CN201506952U - 无支架临时索配合挂篮建筑混凝土斜拉桥 - Google Patents

无支架临时索配合挂篮建筑混凝土斜拉桥 Download PDF

Info

Publication number
CN201506952U
CN201506952U CN200920080251XU CN200920080251U CN201506952U CN 201506952 U CN201506952 U CN 201506952U CN 200920080251X U CN200920080251X U CN 200920080251XU CN 200920080251 U CN200920080251 U CN 200920080251U CN 201506952 U CN201506952 U CN 201506952U
Authority
CN
China
Prior art keywords
hanging basket
cable
crossbeam
main longitudinal
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN200920080251XU
Other languages
English (en)
Inventor
倪红
林伟
魏亚洲
黄金平
陈明凯
张捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Road & Bridge Engineering Co Ltd
Original Assignee
Sichuan Road & Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Road & Bridge Engineering Co Ltd filed Critical Sichuan Road & Bridge Engineering Co Ltd
Priority to CN200920080251XU priority Critical patent/CN201506952U/zh
Application granted granted Critical
Publication of CN201506952U publication Critical patent/CN201506952U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

一种无支架临时索配合挂篮建筑混凝土斜拉桥,由索塔、临时索、挂篮机构构成,挂篮机构由主纵梁和前横梁、中横梁、后横梁及次纵梁共同构成空间梁格体系,挂篮主纵梁、横梁为承重系统,索塔为空间索塔,包括塔柱、上横梁、下横梁、索塔塔柱下横梁、铰座、挂篮主纵梁尾端与铰座铰接,为挂篮机构的挂篮后支点,临时索一端固定于塔柱索导管锚固点,一端锚固在挂篮前支点,前支点和后支点、挂篮组成两端简支梁结构。本实用新型不需要搭设支架,挂篮整体安装到位,施工周期短,现浇段施工完成后,前移挂篮直接进入悬浇施工,施工进度快。挂篮安装时间短,交叉作业时间短,安全性较好。需加强挂蓝吊装安全控制。不需搭设支架材料,直接利用悬浇挂篮系统。经济效益和社会效益明显。

