WO2008128665A1 - Verfahren und vorrichtung zum ausschäumen von schotterbetten - Google Patents
Verfahren und vorrichtung zum ausschäumen von schotterbetten Download PDFInfo
- Publication number
- WO2008128665A1 WO2008128665A1 PCT/EP2008/002910 EP2008002910W WO2008128665A1 WO 2008128665 A1 WO2008128665 A1 WO 2008128665A1 EP 2008002910 W EP2008002910 W EP 2008002910W WO 2008128665 A1 WO2008128665 A1 WO 2008128665A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- ballast
- reactive
- mixing head
- mixture
- ballast bed
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/001—Track with ballast
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B27/00—Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
- E01B27/12—Packing sleepers, with or without concurrent work on the track; Compacting track-carrying ballast
- E01B27/13—Packing sleepers, with or without concurrent work on the track
- E01B27/16—Sleeper-tamping machines
- E01B27/18—Sleeper-tamping machines by introducing additional fresh material under the sleepers, e.g. by the measured-shovel method, by the blowing method
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2203/00—Devices for working the railway-superstructure
- E01B2203/04—Cleaning or reconditioning ballast or ground beneath
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2203/00—Devices for working the railway-superstructure
- E01B2203/04—Cleaning or reconditioning ballast or ground beneath
- E01B2203/047—Adding material, e.g. tar, glue, protective layers
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/03—Injecting, mixing or spraying additives into or onto ballast or underground
Definitions
- the invention relates to a method for partially or completely foaming the cavities in the ballast structure of a ballast bed, under which a planum is arranged, with a reactive plastic, in which the reactive components are mixed in a high-pressure mixer and in which the starting time for the reactive mixture is adjusted, that the foaming process essentially begins only when the reactive mixture has reached the planum.
- the traditional railway path consists essentially of the so-called planum applied ballast bed, in which the sleepers, which may consist of wood, concrete or steel, are embedded and on which the rails are attached.
- DD 86201 has set itself the task of causing a substantial increase in the lateral displacement resistances and proposes to strengthen the threshold compartments by metering hardened plastic resins in the spraying or pouring process, whereby the plastic is atomised or cast as a film , That is, this patent describes measures to improve the ballast bed stability against horizontal track forces, namely by gluing the ballast stones in the upper part of the ballast stand together.
- the stability against horizontal track forces is to be improved by gluing the ballast scaffold located laterally outside the two rails "at most" to about the threshold lower edge at the points of contact.
- the stability against vertical track forces is to be improved by partially or completely filling the cavities of the ballast structure in the area under the sleeper bearing, so that the stones are adhesively bonded to the surface.
- the gluing at the points of contact of the ballast stones in the upper area of the ballast tower should be done by "raining or trickling".
- the surface bonding of the ballast stones to the substrate should be done by "injecting" the binder.
- DE-OS 24 48 978 and US-A-3 942 448 describe special embodiments of injection lances.
- EP 1 619 305 also refers to foam lances in order to inject the reactive plastic into the ballast structure.
- DE-OS 23 05 536 which has actually made the lifting of tracks as a repair measure to the task, describes a special filling probe for injecting reactive plastic under the crossing point between rail and threshold.
- the invention relates to a method for partially or completely foaming the cavities in the ballast structure of a ballast bed, under which a planum is arranged, with a reactive plastic, in which
- the reactive components are required to metering at least one high-pressure mixing head and mixed there, and
- the starting time for the reactive mixture is adjusted so that the foaming process essentially begins only when the reactive mixture has reached the planum.
- the reactive plastic is polyurethane.
- a planum is the separating layer between the superstructure and the substructure of a track construction.
- the superstructure consists of the track, the sleepers on which the track is fixed, and the ballast bed in which the sleepers are located.
- ballast bed is a heap of gravel to understand.
- the ballast bed is a ballast bed for track systems, i. that in the upper part of the ballast bed sleepers are arranged, on which in turn rails are attached.
- the ballast is usually compacted in layers.
- gravel of different grain sizes can be used. It is common, for example, the use of gravel with a grain size of 22.4 to 63 mm. If necessary, this can also be mixed with gravel with a particle size of 16 to 22 mm.
- the gravel content of the ballast bed is to be understood in contrast to the cavities.
- Figures 1 to 6 show an example of the solution for the described task. They illustrate a method for partially foaming the voids in the ballast of ballast beds with a reactive plastic, for example with polyurethane, wherein in the upper part of the ballast bed sleepers are arranged, on which in turn rails are attached.
- the reactive components are metered to at least one high-pressure mixing head and there mixed and ansch manend the liquid reactive mixture applied by the high-pressure mixing head itself above the ballast bed on the ballast and allowed to flow through the ballast bed through to the subgrade under the ballast bed. Thereafter, the reactive mixture will foam and thereby rise.
- the so-called start time for the reactive mixture is adjusted so that the foaming process essentially begins only when the reactive mixture has reached the level.
- a high-pressure mixing head the components are sprayed via nozzles, which convert the pressure energy into flow energy, into a small mixing chamber in which they mix with each other due to their high kinetic energy.
- the pressure of the components entering the nozzles is at an absolute pressure of more than 25 bar, preferably in a range between 30 and 300 bar.
- the mixing chamber is cleaned mechanically after firing by means of a plunger.
- mixing heads which are blown out with air.
- the main advantage of the high-pressure mixing head is the fact that these mixing heads can be cleaned much better and without the use of solvents after each shot.
- high-pressure mixing heads are one-, two- or three-stage mixing heads in question, all of which are self-cleaning. That is, in these types of mixing heads, the complete mixing and discharge system is mechanically cleaned by slide from reactive mixture, so that then no more complicated rinsing and cleaning operations are required.
