured in place concrete, make precast shear wall and adjacent pillars form entirety.
The described assembled syndeton of assembly concrete Frame-Shear Wall, for the reserved through hole of the interspersed main muscle of post and wall vertical reinforcement, adopts metal tube or metal bellows moulding in prefabricated node precast beam integrated component, or adopts the moulding of plastics QC.
The described assembled syndeton of assembly concrete Frame-Shear Wall, metal bellows adopts two rib bellowss, and its rib is high more than 1.5mm; Pore-forming internal diameter is determined according to worn bar diameter d, is taken as 1.2d~3.0d.
In the present invention, the frame shear wall structure thing that can use the assembled syndeton of above-mentioned assembly concrete Frame-Shear Wall described in any one to build.
The assembled method of attachment of above-mentioned assembly concrete frame shear wall structure, comprises the steps:
The first step, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's post of left and right prefabricated post are stretched is up mutually chimeric, locates note mortar in backward sleeve and connected horizontal joint;
Second step, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's wall of precast shear wall are stretched is up mutually chimeric, locates perfusion mortar in backward sleeve and connected horizontal joint;
The 3rd step, carries out level connection joint by post side embedded bar nose section and precast shear wall end face embedded bar nose section, configures vertical reinforcement simultaneously, then at cast-in-place band portion formwork fluid concrete;
The 4th step, prefabricated node precast beam integrated component is installed, the outstanding straight reinforcing bar of prefabricated post and precast shear wall upper end runs through the reserved through hole arranging in prefabricated node precast beam integrated component and protrudes from floor face, behind location, reserve perfusion mortar in the horizontal joint between through hole and post upper end and node to node area, perfusion mortar in the horizontal joint between the reserved through hole in Xiang Liang district and precast shear wall upper end and precast beam;
The 5th step, floor slab construction, i.e. cast-in-situ floor, or laminated floor slab is installed, configuration upper reinforcement is also built overlapping layers concrete, completes this layer of construction;
Carry out last layer construction, repeat above five steps.
The assembled method of attachment of described assembly concrete Frame-Shear Wall, in the time that precast beam span centre arranges horizontal fractionation and need carry out level connection joint to left and right precast beam section longitudinal reinforcement, install behind location at the prefabricated node precast beam of described the 4th step integrated component, first carry out precast beam left and right longitudinal reinforcement level connection joint, then reserve perfusion mortar in the horizontal joint between through hole and post upper end and node to node area, perfusion mortar in horizontal joint between the reserved through hole in Xiang Liang district and precast shear wall upper end and precast beam, finally to precast beam connecting portion formwork concreting.
effect of the present invention:
The present invention is by prefabricated post, precast shear wall, and prefabricated node precast beam integrated component forms structure and splits assembled system.Member method of attachment is: prefabricated post and precast shear wall adjacent surface are established outstanding U-shaped level connection joint muscle mutually, and the reserved through hole of the interspersed main muscle of post and wall vertical reinforcement is set in prefabricated node precast beam integrated component.The lower end embedded bar sleeve of prefabricated post and precast shear wall, mutually chimeric with the reinforcing bar nose section that lower floor's post and lower floor's wall are stretched up.By pour into high-strength mortar in sleeve and connected horizontal joint, become one with lower floor's post and lower floor's wall.The upper end of prefabricated post and precast shear wall is outstanding straight reinforcing bar, in the time that prefabricated node precast beam integrated component is installed, more than making it run through through hole reserved in prefabricated node precast beam integrated component and protruding from beam face (being floor face), by reserved through hole in prefabricated node precast beam integrated component and connected horizontal joint perfusion high-strength mortar, make prefabricated post and prefabricated node, precast shear wall and precast beam are fixed is entirety.Cast-in-place band is set between prefabricated post and precast shear wall and adopts U-shaped muscle level overlap joint and vertical muscle bolt anchor structure.
Fractionation splicing structure and member method of attachment that the present invention proposes have following characteristics:
1. it is reasonable that each member splits position, is convenient to structure manufacture and transportation; 2. member is generally symmetrical, and weight is reasonable, is convenient to lifting and installs; 3. all members are from top to bottom and install, and are convenient to lifting and install; 4. vertical reinforcement joint adopts single reinforced bar sleeve grouting docking, and joint is reliable; 5. reinforced bar sleeve grouting docking is all positioned at slightly high position of floor face, is convenient to grouting operation, and joint efficiency is high.6. shear wall vertical reinforcement is in by the two-sided distribution bar of minimum structure requirement configuration, and it is that the large spacing diameter steel bar of a row is configured on Wall center line that the vertical reinforcement area that calculating is needed is concentrated.So, meet the requirement of standard structure, bar splice is few again.Although amount of reinforcement slightly increases, sleeve is few, and economical (sleeve is expensive), goes back constructability; 7. between post wall, cast-in-place bandwidth is little, and situ wet operation is few, and assembly rate is high.
[accompanying drawing explanation]
Figure 1A-Fig. 1 E: the first assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing.Wherein, Figure 1A is the facade main view splitting; Figure 1B is assembled facade main view; Fig. 1 C is
I-I sectional drawing in Figure 1A; Fig. 1 D is II-II sectional drawing in Figure 1A; Fig. 1 E is Figure 1A central sill sectional view.
Fig. 2 A-Fig. 2 E: the second assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing.Wherein, Fig. 2 A is the facade main view splitting; Fig. 2 B is assembled facade main view; Fig. 2 C is I-I sectional drawing in Fig. 2 A; Fig. 2 D is II-II sectional drawing in Fig. 2 A; Fig. 2 E is superposed beam sectional view in Fig. 2 A.
Fig. 3 A-Fig. 3 E: the third assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing.Wherein, Fig. 3 A is the facade main view splitting; Fig. 3 B is assembled facade main view; Fig. 3 C is I-I sectional drawing in Fig. 3 A; Fig. 3 D is II-II sectional drawing in Fig. 3 A; Fig. 3 E is superposed beam sectional view in Fig. 3 A.
Fig. 4 A-Fig. 4 D: the 4th kind of assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing.Wherein, Fig. 4 A is the facade main view splitting; Fig. 4 B is assembled facade main view; Fig. 4 C is I-I sectional drawing in Fig. 4 A; Fig. 4 D is II-II sectional drawing in Fig. 4 A.