Description

无支架临时索配合挂篮建筑混凝土斜拉桥
技术领域:
[0001] 本实用新型涉及桥梁建筑无支架施工,具体是无支架临时索配合挂篮建筑桥梁。 背景技术:
[0002] 采用有支架施工容易出现这样的问题:(l)从工期标准看,钢管支架搭建作量大, 耗用施工时间较长,与塔柱同时施工,占用施工场地和塔吊时间长,影响塔柱施工主流程;
(2) 从安全指标看,支架搭设高空作业面大,与索塔施工交叉作业面大、时间长,安全性差;
(3) 从施工难度看,场地狭小,施工高度大,倾斜钢管支架搭设极其困难;(4)从经济指标和 施工工艺看,支架搭设需钢管、所需型钢数量大、材料、人工费高、经济效益和社会效益差; 至于施工工艺,因为是按常规方案进行,工艺成熟,也只有这一点占优,但综合看有支架施 工工期长,安全性差,施工难度大,经济型差,需要改进。
[0003] 实用新型内容:
[0004] 本实用新型的目的是克服上述缺点,提供一种施工周期短、安全性能好、减少施工
难度、提高经济效益和社会效益较明显的无支架临时索配合挂篮建筑桥梁。
[0005] 本实用新型的技术方案是这样实现的:
[0006] —种无支架临时索配合挂篮建筑混凝土斜拉桥,其特征在于由索塔、临时索、挂篮 机构构成,挂篮机构由主纵梁和前横梁、中横梁、后横梁及次纵梁共同构成空间梁格体系, 挂篮主纵梁、横梁为承重系统,索塔为空间索塔,包括塔柱、上横梁、下横梁、索塔塔柱下横 梁、铰座、挂篮主纵梁尾端与铰座铰接,为挂篮机构的后支点,临时索一端固定于塔柱索导 管锚固点,一端锚固在挂篮前支点,前支点后支点组成两端简支梁结构,使挂篮形成两端简 支梁结构,挂篮为现浇段承重机构,其上拼装钢管支架浇注0#现浇段。
[0007] 所述的主纵梁、前横梁为钢箱梁,分别制作,段与段之间采用六角扭剪型高强螺栓 连接,至少分两段或两段以上制作,中横梁、次纵梁为工字型梁,分段制作,段与段之间通过 高强螺栓连接,后横梁为万能杆件桁架,采用塔吊拼装。
[0008] 本实用新型不需要搭设支架,挂篮整体安装到位,施工周期短,现浇段施工完成 后,前移挂篮直接进入悬浇段施工,施工进度快。挂篮安装时间短,交叉作业时间短,安全性 较好。需加强挂蓝吊装安全控制。不需搭设支架材料,利用悬浇挂篮系统。经济效益和社 会效益明显。
附图说明:
[0009] 图1是本实用新型结构示意图
[0010] 图2是挂篮尾端与索塔下横梁连接结构示意图
[0011] 其图2-1是立面结构示意图
[0012] 其图2-2是平面结构示意图
[0013] 图3是挂篮前段与临时索连接构造示意图
[0014] 图3-1是图3I-I剖视结构示意图[0015] 图4是挂篮承重系统构造示意图 [0016] 图5是本实用新型实施流程框图
[0017] 图中:1、索塔;2、临时索;2. 1、锚头;2. 2、锚头连接器;3、挂篮前支点;4、挂篮后 支点;5、牵索式前支点挂篮;5. 1、次纵梁;5. 2、前横梁;5. 3、主纵梁;5. 4、后横梁;5. 5、中 横梁;6、主梁0#块件;7、索塔下横梁;8、铰座;9、挂篮主纵梁尾端;10、千斤顶;11 、张拉杆; 12、主纵梁前段;13、角度调节块;14、工具锚板;15、支撑架。
具体实施方式:
[0018] 如图1-5所示:无支架临时索配合挂篮建筑混凝土斜拉桥,由索塔1、临时索2、挂 篮机构构成,挂篮机构由主纵梁5. 3和前横梁5. 2、中横梁5. 5、后横梁5. 4及次纵梁5. 1共 同构成空间梁格体系,挂篮主纵梁5.3、横梁为承重系统,索塔为空间索塔,包括塔柱、上横 梁、下横梁、索塔塔柱下横梁7、铰座8、挂篮主纵梁尾端9与铰座8绞接,为挂篮机构的挂篮 后支点4,临时索2 —端固定于塔柱索导管锚固点, 一端锚固在挂篮前支点3,前支点3后支 点4和挂篮组成两端简支梁结构。所述的主纵梁5. 3、前横梁5. 2为钢箱梁,分别制作,段 与段之间采用六角扭剪型高强螺栓连接,至少分两段或两段以上制作,中横梁5. 5、次纵梁 5. 1为工型梁,分段制作,段与段之间通过高强螺栓连接,后横梁5. 4为万能杆件桁架,采用 塔吊拼装。其中临时索2. 1、锚头2. 2、主梁0#块件6 (6主梁0#块:是主要施工对象,本实 用新型就是为了完成它的施工)、角度调节块13、工具锚板14、支撑架15均为本实用新型需 要用的零、部、块件。

Claims (2)

  1. 一种无支架临时索配合挂篮建筑混凝土斜拉桥,其特征在于由索塔(1)、临时索(2)、挂篮机构构成,挂篮机构由主纵梁(5.3)和前横梁(5.2)、中横梁(5.5)、后横梁(5.4)及次纵梁(5.1)共同构成空间梁格体系,挂篮主纵梁(5.3)、横梁为承重系统,索塔为空间索塔,包括塔柱、上横梁、下横梁、索塔塔柱下横梁(7)、铰座(8)、挂篮主纵梁尾端(9)与铰座(8)铰接,为挂篮机构的挂篮后支点(4),临时索(2)一端固定于塔柱索导管锚固点,一端锚固在挂篮前支点(3),前支点(3)后支点(4)同挂篮组成两端简支梁结构。
  2. 2. 根据权利要求1所述的无支架临时索配合挂篮建筑桥梁,其特征是所述的主纵梁 (5. 3)、前横梁(5. 2)为钢箱梁,分别制作,段与段之间采用六角扭剪型高强螺栓连接,至少 分两段或两段以上制作,中横梁(5. 5)、次纵梁(5. 1)为工字型梁,分段制作,段与段之间通 过高强螺栓连接,后横梁(5.4)为万能杆件桁架梁,采用塔吊拼装。
CN200920080251XU 2009-04-17 2009-04-17 无支架临时索配合挂篮建筑混凝土斜拉桥 Expired - Lifetime CN201506952U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920080251XU CN201506952U (zh) 2009-04-17 2009-04-17 无支架临时索配合挂篮建筑混凝土斜拉桥

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920080251XU CN201506952U (zh) 2009-04-17 2009-04-17 无支架临时索配合挂篮建筑混凝土斜拉桥