- the decision as to whether a one-, two- or three-slide mixing head is used depends on the degree of difficulty of the mixing task for the reactive mixture.
- a squeegee mixing head is quite sufficient, for example the so-called “groove mixing head” well-known in the PUR (polyurethane) industry.
- a two-slide mixing head e.g. the MT mixing head of the company Hennecke, required.
- a three-slide mixing head e.g. the MX mixing head of the company Hennecke.
- this high-quality mixing system there is a control valve for the mixing chamber area, a throttle slide for the throttle zone and a separate slide for the outlet area.
- a high-pressure mixing head which has a separate outlet channel, and through which the reactive mixture can be discharged laminar and free of spatter.
- Also essential for this new process is the process optimized set start time for the reactive mixture. For only in this way is it possible to apply the reactive mixture above the ballast bed to the ballast structure, to allow it to flow through the ballast bed to the ground under the ballast bed and then lather it and thereby allow it to rise.
- the start time is preferably set via the amount of activator in the recipe.
- a high proportion in the formulation causes a short start time, while a low proportion causes a long start time.
- the process is particularly flexible when the activator is dosed individually, as it can react directly and flexibly to the other conditions (ballast bed height, grain size, temperature).
- the usual activators in polyurethane chemistry generally known amine-containing or organometallic catalysts can be used as an activator.
- low-emission or emission-free catalysts should be used which are not elouted by precipitation water. Particular preference is given to using catalysts which react with the precipitation water to give ecologically harmless products.
- the method is surprisingly simple in that, without lances immersed in the heap, it is possible to foam out defined areas in the heap which is limited only by free flow.
- the starting time for the reactive mixture should be 3 to 30 seconds, preferably 4 to 20 seconds, particularly preferably 5 to 15 seconds.
- the start time to be set is dependent on the mixture viscosity of the raw material system, the grain size and packing density of the ballast bed, but above all on the ballast bed height H, which may be 20 to 40 cm, but in curves may also be 70 to 80 cm.
- the Schott temperature has an influence on the flow behavior and thus on the start time to be set.
- the appropriate start time can easily be determined empirically by considering the resulting foam cone as a function of the selected start time.
- Another variant consists in providing one of the main components with a basic activation or basic catalysis and mixing in only further catalyst or activator if necessary.
- the activator in the desired amount in the Nach Schollmengenstrom one of the main components, preferably the polyol component, is metered and mixed.
- the reactive plastic in a further process optimization, it is also possible to vary the size of the contact surface F between the planum and the reactive plastic and the rise height Zs of the foaming within the ballast bed the reactive plastic, namely essentially by the mass M applied reactive mixture, consistency of the chemical or physical parameters, such as Miscibility viscosity, blowing agent and thus foam density provided.
- the applied mass M in turn results from the product of mass flow m per unit of time and the metering time to-
- the mixture discharge at the outlet from the high pressure mixing head is as laminar as possible, so as to ensure a substantially aligned in the vertical direction, undisturbed flow through the reactive mixture through the ballast bed;
- the mixing head type plays an important role, but also the speed with which the reactive mixture leaves the mixing head permissible speeds are very decisively dependent on the viscosity of the mixture, for example, with mixture viscosities above 1000 mPas Exit speeds up to 10 m / s possible. For mixed viscosities below 500 mPas, however, only approx. 1 to 3 m / s are permissible.
- the exit velocity from the outlet from the high pressure mixing head is adjusted so that a laminar flow of the reactive mixture is established at the outlet from the mixing head outlet.
- An additional influencing factor for laminar mixture discharge is the distance d between the mixing head outlet and the ballast stand.
- distances up to 50 cm are quite possible.
- the distance should be only 0.5 to 10 cm.
- the ballast stones are tempered in the ballast bed. This means that in winter at minus temperatures, the gravel stones are heated and cooled in the summer in extreme heat.
- the optimum operating temperatures of the ballast stones are about 20 to 50 ° C, preferably at 25 to 40 0 C, more preferably at about 30 to 35 ° C.
- a particularly important application of this new method is the underfoaming of embedded in the upper part of the ballast bed sleepers, on which in turn rails are attached (see also Figures 3, 4, 5 and 6).
- ballast stones in the so-called load transfer cone below the thresholds, over which the track forces occurring by the driving operation in the planum, in their position, so that they no longer twisting and shifting, whereby a significant increase in the life of ballast beds is achieved.
- each support of the railroad track on the threshold each 2 to 8 injection points not more than 40 cm away from this support of the railroad track on the threshold.
- these injection points are located in each case half on both sides of the threshold.
- the reaction mixture is injected exclusively in this area. It is better, however, if additional injection points are arranged over the entire threshold width, so as to minimize the total lateral resistance and the setting of the track due to the load. However, more than 24 injection points per threshold no longer make sense, since in this case the amount to be injected per injection point is so low that form no more suitable foam chimneys. Consequently, the reactive mixture should be injected per threshold at 4 to a maximum of 24 points and preferably at 8 to a maximum of 20 points.
- Such an “antler” may be a cheap plastic disposable item, and a metal “antler” may burn out after each use so that it can be used again.
- the solution which is certainly more expensive from the investment costs, consists in using two metering units and two mixing heads which discharge the reactive mixture at the same time on both sides of the threshold (see FIGS. 5 and 6). Otherwise, however, this method has the advantage of unrestricted applicability. This means that this variant can also be used for highly reactive raw material systems.
- the mixture entry takes place along the threshold, i. substantially parallel to the longitudinal axis of the sill (i.e., in the Y-axis direction in Fig. 8), and preferably substantially in a passage which is interrupted for a short time only during traversal of the rails. That is, interrupted in these phases, only the Gemischaustrag, but not the further transport of the mixing heads.
- the reaction mixture is preferably injected at regular intervals at at least 6 points per threshold side.