Fig. 5 A-Fig. 5 D: the 5th kind of assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing.Wherein, Fig. 5 A is the facade main view splitting; Fig. 5 B is assembled facade main view; Fig. 5 C is I-I sectional drawing in Fig. 5 A; Fig. 5 D is II-II sectional drawing in Fig. 5 A.
Fig. 6 A-Fig. 6 B: superposed beam and laminated floor slab sectional drawing.Wherein, Fig. 6 A is cast-in-situ floor; Fig. 6 B laminated floor slab.
Fig. 7: the local cast-in-place schematic diagram of reinforced bar sleeve grouting docking in girder span.
Fig. 8: the local cast-in-place schematic diagram of bar splicing in girder span.
In figure: 1 precast beam; 11 reserved through holes; 12 pre-buried vertical beam muscle or through holes; 13 plate muscle; 14 beam longitudinal reinforcements; 15 superposed beam muscle; 16 cast-in-situ concrete I; The straight anchor of 17 reinforcing bar; 18 beam intermediate contacts; 19 cast-in-situ concrete II; 110 beam left ends; 111 grouting grout outlet joints; 112 beam right-hand members; 113 left side grout compartment reinforcing bars; 114 cement grouting steel bar branch sleeves; 115 right side grout compartment reinforcing bars; 116 bar splicing structures; 2 precast shear walls; 21 shear wall vertical reinforcements; 22 shear wall vertical reinforcement butt muffs; 23 two-sided distribution bars within the walls; The U-shaped dowel of 24 wall; 25 wall groove shear connectors; 3 posts; 31 post longitudinal reinforcements; 32 post longitudinal reinforcement butt muffs; The U-shaped dowel of 33 post; 34 post groove shear connectors; 4 grouting; 5 cast-in-situ concrete III; 6 cast-in-situ floors; 7 laminated floor slabs; 8 bight vertical reinforcements.
[specific embodiment]
The assembled syndeton of assembly concrete Frame-Shear Wall of the present invention and assembled method of attachment, specific as follows:
(1) adopt by prefabricated or partial precast post (hereinafter to be referred as prefabricated post), prefabricated or partial precast shear wall (hereinafter to be referred as dry wall), prefabricated or partial precast beam column node core area (hereinafter to be referred as prefabricated node) and the assembled system of fractionation prefabricated or partial precast beam (hereinafter to be referred as precast beam) formation structure.Wherein joint cores and beam adopt integrated prefabricated mode (hereinafter to be referred as prefabricated node precast beam integrated component).For interconnecting of vertical reinforcement between levels post in implementation framework-shear wall structure and levels shear wall, in prefabricated node precast beam integrated component, be provided with the reserved through hole of the interspersed main muscle of post and wall vertical reinforcement.The vertical reinforcement of prefabricated post and precast shear wall all adopts lower end embedded bar sleeve, and straight reinforcing bar form is given prominence in upper end.
(2) in prefabricated node precast beam integrated component, can adopt metal tube or metal bellows moulding for the reserved through hole of the interspersed main muscle of post and wall vertical reinforcement, also can adopt the moulding of plastics QC.Metal bellows should adopt two rib bellowss, and its rib Gao Yi is more than 1.5mm.Pore-forming internal diameter is determined according to worn bar diameter d, generally should be taken as 1.2d~3.0d.
(3) between precast shear wall and adjacent pillars, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel be set carry out level overlap joint from precast shear wall and adjacent pillars are outstanding separately.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.This connected mode can realize following working mechanism: U-shaped overlap joint can significantly reduce the lap length of reinforcing bar on the one hand, further strengthens again the anchoring of U-shaped dowel by Xiao's bolt effect of joint bar.This reinforcement manner can form sleeper on the other hand, strengthens the binding effect to shear wall, thereby improves bearing capacity and the ductility of shear wall.Concrete groove shear connector is set, to increase interface shearing strength, reduces shearing slip, strengthen the co-operation of shear wall and peripheral frame.
Adopt U-shaped muscle level overlap joint and vertical muscle bolt anchor structure can reduce the width of cast-in-place band between prefabricated post and precast shear wall, improve connection reliability.
(4) between prefabricated post and adjacent node, split at capital face and basal surface position, the vertical reinforcement in prefabricated post adopts lower end that sleeve is set, and straight reinforcing bar is given prominence in upper end.Prefabricated post lower end adopts reinforced bar sleeve grouting docking mode, between post lower end and floor face, leaves horizontal joint.After installation in position, to pouring into high-strength mortar in sleeve and connected horizontal joint, this layer of post and lower floor's post and lower floor's beam folder node are become one.Prefabricated post upper end adopts node through hole to wear muscle slip casting connected mode, in the time that being installed, top prefabricated node precast beam integrated component makes more than the outstanding main muscle in prefabricated post upper end runs through through hole reserved in prefabricated node and protrude from node (floor face), between post upper end and node bottom surface, horizontal joint to be also set.After installation in position, make prefabricated post and prefabricated node to pouring into high-strength mortar in through hole reserved in prefabricated node and connected horizontal joint, and fixed by prefabricated node and precast beam be overall.
(5) between precast shear wall and adjacent beams, split at wall end face and basal surface position, the vertical reinforcement in precast shear wall adopts lower end that sleeve is set, and straight reinforcing bar is given prominence in upper end.Precast shear wall lower end adopts reinforced bar sleeve grouting docking mode, between wall lower end and floor face, leaves horizontal joint.After installation in position, to pouring into high-strength mortar in sleeve and connected horizontal joint, this layer of body of wall and lower floor's body of wall folder beam are become one.Precast shear wall upper end adopts precast beam through hole to wear muscle slip casting connected mode,, more than making the outstanding vertical reinforcement in precast shear wall upper end run through through hole reserved in precast beam and protruding from top surface of the beam (floor face), horizontal joint is also set between shear wall upper end and soffit in the time that top prefabricated node precast beam integrated component is installed.After installation in position, to pour in through hole reserved in precast beam and connected horizontal joint high-strength mortar make precast shear wall and precast beam fixed be entirety.
(6) more than, for splitting assembled system and connect, the assembling in frame shear wall structure plane constructs.Above-mentioned form be can adopt equally with the connection of plane external member (be vertical direction member, comprise wall, beam, floor etc.), cast-in-place structural and other modes such as reserved through hole or embedded bar connection also can be adopted.
