CN102900168B - Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall - Google Patents

Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall Download PDF

Info

Publication number
CN102900168B
CN102900168B CN201210378398.3A CN201210378398A CN102900168B CN 102900168 B CN102900168 B CN 102900168B CN 201210378398 A CN201210378398 A CN 201210378398A CN 102900168 B CN102900168 B CN 102900168B
Authority
CN
China
Prior art keywords
shear wall
prefabricated
wall
sleeve
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210378398.3A
Other languages
Chinese (zh)
Other versions
CN102900168A (en
Inventor
赵唯坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201210378398.3A priority Critical patent/CN102900168B/en
Publication of CN102900168A publication Critical patent/CN102900168A/en
Application granted granted Critical
Publication of CN102900168B publication Critical patent/CN102900168B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

本发明涉及混凝土结构领域,具体为一种装配式混凝土框架-剪力墙拆分拼装结构以及拼装连接方法,由预制柱、预制梁、预制剪力墙和现浇节点构成,预制柱下端预埋套筒,与下层柱上端伸出来的钢筋突出段相互嵌合,通过灌注砂浆与下层柱连接为一体。预制梁纵向钢筋伸入节点核心区内锚固或与对侧梁筋进行机械式连接,预制柱和预制剪力墙之间设置现浇带进行柱墙预埋筋连接。预制剪力墙下端预埋钢筋套筒与下层墙伸上来的钢筋突出段相互嵌合,通过灌注砂浆与下层墙连接为一体。预制剪力墙上端与预制梁通过向贯通孔及套筒灌注砂浆,实现上下层剪力墙竖向钢筋的贯通连接,解决因预制梁隔断而使剪力墙竖向钢筋难以连续的关键问题。

The invention relates to the field of concrete structures, in particular to a prefabricated concrete frame-shear wall disassembly and assembly structure and an assembly connection method. The sleeve is fitted with the protruding section of the steel bar protruding from the upper end of the lower column, and is connected with the lower column as a whole by pouring mortar. The longitudinal reinforcement of the prefabricated beam extends into the core area of the node for anchorage or is mechanically connected with the opposite side beam reinforcement, and a cast-in-place belt is set between the prefabricated column and the prefabricated shear wall to connect the pre-embedded reinforcement of the column wall. The pre-embedded steel bar sleeve at the lower end of the prefabricated shear wall is fitted with the protruding section of the steel bar extending from the lower wall, and is connected with the lower wall as a whole by pouring mortar. The upper part of the prefabricated shear wall and the prefabricated beam are poured with mortar into the through hole and the sleeve to realize the connection of the vertical reinforcement of the upper and lower shear walls, and solve the key problem that the vertical reinforcement of the shear wall is difficult to be continuous due to the partition of the prefabricated beam.