- the reaction mixture is preferably initially introduced at each of the at least 6 positions along the Y axis in FIG. 8 at an Y position on both sides of the threshold, before the next position (on the Y axis) is approached along the threshold ,
- the mixture entry along the threshold is a function of the distance (ie of Y in Fig. 8), so that the rise height Zs of rising in the ballast scum a function of the distance (ie from Y in FIG. 8) (see also FIGS. 7 and 8).
- the adaptation of the metering time from step to step is the more sensible method.
- This method variant (rise height Zs - f (Y), ie function of the distance parallel to the longitudinal axis of the threshold) makes it possible, as shown in FIGS. 7 and 8, for Zs to increase steadily from one side to the other of the ballast bed, the gradient being approximately 2 ° to 10 °, preferably 3 ° to 8 °, particularly preferably 4 ° to 6 °.
- Z R f (Y) is the intersection line formed between two foam peaks at adjacent thresholds. Due to the inclination of these forming between the foam mountains gutters, it is thus possible to drain the located above the foam mountains free gravel zones, so that no harmful waterlogging throughout the ballast bed can arise.
- ballast bed drainage consists in the center line of the ballast bed seen in the direction of travel, quasi form a watershed, ie that the maximum rise height Zs max is in the middle of the sleeper and the troughs extend from the ballast bed center to the ballast bed sides.
- the ballast bed ends at the time of foam entry at the lower end of the thresholds and can optionally be further filled then.
- the reaction mixture can be entered immediately next to the threshold. This makes it even more purposeful to foam only the load transfer cone, which can reduce the consumption of raw materials somewhat, which of course has a positive effect on the cost-effectiveness of the process.
- the invention also relates to a device for foaming the cavities in the ballast structure of a ballast bed, under which a planum is arranged, comprising a reactive plastic
- At least one high-pressure mixing head which is hydraulically connected via lines with the metering units for the polyol-containing reactive component and for the isocyanate component, and e) at least one metering unit for an activator or catalyst which is hydraulically connected via lines to the metering unit or the associated container for one of the reactive components or directly to the high-pressure mixing head.
- a self-cleaning high-pressure mixing head As a mixing head, a self-cleaning high-pressure mixing head, whether a one-, two- or three-slider mixing head, has the preference in any case. Although there are also air cleaned high-pressure mixing heads, the use of which would significantly reduce the benefits of the described method, especially in ecological terms.
- the metering units for the two reaction components polyol and isocyanate must be suitable for applying absolute pressures of at least 25 bar, preferably from 30 to 300 bar.
- the dosing unit for the activator is important in order to be able to react flexibly to the other conditions (ballast bed height, grain size, temperature).
- the most flexible solution is to dose the activator individually into the mixing head.
- An alternative is the seeding of the polyol stream with the activator, which is then injected via the polyol nozzle into the mixing chamber. In this case, however, the activator may only be injected during the firing time, otherwise it accumulates undefined in the polyol container. Also conceivable is the seeding of the isocyanate stream with the activator.
- ballast bed height or grain size also usually does not change abruptly, this may still be a viable solution.
- the metering unit for the activator is usually a suitable metering pump.
- a suitable metering pump other types of dosage are also conceivable.
- the activator can also be metered into one of the reaction components by means of pre-pressure and a flexibly controllable, fast-switching valve.
- the ballast bed is first produced from washed, dried and compacted ballast.
- Either the dry ballast bed is then immediately foamed directly after the characterizing features of claim 1 according to the invention or it is temporarily covered to protect against rainfall in a suitable manner to keep it dry until the time of foaming.
- simple, mobile wagons which consist in the simplest case only of a scaffold with cover and wheels, is conceivable.
- the advantage of this variant is that the
- Ballast bed is always filled directly.
- handling devices for guiding the at least one mixing head are available on the rail vehicle since self-cleaning mixing heads can be relatively heavy.
- the weight of such a mixing head 10 kg, but also be 50 kg.
- the handling devices are also associated with a sensor to position the mixing head. In this way it is possible to run the foaming process completely automatically.
- the outlet from the high pressure mixing head is oriented substantially vertically (i.e., at a maximum angle of inclination to the vertical of 10 °) so that the reactive mixture can be discharged as laminarly as possible (i.e., avoiding splashing) in a free-flowing manner in the vertical direction.
- the spout from the high pressure mixing head is oriented substantially perpendicular to the direction of travel of the rail vehicle (i.e., at a maximum angle of inclination to the direction of travel of 10 ° to the direction of travel).
- the rail vehicle has wheels, wherein the outlet from the high-pressure mixing head in the discharge from the high-pressure mixing head is at most 30 cm in front of the rearmost in the discharge direction of the wheels and particularly preferably in the discharge rearmost extent of the wheels even towers. Most preferably, the outlet from the high-pressure mixing head projects beyond the rearmost extent of the wheels in the discharge direction by up to 15 cm, particularly preferably by up to 10 cm. It is thereby achieved that the preferably laminar mixture discharge from the high-pressure mixing head impinges precisely on the ballast stand in order to ensure a substantially vertically aligned, undisturbed flow through the reactive mixture through the ballast bed. Because with a turbulent, spurting mixture discharge, the reactive mixture would spread far beyond the surface of the ballast structure and the reactive mixture in the ballast stand would almost "run".
