EP1873308A1 - Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür - Google Patents

Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür Download PDF

Info

Publication number
EP1873308A1
EP1873308A1 EP05735163A EP05735163A EP1873308A1 EP 1873308 A1 EP1873308 A1 EP 1873308A1 EP 05735163 A EP05735163 A EP 05735163A EP 05735163 A EP05735163 A EP 05735163A EP 1873308 A1 EP1873308 A1 EP 1873308A1
Authority
EP
European Patent Office
Prior art keywords
rails
rail
track system
bolts
railroad track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP05735163A
Other languages
English (en)
French (fr)
Inventor
Juan Francisco Meaza Gabay
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gantry Espanola SA
Original Assignee
Gantry Espanola SA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gantry Espanola SA filed Critical Gantry Espanola SA
Publication of EP1873308A1 publication Critical patent/EP1873308A1/de
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B9/00Fastening rails on sleepers, or the like
    • E01B9/66Rail fastenings allowing the adjustment of the position of the rails, so far as not included in the preceding groups
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails

Definitions

  • the present invention relates to a railroad track system on concreted slabs, as well as to its installation procedure, which due to the elements constituting the track system allow at any time of the work to adjust the height of the tracks and to align them at any time, thereby ensuring that the rails are parallel.
  • the present invention is characterised by the elements used in the track system, whose constructive and technical characteristics are such that they allow adjusting the height, aligning each track and the parallel arrangement of the rails.
  • the present invention lies in the field of track systems covered by concrete except in the heads of the rails.
  • Tracks on concreted slabs are well known and used mainly for railway access to shops, ports, hangars, sheds etc. where trains with great loads at slow speeds travel.
  • the object of the present invention of a railroad track system on concreted slabs is to obtain a system that overcomes the above drawbacks, allowing to adjust the height, align each rail and ensure that they are parallel at any time during the work, by using an adjustable attachment piece, allowing to install a third rail while being maintenance free.
  • the railroad track system on concreted slabs of the invention consists of first providing a supporting bed or base on which they rest, and above it a structure to support the rails instead of the conventional sleepers.
  • the rail support structure consists of a rectangular steel plate placed under the rails in order to support them, so that the assembly formed by the plate and the rails is supported by adjustable bolts placed on either side of the rail, preferably not opposite each other.
  • the rails are attached by adjusting parts placed above the steel plates. Said adjusting parts allow aligning the rails to ensure that they are parallel, as well as absorbing the lateral loads of the system.
  • the assembly procedure for the track system object of the invention comprises the following steps:
  • This railroad track system allows, as mentioned before, to adjust the height of the rails during the work by turning the nut placed under the plate, and to adjust the alignment of each rail and the parallel arrangement of rails at any time of the work before they are embedded in the concrete by adjustable attachment clips used to attach the rails to the steel plates.
  • the adjustable attachment clips are comprised of elements which, after the recommended tightening torque is reached, will ensure that the system is locked while allowing to adjust the lateral position of the adjustment parts, thereby providing the any required rail gauge.
  • Figure 1 shows a representation of the elements composing the railroad track system on concreted slab before the assembly is concreted.
  • Figure 2 shows the previous figure after concreting to half the height of the bolts.
  • Figure 3 shows a detailed view of the attachment of the steel plates to the rails, the bolts and the adjustable attachment elements.
  • Figure 4 shows a detailed view of the construction of the disposition of an additional rail.
  • Figure 1 shows that the track system lies on a bed (10), according to the designer's specifications, which supports the entire system composed of a number of steel plates (2) set between the rails (1).
  • a bed (10) which supports the entire system composed of a number of steel plates (2) set between the rails (1).
  • anchoring and levelling bolts (3) that allow a height adjustment.
  • Said bolts (3) support the steel plates (2), on which the rails (1) are attached.
  • adjustable attachment clips (4) are employed to allow regulating the alignment of each rail as well as the parallel arrangement of the rails during the entire assembly process of the tracks.
  • the adjustable attachment clips (4) are attached to the wings (5) of the rails (1).
  • Figure 2 shows the next stage of the system assembly in which concrete (6) or another material is added to the mid height of the bolts (3), at which point the height is adjusted, the rails are levelled and the rails are made parallel.
  • Figure 3 shows in greater detail the union of the various component parts of the system, showing how the bolts (3) are set on either side of the rail, preferably not opposite each other.
  • the attachment and alignment clips (4) are also placed on both sides of the rail (1), on its wings (5), not opposite each other.
  • Figure 4 shows how the system allows placing an additional rail (7) in order to allow adjusting the rail gauge.
  • one or more bolts (8) and corresponding auxiliary attachment and adjustment clips (9) are provided, so that the bolts (3) and the attachment and alignment clips (4) remain on the sides of the assembly formed by the two rails.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
EP05735163A 2005-04-19 2005-04-19 Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür Withdrawn EP1873308A1 (de)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/ES2005/070044 WO2006111589A1 (es) 2005-04-19 2005-04-19 Sistema de vías de ferrocarril en placa hormigonada y procedimiento de instalación del mismo