Description

Assembly concrete Frame-Shear Wall splits splicing structure and assembled method of attachment
[technical field]
The present invention relates to prefabricated concrete structure field, be specially the assembled system of fractionation of a kind of fabricated assembly overall being formed by prefabricated post, precast beam and precast shear wall (hereinafter to be referred as assembling) concrete frame-shear wall structure, member connects structure, by the assembled system of this fractionation and the works that is connected structure construction, and assembled method of attachment.
[background technology]
The prior art of prefabricated concrete structure is mainly pure frame structure and shear wall structure, and the assembly concrete frame shear wall structure consisting of prefabricated post, precast beam and precast shear wall there is not yet work literary composition.Compare with pure frame structure or shear wall structure, because concrete frame-shear wall structure is the combination of wire rod and plane materiel, particularly shear wall is cut off by beam and column, causes the steel bar stress assembling difficulty that continues large, has no rationally effectively solution.Up to the present, concrete frame-shear wall structure is mainly to build by complete cast-in-place engineering method.The conventional way of assembling frame structure is that beam and column is prefabricated, and node is cast-in-place, is characterized in that the interspersed connection that crosses of reinforcing bar of all directions beam and column is anchored in joint cores, and node construction difficulty is larger, but structural integrity is good, can reach and be equal to cast-in-place structural.The current practice of fabricated shear wall structure is, upper and lower wall vertical reinforcement adopts docking sleeve or preformed hole reinforcing bar slurry anchor overlap joint, and left and right wall horizontal reinforcement adopts cast-in-place band overlap joint, its subject matter is that vertical reinforcement is generally double-sided ribs, its radical is too much, and lap length is longer, is not easy to construction.
[summary of the invention]
The object of the present invention is to provide a kind of assembling of concrete frame-shear wall structure to split assembled syndeton and assembled connection construction method, core content is to adopt cast-in-place node with when reaching simplification structure manufacture and assembled difficulty, propose 1. shear wall upper end and get rid of muscle, 2. independent joint bar, 3. the connected mode of pre-these three kinds of shear wall vertical reinforcements of doweling in beam, solves because precast beam cuts off and makes shear wall vertical reinforcement be difficult to continuous key issue.
technical scheme of the present invention:
Assembly concrete Frame-Shear Wall splits a splicing structure, and this structure is that the structure that prefabricated post, precast beam, precast shear wall and cast-in-place node form splits assembled system;
The lower end embedded bar sleeve of prefabricated post, mutually chimeric with the reinforcing bar nose section that lower floor post is stretched up, by note mortar in sleeve and connected horizontal joint, be connected to integral body with lower floor post;
The lower end embedded bar sleeve of precast shear wall, mutually chimeric with the reinforcing bar nose section that lower floor wall is stretched up, by perfusion mortar in sleeve and connected horizontal joint, be connected to integral body with lower floor shear wall;
Cast-in-place band is set between prefabricated post and precast shear wall, and in cast-in-place band to making prefabricated post side embedded bar and shear wall end face embedded bar carry out level connection joint, by cast-in-place concrete, make prefabricated post and shear wall be connected to integral body;
The upper end of prefabricated post, for outstanding straight reinforcing bar, is run through cast-in-place node and protrudes from floor face.
Described assembly concrete Frame-Shear Wall splits splicing structure, and the upper end of precast shear wall is outstanding straight reinforcing bar, reserved through hole in precast beam; The outstanding straight reinforcing bar of precast shear wall upper end runs through the reserved through hole of precast beam and protrudes from floor face, and perfusion mortar in the horizontal joint between reserved through hole and shear wall upper end and beam makes shear wall and beam consolidation for whole.
Described assembly concrete Frame-Shear Wall splits splicing structure, the upper end embedded bar sleeve of precast shear wall, reserved through hole in precast beam, another standby independently upper and lower wall dowel is as joint bar, joint bar runs through the reserved through hole of precast beam from top to bottom, and insert in the pre-buried reinforced bar sleeve in precast shear wall upper end, at the bottom of sleeve, shear wall upper end and beam between perfusion mortar in horizontal joint and reserved through hole, make shear wall and beam consolidation for integral body.
Described assembly concrete Frame-Shear Wall splits splicing structure, the upper end embedded bar sleeve of precast shear wall, pre-buried upper and lower wall dowel in precast beam, precast beam is installed from top to bottom, the lower end of pre-buried upper and lower wall dowel is inserted in the pre-buried reinforced bar sleeve in precast shear wall upper end, perfusion mortar in horizontal joint between at the bottom of sleeve and shear wall upper end and beam, makes shear wall and beam be connected to integral body.
Described assembly concrete Frame-Shear Wall splits splicing structure, and the fractionation connection arranging in the optional position of described shear wall horizontal direction between shear wall and adjacent post is connected with the fractionation of setting up shear wall self.
Described assembly concrete Frame-Shear Wall splits splicing structure, and precast beam adopts the precast beam of superimposed mode, or precast beam adopts the precast beam of full prefabrication system.
Described assembly concrete Frame-Shear Wall splits splicing structure, and the docking mode of sleeve grouting adopts preformed hole reinforcing bar slurry anchor overlapping mode to replace.
Described assembly concrete Frame-Shear Wall splits splicing structure, and this structure is as having single span shear wall, connecting the frame shear wall structure across shear wall, or has the frame shear wall structure of axle two direction shear walls in length and breadth.
In the present invention, the frame shear wall structure thing that can use the fractionation splicing structure of above-mentioned assembly concrete Frame-Shear Wall described in any one to build.
Above-mentioned assembly concrete Frame-Shear Wall splits the assembled method of attachment of splicing structure, in every floor construction,
The first step, hoisting prefabricated post, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's post of left and right prefabricated post are stretched is up mutually chimeric, locates note mortar in backward sleeve and connected horizontal joint;