- FIG. 1 and FIG. 2 schematically show the basic sequence of the method according to the invention
- Figure 3 and Figure 4 schematically shows the foaming of a threshold with a
- FIG. 5 and FIG. 6 schematically show the underfoaming of a threshold with a tandem mixing head system
- FIG. 7 shows schematically a track section with a plurality of underfoamed
- Thresholds in section A 4 -A (corresponding to FIG. 8),
- FIG. 8 shows schematically a ballast bed in section B T B (corresponding to FIG. 7), and FIG
- FIG. 9 shows schematically a device according to the invention for partial
- polyurethane reactive components of storage containers are fed by means of metering units (not shown in the diagram) by means of connecting lines 2, 3 to a self-cleaning high-pressure mixing head 1 and mixed there. Subsequently, the liquid reactive mixture 4 above the ballast bed 5 is applied to the ballast tower 6 (i.e., the ballast portion of the ballast bed) and allowed to flow through the ballast tower to the ground 7.
- the ballast tower 6 i.e., the ballast portion of the ballast bed
- the mixture discharge is completely laminar and splash-free at a mixture viscosity of about 600 mPa sec and a discharge rate of about 3 m / s at a distance d of about 50 mm between ballast stand and mixing head outlet.
- the ballast bed has a height H of about 30 cm in the example shown in FIG.
- the dosing time is about 2 sec.
- the liquid reactive mixture has reached the planum and distributed on the surface 7 over an area F of about 350 cm 2 .
- the chemical reaction of the polyurethane reactive mixture begins (see also FIG. 4). That is, the starting time for the polyurethane reactive mixture is also about 6 sec.
- the chemical reaction produces propellant gas, through which the reactive mixture foams and rises through the ballast structure 6 in the ballast bed 5.
- the rise height Zs of the foamed reactive plastic is about 25 cm. Approximately 30 seconds after the beginning of the reaction, the foaming process is completed and the reactive plastic hardens, forming a vent 9 of reactive plastic in the ballast of the ballast bed in the area of which ballast stones 8 are fixed in position and so can neither twist nor move.
- FIG. 3 schematically shows a special application of the method according to the invention, namely the underfoaming of a threshold.
- polyurethane reactive components of storage containers via a metering unit (not shown in the diagram) are conveyed by means of connecting lines 2, 3 to a self-cleaning high-pressure mixing head 1 and mixed there.
- the high-pressure mixing head 1 is followed by a so-called antler 10, by means of which the liquid reactive mixture 4 is applied symmetrically to the vertical transverse axis 11 of the threshold 12 arranged in the upper region of the ballast bed 5 on the ballast structure 6.
- the mixture entry takes place on both sides immediately adjacent to the threshold 12, in this case at the same time.
- the lateral distance between the threshold and the mixture inflow into the ballast tower is approximately 20 mm on each side of the threshold in this example.
- the liquid reactive mixture 4 is also applied in this application above the ballast bed 5 on the ballast tower 6 and allowed to flow through the ballast tower through to the planum 7.
- the mixture entry is at a mixture viscosity of about 600 mPas and a discharge rate of about 3 m / s, at a distance d of about 50 mm between ballast 6 and the mixture outlet from the antlers 10 completely laminar and free of spatter.
- the ballast bed also has a height H of about 30 cm in this example.
- the dosing time is about 2 sec.
- the liquid reactive mixture 4 has reached the planum 7 and distributed on the planum on the surface F shown in Figure 4 of about 350 cm 2 .
- the chemical reaction of the polyurethane reactive mixture begins (see also FIG. 4). That is, the starting time for the polyurethane reactive mixture is also about 6 sec.
- the chemical reaction produces propellant gas, through which the reactive mixture foams and rises through the ballast structure 6 in the ballast bed 5.
- the rise height Zs of the foamed reactive plastic is about 25 cm.
- a vent 9 of reactive plastic is formed in the ballast structure of the ballast bed, which extends into the lower region of the threshold 12 and the ballast stones 8 fixed in place in the so-called load transfer cone below the threshold 12 and thus secures against twisting and shifting.
- FIGS. 5 and 6 show a variant of underfoaming of sleepers 12 arranged in the upper region of ballast beds 5.
- Polyurethane reactive components of storage containers but in this case via two metering units (not shown in the diagram), also become two high-pressure mixing heads 1a, 1b promoted and mixed there.
- the Gemischaustrag from the two high-pressure mixing heads Ia, Ib again takes place symmetrically to the vertical transverse axis 11 of the threshold 12, preferably at the same time.
- the lateral distance between the threshold and the respective mixture inflow into the ballast tower is approx. 20 mm. Larger lateral distances of up to approx. 50 mm enable a considerably greater tolerance for the mixing head guide system (see also FIG. 9) and are quite permissible.
- the procedure is the same as already described in FIGS. 1 and 2 as well as 3 and 4.
- the ballast bed height H is again 30 cm.
- the dosing time is slightly longer in this example. It is about 2.5 sec. This changes the flow time for the liquid reactive mixture through the ballast tower to about 5 sec, but is still within the starting time of 6 sec.
- the wetted with liquid reactive plastic surface F on the planum is accordingly also larger, as shown in Figure 6. It is now about 440 cm 2 . Also, the height of rise Zs gets bigger. It now roughly corresponds to the ballast bed height of 30 cm.
- FIG. 7 schematically shows a track section with a plurality of underfoamed sleepers 12a, 12b. This is particularly clear how the ballast stones are fixed within the load transfer areas below the thresholds 12a, 12b by the polyurethane plastic in position. However, FIG. 7 also shows that channels 13a, 13b form below the thresholds between the individual plastic channels 9a, 9b.
- FIG. 8 which corresponds to FIG. 7, shows a solution in which the outflow of water through the channels 13a, 13b is favored.
- the channel 13b between the plastic channels 9a, 9b below the sleepers 12a, 12b are inclined transversely to the ballast bed 5 in this example. In this way, no possibly damaging backwash water can form in the free gravel areas above the plastic channels 9a, 9b.
- the inclination angle is approximately 5 ° in the example shown.
- the maximum possible inclination angle is in this example essentially determined by the threshold length and the threshold thickness , because the maximum possible vertical rise difference (Zs max - Zs m ⁇ ) then corresponds approximately to the threshold thickness .
