WO2006111589A1 - Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo - Google Patents
Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo Download PDFInfo
- Publication number
- WO2006111589A1 WO2006111589A1 PCT/ES2005/070044 ES2005070044W WO2006111589A1 WO 2006111589 A1 WO2006111589 A1 WO 2006111589A1 ES 2005070044 W ES2005070044 W ES 2005070044W WO 2006111589 A1 WO2006111589 A1 WO 2006111589A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- rails
- rail
- fixing
- leveling
- bolts
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B9/00—Fastening rails on sleepers, or the like
- E01B9/66—Rail fastenings allowing the adjustment of the position of the rails, so far as not included in the preceding groups
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/06—Height or lateral adjustment means or positioning means for slabs, sleepers or rails
Definitions
- the object of the present invention is a railroad system in concrete plating as well as its installation system, which thanks to the elements that constitute the rail system allow at any time of the work the leveling of the rails so as their alignment at any time, ensuring the parallelism between lanes.
- Concrete track tracks are known, they are mainly used for rail access to workshops, ports, hangars, garages and so on, where trains with high loads and slow speeds normally run.
- this system does not allow a leveling in height during the work, with the consequent reduction of the traditional gauge, which in some cases is a clear inconvenience. Nor does it allow alignment between the rails or modification of the track width at any time during the work, as well as subsequent technical revisions without the need to lift the track.
- the system of railroad tracks in a concrete plate object of the invention consists in firstly arranging a support bed or support base thereon, on this bed or base a support structure of the rails is arranged, which replace the Traditional naughty
- the support structure of the rails consists of a rectangular steel plate or sheet that is arranged under the rails, serving as a support for the pampering, leaving the assembly formed by the sheet and the rails supported by adjustable bolts arranged on both sides of the rail, and not preferably facing each other.
- adjustable parts for fixing the rails that are arranged on the steel plates are used. These regulating pieces allow the alignment of the rails, and ensure the parallelism between them, in addition to absorbing the lateral forces of the system.
- the assembly process of the track system object of the invention comprises the following steps: - Laying of a base or bed where the entire track system will be supported.
- This railroad system allows, as previously mentioned, a leveling of the rails' height during the work, by means of the nut under the sheet, a regulation of the alignment of each of the rails and the parallelism of the rails at any moment of the work before the final embedding of concrete, thanks to the use of the adjustable clips for fixing the rails to the steel plates.
- the adjustable fixing clips are made up of elements that, once given the recommended tightening torque, ensure the locking of the system, the lateral adjustment of the fixing parts, allowing to guarantee the necessary track width.
- Figure 1 shows a representation of the elements that make up the system of railroad tracks in concreted plate before proceeding to the concreting of the assembly.
- Figure 2 shows the same previous figure that has been concreted up to half of the bolts.
- FIG. 3 shows in detail the fixing of steel plates with rails, bolts and adjustable fixing elements.
- Figure 4 shows in detail the constructive form of how an additional rail is arranged.
- Figure 1 shows that the track system is arranged on a bed (10), according to the specifications of the designer, which serves as support for the whole system that is composed of a series of steel plates (2), arranged between the rails (1).
- a bed (10) which serves as support for the whole system that is composed of a series of steel plates (2), arranged between the rails (1).
- anchoring and leveling bolts (3) that allow height leveling. Said bolts (3) serve as support for the steel plates (2), and on these the rails (1) are fixed.
- adjustable fixing clips (4) are used, which allow the regulation of the alignment of each of the rails, as well as the parallelism between the rails, throughout the assembly process of the tracks.
- the adjustable fixing clips (4) are fixed to the wings (5) of the rails (1).
- FIG 3 the connection between the different parts that make up the system is shown in more detail, where it is noteworthy how the bolts (3) are placed on both sides of the rail, and preferably in a non-facing manner.