Second step, hoisting prefabricated shear wall, the reinforcing bar nose section that lower end embedded bar sleeve and lower floor's wall of precast shear wall are stretched is up mutually chimeric, locates perfusion mortar in backward sleeve and connected horizontal joint;
The 3rd step, carries out level overlap joint by post side embedded bar nose section and shear wall end face embedded bar nose section, configures vertical reinforcement simultaneously, then at cast-in-place band portion formwork fluid concrete;
The 4th step, hoisting prefabricated beam, make the outstanding straight reinforcing bar in precast shear wall upper end run through reserved through hole in precast beam, or upper and lower wall dowel is inserted in the pre-buried sleeve in precast shear wall upper end through precast beam through hole from top to bottom, or pre-doweling in precast beam is inserted in the pre-buried sleeve in precast shear wall upper end from top to bottom; After precast beam install is in place, to perfusion mortar in horizontal joint and reserved through hole and sleeve;
The 5th step, beam column node core area formwork, cast-in-situ floor formwork or superimposed sheet is installed and is configured upper reinforcement;
The 6th step, builds node concrete, builds overlapping layers concrete, completes this layer of construction;
Carry out last layer construction, repeat above six steps.
effect of the present invention:
1, the present invention proposes fractionation splicing structure system and member method of attachment, see on the whole and have following characteristics: it is reasonable that 1. each member splits position, is convenient to structure manufacture and transportation; 2. member is generally symmetrical, and weight is reasonable, is convenient to lifting and installs; 3. all members are from top to bottom and install, and are convenient to lifting and install; 4. vertical reinforcement joint adopts single reinforced bar sleeve grouting docking, and joint is reliable; 5. shear wall vertical reinforcement is in by the two-sided distribution bar of minimum structure requirement configuration, and it is that the large spacing diameter steel bar of a row is configured on wall center line that the vertical reinforcement area that calculating is needed is concentrated.Like this, meet the requirement of standard structure, bar splice is few again.Although amount of reinforcement slightly increases, sleeve is few, and cost is relatively low, goes back constructability; 6. between post wall, cast-in-place bandwidth is little, and situ wet operation is few, and assembly rate is high.
2, core content of the present invention is the method for attachment of precast shear wall vertical reinforcement (core muscle), and three kinds of methods in the present invention have feature separately, can be according to physical condition reasonable selection.While forming assembly concrete frame shear wall structure by prefabricated post, precast beam and precast shear wall, fractionation how to carry out post be connected, the fractionation of beam be connected, the fractionation of shear wall and adjacent post be connected, the fractionation of shear wall and adjacent beams be connected, and the connection of reinforcing bar between levels shear wall.By adopting, rationally effectively split assembled system and member connected mode, reduce to greatest extent the wet trades such as cast-in-place concrete, improve assemblingization degree, the reduction of erection time, facilitate structure manufacture and the globality that guarantees fabricated construction simultaneously.
3, structural system of the present invention consists of prefabricated post, precast beam, precast shear wall and cast-in-place node, prefabricated post lower end embedded sleeve barrel, mutually chimeric with the reinforcing bar nose section that lower floor's post upper end is stretched, by perfusion mortar and lower floor's post, connect as one, precast beam longitudinal reinforcement stretch in joint cores anchoring or with curb girder muscle carried out to mechanical type be connected, cast-in-place band is set between prefabricated post and precast shear wall and carries out post wall embedded ribs and connect.The reinforcing bar nose section that precast shear wall lower end embedded bar sleeve and lower floor's wall are stretched is up mutually chimeric, by perfusion mortar and lower floor's wall, connects as one.The outstanding reinforcing bar in precast shear wall upper end and the reserved corresponding linking of vertical through hole in precast beam, or precast shear wall upper end embedded bar sleeve inserts the corresponding linking of bar dowel with after reserved through hole in pre-doweling or precast beam in precast beam.Thereby, by through hole and sleeve perfusion mortar, realize the perforation connection of levels shear wall vertical reinforcement.
[accompanying drawing explanation]
Fig. 1 (a)-Fig. 1 (d): the first assembly concrete frame shear wall structure of the present invention splits assembled connection constructional drawing (1. reserved through hole in precast beam, is inserted in the outstanding reinforcing bar mode in dry wall top).Wherein, the facade main view of Fig. 1 (a) for splitting; Fig. 1 (b) is assembled facade main view; Fig. 1 (c) is II-II sectional drawing in Fig. 1 (a); Fig. 1 (d) is I-I sectional drawing in Fig. 1 (a).
Fig. 2 (a)-Fig. 2 (d): it is flat, vertical that the second assembly concrete frame shear wall structure of the present invention splits assembled connection structure, sectional drawing (2. reserving through hole, beam rear insertion bar dowel mode in place in precast beam).Wherein, the facade main view of Fig. 2 (a) for splitting; Fig. 2 (b) is assembled facade main view; Fig. 2 (c) is II-II sectional drawing in Fig. 2 (a); Fig. 2 (d) is I-I sectional drawing in Fig. 2 (a).
Fig. 3 (a)-Fig. 3 (d): it is flat, vertical that the third assembly concrete frame shear wall structure of the present invention splits assembled connection structure, sectional drawing (3. pre-doweling mode in precast beam).Wherein, the facade main view of Fig. 3 (a) for splitting; Fig. 3 (b) is assembled facade main view; Fig. 3 (c) is II-II sectional drawing in Fig. 3 (a); Fig. 3 (d) is I-I sectional drawing in Fig. 3 (a).
In figure, 1 precast beam (superposed beam); 2 reserved through holes; 3 groove shear key I; 4 prefabricated post; 5 precast shear walls; Wall dowel Shang Xia 6; 7 cast-in-place band joint bars; 8 groove shear key II; 9 cast-in-situ concretes; 10 grouting; 11 on-the-spot arrangements of reinforcement; 12 cast-in-place bands; 13 cast-in-place nodes; 14 groove shear key III; 15 two-sided distribution bars within the walls; 16 sleeve I; Wall dowel (joint bar) Shang Xia 17; 18 horizontal joint grouting or seat slurry; 19 sleeve II; Wall dowel (pre-buried) Shang Xia 21; The U-shaped dowel of 22 wall; The U-shaped dowel of 23 post.
[specific embodiment]
Assembly concrete Frame-Shear Wall of the present invention splits splicing structure and assembled method of attachment, specific as follows:
(1) adopt by prefabricated or partial precast post (hereinafter to be referred as prefabricated post), prefabricated or partial precast beam (hereinafter to be referred as precast beam) and the assembled system of fractionation prefabricated or partial precast shear wall (hereinafter to be referred as dry wall) formation structure.Wherein node of column and beam core space adopts cast-in-place mode, to guarantee the globality of post beam, is convenient to element precast simultaneously.For the interconnecting of vertical reinforcement between levels shear wall in implementation framework-shear wall structure, in precast beam, be provided with and intert reserved through hole or the pre-doweling of body of wall vertical reinforcement.The connection of the vertical reinforcement of prefabricated post and precast shear wall all adopts docking sleeve mode.
(2) in precast beam, the reserved through hole for interspersed shear wall vertical reinforcement can adopt metal bellows moulding, also can adopt the moulding of plastics QC.Metal bellows should adopt two rib bellowss, and its rib Gao Yi is more than 1mm.Pore-forming internal diameter is determined according to worn bar diameter d, generally should be taken as 1.2d~3.0d.
(3) between precast shear wall and adjacent post, on wall limit, split.Between connection adopt cast-in-place band mode, from precast shear wall and adjacent post are outstanding separately, U-shaped dowel be set carry out level overlap joint.When assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, thereby insert from top to bottom bight vertical reinforcement at four interior angle places of this closed space, form sleeper.In addition, at shear wall end face, with relative prefabricated post side, concrete groove shear key should be set respectively.By cast-in-place band portion formwork poured in place concrete, make shear wall and adjacent post form integral body.This connected mode can realize following working mechanism: on the one hand U-shaped dowel overlap joint can significantly reduce the lap length of reinforcing bar, and Xiao's bolt effect by joint bar further strengthens the anchoring of U-shaped dowel again.This reinforcement manner can form sleeper on the other hand, strengthens the binding effect to shear wall, thereby improves bearing capacity and the ductility of shear wall.Concrete groove shear key is set, to increase interface shearing strength, reduces shearing slip, strengthen the co-operation of shear wall and peripheral frame.
(4) prefabricated post splits at capital face and basal surface position.The connection of the vertical reinforcement of levels prefabricated post adopts sleeve grouting docking mode, with the reliability that guarantees to connect.Be that prefabricated post lower end is buried sleeve underground, the outstanding straight reinforcing bar that passes through cast-in-place joint cores in upper end.After lower floor beam column node core area and the hardening of concrete of floor in-situ layer, lift this layer of post installation in position, in sleeve and prefabricated post lower end horizontal joint, pour into high-strength mortar, Ben Cengzhuyu lower floor post folder node is become one, and be connected to integral body by cast-in-place node and precast beam.
(5) between precast shear wall and upper underbeam, at wall end face and basal surface position, split.In precast shear wall, except single or double level and vertical distribution reinforcement are set, will calculate required vertical applied force reinforcing bar centralized arrangement in wall core (being called for short shear wall core muscle), and be connected with levels shear wall core muscle.The vertical connection of shear wall core muscle adopts sleeve grouting docking mode, its lower end embedded sleeve barrel, the core muscle tabling of stretching up with lower floor shear wall, after installation in position, becomes one this layer of body of wall and lower floor's body of wall folder beam to pouring into high-strength mortar in sleeve and connected horizontal joint.There are following three kinds of ways the upper end of precast shear wall:
(1) the outstanding straight reinforcing bar in precast shear wall upper end (upper and lower wall dowel).When top precast beam is installed, more than making the outstanding vertical reinforcement in precast shear wall upper end run through through hole reserved in precast beam and protruding from top surface of the beam (being floor face), between shear wall upper end and soffit, horizontal joint is set.After precast beam install is in place, to pouring into high-strength mortar in reserved through hole and connected horizontal joint in precast beam, making precast shear wall and precast beam fixed is integral body.
(2) precast shear wall upper end embedded sleeve barrel.When top precast beam is installed, make the interior reserved through hole of beam roughly consistent with the position, hole of its lower shear wall upper end embedded sleeve barrel, then upper and lower wall dowel (abbreviation joint bar) is inserted in the pre-buried sleeve in precast shear wall upper end through through hole from top to bottom, in sleeve, between precast beam and lower wall, in horizontal joint and pour into high-strength mortar in reserved through hole in precast beam, making precast shear wall and precast beam fixed is integral body.
(3) precast shear wall upper end embedded sleeve barrel, pre-buried upper and lower wall dowel (joint bar) in precast beam.When top precast beam is installed, pre-doweling in beam is inserted in the pre-buried sleeve in precast shear wall upper end from top to bottom, after precast beam install is in place, in sleeve and between precast beam and lower wall, in horizontal joint, pour into high-strength mortar, make precast shear wall and precast beam fixed for whole.
(6) more than, for splitting assembled system and connect, the assembling in frame shear wall structure plane constructs.Can adopt above-mentioned form equally with the connection of plane external member (be vertical direction member, comprise wall, beam, floor etc.).
(7) structure of the present invention splits the construction method of assembled system and is: from the floor face of every layer, 1. prefabricated post is installed.Make prefabricated post bottom embedded sleeve barrel and lower floor's post bar splice mutually chimeric, in place after, the precast shear wall between erection column of column bottom sleeve and horizontal joint grouting connection → 2..First lift body of wall to post plane outside and the bar splice that keeps a little higher than lower floor wall to stretch out, confirming that post stretches out U-shaped dowel and wall and stretches out the non-interference height of U-shaped dowel body of wall is moved horizontally to intercolumniation, then decline make shear wall bottom embedded sleeve barrel and lower floor's wall bar splice mutually chimeric.After in place, U-shaped dowel interior angle place's vertical reinforcement colligation connect → are 3. inserted in the grouting of shear wall bottom sleeves and horizontal joint from top to bottom, complete cast-in-place band arrangement of reinforcement, cast-in-place band both sides formwork, concreting → 4. install precast beam.Hoisting prefabricated beam from top to bottom, make the outstanding straight reinforcing bar in precast shear wall upper end run through reserved through hole in precast beam/or by upper and lower wall dowel (joint bar) from top to bottom through precast beam through hole insert in the pre-buried sleeve in precast shear wall upper end/or pre-doweling in precast beam is inserted in the pre-buried sleeve in precast shear wall upper end from top to bottom.After precast beam install is in place, to perfusion high-strength mortar in horizontal joint and reserved through hole (and sleeve) → 5. bean column node and floor slab construction.Cast-in-place beam column node core area, cast-in-situ floor or laminated floor slab top configuration reinforcement are also built overlapping layers concrete.
