CN107675838A - Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method - Google Patents

Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method Download PDF

Info

Publication number
CN107675838A
CN107675838A CN201710877974.1A CN201710877974A CN107675838A CN 107675838 A CN107675838 A CN 107675838A CN 201710877974 A CN201710877974 A CN 201710877974A CN 107675838 A CN107675838 A CN 107675838A
Authority
CN
China
Prior art keywords
precast beam
lane change
cast
wall
brick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710877974.1A
Other languages
Chinese (zh)
Inventor
张晓峰
迟毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201710877974.1A priority Critical patent/CN107675838A/en
Publication of CN107675838A publication Critical patent/CN107675838A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/18Spacers of metal or substantially of metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, and when progress cast-in-situ wall ties up muscle, the placement space of sidewalk brick precast beam is reserved on wall top;The overlap joint reinforcing bar reserved by lane change brick precast beam bottom, is attached with cast-in-situ wall, and by the grout hole reserved on lane change brick precast beam, cast-in-situ wall is poured;Lane change brick precast beam forms an entirety with cast-in-situ wall;The pre-buried sleeve joint bar in precast beam top is attached with upper strata precast wall body sleeve.Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention, is attached by reinforcing bar pre-buried on precast beam and following cast-in-situ wall, and precast beam top embedded sleeve barrel joint bar carries out sleeve connection with upper wall;Accelerate first floor precast wall body installation rate and inject pre-buried precision, and then save construction cost, reduce labor strength, improve efficiency of construction, ensure construction quality.

Description

Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method
Technical field
It is that to be related to a kind of assembled architecture sidewalk brick prefabricated specifically the present invention relates to a kind of construction techniques Beam embedded sleeve barrel joint bar construction method.
Background technology
During fabricated shear wall installation, the longitudinal reinforcement connection of node and seam crossing is more to be in the milk using sleeve Connection.
Due to removing basal layer, the shear wall of index bed is all prefabricated, so during installation, index bed and top The shear wall of layer can be installed accurately by the reserved sleeve joint bar of lower floor's shear wall, therefore above-mentioned connected mode exists Technical requirements are high in the work progress of reserved joint bar on the conversion layer of in-situ layer and preformed layer, and difficulty of construction is big.
The content of the invention
For above-mentioned deficiency of the prior art, the present invention provides a kind of simple in construction, easy for construction, raising construction matter Amount, reduce the assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of difficulty of construction.
The technical solution used in the present invention is:
A kind of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, including it is arranged on top on cast-in-place wall Lane change brick precast beam;
The grout hole for grouting is provided with the middle part of the lane change brick precast beam along its length;
Lane change brick precast beam is provided with sleeve joint bar and overlap joint reinforcing bar;
The cylinder joint bar and overlap joint reinforcing bar are structure as a whole with lane change brick precast beam;
The lane change brick precast beam is provided with split bolt hole;
Specific construction step is as follows:
When progress cast-in-situ wall ties up muscle, the placement space of sidewalk brick precast beam is reserved on wall top;
Colligation cast-in-situ wall reinforcing bar, after cast-in-situ wall reinforcing bar colligation;
Lane change brick precast beam is placed on the good reinforcing bar of cast-in-situ wall colligation;
The reserved overlap joint reinforcing bar in lane change brick precast beam bottom is attached with cast-in-situ wall, by being arranged on lane change brick during formwork The split bolt in reserved split bolt hole on formula precast beam is reinforced to template;
By the grout hole reserved on lane change brick precast beam, cast-in-situ wall is poured;
Lane change brick precast beam forms an entirety with cast-in-situ wall;
The pre-buried sleeve joint bar in precast beam top is attached with upper strata precast wall body sleeve.
The grout hole is through hole.
The sleeve joint bar stretches out from lane change brick precast beam upper surface;Reinforcing bar is overlapped from lane change brick precast beam lower surface Stretch out..
The beneficial effect of the present invention compared with the prior art:
Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention, passes through reinforcing bar pre-buried on precast beam It is attached with following cast-in-situ wall, precast beam top embedded sleeve barrel joint bar carries out sleeve connection with upper wall;Due to can be with By controlling the hole of prefabricated beam mould embedded sleeve barrel joint bar, accelerate first floor precast wall body installation rate and inject pre-buried essence Degree, and then construction cost is saved, labor strength is reduced, improves efficiency of construction, ensures construction quality.
Brief description of the drawings
Fig. 1 is the constructing structure signal of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention Figure;
Fig. 2 is the lane change brick precast beam master of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention Depending on structural representation;
Fig. 3 is that the lane change brick precast beam of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention is bowed Depending on structural representation;
Fig. 4 is the lane change brick precast beam side of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention Depending on structural representation.
Critical piece symbol description in accompanying drawing:
In figure:
1st, lane change brick precast beam 2, sleeve joint bar
3rd, reinforcing bar 4, split bolt hole are overlapped
5th, cast-in-situ wall reinforcing bar 6, grout hole.
Embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Knowable to accompanying drawing 1-4, a kind of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, including be arranged on existing Pour the lane change brick precast beam 1 on top on wall;
The middle part of lane change brick precast beam 1 is provided with the grout hole 6 for grouting along its length;
Lane change brick precast beam 1 is provided with sleeve joint bar 2 and overlap joint reinforcing bar 3;
The cylinder joint bar 2 and overlap joint reinforcing bar 3 are structure as a whole with lane change brick precast beam 1;
The lane change brick precast beam 1 is provided with split bolt hole 4;
Specific construction step is as follows:
When progress cast-in-situ wall ties up muscle, the placement space of sidewalk brick precast beam is reserved on wall top;
Colligation cast-in-situ wall reinforcing bar 5, after the colligation of cast-in-situ wall reinforcing bar 5;
Lane change brick precast beam is placed on the good reinforcing bar of cast-in-situ wall colligation;
The reserved overlap joint reinforcing bar 3 in lane change brick precast beam bottom is attached with cast-in-situ wall, by being arranged on lane change during formwork The split bolt in reserved split bolt hole on brick precast beam is reinforced to template;
By the grout hole reserved on lane change brick precast beam, cast-in-situ wall is poured;
Lane change brick precast beam forms an entirety with cast-in-situ wall;
The pre-buried sleeve joint bar in precast beam top is attached with upper strata precast wall body sleeve.
The grout hole 6 is through hole.
The sleeve joint bar stretches out from lane change brick precast beam upper surface;Reinforcing bar is overlapped from lane change brick precast beam lower surface Stretch out..
Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method of the present invention, by pre-buried on precast beam Reinforcing bar is attached with following cast-in-situ wall, and precast beam top embedded sleeve barrel joint bar carries out sleeve connection with upper wall;Due to It can accelerate first floor precast wall body installation rate by controlling prefabricated beam mould embedded sleeve barrel joint bar hole and inject pre-buried Precision, and then construction cost is saved, labor strength is reduced, improves efficiency of construction, ensures construction quality.
The above described is only a preferred embodiment of the present invention, not the structure of the present invention is made any formal Limitation.Any simple modification, equivalent change and modification that every technical spirit according to the present invention is made to above example, Belong in the range of technical scheme.