- the fixing and alignment clips (4) are also arranged on both sides of the rail (1), on its wings (5), and not facing each other.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP05735163A EP1873308A1 (de) | 2005-04-19 | 2005-04-19 | Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür |
PCT/ES2005/070044 WO2006111589A1 (es) | 2005-04-19 | 2005-04-19 | Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/ES2005/070044 WO2006111589A1 (es) | 2005-04-19 | 2005-04-19 | Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2006111589A1 true WO2006111589A1 (es) | 2006-10-26 |
Family
ID=35276421
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/ES2005/070044 WO2006111589A1 (es) | 2005-04-19 | 2005-04-19 | Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP1873308A1 (de) |
WO (1) | WO2006111589A1 (de) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102009060812A1 (de) * | 2009-12-28 | 2011-06-30 | DB Bahnbau Gruppe GmbH, 10179 | System zum Richten eines Gleises einer festen Schienenfahrbahn |
WO2019047305A1 (zh) * | 2017-09-07 | 2019-03-14 | 朱秀青 | 一种轨道施工的压杠接长装置 |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101538818B (zh) * | 2009-04-29 | 2011-07-06 | 成都普罗米新科技有限责任公司 | 钢轨精调装置 |
ES2363849B1 (es) * | 2009-06-16 | 2012-06-19 | Fcc Contrucción, S.A. | Procedimiento de instalación de vía en placa en túneles bitubo. |
DE102010020801B4 (de) | 2010-05-18 | 2013-03-14 | Wirthwein Ag | Schienenbefestigung |
DE102011108093B4 (de) * | 2011-07-19 | 2020-03-05 | Siemag Tecberg Gmbh | Fertigteilfahrbahn für Schrägförderanlage für Bergbautrucks |
WO2013030723A1 (de) * | 2011-08-26 | 2013-03-07 | Rte Technologie Gmbh | Heberichtsystem |
CN102995503B (zh) * | 2012-12-12 | 2016-01-20 | 中铁二十三局集团有限公司 | 一种无砟轨道先张预应力结构道岔板 |
CN105133447B (zh) * | 2015-10-07 | 2016-07-13 | 李红卫 | 一种液压轨距调整器 |
FR3062139B1 (fr) * | 2017-01-20 | 2019-04-05 | Alstom Transport Technologies | Voie de chemin de fer pour vehicule ferroviaire urbain et methode de fabrication d'une telle voie de chemin de fer |
AT16434U1 (de) * | 2018-05-02 | 2019-09-15 | Edilon Sedra Gmbh | Einrichtung zur verlegung von gleisen |
DE202019102034U1 (de) | 2019-04-09 | 2020-07-10 | Alois Schranz Metall & Maschinenbau | Ausrichtvorrichtung zum Ausrichten von Schienen im Gleisbau |
CN111809460B (zh) * | 2020-07-28 | 2021-11-26 | 河北冀科工程项目管理有限公司 | 一种快速高精度高铁墙式检查坑铺轨施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE554240C (de) * | 1929-05-23 | 1932-07-06 | William Patrick Day | Verfahren zur Herstellung von Schienenbettungen aus Beton |
US5285964A (en) * | 1992-05-22 | 1994-02-15 | Etablissements Vape | Method for constructing a railroad in concrete having vertical and lateral adjustment steps prior to concrete pouring |
DE10107116A1 (de) * | 2001-02-14 | 2002-10-24 | Schreck Mieves Gmbh | Ausrichteinrichtung und Verfahren zum Ausrichten und Einstellen der Soll-Einbaulage eines vormontierten Gleisrostes in ein schotterloses Oberbausystem in Trogbauweise |
DE10316143A1 (de) * | 2003-01-21 | 2004-08-05 | Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg | Spindelvorrichtung zur Höhenverstellung von Gleisrosten |
-
2005
- 2005-04-19 WO PCT/ES2005/070044 patent/WO2006111589A1/es not_active Application Discontinuation
- 2005-04-19 EP EP05735163A patent/EP1873308A1/de not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE554240C (de) * | 1929-05-23 | 1932-07-06 | William Patrick Day | Verfahren zur Herstellung von Schienenbettungen aus Beton |
US5285964A (en) * | 1992-05-22 | 1994-02-15 | Etablissements Vape | Method for constructing a railroad in concrete having vertical and lateral adjustment steps prior to concrete pouring |