Fig. 1 (a)-(d) is reserved through hole 2 in precast beam, is inserted in the outstanding reinforcing bar mode in dry wall 5 tops.This assembly concrete Frame-Shear Wall splits splicing structure and mainly comprises: precast beam (superposed beam) 1, reserved through hole 2, groove shear key I 3, prefabricated post 4, precast shear wall 5, upper and lower wall dowel 6, cast-in-place band joint bar 7, groove shear key II 8, cast-in-situ concrete 9, grouting 10, on-the-spot arrangement of reinforcement 11, be cast-in-placely with 12, cast-in-place node 13, groove shear key III 14, two-sided distribution bar 15, sleeve I 16, the U-shaped dowel 22 of wall, the U-shaped dowel 23 of post etc. within the walls, concrete structure is as follows:
Between prefabricated post 4, be provided with precast shear wall 5, precast shear wall 5 is with 12 to be connected with prefabricated post 4 by cast-in-place, 4 liang of side-prominent U-shaped dowels 23 of post that arrange of prefabricated post, the outstanding U-shaped dowel 22 of wall that arranges of the precast shear wall 5 corresponding with prefabricated post 4, the U-shaped dowel 22 of wall and the U-shaped dowel 23 level overlap joints of post, when assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, and plug from top to bottom cast-in-place band joint bar 7 at interior angle place, four, this closed confinement space, on precast shear wall 5 and prefabricated post 4 opposite faces, be respectively equipped with groove shear key II 8 and groove shear key III 14, cast-in-placely be with 12 to be cast in precast shear wall 5 and prefabricated post 4 junctions.
Precast shear wall 5 vertically wears upper and lower wall dowel 6, the top of precast shear wall 5 arranges precast beam (superposed beam) 1, precast beam (superposed beam) 1 has reserved through hole 2, the upper end of upper and lower wall dowel 6 and the corresponding coupling of reserved through hole 2 in precast beam (superposed beam) 1, during tipping, upper and lower wall dowel 6 stretches out outside precast beam (superposed beam) 1, and upper and lower wall dowel 6 is connected by grouting 10 with precast beam (superposed beam) 1.
As shown in Fig. 1 (a)-Fig. 1 (c), after precast beam (superposed beam) 1 is in place, between contiguous prefabricated beam (superposed beam) 1 and prefabricated post 4 tops, by on-the-spot arrangement of reinforcement 11(is set, be mainly lateral tie in joint cores) and cast-in-situ concrete 9, cast-in-place node 13 formed.In addition, between contiguous prefabricated beam (superposed beam) 1, on opposite face, be respectively equipped with groove shear key I 3.
Connection between levels prefabricated post and between levels precast shear wall all adopts sleeve grouting docking mode.The bottom of prefabricated post 4 and precast shear wall 5 arranges sleeve I 16, and the outstanding straight reinforcing bar in prefabricated post 4 upper ends also passes through cast-in-place node 13, and the outstanding upper and lower wall dowel 6 in precast shear wall 5 upper ends also passes through precast beam (superposed beam) 1.Chimeric and the grouting of straight reinforcing bar that prefabricated post 4 is stretched up by sleeve Ⅰ16Yu lower floor, the chimeric and grouting of the dowel of wall up and down 6 that precast shear wall 5 is stretched up by sleeve Ⅰ16Yu lower floor, forms sleeve grouting docking.
As shown in Figure 1 (d) shows, the surrounding of prefabricated post 4 arranges respectively precast shear wall 5, on prefabricated post 4 and precast shear wall 5 opposite faces, groove shear key III 14 is set, and adopts two-sided distribution bar 15 within the walls in precast shear wall 5.
Its advantage is sleeve minimum number, and cost is low; Shortcoming is that the outstanding reinforcing bar in dry wall top is longer, and inconvenience transportation is deposited and lifted, and reserved through hole grouting amount increases.
Fig. 2 (a)-(d) is reserved through hole in precast beam, beam rear insertion bar dowel mode in place.This assembly concrete Frame-Shear Wall splits splicing structure and mainly comprises: precast beam (superposed beam) 1, reserved through hole 2, groove shear key I 3, prefabricated post 4, precast shear wall 5, cast-in-place band joint bar 7, groove shear key II 8, cast-in-situ concrete 9, grouting 10, on-the-spot arrangement of reinforcement 11, be cast-in-placely with 12, cast-in-place node 13, groove shear key III 14, two-sided distribution bar 15, sleeve I 16, upper and lower wall dowel (joint bar) 17, sleeve II 19, the U-shaped dowel 22 of wall, the U-shaped dowel 23 of post etc. within the walls, concrete structure is as follows:
Between prefabricated post 4, be provided with precast shear wall 5, precast shear wall 5 is with 12 to be connected with prefabricated post 4 by cast-in-place, 4 liang of side-prominent U-shaped dowels 23 of post that arrange of prefabricated post, the outstanding U-shaped dowel 22 of wall that arranges of the precast shear wall 5 corresponding with prefabricated post 4, the U-shaped dowel 22 of wall and the U-shaped dowel 23 level overlap joints of post, when assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, and plug from top to bottom cast-in-place band joint bar 7 at interior angle place, four, this closed confinement space, on precast shear wall 5 and prefabricated post 4 opposite faces, be respectively equipped with groove shear key II 8 and groove shear key III14, cast-in-placely be with 12 to be cast in precast shear wall 5 and prefabricated post 4 junctions.
The top of precast shear wall 5 arranges precast beam (superposed beam) 1, precast beam (superposed beam) 1 has reserved through hole 2, precast beam (superposed beam) 1 vertically wears upper and lower wall dowel (joint bar) 17, upper and lower wall dowel (joint bar) 17 and the corresponding coupling of reserved through hole 2 in precast beam (superposed beam) 1, the top of precast shear wall 5 arranges sleeve II 19, when assembled, stretch out outside precast beam (superposed beam) 1 one end of upper and lower wall dowel (joint bar) 17, the other end of upper and lower wall dowel (joint bar) 17 is connected with precast shear wall 5 with grouting 10 by sleeve II 19.
As shown in Fig. 2 (a)-Fig. 2 (c), after precast beam (superposed beam) 1 is in place, between contiguous prefabricated beam (superposed beam) 1 and prefabricated post 4 tops, by on-the-spot arrangement of reinforcement 11(is set, be mainly lateral tie in joint cores) and cast-in-situ concrete 9, cast-in-place node 13 formed.In addition, between contiguous prefabricated beam (superposed beam) 1, on opposite face, be respectively equipped with groove shear key I 3.