Claims (3)

1. a kind of assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, it is characterised in that including being arranged on The lane change brick precast beam on cast-in-place wall top;
The grout hole for grouting is provided with the middle part of the lane change brick precast beam along its length;
Lane change brick precast beam is provided with sleeve joint bar and overlap joint reinforcing bar;
The cylinder joint bar and overlap joint reinforcing bar are structure as a whole with lane change brick precast beam;
The lane change brick precast beam is provided with split bolt hole;
Specific construction step is as follows:
When progress cast-in-situ wall ties up muscle, the placement space of sidewalk brick precast beam is reserved on wall top;
Colligation cast-in-situ wall reinforcing bar, after cast-in-situ wall reinforcing bar colligation;
Lane change brick precast beam is placed on the good reinforcing bar of cast-in-situ wall colligation;
The reserved overlap joint reinforcing bar in lane change brick precast beam bottom is attached with cast-in-situ wall, by being arranged on lane change brick during formwork The split bolt in reserved split bolt hole on formula precast beam is reinforced to template;
By the grout hole reserved on lane change brick precast beam, cast-in-situ wall is poured;
Lane change brick precast beam forms an entirety with cast-in-situ wall;
The pre-buried sleeve joint bar in precast beam top is attached with upper strata precast wall body sleeve.
2. assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, its feature exist according to claim 1 In:The grout hole is through hole.
3. assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method, its feature exist according to claim 1 In:The sleeve joint bar stretches out from lane change brick precast beam upper surface;Reinforcing bar is overlapped to stretch out from lane change brick precast beam lower surface.
CN201710877974.1A 2017-09-26 2017-09-26 Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method Pending CN107675838A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710877974.1A CN107675838A (en) 2017-09-26 2017-09-26 Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710877974.1A CN107675838A (en) 2017-09-26 2017-09-26 Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method