(7) structure of the present invention splits the construction method of assembled system and is: from the floor face of every layer, 1. prefabricated post is installed.Make column bottom sleeve and lower floor's post bar splice mutually chimeric, in place after, column bottom sleeve and horizontal joint grouting connection → 2. dry wall between erection column.First lift body of wall to post plane outside and the bar splice that keeps a little higher than lower floor wall to stretch out, confirming that post stretches out U-shaped muscle and wall and stretches out the non-interference height of U-shaped muscle body of wall is moved horizontally to intercolumniation, then decline make wall bottom sleeves and lower floor's wall bar splice mutually chimeric.After in place, U-shaped muscle interior angle place's vertical reinforcement colligation connect → are 3. inserted in the grouting of wall bottom sleeves and horizontal joint from top to bottom, complete cast-in-place band arrangement of reinforcement, cast-in-place band both sides formwork, the prefabricated node precast beam integrated component of concreting → 4. install.Hoisting prefabricated node precast beam integrated component from top to bottom, and make the outstanding straight reinforcing bar of prefabricated post and dry wall upper end run through reserved through hole in prefabricated node precast beam integrated component.After prefabricated node precast beam integrated component is in place, in prefabricated node precast beam integrated component, reserve through hole and horizontal joint perfusion high-strength mortar → 5. floor slab construction.Cast-in-situ floor, or laminated floor slab configures upper reinforcement and builds overlapping layers concrete.
Fig. 1 is the full prefabrication system of beam.Concrete frame-the shear wall structure of which mainly comprises: precast beam 1, reserved through hole 11, pre-buried vertical beam muscle or through hole 12, plate muscle 13, beam longitudinal reinforcement 14, precast shear wall 2, shear wall vertical reinforcement 21, shear wall vertical reinforcement butt muff 22, two-sided distribution bar 23, post 3, post longitudinal reinforcement 31, post longitudinal reinforcement butt muff 32, grouting 4, cast-in-situ concrete III 5 etc. within the walls, and concrete structure is as follows:
Precast shear wall 2 two ends are connected with post 3 by cast-in-situ concrete III 5 respectively, on precast shear wall 2 and post 3, precast beam 1 are installed; Through hole 11 is reserved in vertically having in precast beam 1, and the length direction in precast beam 1 arranges beam longitudinal reinforcement 14; In precast beam 1 two end portions, through-thickness has pre-buried vertical beam muscle or through hole 12 respectively;
In precast shear wall 2, vertically wear shear wall vertical reinforcement 21, the upper end of shear wall vertical reinforcement 21 and the corresponding coupling of reserved through hole 11 in precast beam 1, and stretch out outside precast beam 1; Precast shear wall 2 bottoms arrange shear wall vertical reinforcement butt muff 22, shear wall vertical reinforcement butt muff 22 and the corresponding coupling of shear wall vertical reinforcement 21 of stretching out outside precast beam 1;
In post 3, vertically wear post longitudinal reinforcement 31, the upper end of post longitudinal reinforcement 31 and the corresponding coupling of reserved through hole 11 in post 3, and stretch out outside post 3; Post 3 bottoms arrange post longitudinal reinforcement butt muff 32, post longitudinal reinforcement butt muff 32 and the corresponding coupling of post longitudinal reinforcement 31 of stretching out outside post 3;
Between precast shear wall 2 and adjacent pillars 3, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall 2 and adjacent pillars 3 are outstanding separately, the U-shaped dowel 24 of wall is set on precast shear wall 2, the U-shaped dowel 33 of post is set on post 3.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement 8 from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector 25 is set on precast shear wall 2, post groove shear connector 34 is set on post 3.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.
Gap between described reserved through hole 11 and shear wall vertical reinforcement 21 and post longitudinal reinforcement 31 is grouting 4.
Its advantage is that node and deck-molding are unified, is convenient to prefabricated.For guaranteeing structural integrity, should adopt precast beam 1 both sides to throw away reinforcing bar and on-the-spot plate muscle 13 overlapping modes of laying, floor is entirely cast-in-place.
Fig. 2 is superposed beam mode.Concrete frame-the shear wall structure of which mainly comprises: precast beam 1, reserved through hole 11, pre-buried vertical beam muscle or through hole 12, beam longitudinal reinforcement 14, superposed beam muscle 15, cast-in-situ concrete I 16, precast shear wall 2, shear wall vertical reinforcement 21, shear wall vertical reinforcement butt muff 22, two-sided distribution bar 23, post 3, post longitudinal reinforcement 31, post longitudinal reinforcement butt muff 32, grouting 4, cast-in-situ concrete III 5 etc. within the walls, and concrete structure is as follows:
Precast shear wall 2 two ends are connected with post 3 by cast-in-situ concrete III 5 respectively, on precast shear wall 2 and post 3, precast beam 1 are installed; Through hole 11 is reserved in vertically having in precast beam 1, and the length direction in precast beam 1 arranges beam longitudinal reinforcement 14; In precast beam 1 two end portions, through-thickness has pre-buried vertical beam muscle or through hole 12 respectively, and precast beam 1 top plugs superposed beam muscle 15, and cast-in-situ concrete I 16 is by superposed beam muscle 15 and precast beam 1 combination;
In precast shear wall 2, vertically wear shear wall vertical reinforcement 21, the upper end of shear wall vertical reinforcement 21 and the corresponding coupling of reserved through hole 11 in precast beam 1, and stretch out outside precast beam 1; Precast shear wall 2 bottoms arrange shear wall vertical reinforcement butt muff 22, shear wall vertical reinforcement butt muff 22 and the corresponding coupling of shear wall vertical reinforcement 21 of stretching out outside precast beam 1;
In post 3, vertically wear post longitudinal reinforcement 31, the upper end of post longitudinal reinforcement 31 and the corresponding coupling of reserved through hole 11 in post 3, and stretch out outside post 3; Post 3 bottoms arrange post longitudinal reinforcement butt muff 32, post longitudinal reinforcement butt muff 32 and the corresponding coupling of post longitudinal reinforcement 31 of stretching out outside post 3;
Between precast shear wall 2 and adjacent pillars 3, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall 2 and adjacent pillars 3 are outstanding separately, the U-shaped dowel 24 of wall is set on precast shear wall 2, the U-shaped dowel 33 of post is set on post 3.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement 8 from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector 25 is set on precast shear wall 2, post groove shear connector 34 is set on post 3.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.
Gap between described reserved through hole 11 and shear wall vertical reinforcement 21 and post longitudinal reinforcement 31 is grouting 4.