Connection between levels prefabricated post and between levels precast shear wall all adopts sleeve grouting docking mode.Prefabricated post 4 bottoms arrange sleeve I 16, and the outstanding straight reinforcing bar in upper end also passes through cast-in-place node 13.Chimeric and the grouting of straight reinforcing bar that prefabricated post 4 is stretched up by sleeve Ⅰ16Yu lower floor, forms sleeve grouting docking.
The bottom of precast shear wall 5 arranges sleeve I 16, and top arranges sleeve II 19.Upper and lower wall dowel (joint bar) 17 downwards and lower floor's precast shear wall top sleeve II 19 is chimeric and grouting, and upwards and grouting chimeric with upper strata precast shear wall bottom sleeves I 16 forms sleeve grouting docking.
As shown in Figure 1 (d) shows, the surrounding of prefabricated post 4 arranges respectively precast shear wall 5, on prefabricated post 4 and precast shear wall 5 opposite faces, groove shear key III 14 is set, and adopts two-sided distribution bar 15 within the walls in precast shear wall 5.
Its advantage be dry wall without outstanding reinforcing bar, be convenient to transportation and install; Shortcoming is to need to hold up straight location after bar dowel inserts, and reserved through hole grouting amount increases.
Fig. 3 (a)-(d) is pre-doweling mode in precast beam.This assembly concrete Frame-Shear Wall splits splicing structure and mainly comprises: precast beam (superposed beam) 1, groove shear key I 3, prefabricated post 4, precast shear wall 5, cast-in-place band joint bar 7, groove shear key II 8, cast-in-situ concrete 9, grouting 10, on-the-spot arrangement of reinforcement 11, be cast-in-placely with 12, cast-in-place node 13, groove shear key III 14, two-sided distribution bar 15, sleeve I 16, horizontal joint grouting or seat slurry 18, sleeve II 19, upper and lower wall dowel (pre-buried) 21, the U-shaped dowel 22 of wall, the U-shaped dowel 23 of post etc. within the walls, concrete structure is as follows:
Between prefabricated post 4, be provided with precast shear wall 5, precast shear wall 5 is with 12 to be connected with prefabricated post 4 by cast-in-place, 4 liang of side-prominent U-shaped dowels 23 of post that arrange of prefabricated post, the outstanding U-shaped dowel 22 of wall that arranges of the precast shear wall 5 corresponding with prefabricated post 4, the U-shaped dowel 22 of wall and the U-shaped dowel 23 level overlap joints of post, when assembled, make it mutually overlap and form degree of lip-rounding closed confinement space, and plug from top to bottom cast-in-place band joint bar 7 at interior angle place, four, this closed confinement space, on precast shear wall 5 and prefabricated post 4 opposite faces, be respectively equipped with groove shear key II 8 and groove shear key III14, cast-in-placely be with 12 to be cast in precast shear wall 5 and prefabricated post 4 junctions.
The top of precast shear wall 5 arranges precast beam (superposed beam) 1, precast beam (superposed beam) 1 vertically wears upper and lower wall dowel (pre-buried) 21, the top of precast shear wall 5 arranges sleeve II 19, stretch out outside precast beam (superposed beam) 1 one end of upper and lower wall dowel (pre-buried) 21, and when assembled, the other end of upper and lower wall dowel (pre-buried) 21 is connected with precast shear wall 5 with grouting 10 by sleeve II 19.During tipping, in the top of precast shear wall 5 and bottom and precast beam (superposed beam) 1 junction, horizontal joint grouting or seat slurry 18 are set.
As shown in Fig. 3 (a)-Fig. 3 (c), after precast beam (superposed beam) 1 is in place, between contiguous prefabricated beam (superposed beam) 1 and prefabricated post 4 tops, by on-the-spot arrangement of reinforcement 11(is set, be mainly lateral tie in joint cores) and cast-in-situ concrete 9, cast-in-place node 13 formed.In addition, between contiguous prefabricated beam (superposed beam) 1, on opposite face, be respectively equipped with groove shear key I 3.
Connection between levels prefabricated post and between levels precast shear wall all adopts sleeve grouting docking mode.Prefabricated post 4 bottoms arrange sleeve I 16, and the outstanding straight reinforcing bar in upper end also passes through cast-in-place node 13.Chimeric and the grouting of straight reinforcing bar that prefabricated post 4 is stretched up by sleeve Ⅰ16Yu lower floor, forms sleeve grouting docking.
The bottom of precast shear wall 5 arranges sleeve I 16, and top arranges sleeve II 19.Upper and lower wall dowel (pre-buried) 21 downwards and lower floor's precast shear wall top sleeve II 19 is chimeric and grouting, and upwards and grouting chimeric with upper strata precast shear wall bottom sleeves I 16 forms sleeve grouting docking.
As shown in Fig. 3 (d), the surrounding of prefabricated post 4 arranges respectively precast shear wall 5, on prefabricated post 4 and precast shear wall 5 opposite faces, groove shear key III 14 is set, and adopts two-sided distribution bar 15 within the walls in precast shear wall 5.
Its advantage is to omit through hole, reduces grouting amount, to vertical muscle configuration in beam, disturbs little; Shortcoming is that precast beam top and bottom reinforcing bar is outstanding, and unfavorable transportation is deposited, and the difficulty of being in the milk in addition increases.
Other embodiments:
(1) embodiment shown in Fig. 1-Fig. 3 is superposed beam mode, and precast beam also can adopt full prefabrication system.
(2) the overlap joint degree of the beam-ends of precast beam and post should not be less than 20mm, and beam-ends face should be established groove shear key.The anchoring of precast beam longitudinal reinforcement in joint cores can adopt crotch form, also can adopt the mechanical types such as docking sleeve to be connected with the beam pairing of node opposite side.
(3) connection of precast shear wall vertical reinforcement (core muscle), except sleeve grouting docking mode, also can adopt preformed hole reinforcing bar slurry anchor overlapping mode.
(4) between shear wall and adjacent post, in the connected mode of U-shaped dowel, can form sleeper as required.The formation method of sleeper is, increases radical and the diameter of vertical joint bar, simultaneously can be between U-shaped dowel separately configuration realize stirrup encryption with the close-shaped consistent single rectangle hoop of U-shaped dowel.
(5) when reducing the size of body of wall transportation or lifting or weight and need further segmenting wall body, can increase laterally fractionation (vertical cast-in-place band) in any position in the middle of body of wall, the connected mode between its assembled connected mode and shear wall and adjacent post is basic identical.
(6) the horizontal reinforcement method of attachment between shear wall and adjacent post is not limited to U-shaped dowel connected mode, also can adopt other overlapping modes or mechanical type connected mode.
(7) the present invention goes for having single span shear wall, connects the frame shear wall structure across shear wall, is applicable to too have the frame shear wall structure of axle two direction shear walls in length and breadth.