Publications (1)

Publication Number Publication Date
CN107675838A true CN107675838A (en) 2018-02-09

Family

ID=61136123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710877974.1A Pending CN107675838A (en) 2017-09-26 2017-09-26 Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method

Country Status (1)

Country Link
CN (1) CN107675838A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409710A (en) * 2019-08-14 2019-11-05 长沙远大住宅工业(江苏)有限公司 A kind of composite beam, composite beam and cast-in-place column connected node and its construction method
CN110761419A (en) * 2019-10-29 2020-02-07 袁建华 Construction method for three-dimensional positioning accuracy of prefabricated house foundation connecting piece
CN111321821A (en) * 2020-02-28 2020-06-23 南京工程学院 Adopt prefabricated shear force wall steel bar connection structure tied in a bundle of full assembled level seam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101929200A (en) * 2010-08-11 2010-12-29 管乃彦 Prefabricated vertical component and construction method in application thereof
CN102425310A (en) * 2011-12-15 2012-04-25 中国二十二冶集团有限公司 Assembly-type residential shear wall structural wall body vertical connection construction method
CN102808465A (en) * 2012-08-08 2012-12-05 沈阳建筑大学 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN105780935A (en) * 2016-05-09 2016-07-20 福建工程学院 Prefabricated assembling type steel pipe restrained energy-dissipation connection node and construction method
CN105908977A (en) * 2016-06-08 2016-08-31 成都建筑工程集团总公司 Joint bar construction structure and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101929200A (en) * 2010-08-11 2010-12-29 管乃彦 Prefabricated vertical component and construction method in application thereof
CN102425310A (en) * 2011-12-15 2012-04-25 中国二十二冶集团有限公司 Assembly-type residential shear wall structural wall body vertical connection construction method
CN102808465A (en) * 2012-08-08 2012-12-05 沈阳建筑大学 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN105780935A (en) * 2016-05-09 2016-07-20 福建工程学院 Prefabricated assembling type steel pipe restrained energy-dissipation connection node and construction method
CN105908977A (en) * 2016-06-08 2016-08-31 成都建筑工程集团总公司 Joint bar construction structure and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409710A (en) * 2019-08-14 2019-11-05 长沙远大住宅工业(江苏)有限公司 A kind of composite beam, composite beam and cast-in-place column connected node and its construction method
CN110761419A (en) * 2019-10-29 2020-02-07 袁建华 Construction method for three-dimensional positioning accuracy of prefabricated house foundation connecting piece
CN111321821A (en) * 2020-02-28 2020-06-23 南京工程学院 Adopt prefabricated shear force wall steel bar connection structure tied in a bundle of full assembled level seam

Similar Documents

Publication Publication Date Title
CN102425310B (en) Assembly-type residential shear wall structural wall body vertical connection construction method
CN104179174B (en) A kind of multiple holes grouting pipe shaped pile and pile making method thereof
CN105019475A (en) Prefabricated integral concrete comprehensive pipe rack and construction method
CN105178357A (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN104847014A (en) Vertical connection structure for precast concrete shear walls and construction method
CN203080430U (en) Assembly and cast-in-place combined type reinforced concrete pipe type culvert
CN109837831A (en) A kind of centrifugation prefabricated assembled concrete bridge pier and construction method
CN106014446B (en) A kind of reinforcement means of enhancing high ground stress soft rock stress tunnel inverted arch structural stability
CN103485548B (en) Assembling hollow concrete overlapped shear wall Vertical bar connection method
CN102839601A (en) Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure
CN103334357A (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN106894587A (en) Precast stair connection method
CN107675838A (en) Assembled architecture sidewalk brick precast beam embedded sleeve barrel joint bar construction method
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN104631440A (en) Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN103590493A (en) Overlaid plate type concrete shear wall and longitudinal connecting method
CN206408515U (en) Precast pier section assembling structure
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN104074197A (en) Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof
CN108867361A (en) A kind of half grout sleeve connection prefabricated assembling type reinforced concrete side crashproof guardrail
CN107574934A (en) Fabricated shear wall embedded sleeve barrel joint bar construction method
CN108729466B (en) Large formwork supporting method for constructing anchor-free concrete retaining wall
CN204174527U (en) The hollow pier stud syndeton of a kind of bridge prefabrication
CN203498828U (en) Top reinforced cast-in-place concrete thin-wall pipe pile
CN206554428U (en) A kind of precast stair connecting node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180209

RJ01 Rejection of invention patent application after publication