NO341102B1 - Construction of buildings and underground facilities - Google Patents

Construction of buildings and underground facilities Download PDF

Info

Publication number
NO341102B1
NO341102B1 NO20076650A NO20076650A NO341102B1 NO 341102 B1 NO341102 B1 NO 341102B1 NO 20076650 A NO20076650 A NO 20076650A NO 20076650 A NO20076650 A NO 20076650A NO 341102 B1 NO341102 B1 NO 341102B1
Authority
NO
Norway
Prior art keywords
foil
shotcrete
construction according
distance
rock
Prior art date
Application number
NO20076650A
Other languages
Norwegian (no)
Other versions
NO20076650L (en
Inventor
Carsten Kofoed
Svein Jonsson
Original Assignee
Skumtech As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from DE200510048118 external-priority patent/DE102005048118A1/en
Priority claimed from DE102005057959A external-priority patent/DE102005057959A1/en
Application filed by Skumtech As filed Critical Skumtech As
Publication of NO20076650L publication Critical patent/NO20076650L/en
Publication of NO341102B1 publication Critical patent/NO341102B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall

Abstract

Construction has a seal secured at the outer side against traversing water or a anchor isolation against corrosion or a film with rough surface or a claw mat or an agent for spraying concrete with enclosed plastic foam particles. The film is held by means of sealing elements at the anchoring elements.

Description

Oppfinnelsen gjelder konstruksjoner for bygg og underjordiske anlegg, særlig konstruksjon av underjordiske rom som tunneler og stoller eller rørledninger i fast fjell. The invention relates to structures for buildings and underground facilities, in particular the construction of underground spaces such as tunnels and tunnels or pipelines in solid rock.

Fester blir særlig ofte brukt innenfor tunnelbygging. Her må det skilles mellom tunneler i fast fjell og i løst fjell. Fast fjell raser ikke sammen når tunnelmassene sprenges ut. Dersom fjellet er løst, er det derimot nødvendig med en konstruksjon med stor bæreevne, som delvis bærer vekten av fjellet. I løst fjell er det vanlig både med stål- og betongkonstruksjoner, noen ganger kombinerer man de to materialene. Betongkonstruksjonene kan som regel tilvirkes på byggeplassen. Det er også vanlig med betongpanel som produseres på fabrikk og transporteres til byggeplassen. Fasteners are particularly often used in tunnel construction. Here a distinction must be made between tunnels in solid rock and in loose rock. Solid rock does not collapse when the tunnel masses are blasted out. If the rock is loose, on the other hand, a structure with a large bearing capacity is required, which partially bears the weight of the rock. In loose rock, it is common to use both steel and concrete structures, sometimes combining the two materials. The concrete structures can usually be manufactured on the construction site. It is also common for concrete panels to be produced in a factory and transported to the construction site.

I fast fjell faller problemet med festing bort, men man må likevel sikre mot steiner som faller fra taket. Dette problemet løses vanligvis med sprøytebetong. Betong sprøytes mot fjellveggen, herdes og danner et beskyttende lag. In solid rock, the problem of fastening disappears, but you still have to secure against stones falling from the roof. This problem is usually solved with shotcrete. Concrete is sprayed against the rock wall, hardens and forms a protective layer.

Et annet problem er vann som siver ut gjennom fjellveggen. Vannet fryser om vinteren, og dermed oppstår fare for at ismasser skal falle ned. Dette problemet løses vanligvis med tetningsfolie. Alt etter tykkelsen på folien kalles denne også bane eller membran. Another problem is water seeping out through the rock wall. The water freezes in winter, and thus there is a danger that masses of ice will fall down. This problem is usually solved with sealing foil. Depending on the thickness of the foil, this is also called web or membrane.

Tetningsfolien leder vannet bort. Samtidig forhindrer en varmeisolasjon at vannet fryser. The sealing foil directs the water away. At the same time, thermal insulation prevents the water from freezing.

Tetningsfolien lages av foliebaner. Foliebanene legges overlappende på fjellveggen slik at kantene kan sveises sammen. Det brukes her fortrinnsvis dobbel sveisesøm. To sveisesømmer ligger da ved siden av hverandre, og rommet mellom dem kan fylles med luft. Når mellomrommet er lukket kan man regne med en tilstrekkelig tetningsvirkning så lenge trykkfallet ikke overskrider bestemte grenser per tidsenhet. The sealing foil is made from foil webs. The foil webs are laid overlapping on the rock wall so that the edges can be welded together. A double welding seam is preferably used here. Two welding seams are then next to each other, and the space between them can be filled with air. When the space is closed, a sufficient sealing effect can be expected as long as the pressure drop does not exceed certain limits per unit of time.

Festingen av folien skjer på ulike måter. Når det ikke er vanskelig å feste, har det vært vanlig å feste folien med et feste av kunststoff som er formet som en rondell. Rondellen nagles eller skytes rett i fjellet eller i et første lag av sprøytebetong. At rondellene skytes inn, betyr at de ikke slås inn med en hammer eller tilsvarende, men at de drives inn i fjellet eller det første betonglaget ved hjelp av en sprengpatron. The fixing of the foil takes place in different ways. When it is not difficult to attach, it has been common to attach the foil with a plastic attachment that is shaped like a ring. The roundel is nailed or shot directly into the rock or into a first layer of shotcrete. The fact that the rondels are shot in means that they are not driven in with a hammer or similar, but that they are driven into the rock or the first layer of concrete with the help of a blasting cartridge.

Tradisjonelle rondeller er vist og beskrevet for eksempel i DE-3244000C1, DE4100902A1, DE19519595A1, DE8632994.4U1, DE8701969.8U1, DE20217044U1. Disse er sammensveiset med folien. Det har vært ansett som særlig gunstig å bruke rondeller med fastlagte bruddsted. Rondellene skal da brekke der dersom folien blir belastet. Motstandskraften til bruddstedet er vesentlig lavere enn motstandskraften til folien. På denne måten brekker rondellen når folien utsettes for et for høyt trykk. Dette betyr at tetningsfolien forblir uskadd selv om trykket på folien blir for høyt, mens rondellen brekker. Traditional roundabouts are shown and described for example in DE-3244000C1, DE4100902A1, DE19519595A1, DE8632994.4U1, DE8701969.8U1, DE20217044U1. These are welded together with the foil. It has been considered particularly advantageous to use roundabouts with defined breaking points. The circular parts must then break there if the foil is subjected to stress. The resistance of the breaking point is significantly lower than the resistance of the foil. In this way, the disc breaks when the foil is exposed to too much pressure. This means that the sealing foil remains undamaged even if the pressure on the foil becomes too high, while the washer breaks.

Kunststoffrondellene er imidlertid bare velegnet når det ved festingen av folien og den påfølgende påføringen av sprøytebetong oppstår svake krefter. However, the plastic rondels are only suitable when weak forces arise during the fixing of the foil and the subsequent application of shotcrete.

Men særlig i tunneler forekommer sterke krefter. I jernbanetunneler produserer de passerende togene et ekstremt lufttrykk og deretter et ekstremt dragsug Trykkene virker på ekstremt store flater, og dermed oppstår totaltrykk som gjør det nødvendig med en tilstrekkelig fast forbindelse mellom tunnelkonstruksjonen og fjellet. Trykket er avhengig av togets fart, og høyhastighetstog skaper et mange ganger høyere trykk enn normale tog. Tilsvarende gjelder for biltunneler. But especially in tunnels strong forces occur. In railway tunnels, the passing trains produce an extreme air pressure and then an extreme suction. The pressures act on extremely large surfaces, resulting in a total pressure which makes it necessary to have a sufficiently firm connection between the tunnel structure and the rock. The pressure depends on the speed of the train, and high-speed trains create a pressure many times higher than normal trains. The same applies to car tunnels.

Ved slike belastninger er det rondeller av stål som er mest brukt. Disse holdes fast i fjellet med bolter. For such loads, steel washers are most commonly used. These are held firmly in the rock with bolts.

Tradisjonelle rondeller har en diameter på ca. 150 mm og en tykkelse på 3 til 4 mm. Slike rondeller har stor motstandskraft. Tradisjonelle bolter har en diameter på 12, 14, 16 eller 20 mm. De er som regel av rustfritt stål og er profilert på den siden som vender inn mot fjellet for å gi stor motstandskraft mot å bli dratt ut. Det lages egne borehull til boltene. Deretter festes boltene i borehullene med monteringssement eller andre egnede monteringsmidler. Slike bolter kan i motsetning til tradisjonelle naglekonstruksjoner motstå sterke krefter. Belastningen ledes inn i fjellet, og derfor er det med slike bolter mulig å bygge en tunnelkonstruksjon som tåler belastningen av tog og kjøretøy som kjører gjennom. Traditional roundabouts have a diameter of approx. 150 mm and a thickness of 3 to 4 mm. Such rondels have great resilience. Traditional bolts have a diameter of 12, 14, 16 or 20 mm. They are usually made of stainless steel and are profiled on the side facing the mountain to provide great resistance to being pulled out. Separate drill holes are made for the bolts. The bolts are then fixed in the drill holes with mounting cement or other suitable mounting materials. In contrast to traditional rivet constructions, such bolts can withstand strong forces. The load is directed into the rock, and therefore with such bolts it is possible to build a tunnel structure that can withstand the load of trains and vehicles driving through.

I den frie enden utstyres bolten som regel med en gjenge, fortrinnsvis med diametermål tilsvarende metrisk gjenge M12, M14, M16 eller M20. På denne siden holdes stålrondellene mellom to skruer. Skruene gjør det mulig å stille rondellene på bolten. The free end of the bolt is usually fitted with a thread, preferably with a diameter corresponding to metric thread M12, M14, M16 or M20. On this side, the steel washers are held between two screws. The screws make it possible to position the washers on the bolt.