Its advantage is as shown in Figure 6, and floor can adopt the cast-in-situ floor 6 of complete cast-in-place mode on precast beam 1, can adopt again the laminated floor slab 7 of superimposed sheet form on precast beam 1.With floor complete cast-in-place compared with, adopt laminated floor slab in guaranteeing structural integrity, to save template and support, improve assembly rate.
Fig. 3 is prefabricated node end face and the concordant mode of superposed beam pre-erection end face.Concrete frame-the shear wall structure of which mainly comprises: precast beam 1, reserved through hole 11, pre-buried vertical beam muscle or through hole 12, beam longitudinal reinforcement 14, superposed beam muscle 15, cast-in-situ concrete I 16, the straight anchor 17 of reinforcing bar, precast shear wall 2, shear wall vertical reinforcement 21, shear wall vertical reinforcement butt muff 22, two-sided distribution bar 23, post 3, post longitudinal reinforcement 31, post longitudinal reinforcement butt muff 32, grouting 4, cast-in-situ concrete III 5 etc. within the walls, and concrete structure is as follows:
Precast shear wall 2 two ends are connected with post 3 by cast-in-situ concrete III 5 respectively, on precast shear wall 2 and post 3, precast beam 1 are installed; Through hole 11 is reserved in vertically having in precast beam 1, and the length direction in precast beam 1 arranges beam longitudinal reinforcement 14; In precast beam 1 two end portions, through-thickness has pre-buried vertical beam muscle or through hole 12 respectively, precast beam 1 top plugs superposed beam muscle 15, and superposed beam muscle 15 two ends are connected and fixed by the straight anchor 17 of reinforcing bar, and cast-in-situ concrete I 16 is by superposed beam muscle 15, the straight anchor 17 of reinforcing bar and precast beam 1 combination;
In precast shear wall 2, vertically wear shear wall vertical reinforcement 21, the upper end of shear wall vertical reinforcement 21 and the corresponding coupling of reserved through hole 11 in precast beam 1, and stretch out outside precast beam 1; Precast shear wall 2 bottoms arrange shear wall vertical reinforcement butt muff 22, shear wall vertical reinforcement butt muff 22 and the corresponding coupling of shear wall vertical reinforcement 21 of stretching out outside precast beam 1;
In post 3, vertically wear post longitudinal reinforcement 31, the upper end of post longitudinal reinforcement 31 and the corresponding coupling of reserved through hole 11 in post 3, and stretch out outside post 3; Post 3 bottoms arrange post longitudinal reinforcement butt muff 32, post longitudinal reinforcement butt muff 32 and the corresponding coupling of post longitudinal reinforcement 31 of stretching out outside post 3;
Between precast shear wall 2 and adjacent pillars 3, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall 2 and adjacent pillars 3 are outstanding separately, the U-shaped dowel 24 of wall is set on precast shear wall 2, the U-shaped dowel 33 of post is set on post 3.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement 8 from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector 25 is set on precast shear wall 2, post groove shear connector 34 is set on post 3.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.
Gap between described reserved through hole 11 and shear wall vertical reinforcement 21 and post longitudinal reinforcement 31 is grouting 4.
Be characterized in combining the advantage of Fig. 1 and Fig. 2, beam top longitudinal reinforcement is on-the-spot laying simultaneously, and its end must adopt efficiently straight anchor engineering method to be anchored in in-situ layer.
Fig. 4 splits connection for beam is set in girder span, or increases the assembled connected mode laterally splitting in the middle of wall.The former is applicable to the situation that frame shear wall structure middle frame is multispan, and the latter is the situation that needs further segmenting wall body for reducing body of wall lifting weight.
Concrete frame-the shear wall structure of which mainly comprises: precast beam 1, reserved through hole 11, pre-buried vertical beam muscle or through hole 12, beam longitudinal reinforcement 14, beam intermediate contact 18, cast-in-situ concrete II 19, precast shear wall 2, shear wall vertical reinforcement 21, shear wall vertical reinforcement butt muff 22, two-sided distribution bar 23, post 3, post longitudinal reinforcement 31, post longitudinal reinforcement butt muff 32, grouting 4, cast-in-situ concrete III 5 etc. within the walls, and concrete structure is as follows:
Precast shear wall 2 two ends are connected with post 3 by cast-in-situ concrete III 5 respectively, on precast shear wall 2 and post 3, precast beam 1 are installed; Through hole 11 is reserved in vertically having in precast beam 1, and the length direction in precast beam 1 arranges beam longitudinal reinforcement 14; In precast beam 1 two end portions, through-thickness has pre-buried vertical beam muscle or through hole 12 respectively; Between contiguous prefabricated beam 1, connect by beam intermediate contact 18, beam intermediate contact 18 places adopt cast-in-situ concrete II 19;
In precast shear wall 2, vertically wear shear wall vertical reinforcement 21, the upper end of shear wall vertical reinforcement 21 and the corresponding coupling of reserved through hole 11 in precast beam 1, and stretch out outside precast beam 1; Precast shear wall 2 bottoms arrange shear wall vertical reinforcement butt muff 22, shear wall vertical reinforcement butt muff 22 and the corresponding coupling of shear wall vertical reinforcement 21 of stretching out outside precast beam 1;
In post 3, vertically wear post longitudinal reinforcement 31, the upper end of post longitudinal reinforcement 31 and the corresponding coupling of reserved through hole 11 in post 3, and stretch out outside post 3; Post 3 bottoms arrange post longitudinal reinforcement butt muff 32, post longitudinal reinforcement butt muff 32 and the corresponding coupling of post longitudinal reinforcement 31 of stretching out outside post 3;
Between precast shear wall 2 and adjacent pillars 3, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall 2 and adjacent pillars 3 are outstanding separately, the U-shaped dowel 24 of wall is set on precast shear wall 2, the U-shaped dowel 33 of post is set on post 3.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement 8 from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector 25 is set on precast shear wall 2, post groove shear connector 34 is set on post 3.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.
Gap between described reserved through hole 11 and shear wall vertical reinforcement 21 and post longitudinal reinforcement 31 is grouting 4.
Beam is set in girder span and splits while connection, in girder span, longitudinal reinforcement connects the reinforced bar sleeve grouting docking mode that can adopt as shown in Figure 7, also can adopt bar splicing mode and other modes as shown in Figure 8.
