AU2020352698B2 - Method for erecting segmental steel girder on pier-top short slideway girder - Google Patents

Method for erecting segmental steel girder on pier-top short slideway girder Download PDF

Info

Publication number
AU2020352698B2
AU2020352698B2 AU2020352698A AU2020352698A AU2020352698B2 AU 2020352698 B2 AU2020352698 B2 AU 2020352698B2 AU 2020352698 A AU2020352698 A AU 2020352698A AU 2020352698 A AU2020352698 A AU 2020352698A AU 2020352698 B2 AU2020352698 B2 AU 2020352698B2
Authority
AU
Australia
Prior art keywords
girder
pier
steel girder
steel
short slideway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
AU2020352698A
Other languages
English (en)
Other versions
AU2020352698A1 (en
Inventor
Tao Chen
Yibing CUI
Yong Hu
Weijun JIA
Jianghua JIANG
Juntang Li
Bing Luo
Haihua SHU
Yuliang SONG
Hao Yang
Sen YAO
Daohong ZHA
Geng Zhang
Wenbin Zhang
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Publication of AU2020352698A1 publication Critical patent/AU2020352698A1/en
Application granted granted Critical
Publication of AU2020352698B2 publication Critical patent/AU2020352698B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
AU2020352698A 2019-09-29 2020-06-29 Method for erecting segmental steel girder on pier-top short slideway girder Active AU2020352698B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201910934860.5 2019-09-29
CN201910934860.5A CN110629677B (zh) 2019-09-29 2019-09-29 墩顶短滑道梁上架设节段钢梁的方法
PCT/CN2020/098665 WO2021057145A1 (zh) 2019-09-29 2020-06-29 墩顶短滑道梁上架设节段钢梁的方法

Publications (2)

Publication Number Publication Date
AU2020352698A1 AU2020352698A1 (en) 2022-03-24
AU2020352698B2 true AU2020352698B2 (en) 2024-03-14

Family

ID=68973598

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2020352698A Active AU2020352698B2 (en) 2019-09-29 2020-06-29 Method for erecting segmental steel girder on pier-top short slideway girder

Country Status (7)

Country Link
JP (1) JP7276599B2 (zh)
KR (1) KR102635982B1 (zh)
CN (1) CN110629677B (zh)
AU (1) AU2020352698B2 (zh)
GB (1) GB2603424B (zh)
MA (1) MA56285B1 (zh)
WO (1) WO2021057145A1 (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110629677B (zh) * 2019-09-29 2021-01-26 中铁大桥局集团有限公司 墩顶短滑道梁上架设节段钢梁的方法
CN114016422B (zh) * 2021-11-23 2023-11-03 中铁大桥局集团有限公司 一种钢梁架设方法
CN114214967A (zh) * 2021-12-25 2022-03-22 中交路桥建设有限公司 一种山区高墩大跨度无支架钢箱梁顶推安装方法
CN114687295B (zh) * 2022-04-26 2024-03-19 石家庄铁道大学 循环浮运桥位架设简支钢梁的施工方法
CN114808752B (zh) * 2022-04-27 2023-09-05 中交路桥建设有限公司 钢桁梁双顶托举顶推安装方法
CN114808740A (zh) * 2022-05-27 2022-07-29 山东省路桥集团有限公司 一种首孔梁架设施工的方法

Family Cites Families (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5115539A (ja) * 1974-07-29 1976-02-07 Nippon Kokan Kk Hashigetakasetsukoho
JPS6038488B2 (ja) * 1978-07-07 1985-09-02 オイレス工業株式会社 橋梁の押し出し架設工法
JPS5536553A (en) * 1978-09-06 1980-03-14 Nippon Kogen Concrete Method of installing truss beam by pushinggout
DE3124038C2 (de) * 1981-06-19 1985-03-07 Philipp Holzmann Ag, 6000 Frankfurt Verfahren und Vorrichtung zum Herstellen von Bauwerken wie Brücken unter Verwendung von Beton-Fertigteilträgern
JPS62189206A (ja) * 1986-02-17 1987-08-19 株式会社 宮地鐵工所 橋の構築方法
JP4264470B2 (ja) * 1997-02-19 2009-05-20 株式会社横河ブリッジ 橋桁部材の架設方法および架設装置
JP2003105719A (ja) * 2001-10-01 2003-04-09 Nichiei Kensetsu:Kk パッケージ化による一括架設工法に用いる地組装置
JP3885554B2 (ja) * 2001-10-31 2007-02-21 鹿島建設株式会社 橋梁の押出し工法
JP2005171638A (ja) * 2003-12-11 2005-06-30 Oriental Construction Co Ltd コンクリート桁の張出し架設工法における変位調整方法
JP5214371B2 (ja) * 2008-08-26 2013-06-19 株式会社Ihiインフラシステム 構造物
CN201574357U (zh) * 2009-10-13 2010-09-08 武汉通联路桥机械技术有限公司 移动模架梳形梁自动平衡机构
KR101415908B1 (ko) * 2012-04-03 2014-07-09 원대연 복합트러스 거더교 가설을 위한 압출공법
RU2514331C1 (ru) * 2012-12-14 2014-04-27 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Способ монтажа балки жесткости вантового моста
JP6025544B2 (ja) * 2012-12-14 2016-11-16 株式会社Ihiインフラシステム 橋梁の架設方法
TWI564452B (zh) * 2014-12-03 2017-01-01 財團法人國家實驗研究院 輕量便橋系統及其建造方法
CN104480862B (zh) * 2014-12-03 2016-04-20 中铁大桥局集团有限公司 一种斜拉桥边跨钢桁梁的架设方法
JP6514882B2 (ja) * 2014-12-03 2019-05-15 大成建設株式会社 橋桁の架設工法
CN105088959B (zh) * 2015-08-21 2017-04-12 中交武汉港湾工程设计研究院有限公司 一种钢桁梁节点自适应连续顶推系统
CN105648914B (zh) * 2015-12-30 2017-05-24 海波重型工程科技股份有限公司 一种中小型钢桁系杆拱桥的施工方法
CN206173812U (zh) * 2016-10-21 2017-05-17 金华职业技术学院 一种桥梁新型连续梁施工滑移装置
CN206783181U (zh) * 2017-01-16 2017-12-22 宜宾市远平机械制造有限公司 一种配重可移动的新型塔吊
CN107503296A (zh) * 2017-08-31 2017-12-22 中国十九冶集团有限公司 贝雷桥就位方法
CN207775734U (zh) * 2017-12-12 2018-08-28 中交第二公路工程局有限公司 一种单悬臂拼装的平衡调节装置
CN207974016U (zh) * 2018-03-09 2018-10-16 陕西华山路桥集团有限公司 一种钢桁架顶推支撑系统
KR101996819B1 (ko) 2018-07-18 2019-07-05 에스오씨기술지주 주식회사 카운트웨이트 및 중간횡레일을 이용한 숏 거더 런칭 시스템 및 이를 이용한 거더 시공방법
CN109778700B (zh) * 2019-01-15 2020-07-24 中铁一局集团有限公司 一种跨越既有道路的现浇槽形梁三点滑移顶推施工方法
CN109629458B (zh) * 2019-01-23 2020-11-27 腾达建设集团股份有限公司 桥梁悬臂施工的体系转换方法
CN109944170A (zh) * 2019-05-06 2019-06-28 重庆建工市政交通工程有限责任公司 高墩连续梁边跨现浇段及合龙段一体化施工体系及施工方法
KR102120757B1 (ko) * 2019-05-13 2020-06-10 에스오씨기술지주 주식회사 카운트웨이트 및 중간횡레일을 이용한 숏 거더 런칭 시스템 및 이를 이용한 거더 시공방법
CN210288140U (zh) * 2019-07-03 2020-04-10 桂林电子科技大学 一种简易的预制桥面板吊装台车
CN110258293A (zh) * 2019-07-22 2019-09-20 中铁大桥局集团有限公司 斜拉桥钢桁梁主塔墩顶架设施工方法
JP7172916B2 (ja) * 2019-08-20 2022-11-16 Jfeエンジニアリング株式会社 橋梁上部工撤去工法
CN110644378A (zh) * 2019-09-04 2020-01-03 中国一冶集团有限公司 合拢段施工的配重卸载自动调节系统及其施工调节方法
CN110629677B (zh) * 2019-09-29 2021-01-26 中铁大桥局集团有限公司 墩顶短滑道梁上架设节段钢梁的方法

Also Published As

Publication number Publication date
KR20220051851A (ko) 2022-04-26
GB2603424B (en) 2023-07-05
CN110629677A (zh) 2019-12-31
JP2022550266A (ja) 2022-12-01
GB202205842D0 (en) 2022-06-08
AU2020352698A1 (en) 2022-03-24
WO2021057145A1 (zh) 2021-04-01
MA56285B1 (fr) 2023-12-29
MA56285A1 (fr) 2023-06-28
KR102635982B1 (ko) 2024-02-08
JP7276599B2 (ja) 2023-05-18
CN110629677B (zh) 2021-01-26
GB2603424A (en) 2022-08-03

Similar Documents

Publication Publication Date Title
AU2020352698B2 (en) Method for erecting segmental steel girder on pier-top short slideway girder
CN111501574B (zh) 钢板梁s平面线型无导梁分联平行顶推施工方法
US20170247877A1 (en) Method for constructing cylindrical tank
US3027633A (en) Method and apparatus for bridge construction
WO1996036780A1 (fr) Ossature provisoire utilisee dans la construction d'un batiment
CN110219242B (zh) 一种双层同步梁内起梁的安装施工方法
CN107761573A (zh) 跨河桥梁底部贝雷梁临时支架顶升浮运拆除方法
CN113073839B (zh) 一种重载自爬施工装置及其爬升方法
JP2016142097A (ja) 可搬式昇降装置および水平部材の解体方法
CN210917052U (zh) 大吨位顶推装置
JPH08333898A (ja) 建物ブロック等の垂直、水平運搬用架台
CN111593732A (zh) 采用贝雷桥跨越常态混凝土坝段的碾压混凝土入仓方法
CN110258358B (zh) 采用吊推支架施工变高度钢梁的方法
CN114197889B (zh) 一种楼层装配节提升装置
CN116119540B (zh) 一种水上吊装机系统及其转移方法
JPS58523B2 (ja) キヨウリヨウトウノ ジヨウブコウゾウコウチクソウチ
CN114737494B (zh) 海上施工方法
CN216921424U (zh) 一种超高锥形钢塔分段提升安装装置
CN218951990U (zh) 一种横移落梁便携组装式钢支墩
CN111945575B (zh) 一种大方量承台双壁套箱整体吊装施工装置及施工方法
CN220927541U (zh) 一种用于上承式拱桥主梁安装施工的提吊系统
CN115404786B (zh) 一种钢混组合梁顶推施工方法
JPH08333813A (ja) 垂直、水平運搬する建物ブロックによる建物の建築工法
CN101391727A (zh) 吊车
CN110644368A (zh) 一种移动模架整体安装方法