Boltene er vanligvis så lange at de rager forbi rondellene ut i tunnelen. Dette gjør det mulig å feste et trådgitter som støtte ved påsprøyting av betong og som avstivning av tunnelkonstruksjonen gjennom festing i fjellet. The bolts are usually so long that they protrude past the washers into the tunnel. This makes it possible to attach a wire mesh as support when spraying concrete and as stiffening of the tunnel construction through fastening in the rock.

Ved sprøyting av betong på folie er det risiko for at folien mister betongen dvs. at betongen ikke festes på folien. Da er det formålstjenlig å sette opp et trådgitter eller lignende et stykke fra folien for å hindre at betongen faller ned. When spraying concrete on foil, there is a risk that the foil will lose the concrete, i.e. that the concrete will not stick to the foil. Then it is expedient to set up a wire mesh or similar some distance from the foil to prevent the concrete from falling down.

Trådgitteret fungerer også som armering av sprøytebetonglaget. The wire mesh also serves as reinforcement for the shotcrete layer.

Det kan også monteres et avstandsstykke for trådgitteret på bolten. Tradisjonelle avstandsstykker er stjerneformet og utstyrt med stenger for å støtte trådgitteret i så stor utstrekning som mulig. A spacer for the wire mesh can also be mounted on the bolt. Traditional spacers are star-shaped and equipped with rods to support the wire mesh as much as possible.

Ved tradisjonell konstruksjon gjennomborer boltene folien. Folien spennes så fast mellom stålrondellene, den ene rondellen på utsiden av tetningsfolien og den andre på innsiden. With traditional construction, the bolts pierce the foil. The foil is then clamped between the steel discs, one disc on the outside of the sealing foil and the other on the inside.

I praksis viser det seg at vannet fra fjellet renner langs boltene. Dette betyr at bolter og rondeller er utsatt for høy vannbelastning. EP 1950375 har tatt høyde for at vannet trenger inn via skruegjengene i rondellene og boltene og dermed også gjennom hullene som har kommet i folien. Dette fører til lekkasje, og selv en dråpevis lekkasje fører med tiden til betydelige vannmengder. Disse kan renne inn på innsiden av tunnelen og bli til istapper når vannet fryser om vinteren. Når det igjen blir mildvær, faller istappene ned og skaper stor risiko for ulykker. In practice, it turns out that the water from the mountain flows along the bolts. This means that bolts and washers are exposed to high water loads. EP 1950375 has taken into account that the water penetrates via the screw threads in the washers and bolts and thus also through the holes that have appeared in the foil. This leads to leakage, and even a drop-by-drop leak eventually leads to significant amounts of water. These can flow into the inside of the tunnel and turn into icicles when the water freezes in winter. When the weather becomes mild again, the icicles fall and create a great risk of accidents.

Dessuten kan istappene gjøre stor skade på tunnelkonstruksjonen. In addition, the icicles can cause great damage to the tunnel construction.

For å hindre vannet i å trenge inn i gjengene på rondellen, er det vanlig å sette en gummiring inn i det hullet rondellen lager. Gummiringen har imidlertid en svært begrenset effekt fordi den ikke i tilstrekkelig grad kan gripe inn i skruegangene til bolten. Det er riktignok vanlig å utstyre gummiringen med nupper på den siden som vender mot gjengene slik at den skal få bedre grep mellom skruegangene enn en glatt ring, men heller ikke dette fører til en tilstrekkelig tetning. To prevent water from penetrating the threads of the washer, it is common to insert a rubber ring into the hole made by the washer. However, the rubber ring has a very limited effect because it cannot sufficiently engage the screw threads of the bolt. It is true that it is common to equip the rubber ring with knobs on the side facing the threads so that it will have a better grip between the screw threads than a smooth ring, but this does not lead to a sufficient seal either.

Det er for øvrig også vanlig å utstyre innsiden av tunnelen med en isolering for å unngå isdannelse. It is also common to equip the inside of the tunnel with insulation to avoid ice formation.

Oppfinnelsen har satt seg som mål å forbedre tunnelkonstruksjonen gjennom en bedre folie. The invention has set itself the goal of improving tunnel construction through a better foil.

I henhold til oppfinnelsen oppnås dette gjennom særtrekkene i patentkravene. According to the invention, this is achieved through the distinctive features of the patent claims.

Som nevnt over settes folien sammen av ulike foliebaner. As mentioned above, the foil is assembled from different foil webs.

De enkelte foliebanene legges tradisjonelt i tunnelens omkrets. Antall bolter og fester avhenger da av avstanden mellom dem. Samtlige utvendige fester bør klargjøres på den måten som er beskrevet over. The individual foil tracks are traditionally laid around the perimeter of the tunnel. The number of bolts and fasteners then depends on the distance between them. All external fixings should be prepared in the manner described above.

Deretter legges den klargjorte foliebanen, og man begynner for eksempel ved sålen på den ene tunnelsiden. Folien føres oppover tunnelsiden, og så snart den berører den nevnte stiften på det utvendige festet, viser stiften seg på folien, og man kan kjenne den. Dette kan brukes til å skjære åpninger i folien på akkurat disse stedene, og dette kan skje enten mekanisk eller for hånd. Så snart man har laget hull i folien, kan folien skyves over stiften The prepared foil track is then laid, and you start, for example, at the sole on one side of the tunnel. The foil is guided up the tunnel side, and as soon as it touches the mentioned pin on the external attachment, the pin shows up on the foil and you can feel it. This can be used to cut openings in the foil at exactly these places, and this can be done either mechanically or by hand. As soon as a hole has been made in the foil, the foil can be pushed over the pin

Helst bør man feste folien til den aktuelle stiften med en gang. Dette kan gjøres ved å feste en tetning på folien og deretter skyve det innvendige festet på stiften. Ideally, the foil should be attached to the relevant pin straight away. This can be done by attaching a seal to the foil and then pushing the inner attachment onto the pin.

Helst bør man feste folien til den aktuelle stiften med en gang. Dette kan gjøres ved å feste en tetning på folien og deretter skyve det innvendige festet på stiften. Ideally, the foil should be attached to the relevant pin straight away. This can be done by attaching a seal to the foil and then pushing the inner attachment onto the pin.

Med oppfinnelsen skapes en optimalt belastbar boltkonstruksjon uten at tetning og folie blir mekanisk overbelastet ved fastspenningen av festene. Dette skyldes særlig avstandsstykkene mellom festene. Det er best å bruke ringer som avstandsstykker. With the invention, an optimally loadable bolt construction is created without the seal and foil being mechanically overloaded by the fastening of the fasteners. This is mainly due to the spacers between the fasteners. It is best to use rings as spacers.

Man får lignende forhold også dersom man i stedet uten ytterligere tetning skyver festet på stiften og trykker det mot folien. A similar situation is also obtained if, instead of without further sealing, you push the fastener onto the pin and press it against the foil.

Lengden på stiften avhenger av tykkelsen på sprøytebetongkonstruksjonen. Den kan bestå utelukkende av betong, men den kan også ha et isolerende lag. Et slikt isolerende lag legges best bak betongen inn mot fjellet. Stiften må da stikke ut gjennom det isolerende laget for med fremre ende å bære det tidligere nevnt trådgitteret og avstandsstykket. The length of the staple depends on the thickness of the shotcrete construction. It can consist entirely of concrete, but it can also have an insulating layer. Such an insulating layer is best placed behind the concrete towards the rock. The pin must then protrude through the insulating layer in order to carry the previously mentioned wire grid and the spacer with its front end.

Ved alle tetningsproblemer må det skilles mellom vannbelastning utenfra, vannbelastning innenfra og vannbelastning som virker virker på sprøytebetongen både utenfra og innenfra. For å møte dette blir det ofte brukt tetningsfolier. Tetningsfolien kan festes på begge sider av sprøytebetongen, men den kan også brukes på bare den ene siden. Den kan være plassert på innsiden av sprøytebetongen for å hindre avløpsvann og annen væske i å trenge ut. In the case of all sealing problems, a distinction must be made between water stress from the outside, water stress from the inside and water stress that acts on the shotcrete from both the outside and the inside. To meet this, sealing foils are often used. The sealing foil can be attached to both sides of the shotcrete, but it can also be used on just one side. It can be placed on the inside of the shotcrete to prevent waste water and other liquids from seeping out.

Sprøytebetongen kan legges på i ett eller flere lag. The shotcrete can be applied in one or more layers.

Bruken er hyppig i underjordiske rom i fast fjell, enten det dreier seg om tunneler, lagerrom, bunkere, kanaler eller annet. Oppå jorden er bruken hyppig i åpne byggegruber. It is frequently used in underground spaces in solid rock, whether it is tunnels, storage rooms, bunkers, canals or something else. Above ground, it is frequently used in open construction pits.

Det finnes flere varianter av underjordisk bruk. There are several varieties of underground use.

For eksempel legges iht. DE-3244000 C et første lag sprøytebetong på fjellveggen. Dette laget bidrar i hovedsak til å forsegle denne. En tetningsfolie legges på det første laget sprøytebetong. Dette laget trenger ikke være tykt. Tetningsfolien skjer vanligvis i baner som må festes på fjellet eller i sprøytebetongen. Banene plasseres etter hverandre på en slik måte at kantene overlapper hverandre og utfyller hverandre slik at man oppnår ønsket tetning. Der kantene overlapper hverandre sveises de sammen. For å feste banene plasserer man først bolter i fjellet. Tetningsfolien kan perforeres av boltene dersom man tetter de lekkasjepunktene som oppstår. For example, according to DE-3244000 C a first layer of shotcrete on the rock face. This layer mainly helps to seal it. A sealing foil is placed on the first layer of shotcrete. This layer does not need to be thick. The sealing foil is usually applied in strips that must be attached to the rock or in the shotcrete. The strips are placed one after the other in such a way that the edges overlap and complement each other so that the desired seal is achieved. Where the edges overlap, they are welded together. To fasten the tracks, bolts are first placed in the rock. The sealing foil can be perforated by the bolts if the leakage points that occur are sealed.

Dette kan gjøres ved hjelp av to flenser, hvorav minst én samtidig tetter med folien. Dette skjer for eksempel ved å forme flensen som neoprenskive. Flensene skal klemme folien mellom seg. Det er best å la flensen inn mot fjellet være fast plassert mens den andre lar seg justere. Boltene utgjør forbindelsen til fjellet og holder betongarmeringen med sprøytebetongnisjen som muliggjør og støtter den indre This can be done using two flanges, at least one of which simultaneously seals with the foil. This happens, for example, by shaping the flange as a neoprene disc. The flanges must squeeze the foil between them. It is best to leave the flange towards the mountain firmly positioned while the other can be adjusted. The bolts form the connection to the rock and hold the concrete reinforcement with the shotcrete niche that enables and supports the interior

sprøytebetongkonstruksjonen. Betongarmeringen består vanligvis av stål for eksempel i form av the shotcrete construction. The concrete reinforcement usually consists of steel, for example in the form of

armeringsmatter. Sprøytebetongnisjene dannes iht. DE-3244000 ved hjelp av et trådnett. Dette er plassert et stykke fra folien og skal forhindre at sprøytebetong som treffer tetningsfolien skal kastes tilbake. reinforcement mats. The shotcrete niches are formed according to DE-3244000 using a wire mesh. This is placed some distance from the foil and should prevent shotcrete that hits the sealing foil from being thrown back.

For øvrig presenterer DE2833148 en tetning i form av et første og et andre lag av mykgjort PVC- plastisol. Inn i dette andre laget som er i en ugelatinert tilstand, legges det delvis inn en krøllfibermatte avpolyamidfiber. Deretter varmes den myke PVC-plastisolen opp og gelatineres slik at krøllfibermatten festes i og forbindes med PVC-plastisollaget. Fibrene i krøllfibermatten kan betraktes som kunststoffpartikler som påføres på sprøytebetongsiden av folien for å festes der. Furthermore, DE2833148 presents a seal in the form of a first and a second layer of softened PVC plastisol. Into this second layer, which is in an ungelatinized state, a curly fiber mat made of polyamide fiber is partially inserted. The soft PVC plastisol is then heated and gelatinized so that the curling fiber mat is attached to and connected to the PVC plastisol layer. The fibers in the curling fiber mat can be regarded as plastic particles that are applied to the shotcrete side of the foil to be fixed there.

Ved annet bruk skal tetningsfolien monteres et stykke fra fjellet. Dette gjennomføres ved at tetningsfolien festes til de beskrevne boltene. Ved denne bruken er problemet med sprøytebetong som preller av, enda større enn i forrige eksempel. Like fullt hjelper trådnettet også i dette tilfellet slik at men ved hjelp av den trådnetteknikken som er beskrevet over, uten videre kan oppføre en sprøytebetongkonstruksjon et stykke fra fjellveggen. For other uses, the sealing foil must be installed some distance from the rock. This is done by attaching the sealing foil to the described bolts. With this use, the problem of shotcrete bouncing off is even greater than in the previous example. The wire mesh also helps just as much in this case, so that with the help of the wire mesh technique described above, a shotcrete structure can easily be erected some distance from the rock face.

Som alternativ til den ovennevnte plasseringen av tetningsfolien med en viss avstand, kan man bruke et gitter eller en trådnetting mellom konstruksjonen og fjellveggen. På denne måten virker trådflettverket fortrinnsvis som sikring mot ras fra fjellet. As an alternative to the above-mentioned placement of the sealing foil at a certain distance, a grid or wire mesh can be used between the structure and the rock wall. In this way, the wire braid works preferably as protection against landslides from the mountain.

I tidsskriftet Forschung + Praksis, 1970, s. 184 er det beskrevet å spenne trådnettet direkte mot tetningsfolien. Likevel får man ved påsprøyting et mellomrom mellom trådnettet og folien fordi folien buler ut i mye større grad enn trådnettet. In the journal Forschung + Praksis, 1970, p. 184, it is described to tension the wire mesh directly against the sealing foil. Nevertheless, by spraying, you get a space between the wire mesh and the foil because the foil bulges out to a much greater extent than the wire mesh.

DE-2400866A1 og DE-36526980A1 angir å dekke til på sprøytebetongsiden tetningsfolien med nonwoven som kan utføre ulike oppgaver. Iht. DE-3626980 kan nonwovenet fylle forskjellige funksjoner, både en beskyttelsesfunksjon og en dreneringsfunksjon. Iht. DE-2400866 bør dessuten fiberstoffet først grunnes før den egentlige leggingen av sprøytebetong begynner. DE-2400866A1 and DE-36526980A1 indicate covering on the shotcrete side the sealing foil with nonwoven which can perform various tasks. According to DE-3626980, the nonwoven can fulfill different functions, both a protective function and a drainage function. According to DE-2400866, moreover, the fiber material should first be primed before the actual laying of shotcrete begins.

DE-3741699 angir bruk av tetningsfolie med nuppestruktur. Inn mot fjellveggen skal nuppene holde en viss avstand slik at vannet som trenger ut av fjellet kan renne bort. DE-3741699 specifies the use of sealing foil with a nub structure. Towards the rock face, the knobs must maintain a certain distance so that the water that penetrates out of the rock can drain away.

DE-3823898 angir å benytte nuppe strukturen på en tetningsfolie til andre formål, nemlig til å holde sprøytebetongen tilbake. DE-3823898 indicates using the bumpy structure on a sealing foil for other purposes, namely to hold back the shotcrete.

I henhold til denne oppfinnelsen skal tetningsfolien ha en spesiell utforming. According to this invention, the sealing foil must have a special design.

Minstestivheten oppnås med uskummet olefinfolie, særlig med polyolefinfolie, f. eks. polyetylenfolie (PE-folie). Det kan også brukes kopolymerisat, f. eks. etylenkopolymerisat. The minimum stiffness is achieved with unfoamed olefin foil, especially with polyolefin foil, e.g. polyethylene foil (PE foil). Copolymers can also be used, e.g. ethylene copolymer.

Alle PE er egnet som tetningsfolie. Det innbefatter blant annet LD-polyetylen, HD-polyetylen og polypropylen (PP). All PE is suitable as a sealing foil. This includes, among other things, LD polyethylene, HD polyethylene and polypropylene (PP).

Stivheten dannes ved en minstetykkelse på 1,5 mm, men helst minst 1,8 mm. For andre foliematerialer økes tykkelsen inntil ønsket stivhet er oppnådd. The stiffness is created by a minimum thickness of 1.5 mm, but preferably at least 1.8 mm. For other foil materials, the thickness is increased until the desired stiffness is achieved.

Overflatens ruhet oppstår ved påføring av partikler av samme materiale som folien selv på den siden av folieflaten som vender mot sprøytebetongen. Partiklene kan ha forskjellig form, men en avlang form er å foretrekke. Dette innbefatter for eksempel tråd- eller strengform. Materialet smeltes lett på overflaten før partiklene føres på, slik at partiklene heftes til folieflaten ved berøring. Materialet skal ikke smeltes så det blir flytende i kjernen. For at fastsmeltingen skal finne sted, må overflatetemperaturen bli høyere enn smeltepunktet for det aktuelle stoffet. Temperaturen bør ligge noe over dette slik at det skjer en rask oppvarming. Til dette bruker man åpen flamme eller andre fremgangsmåter. Man fremstiller kunststoffpartikler for eksempel ved å male opp granulat på 2 til 8 mm så de får et tverrsnitt på 2, 1 Vi eller aller helst 0,2 til 1 mm. Hvor stor mengde som skal påføres, avgjøres av flatevekten til materialet som påføres. Målinger iht. flatevekt er også kjent fra tekstiler. I henhold til oppfinnelsen skal det påføres minst 20, 50 eller helst 100 gram eller mer per kvadratmeter. I praksis vil det bli brukt påføringsmengder på inntil 500 gram og mer per kvadratmeter. Detaljer og variasjoner i påføringen av partikler er beskrevet i følgende trykksaker: AT 194605, CH332229, DE4207210A1, DE19718035C, EP901408A The roughness of the surface occurs when particles of the same material as the foil are applied even on the side of the foil surface that faces the shotcrete. The particles can have different shapes, but an elongated shape is preferable. This includes, for example, thread or string form. The material is easily melted on the surface before the particles are applied, so that the particles adhere to the foil surface when touched. The material must not be melted so that it becomes liquid in the core. For solidification to take place, the surface temperature must be higher than the melting point of the substance in question. The temperature should be somewhat above this so that a rapid heating occurs. An open flame or other methods are used for this. Plastic particles are produced, for example, by grinding up granules of 2 to 8 mm so that they have a cross section of 2.1 Vi or most preferably 0.2 to 1 mm. The amount to be applied is determined by the surface weight of the material being applied. Measurements according to basis weight is also known from textiles. According to the invention, at least 20, 50 or preferably 100 grams or more per square meter must be applied. In practice, application amounts of up to 500 grams and more per square meter will be used. Details and variations in the application of particles are described in the following publications: AT 194605, CH332229, DE4207210A1, DE19718035C, EP901408A

eller i WO 97/37772 hhv. PCT/US97/05029, US 2987104, US 5612081, US 5075135, US 3622422, US 2936814. or in WO 97/37772 or PCT/US97/05029, US 2987104, US 5612081, US 5075135, US 3622422, US 2936814.

Man kan også forvarme folieoverflaten ytterligere for materialpåføringen for å få en bedre forbindelse mellom partikler og folieoverflate. Denne forvarmingen er ikke nødvendig dersom man benytter varmen fra fremstillingen av folien. You can also preheat the foil surface further for the material application to get a better connection between the particles and the foil surface. This pre-heating is not necessary if you use the heat from the production of the foil.

Vanlig fremstilling av folien skjer ved ekstrudering av materialet. Ved hjelp av en ekstruder sendes det smeltedeigaktige kunststoffet gjennom en dyse og inn i spalten til et valsepar. Når kunststoffet kommer inn mellom valsene, kan det allerede ha en folieform. Denne oppnås ved hjelp av en slissedyse. Slissen i dysen har da en lengde og bredde som tilsvarer formen. Conventional production of the foil takes place by extruding the material. With the help of an extruder, the molten dough-like plastic is sent through a nozzle and into the gap of a pair of rollers. When the plastic enters between the rollers, it may already have a foil shape. This is achieved using a slit nozzle. The slot in the nozzle then has a length and width that correspond to the shape.

Det smeltedeigaktige kunststoffet kan også sendes inn i spalten med granulatform eller strimmelform slik at det dannes kunststoffplastilin som fortløpende dras gjennom valsespalten så det dannes folie mellom valsene. The melt-like plastic can also be sent into the gap in granule form or strip form so that plastic plasticine is formed which is continuously drawn through the roller gap so that foil is formed between the rollers.

Mellom valsene i valseparet får folien den nøyaktig ønskede tykkelsen, eventuelt etter å gjenta prosessen én eller flere ganger. Ved første valsegjennomkjøring er ikke foliebredden avgjørende. Valsingen gir en mer eller mindre slangeformet foliekant, og derfor skjæres denne til langs siden når valsingen er over. De kantstrimlene som blir til overs, føres inn igjen i ekstruderen og blir således gjort om til nytt smeltedeigaktig utgangsmateriale for valseprosessen. Under valseprosessen får folien en betydelig temperatur. Denne temperaturen kan benyttes ved påføringen av partikler for å gjøre overflaten ruere. Between the rollers in the roller pair, the foil gets the exact desired thickness, possibly after repeating the process one or more times. For the first roll pass, the foil width is not decisive. The rolling produces a more or less snake-shaped foil edge, and therefore this is cut along the side when the rolling is over. The edge strips that are left over are fed back into the extruder and are thus converted into new melt dough-like starting material for the rolling process. During the rolling process, the foil gets a significant temperature. This temperature can be used when applying particles to roughen the surface.

Man kan dessuten foreta en etteroppvarming for at partiklene skal feste seg bedre til folieoverflaten. Eventuelt kan man også presse partiklene på folieflaten med valsetrykk så partiklene fester seg enda bedre til folieoverflaten. Post-heating can also be carried out so that the particles adhere better to the foil surface. Optionally, you can also press the particles onto the foil surface with roller pressure so that the particles adhere even better to the foil surface.

Likevel tar EP901408A utgangspunkt i at sveisefaktoren til forbindelsen mellom partikler og folieflate ligger vesentlig lavere enn 1. Nevertheless, EP901408A assumes that the welding factor for the connection between particles and foil surface is significantly lower than 1.

Dette anses som fordelaktig med tanke på at partiklene ved en gitt belastning kan løsne igjen, uten at tetningsfolien ødelegges. This is considered advantageous in view of the fact that, under a given load, the particles can loosen again, without the sealing foil being destroyed.

Varmen kan også påføre partiklene bare ved å bruke varme gasser. Det er mulig å dosere partiklene inn i den varme gasstrømmen. Oppholdstiden i den varme gassen bestemmer graden av fastsmelting. Denne tiden avhenger av strekningen partikkelen tilbakelegger før den treffer på folieflaten og av gassens hastighet. The heat can also be applied to the particles just by using hot gases. It is possible to dose the particles into the hot gas flow. The residence time in the hot gas determines the degree of solidification. This time depends on the distance the particle travels before it hits the foil surface and on the speed of the gas.

Varmen kan også tilføres som ren strålevarme ved at partiklene faller gjennom en varmekanal og i fallet smeltes lett på overflaten. The heat can also be supplied as pure radiant heat by the particles falling through a heating channel and melting easily on the surface as they fall.

Vanlig fremstilling av folien skjer ved ekstrudering av materialet. Ved hjelp av en ekstruder sendes det smeltedeigaktige kunststoffet gjennom en dyse og inn i spalten til et valsepar. Når kunststoffet kommer inn mellom valsene, kan det allerede ha en folieform. Denne oppnås ved hjelp av en slissedyse. Slissen i dysen har da en lengde og bredde som tilsvarer formen. Conventional production of the foil takes place by extruding the material. With the help of an extruder, the molten dough-like plastic is sent through a nozzle and into the gap of a pair of rollers. When the plastic enters between the rollers, it may already have a foil shape. This is achieved using a slit nozzle. The slot in the nozzle then has a length and width that correspond to the shape.

Det smeltedeigaktige kunststoffet kan også sendes inn i spalten med granulatform eller strimmelform slik at det dannes kunststoffplastilin som fortløpende dras gjennom valsespalten så det dannes folie mellom valsene. The melt-like plastic can also be sent into the gap in granule form or strip form so that plastic plasticine is formed which is continuously drawn through the roller gap so that foil is formed between the rollers.

Mellom valsene i valseparet får folien den nøyaktig ønskede tykkelsen, eventuelt etter å gjenta prosessen én eller flere ganger. Ved første valsegjennomkjøring er ikke foliebredden avgjørende. Valsingen gir en mer eller mindre slangeformet foliekant, og derfor skjæres denne til langs siden når valsingen er over. De kantstrimlene som blir til overs, føres inn igjen i ekstruderen og blir således gjort om til nytt smeltedeigaktig utgangsmateriale for valseprosessen. I løpet av valseprosessen får folien en betydelig temperatur. Between the rollers in the roller pair, the foil gets the exact desired thickness, possibly after repeating the process one or more times. For the first roll pass, the foil width is not decisive. The rolling produces a more or less snake-shaped foil edge, and therefore this is cut along the side when the rolling is over. The edge strips that are left over are fed back into the extruder and are thus converted into new melt dough-like starting material for the rolling process. During the rolling process, the foil gets a significant temperature.

Man kan også samtidig lage en profil slik det er beskrevet i DEI 9721799. You can also simultaneously create a profile as described in DEI 9721799.

Jo mindre elastisk tetningsfolien er, desto lettere er det å legge sprøytebetongen. Elastisiteten er på den en side avhengig av folietykkelsen, og på den annen side av monteringen av folien. Jo flere jevnt fordelt festepunkt tetningsfolien har, desto stivere blir den. Fortrinnsvis bør festepunktene plasseres slik at fire tilstøtende festepunkter utgjør hjørnene i et kvadrat. Sidelengden i kvadratet er da den samme som avstanden mellom to tilstøtende festepunkter. Jo mindre avstanden mellom de tilstøtende festepunktene og dermed sidelengden i kvadratet er, desto flere festepunkter er nødvendig. Dersom folietykkelsen er 2 mm, bør det være en avstand på 1,2 m mellom tilstøtende festepunkter. Avstanden bør ikke være mer enn 15 % eller helst ikke mer enn 7,5 % høyere enn dette. Tilstøtende betyr de nærmeste festepunktene. The less elastic the sealing foil is, the easier it is to lay the shotcrete. The elasticity is, on the one hand, dependent on the foil thickness, and on the other hand, on the installation of the foil. The more evenly distributed attachment points the sealing foil has, the stiffer it becomes. Preferably, the attachment points should be placed so that four adjacent attachment points form the corners of a square. The side length in the square is then the same as the distance between two adjacent attachment points. The smaller the distance between the adjacent attachment points and thus the side length of the square, the more attachment points are needed. If the foil thickness is 2 mm, there should be a distance of 1.2 m between adjacent attachment points. The distance should not be more than 15% or preferably not more than 7.5% higher than this. Adjacent means the closest attachment points.

Tillatt avstand kan endres ved endring av festenes posisjon. Da forminsker man avstanden dem imellom til man får en minst like stiv konstruksjon som ved plassering på hjørnepunktene i et kvadrat. The permitted distance can be changed by changing the position of the fasteners. Then you reduce the distance between them until you get a construction that is at least as rigid as when placed at the corner points of a square.

Dersom folien er tykkere, øker den tillatte avstanden mellom tilstøtende festepunkter. Avstanden kan bare økes så mye og/eller posisjonen til festepunktene endres så mye at man til tross for den tykkere folien beholder den konstruksjonsstivheten som er beskrevet over. If the foil is thicker, the permitted distance between adjacent attachment points increases. The distance can only be increased so much and/or the position of the attachment points changed so much that, despite the thicker foil, the structural rigidity described above is retained.

Dersom folien er tynnere enn 2 mm, minskes den tillatte avstanden mellom to tilstøtende festepunkter. Avstanden minskes så mye og/eller posisjonen til festepunktene fordeles slik at man til tross for den tynnere folien beholder den konstruksjonsstivheten som er beskrevet over. If the foil is thinner than 2 mm, the permitted distance between two adjacent attachment points is reduced. The distance is reduced so much and/or the position of the attachment points is distributed so that, despite the thinner foil, the structural rigidity described above is retained.

Oppbyggingen av sprøytebetongkonstruksjonen blir lettere med grunning av tetningsfolien. Grunning i henhold til oppfinnelsen bidrar i tillegg til overflateutformingen som er nevnt over, til at sprøytebetongen festes til tetningsfolien og geotekstilduken. Grunningen kan skje med samme sement, klebemiddel eller bindemiddel som brukes til sprøytebetongen, bare uten de tilslag som brukes i denne. Sement/klebemiddel/bindemiddel kan brukes i pulverform og blandes med vann før påføringen på folieflaten og sprøytes på med en dyse i en tåkeaktig form, eller sprøytes på i tåkeaktig form sammen med sement/klebemiddel/bindemiddel i pulveraktig form.. Det kan også brukes en spesiell grunning med en kunststoffilm med mineralsk tilslag. Samtidig gir de mineralske tilslagene i limet en bedre klebevirkning for sprøytebetongen. The build-up of the shotcrete construction becomes easier with priming of the sealing foil. Priming according to the invention contributes, in addition to the surface design mentioned above, to the shotcrete being attached to the sealing foil and the geotextile sheet. The priming can be done with the same cement, adhesive or binder that is used for the shotcrete, just without the aggregates used in it. Cement/adhesive/binder can be used in powder form and mixed with water before application to the foil surface and sprayed on with a nozzle in a misty form, or sprayed on in misty form together with cement/adhesive/binder in powdery form.. It can also be used a special primer with a synthetic film with mineral aggregate. At the same time, the mineral aggregates in the glue provide a better adhesive effect for the shotcrete.

Den tåkeaktige påsprøytingen av grunningen fører til et tynt fuktlag på folieflaten, Tykkelsen på fuktlaget innstilles slik at grunningen ikke begynner å renne på grunn av sin egenvekt. I praksis minskes påføringsmengden helt til man ikke lenger kan observere at det renner. The fog-like spraying of the primer leads to a thin moisture layer on the foil surface. The thickness of the moisture layer is set so that the primer does not start to flow due to its own weight. In practice, the amount of application is reduced until you can no longer observe that it is running.

Dersom hastigheten på grunningen ut av dysen holdes konstant, kan man regulere påføringsmengden med hastigheten man beveger dysen. Dersom påføringsmengden skal minskes, så oppnås dette ved å bevege dysen raskere over påføringsflaten, her altså tetningsfolien. Dersom tetningsfolien sprøytes flere ganger på samme sted, kan man redusere påføringen ved å redusere antall påsprøytinger. If the speed of the primer out of the nozzle is kept constant, the amount of application can be regulated with the speed at which the nozzle is moved. If the amount of application is to be reduced, this is achieved by moving the nozzle faster over the application surface, in this case the sealing foil. If the sealing foil is sprayed several times in the same place, the application can be reduced by reducing the number of applications.

Dersom man gjentar påsprøyting på samme sted på tetningsfolien, kan man redusere påføringsmengden ved å redusere antall gjentakelser. If spraying is repeated at the same place on the sealing foil, the amount of application can be reduced by reducing the number of repetitions.

Om ønskelig kan man blande inn vannabsorberende materialer i grunningen. If desired, water-absorbing materials can be mixed into the primer.

Etter grunningen kan man legge sprøytebetongen i ett eller flere lag på tetningsfolien. Det er da gunstig å legge sprøytebetongen på, ett lag om gangen, og å begynne nederst. Dette gjøres ved hjelp av en bevegelse frem- og tilbake med et verktøy for legging av sprøytebetong. Man kan bruke sprøytebetong, betong, tilsetningsstoffer, tilslag, forsterkningsinnlegg og slikt verktøy som er beskrevet i følgende trykksaker: DE69910173T2, DE69801995T2, DE69721121T2, DE69718705T2, DE69701890T2, DE69700205T2, DE69418316T2, DE69407418T2, DE69403183T2, DE69122267T2, DE69118723T2, DE69010067T2, DE69006589T2, DE60010252T2, DE60001390T2, DE29825081U1, DE29824292U1, DE29824278U1, DE29818934U1, DE29724212U1, DE29718950U1, DE29710362U1, DE29812769U1, DE19854476C2, DE19854476A1, DE19851913A1, DE19838710C2, DE19819660A1, DE19819148C1, DE19754446A1, DE19746958C1, DE19733029C2, DE19652811A1,DE19650330A1. After priming, the shotcrete can be laid in one or more layers on the sealing foil. It is then advantageous to lay the shotcrete on, one layer at a time, and to start at the bottom. This is done using a back and forth movement with a tool for laying shotcrete. Man kan bruke sprøytebetong, betong, tilsetningsstoffer, tilslag, forsterkningsinnlegg og slikt verktøy som er beskrevet i følgende trykksaker: DE69910173T2, DE69801995T2, DE69721121T2, DE69718705T2, DE69701890T2, DE69700205T2, DE69418316T2, DE69407418T2, DE69403183T2, DE69122267T2, DE69118723T2, DE69010067T2, DE69006589T2, DE60010252T2, DE60001390T2, DE29825081U1, DE29824292U1, DE29824278U1, DE29818934U1, DE29724212U1, DE29718950U1, DE29710362U1, DE29812769U1, DE19854476C2, DE19854476A1, DE19851913A1, DE19838710C2, DE19819660A1, DE19819148C1, DE19754446A1, DE19746958C1, DE19733029C2, DE19652811A1,DE19650330A1.

På tegningen er det vist forskjellige eksempler på utforming av oppfinnelsen. The drawing shows various examples of the design of the invention.

Fig. 1 viser en fjellvegg (1) i fast fjell. Bolter er satt inn i fjellet med jevn avstand. Til dette ble det boret de nødvendige hull, og boltene ble festet med monteringssement i disse. Boltene er fremstilt ved midtaksene (2). Fig. 1 shows a rock wall (1) in solid rock. Bolts are inserted into the rock at regular intervals. For this, the necessary holes were drilled, and the bolts were fixed with mounting cement in these. The bolts are produced at the center axes (2).

Fjellveggen (1) skal brukes til å lage en tunnel. Til drenering av vann som siver ut og til sikring mot steiner som faller ned, skal det lages en sprøytebetongkonstruksjon i fjellveggen. The mountain wall (1) will be used to make a tunnel. To drain water that seeps out and to protect against falling stones, a shotcrete structure must be made in the rock face.

Sprøytebetongkonstruksjonen består i grove trekk av et lag folie (4) og et lag sprøytebetong (3). Laget med folie (4) er satt sammen av enkle baner som er lagt slik at de overlapper hverandre og kantene er sveiset sammen. Det er gjort med to sveisesømmer som ligger ved siden av hverandre med noe avstand mellom. Hulrommet mellom sveisesømmene fylles med trykkluft for å kontrollere at sveisesømmene er tette. The shotcrete construction roughly consists of a layer of foil (4) and a layer of shotcrete (3). The layer of foil (4) is composed of simple webs that are laid so that they overlap each other and the edges are welded together. It is made with two welding seams that lie next to each other with some distance between them. The cavity between the welds is filled with compressed air to check that the welds are tight.

Detaljer i sprøytebetongkonstruksjonen er vist på figur 2. En bolt (5) er skjematisk fremstilt. I den enden som stikker ut av fjellet, er bolten (5) forbundet med et feste (14). Laget med folie (4) ligger inntil festet (14). Details of the shotcrete construction are shown in Figure 2. A bolt (5) is shown schematically. At the end that protrudes from the rock, the bolt (5) is connected to a fastener (14). The layer of foil (4) is adjacent to the attachment (14).

På den andre siden av laget med folie fra der festet (14) ligger, er et annet feste (15). Festene (14) og 15) spenner laget med folie inn mellom seg. On the other side of the layer of foil from where the attachment (14) is located, is another attachment (15). The fasteners (14) and 15) clamp the layer of foil between them.

Dessuten bærer festene et avstandsstykke (13) for en trådnetting (12). Trådnettingen (12) har to oppgaver. Den bidrar til leggingen av laget med sprøytebetong (3) ved at det forhindrer at betong som preller av folien, skal falle ned. Dessuten danner trådnettingen (12) en armering for laget med sprøytebetong. Sprøytebetongkonstruksjonen veier så mye i forhold til formen at den uten boltene ville falle sammen før den hadde størknet. Boltene leder vekten av sprøytebetongkonstruksjonen inn i fjellet. Etter at sprøytebetongkonstruksjonen har størknet, danner boltene en fast forbindelse mellom konstruksjon og fjell. In addition, the fasteners carry a spacer (13) for a wire mesh (12). The wire mesh (12) has two tasks. It contributes to the laying of the shotcrete layer (3) by preventing concrete that bounces off the foil from falling down. In addition, the wire mesh (12) forms a reinforcement for the shotcrete layer. The shotcrete construction weighs so much in relation to its shape that without the bolts it would collapse before it had solidified. The bolts guide the weight of the shotcrete structure into the rock. After the shotcrete structure has solidified, the bolts form a firm connection between the structure and the rock.

Fig. 5 viser en mulig sekskantstruktur (43) for trådnettingen som er vist i fig. 2. Fig. 5 shows a possible hexagon structure (43) for the wire netting shown in fig. 2.

Fig. 4 viser et avstandsstykke (40) for posisjonering av trådnettingen. Avstandsstykket (40) presses mot skruemutteren (25) med en annen skruemutter. Avstandsstykket (40) har diverse armer der trådnettet (43) kan festes. Fig. 4 shows a spacer (40) for positioning the wire mesh. The spacer (40) is pressed against the screw nut (25) with another screw nut. The spacer (40) has various arms where the wire mesh (43) can be attached.

På figur 6 vises en egnet folie for sprøytebetongkonstruksjon. Folien (110) er 2 mm tykk og strødd med materialstrenger. Materialstrengene (111) har en trådaktig struktur med en tykkelse eller et tverrmål på 0,1 til 0,3 mm og er fra 5 til 50 mm lange. Materialstrengene (112) har en tykkelse på 1 til 2 mm og er fra 10 til 30 mm lange. De forskjellige materialstrengene blir i eksempelet påført i separate omganger for å kunne varme opp strenger med stort tverrmål på en annen måte enn de med lite tverrmål. I andre eksempler påføres materialstrengene i én felles omgang. Materialstrengene ligger hulter til bulter over hverandre slik at det delvis blir huldannelser i materialstrengene. I denne situasjonen danner materialstrengene (112) forhøyninger på inntil 3 mm. Deler av folieoverflaten forblir udekket. Materialpåstrøingen har en flatevekt på 250 gram per kvadratmeter. I andre eksempler kan det forekomme både høyere og lavere flatevekt. Lavere flatevekt forekommer særlig når folieoverflaten er profilert. I slike tilfeller er det mulig med en flatevekt helt ned til 20 gram per kvadratmeter. Figure 6 shows a suitable foil for shotcrete construction. The foil (110) is 2 mm thick and strewn with strings of material. The material strands (111) have a thread-like structure with a thickness or cross-sectional dimension of 0.1 to 0.3 mm and are from 5 to 50 mm long. The material strands (112) have a thickness of 1 to 2 mm and are from 10 to 30 mm long. In the example, the different strands of material are applied in separate rounds in order to be able to heat up strands with a large cross-section in a different way than those with a small cross-section. In other examples, the strands of material are applied in one common pass. The material strands lie hollow to bolt above each other so that there are partial hollow formations in the material strands. In this situation, the material strands (112) form elevations of up to 3 mm. Parts of the foil surface remain uncovered. The material spread has a surface weight of 250 grams per square metre. In other examples, both higher and lower basis weight may occur. Lower surface weight occurs especially when the foil surface is profiled. In such cases, it is possible with an area weight as low as 20 grams per square meter.

Høyere flatevekt er formålstjenlig når det alt etter sprøytebetongens sammensetning er vanskeligheter med leggingen som må overvinnes. A higher surface weight is expedient when, depending on the composition of the shotcrete, there are difficulties with laying that must be overcome.

Etter at de selv har blitt varmet opp på overflaten, er de forskjellige materialstrengene i eksempelet strødd på folien (10) som på forhånd er overflateoppvarmet. Materialstrengene har blitt varmet opp på overflaten til den har smeltet og blitt flytende. Oppvarmingen skjer med stråling ved at materialstrengene tas ut av en lagringsbeholder ved hjelp av en cellehjulsluse og slippes gjennom en varmekanal ned på folien som føres langsomt forbi. I eksempelet har varmekanalen et stort antall elektrisk drevne varmetråder og en temperaturregulering. Dermed kan temperaturen i varmekanalen økes helt til materialstrengene som faller gjennom, får riktig overflatetemperatur. After they themselves have been heated on the surface, the different strands of material in the example are strewn on the foil (10) which has previously been surface heated. The strands of material have been heated on the surface until it has melted and liquefied. The heating takes place with radiation by the material strands being taken out of a storage container with the help of a cell wheel lock and dropped through a heating channel onto the foil which is slowly passed by. In the example, the heating channel has a large number of electrically driven heating wires and a temperature control. In this way, the temperature in the heating channel can be increased until the material strands that fall through have the correct surface temperature.

Etter monteringen av folien i tunnelen sprøytes det først en hurtigbindende slemme tynt på folien. Når slemmen har tørket, danner den en god grunning for en påfølgende legging av sprøytebetong. Sprøytebetongen legges på i lag, og man begynner ved tunnelsålen. After the installation of the foil in the tunnel, a quick-setting slime is first sprayed onto the foil. When the slime has dried, it forms a good primer for a subsequent laying of shotcrete. The shotcrete is laid in layers, starting at the tunnel sole.

I eksempelet går tunnelen horisontalt slik at sprøytebetongen legges i horisontale lag nedenfra og opp på folien. Lagene har en bredde som tilsvarer ønsket tykkelse på hvert lag sprøytebetong. I andre utførelser er lagene smalere. Da legges først et første lag sprøytebetong på folien, som dekker hele foliesiden. Deretter legges et nytt lag sprøytebetong på, som helt dekker det forrige laget. Dette gjentas til laget med sprøytebetong har fått ønsket tykkelse. In the example, the tunnel runs horizontally so that the shotcrete is laid in horizontal layers from the bottom up on the foil. The layers have a width that corresponds to the desired thickness of each layer of shotcrete. In other designs, the layers are narrower. Then a first layer of shotcrete is first placed on the foil, which covers the entire foil side. A new layer of shotcrete is then applied, completely covering the previous layer. This is repeated until the layer of shotcrete has reached the desired thickness.

Etter at laget med sprøytebetong er lagt, stikker boltene fremdeles ut av betonglaget. After the shotcrete layer has been laid, the bolts still stick out of the concrete layer.

Claims (12)

1. Tunnelkonstruksjoner i fast fjell (1), med folie som tetning (4) mot vann ved bruk av bolter (5) som settes inn i det stabile fjellet (1), folien holdes på boltene ved hjelp av fester (14, 15), samtidig som folien spennes inne mellom to fester (14, 15), hvorav det ene er på utsiden av folien og det andre er på innsiden og det utvendige festet (14) har en forbindelse med bolten (5) og det legges et lag sprøytebetong (3) på folien, som kjennetegnes ved bruk av en folie (11) som har oppruet overflate på den siden sprøytebetongen legges, og som er dannet ved påføring av kunststoffpartikler (111,112), samtidig som kunststoffpartiklene (111, 112) har en trådform med tverrmål på 0,1 til 2 mm og en lenge på 5 til 50 mm og de (111, 112) først er smeltet og deretter strødd eller påført på sprøytebetongsiden av folien for å festes der.1. Tunnel constructions in solid rock (1), with foil as a seal (4) against water using bolts (5) which are inserted into the stable rock (1), the foil is held on the bolts by means of fasteners (14, 15), at the same time that the foil is clamped between two fasteners (14, 15), one of which is on the outside of the foil and the other is on the inside and the external attachment (14) has a connection with the bolt (5) and a layer of shotcrete (3) is placed on the foil, which is characterized by the use of a foil (11) which has a roughened surface on the side where the shotcrete is laid, and which is formed by the application of plastic particles (111,112), at the same time that the plastic particles (111, 112) have a wire shape with a cross-section of 0.1 to 2 mm and a length of 5 to 50 mm and they (111, 112) are first melted and then sprinkled or applied on the shotcrete side of the foil to attach there. 2. Konstruksjon i henhold til krav 1 kjennetegnet ved a) at det anbringes mange bolter (5) i fjellveggen som feste for folien (110). Disse skal ved en folietykkelse på 2 mm festes med en avstand som er på 1,2 meter eller maksimalt overskrider dette med 15 %. Dersom folien (110) har en lavere tykkelse, skal avstanden mellom festepunktene reduseres så mye at folien (110) blir like stiv som en 2 mm tykk folie (110) med avstand på 1,2 meter pluss eller minus 15 %. Dersom folien er tykkere, skal avstanden mellom festepunktene maksimalt økes så mye at folien (110) har samme stivhet som en 2 mm tykk folie (110) med avstand på 1,2 meter pluss eller minus 15 %.2. Construction in accordance with claim 1 characterized by a) that many bolts (5) are placed in the rock wall as fasteners for the foil (110). With a foil thickness of 2 mm, these must be attached at a distance of 1.2 meters or, at most, exceeding this by 15%. If the foil (110) has a lower thickness, the distance between the attachment points must be reduced so much that the foil (110) becomes as stiff as a 2 mm thick foil (110) with a distance of 1.2 meters plus or minus 15%. If the foil is thicker, the distance between the attachment points must be increased as much as possible so that the foil (110) has the same stiffness as a 2 mm thick foil (110) with a distance of 1.2 meters plus or minus 15%. 3. Konstruksjon i henhold til krav 1 eller 2 kjennetegnet ved at kunststoffpartiklene (111, 112) ved påføring faller fritt gjennom en varmekanal eller varmes opp med en flamme.3. Construction according to claim 1 or 2 characterized by the fact that the plastic particles (111, 112) fall freely through a heating channel or are heated with a flame when applied. 4. Konstruksjon i henhold til krav 3 kjennetegnet ved at kunststoffpartiklene (111, 112) ved påføring føres inn i en varmgasstrøm og at de (111, 112) i denne akselereres mot foliesiden.4. Construction according to claim 3 characterized by the fact that the plastic particles (111, 112) are introduced into a hot gas stream during application and that they (111, 112) are accelerated in this towards the foil side. 5. Konstruksjon i henhold til krav 3 eller 4 kjennetegnet ved at det til oppvarmingen av kunststoffpartiklene (111, 112) brukes en stasjonært montert mekanisme og at folien (110) beveges forbi denne.5. Construction according to claim 3 or 4, characterized in that a stationary mounted mechanism is used for heating the plastic particles (111, 112) and that the foil (110) is moved past this. 6. Konstruksjon i henhold til krav 5 kjennetegnet ved at den siden av folien som skal vende mot sprøytebetongen, varmes opp før og/eller etter at partiklene føres på.6. Construction according to claim 5 characterized by the fact that the side of the foil which should face the shotcrete is heated before and/or after the particles are applied. 7. Konstruksjon i henhold til ett av kravene krav 1 til 6 kjennetegnet ved at materialstrenger med ulik diameter får separat oppvarming og påføring.7. Construction according to one of the requirements, requirements 1 to 6, characterized by material strands of different diameters being heated and applied separately. 8. Konstruksjon i henhold til krav 7 kjennetegnet ved at det brukes materialstrenger med en diameter på 0,1 til 0,3 mm og med en diameter på 1 til 2 mm.8. Construction according to claim 7 characterized by the use of material strands with a diameter of 0.1 to 0.3 mm and with a diameter of 1 to 2 mm. 9. Konstruksjon i henhold til et av kravene 1 til 8 kjennetegnet ved at materialstrengene legges hulter til bulter over hverandre.9. Construction according to one of claims 1 to 8, characterized by the fact that the material strands are laid bolt to bolt above each other. 10. Konstruksjon i henhold til ett av kravene 1 til 9 kjennetegnet ved at det fremstilles materialpåstrøing med en flatevekt på minst 20 gram per kvadratmeter, men heller 50 gram per kvadratmeter og helst 100 gram per kvadratmeter.10. Construction according to one of the requirements 1 to 9, characterized by the fact that material is sprinkled with a surface weight of at least 20 grams per square meter, but rather 50 grams per square meter and preferably 100 grams per square meter. 11. Konstruksjon i henhold til ett av kravene 1 til 10 kjennetegnet ved at ikke bare sprøytebetongen legges i horisontale lag over hverandre, men at det også med tanke på folieflaten påføres flere lag oppå hverandre.11. Construction according to one of claims 1 to 10, characterized by the fact that not only is the shotcrete laid in horizontal layers above each other, but that also with regard to the foil surface, several layers are applied on top of each other. 12. Konstruksjon i henhold til et av kravene 1 til 11 kjennetegnet ved en grunning på den siden av folien (110) som skal vende mot sprøytebetongens samtidig som grunningen er sammensatt av en kunststoffilm og mineralske tilslag i limet.12. Construction according to one of the claims 1 to 11 characterized by a primer on the side of the foil (110) which is to face the shotcrete at the same time that the primer is composed of a plastic film and mineral aggregates in the glue.
NO20076650A 2005-07-09 2007-12-27 Construction of buildings and underground facilities NO341102B1 (en)

Applications Claiming Priority (6)

Application Number Priority Date Filing Date Title
DE102005032434 2005-07-09
DE102005038363 2005-08-11
DE200510048118 DE102005048118A1 (en) 2005-10-06 2005-10-06 Construction for superstructures and infrastructures has seal secured at outer side against traversing water or anchor isolation against corrosion or film with rough surface or claw mat or agent for spraying concrete
DE102005057960 2005-12-03
DE102005057959A DE102005057959A1 (en) 2005-07-09 2005-12-03 Gunned concrete structure used in tunnel construction comprises a seal in the form of a film preventing penetration of water and fixed to anchors using fixing units
PCT/EP2006/006358 WO2007006428A2 (en) 2005-07-09 2006-06-30 Construction of superstructures and infrastructures

Publications (2)

Publication Number Publication Date
NO20076650L NO20076650L (en) 2007-12-27
NO341102B1 true NO341102B1 (en) 2017-08-28

Family

ID=37637516

Family Applications (2)

Application Number Title Priority Date Filing Date
NO20076650A NO341102B1 (en) 2005-07-09 2007-12-27 Construction of buildings and underground facilities
NO20160753A NO20160753A1 (en) 2005-07-09 2016-05-04 MOUNTING DEVICE FOR FITTING A FILM FOR USE IN TUNNELS OR IN STELLS IN FIXED MOUNTAINS

Family Applications After (1)

Application Number Title Priority Date Filing Date
NO20160753A NO20160753A1 (en) 2005-07-09 2016-05-04 MOUNTING DEVICE FOR FITTING A FILM FOR USE IN TUNNELS OR IN STELLS IN FIXED MOUNTAINS

Country Status (7)

Country Link
EP (4) EP1902197A2 (en)
AT (1) ATE467747T1 (en)
DE (1) DE502006006948D1 (en)
DK (1) DK1950375T3 (en)
ES (3) ES2341592T3 (en)
NO (2) NO341102B1 (en)
WO (1) WO2007006428A2 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007006428A2 (en) 2005-07-09 2007-01-18 Skumtech As Construction of superstructures and infrastructures
NO334815B1 (en) * 2009-02-03 2014-06-02 John Oldroyd Cheetham Waterproof membrane of an extruded plastic material
DE102012012522A1 (en) 2011-11-16 2013-05-16 Skumtech As Expansion in civil engineering
CN105201532B (en) * 2015-09-11 2017-09-22 中铁九局集团第二工程有限公司 The Ring Cutting construction method of underground Long span spherical crown shape dome under weak surrounding rock
KR101790217B1 (en) * 2016-12-30 2017-10-25 씨카코리아(주) Waterproofing system
NO20171905A1 (en) * 2017-11-29 2019-05-30 John Oldroyd Cheetham Disk for fixing and sealing a lining
CN108194106B (en) * 2018-02-26 2019-09-03 龚岗 The mobile pouring construction technique of tunnel bolt-spary supports concrete trolley
CN109973120B (en) * 2019-04-28 2020-01-10 中国矿业大学 Two-lane deformation control method for reserving pressure relief observation drilling and combined grouting
CN110159309B (en) * 2019-05-27 2021-03-23 中国水利水电第八工程局有限公司 Construction method for backfilling mine method tunnel with foam concrete
CN115234241B (en) * 2022-07-25 2023-06-06 广东省源天工程有限公司 Construction method of diversion tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2833148A1 (en) * 1978-07-28 1980-02-07 Dynamit Nobel Ag SEALING WALLS AGAINST PRESSURE AND / OR SEWAGE WATER USING A MULTI-LAYERED SEALING COATING
DE3244000A1 (en) * 1982-11-27 1984-05-30 Niederberg-Chemie GmbH, 4133 Neukirchen-Vluyn Spray-applied concrete lining
US5728424A (en) * 1996-04-10 1998-03-17 Gse Lining Technology, Inc. Method for forming a textured surface on a geomembrane
DE19718035A1 (en) * 1997-04-29 1998-11-05 Gse Lining Technology Gmbh Applying plastic particles to sheet forming roughened product
US5851580A (en) * 1995-12-27 1998-12-22 Amberg; Felix Shotcrete spraying process

Family Cites Families (59)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT194605B (en) 1954-01-23 1958-01-10 Munk & Schmitz Kommanditgesell Method and device for flame spraying powdery or pasty thermoplastic materials
GB777984A (en) 1954-01-26 1957-07-03 Montedison Spa Method for assuring the adhesion of polyethylene coatings to surfaces
US2936814A (en) 1956-06-25 1960-05-17 Goodyear Tire & Rubber Method of embedding particles in plastic sheet material
US2987104A (en) 1957-09-19 1961-06-06 Congoleum Nairn Inc Method of producing decorative surface covering
US3622422A (en) 1965-12-15 1971-11-23 Kendall & Co Process for producing a nonwoven fabric
DE2400866C2 (en) 1974-01-09 1981-10-01 Ruhrkohle Ag, 4300 Essen Expansion for underground spaces, especially in tunnel and underground mining, e.g. for route expansion
DE3622559A1 (en) 1986-07-04 1987-05-21 Schlegel Lining Tech Gmbh METHOD FOR FINISHING THE SURFACE OF A FILM OF WELDABLE POLYMER MATERIAL WITH PROJECTED PRESSURES AND FILM PRODUCED BY THIS METHOD
DE3626980A1 (en) 1986-08-08 1988-02-11 Niederberg Chemie Tunnel lining
DE8701969U1 (en) 1986-12-09 1987-04-02 Niederberg-Chemie Gmbh, 4133 Neukirchen-Vluyn, De
DE8632994U1 (en) 1986-12-09 1987-02-05 Niederberg-Chemie Gmbh, 4133 Neukirchen-Vluyn, De
DE3741699A1 (en) 1987-12-09 1989-06-22 Niederberg Chemie Frost-proofing
JPH0742497B2 (en) 1988-02-04 1995-05-10 山陽特殊製鋼株式会社 Heat treatment method for corrosion and heat resistant bearing steel
DE3823898A1 (en) 1988-07-14 1990-01-25 Niederberg Chemie Frost protection in tunnels
DE8809049U1 (en) 1988-07-14 1988-09-01 Niederberg-Chemie Gmbh, 4133 Neukirchen-Vluyn, De
IT1234069B (en) 1989-04-28 1992-04-29 Trevi Spa PROCEDURE FOR THE EXECUTION OF THE COVERING OF A GALLERY AND EQUIPMENT FOR THE ACTIVATION OF THIS PROCEDURE
US5002438B1 (en) 1990-01-03 1995-05-30 Strong Systems Inc Method of rehabilitating manholes by custom lining/relining.
GB9001799D0 (en) 1990-01-26 1990-03-28 Blue Circle Ind Plc Cementitious composition and making concrete therefrom
DE4100902A1 (en) 1990-02-26 1991-08-29 Huels Troisdorf Attaching sealing membrane to substrates - using hooked pile type fasteners fixed to membrane and to e.g. foundation respectively so that bond can always be released if desired
JPH0819833B2 (en) * 1990-05-24 1996-02-28 環構エンヂニアリング株式会社 Mounting method of waterproof sheet in tunnel construction and its mounting member
NO172255C (en) 1991-01-08 1993-06-23 Sandoz Ltd PROCEDURE FOR MIXING ADDITIVES IN A SUBSTANCES AND ADDITION TO USE BY THE PROCEDURE
DE4207210A1 (en) * 1992-03-06 1993-09-09 Mauser Werke Gmbh Additionally roughening surface of thermoplastics e.g. to non-skid state - by e.g. heating to form soft surface skin and applying suitable particles so that they become embedded
SE501419C2 (en) 1993-02-25 1995-02-13 Svensk Glasaatervinning Ab Process for making concrete comprising glass filler and use of glass filler in making concrete
FR2708592B1 (en) 1993-07-29 1995-09-29 Lafarge Coppee Accelerating and hardening agent for silicic hydraulic binders.
JPH0742497A (en) * 1993-07-30 1995-02-10 Kanko Eng Kk Fitting method of impervious sheet and fitting members thereof
CH686513A5 (en) 1993-12-06 1996-04-15 Sika Ag Method of accelerating the setting and setting of a binder and setting and setting accelerators.
US5612081A (en) 1994-11-25 1997-03-18 Netlon Limited Applying grit particles to a continuous web
DE19519595A1 (en) 1995-05-29 1996-12-05 Niedlich Thorsten Simple, cheaper, more damage=proof tunnel sealing web
NO301786B1 (en) * 1996-04-11 1997-12-08 Oersta Staalindustri Device for fixing tunnel cladding
EP0807614B1 (en) 1996-05-13 2003-04-23 Denki Kagaku Kogyo Kabushiki Kaisha Accelerating agent, spraying material and spraying method employing it
AU723970B2 (en) 1996-06-14 2000-09-07 Construction Research & Technology Gmbh Concrete spraying additives
IT1283165B1 (en) 1996-07-17 1998-04-07 Italcementi Spa RAPID CONCRETE CONTAINING CLINKER BASED ON CALCIUM FLUORALUMINATE MIXED WITH LIME
DE19650330A1 (en) 1996-08-16 1998-02-19 Johannes Junior Process and device in tunnel construction
SE9603418D0 (en) 1996-09-19 1996-09-19 Eka Chemicals Ab A method of preparation of a hardening composition
GB9625163D0 (en) 1996-12-04 1997-01-22 Sandoz Ltd Organic compounds
JPH10306695A (en) * 1997-04-28 1998-11-17 Taisei Corp Hanging metal tool for reinforcing bar in tunnel
GB9708831D0 (en) 1997-04-30 1997-06-25 Unilever Plc Suspensions with high storage stability, comprising an aqueous silicate solution and filler material
DE19721799A1 (en) 1997-05-24 1998-11-26 Naue Fasertechnik Plastic sealing strip used on slopes of waste disposal sites and manufacturing equipment
AT2027U1 (en) 1997-05-27 1998-03-25 Lukas Walter Dr SPRAY NOZZLE AND METHOD FOR DRY SPRAYING SPRAY CONCRETE
DE29710362U1 (en) 1997-06-13 1997-08-14 Zueblin Ag Device for concreting reinforced ceilings, especially vaults of tunnels
DE19733029C2 (en) 1997-07-31 2002-03-28 Ludwig Pfeiffer Process for the rehabilitation of a pipeline, especially for civil engineering
DE29718950U1 (en) 1997-10-24 1998-01-02 Eber Friedhelm Spray nozzle for blowing out finished mixtures, such as shotcrete, spraying mortar, foam concrete, foam mortar or the like.
DE19746958C1 (en) 1997-10-24 1999-06-17 Friedhelm Eber Assembly to mix building mortar, water and air and discharge through a jet
DE19754446A1 (en) 1997-12-08 1999-06-10 Dyckerhoff Ag Spray binder and its use
DE29824292U1 (en) 1997-12-08 2000-10-26 Dyckerhoff Ag Shotcrete
US5981630A (en) 1998-01-14 1999-11-09 Synthetic Industries, Inc. Fibers having improved sinusoidal configuration, concrete reinforced therewith and related method
DE19819148C1 (en) 1998-04-24 1999-12-16 Mannesmann Ag Fiber for reinforcing castable curing materials and method and device for their production
DE29812769U1 (en) 1998-07-17 1998-11-12 Hanisch Wolfgang Trailer vehicle, in particular on passenger cars, for advertising and information
GB2340070B (en) 1998-07-28 2003-04-16 Fosroc International Ltd Waterproofing membranes and a method for their application
DE19838710C2 (en) 1998-08-26 2002-03-21 Spritzbeton Stuttgart Gmbh & C Process for the production of ready-to-use shotcrete
DE29818934U1 (en) 1998-10-23 2000-02-24 Tepe Maschinen Anlagen Und Ind Device for the production of ready-to-use mixtures from bulk material
DE19851913C2 (en) 1998-11-11 2001-02-15 Rombold & Gfroehrer Gmbh & Co Process for the preparation of a shotcrete or shot mortar
DE19854476C2 (en) 1998-11-25 2002-04-11 Dyckerhoff Ag Hydraulic binder composition free of sulfate carrier and its use
DE29825081U1 (en) 1998-11-25 2004-09-09 Dyckerhoff Ag Quick setting hydraulic binder composition used e.g. in the production of spray concrete contains a binder component free from a sulfate carrier and a fluxing agent free from sulfonate groups
JP2000220395A (en) * 1999-02-02 2000-08-08 Bridgestone Corp Waterproof connecting tool used for attaching support for covering concrete onto execution surface
IT1308638B1 (en) 1999-03-02 2002-01-09 Italcementi Spa QUICK CONCRETE BASED ON LIME AND ALUMINATES.
ATE265401T1 (en) 2000-08-08 2004-05-15 Denki Kagaku Kogyo Kk SETTING ACCELERATOR, SPRAY MATERIAL AND METHOD USING SUCH MATERIAL
DE20217044U1 (en) 2002-11-05 2003-06-26 Mohr Peter Protection and strengthening cover consists of two synthetic-fiber fleece layers provided with foils consisting of flexible thermoplastic polyolefins with a high biaxial stretch capability
DE102005019645A1 (en) * 2005-04-26 2006-11-02 Skumtech As Shotcrete construction establishing method for tunnels, involves attaching fixing points at mountain excavation, and forming shotcrete as layers, where distance of points is increased/or reduced until foil has same rigidity
WO2007006428A2 (en) 2005-07-09 2007-01-18 Skumtech As Construction of superstructures and infrastructures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2833148A1 (en) * 1978-07-28 1980-02-07 Dynamit Nobel Ag SEALING WALLS AGAINST PRESSURE AND / OR SEWAGE WATER USING A MULTI-LAYERED SEALING COATING
DE3244000A1 (en) * 1982-11-27 1984-05-30 Niederberg-Chemie GmbH, 4133 Neukirchen-Vluyn Spray-applied concrete lining
US5851580A (en) * 1995-12-27 1998-12-22 Amberg; Felix Shotcrete spraying process
US5728424A (en) * 1996-04-10 1998-03-17 Gse Lining Technology, Inc. Method for forming a textured surface on a geomembrane
DE19718035A1 (en) * 1997-04-29 1998-11-05 Gse Lining Technology Gmbh Applying plastic particles to sheet forming roughened product

Also Published As

Publication number Publication date
EP1902197A2 (en) 2008-03-26
EP2837768A2 (en) 2015-02-18
EP2837768B1 (en) 2018-01-31
ES2659022T3 (en) 2018-03-13
EP2837768A3 (en) 2015-09-09
NO20160753A1 (en) 2016-05-04
EP2420648A3 (en) 2013-01-02
EP2420648B1 (en) 2014-10-08
ES2341592T3 (en) 2010-06-22
EP2420648A2 (en) 2012-02-22
DE502006006948D1 (en) 2010-06-24
EP1950375A3 (en) 2008-08-27
WO2007006428A3 (en) 2007-03-29
EP1950375B1 (en) 2010-05-12
ATE467747T1 (en) 2010-05-15
ES2523276T3 (en) 2014-11-24
DK1950375T3 (en) 2010-07-05
WO2007006428A2 (en) 2007-01-18
EP1950375A2 (en) 2008-07-30
NO20076650L (en) 2007-12-27

Similar Documents

Publication Publication Date Title
NO341102B1 (en) Construction of buildings and underground facilities
US9637926B2 (en) Membrane roofing
US10968596B2 (en) Below grade, blind side, dual waterproofing membrane assembly incorporating a sheet membrane with adhesive to fully bond to concrete/shotcrete, and a method of making, and using same
US20110135851A1 (en) Polymer granules suitable as infill material for artificial turf structures
JP2016037746A (en) Embedded joint structure for road bridge and construction method for the embedded joint structure
US5950383A (en) Metal roof sealing system and method
US20040137813A1 (en) Air and vapor barrier sheathing system
JP2015224478A (en) Abutted-type expansion/contraction device for road bridge, and construction and repair methods therefor
US20160305080A1 (en) Methods for the manufacture of a module for use in a crash barrier and assembly of the crash barrier
NO20171905A1 (en) Disk for fixing and sealing a lining
WO2008107466A1 (en) Reinforcement nets for the processing of bituminous asphalt layers and method for the production and installation thereof
EP1978207A2 (en) Fire protection for structures
NO323883B1 (en) Device for non-combustible water and frost protection of tunnels and rock cavities
DE102005019645A1 (en) Shotcrete construction establishing method for tunnels, involves attaching fixing points at mountain excavation, and forming shotcrete as layers, where distance of points is increased/or reduced until foil has same rigidity
EP2563589B1 (en) Laminated fire-proof membrane and method for fabricating same
CN211080818U (en) Passive ultralow-energy-consumption dry-operation flat roof slope-finding heat-insulation waterproof integrated eaves gutter
DE102005048118A1 (en) Construction for superstructures and infrastructures has seal secured at outer side against traversing water or anchor isolation against corrosion or film with rough surface or claw mat or agent for spraying concrete
DE10245470A1 (en) Foamed heat insulation material, e.g. for tunnel lining, is built up of joined extruded sheets and contains aluminum flakes
DE102008046055A1 (en) Tunnel lining for use in mountain for e.g. motor vehicle, has heat insulation arranged at seal at inner side of tunnel, where sprayed concrete return layer is partially held with screw i.e. hexagonal screw, in heat insulation
DE102008014757A1 (en) Tunnel extension for use between tunnels at stable rock mass and unstable rock mass, has heat insulation made of plastic foam, and arranged on seal at tunnel side, where heat insulation and seal are formed together
HU211781B (en) Method for carrying out of foam material mixture, particularly for heat insulatings, mixing head for carrying out the method and insulating material produced by this method
CN116291556A (en) Waterproof heat-insulating structure of railway tunnel in cold region and construction method thereof
DE202005021976U1 (en) Shotcrete construction with foil seal
CN201221381Y (en) Tunnel main drainpipe bracket
AU640568B2 (en) Waterstops

Legal Events

Date Code Title Description
CREP Change of representative
CHAD Change of the owner's name or address (par. 44 patent law, par. patentforskriften)

Owner name: SKUMTECH AS, NO

MM1K Lapsed by not paying the annual fees