DE10107116A1 (de) * | 2001-02-14 | 2002-10-24 | Schreck Mieves Gmbh | Ausrichteinrichtung und Verfahren zum Ausrichten und Einstellen der Soll-Einbaulage eines vormontierten Gleisrostes in ein schotterloses Oberbausystem in Trogbauweise |
DE10316143A1 (de) * | 2003-01-21 | 2004-08-05 | Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg | Spindelvorrichtung zur Höhenverstellung von Gleisrosten |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102009060812A1 (de) * | 2009-12-28 | 2011-06-30 | DB Bahnbau Gruppe GmbH, 10179 | System zum Richten eines Gleises einer festen Schienenfahrbahn |
DE102009060812B4 (de) * | 2009-12-28 | 2012-05-16 | Db Bahnbau Gruppe Gmbh | System zum Richten eines Gleises einer festen Schienenfahrbahn |
WO2019047305A1 (zh) * | 2017-09-07 | 2019-03-14 | 朱秀青 | 一种轨道施工的压杠接长装置 |
Also Published As
Publication number | Publication date |
---|---|
EP1873308A1 (de) | 2008-01-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2006111589A1 (es) | Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo | |
AU2011351482B2 (en) | Method for producing a slab trackway | |
ES2649963T3 (es) | Procedimiento para convertir una vía sobre balasto en una vía sólida | |
KR101040102B1 (ko) | 자기부상열차용 궤도레일의 설치방법 | |
US20180148896A1 (en) | Support for a panel of a section of guided transport track | |
CA3022814C (en) | Device for setting up a level crossing | |
ES2387965A1 (es) | Traviesa provisional recuperable. | |
KR20160061551A (ko) | 탄성체 전용 트램 궤광조립대 | |
US3317137A (en) | Railroad crossing rail bed unit | |
ES2936222T3 (es) | Sección de vía sin balasto para vehículo ferroviario | |
HUE029941T2 (hu) | Rögzített pálya sínjármûvek részére átvezetéssel | |
ES2213243T3 (es) | Procedimiento y dispositivo para transportar un tramo de via. | |
ES2258804T3 (es) | Procedimiento para la construccion de una bancada de via fija para trafico guiado sobre railes, asi como una bancada de via fija para llevar a cabo el procedimiento. | |
ES2945957T3 (es) | Estructura sustentadora modular | |
US5465903A (en) | Mounting plate for fixing elastomeric grade crossing panels to ties | |
RU2676772C1 (ru) | Железнодорожный переезд | |
EP4182504A1 (de) | Plattenspuranpassungsplatte und installationsverfahren | |
ES2574538B1 (es) | Sistema para cambio a tres carriles en vias en placa de taco polivalente o monovalente de dos carriles y procedimiento para dicho sistema | |
ES2222114T3 (es) | Dispositivo de vias ferreas de aprovisionamiento de estanterias especialmente para el almacenamiento de productos pesados y su procedimiento de montaje. | |
KR20170075480A (ko) | 철도용 레일 지지장치 | |
CN216008055U (zh) | 一种城市轨道交通建设工程用防护栏 | |
BR112020014241B1 (pt) | Estrutura de suporte modular | |
ES2704178A1 (es) | Zócalo de hormigón para vías ferroviarias, vía ferroviaria que incorpora dichos zócalos y método de instalación de la vía | |
ES1299486U (es) | Dispositivo para transformar una vía de balasto en una vía en placa. | |
ES2313813B1 (es) | Sistema de rail de rodadura. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
WWE | Wipo information: entry into national phase |
Ref document number: 2005735163 Country of ref document: EP |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
NENP | Non-entry into the national phase |
Ref country code: RU |
|
WWW | Wipo information: withdrawn in national office |
Country of ref document: RU |
|
WWP | Wipo information: published in national office |
Ref document number: 2005735163 Country of ref document: EP |