WO2014139252A1 - 高温环境下大型筏基施工方法 - Google Patents

高温环境下大型筏基施工方法 Download PDF

Info

Publication number
WO2014139252A1
WO2014139252A1 PCT/CN2013/078991 CN2013078991W WO2014139252A1 WO 2014139252 A1 WO2014139252 A1 WO 2014139252A1 CN 2013078991 W CN2013078991 W CN 2013078991W WO 2014139252 A1 WO2014139252 A1 WO 2014139252A1
Authority
WO
WIPO (PCT)
Prior art keywords
construction
foundation
concrete
raft foundation
joint
Prior art date
Application number
PCT/CN2013/078991
Other languages
English (en)
French (fr)
Inventor
陈明宝
刘祖国
Original Assignee
中国十七冶集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国十七冶集团有限公司 filed Critical 中国十七冶集团有限公司
Publication of WO2014139252A1 publication Critical patent/WO2014139252A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Definitions

  • the invention belongs to the technical field of civil construction, and particularly relates to a construction method of 'cabin separation and joint pouring pouring' of a super large-area integral slab reinforced concrete foundation under high temperature conditions.
  • the basement of reinforced concrete slabs in the basement is getting larger and larger, and the reinforced concrete slab foundation of 200m ⁇ 200m is more and more.
  • Such a large reinforced concrete raft foundation is selected in the environment where the design is not set with the post-casting belt and the construction joint, and the environment is dry, the annual average temperature is 41 °C, the maximum temperature is 52 °C, and the temperature difference between day and night is 20 °C. Appropriate construction methods are particularly important. Otherwise, the following problems will occur: 1. Under the conditions of no post-casting and construction joints, the large-scale reinforced concrete slab foundation under high temperature environment may have temperature,shrinking cracks; at the same time, it will also have an impact on the construction schedule. 2. Adopting the 'blocking jump method' to influence the simultaneous parallel operation of the concrete pouring and waterproof construction of the large reinforced concrete raft foundation.
  • the object of the present invention is to solve the above problems, and to provide a large-scale raft foundation construction method in a high temperature environment for the technical problems existing in the existing construction method of a super large-area integral reinforced concrete raft foundation in a high temperature environment, and to ensure a large raft foundation.
  • On the basis of no cracks in reinforced concrete under high temperature environment it also overcomes the contradiction between waterproof construction and concrete-based concrete pouring caused by pouring a piece of 'blocking jump' construction method, which improves the mechanical use efficiency and shortens. The construction period.
  • the technical solution of the present invention is realized in this way: a large-scale raft foundation construction method in a high temperature environment, characterized in that the construction method is as follows:
  • the length of the raft foundation concrete is not calculated by calculation, and the raft foundation is divided into small pieces to form 'cabin separation'.
  • the slab foundation construction joint meets the design requirements and considerations. the elements of:
  • a groove type construction joint is used in the middle of the thickness of the raft foundation construction joint
  • the 'cabin compartment' is constructed by a method of fully advancing one side or four sides of a small piece of raft foundation to achieve 'joint pouring'.
  • the invention improves the construction method of the slab-based concrete 'block jumping method' by the 'cabin separation' design, the construction joint and the waterproof design, the 'jointing pouring' construction method, and the construction method of filling the super large raft base to the poured
  • the 'cabin separation' is constructed by one-sided or four-sided construction of a small piece of raft foundation, thereby realizing the 'joint pouring', overcoming the construction method of pouring a piece of 'blocking jump'
  • the contradiction between construction and concrete-based concrete watering; the traditional raft foundation construction technology can be extended, the quality is guaranteed, the construction period is shortened, the mechanical use efficiency is improved, and the cost is reduced.
  • Fig. 1 is a sectional view showing the design of a construction joint of the present invention.
  • the length of the raft foundation concrete is not calculated by calculation, and the raft foundation is divided into small pieces to form 'cabin separation'.
  • the slab foundation construction joint meets the design requirements and considerations. the elements of:
  • a groove type construction joint is used in the middle of the thickness of the raft foundation construction joint
  • the groove-type construction joint is set in the middle part of the construction joint to increase the waterproof effect.
  • a water stop belt is arranged on the construction seam of the waterproof coil, and a grouting pipe is laid on the water stop belt.
  • the grouting liquid is injected into the grouting pipe system at the partition of the leaking water to achieve the effect of prevention and control;
  • the 'cabin compartment' is constructed by a method of fully advancing one side or four sides of a small piece of raft foundation to achieve 'joint pouring'.

Abstract

一种高温环境下大型筏基施工方法,将筏板基础分隔成小块;在筏板基础施工缝的厚度中部采用凹槽型施工缝;在素混凝土垫层(2)上铺一层土工布(3);在土工布(3)上铺一层PVC防水卷材(4);在PVC防水卷材(4)上抹砂浆找平层(5);在施工缝处设置橡胶止水带(10);在橡胶止水带(10)上铺设水平注浆管(8)、竖向注浆管(9);在施工缝的凹槽和防水设计施工完毕后,浇筑小块混凝土,养护7天后,向已浇注的小块的筏板基础一侧或四周全面推进的方法施工。本方法提高了机械使用效率,缩短了工期。

Description

高温环境下大型筏基施工方法 技术领域
本发明属于土建施工技术领域,具体涉及一种在高温条件下超大面积整体筏板钢筋混凝土基础的'船舱分隔,联仓浇注'施工方法。
背景技术
随着人类对地下空间的利用,地下室钢筋混凝土筏板基础越来越大,200m×200m的钢筋混凝土整体筏板基础越来越多。如此大的钢筋混凝土筏板基础在设计图纸未设置后浇带和施工缝的条件下,在施工地点气候干燥、年平均气温41℃、最高气温52℃、昼夜温差最大20℃的环境中,选择合适的施工方法尤为重要,否则,将会出现以下问题:1、高温环境下大型钢筋混凝土筏板基础在没有设置后浇带和施工缝的条件下,若采取整体浇注,则有可能产生温度、收缩裂缝;同时,对施工安排上也将带来影响。2、采取'分块跳仓法',对大型钢筋混凝土筏板基础混凝土浇注与防水施工同步平行作业带来影响。
发明内容
本发明的目的就是要解决以上问题,针对超大面积整体钢筋混凝土筏板基础在高温环境下现有施工方法存在的技术问题,提供一种高温环境下大型筏基施工方法,在保证大型筏板基础在高温环境下钢筋混凝土不产生裂缝的基础上,还克服了浇筑一块预留一块的'分块跳仓'施工方法带来的防水施工和筏基混凝土浇灌的矛盾,提高了机械使用效率,缩短了工期。
本发明的技术方案是这样得以实现的:一种高温环境下大型筏基施工方法,其特点是:施工方法具体如下:
1)'船舱分隔'设计:
在重点考虑当地高温环境因素的基础上,通过计算确定筏板基础混凝土不产生施工裂缝的长度,将筏板基础分隔成小块,形成'船舱分隔',筏板基础施工缝满足设计要求及考虑的因素:
混凝土一般控制在1500-2500平方米/块;
错开塔吊基础和柱基位置;
避开独立柱基础弯起筋与相邻另一柱基基坑钢筋搭接所涉及的位置;
避开地下管道、厨房、厕所、水池集水井等管道位置;
综合考虑施工顺序考虑相邻的临时道路、安装道路;
尽量避免太窄、太长的分块,每分块四周外侧至少延长3m,便于相邻筏基独立基础弯起钢筋伸入和防水卷材焊接;
2)施工缝及防水设计:
在筏板基础施工缝的厚度中部采用凹槽型施工缝;
在素混凝土垫层2上铺一层土工布3;
在土工布3上铺一层PVC防水卷材4;
在PVC防水卷材4上抹40mm厚的1:3水泥砂浆找平层5;
在施工缝处设置橡胶止水带10;
在橡胶止水带10上铺设水平注浆管8、竖向注浆管9;
3)'联仓浇注'施工方法:
将'船舱分隔'成小块的钢筋混凝土筏板基础,在施工缝的凹槽和防水设计施工完毕后,浇筑小块混凝土,养护7天后,待混凝土的变形大部分完成后,向已浇注的'船舱分隔'成小块的筏板基础一侧或四周全面推进的方法施工,从而实现'联仓浇注'。
本发明通过其'船舱分隔'设计,施工缝及防水设计,'联仓浇注'施工方法,改进筏基混凝土'分块跳仓法'施工方法,填补超大筏基的施工方法,向已浇注的'船舱分隔'成小块的筏板基础一侧或四周全面推进的方法施工,从而实现'联仓浇注',克服了浇筑一块预留一块的'分块跳仓'施工方法,带来的防水施工和筏基混凝土浇灌的矛盾;使传统的筏基施工技术得以延伸,保证质量,缩短了工期,提高了机械使用效率,降低了成本。
附图说明
图1是本发明施工缝处设计剖面图。
图中:
1.粘土;2.素混凝土垫层;3.土工布;4.PVC卷材防水层;5.砂浆找平层;6.后浇筑混凝土;7.筏板基础下层双向钢筋;8.水平注浆管;9.竖向注浆管;10.橡胶止水带;11.筏板基础上层双向钢筋;12.先浇筑混凝土。
具体实施方式
从图1可见,本发明施工方法具体如下:
1)'船舱分隔'设计:
在重点考虑当地高温环境因素的基础上,通过计算确定筏板基础混凝土不产生施工裂缝的长度,将筏板基础分隔成小块,形成'船舱分隔',筏板基础施工缝满足设计要求及考虑的因素:
混凝土一般控制在1500-2500平方米/块;
错开塔吊基础和柱基位置;
避开独立柱基础弯起筋与相邻另一柱基基坑钢筋搭接所涉及的位置;
避开地下管道、厨房、厕所、水池集水井等管道位置;
综合考虑施工顺序考虑相邻的临时道路、安装道路;
尽量避免太窄、太长的分块,每分块四周外侧至少延长3m,便于相邻筏基独立基础弯起钢筋伸入和防水卷材焊接;
2)施工缝及防水设计:
在筏板基础施工缝的厚度中部采用凹槽型施工缝;
在素混凝土垫层2上铺一层土工布3;
在土工布3上铺一层PVC防水卷材4;
在PVC防水卷材4上抹40mm厚1:3水泥砂浆找平层5;
在施工缝处设置橡胶止水带10;
在橡胶止水带10上铺设水平注浆管8、竖向注浆管9;
将施工缝处的中间部位设置凹槽型施工缝,增加防水效果。同时为了改进防水渗漏治理功能,从防水功能出发,在防水卷材上施工缝处设置止水带,并在止水带上敷设注浆管。当施工缝处漏水时,对漏水处的分隔块处注浆管系统注入灌浆液,达到防治结合的效果;
3)'联仓浇注'施工方法:
将'船舱分隔'成小块的钢筋混凝土筏板基础,在施工缝的凹槽和防水设计施工完毕后,浇筑小块混凝土,养护7天后,待混凝土的变形大部分完成后,向已浇注的'船舱分隔'成小块的筏板基础一侧或四周全面推进的方法施工,从而实现'联仓浇注'。

Claims (1)

1、一种高温环境下大型筏基施工方法,其特征在于:施工方法具体如下:
1)'船舱分隔'设计:
在重点考虑当地高温环境因素的基础上,通过计算确定筏板基础混凝土不产生施工裂缝的长度,将筏板基础分隔成小块,形成'船舱分隔',筏板基础施工缝满足设计要求及考虑的因素:
混凝土一般控制在1500-2500平方米/块;
错开塔吊基础和柱基位置;
避开独立柱基础弯起筋与相邻另一柱基基坑钢筋搭接所涉及的位置;
避开地下管道、厨房、厕所、水池集水井等管道位置;
综合考虑施工顺序考虑相邻的临时道路、安装道路;
尽量避免太窄、太长的分块,每分块四周外侧至少延长3m,便于相邻筏基独立基础弯起钢筋伸入和防水卷材焊接;
2)施工缝及防水设计:
在筏板基础施工缝的厚度中部采用凹槽型施工缝;
在素混凝土垫层上铺一层土工布;
在土工布上铺一层PVC防水卷材;
在PVC防水卷材上抹40mm厚的1:3水泥砂浆找平层;
在施工缝处设置橡胶止水带;
在橡胶止水带上铺设水平注浆管、竖向注浆管;
3)'联仓浇注'施工方法:
将'船舱分隔'成小块的钢筋混凝土筏板基础,在施工缝的凹槽和防水设计施工完毕后,浇筑小块混凝土,养护7天后,待混凝土的变形大部分完成后,向已浇注的'船舱分隔'成小块的筏板基础一侧或四周全面推进的方法施工,从而实现'联仓浇注'。
PCT/CN2013/078991 2013-03-15 2013-07-08 高温环境下大型筏基施工方法 WO2014139252A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201310083221.5A CN103205979B (zh) 2013-03-15 2013-03-15 高温环境下大型筏基施工方法
CN201310083221.5 2013-03-15

Publications (1)

Publication Number Publication Date
WO2014139252A1 true WO2014139252A1 (zh) 2014-09-18

Family

ID=48753371

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2013/078991 WO2014139252A1 (zh) 2013-03-15 2013-07-08 高温环境下大型筏基施工方法

Country Status (3)

Country Link
CN (1) CN103205979B (zh)
MY (1) MY171194A (zh)
WO (1) WO2014139252A1 (zh)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264676A (zh) * 2014-09-25 2015-01-07 沈建东 高层建筑基础大体积混凝土施工方法
CN106120873A (zh) * 2016-07-06 2016-11-16 江苏江中集团有限公司 一种桩筏基础预铺反粘复合高分子防水卷材的施工方法
CN106592658A (zh) * 2016-11-22 2017-04-26 叶香菲 拆建房屋地基的基础施工方法
CN106869188A (zh) * 2017-04-07 2017-06-20 黄以恒 一种基础底板后浇带防渗漏水的施工结构及其施工方法
CN108867822A (zh) * 2018-08-10 2018-11-23 中建八局第二建设有限公司 一种防存水双层地漏的施工装置及其施工方法
CN109024700A (zh) * 2017-02-27 2018-12-18 中冶建工集团有限公司 一种防水混凝土配置装置及其建筑地下室外墙防水施工方法
CN110067311A (zh) * 2019-05-14 2019-07-30 长江勘测规划设计研究有限责任公司 新旧混凝土构件结合处的连接结构及方法
CN111335364A (zh) * 2020-03-06 2020-06-26 河北建设集团股份有限公司 一种钢板止水带遇混凝土外墙柱处钢筋构造的施工方法
CN112081146A (zh) * 2020-09-03 2020-12-15 江苏凯伦建材股份有限公司 一种可雨季施工的高分子自粘胶膜防水卷材施工方法
CN112177001A (zh) * 2020-09-18 2021-01-05 中国三峡建设管理有限公司 一种提高拖模或翻模浇筑大体积混凝土施工效率的方法
CN112681324A (zh) * 2020-12-16 2021-04-20 中建科技集团有限公司 一种地下超长薄壁混凝土结构的施工方法及混凝土
CN113323010A (zh) * 2021-05-17 2021-08-31 宇旺建工集团有限公司 一种内埋式塔吊基础施工工法
CN113529774A (zh) * 2021-07-19 2021-10-22 中国十九冶集团有限公司 用于大型基础钢筋安装的施工方法
CN113756371A (zh) * 2021-09-15 2021-12-07 中国二十二冶集团有限公司 防水砼水平缝处混凝土密实施工方法
CN113818468A (zh) * 2021-08-11 2021-12-21 广州地铁设计研究院股份有限公司 灵活预留落地高层建筑的地铁车辆段结构的一期施工方法
CN114059505A (zh) * 2021-12-16 2022-02-18 中国电建集团贵阳勘测设计研究院有限公司 一种水电站涌水部位灌浆施工方法及灌浆设备
CN114059654A (zh) * 2021-12-03 2022-02-18 河南沃克曼建设工程有限公司 一种污水处理站改良型aao生物池跳仓法快速施工方法
CN114525800A (zh) * 2022-02-28 2022-05-24 苏州佳固士新材料科技有限公司 一种用于地下室筏板的渗漏治理方法
CN115897589A (zh) * 2022-10-31 2023-04-04 中铁一局集团市政环保工程有限公司 一种地埋式污水处理厂防水混凝土间隔浇筑施工方法
CN116163331A (zh) * 2023-03-23 2023-05-26 中国建筑第二工程局有限公司 大厚度变截面筏板基础施工工艺
CN116815837A (zh) * 2023-08-29 2023-09-29 上海建工一建集团有限公司 软土地质超高层桩筏基础预抬施工方法
CN117822592A (zh) * 2024-03-05 2024-04-05 山东金城建设有限公司 后浇带混凝土封挡结构施工方法及后浇带混凝土封挡结构

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499498B (zh) * 2014-12-24 2016-11-23 河北省电力勘测设计研究院 一种大体积混凝土建筑的施工方法
CN104746526B (zh) * 2015-04-10 2016-06-15 天津市赛英工程技术咨询有限公司 一种带有液体管道通路的筏板基础
CN106320274A (zh) * 2016-10-27 2017-01-11 中国葛洲坝集团第工程有限公司 一种堆石坝面板水平施工缝及其施工方法
WO2018214144A1 (zh) * 2017-05-26 2018-11-29 南通八建集团有限公司 超高层住宅工程3.3m厚筏板基础施工控制方法
CN109308362B (zh) * 2017-07-28 2022-12-13 广联达科技股份有限公司 筏板后浇带的构建方法、系统及计算机装置
CN108240038B (zh) * 2018-03-15 2023-09-08 北京城建集团有限责任公司 基于多级网格式后浇带的超大平面混凝土结构及施工方法
CN109208907A (zh) * 2018-10-19 2019-01-15 中国十七冶集团有限公司 高温且温差大的条件下超长钢筋混凝土墙板隔段施工方法
CN109778917B (zh) * 2019-02-22 2024-02-09 中铁第六勘察设计院集团有限公司 一种地下工程施工冷缝防水结构及施工方法
CN115341575A (zh) * 2022-09-03 2022-11-15 锦汇建设集团有限公司 一种地下室抗裂筏板及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030013088A (ko) * 2001-08-07 2003-02-14 주식회사유신코퍼레이션 매스 콘크리트의 수화열 저감방법
JP2007039948A (ja) * 2005-08-02 2007-02-15 Canadian Home Kk 基礎施工方法及び基礎
CN101962997A (zh) * 2010-09-30 2011-02-02 天津二十冶建设有限公司 超厚基础大体积混凝土施工方法
CN102425307A (zh) * 2011-10-19 2012-04-25 江苏瑞峰建设集团有限公司 一种避免大体积混凝土裂缝形成的浇筑方法
CN102433930A (zh) * 2011-08-26 2012-05-02 中国建筑东北设计研究院有限公司 地上地下双向超长混凝土无缝设计方法
CN102653946A (zh) * 2012-05-21 2012-09-05 中国十七冶集团有限公司 钢筋混凝土筏板基础底部设置橡胶止水带防水施工方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000212971A (ja) * 1999-01-25 2000-08-02 Hitoshi Mori べた基礎用のpc礎版とpc基礎梁部材ならびにこれらを使用するべた基礎の施工方法
JP2008285808A (ja) * 2007-05-15 2008-11-27 Ksk:Kk レベリング材用の組成物及びその使用方法
CN102041809A (zh) * 2010-11-17 2011-05-04 中国核工业华兴建设有限公司 核电站核岛筏基施工方法
CN102363960A (zh) * 2011-11-23 2012-02-29 国核工程有限公司 一种核岛筏基大体积混凝土浇筑方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030013088A (ko) * 2001-08-07 2003-02-14 주식회사유신코퍼레이션 매스 콘크리트의 수화열 저감방법
JP2007039948A (ja) * 2005-08-02 2007-02-15 Canadian Home Kk 基礎施工方法及び基礎
CN101962997A (zh) * 2010-09-30 2011-02-02 天津二十冶建设有限公司 超厚基础大体积混凝土施工方法
CN102433930A (zh) * 2011-08-26 2012-05-02 中国建筑东北设计研究院有限公司 地上地下双向超长混凝土无缝设计方法
CN102425307A (zh) * 2011-10-19 2012-04-25 江苏瑞峰建设集团有限公司 一种避免大体积混凝土裂缝形成的浇筑方法
CN102653946A (zh) * 2012-05-21 2012-09-05 中国十七冶集团有限公司 钢筋混凝土筏板基础底部设置橡胶止水带防水施工方法

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264676A (zh) * 2014-09-25 2015-01-07 沈建东 高层建筑基础大体积混凝土施工方法
CN106120873A (zh) * 2016-07-06 2016-11-16 江苏江中集团有限公司 一种桩筏基础预铺反粘复合高分子防水卷材的施工方法
CN106592658A (zh) * 2016-11-22 2017-04-26 叶香菲 拆建房屋地基的基础施工方法
CN106592658B (zh) * 2016-11-22 2018-11-09 叶香菲 拆建房屋地基的基础施工方法
CN109024700A (zh) * 2017-02-27 2018-12-18 中冶建工集团有限公司 一种防水混凝土配置装置及其建筑地下室外墙防水施工方法
CN106869188A (zh) * 2017-04-07 2017-06-20 黄以恒 一种基础底板后浇带防渗漏水的施工结构及其施工方法
CN108867822A (zh) * 2018-08-10 2018-11-23 中建八局第二建设有限公司 一种防存水双层地漏的施工装置及其施工方法
CN110067311A (zh) * 2019-05-14 2019-07-30 长江勘测规划设计研究有限责任公司 新旧混凝土构件结合处的连接结构及方法
CN110067311B (zh) * 2019-05-14 2024-04-12 长江勘测规划设计研究有限责任公司 新旧混凝土构件结合处的连接结构及方法
CN111335364A (zh) * 2020-03-06 2020-06-26 河北建设集团股份有限公司 一种钢板止水带遇混凝土外墙柱处钢筋构造的施工方法
CN111335364B (zh) * 2020-03-06 2022-07-26 河北建设集团股份有限公司 一种钢板止水带遇混凝土外墙柱处钢筋构造的施工方法
CN112081146A (zh) * 2020-09-03 2020-12-15 江苏凯伦建材股份有限公司 一种可雨季施工的高分子自粘胶膜防水卷材施工方法
CN112177001A (zh) * 2020-09-18 2021-01-05 中国三峡建设管理有限公司 一种提高拖模或翻模浇筑大体积混凝土施工效率的方法
CN112681324A (zh) * 2020-12-16 2021-04-20 中建科技集团有限公司 一种地下超长薄壁混凝土结构的施工方法及混凝土
CN113323010A (zh) * 2021-05-17 2021-08-31 宇旺建工集团有限公司 一种内埋式塔吊基础施工工法
CN113529774A (zh) * 2021-07-19 2021-10-22 中国十九冶集团有限公司 用于大型基础钢筋安装的施工方法
CN113529774B (zh) * 2021-07-19 2023-02-28 中国十九冶集团有限公司 用于大型基础钢筋安装的施工方法
CN113818468A (zh) * 2021-08-11 2021-12-21 广州地铁设计研究院股份有限公司 灵活预留落地高层建筑的地铁车辆段结构的一期施工方法
CN113756371A (zh) * 2021-09-15 2021-12-07 中国二十二冶集团有限公司 防水砼水平缝处混凝土密实施工方法
CN114059654A (zh) * 2021-12-03 2022-02-18 河南沃克曼建设工程有限公司 一种污水处理站改良型aao生物池跳仓法快速施工方法
CN114059505B (zh) * 2021-12-16 2023-08-25 中国电建集团贵阳勘测设计研究院有限公司 一种水电站涌水部位灌浆施工方法及灌浆设备
CN114059505A (zh) * 2021-12-16 2022-02-18 中国电建集团贵阳勘测设计研究院有限公司 一种水电站涌水部位灌浆施工方法及灌浆设备
CN114525800A (zh) * 2022-02-28 2022-05-24 苏州佳固士新材料科技有限公司 一种用于地下室筏板的渗漏治理方法
CN115897589A (zh) * 2022-10-31 2023-04-04 中铁一局集团市政环保工程有限公司 一种地埋式污水处理厂防水混凝土间隔浇筑施工方法
CN116163331A (zh) * 2023-03-23 2023-05-26 中国建筑第二工程局有限公司 大厚度变截面筏板基础施工工艺
CN116815837A (zh) * 2023-08-29 2023-09-29 上海建工一建集团有限公司 软土地质超高层桩筏基础预抬施工方法
CN116815837B (zh) * 2023-08-29 2023-11-17 上海建工一建集团有限公司 软土地质超高层桩筏基础预抬施工方法
CN117822592A (zh) * 2024-03-05 2024-04-05 山东金城建设有限公司 后浇带混凝土封挡结构施工方法及后浇带混凝土封挡结构

Also Published As

Publication number Publication date
MY171194A (en) 2019-10-01
CN103205979A (zh) 2013-07-17
CN103205979B (zh) 2015-04-08

Similar Documents

Publication Publication Date Title
WO2014139252A1 (zh) 高温环境下大型筏基施工方法
CN105862873B (zh) 深基坑狭窄空间地下防水及外墙结构施工方法
CN110747899B (zh) 地下室防水施工方法
CN104032771B (zh) 一种地下结构增设诱导缝防裂施工方法
CN206545228U (zh) 一种带防水结构的管廊
CN202830989U (zh) 一种地下建筑结构钢筋混凝土外墙半通式诱导缝系统
CN106759420B (zh) 一种预制装配式变电站基础结构
CN110258640A (zh) 一种盖挖逆作的叠合墙体系的施工方法
CN101768908A (zh) 钢纤维混凝土地坪施工方法
CN112376610B (zh) 交叉管廊外防水施工方法
CN105350581A (zh) 一种地下室顶板沉降后浇带提前封闭构造
CN103410173A (zh) 一种地下结构外墙竖向后浇带封堵的施工方法
CN202347544U (zh) 地下室外墙后浇带超前止水施工结构
CN205077753U (zh) 屋面伸缩缝的防水结构
CN105756102A (zh) 地下连续墙与地下室外墙两墙合一的防水结构及工艺
CN212129250U (zh) 高水位基础后浇带增设收集槽施工结构
CN210766835U (zh) 一种基础梁侧立面防水结构
CN111472813A (zh) 一种超大跨度锚喷支护岩石隧道防排水体系及施工方法
CN208122041U (zh) 一种ips现浇砼剪力墙自保温体系结构系统
CN115961647A (zh) 地下室顶板后浇带超前封闭结构、施工结构及施工方法
CN206635786U (zh) 预制装配式变电站基础结构
CN109322332A (zh) 一种提前对基础及后浇带防水处理方法
CN103628506B (zh) 一种基础承台与桩头防水处施工方法
CN204645093U (zh) 地下室外墙后浇带提前处理构造
CN110331740B (zh) 一种地下工程防水施工方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13878112

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13878112

Country of ref document: EP

Kind code of ref document: A1