- Zs mm must still be so high that at this point a properly foamed load transfer cone is below the threshold and Zsmax should in turn not significantly exceed the ballast bed height. Since (Zsmax - Zsmm) is approximately proportional to (Z Rmax - Z Rmin ), a corresponding inclination angle also results for the drainage channels.
- Figure 9 shows schematically a device 20 according to the invention for partially filling the cavities in the ballast structure 6 of a ballast bed 5 with reactive plastic, e.g. with polyurethane.
- a rail vehicle 21 with drive 22 container 23 and a double metering 24 are arranged for the reactive components. Furthermore, there is a three-coordinate Mischkopf exchangessystem 25 for a tandem mixing head system with two mixing heads 26 on the rail vehicle 21.
- the connecting lines between containers, Doppeldosieraggregat and the mixing heads are not shown in this diagram.
- the Y coordinate guidance is necessary to guide the mixing heads 26 along the thresholds 27.
- the Z coordinate guidance is required in order to lift the mixing heads 26, on the one hand, over the rails 28, but, above all, to position them in the required distance to the ballast structure 6.
- the mixing head guidance system is also assigned a sensor system 29, which transmits the threshold and rail positions to a superordinate control device 30 and controls the X, Y, Z movements of the mixing head guidance system 25.
- a temperature control unit 31 On the rail vehicle 21 and a temperature control unit 31 is arranged. About a - not shown in the diagram - temperature sensor, the temperature of the ballast stones is transmitted to the control unit 30, which in turn switches the temperature control unit 31 when needed.
- the optimum temperature for the foaming process is around 30 ° C. In other words, in winter, the gravel must be heated and cooled in the summer heat.
- the conditions (pressure, temperature, level) for the container 23 and the Doppeldosieraggregat 25 are monitored by means not shown in the diagram indicators and transmitted to the control unit 30, which either outputs a signal in a tolerance violation or initiates a corresponding measure (in the scheme, however not shown).
- Figure 9 also shows the preferred embodiment in which the discharge from the high pressure mixing head 26 in the discharge direction from the high pressure mixing head (i.e., substantially in the vertical direction) overhangs the rearmost extent of the wheels (i.e., the contact point of wheels and rail 28). It is thereby achieved that the preferably laminar mixture discharge from the high-pressure mixing head impinges precisely on the ballast stand in order to ensure a substantially vertically aligned, undisturbed flow through the reactive mixture through the ballast bed.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
- Railway Tracks (AREA)
- Polyurethanes Or Polyureas (AREA)
- Manufacture Of Porous Articles, And Recovery And Treatment Of Waste Products (AREA)
- Processing And Handling Of Plastics And Other Materials For Molding In General (AREA)
Abstract
Description
Claims
Priority Applications (10)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES08748898.7T ES2546207T3 (es) | 2007-04-24 | 2008-04-12 | Procedimiento y dispositivo para rellenar con espuma lechos de balasto |
PL08748898T PL2150652T3 (pl) | 2007-04-24 | 2008-04-12 | Sposób i urządzenie do wypełniania pianką podłoży z tłucznia |
EP08748898.7A EP2150652B1 (de) | 2007-04-24 | 2008-04-12 | Verfahren und vorrichtung zum ausschäumen von schotterbetten |
US12/597,253 US20100140367A1 (en) | 2007-04-24 | 2008-04-12 | Method and device for foaming ballast beds |
MX2009011240A MX2009011240A (es) | 2007-04-24 | 2008-04-12 | Procedimiento y dispositivo para espumar lechos de balasto. |
AU2008241025A AU2008241025B2 (en) | 2007-04-24 | 2008-04-12 | Method and device for foaming ballast beds |
CA002684082A CA2684082A1 (en) | 2007-04-24 | 2008-04-12 | Method and device for foaming ballast beds |
JP2010504496A JP4960499B2 (ja) | 2007-04-24 | 2008-04-12 | バラスト床を発泡する方法およびデバイス |
BRPI0810398-4A BRPI0810398B1 (pt) | 2007-04-24 | 2008-04-12 | Método para espumar, parcialmente ou completamente, as cavidades em uma estrutura de lastro de um leito de lastro e dispositivo para espumar cavidades em estrutura de lastro de leito de lastro |
CN2008800130008A CN101663437B (zh) | 2007-04-24 | 2008-04-12 | 用于道床的泡沫充填的方法和装置 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102007019669A DE102007019669A1 (de) | 2007-04-24 | 2007-04-24 | Verfahren und Vorrichtung zum Ausschäumen von Schotterbetten |
DE102007019669.7 | 2007-04-24 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2008128665A1 true WO2008128665A1 (de) | 2008-10-30 |
Family