As shown in Figure 7, between right side grout compartment reinforcing bar 115 on left side grout compartment reinforcing bar 113 and beam right-hand member 112 on beam left end 110, be connected by cement grouting steel bar branch sleeve 114, grouting grout outlet joint 111 is set on cement grouting steel bar branch sleeve 114, and left side grout compartment reinforcing bar 113, right side grout compartment reinforcing bar 115 are connected by cementation with cement grouting steel bar branch sleeve 114.As shown in Figure 8, between beam left end 110 and beam right-hand member 112, be connected by bar splicing structure 116.
In addition, it shown in Fig. 4, is only the example of the full prefabrication system of beam, for being set in girder span, beam splits connection, or the assembled connected mode that increase laterally splits in the middle of wall, can adopt equally the superposed beam mode shown in Fig. 2, and the prefabricated node end face node section prefabrication system concordant with superposed beam pre-erection end face shown in Fig. 3.
Fig. 5 is that framework and shear wall are multispan, and beam is at span centre, and shear wall arranges with shear wall boundary and shear wall middle part the situation about being connected that splits at post.Concrete frame-the shear wall structure of which mainly comprises: precast beam 1, reserved through hole 11, pre-buried vertical beam muscle or through hole 12, beam longitudinal reinforcement 14, beam intermediate contact 18, cast-in-situ concrete II 19, precast shear wall 2, shear wall vertical reinforcement 21, shear wall vertical reinforcement butt muff 22, two-sided distribution bar 23, post 3, post longitudinal reinforcement 31, post longitudinal reinforcement butt muff 32, grouting 4, cast-in-situ concrete III 5 etc. within the walls, and concrete structure is as follows:
Precast shear wall 2 two ends are connected with post 3 by cast-in-situ concrete III 5 respectively, on precast shear wall 2 and post 3, precast beam 1 are installed; Through hole 11 is reserved in vertically having in precast beam 1, and the length direction in precast beam 1 arranges beam longitudinal reinforcement 14; In precast beam 1 two end portions, through-thickness has pre-buried vertical beam muscle or through hole 12 respectively; Between contiguous prefabricated beam 1, connect by beam intermediate contact 18, beam intermediate contact 18 places adopt cast-in-situ concrete II 19;
In precast shear wall 2, vertically wear shear wall vertical reinforcement 21, the upper end of shear wall vertical reinforcement 21 and the corresponding coupling of reserved through hole 11 in precast beam 1, and stretch out outside precast beam 1; Precast shear wall 2 bottoms arrange shear wall vertical reinforcement butt muff 22, shear wall vertical reinforcement butt muff 22 and the corresponding coupling of shear wall vertical reinforcement 21 of stretching out outside precast beam 1;
In post 3, vertically wear post longitudinal reinforcement 31, the upper end of post longitudinal reinforcement 31 and the corresponding coupling of reserved through hole 11 in post 3, and stretch out outside post 3; Post 3 bottoms arrange post longitudinal reinforcement butt muff 32, post longitudinal reinforcement butt muff 32 and the corresponding coupling of post longitudinal reinforcement 31 of stretching out outside post 3;
Between precast shear wall 2 and adjacent pillars 3, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall 2 and adjacent pillars 3 are outstanding separately, the U-shaped dowel 24 of wall is set on precast shear wall 2, the U-shaped dowel 33 of post is set on post 3.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement 8 from top to bottom.In addition, at shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector 25 is set on precast shear wall 2, post groove shear connector 34 is set on post 3.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent pillars form entirety.
Gap between described reserved through hole 11 and shear wall vertical reinforcement 21 and post longitudinal reinforcement 31 is grouting 4.
The fractionation of multiple bay frame-shear wall structure is assembled basic identical with connected mode and single span.In addition, identical with Fig. 4, it shown in Fig. 5, is only the example of the full prefabrication system of beam, for being set in girder span, beam splits connection, or the assembled connected mode that increase laterally splits in the middle of wall, can adopt equally the superposed beam mode shown in Fig. 2, and the prefabricated node end face node section prefabrication system concordant with superposed beam pre-erection end face shown in Fig. 3.
Between shear wall and adjacent pillars, in U-shaped muscle connected mode, can form as required sleeper.The formation method of sleeper is, increases radical and the diameter of vertical joint bar, simultaneously can be between U-shaped muscle separately the configuration single rectangle hoop consistent with U-shaped closed rib shape realize stirrup encryption.
Fractionation position between shear wall and adjacent pillars is not limited to post and shear wall intersection.In the situation that wall size or weight are transported or lifts restriction, or when obtaining better connection effect, can split position to shear wall one side shifting, by prefabricated to a part of body of wall and post one.
Horizontal reinforcement method of attachment between shear wall and adjacent pillars is not limited to U-shaped muscle connected mode, also can adopt other overlapping modes or mechanical type connected mode.
Result shows, when the present invention forms concrete frame-shear wall structure by prefabricated post, precast wall body, prefabricated node and precast beam, the fractionation of post be connected, the fractionation of beam be connected, the fractionation of node be connected, the fractionation of shear wall and adjacent pillars be connected, the fractionation of shear wall and adjacent beams be connected, and the connection of reinforcing bar between levels shear wall.Rationally effectively split assembled system and member connected mode by adopting, reduce to greatest extent the wet trades such as cast-in-place concrete, improve assemblingization degree, realize energy-saving and emission-reduction, raise labour productivity, improve construction quality, the reduction of erection time.

Claims (10)

1. the assembled syndeton of assembly concrete Frame-Shear Wall, it is characterized in that: form structure by prefabricated or partial precast post, prefabricated or partial precast shear wall, prefabricated or partial precast beam column node core area and prefabricated or partial precast beam and split assembled system, wherein: prefabricated or partial precast post, hereinafter to be referred as prefabricated post; Prefabricated or partial precast shear wall, hereinafter to be referred as dry wall; Prefabricated or partial precast beam column node core area, hereinafter to be referred as prefabricated node; Prefabricated or partial precast beam, hereinafter to be referred as precast beam; Joint cores and beam adopt integrated prefabricated mode, hereinafter to be referred as prefabricated node precast beam integrated component, the reserved through hole of the interspersed main muscle of post and shear wall vertical reinforcement are set in prefabricated node precast beam integrated component;
The lower end embedded bar sleeve of prefabricated post, mutually chimeric with the reinforcing bar nose section that lower floor post is stretched up, by note mortar in sleeve and connected horizontal joint, be connected to entirety with lower floor post;
The lower end embedded bar sleeve of precast shear wall, mutually chimeric with the reinforcing bar nose section that lower floor wall is stretched up, by perfusion mortar in sleeve and connected horizontal joint, be connected to entirety with lower floor precast shear wall;
Cast-in-place band is set between prefabricated post and precast shear wall, and coupled columns side embedded bar and precast shear wall end face embedded bar carry out level connection joint in cast-in-place band, make post and precast shear wall be connected to entirety by cast-in-place concrete;
The upper end of prefabricated post is outstanding straight reinforcing bar, run through the reserved through hole of the node area arranging in prefabricated node precast beam integrated component and protrude from floor face, perfusion mortar in horizontal joint between reserved through hole and post upper end and node, making post and node fixed is entirety;
The upper end of precast shear wall is outstanding straight reinforcing bar, run through and the reserved through hole in Liang district is set in prefabricated node precast beam integrated component and protrudes from floor face, perfusion mortar in horizontal joint between reserved through hole and precast shear wall upper end and precast beam, making precast shear wall and precast beam fixed is entirety.
