CN103806375A - 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法 - Google Patents

一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法 Download PDF

Info

Publication number
CN103806375A
CN103806375A CN201410083518.6A CN201410083518A CN103806375A CN 103806375 A CN103806375 A CN 103806375A CN 201410083518 A CN201410083518 A CN 201410083518A CN 103806375 A CN103806375 A CN 103806375A
Authority
CN
China
Prior art keywords
hanging basket
concrete
cable
construction
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410083518.6A
Other languages
English (en)
Inventor
苏慈
王晓佳
郭广银
钟建锋
胡慧君
鄢生全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN201410083518.6A priority Critical patent/CN103806375A/zh
Publication of CN103806375A publication Critical patent/CN103806375A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法,其步骤为(1)挂篮前移准备;(2)挂篮下放、前移;(3)挂篮定位、提升、锚固;(4)调整立模标高;(5)安装节段斜拉索;(6)斜拉索初拉;(7)安装钢筋、预应力及模板等;(8)浇筑节段混凝土;(9)节段混凝土养护、等强;(10)节段预应力张拉;(11)索力转换;按此循环直至完成所有主梁施工浇筑;本发明不但减少劳动力、减少施工环节、缩短工程总工期,而且挂篮效率高、比重小、社会效益和经济效益明显的特点。

Description

一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法
技术领域
本发明专利涉及到一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法。 
背景技术
近年来,由于斜拉桥属于高次超静定结构,箱梁在日光照射下,箱梁顶板、底板温差引起长悬臂下坠,因此通常采用的绝对标高立模法必须在晚上进行立模作业,这就有可能打断正常的循环工序,影响施工工期。混凝土斜拉桥主梁常见的施工工艺,为了满足线形控制要求,除了需固定测量时间、明确施工荷载和同步施工以外,往往还需要在节段浇筑过程中多次调节斜拉索索力。如此增加了施工操作的复杂性,也增加了对已浇混凝土的扰动。特别是对宽幅混凝土斜拉桥全截面一次浇注时,由于面积较大,布料较广,浇筑时间相对较长。浇筑至总方量一半时,最初浇筑的混凝土基本接近初凝,若此时再进行调索,对先浇筑的箱梁底板拢动较大,容易出现大面积裂缝。加之浇筑过程中进行调索,可能会导致浇筑过程中断,容易造成混凝土堵管,影响混凝土的泵送性能,降低混凝土施工效率,对混凝土施工质量造成影响。 
发明内容
    本发明的目的在于提供一种不但减少劳动力、减少施工环节、缩短工程总工期, 而且挂篮效率高、比重小、社会效益和经济效益明显的一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法。 
为实现上述目的本发明的一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法, 该方法步骤为其步骤为(1)挂篮前移准备;(2)挂篮下放、前移;(3)挂篮定位、提升、锚固;(4)调整立模标高;(5)安装节段斜拉索;(6)斜拉索初拉;(7)安装钢筋、预应力及模板等;(8)浇筑节段混凝土;(9)节段混凝土养护、等强;(10)节段预应力张拉; 
(11)索力转换;按此循环直至完成所有主梁施工浇筑。
本发明特点 
1)设计了能够满足一期索力的长平台斜拉挂篮作为主梁悬浇施工设备
挂篮主纵梁承受斜拉索一期索力,主纵梁受力预抬。一期索力的竖向分力与待浇节段混凝土的重量相对应。主纵梁与斜拉索一起形成预紧系统共同抵抗待浇混凝土重量,在混凝土浇筑过程中斜拉索索力不进行调整,主纵梁受力的预抬值在混凝土浇筑后归零。前横梁采用桁架结构形式以提高横梁抗弯刚度,确保箱梁浇筑线形;次纵梁采用倒三角形式,设置在梁底,不占用桥面空间。且次纵梁与前横梁直接连接,并在次纵梁尾部设置次反顶千斤顶,利用杠杆原理给前横梁跨中提供支点,减小前横梁跨度,以此提高前横梁刚度。通过次纵梁尾部恒力自动千斤顶,利用挂篮刚度,自动进行浇筑过程中内力分配,有效控制箱梁线形。在主纵梁尾端设置主反顶,充分利用主纵梁自身刚度承载现浇混凝土重量,减小了浇注过程中挂篮的整体变形值。
2)在挂篮的悬臂状态观测和调整立模标高时,采用相对法立模。通过对已浇梁段连续观测,发现日照及温差变化对于相邻两节段间对应的控制点高差影响甚小。可以认为待浇梁段与挂篮锚固梁段对应控制点的高差在任何时候都是一个定值,而调整立模标高用时约1小时,而在一个小时内温差对于单个控制点的标高影响十分有限,不会对立模准确性造成影响。因而采取相对立模法能确保挂篮立模标高的准确性,且标高调整难度小,标高测量的时间不受限制。 
附图说明
图1为本发明的施工流程图。 
具体实施方案
本发明的一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法, 该方法为: 
1、挂篮前移准备:检查挂篮千斤顶等装置是否运行良好,安装挂篮前移轨道及顶推装置。
2、挂篮下放、前移:利用千斤顶解除挂篮锚固状态,并使挂篮平稳下降至行走轨道上,使挂篮重量通过两侧的C型挂钩作用在行走轨道上;而后拆除挂篮的锚固装置进而开始挂篮前移。 
3、挂篮定位、提升、锚固:通过测量对挂篮相对节段的准确位置进行放样,挂篮行走至指定位置进而定位;安装挂篮的锚固装置,利用锚固装置将挂篮提升到梁底并进行临时锚固。 
4、调整立模标高:根据监控单位提供的监控指令,通过挂篮的锚固装置及主反顶装置采用相对立模法将挂篮的标高调整到指令数值,进而对工作吊杆施加锚固力及次反顶力并安装止推装置。 
5、安装节段斜拉索:安装待浇筑节段斜拉索,塔端锚固于对应塔内齿块上;梁端通过牵引张拉杆临时锚固于挂篮弧形首对应位置处,作为挂篮的前支点。 
6、斜拉索初拉:根据监控单位提供的监控指令,将斜拉索索力调整到指令数值。 
7、安装钢筋、预应力及模板等:在挂篮上安装待浇筑节段的钢筋、预应力、预埋件以及模板等。 
8、浇筑节段混凝土:浇筑本节段混凝土,在整个节段混凝土浇筑过程中不对斜拉索索力进行调整;浇筑节段混凝土前、中、后测量挂篮观测点标高,对比分析数据,作为监控指令的参考依据。 
9、节段混凝土养护、等强:对刚浇筑的混凝土进行养生,等待混凝土强度提升;待混凝土强度满足拆模要求时便可拆除内模及侧模。 
10、节段预应力张拉:待混凝土强度满足设计要求的张拉强度时,便按设计要求进行节段内的预应力张拉作业。 
11、索力转换:利用挂篮弧形首处的张拉千斤顶,装斜拉索的锚固力转换到节段梁体齿块上,而后使牵引张拉杆与锚杯离脱、拆除止推装置。 
按此循环直至完成所有主梁施工浇筑。 

Claims (1)

1.一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法,其特征在于: 其步骤为(1)挂篮前移准备;(2)挂篮下放、前移;(3)挂篮定位、提升、锚固;(4)调整立模标高;(5)安装节段斜拉索;(6)斜拉索初拉;(7)安装钢筋、预应力及模板等;(8)浇筑节段混凝土;(9)节段混凝土养护、等强;(10)节段预应力张拉;(11)索力转换;按此循环直至完成所有主梁施工浇筑。
CN201410083518.6A 2014-03-10 2014-03-10 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法 Pending CN103806375A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410083518.6A CN103806375A (zh) 2014-03-10 2014-03-10 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410083518.6A CN103806375A (zh) 2014-03-10 2014-03-10 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法

Publications (1)

Publication Number Publication Date
CN103806375A true CN103806375A (zh) 2014-05-21

Family

ID=50703727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410083518.6A Pending CN103806375A (zh) 2014-03-10 2014-03-10 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法

Country Status (1)