ID=39651363
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/EP2008/002910 WO2008128665A1 (de) | 2007-04-24 | 2008-04-12 | Verfahren und vorrichtung zum ausschäumen von schotterbetten |
Country Status (15)
Country | Link |
---|---|
US (1) | US20100140367A1 (de) |
EP (1) | EP2150652B1 (de) |
JP (1) | JP4960499B2 (de) |
KR (1) | KR101468245B1 (de) |
CN (1) | CN101663437B (de) |
AU (1) | AU2008241025B2 (de) |
BR (1) | BRPI0810398B1 (de) |
CA (1) | CA2684082A1 (de) |
DE (1) | DE102007019669A1 (de) |
ES (1) | ES2546207T3 (de) |
MX (1) | MX2009011240A (de) |
PL (1) | PL2150652T3 (de) |
RU (1) | RU2448211C2 (de) |
UA (1) | UA94815C2 (de) |
WO (1) | WO2008128665A1 (de) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102010016733A1 (de) | 2010-04-30 | 2011-11-03 | Bayer Materialscience Ag | Konditioniervorrichtung und Verfahren zum Trocknen und Temperieren eines Schotterbetts |
WO2013030149A1 (de) | 2011-09-01 | 2013-03-07 | Bayer Intellectual Property Gmbh | Verfahren zur herstellung von schotterkörpern |
DE102011053368A1 (de) | 2011-09-07 | 2013-03-07 | Bayer Materialscience Aktiengesellschaft | Raupenkette, Konditioniervorrichtung, Verfahren zum Temperieren eines Schotterbetts sowie Verwendung eines Schaumstoffs |
WO2013064546A1 (en) * | 2011-11-03 | 2013-05-10 | Bayer Intellectual Property Gmbh | Pouring and foaming vehicle |
WO2013057068A3 (en) * | 2011-10-19 | 2013-08-29 | Bayer Intellectual Property Gmbh | Mixing head-moving apparatus for a pouring machine for a ballast bed |
EP2730699A1 (de) * | 2012-11-09 | 2014-05-14 | Bayer MaterialScience AG | Verfahren zum Verschäumen eines Schotterbetts einer Eisenbahngleisanlage |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102251442B (zh) * | 2010-05-21 | 2015-07-29 | 拜耳材料科技(中国)有限公司 | 一种聚氨酯道碴层、及其制备方法和用途 |
AU2011244434B2 (en) * | 2010-04-21 | 2015-07-02 | Covestro Deutschland Ag | A polyurethane ballast layer, the method for preparing the same and the use thereof |
WO2012126145A1 (en) | 2011-03-24 | 2012-09-27 | Bayer Materialscience Ag | Process for production of ballast |
CN102950694A (zh) * | 2011-08-16 | 2013-03-06 | 拜耳材料科技(中国)有限公司 | 聚氨酯发泡装置及其用途和使用方法 |
CN103031786B (zh) * | 2011-09-29 | 2016-02-10 | 拜耳材料科技(中国)有限公司 | 装置及使用其制备道碴道床的方法 |
DE102012004720A1 (de) * | 2012-03-07 | 2013-09-12 | Frank Petrick | Verfahren und Vorrichtung zum Verfestigen von lockeren Bodenmaterialien |
DE102012009284B4 (de) * | 2012-05-11 | 2015-01-22 | Goldschmidt Thermit Railservice Gmbh | Verfahren zur Sanierung einer festen Fahrbahn / Verfestigte Schotterbahn |
JP6251541B2 (ja) * | 2013-10-28 | 2017-12-20 | 東日本旅客鉄道株式会社 | 路盤構築方法 |
CN104018403B (zh) * | 2014-06-24 | 2016-06-15 | 西南交通大学 | 一种重载铁路路基基床的建造方法 |
RU2583112C2 (ru) * | 2014-07-09 | 2016-05-10 | Олег Александрович Мичурин | Способ укрепления балластной призмы железнодорожного пути |
CN107034748B (zh) * | 2017-05-12 | 2019-03-29 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种用于聚氨酯固化道床灌注的压力注浆方法 |
RU2666501C1 (ru) * | 2017-09-15 | 2018-09-07 | Акционерное общество "ОргСинтезРесурс" | Способ укрепления балластной призмы |
CN111451222B (zh) * | 2020-03-18 | 2024-08-23 | 成都东日瑞姆机械有限公司 | 添加粉末组分多流道浇注的聚氨酯发泡设备 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0424552A1 (de) * | 1988-06-29 | 1991-05-02 | Karl Reinhard Zeiss | Verfahren zur Verfestigung von Schotterbetten und anderen Haufwerkgebilden |
DE10241293A1 (de) * | 2002-09-04 | 2004-03-18 | Basf Ag | Verfahren zur Befestigung von Ufern |
EP1619305A2 (de) * | 2004-07-23 | 2006-01-25 | Frenzel-Bau GmbH | Teilverschäumter Gleisoberbau |
WO2007090901A2 (de) * | 2006-02-10 | 2007-08-16 | Msb-Management Gmbh | Verfahren zur herstellung eines teilverschäumten gleisoberbaus |
Family Cites Families (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD86201A (de) | ||||
DE2063727A1 (de) | 1970-12-24 | 1972-08-24 | Michelfelder, Gerhard, 8000 München | Verfahren zur Stabilisierung eines Schotterbettes |
DE2305536A1 (de) | 1973-02-05 | 1974-08-08 | Sieke Helmut | Verfahren zum heben von gleisen und von strassenbelagsstuecken, vorrichtung zum durchfuehren dieses verfahrens und gleisschwelle |
DE7319950U (de) | 1973-05-26 | 1973-09-06 | Basf Ag | Vorrichtung zum verfestigen von schotterbetten |
AT337748B (de) | 1974-01-17 | 1977-07-11 | Plasser Bahnbaumasch Franz | Vorrichtung und verfahren zum verkleben des schotters einer gleisbettung |
JP3340795B2 (ja) * | 1993-05-11 | 2002-11-05 | 三洋化成工業株式会社 | バラスト固結法および固結材 |
JP3473998B2 (ja) * | 1994-09-08 | 2003-12-08 | 財団法人鉄道総合技術研究所 | 線路地盤の改良工法 |
JPH08245741A (ja) * | 1995-03-09 | 1996-09-24 | Mitsui Toatsu Chem Inc | インテグラルスキン付ポリウレタンフォームの製造法 |
JP3876345B2 (ja) * | 1997-01-24 | 2007-01-31 | 財団法人鉄道総合技術研究所 | 道床バラストの安定化工法及びその軌道構造 |
JPH10266105A (ja) * | 1997-03-27 | 1998-10-06 | Railway Technical Res Inst | 道床バラストの安定化装置 |