Publications (1)

Publication Number Publication Date
CN201506952U true CN201506952U (zh) 2010-06-16

Family

ID=42468081

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920080251XU Expired - Lifetime CN201506952U (zh) 2009-04-17 2009-04-17 无支架临时索配合挂篮建筑混凝土斜拉桥

Country Status (1)

Country Link
CN (1) CN201506952U (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900020A (zh) * 2012-10-10 2013-01-30 无锡久一重工机械有限公司 索塔专用吊篮机构
CN103498426A (zh) * 2013-10-17 2014-01-08 重庆城建控股(集团)有限责任公司 超大吨位单索面前、后支点组合式挂篮体系施工工法
CN105507151A (zh) * 2015-11-20 2016-04-20 中交二公局第一工程有限公司 结形撑与混凝土塔柱匹配安装施工方法
CN105735146A (zh) * 2016-03-11 2016-07-06 广东省长大公路工程有限公司 混凝土斜拉桥的牵索挂篮异索施工方法
CN106544959A (zh) * 2016-12-12 2017-03-29 中铁大桥局集团有限公司 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法
CN111996913A (zh) * 2020-07-14 2020-11-27 中交第二航务工程局有限公司 一种新型前支点挂篮施工工艺

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900020A (zh) * 2012-10-10 2013-01-30 无锡久一重工机械有限公司 索塔专用吊篮机构
CN102900020B (zh) * 2012-10-10 2014-06-18 无锡久一重工机械有限公司 索塔专用吊篮机构
CN103498426A (zh) * 2013-10-17 2014-01-08 重庆城建控股(集团)有限责任公司 超大吨位单索面前、后支点组合式挂篮体系施工工法
CN105507151A (zh) * 2015-11-20 2016-04-20 中交二公局第一工程有限公司 结形撑与混凝土塔柱匹配安装施工方法
CN105735146A (zh) * 2016-03-11 2016-07-06 广东省长大公路工程有限公司 混凝土斜拉桥的牵索挂篮异索施工方法
CN106544959A (zh) * 2016-12-12 2017-03-29 中铁大桥局集团有限公司 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法
CN106544959B (zh) * 2016-12-12 2018-05-29 中铁大桥局集团有限公司 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法
CN111996913A (zh) * 2020-07-14 2020-11-27 中交第二航务工程局有限公司 一种新型前支点挂篮施工工艺

Similar Documents

Publication Publication Date Title
CN201506952U (zh) 无支架临时索配合挂篮建筑混凝土斜拉桥
CN101220580B (zh) 钢桁梁纵向多点连续拖拉施工方法
CN100543235C (zh) 斜拉索辅助全悬臂架设钢桁梁的方法及系统
CN203855866U (zh) 工便梁大跨度框架桥架空顶
CN103572708B (zh) 大跨度混凝土连续梁桥边跨合拢装置及方法
CN103669224A (zh) 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工方法及钢管支架
CN101173503A (zh) 三点走行单索面牵索挂篮
CN104213508A (zh) 一种利用横撑和体外索控制塔柱位移的方法
CN202626846U (zh) 桥梁边跨现浇段超高组合支架
CN201106155Y (zh) 斜拉索辅助全悬臂架设钢桁梁装置
CN104532749A (zh) 一种用于悬索桥主塔上横梁施工的支架
CN102691266A (zh) 桥梁边跨现浇段超高组合支架施工方法
CN202482776U (zh) 一种大风及高空条件下桥梁施工用腹板式造桥机
CN203296361U (zh) 大跨度钢结构跨外组对吊装平台
CN204690605U (zh) 大跨度梁桥的自行式三角桁架挂篮
CN103774543A (zh) 一种上乘式索拱组合结构桥
CN203716044U (zh) 一种下承或中承式索拱组合结构桥
CN204385629U (zh) 一种用于悬索桥主塔上横梁施工的支架
CN103993739B (zh) 造粒塔喷淋层劲性梁的施工方法
CN205444975U (zh) 一种带有观景平台的大型屋盖钢结构施工支撑系统
CN202744960U (zh) 一种大跨度钢桁梁悬索桥合龙装置
CN102535351B (zh) 大风及高空条件下桥梁施工用腹板式造桥机及施工工艺
CN110512517B (zh) 一种桥梁工程施工平台
CN204112226U (zh) 一种两孔连做节段拼装造桥机
CN102372228B (zh) 大跨度吊车梁平移安装方法

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20100616