2. according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 1, it is characterized in that, horizontal fractionation is set and at this place, precast beam longitudinal reinforcement is carried out to level connection joint at described precast beam span centre, make precast beam left and right be connected to entirety by cast-in-place concrete.
3. according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 1, it is characterized in that, the fractionation connection arranging in the optional position of described precast shear wall horizontal direction between precast shear wall and adjacent pillars is connected with the fractionation of setting up precast shear wall self.
4. according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 1, it is characterized in that, the structure that is connected that adopts U-shaped muscle level overlap joint and vertical muscle bolt anchor between described post and described precast shear wall, makes post and precast shear wall be connected to entirety by cast-in-place concrete.
5. described according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 4, it is characterized in that, between described precast shear wall and adjacent pillars, split on wall limit, between connection adopt cast-in-place band mode, U-shaped dowel is set carries out level overlap joint from precast shear wall and adjacent pillars are outstanding separately, when assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, at this closed space, four interior angle places insert bight vertical reinforcement from top to bottom; At precast shear wall end face and phase coupled columns side, concrete groove shear connector should be set respectively, wall groove shear connector is set on precast shear wall, post groove shear connector is set on post; By cast-in-place band portion formwork poured in place concrete, make precast shear wall and adjacent pillars form entirety.
6. according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 1, it is characterized in that, the interior reserved through hole for the interspersed main muscle of post and wall vertical reinforcement of prefabricated node precast beam integrated component, adopt metal tube or metal bellows moulding, or adopt the moulding of plastics QC.
7. according to the assembled syndeton of assembly concrete Frame-Shear Wall claimed in claim 6, it is characterized in that, metal bellows adopts two rib bellowss, and its rib is high more than 1.5mm; Pore-forming internal diameter is determined according to worn bar diameter d, is taken as 1.2d~3.0d.
8. right to use requires in 1 to 7 the frame shear wall structure thing that the assembled syndeton of the assembly concrete Frame-Shear Wall described in any one is built.
9. an assembled method of attachment for assembly concrete frame shear wall structure, is characterized in that, comprises the steps:
The first step, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's post of left and right prefabricated post are stretched is up mutually chimeric, locates note mortar in backward sleeve and connected horizontal joint;
Second step, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's wall of precast shear wall are stretched is up mutually chimeric, locates perfusion mortar in backward sleeve and connected horizontal joint;
The 3rd step, carries out level connection joint by post side embedded bar nose section and precast shear wall end face embedded bar nose section, configures vertical reinforcement simultaneously, then at cast-in-place band portion formwork fluid concrete;
The 4th step, prefabricated node precast beam integrated component is installed, the outstanding straight reinforcing bar of prefabricated post and precast shear wall upper end runs through the reserved through hole arranging in prefabricated node precast beam integrated component and protrudes from floor face, behind location, reserve perfusion mortar in the horizontal joint between through hole and post upper end and node to node area, perfusion mortar in the horizontal joint between the reserved through hole in Xiang Liang district and precast shear wall upper end and precast beam;
The 5th step, floor slab construction, i.e. cast-in-situ floor, or laminated floor slab is installed, configuration upper reinforcement is also built overlapping layers concrete, completes this layer of construction;
Carry out last layer construction, repeat above five steps.
10. the assembled method of attachment of assembly concrete Frame-Shear Wall claimed in claim 9, it is characterized in that, in the time that precast beam span centre arranges horizontal fractionation and need carry out level connection joint to left and right precast beam section longitudinal reinforcement, install behind location at the prefabricated node precast beam of described the 4th step integrated component, first carry out precast beam left and right longitudinal reinforcement level connection joint, then reserve perfusion mortar in the horizontal joint between through hole and post upper end and node to node area, perfusion mortar in horizontal joint between the reserved through hole in Xiang Liang district and precast shear wall upper end and precast beam, finally to precast beam connecting portion formwork concreting.
CN201210281096.4A 2012-08-08 2012-08-08 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination Active CN102808465B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210281096.4A CN102808465B (en) 2012-08-08 2012-08-08 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210281096.4A CN102808465B (en) 2012-08-08 2012-08-08 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination

Publications (2)

Publication Number Publication Date
CN102808465A CN102808465A (en) 2012-12-05
CN102808465B true CN102808465B (en) 2014-07-09

Family

ID=47232321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210281096.4A Active CN102808465B (en) 2012-08-08 2012-08-08 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination

Country Status (1)

Country Link
CN (1) CN102808465B (en)

Families Citing this family (67)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046669B (en) * 2012-12-10 2015-04-29 北京工业大学 Prefabricated high strength reinforced concrete shear wall with low strength energy dissipation strip and fabrication method
CN103924687A (en) * 2013-01-14 2014-07-16 上海核工程研究设计院 Connection method of steel plate-concrete composite shear wall and concrete shear wall
CN103088940B (en) * 2013-01-29 2015-08-12 湖南大学 A kind of compound shear wall and construction method thereof
CN103088939B (en) * 2013-01-29 2015-01-21 湖南禹班建设集团有限公司 Assembly interlocking prestressing force shear wall system and construction method thereof
CN103195183A (en) * 2013-03-28 2013-07-10 中铁建设集团有限公司 Standard unit assembled shock isolating and damping structure system
CN103306402B (en) * 2013-06-26 2015-04-08 中国十七冶集团有限公司 Non-superimposition beam type fabricated frame-shear wall connection structure and construction method thereof
CN103510639B (en) * 2013-10-15 2016-03-23 合肥工业大学 A kind of can the overlaid plate type shear wall of restore funcitons and implementation method thereof
CN103485548B (en) * 2013-10-17 2015-08-12 孟凡林 Assembling hollow concrete overlapped shear wall Vertical bar connection method
CN103572865B (en) * 2013-10-23 2016-08-24 沈阳建筑大学 Prefabricated assembled Frame-Shear Wall wall-face, Liangping aggregate leakage outside connecting device
CN103590492A (en) * 2013-10-23 2014-02-19 沈阳建筑大学 Prefabricated-type external connection structure for lower half wall frame, shear wall and girder plane
CN103572838A (en) * 2013-10-23 2014-02-12 沈阳建筑大学 External connecting technology for prefabricated frame, shear wall and beam panel
CN103850363B (en) * 2014-03-11 2015-02-25 赵春樵 Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN104032836B (en) * 2014-05-28 2017-01-04 同济大学 What buckling-restrained steel plate wall was connected with concrete frame wears muscle connection node
CN104047381B (en) * 2014-07-04 2016-04-20 孟凡林 Assembled integral rare-reinforcement concrete shear wall structure
CN104264786B (en) * 2014-09-29 2016-08-17 中铁四局集团有限公司 The bar connecting mode of a kind of prefabricated concrete element and application thereof
CN104992613B (en) * 2015-07-28 2018-03-06 上海建工二建集团有限公司 Visualize prefabricated assembled shear wall construction lab simulation teaching aid and installation method
CN105369901A (en) * 2015-12-10 2016-03-02 中建三局集团有限公司重庆分公司 Floor slab embedded rebar structure
NZ747688A (en) * 2016-04-28 2024-02-23 Lucobit Ag System for wall to wall connection for precast shear walls and method thereof
CN106436968A (en) * 2016-05-06 2017-02-22 湖南标迪夫节能科技有限公司 Manufacturing method for wallboard of steel-concrete combination structure
CN106088397B (en) * 2016-08-04 2017-10-31 广东省建筑设计研究院 Assembly concrete composite shear wall and its construction method
CN106436894B (en) * 2016-09-29 2019-10-11 中国航天建设集团有限公司 A kind of prefabricated dwelling house and its method of construction
CN106436973B (en) * 2016-10-26 2022-09-27 曲周县和盛新型建筑材料有限公司 Steel column arranged in post-cast section of steel shear structure and casting method of steel column
CN108222321A (en) * 2016-12-22 2018-06-29 李聪 A kind of building construction method of precast shear wall and precast floor slab
CN106759881B (en) * 2016-12-29 2022-07-19 上海建工五建集团有限公司 Prefabricated column connecting node grouting plugging structure and method
CN106869331A (en) * 2017-01-18 2017-06-20 成张佳宁 The connection method of precast shear wall composite beam in assembled RC frame-shear structures
CN106760936A (en) * 2017-01-24 2017-05-31 赤峰市建筑科学研究院有限公司 A kind of light-duty Assembled enclosing wall of post-tensioned prestressing
CN106759873A (en) * 2017-03-25 2017-05-31 河北合创建筑节能科技有限责任公司 A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN107675838A (en) * 2017-09-26 2018-02-09 中国二十二冶集团有限公司 Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method
CN107542185B (en) * 2017-09-30 2023-12-01 新疆玉龙河建设工程有限公司 Bending shear type combined key slot connecting structure of assembly frame shear structure and assembly method
CN107642179B (en) * 2017-09-30 2023-12-08 新疆玉龙河建设工程有限公司 Key groove connecting structure of steel plate of assembled frame shear structure and assembling method
CN108104310B (en) * 2017-12-01 2023-12-05 新疆中联建设工程有限公司 Assembled frame shear structure column staggered connection structure and assembling method
CN108360689A (en) * 2018-02-10 2018-08-03 南通联泷建筑材料有限公司 A kind of connection structure of wallboard and coupling beam
CN108240053B (en) * 2018-02-13 2023-06-20 上海建工五建集团有限公司 Assembled integral energy-consumption frame wallboard system and construction method
CN108265671A (en) * 2018-03-12 2018-07-10 中交上海港湾工程设计研究院有限公司 A kind of prefabricated panel and the connection system and method for longitudinal and transverse beam
CN108589970A (en) * 2018-05-18 2018-09-28 中国二十二冶集团有限公司 The construction method of prefabricated window frame shear wall
CN108643381A (en) * 2018-05-18 2018-10-12 中国二十二冶集团有限公司 Assembly of shear wall structure is without support bottom bridging method
CN108755728A (en) * 2018-06-22 2018-11-06 中船第九设计研究院工程有限公司 A method of it is connect with pile foundation for launching way beam
CN108678279A (en) * 2018-07-13 2018-10-19 中国建筑标准设计研究院有限公司 Based on the built-in assembled architecture and its construction method for leading to high bellows prefabricated panel
CN108643395B (en) * 2018-07-24 2023-05-26 华北理工大学 Prefabricated assembly type prestress self-resetting shear wall structure and construction method thereof
CN108867938A (en) * 2018-09-04 2018-11-23 中冶建筑研究总院有限公司 A kind of wall beam unit and its connection structure for assembled-type house system
CN108867885B (en) * 2018-09-10 2023-08-25 西北民族大学 Damping energy consumption assembly node of prefabricated column and integrated prefabricated beam slab and construction method thereof
CN108999341B (en) * 2018-09-11 2023-06-23 深圳大学 Engaged steel-concrete combined column and column connecting node and manufacturing method
CN109138154B (en) * 2018-10-19 2020-05-12 南通大学 Node connection method for fabric concrete prefabricated part
CN109577478A (en) * 2018-12-21 2019-04-05 贺州学院 The bracing means of assembled wall
CN109610875B (en) * 2019-01-25 2023-12-22 江苏瑞永建设工程技术有限公司 Assembled floor door frame of existing building with elevator and construction method