FR2770235A1 (fr) * | 1997-10-23 | 1999-04-30 | Et L Entretien Des Routes Sa P | Structure stabilisee, notamment de type ballast, et procede de stabilisation d'une telle structure |
JP2002242103A (ja) * | 2001-02-14 | 2002-08-28 | Railway Technical Res Inst | まくらぎ下の隙間充填工法 |
CN1399035A (zh) * | 2002-09-10 | 2003-02-26 | 董小岩 | 关于铁路路基道碴固化处理的方法及其用途 |
CN2721877Y (zh) * | 2004-06-29 | 2005-08-31 | 杨海 | 矿用移动式固化泡沫充填装置 |
DE102006003033A1 (de) * | 2006-01-20 | 2007-08-02 | Bayer Materialscience Ag | Schotterkörper sowie Verfahren zur Herstellung von Schotterkörpern |
-
2007
- 2007-04-24 DE DE102007019669A patent/DE102007019669A1/de not_active Withdrawn
-
2008
- 2008-04-12 US US12/597,253 patent/US20100140367A1/en not_active Abandoned
- 2008-04-12 EP EP08748898.7A patent/EP2150652B1/de active Active
- 2008-04-12 PL PL08748898T patent/PL2150652T3/pl unknown
- 2008-04-12 CN CN2008800130008A patent/CN101663437B/zh active Active
- 2008-04-12 AU AU2008241025A patent/AU2008241025B2/en active Active
- 2008-04-12 KR KR1020097022211A patent/KR101468245B1/ko active IP Right Grant
- 2008-04-12 CA CA002684082A patent/CA2684082A1/en not_active Abandoned
- 2008-04-12 MX MX2009011240A patent/MX2009011240A/es active IP Right Grant
- 2008-04-12 ES ES08748898.7T patent/ES2546207T3/es active Active
- 2008-04-12 RU RU2009143327/11A patent/RU2448211C2/ru active
- 2008-04-12 JP JP2010504496A patent/JP4960499B2/ja active Active
- 2008-04-12 BR BRPI0810398-4A patent/BRPI0810398B1/pt active IP Right Grant
- 2008-04-12 WO PCT/EP2008/002910 patent/WO2008128665A1/de active Application Filing
- 2008-04-12 UA UAA200911922A patent/UA94815C2/ru unknown
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0424552A1 (de) * | 1988-06-29 | 1991-05-02 | Karl Reinhard Zeiss | Verfahren zur Verfestigung von Schotterbetten und anderen Haufwerkgebilden |
DE10241293A1 (de) * | 2002-09-04 | 2004-03-18 | Basf Ag | Verfahren zur Befestigung von Ufern |
EP1619305A2 (de) * | 2004-07-23 | 2006-01-25 | Frenzel-Bau GmbH | Teilverschäumter Gleisoberbau |
WO2007090901A2 (de) * | 2006-02-10 | 2007-08-16 | Msb-Management Gmbh | Verfahren zur herstellung eines teilverschäumten gleisoberbaus |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2011134967A1 (de) | 2010-04-30 | 2011-11-03 | Bayer Materialscience Ag | Konditioniervorrichtung und verfahren zum trocknen und temperieren eines schotterbetts |
DE102010016733B4 (de) * | 2010-04-30 | 2012-09-20 | Bayer Materialscience Aktiengesellschaft | Konditioniervorrichtung und Verfahren zum Trocknen und Temperieren eines Schotterbetts |
DE102010016733A1 (de) | 2010-04-30 | 2011-11-03 | Bayer Materialscience Ag | Konditioniervorrichtung und Verfahren zum Trocknen und Temperieren eines Schotterbetts |
US8938887B2 (en) | 2010-04-30 | 2015-01-27 | Bayer Intellectual Property Gmbh | Conditioning device and method for drying and controlling the temperature of a ballast bed |
CN103764912A (zh) * | 2011-09-01 | 2014-04-30 | 拜耳知识产权有限责任公司 | 道碴的制造方法 |
WO2013030149A1 (de) | 2011-09-01 | 2013-03-07 | Bayer Intellectual Property Gmbh | Verfahren zur herstellung von schotterkörpern |
US9562332B2 (en) | 2011-09-01 | 2017-02-07 | Covestro Deutschland Ag | Method for producing ballast bodies |
AU2012301062B2 (en) * | 2011-09-01 | 2017-02-02 | Covestro Deutschland Ag | Method for producing ballast bodies |
CN103764912B (zh) * | 2011-09-01 | 2016-08-17 | 科思创德国股份有限公司 | 道碴的制造方法 |
DE102011053368A1 (de) | 2011-09-07 | 2013-03-07 | Bayer Materialscience Aktiengesellschaft | Raupenkette, Konditioniervorrichtung, Verfahren zum Temperieren eines Schotterbetts sowie Verwendung eines Schaumstoffs |
WO2013034643A3 (de) * | 2011-09-07 | 2014-02-20 | Bayer Intellectual Property Gmbh | Raupenkette, konditioniervorrichtung, verfahren zum temperieren eines schotterbetts sowie verwendung eines schaumstoffs |
WO2013034643A2 (de) | 2011-09-07 | 2013-03-14 | Bayer Intellectual Property Gmbh | Raupenkette, konditioniervorrichtung, verfahren zum temperieren eines schotterbetts sowie verwendung eines schaumstoffs |
WO2013057068A3 (en) * | 2011-10-19 | 2013-08-29 | Bayer Intellectual Property Gmbh | Mixing head-moving apparatus for a pouring machine for a ballast bed |
WO2013064546A1 (en) * | 2011-11-03 | 2013-05-10 | Bayer Intellectual Property Gmbh | Pouring and foaming vehicle |
EP2730699A1 (de) * | 2012-11-09 | 2014-05-14 | Bayer MaterialScience AG | Verfahren zum Verschäumen eines Schotterbetts einer Eisenbahngleisanlage |
WO2014072460A1 (de) * | 2012-11-09 | 2014-05-15 | Bayer Materialscience Ag | Verfahren zum verschäumen eines schotterbetts einer eisenbahngleisanlage |
US9822491B2 (en) | 2012-11-09 | 2017-11-21 | Covestro Deutschland Ag | Method for covering a ballast bed with foam in a railway track system |