Country Link
CN (1) CN103806375A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112855169A (zh) * 2021-01-05 2021-05-28 广西壮族自治区公路发展中心 一种跨越特大型溶洞的斜拉桥式隧道施工方法
CN113884056A (zh) * 2021-10-14 2022-01-04 中铁大桥局第九工程有限公司 一种大跨度连续梁挂篮悬臂现浇梁测量方法
CN114182651A (zh) * 2021-12-31 2022-03-15 中铁一局集团有限公司 一种牵索挂篮分节段拆除方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2129854A (en) * 1982-06-01 1984-05-23 Oestlandske Spennbetong Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method
CN101845795A (zh) * 2010-05-17 2010-09-29 广东省长大公路工程有限公司 一种斜拉桥施工免调索力长平台斜拉挂篮

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2129854A (en) * 1982-06-01 1984-05-23 Oestlandske Spennbetong Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method
CN101845795A (zh) * 2010-05-17 2010-09-29 广东省长大公路工程有限公司 一种斜拉桥施工免调索力长平台斜拉挂篮

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李丹: "甘竹溪大桥主梁标准段牵索挂篮施工计算与模拟分析", 《公路》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112855169A (zh) * 2021-01-05 2021-05-28 广西壮族自治区公路发展中心 一种跨越特大型溶洞的斜拉桥式隧道施工方法
CN112855169B (zh) * 2021-01-05 2023-06-16 广西壮族自治区公路发展中心 一种跨越特大型溶洞的斜拉桥式隧道施工方法
CN113884056A (zh) * 2021-10-14 2022-01-04 中铁大桥局第九工程有限公司 一种大跨度连续梁挂篮悬臂现浇梁测量方法
CN113884056B (zh) * 2021-10-14 2024-05-14 中铁大桥局第九工程有限公司 一种大跨度连续梁挂篮悬臂现浇梁测量方法
CN114182651A (zh) * 2021-12-31 2022-03-15 中铁一局集团有限公司 一种牵索挂篮分节段拆除方法
CN114182651B (zh) * 2021-12-31 2024-06-11 中铁一局集团有限公司 一种牵索挂篮分节段拆除方法

Similar Documents

Publication Publication Date Title
CN109972493A (zh) 一种先缆后梁的自锚式悬索桥设计与施工方法
CN101781878B (zh) 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法
CN103821359A (zh) 大截面混凝土梁分层浇筑施工工法
CN202627506U (zh) 现浇混凝土联系梁模板
CN108179816A (zh) 一种偏位提升滑移装置及方法
CN102094389A (zh) 分离式大节段桁架梁液压提升装置
CN102094392A (zh) 桥梁施工中的下承式挂篮及其应用
CN201506952U (zh) 无支架临时索配合挂篮建筑混凝土斜拉桥
CN104631324A (zh) 用于斜拉桥超宽翼缘主梁的前支点挂篮施工工艺
CN104480863B (zh) 斜拉桥主塔施工的钢锚梁安装定位方法
CN103437302A (zh) 一种用于单索面斜拉桥悬浇段的挂篮施工方法
CN105369736A (zh) 斜拉桥索塔体外锚固结构
CN103806375A (zh) 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法
CN109853964A (zh) 一种用于钢结构钢筋混凝土混合结构的施工方法
CN210151596U (zh) 高墩连续梁边跨现浇段及合龙段一体化施工体系
CN102094393B (zh) 钢与混凝土混合连续刚构桥钢混接头施工工艺
CN103726445B (zh) 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法
CN103184721B (zh) 预制节段拼装pc连续箱梁逐块悬挂、胶拼线形控制方法
CN109629449B (zh) 一种钢箱拱桥拱脚钢混结合段安装定位支架及对位方法
CN203113793U (zh) 一种倾斜结构大模板安装系统
RU2495184C1 (ru) Способ разборки пролетного строения моста и устройство для осуществления этого способа
CN208533370U (zh) 一种大跨度钢混组合梁架设施工的架桥机
CN110043035A (zh) 一种新型的后浇带施工支撑方法
CN102493363A (zh) 连续梁0号块快速施工方法
CN110439297A (zh) 一种用于单片大跨度钢桁架翻转提升装置及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140521