Publications (1)

Publication Number Publication Date
EP1873308A1 true EP1873308A1 (de) 2008-01-02

Family

ID=35276421

Family Applications (1)

Application Number Title Priority Date Filing Date
EP05735163A Withdrawn EP1873308A1 (de) 2005-04-19 2005-04-19 Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür

Country Status (2)

Country Link
EP (1) EP1873308A1 (de)
WO (1) WO2006111589A1 (de)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101538818B (zh) * 2009-04-29 2011-07-06 成都普罗米新科技有限责任公司 钢轨精调装置
ES2363849A1 (es) * 2009-06-16 2011-08-17 Fcc Contrucción, S.A. Procedimiento de instalación de vía en placa en túneles bitubo.
EP2388374A2 (de) 2010-05-18 2011-11-23 Wirthwein AG Schienenbefestigung
WO2013030723A1 (de) * 2011-08-26 2013-03-07 Rte Technologie Gmbh Heberichtsystem
CN102995503A (zh) * 2012-12-12 2013-03-27 中铁二十三局集团有限公司 一种无砟轨道先张预应力结构道岔板
WO2013011083A3 (de) * 2011-07-19 2013-05-30 Siemag Tecberg Gmbh Fertigteilfahrbahn für schrägförderanlage für bergbautrucks
CN105133447B (zh) * 2015-10-07 2016-07-13 李红卫 一种液压轨距调整器
FR3062139A1 (fr) * 2017-01-20 2018-07-27 Alstom Transport Technologies Voie de chemin de fer pour vehicule ferroviaire urbain et methode de fabrication d'une telle voie de chemin de fer
AT16434U1 (de) * 2018-05-02 2019-09-15 Edilon Sedra Gmbh Einrichtung zur verlegung von gleisen
CN111809460A (zh) * 2020-07-28 2020-10-23 河北冀科工程项目管理有限公司 一种快速高精度高铁墙式检查坑铺轨施工方法
EP3722503B1 (de) 2019-04-09 2022-01-12 Schranz Bahntechnik GmbH Ausrichtvorrichtung zum ausrichten von schienen im gleisbau

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102009060812B4 (de) * 2009-12-28 2012-05-16 Db Bahnbau Gruppe Gmbh System zum Richten eines Gleises einer festen Schienenfahrbahn
CN207121763U (zh) * 2017-09-07 2018-03-20 中铁五局集团第二工程有限责任公司 一种轨道板自密实混凝土压杠接长装置

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE554240C (de) * 1929-05-23 1932-07-06 William Patrick Day Verfahren zur Herstellung von Schienenbettungen aus Beton
FR2691484B1 (fr) * 1992-05-22 1994-07-29 Vanotti Gerard Procede de construction d'une voie ferree dans du beton.
DE10107116A1 (de) * 2001-02-14 2002-10-24 Schreck Mieves Gmbh Ausrichteinrichtung und Verfahren zum Ausrichten und Einstellen der Soll-Einbaulage eines vormontierten Gleisrostes in ein schotterloses Oberbausystem in Trogbauweise
DE10316143B4 (de) * 2003-01-21 2005-08-04 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg Spindelvorrichtung zur Höhenverstellung von Gleisrosten