Also Published As
Publication number | Publication date |
---|---|
EP2150652A1 (de) | 2010-02-10 |
UA94815C2 (ru) | 2011-06-10 |
KR20100015852A (ko) | 2010-02-12 |
DE102007019669A1 (de) | 2008-11-06 |
EP2150652B1 (de) | 2015-06-10 |
JP4960499B2 (ja) | 2012-06-27 |
MX2009011240A (es) | 2009-11-23 |
BRPI0810398A2 (pt) | 2014-11-04 |
CN101663437B (zh) | 2012-12-12 |
AU2008241025A1 (en) | 2008-10-30 |
KR101468245B1 (ko) | 2014-12-03 |
US20100140367A1 (en) | 2010-06-10 |
JP2010525198A (ja) | 2010-07-22 |
AU2008241025B2 (en) | 2013-06-20 |
PL2150652T3 (pl) | 2015-11-30 |
ES2546207T3 (es) | 2015-09-21 |
CN101663437A (zh) | 2010-03-03 |
CA2684082A1 (en) | 2008-10-30 |
RU2448211C2 (ru) | 2012-04-20 |
BRPI0810398B1 (pt) | 2018-05-22 |
RU2009143327A (ru) | 2011-05-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2150652B1 (de) | Verfahren und vorrichtung zum ausschäumen von schotterbetten | |
EP2227598B1 (de) | Verfahren zum verfestigen eines schotterbetts und vorrichtung zur durchführung des verfahrens | |
EP1982019B1 (de) | Verfahren zur Herstellung eines teilverschäumten Schotterkörpers für einen Gleisoberbau | |
DE2142450A1 (de) | Verfahren und Vorrichtung zur Herstellung von Polymerschaum | |
EP2423384A2 (de) | Einsprüheinrichtung für eine Baumaschine zur Bodenbearbeitung, Baumaschine mit einer Einsprüheinrichtung und Verfahren zum Betrieb einer Einsprüheirichtung | |
WO2018010860A1 (de) | Einrichtung zum austragen von mehrkomponentenklebstoffen auf ein körniges gemenge, sowie verfahren zum austragen und verwendung der einrichtung | |
EP1939355B1 (de) | Gleisbaumaschine und Verfahren zur Gleissanierung | |
EP3095916B1 (de) | Verfahren zur bankettstabilisierung, fahrwerk zur durchführung desselben und spezial-streuwagen | |
DE1784659C3 (de) | Fahrbare Einrichtung und Verfahren zur Instandhaltung eines Eisenbahnoberbaues | |
EP0502920B1 (de) | Verfahren und vorrichtung zum auftragen von mehrkomponentenharzen und anwendungen derselben | |
EP1022386A2 (de) | Verfahren zum Einbauen eines Gleises auf Tragplatten einer festen Fahrbahn sowie Schalung und Förderungs- und Einbaueinrichtung hierfür | |
DE2512917A1 (de) | Vorrichtung und verfahren zum herstellen von gipsplatten | |
EP2917410B1 (de) | Verfahren zum verschäumen eines schotterbetts einer eisenbahngleisanlage | |
DE3151030A1 (de) | Fahrbare anlage zur herstellung einer zwischen planum und schotterbett eines gleises verlaufenden schutzschichte | |
CH595512A5 (en) | Consolidation and vibration suppression of railway track upper layer | |
AT512274B1 (de) | Vorrichtungen und verfahren zur kontinuierlichen sanierung eines gleisbetts und seines unterbaus | |
DE19632638A1 (de) | Vorrichtung und Verfahren zur Stabilisierung bzw. Verfestigung von Schotterbetten und anderen Haufwerksgebilden und deren Anwendung | |
DE918252C (de) | Verfahren und Vorrichtung zum Herstellen von Schaumschlacke oder schaumartigen Schmelzfluessen | |
DE20313800U1 (de) | Schutzschicht für den Bettungskörper eines Gleisfahrweges | |
CH498980A (de) | Randstreifenfertiger zum Herstellen von Randstreifen aus Beton | |
DE4207081A1 (de) | Verfahren zur verfestigung von schlammablagerungen und einrichtung zur durchfuehrung des verfahrens | |
DE2362804A1 (de) | Billard-tisch | |
DE2354378A1 (de) | Verfahren und vorrichtung zur herstellung von kaschierten laminaten mit kunstharz-schaumstoffkern |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WWE | Wipo information: entry into national phase |
Ref document number: 200880013000.8 Country of ref document: CN |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 08748898 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 6426/DELNP/2009 Country of ref document: IN |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2684082 Country of ref document: CA |
|
WWE | Wipo information: entry into national phase |
Ref document number: MX/A/2009/011240 Country of ref document: MX Ref document number: 2008748898 Country of ref document: EP |
|
ENP | Entry into the national phase |
Ref document number: 20097022211 Country of ref document: KR Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2008241025 Country of ref document: AU Ref document number: 2010504496 Country of ref document: JP |
|
ENP | Entry into the national phase |
Ref document number: 2008241025 Country of ref document: AU Date of ref document: 20080412 Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2009143327 Country of ref document: RU |
|
WWE | Wipo information: entry into national phase |
Ref document number: 12597253 Country of ref document: US |
|
ENP | Entry into the national phase |
Ref document number: PI0810398 Country of ref document: BR Kind code of ref document: A2 Effective date: 20091020 |