JPH1018322A - 逆打ち工法による免震建物の構築方法 - Google Patents

逆打ち工法による免震建物の構築方法

Info

Publication number
JPH1018322A
JPH1018322A JP8176039A JP17603996A JPH1018322A JP H1018322 A JPH1018322 A JP H1018322A JP 8176039 A JP8176039 A JP 8176039A JP 17603996 A JP17603996 A JP 17603996A JP H1018322 A JPH1018322 A JP H1018322A
Authority
JP
Japan
Prior art keywords
constructed
column
base
floor
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8176039A
Other languages
English (en)
Other versions
JP3648651B2 (ja
Inventor
Toshiharu Urano
敏晴 浦野
Masanao Nishiyama
正直 西山
Osamu Hase
理 長谷
Fumio Sato
文雄 佐藤
Kazuhide Yoneyama
和秀 米山
Yoshihiro Ishikawa
善弘 石川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP17603996A priority Critical patent/JP3648651B2/ja
Publication of JPH1018322A publication Critical patent/JPH1018322A/ja
Application granted granted Critical
Publication of JP3648651B2 publication Critical patent/JP3648651B2/ja
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

(57)【要約】 【課題】 建物の柱脚基礎の下に柱脚基礎を組み込んだ
免震建物を逆打ち工法で構築する技術分野を提供する。 【解決手段】 地中に山留め壁及び構真柱を構築した
後、地盤の1次掘削と1階床、梁の構築を行い、つづい
て2次掘削と地下1階床、梁を構築する工程を順次下向
き方向へ繰り返し、地盤を最終掘削レベルまで掘削した
段階で、まず掘削底面に基礎梁を構築し、つづいて前記
基礎梁の上方に柱脚基礎の床及び梁を構築し、その後前
記基礎梁と柱脚基礎梁との間に支保工を設置し、同支保
工で建物上部荷重を支持する状態とした後、構真柱を免
震層の部分で切除し、前記構真柱を切除した部分に免震
装置を取付け、しかる後に前記支保工を撤去して免震装
置による支持に盛り変える。

Description

【発明の詳細な説明】
【0001】
【発明の属する技術分野】この発明は、建物の柱脚基礎
の下に柱脚基礎を組み込んだ免震建物を逆打ち工法で構
築する技術分野に属する。
【0002】
【従来の技術】近年、地震に強い免震構造建物の要請が
高まり、建物の基礎部に免震装置を組み込んだ免震建物
(例えば特公平7ー81284号公報に記載の建物を参
照)の需要が増大している。しかし、免震建物は、免震
装置を設置する階層(免震層)が設けられるため、一般
の建物に比して建築工期が長くなる欠点がある。
【0003】ところで、地下階を有する建物の建築にお
いて、山留め架構の安定性を向上させ、更に全体工期の
短縮を図ることを主目的にして逆打ち工法を採用するこ
とが多い。逆打ち工法の特長は、山留め支保工の働きを
兼ねる地下階床の鉛直荷重を構真柱に支持させて地盤の
掘削を進めるのと並行して地上部分の躯体工事の建築を
進められることである。
【0004】従って、この逆打ち工法を前記免震建物の
建築に採用できれば、工期の短縮を図る上で大いに有効
的であることが理解される。しかしながら、免震建物の
場合は、構真柱の位置と免震装置の位置とが干渉するた
め、一般論として逆打ち工法の採用は困難という考えが
ある。
【0005】
【本発明が解決しようとする課題】本発明の目的は、上
述したように構真柱の位置と免震装置の位置とが干渉す
るため採用が困難と考えられる逆打ち工法で免震建物の
建築を行い、もって大幅な工期の短縮を達成することで
ある。
【0006】
【課題を解決するための手段】上述の課題を解決するた
めの手段として、請求項1に記載した発明は、建物の柱
脚基礎の下に免震装置を組み込んだ免震建物を逆打ち工
法で構築する方法において、地中に山留め壁及び構真柱
を構築した後、地盤の1次掘削と1階床、梁の構築を行
い、つづいて2次掘削と地下1階床、梁を構築する工程
を順次下向き方向へ繰り返し、地盤を最終掘削レベルま
で掘削した段階で、まず掘削底面に基礎梁を構築し、つ
づいて前記基礎梁の上方に柱脚基礎の床及び梁を構築
し、その後前記基礎梁と柱脚基礎梁との間に支保工を設
置し、同支保工で建物上部荷重を支持する状態とした
後、構真柱を免震層の部分で切除し、前記構真柱を切除
した部分に免震装置を取付け、しかる後に前記支保工を
撤去して免震装置による支持に盛り変えることをそれぞ
れ特徴とする。
【0007】
【発明の実施形態及び実施例】本願発明は、建物の柱脚
基礎の下に免震装置を組み込んだ免震建物を逆打ち工法
で構築する方法として好適に実施される。本発明の構築
方法は、基本的に逆打ち工法の手順であり、先ず図1に
示したように、地中に山留め壁1及び構真柱2を構築す
る。山留め壁1は例えばソイル柱列壁として構築され
る。また、構真柱2は地中に深く打設した支持杭3の上
に連続する形に構築される。
【0008】かくして山留め壁1及び構真柱2を完成し
た後に、図2のように地盤の1次掘削を行い、地面レベ
ルに1階床4及び梁5の構築を行う。つづいて図3のよ
うに地盤の2次掘削を行い、地下1階床4´及び梁5´
を構築する工程を順次下向き方向へ繰り返す。こうして
地盤を最終掘削レベルD(図3)まで掘削した段階で、
図4に示したように、まず掘削底面に基礎梁7を構築す
る。つづいて前記基礎梁7の上方に柱脚基礎となる床8
及び梁9(その構造詳細は図7を参照)を構築し、前記
基礎梁7との間に免震装置を設置可能な広さの空間を免
震層10として形成する。また、この段階で、山留め壁
1の内側面に沿って建物の地下外壁13を構築し、構真
柱2に沿って地下階柱14を構築する。
【0009】その後、前記基礎梁7と柱脚基礎梁9との
間に支保工11を設置し、同支保工11で建物上部荷重
を支持する状態とする(図5)。支保工11には、仮設
ジャッキを好適に使用することができる。次に、構真柱
2のうち免震層10に露出した部分S(詳細は図7を参
照)を切除する(図6)。そして、前記構真柱を切除し
た部分Sに免震装置12を取付け(図7、図8を参
照)、その後に前記支保工11を撤去して免震装置12
による支持に盛り変える(図9)。ここでいう免震装置
12とは、一例として鉄板とゴムシートを交互に貼り合
わせた積層ゴム柱体であり、必要に応じて地震エネルギ
ーを減衰する粘弾性ダンパー等が付属する構成とされ
る。
【0010】上述の通りであるから、逆打ち工法を実施
する際に問題となる、構真柱2の位置と免震装置12の
位置とが干渉を起こす点は合理的に解決されて支障な
い。
【0011】
【本発明が奏する効果】本発明の構築方法によれば、免
震建物の建築に逆打ち工法の採用が容易に可能となり、
その結果、地下工事中の山留め架構の安定性が向上し、
工事の安全性の向上が図れると共に、全体工期の大幅な
短縮が可能となるのである。
【図面の簡単な説明】
【図1】本発明の構築方法の第1段階として山留め壁及
び構真柱を構築した断面図である。
【図2】地盤を第1次掘削し、地上1階の床、梁を構築
した断面図である。
【図3】地盤を第2次掘削し地下1階の床、梁を構築し
た断面図である。
【図4】基礎梁等を構築した段階の断面図である。
【図5】支保工を設置した段階の断面図である。
【図6】免震層の構真柱を切除した段階の断面図であ
る。
【図7】免震装置の設置状況を拡大して示した断面図で
ある。
【図8】免震装置を設置した段階の断面図である。
【図9】支保工を撤去した段階の断面図である。
【符号の説明】
12 免震装置 1 山留め壁 2 構真柱 4 床 5 梁 7 基礎梁 9 柱脚基礎梁 11 支保工
───────────────────────────────────────────────────── フロントページの続き (72)発明者 佐藤 文雄 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 米山 和秀 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 石川 善弘 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内

Claims (1)

    【特許請求の範囲】
  1. 【請求項1】 建物の柱脚基礎の下に免震装置を組み込
    んだ免震建物を逆打ち工法で構築する方法において、 地中に山留め壁及び構真柱を構築した後、地盤の1次掘
    削と1階床、梁の構築を行い、つづいて2次掘削と地下
    1階床、梁を構築する工程を下向き方向へ繰り返し、地
    盤を最終掘削レベルまで掘削した段階で、まず掘削底面
    に基礎梁を構築し、つづいて前記基礎梁の上方に柱脚基
    礎の床及び梁を構築し、その後前記基礎梁と柱脚基礎梁
    との間に支保工を設置し、同支保工で建物上部荷重を支
    持する状態とした後、構真柱を免震層の部分で切除し、
    前記構真柱を切除した部分に免震装置を取付け、しかる
    後に前記支保工を撤去して免震装置による支持に盛り変
    えることをそれぞれ特徴とする、逆打ち工法による免震
    建物の構築方法。
JP17603996A 1996-07-05 1996-07-05 逆打ち工法による免震建物の構築方法 Expired - Lifetime JP3648651B2 (ja)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17603996A JP3648651B2 (ja) 1996-07-05 1996-07-05 逆打ち工法による免震建物の構築方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17603996A JP3648651B2 (ja) 1996-07-05 1996-07-05 逆打ち工法による免震建物の構築方法

Publications (2)

Publication Number Publication Date
JPH1018322A true JPH1018322A (ja) 1998-01-20
JP3648651B2 JP3648651B2 (ja) 2005-05-18

Family

ID=16006658

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17603996A Expired - Lifetime JP3648651B2 (ja) 1996-07-05 1996-07-05 逆打ち工法による免震建物の構築方法

Country Status (1)

Country Link
JP (1) JP3648651B2 (ja)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008303587A (ja) * 2007-06-06 2008-12-18 Takenaka Komuten Co Ltd 免震建物の逆打ち工法
CN102116027A (zh) * 2010-12-17 2011-07-06 上海市第四建筑有限公司 框架式组合换撑体系及其施工方法
JP2015218546A (ja) * 2014-05-21 2015-12-07 清水建設株式会社 免震建物の施工方法
JP2017031755A (ja) * 2015-08-05 2017-02-09 大成建設株式会社 免震建物構築方法
JP2018091107A (ja) * 2016-12-07 2018-06-14 鹿島建設株式会社 地下構造体の構築方法
JP2018178613A (ja) * 2017-04-18 2018-11-15 株式会社竹中工務店 施工方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5984655B2 (ja) * 2012-12-17 2016-09-06 大成建設株式会社 免震建物の施工方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008303587A (ja) * 2007-06-06 2008-12-18 Takenaka Komuten Co Ltd 免震建物の逆打ち工法
CN102116027A (zh) * 2010-12-17 2011-07-06 上海市第四建筑有限公司 框架式组合换撑体系及其施工方法
JP2015218546A (ja) * 2014-05-21 2015-12-07 清水建設株式会社 免震建物の施工方法
JP2017031755A (ja) * 2015-08-05 2017-02-09 大成建設株式会社 免震建物構築方法
JP2018091107A (ja) * 2016-12-07 2018-06-14 鹿島建設株式会社 地下構造体の構築方法
JP2018178613A (ja) * 2017-04-18 2018-11-15 株式会社竹中工務店 施工方法

Also Published As

Publication number Publication date
JP3648651B2 (ja) 2005-05-18

Similar Documents

Publication Publication Date Title
JP2001262595A (ja) 地下躯体の構築工法
JP4558145B2 (ja) 既存建物の地下免震化工法
JPH1018322A (ja) 逆打ち工法による免震建物の構築方法
JP2700811B2 (ja) スーパーフレームを含む構造物の構築方法
JP3240438B2 (ja) 免震建物および既存建物の免震化工法
JP2989539B2 (ja) 既存建物の免震化工法
JP5316897B2 (ja) 免震化工法
JP2000179161A (ja) 既存建物の免震化工法
JP2000291031A (ja) 免震構造物の構築方法
JP3248458B2 (ja) 支保工架設地下構築工法
JP3381066B2 (ja) 既存建物の免震化工法及び免震建物
JPH0559728A (ja) 地下既設構造物上方における山留工法
JP3656452B2 (ja) 既存建物の免震化工法
JP2016079651A (ja) 支持構造
JP2020125630A (ja) 建物の構築方法
JP3246287B2 (ja) 既存建物のジャッキアップ工法
JP2003328587A (ja) 既存建築物の免震化工法
JP2001173269A (ja) 免震建物の構築方法
JP2019173453A (ja) 建物の構築方法
JPH1130053A (ja) 免震建物の施工法
JP2819008B2 (ja) 既存建物の免震化構法
JP7193065B2 (ja) 逆打ち工法
JPH0762897A (ja) 建物の下部増築工法
JP2006022557A (ja) 既存建造物の免震化工法
JP2020070701A (ja) 地下構造体、建物、および地下構造体の構築方法

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040803

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040909

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041026

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041027

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050111

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050202

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090225

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090225

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100225

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100225

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110225

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110225

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120225

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120225

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130225

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130225

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140225

Year of fee payment: 9

EXPY Cancellation because of completion of term