Claims (10)

1.一种装配式混凝土框架-剪力墙拆分拼装结构,其特征是:1. A prefabricated concrete frame-shear wall split assembly structure is characterized in that: 该结构为预制柱、预制梁、预制剪力墙和现浇节点构成的结构拆分拼装体系;The structure is a structural disassembly and assembly system composed of prefabricated columns, prefabricated beams, prefabricated shear walls and cast-in-place nodes; 预制柱的下端预埋钢筋套筒,与下层柱伸上来的钢筋突出段相互嵌合,通过向套筒及相连水平缝内注砂浆,与下层柱连接为整体;The lower end of the prefabricated column is pre-embedded with a steel sleeve, which is fitted with the protruding section of the steel bar extending from the lower column, and is connected with the lower column as a whole by injecting mortar into the sleeve and the connected horizontal joint; 预制剪力墙的下端预埋钢筋套筒,与下层墙伸上来的钢筋突出段相互嵌合,通过向套筒及相连水平缝内灌注砂浆,与下层剪力墙连接为整体;The lower end of the prefabricated shear wall pre-embeds the steel bar sleeve, which is fitted with the protruding section of the steel bar extending from the lower wall, and is connected with the lower shear wall as a whole by pouring mortar into the sleeve and the connected horizontal joints; 预制柱与预制剪力墙之间设置现浇带,并在现浇带内对使预制柱侧预埋钢筋和剪力墙端面预埋钢筋进行水平连接,通过现场浇注混凝土使预制柱与剪力墙连接为整体;A cast-in-place belt is set between the prefabricated column and the prefabricated shear wall, and the pre-embedded steel bars on the side of the precast column and the pre-embedded steel bars on the end of the shear wall are horizontally connected in the cast-in-place belt. The wall is connected as a whole; 预制柱的上端为突出直钢筋,贯穿现浇节点并突出于楼板面之上。The upper end of the prefabricated column is a protruding straight steel bar, which runs through the cast-in-place node and protrudes above the floor surface. 2.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:预制剪力墙的上端为突出直钢筋,预制梁内预留贯通孔;预制剪力墙上端的突出直钢筋贯穿预制梁预留贯通孔并突出于楼板面之上,预留贯通孔及剪力墙上端与梁之间的水平缝内灌注砂浆,使剪力墙与梁固结为整体。2. According to claim 1, the assembled concrete frame-shear wall disassembly and assembly structure is characterized in that: the upper end of the prefabricated shear wall is a protruding straight steel bar, and a through hole is reserved in the prefabricated beam; the upper end of the prefabricated shear wall The protruding straight steel bars run through the reserved through-holes of the prefabricated beams and protrude above the floor surface. The reserved through-holes and the horizontal joints between the top of the shear wall and the beam are poured with mortar to consolidate the shear wall and the beam as a whole. 3.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:预制剪力墙的上端预埋钢筋套筒,预制梁内预留贯通孔,另备独立的上下墙连接筋作为插筋,插筋由上向下贯穿预制梁预留贯通孔,并插入预制剪力墙上端预埋的钢筋套筒内,套筒、剪力墙上端与梁底之间水平缝及预留贯通孔内灌注砂浆,使剪力墙与梁固结为整体。3. The assembled concrete frame-shear wall disassembly and assembly structure according to claim 1 is characterized in that: the upper end of the prefabricated shear wall is pre-embedded with a steel sleeve, and a through hole is reserved in the prefabricated beam, and an independent The connecting bars of the upper and lower walls are used as inserting bars, and the inserting bars run through the reserved through-holes of the prefabricated beam from top to bottom, and are inserted into the pre-embedded steel bar sleeves at the top of the precast shear wall. Pour mortar into the joints and reserved through-holes to consolidate the shear walls and beams as a whole. 4.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:预制剪力墙的上端预埋钢筋套筒,预制梁内预埋上下墙连接筋,由上向下安装预制梁,使预埋上下墙连接筋的下端插入预制剪力墙上端预埋的钢筋套筒内,套筒及剪力墙上端与梁底之间的水平缝内灌注砂浆,使剪力墙与梁连接为整体。4. The assembled concrete frame-shear wall disassembly and assembly structure according to claim 1 is characterized in that: the upper end of the prefabricated shear wall is pre-embedded with a steel bar sleeve, and the upper and lower walls are pre-embedded in the prefabricated beam. Install the prefabricated beam downwards so that the lower end of the pre-embedded upper and lower wall connecting ribs is inserted into the pre-embedded steel bar sleeve at the upper end of the prefabricated shear wall, and mortar is poured into the sleeve and the horizontal joint between the upper end of the shear wall and the bottom of the beam to make the shear wall The force wall is connected with the beam as a whole. 5.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:在所述剪力墙水平方向的任意位置设置剪力墙和相邻柱之间的拆分连接和增设剪力墙自身的拆分连接。5. According to the assembled concrete frame-shear wall split assembly structure according to claim 1, it is characterized in that: the split between the shear wall and the adjacent column is set at any position in the horizontal direction of the shear wall Connect and add split connections for the shear wall itself. 6.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:预制梁采用叠合方式的预制梁,或者预制梁采用全预制方式的预制梁。6. The prefabricated concrete frame-shear wall disassembly and assembly structure according to claim 1, characterized in that: the prefabricated beam adopts a prefabricated beam in a superimposed manner, or the prefabricated beam adopts a prefabricated beam in a fully prefabricated manner. 7.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:套筒灌浆的对接方式采用预留孔钢筋浆锚搭接方式代替。7. The prefabricated concrete frame-shear wall disassembly and assembly structure according to claim 1, characterized in that: the butt joint of sleeve grouting is replaced by the lap joint of reinforced grout with reserved holes. 8.按照权利要求1所述的装配式混凝土框架-剪力墙拆分拼装结构,其特征是:该结构作为具有单跨剪力墙、连跨剪力墙的框架-剪力墙结构,或者具有纵横轴二方向剪力墙的框架-剪力墙结构。8. according to claim 1, the assembled concrete frame-shear wall disassembly and assembly structure is characterized in that: the structure is used as a frame-shear wall structure with single-span shear walls and continuous-span shear walls, or Frame-shear wall structure with shear walls in two directions of vertical and horizontal axes. 9.使用权利要求1至7中任何一项所述的装配式混凝土框架-剪力墙的拆分拼装结构建造的框架-剪力墙结构物。9. The frame-shear wall structure constructed by using the split and assembled structure of the prefabricated concrete frame-shear wall described in any one of claims 1 to 7. 10.一种权利要求1至7中任何一项所述的装配式混凝土框架-剪力墙拆分拼装结构的拼装连接方法,其特征是:在每层楼施工中,10. A method for assembling and connecting the prefabricated concrete frame-shear wall split and assembling structure described in any one of claims 1 to 7, characterized in that: in the construction of each floor, 第一步,吊装预制柱,将左右预制柱的下端预埋钢筋套筒与下层柱伸上来的钢筋突出段相互嵌合,定位后向套筒及相连水平缝内注砂浆;The first step is to hoist the prefabricated columns, fit the pre-embedded reinforcement sleeves at the lower ends of the left and right prefabricated columns with the protruding sections of the reinforcement protruding from the lower columns, and inject mortar into the sleeves and connected horizontal joints after positioning; 第二步,吊装预制剪力墙,将预制剪力墙的下端预埋钢筋套筒与下层墙伸上来的钢筋突出段相互嵌合,定位后向套筒及相连水平缝内灌注砂浆;The second step is to hoist the prefabricated shear wall, fit the pre-embedded steel bar sleeve at the lower end of the prefabricated shear wall with the protruding section of the steel bar protruding from the lower wall, and pour mortar into the sleeve and the connected horizontal joint after positioning; 第三步,将柱侧预埋钢筋突出段与剪力墙端面预埋钢筋突出段进行水平搭接,同时配置竖向钢筋,然后对在现浇带部分支模并浇注混凝土;The third step is to horizontally overlap the protruding section of the pre-embedded steel bar on the column side with the protruding section of the pre-embedded steel bar on the end face of the shear wall, and arrange vertical reinforcement at the same time, and then set up the mold and pour concrete on the part of the cast-in-place belt; 第四步,吊装预制梁,使预制剪力墙上端突出直钢筋贯穿预制梁内预留贯通孔,或将上下墙连接筋由上向下穿过预制梁贯通孔插入预制剪力墙上端预埋的套筒内,或使预制梁内预埋插筋由上向下插入预制剪力墙上端预埋的套筒内;预制梁安装就位后,向水平缝和预留贯通孔以及套筒内灌注砂浆;The fourth step is to hoist the prefabricated beam so that the protruding straight steel bar on the top of the prefabricated shear wall runs through the reserved through hole in the prefabricated beam, or insert the connecting bars of the upper and lower walls through the through hole of the prefabricated beam from top to bottom and insert it into the prefabricated shear wall. into the sleeve, or insert the pre-embedded ribs in the prefabricated beam into the pre-embedded sleeve at the top of the prefabricated shear wall from top to bottom; pouring mortar; 第五步,梁柱节点核心区支模,现浇楼板支模或安装叠合板并配置上部钢筋;The fifth step is to set up the formwork in the core area of the beam-column joint, support the formwork for the cast-in-place floor slab or install the laminated slab and configure the upper reinforcement; 第六步,浇筑节点混凝土,浇筑叠合层混凝土,完成本层施工;The sixth step is to pour the node concrete, pour the composite layer concrete, and complete the construction of this layer; 进行上一层施工,重复以上六个步骤。Carry out the construction of the previous layer and repeat the above six steps.
CN201210378398.3A 2012-10-08 2012-10-08 Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall Active CN102900168B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210378398.3A CN102900168B (en) 2012-10-08 2012-10-08 Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210378398.3A CN102900168B (en) 2012-10-08 2012-10-08 Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall

Publications (2)

Publication Number Publication Date
CN102900168A CN102900168A (en) 2013-01-30
CN102900168B true CN102900168B (en) 2014-08-20

Family

ID=47572631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210378398.3A Active CN102900168B (en) 2012-10-08 2012-10-08 Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall

Country Status (1)

Country Link
CN (1) CN102900168B (en)

Families Citing this family (44)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590510B (en) * 2013-11-27 2016-01-13 上海建工五建集团有限公司 The fixed connection method of embedded bar in fabricated construction and cast-in-place structural
CN104032858B (en) * 2014-05-15 2016-06-29 中国建筑股份有限公司 Assembled girder steel seam in-line mixing coupled wall and construction method thereof
CN104032855B (en) * 2014-05-15 2016-08-24 中国建筑股份有限公司 Assembled cross mixing coupled wall and construction method thereof
CN104481031B (en) * 2014-11-05 2017-01-11 沈阳建筑大学 Assembly connection structure and method of coupling beams of shear walls of assembly concrete frame shear structure
CN104652654B (en) * 2015-02-11 2017-04-26 沈阳建筑大学 Assembled shear wall structure
CN104775545B (en) * 2015-03-09 2016-09-07 沈阳建筑大学 Assembly concrete Frame-Shear Wall splits the method for attachment of component
CN104727467A (en) * 2015-03-23 2015-06-24 河北联合大学 Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method
CN104790533B (en) * 2015-04-27 2017-10-13 沈阳建筑大学 Fabricated construction preformed hole starches anchor lapping construction method under a kind of low temperature environment
CN104790556B (en) * 2015-05-01 2017-08-01 俞锡贤 The impervious self-heat conserving external wall body of architectural exterior-protecting construction fire prevention and its construction
CN106320712A (en) * 2015-06-30 2017-01-11 上海宝冶集团有限公司 Method for grouting of assembly type building shear wall sleeve
CN105003029B (en) * 2015-07-22 2017-10-27 山东明达建筑科技有限公司 Sleeve muscle straightening opposed former
CN106436975A (en) * 2016-10-26 2017-02-22 曲周县和盛新型建筑材料有限公司 Built-in girder shear wall
CN106638455A (en) * 2016-12-15 2017-05-10 长春工程学院 Composite Z-shaped precast reinforced concrete bunding protective wall
CN106968381B (en) * 2017-04-28 2023-09-22 广东省建科建筑设计院有限公司 Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves
CN106930430B (en) * 2017-05-03 2023-12-08 承德绿建建筑节能科技有限公司 Wall structure with exposed rib groove observation holes
CN107268888A (en) * 2017-07-31 2017-10-20 中民筑友建筑科技(昆山)有限公司 A kind of precast beam structure
CN107795036A (en) * 2017-12-01 2018-03-13 三筑工科技有限公司 Shear wall attachment structure and shear wall connection system
CN108166627B (en) * 2017-12-19 2023-11-10 浙江绿筑集成科技有限公司 Corner construction method of combined wall
CN108005410B (en) * 2017-12-20 2023-06-20 中冶建筑研究总院有限公司 Assembled steel-concrete combined structure residential system and construction method thereof
CN107989228B (en) * 2017-12-20 2023-06-20 中冶建筑研究总院有限公司 Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof
CN108316508A (en) * 2018-02-05 2018-07-24 华北水利水电大学 A kind of Node Processing Method of assembled architecture wall
CN108801346B (en) * 2018-06-04 2024-02-06 广东省建科建筑设计院有限公司 Parallel sleeve grouting detection structure and method for vertical prefabricated parts
CN108801345B (en) * 2018-06-04 2024-02-09 广东省建科建筑设计院有限公司 Tandem sleeve grouting detection structure and method for vertical prefabricated parts
CN109440968A (en) * 2018-12-14 2019-03-08 湖南远大建工股份有限公司 Prefabricated panel, panel wall system and its construction method
CN109487910A (en) * 2018-12-22 2019-03-19 徐州工业职业技术学院 - inside casing assembled architecture mixed structure is cut outside a kind of
CN109680835B (en) * 2019-02-15 2024-03-22 姚攀峰 Self-supporting precast concrete wallboard, concrete wall, structural system and construction method
CN109811878A (en) * 2019-03-18 2019-05-28 江西万和建筑科技有限公司 Integrated structure and construction method of cast-in-place laminated formwork for prefabricated buildings
CN110106970B (en) * 2019-05-31 2024-08-02 西安建工绿色建筑集团有限公司 Assembled standard layer module and standard layer construction method combining dry and wet processes
CN110107016B (en) * 2019-05-31 2023-12-29 西安建工绿色建筑集团有限公司 Assembled prefabricated wallboard and wall construction method combining dry-wet technology
CN111270754A (en) * 2019-06-06 2020-06-12 吴充 Disassembly-free assembled house structure system
CN110206190B (en) * 2019-06-10 2020-12-22 安徽松之梦科技有限公司 Prefabricated reinforced concrete shear wall
CN110424579B (en) * 2019-07-30 2021-05-11 中国建筑第八工程局有限公司 Frame deformation mode resists assembled concrete shear force wall of macroseism
CN110374228A (en) * 2019-08-14 2019-10-25 六安远大住宅工业有限公司 A kind of cast-in-place sleeper steel bar arrangement of shear wall and its construction technology
CN110644624A (en) * 2019-09-16 2020-01-03 佛山建装建筑科技有限公司 Building connection node and construction method thereof
CN110644646A (en) * 2019-09-16 2020-01-03 佛山建装建筑科技有限公司 Split-level grouting sleeve connected assembled shear wall system
CN111119481A (en) * 2020-01-13 2020-05-08 中国建筑第八工程局有限公司 Reinforcement structure and method of 3D printing components
CN112575964B (en) * 2020-11-30 2025-01-14 康博达建设科技集团有限公司 Prefabricated concrete column connected by non-grouting sleeve and installation method
CN112695928B (en) * 2021-01-07 2024-04-26 中铁建设集团有限公司 PBL-based precast concrete shear wall-ring beam connection structure and installation method
CN113006321B (en) * 2021-03-12 2021-09-28 昆山市建设工程质量检测中心 Construction method for connecting joints between combined precast concrete wall bodies
CN115341652B (en) * 2021-05-14 2024-07-09 河南众鼎智拓环保科技有限公司 Prefabricated reinforced concrete frame, shear wall structure and construction method
CN113136948B (en) * 2021-06-04 2025-01-07 中建海龙科技有限公司 An assembled concrete beam-column mortar anchor connection structure with shear keys and an assembly method
CN113775083A (en) * 2021-09-23 2021-12-10 广东博智林机器人有限公司 Prefabricated wallboard and cast-in-place beam connecting node structure and connecting method
CN114635502B (en) * 2022-03-11 2023-06-13 桂林理工大学 Prefabricated Split Beam with Superposed Nodes and Its Construction Method
CN118148375B (en) * 2024-01-26 2024-11-22 广州广检建设工程检测中心有限公司 An assembled shear wall suitable for frame shear wall structure and installation method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH084196A (en) * 1994-06-24 1996-01-09 Taisei Corp Building panel
JPH11172810A (en) * 1997-12-16 1999-06-29 Dps Bridge Works Co Ltd Earthquake resisting wall and earthquake resisting reinforcing structure
CN1260436A (en) * 1999-01-13 2000-07-19 北京华洋建设开发有限公司 Medium- and high-rise steel structure earthquake-resistant building system
CN2893023Y (en) * 2006-03-27 2007-04-25 扬州大学 Reinforced Concrete Prefabricated Frame-Shear Wall Building Structure
CN202831203U (en) * 2012-10-08 2013-03-27 沈阳建筑大学 Assembly type concrete frame-shear wall split assembling structure and fabricative structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH084196A (en) * 1994-06-24 1996-01-09 Taisei Corp Building panel
JPH11172810A (en) * 1997-12-16 1999-06-29 Dps Bridge Works Co Ltd Earthquake resisting wall and earthquake resisting reinforcing structure
CN1260436A (en) * 1999-01-13 2000-07-19 北京华洋建设开发有限公司 Medium- and high-rise steel structure earthquake-resistant building system
CN2893023Y (en) * 2006-03-27 2007-04-25 扬州大学 Reinforced Concrete Prefabricated Frame-Shear Wall Building Structure
CN202831203U (en) * 2012-10-08 2013-03-27 沈阳建筑大学 Assembly type concrete frame-shear wall split assembling structure and fabricative structure

Also Published As

Publication number Publication date
CN102900168A (en) 2013-01-30

Similar Documents

Publication Publication Date Title
CN102900168B (en) Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall
CN202831203U (en) Assembly type concrete frame-shear wall split assembling structure and fabricative structure
CN102808465B (en) Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN202831296U (en) Assembled spliced connecting structure of concrete frame-shear wall and structure constructed
CN203113553U (en) Prefabricated concrete frame-shear wall structure
CN203097016U (en) Assembled-type concrete frame shear wall structure
CN203320738U (en) Assembled concrete frame-shear wall structure
CN104775545B (en) Assembly concrete Frame-Shear Wall splits the method for attachment of component
CN202865991U (en) Assembled monolithic shear wall building structure
CN107044177A (en) A kind of assembly concrete shear wall fractionation, assembled attachment structure and connection method
CN102561553A (en) Prefabricated concrete-filled steel tube frame-shear wall and construction method thereof
KR101207786B1 (en) Precast concrete slab module
KR101225661B1 (en) Concrete shear key strengthened with steel cover plate and tension member and the construction method therewith
KR101661644B1 (en) Girder using precast slab connection block and precast slab construction method therewith
CN103572873A (en) Assembled monolithic floor slab and construction method thereof
CN109930484A (en) A kind of very-high performance deck structrue and its construction method
CN204590240U (en) Assembly concrete Frame-Shear Wall precast construction
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN106760036B (en) A kind of prefabricated steel-combined concrete shear wall
KR101263370B1 (en) Precast end-block with girder connection member and bridge construction method using ths same
CN114033111A (en) Assembled cornice inclined roof and installation and construction method thereof
CN110042770A (en) A method of using the original bridge of external prestressing steel Shu Tuokuan in length and breadth
CN211312950U (en) Assembled integral elevator shaft prefabricated part
KR101007012B1 (en) Tunnel end reinforcement structure and tunnel top end reinforcement method using the same
KR101735077B1 (en) Bridge deck using precast concrete panel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant