WO1983004274A1 - Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method - Google Patents

Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method Download PDF

Info

Publication number
WO1983004274A1
WO1983004274A1 PCT/NO1983/000020 NO8300020W WO8304274A1 WO 1983004274 A1 WO1983004274 A1 WO 1983004274A1 NO 8300020 W NO8300020 W NO 8300020W WO 8304274 A1 WO8304274 A1 WO 8304274A1
Authority
WO
WIPO (PCT)
Prior art keywords
casting
section
carriage
bridge
runners
Prior art date
Application number
PCT/NO1983/000020
Other languages
English (en)
French (fr)
Inventor
Oscar Semb
Arne Askveien Arntzen
Original Assignee
O^/Stlandske Spennbetong A-S
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by O^/Stlandske Spennbetong A-S filed Critical O^/Stlandske Spennbetong A-S
Priority to NL8320159A priority Critical patent/NL8320159A/nl
Priority to DE19833390026 priority patent/DE3390026T1/de
Priority to GB08400112A priority patent/GB2129854A/en
Publication of WO1983004274A1 publication Critical patent/WO1983004274A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Definitions

  • the present invention relates to an arrangement for the casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method, comprising a cantilever construction carriage (casting carriage) with a front jib and front and rear runners rolling on a rail track with preferably dualtraversing rails on a previously cast bridge section or bridge pier, having two rear runner units each of which comprises two runner sets co-operating with the rails on the same side of the rail track and equipped to abut the top or underside of the said rails, every rear runner unit comprising a frame to which the rear part of the casting carriage is attached.
  • Casting arrangements of the said type have been previously known, and such an arrangement is e.g. described in Patent 138855 which is the applicants property.
  • the anchoring frame between the rear end section of the casting carriage and the runner unit is made rigid and incapable of being displaced longitudinally and to the sides. Since the rear end section of the carriage is anchored to the frame it is also not possible to displace (e.g. with a view to adjustment) the end section of the carriage in the lateral direction. The required lateral adjustments must therefore be carried out direct on every one of the formwork panels.
  • the bearing frame between the rear end section of the casting carriage and the runner unit as a parallelepiped, with joints in all four corners and with the joint axes extending in the longitudinal direction of the rail track, the frame being capable of being swung sideways about its two lower joint axes.
  • the bearing frame comprises preferably two parallel supports and a horizontal crossbeam at the top, the height of the beam being variable in relation to the support.
  • the crossbeam has suspended tie-rods for attachment to the cast bridge deck so as to relieve the rear runners.
  • a tensioning device or jack adjustable in height to be fitted between the underside of the casting carriage's rear section and the cast section of the concrete bridge and for the rear tie-rods of the carriage or/and tensioning device to be adjusted in such a way that the tie-rods are stressed at least 10% above the calculated maximum load.
  • the latter embodiment has the advantage that load-dependent displacement in height of the front section of the carriage and the formwork is avoided while at the same time the tie-rods subject to tension are relieved as the load acting on the front section of the carriage increases, which is the opposite to what has been the case so far.
  • the arrangement in accordance with the invention is provided with a tensioningdevice or jack capable of being regulated in height and possibly equipped with a force measuring device, this being provided between the rear bearing frame supports under the rear section of the carriage, extending downward to about the lower ends of the runners and extendable down to the top surface of the concrete deck.
  • cantilever construction proceeds in two opposite directions from the pier and use is made of an arrangement comprising two cantilever construction carriages (casting carriages) each carrying its formwork and capable of running on rails located on a previously cast section of the bridge.
  • Each casting carriage can be subdivided into a front section comprising a jib and a rear section.
  • the arrangement also comprises a system of bars for releasable coupling of the two front sections of the carriages when the latter are at a distance from one another in the longitudinal direction facing away from one another in symmetrical fashion.
  • An arrangement of this type is described in the said Patent 138 855.
  • the system of bars comprises a stiff frame so designed that the relative position of the carriages (to be precise the front sections of the carriages) cannot be changed and that the carriages are always in line with one another.
  • Such a design is hardly efficient when it comes to casting a curving bridge.
  • the known arrangement does not enable casting along curves since the carriages are separate from one another and can move independently.
  • a further intention of the present invention consists in bringing about an arrangement enabling the casting in sections along curves - starting from a bridge pier - it being possible to adjust the relative position of the carriages following their location on the pier head.
  • the system of bars comprises two roughly level coupling frames which together with the carriages in the coupled state extend between the end sections of the carriages at a mutual distance which substantially corresponds to the distance between the traversing rails (track gauge) and link the carriages with one another in an adjustable manner, inasmuch as each coupling frame has an upper and a lower basically horizontal flange of adjustable length.
  • the flanges can be linked with one another by means of diagonal threaded tie-rods of adjustable length and they can be so designed as to be capable of telescoping into one another.
  • the advantage of the said design consists in the fact that the carriages (the front sections) can be angled in relation to one another in order to match the curvature of the bridge.
  • Another advantage consists in the fact that the same coupling frame can be used for different bridge constructions inasmuch as this can be adapted to the local conditions.
  • Fig. 1 is an elevation partly in section of a previously cast bridge section with the arrangement in accordance with the invention
  • fig. 2 is a front section of the arrangement and a section of a support bridge viewed in the direction of the arrows II-II in fig.
  • fig. 3 is an end section which on a larger scale shows detail A of fig. 1 viewed in the direction of arrow III comprising an embodiment of the invention
  • fig. 4 is an end section corresponding to fig. 3 but showing detail A viewed in the direction of arrow III with a different embodiment of the invention.
  • Fig. 5 shows an arrangement for casting bridge sections starting from a previously cast bridge pier of the kind described in the applicants' Patent 138 855
  • fig. 6 illustrates the casting method at a later stage of the work
  • fig. 7 shows an arrangement of the kind presented in figs. 5 and 6 but carried out in accordance with the invention
  • fig. 8 is a lateral section or elevation of the same arrangement as shown in fig. 7 but drawn in a larger scale.
  • Figs. 1 and 2 show a recently cast bridge section 1 which may be the top of a bridge pier and on which are placed paralleltraversing rails 2.
  • a casting carriage 3 with a front jib 4 and lower and upper runners 15 and 5 respectively, which co-operate with the traversing rails 2.
  • To the front end of jib 4 are attached supporting tie-rods 6 extending downward, to the lower ends of which are secured two lower traversing rails 7 freely extending backward, the mutual distance between which is considerably smaller than the width of the inner formwork (see fig. 2).
  • the rear section of traversing rails 7 is rollably suspended in brackets 8 with runners 9 so that the rails 7 can be advanced together with carriage 3.
  • the front section of casting carriage 3 is designated 22 and the rear section 23.
  • the traversing rails 7 support a formwork carriage 10 with inner formwork 11,12,13.
  • the carriage has runners 14 and can be displaced forward and rearward on the rails 7.
  • Fig. 2 shows that the cross-section of the bridge sections 1 is roughly box-shaped, with the side walls and the top of the box being cast between the inner formwork 11,12,13 and the outer formwork 16,17.
  • the carriageway of the bridge is designated 18.
  • the formwork has vertical sections suspended from hangers 20 and 21 respectively.
  • the -inner formwork 11,12,13 comprises a steel construction 11,12 arranged on the said formwork carriage 10 so that it can be transported along the rails 7 and displaced irrespective of the outer formwork 16,17 connected with the same carriage 3 as well as with the aid of the schematically drawn tie-rods 19.
  • Fig. 1 does not show the outer formwork.
  • Fig. 1 shows that a support 8 is provided at the front end of the last section cast with a view to supporting the rails 7. The required reinforcing work has been carried out at an earlier stage when the insides of the outer formwork and the inner formwork were free, and fig. 1 shows carriage 10 for the inner formwork advanced to such a point that it is immediately above the outer formwork 16,17 (not shown in fig. 1).
  • Fig. 3 shows detail A in figs. 1 and 2 seen from the back (or from the front).
  • the traversing rail track 2 comprises two rails 2a and 2b arranged at a distance from one another, which are secured to the previously cast bridge deck 18 with the aid of anchoring units 34 and anchor bolts 35.
  • the rear section 23 of casting carriage 3 comprises inter alia a longitudinal girder 33, a frame unit 36 and a horizontal crossbeam or end beam 30 which are rigidly linked with one another.
  • Two supports or suspended beams 28,29 are suspended, in a rotatable manner and at a distance from one another, with the aid of pivot bolts 31,32 from crossbeam 30, with their lower ends connected with trolley yokes 24,25 so as to be capable of being swung to and fro, the said trolley yokes having from the rear the appearance of an inverted U with the vertical legs 37 bearing at their lower ends the previously mentioned runners 15a,15b.
  • the distance between supports 28,29 substantially corresponds to the distance between the rails 2a, 2b.
  • the runners 15,15a normally roll along the underside of the flanges of rails 15a,15b.
  • a tie-rod 38 for attachment to bridge deck 18 hangs from the end sections of crossbeam 30.
  • the tie-rods are threaded and provided with nuts 39,40.
  • the joints 26,27,31,32 constitute a parallelepiped.
  • the supports 28,29 will be in the initial position, i.e. they will be substantially vertical as shown in fig. 4.
  • the supports 28,29 will be subject to tension owing to the weight of the front section 22.
  • the lateral position of rear section 23 may if required be fixed with the aid of devices not shown in fig. 3.
  • the formwork elements are suspended at the front of the casting carriage (roughly at 4,6) and roughly at the edge of the preceding cast bridge section.
  • the rear end section 23 of the casting carriage with crossbeam 30 is displaced sideways, with the aid of the arrangement shown in fig. 3. from the position shown in fig. 4 to the position shown in fig. 3. e.g. to the left as shown in fig. 3, the formwork panels at the front of the casting carriage will move correspondingly in the opposite direction, i.e. to the right, since in this case the casting carriage will pivot an axis located at a point between the upper runners 5 ( see fig. 1) .
  • Fig. 4 corresponds substantially to fig. 3.
  • a tensioning device 42 is suspended in a bracket 41, the said tensioning device extending in its normal, unloaded state nearly down to the anchoring plates 44 for rails 2a, 2b but which are also capable of serving as a base for the device 42.
  • the tensioning device is shown with a threaded spindle 43 and can with the aid of the latter be made to abut the concrete deck 18 so that the tensioning device is clamped between the longitudinal girder 33. i.e. the rear section 23 of the casting carriage, and the concrete deck.
  • the tie-rods 38 are located in position between crossbeam 30 pertaining to this section and bridge deck 18.
  • a tensioning jack with a force indicator as shown at 45.
  • a mechanical tensioning device 42 use may be made of a hydraulic jack with a cylinder (42) and a ram (43).
  • the tensioning device 42,43 is adjusted in height so that the longitudinal girder 33 lies roughly horizontal . Then the tie-rods 38 are tensioned so as to achieve a prestress which is about 10% higher than the effective loading. Application of this stress ensures that the extension of tie-rods 38 is taken up already when adjusting and releasing the casting carriage and not as used to be the case, when the extension came about gradually in the course of time as the casting process proceeded.
  • the advantage of the design consists in the fact that the downward deflection at the front of casting carriage 3 is considerably reduced. In addition it offers greater safety against total damage.
  • the tie-rods 38 take up all anchoring forces at the rear as the casting proceeds.
  • the arrangement 42,43 according to fig. 4 is preferably not in the same cross-sectional plane as the arrangement in accordance with fig. 3.
  • the tensioning arrangement in accordance with fig. 4 can be used with casting carriages equipped with the arrangement in accordance with fig. 3 but also with casting carriages having a rigid rear runner suspension, e.g. of the type shown in Patent 138855.
  • Figs. 5 and 6 illustrate stepwise casting of bridge sections from a previously cast pier 101 using two casting carriages of the type described above, and the figures show an arrangement as discussed in the above Patent 138855.
  • fig. 5 101 designates the top of a previously cast pier serving as an anchoring section for the bridge spans to be cast, which bear traversing rails 102.
  • On pier 101 are mounted the front sections 122 of two casting carriages 103 each with its own front jib 104.
  • the formwork carriage for the inner formwork and its lower traversing rails are not shown.
  • the two casting carriage sections 122 are linked with the aid of a rigid coupling frame 121, and a part of the rear end sections 123 of the carriages has therefore been removed in order to enable such coupling without the two carriages together taking up more space than is available on top of pier 101.
  • the first bridge sections already cast are designated 101a and 101b in fig. 6.
  • Fig. 6 shows the situation after removal of coupling frame 121.
  • Each carriage 103 has a front support leg 161, which during erection supports the front section 122 of the carriage on the previously cast section (via traversing rails 102).
  • Figs. 7 and 8 show a coupling frame 150 designed in accordance with the invention.
  • the coupling frame comprises an upper flange which consists of two flange sections 151,152 longitudinally displaceable in relation to one another and capable of being locked with the aid of bolts 155 which pass through holes 156 in the parts 151,152.
  • the lower flange comprises in corresponding manner two flange sections 153,154 designed in the same way.
  • pivot bolts 162 for fasteners 159 serving to anchor threaded tie-rods 157,158 which link the diagonally opposite corners or fasteners of the flanges with one another.
  • supports as indicated at 160 but these are strictly speaking not necessary since at the erection stage the flanges are anchored in adjacent rigid rear sections 122 of the casting carriages 103.
  • both the diagonal rods and the flanges are designed with a view to modifying the length.
  • the two coupling frames 150 When erecting the carriages for casting curved bridge sections the two coupling frames 150 are so fitted that the frame at the outer side of the bridge is longer as a result of the fact that the carriages are angled in relation to one another.
  • the two coupling frames are in plane 50 as are the side walls of the casting carriage, see fig. 2, i.e. virtually straight above the traversing rails.
  • the frame lengths and as a result the relative position of the casting carriages can be adjusted if required whereas previously it was not possible to adapt the carriages to the curvature of the bridge prior to separation from one another of the carriages, i.e.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
PCT/NO1983/000020 1982-06-01 1983-06-01 Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method WO1983004274A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
NL8320159A NL8320159A (nl) 1982-06-01 1983-06-01 Inrichting voor het volgens de vrijdragende constructiewerkwijze in secties starten van een brug van voorgespannen beton.
DE19833390026 DE3390026T1 (de) 1982-06-01 1983-06-01 Anordnung zum abschnittsweisen Gießen von Spannbetonbrücken nach dem Freiträger-Vorbauverfahren
GB08400112A GB2129854A (en) 1982-06-01 1983-06-01 Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO821820A NO150289C (no) 1982-06-01 1982-06-01 Anordning for seksjonsvis stoeping av spennarmert betongbro etter frittfrembyggmetoden
NO821820 1982-06-01

Publications (1)

Publication Number Publication Date
WO1983004274A1 true WO1983004274A1 (en) 1983-12-08

Family

ID=19886596

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/NO1983/000020 WO1983004274A1 (en) 1982-06-01 1983-06-01 Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method

Country Status (6)

Country Link
JP (1) JPS59501465A (no)
DE (1) DE3390026T1 (no)
GB (1) GB2129854A (no)
NL (1) NL8320159A (no)
NO (1) NO150289C (no)
WO (1) WO1983004274A1 (no)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007047439A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanrodnung für den Freivorbau von Brücken
DE102007047438A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanordnung für den Freivorbau von Brücken
DE102007047443A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanordnung für den Freivorbau von Brücken
CN101413251B (zh) * 2008-11-21 2011-12-28 中国葛洲坝集团股份有限公司 高墩大跨连续刚构桥0号块防裂施工方法
CN102425141A (zh) * 2011-08-25 2012-04-25 中国水电顾问集团华东勘测设计研究院 大悬臂叠合构件及其施工方法
CN102926330A (zh) * 2012-11-27 2013-02-13 吴云 一种适用于桥梁施工用挂蓝的安装方法
ES2396291A1 (es) * 2010-02-05 2013-02-20 Rubrica Ingeniería Y Arquitectura S.L. Carro en voladizo de avance sucesivo para construcción de puentes.
ES2398177A1 (es) * 2010-02-08 2013-03-14 Rubrica Ingeniería Y Arquitectura, S.L. Mejoras introducidas en un carro de avance progresivo para la construcción de puentes.
ES2424774A1 (es) * 2012-04-02 2013-10-08 Ulma C Y E, S. Coop Estructura desplazable adaptada para soportar en voladizo un encofrado de un tramo nuevo de puente
CN104963294A (zh) * 2015-07-26 2015-10-07 中铁十一局集团第一工程有限公司 一种铁路薄壁空心墩循环滴灌养护系统
CN105484166A (zh) * 2016-01-15 2016-04-13 中国铁建大桥工程局集团有限公司 一种梯型桅杆式悬拼吊机
CN106800245A (zh) * 2017-01-25 2017-06-06 中铁大桥局集团第工程有限公司 一种桥面板吊装用吊架、吊装装置及吊装方法
CN108360395A (zh) * 2018-04-27 2018-08-03 中交武汉港湾工程设计研究院有限公司 一种桥梁长大节段箱梁施工挂篮、挂篮的混凝土箱梁施工结构、挂篮的钢箱梁施工结构
CN116575359A (zh) * 2023-07-14 2023-08-11 中铁五局集团第一工程有限责任公司 一种连续梁异位挂篮及施工方法

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0514207U (ja) * 1991-07-03 1993-02-23 石川島建材工業株式会社 床版移送用エレクター
CN102605720B (zh) * 2012-03-30 2013-12-11 中铁四局集团第一工程有限公司 连续梁钢筋骨架绑吊装一体化施工装备及施工方法
CN103806375A (zh) * 2014-03-10 2014-05-21 广东省长大公路工程有限公司 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法
CN104711933A (zh) * 2015-03-26 2015-06-17 招商局重庆交通科研设计院有限公司 悬臂浇筑和劲性骨架结合的钢筋混凝土拱桥施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3937165A (en) * 1973-09-21 1976-02-10 Campenon Bernard Europe Construction of bridge decking and like structures
CH590970A5 (no) * 1974-03-12 1977-08-31 Koss Kurt
DE2555311B2 (de) * 1975-12-09 1978-03-23 Dyckerhoff & Widmann Ag, 8000 Muenchen Einrichtung zum abschnittsweisen freien Vorbau an Brückentragwerken aus Stahl- oder Spannbeton
NO138855B (no) * 1976-10-28 1978-08-14 Hoesveis A S Fremgangsmaate og anordning for seksjonsvis stoeping av spennarmert betongbro etter den saakalte frittfrembyggmetoden (konsollmetoden)

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3937165A (en) * 1973-09-21 1976-02-10 Campenon Bernard Europe Construction of bridge decking and like structures
CH590970A5 (no) * 1974-03-12 1977-08-31 Koss Kurt
DE2555311B2 (de) * 1975-12-09 1978-03-23 Dyckerhoff & Widmann Ag, 8000 Muenchen Einrichtung zum abschnittsweisen freien Vorbau an Brückentragwerken aus Stahl- oder Spannbeton
NO138855B (no) * 1976-10-28 1978-08-14 Hoesveis A S Fremgangsmaate og anordning for seksjonsvis stoeping av spennarmert betongbro etter den saakalte frittfrembyggmetoden (konsollmetoden)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007047438A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanordnung für den Freivorbau von Brücken
DE102007047443A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanordnung für den Freivorbau von Brücken
DE102007047438B4 (de) 2007-10-04 2022-11-24 Doka Gmbh Schalungsanordnung für den Freivorbau von Brücken
DE102007047439A1 (de) 2007-10-04 2009-04-16 Doka Industrie Gmbh Schalungsanrodnung für den Freivorbau von Brücken
CN101413251B (zh) * 2008-11-21 2011-12-28 中国葛洲坝集团股份有限公司 高墩大跨连续刚构桥0号块防裂施工方法
ES2396291A1 (es) * 2010-02-05 2013-02-20 Rubrica Ingeniería Y Arquitectura S.L. Carro en voladizo de avance sucesivo para construcción de puentes.
ES2398177A1 (es) * 2010-02-08 2013-03-14 Rubrica Ingeniería Y Arquitectura, S.L. Mejoras introducidas en un carro de avance progresivo para la construcción de puentes.
CN102425141B (zh) * 2011-08-25 2014-08-13 中国水电顾问集团华东勘测设计研究院 大悬臂叠合构件的施工方法
CN102425141A (zh) * 2011-08-25 2012-04-25 中国水电顾问集团华东勘测设计研究院 大悬臂叠合构件及其施工方法
ES2424774A1 (es) * 2012-04-02 2013-10-08 Ulma C Y E, S. Coop Estructura desplazable adaptada para soportar en voladizo un encofrado de un tramo nuevo de puente
CN102926330A (zh) * 2012-11-27 2013-02-13 吴云 一种适用于桥梁施工用挂蓝的安装方法
CN104963294A (zh) * 2015-07-26 2015-10-07 中铁十一局集团第一工程有限公司 一种铁路薄壁空心墩循环滴灌养护系统
CN104963294B (zh) * 2015-07-26 2016-09-07 中铁十一局集团第一工程有限公司 一种铁路薄壁空心墩循环滴灌养护系统
CN105484166A (zh) * 2016-01-15 2016-04-13 中国铁建大桥工程局集团有限公司 一种梯型桅杆式悬拼吊机
CN106800245A (zh) * 2017-01-25 2017-06-06 中铁大桥局集团第工程有限公司 一种桥面板吊装用吊架、吊装装置及吊装方法
CN108360395A (zh) * 2018-04-27 2018-08-03 中交武汉港湾工程设计研究院有限公司 一种桥梁长大节段箱梁施工挂篮、挂篮的混凝土箱梁施工结构、挂篮的钢箱梁施工结构
CN116575359A (zh) * 2023-07-14 2023-08-11 中铁五局集团第一工程有限责任公司 一种连续梁异位挂篮及施工方法
CN116575359B (zh) * 2023-07-14 2023-09-26 中铁五局集团第一工程有限责任公司 一种连续梁异位挂篮及施工方法

Also Published As

Publication number Publication date
GB2129854A (en) 1984-05-23
GB8400112D0 (en) 1984-02-08
JPS59501465A (ja) 1984-08-16
NO821820L (no) 1983-12-02
NL8320159A (nl) 1984-04-02
DE3390026T1 (de) 1984-05-17
NO150289C (no) 1984-09-19
DE3390026C2 (no) 1992-10-08
NO150289B (no) 1984-06-12
JPH0551725B2 (no) 1993-08-03

Similar Documents

Publication Publication Date Title
WO1983004274A1 (en) Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method
JP5056608B2 (ja) 片持架設用移動作業車の後退撤去方法および後退装置
US3571835A (en) Apparatus for concreting multiple section structures, particularly bridge supports of reinforced or prestressed concrete
JP3340681B2 (ja) 波形鋼板ウエブを用いた張出架設桁橋の施工方法
JPS6024247B2 (ja) 鉄筋コンクリ−トまたはプレストレスト・コンクリ−ト製の多径間橋梁構造を区分毎に片持張出架設するための装置
US3985480A (en) Apparatus for the sectional cantilever construction of bridge girder systems
WO1996005375A1 (en) Construction of large structures by robotic crane placement of modular bridge sections
CN101250854B (zh) 大跨度双线箱梁串架法施工造桥机
WO1996005375A9 (en) Construction of large structures by robotic crane placement of modular bridge sections
KR20190122925A (ko) 교량 시공용 벤트 구조물
CN102926330A (zh) 一种适用于桥梁施工用挂蓝的安装方法
JP3065916B2 (ja) 床板コンクリート打設用型枠の移動装置
JP3038154B2 (ja) 張出架設作業装置
CN212077660U (zh) 大跨度宽幅桥梁主梁菱形挂篮施工结构
CN210766433U (zh) 一种梯形挂篮结构
CN111749132B (zh) 拱梁组合式连续刚构桥下弦梁施工方法
JP4813702B2 (ja) 連続ベルトコンベアの移動装置
JP3197234B2 (ja) 床版鉄筋組立用の移動足場
CN111960267A (zh) 悬臂门架
EP3741957B1 (en) Modular support structure
JPH03275803A (ja) 高架構造物の移動構築装置
JPH05195513A (ja) アーチ橋用巻立作業車
CN218712236U (zh) 一种应用于连续梁施工的外模装置
CN212315330U (zh) 悬臂门架
CN212426786U (zh) 箱梁纵移架设施工用移梁装置

Legal Events

Date Code Title Description
AK Designated states

Designated state(s): DE GB JP NL US

RET De translation (de og part 6b)

Ref document number: 3390026

Country of ref document: DE

Date of ref document: 19840517

WWE Wipo information: entry into national phase

Ref document number: 3390026

Country of ref document: DE