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2006111589A1 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101538818B (zh) * 2009-04-29 2011-07-06 成都普罗米新科技有限责任公司 钢轨精调装置
ES2363849A1 (es) * 2009-06-16 2011-08-17 Fcc Contrucción, S.A. Procedimiento de instalación de vía en placa en túneles bitubo.
EP2388374A2 (de) 2010-05-18 2011-11-23 Wirthwein AG Schienenbefestigung
DE102010020801A1 (de) 2010-05-18 2011-11-24 Wirthwein Ag Schienenbefestigung
DE102010020801B4 (de) * 2010-05-18 2013-03-14 Wirthwein Ag Schienenbefestigung
CN103842616B (zh) * 2011-07-19 2016-06-08 西马格特宝有限责任公司 用于露天采矿中的倾斜运输系统的成品部件轨道及其制造方法
EA026169B1 (ru) * 2011-07-19 2017-03-31 Сиемаг Текберг Гмбх Способ создания заключительного участка пути наклонной системы транспортировки карьерных самосвалов и заключительная часть пути наклонной системы транспортировки карьерных самосвалов
WO2013011083A3 (de) * 2011-07-19 2013-05-30 Siemag Tecberg Gmbh Fertigteilfahrbahn für schrägförderanlage für bergbautrucks
CN103842616A (zh) * 2011-07-19 2014-06-04 西马格特宝有限责任公司 矿用卡车的倾斜运输系统的成品部件轨道
AU2012285793B2 (en) * 2011-07-19 2015-09-17 Siemag Tecberg Gmbh Finished-part track for an inclined conveyor system for mining trucks
WO2013030723A1 (de) * 2011-08-26 2013-03-07 Rte Technologie Gmbh Heberichtsystem
CN102995503B (zh) * 2012-12-12 2016-01-20 中铁二十三局集团有限公司 一种无砟轨道先张预应力结构道岔板
CN102995503A (zh) * 2012-12-12 2013-03-27 中铁二十三局集团有限公司 一种无砟轨道先张预应力结构道岔板
CN105133447B (zh) * 2015-10-07 2016-07-13 李红卫 一种液压轨距调整器
FR3062139A1 (fr) * 2017-01-20 2018-07-27 Alstom Transport Technologies Voie de chemin de fer pour vehicule ferroviaire urbain et methode de fabrication d'une telle voie de chemin de fer
AT16434U1 (de) * 2018-05-02 2019-09-15 Edilon Sedra Gmbh Einrichtung zur verlegung von gleisen
EP3722503B1 (de) 2019-04-09 2022-01-12 Schranz Bahntechnik GmbH Ausrichtvorrichtung zum ausrichten von schienen im gleisbau
CN111809460A (zh) * 2020-07-28 2020-10-23 河北冀科工程项目管理有限公司 一种快速高精度高铁墙式检查坑铺轨施工方法
CN111809460B (zh) * 2020-07-28 2021-11-26 河北冀科工程项目管理有限公司 一种快速高精度高铁墙式检查坑铺轨施工方法

Also Published As

Publication number Publication date
WO2006111589A1 (es) 2006-10-26

Similar Documents

Publication Publication Date Title
EP1873308A1 (de) Eisenbahnschienensystem auf betonplatten und installationsverfahren dafür
KR101234092B1 (ko) 피씨 슬래브와 강거더를 포함하는 피씨 합성판형교 및 그 시공방법
US7730840B2 (en) Girder of a guideway for a track-bound vehicle
CN106758590B (zh) 用于不停运条件下更换铁路轨道的施工便梁及施工方法
KR20080030662A (ko) 교량 구조물의 고정 주행 트랙
CN110117923A (zh) 一种单轨车轨道安装节点及安装节点的施工方法
CN206289476U (zh) 用于不停运条件下更换铁路轨道的施工便梁
US3430857A (en) Ballastless railway track structure
DE19602694A1 (de) Verfahren zur Herstellung eines schotterlosen Oberbaus
KR101259172B1 (ko) 소형궤도차량의 교량 구조 및 교량 시공 방법
CN211734876U (zh) 一种可调节分开式中低速磁浮扣件系统
US20220162806A1 (en) Ballastless track section for a rail vehicle
KR100389562B1 (ko) 철도 분기 구간에 사용되는 레일 가조립장치 및 그 방법
KR20170075480A (ko) 철도용 레일 지지장치
EP0814197B1 (de) Lagestabiles Gleis aus Betonfertigteilen
JP3087093B2 (ja) 鉄道高架橋の縦粱の構造
JP2589046Y2 (ja) 軌框支承装置
JP2019090191A (ja) 鉄道施設の高さ調整装置及び方法
KR200239985Y1 (ko) 철도 분기 구간에 사용되는 레일 가조립장치
CN113605159A (zh) 一种双向轨道高程调节装置
AU2005205748A1 (en) Method of installing a railway sleeper
AU2022278414A1 (en) Assembly comprising at least one rail and a support
WO2020249981A1 (en) An improved rail clamp
AT409392B (de) Verfahren zur herstellung eines schotterlosen oberbaus
KR200245933Y1 (ko) 철도 분기 구간에 사용되는 레일 가조립장치

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20070313

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU MC NL PL PT RO SE SI SK TR

DAX Request for extension of the european patent (deleted)
17Q First examination report despatched

Effective date: 20080729

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20120817