CN109680835B (en) * 2019-02-15 2024-03-22 姚攀峰 Self-supporting precast concrete wallboard, concrete wall, structural system and construction method
CN109680833B (en) * 2019-02-15 2024-06-11 姚攀峰 Self-supporting prefabricated steel reinforced concrete wall plate component, wall, structural system and manufacturing method
CN110106970A (en) * 2019-05-31 2019-08-09 西安建工绿色建筑集团有限公司 The index bed method of construction that pin-connected panel index bed module and dry and wet technique combine
CN110258784A (en) * 2019-07-02 2019-09-20 广东工业大学 A kind of assembled arthitecutral structure
CN110318426B (en) * 2019-08-07 2024-01-09 哈尔滨工业大学 Assembled steel-concrete mixed structure subway station and assembling method
CN110439116A (en) * 2019-08-09 2019-11-12 昌大建筑科技有限公司 Concrete assembles dry construction linked system entirely
CN110359551A (en) * 2019-08-16 2019-10-22 陈玲玲 A kind of knockdown assembled arthitecutral structure
CN110644645A (en) * 2019-09-16 2020-01-03 佛山建装建筑科技有限公司 Prefabricated column wall and construction method of vertical joint of prefabricated column wall
CN110761419A (en) * 2019-10-29 2020-02-07 袁建华 Construction method for three-dimensional positioning accuracy of prefabricated house foundation connecting piece
CN111364647A (en) * 2020-04-29 2020-07-03 中国建筑第七工程局有限公司 Assembled outer frame shear wall structure system and construction method thereof
CN111364644A (en) * 2020-04-29 2020-07-03 中国建筑第七工程局有限公司 Assembly type inner frame shear wall structure system and construction method thereof
CN111502070B (en) * 2020-05-14 2022-03-25 华北理工大学 Vertical splicing structure of prefabricated shear wall and construction method thereof
CN111779160A (en) * 2020-07-27 2020-10-16 中国建筑技术集团有限公司 Prestress assembly type concrete shear wall system and construction method thereof
CN114370108A (en) * 2020-10-16 2022-04-19 万平华 Method for building assembled concrete house by adopting novel connecting end component
CN112609860A (en) * 2020-11-17 2021-04-06 四川省振控科技有限公司 Novel full-assembly reinforced concrete shear wall and manufacturing method thereof
CN114575523A (en) * 2020-11-30 2022-06-03 周俏 Shear wall and mounting method thereof
CN112681515A (en) * 2020-12-24 2021-04-20 应义淼 Connecting method of precast concrete horizontal members
CN113503038A (en) * 2021-07-20 2021-10-15 广州大学 Processing and mounting method of buttress connecting joint with energy dissipation adjusting function
CN113529971B (en) * 2021-08-04 2022-09-30 山西职业技术学院 Assembled steel construction building wall and post connection structure
CN113863533A (en) * 2021-10-13 2021-12-31 廖火平 Construction method and member for non-completely assembled wall
CN114033219A (en) * 2021-12-21 2022-02-11 吴云涛 Concrete box type building module, modular building and construction method thereof
CN114541611A (en) * 2022-03-17 2022-05-27 沈阳工业大学 Prefabricated light lattice type concrete wall assembly structure system and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291130A (en) * 1999-04-12 2000-10-17 Toyo Alex Corp Plate member excellent in earthquake resistance, and building structure using the same
CN2811428Y (en) * 2005-07-08 2006-08-30 马小萍 Frame-shear structure for cast-in-place reinforced concrete floor slab and large floating slab combined building
CN101012670A (en) * 2006-12-29 2007-08-08 北京工业大学 Shearing wall constrained and galvanized iron sheet enveloped no-binding energy dissipating steel support and method for making same
CN101046109A (en) * 2006-03-31 2007-10-03 同济大学 New type of frame supported shear wall structure and its making process
CN202831296U (en) * 2012-08-08 2013-03-27 沈阳建筑大学 Assembled spliced connecting structure of concrete frame-shear wall and structure constructed

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11172810A (en) * 1997-12-16 1999-06-29 Dps Bridge Works Co Ltd Earthquake resisting wall and earthquake resisting reinforcing structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291130A (en) * 1999-04-12 2000-10-17 Toyo Alex Corp Plate member excellent in earthquake resistance, and building structure using the same
CN2811428Y (en) * 2005-07-08 2006-08-30 马小萍 Frame-shear structure for cast-in-place reinforced concrete floor slab and large floating slab combined building
CN101046109A (en) * 2006-03-31 2007-10-03 同济大学 New type of frame supported shear wall structure and its making process
CN101012670A (en) * 2006-12-29 2007-08-08 北京工业大学 Shearing wall constrained and galvanized iron sheet enveloped no-binding energy dissipating steel support and method for making same
CN202831296U (en) * 2012-08-08 2013-03-27 沈阳建筑大学 Assembled spliced connecting structure of concrete frame-shear wall and structure constructed

Also Published As

Publication number Publication date
CN102808465A (en) 2012-12-05

Similar Documents

Publication Publication Date Title
CN102808465B (en) Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN102900168B (en) Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall
CN202831296U (en) Assembled spliced connecting structure of concrete frame-shear wall and structure constructed
CN202831203U (en) Assembly type concrete frame-shear wall split assembling structure and fabricative structure
CN203113553U (en) Prefabricated concrete frame-shear wall structure
CN203097016U (en) Assembled-type concrete frame shear wall structure
CN104727467A (en) Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method
CN202865991U (en) Assembled monolithic shear wall building structure
CN107401217B (en) A kind of beamless hollow floor-chamber concrete-filled steel tube shear wall combined structure system and method
CN204225283U (en) The assembled syndeton of assembly concrete frame structure Shear-wall Connecting Beam Used
CN108374504B (en) Prefabricated reinforced concrete shear wall structure and construction method thereof
CN202925716U (en) Integrally assembled type concrete filled steel tube frame shear wall
CN110792164B (en) Transverse assembling device and method for assembled shear wall
CN104775545A (en) Novel disassembling component for assembling type concrete frame and shear wall structure and connecting method
CN104032854B (en) Assembled T-shaped mixing coupled wall and construction method thereof
CN103572873A (en) Assembled monolithic floor slab and construction method thereof
CN108086488B (en) Assembled frame shear structure wall staggered connection structure and assembling method
CN108316466B (en) Prefabricated bay window component, assembled bay window node structure and construction method thereof
CN104481031A (en) Assembly connection structure and method of coupling beams of shear walls of assembly concrete frame shear structure
CN108343176B (en) Prefabricated assembled hybrid shear wall structure
CN106760036B (en) A kind of prefabricated steel-combined concrete shear wall
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN212534652U (en) Steel-concrete composite structure frame-cast-in-place concrete shear wall structure system
CN104032855B (en) Assembled cross mixing coupled wall and construction method thereof
CN105297910A (en) Connecting structure of prefabricated floor plate and steel beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant