CN103726445B - 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 - Google Patents
一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 Download PDFInfo
- Publication number
- CN103726445B CN103726445B CN201310651665.4A CN201310651665A CN103726445B CN 103726445 B CN103726445 B CN 103726445B CN 201310651665 A CN201310651665 A CN 201310651665A CN 103726445 B CN103726445 B CN 103726445B
- Authority
- CN
- China
- Prior art keywords
- construction
- hanging basket
- block
- section
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法属于桥梁施工领域。以往0#块现浇箱梁施工均采用支架法施工,在实际应用中存在的安全风险大,施工质量控制难,进度慢,成本高,人员机械使用效率降低。因此为降低施工安全风险,减少施工成本,特此将0#块段施工分为两个部分施工,第一部分(TO-1段)采用常规的支架法施工,第二部分(TO-2段)采用挂篮施工,即将用于1#块及后续块断施工的挂篮提前半个节段(即0#块的第二部分)安装、施工。这样可减少约1/2支架材料的投入,节省成本,加快施工进度,安全保证系数得以提高,为此形成一种塔梁固斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法。
Description
技术领域
本发明型涉及一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法。
背景技术
在大型斜拉桥塔梁固结段0#块的施工过程中,尤其是大型高支架现浇箱梁施工中存在较大安全、质量隐患,材料投入大,施工成本高。
以往0#块现浇箱梁施工均采用支架法施工,在实际应用中存在的安全风险大,施工质量控制难,进度慢,成本高,人员机械使用效率降低。因此为降低施工安全风险,减少施工成本,特此将0#块段施工分为两个部分施工,第一部分(TO-1段)采用大型超高钢管支架法施工,钢管支架支撑在主塔下塔柱根部,第二部分(TO-2段)采用挂篮施工,即将用于1#块及后续块段施工的挂篮提前半个节段(即0#块的第二部分(TO-2段))安装、施工。这样可减少约1/2支架材料的投入,节省成本,加快施工进度,安全保证系数得以提高,为此形成一种全新的塔梁固结段0#块支架现浇与挂篮悬浇相结合的施工方法。
发明内容
充分挂篮施工原理的基础上,在保证安全的基础上,提前将挂篮用于0#块部分节段箱梁施工,从而实现减少了0#块50%大型支架得投入量,增大了施工安全保证系数,加快了施工进度,确保了施工质量。用挂篮替代高支架施工技术,打破了常规支架法施工理念,减少了成本投入,安全系数得以提高,且加快了进度,确保了施工质量,形成了一种塔梁固结段0#块支架与挂篮悬浇相结合的施工方法。结合现有施工条件的基础上加大了安全系数,便于操作。施工中监控量测各项指标均符合要求。
一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,其特征在于:0#块在纵桥向分两次施工,先采用大型超高钢管支架体系施工箱梁底板以下的横梁及横梁上主梁部分即TO-1段,张拉横向预应力束后再在已浇筑的TO-1段顶部设置挂篮,利用挂篮作为箱梁混凝土结构的支撑体系,浇筑剩余的TO-2段,所述TO-2段为两段,分别位于TO-1段的两侧;
所述挂篮包括主梁、立杆、主桁、行走系统、锚固系统、吊挂锚点、悬吊系统、 底模板、底托吊挂系统和安全护栏;
所述主桁、立杆、主梁采用销轴锚固方式固定在行走系统上面,行走系统通过锚固系统固定在主梁混凝土梁体结构上面,底模板通过底托吊挂或悬吊系统体系锚固在主梁上,安全护栏锚固在底模板周侧边位置。
本发明型的特点是:施工方法工艺简单,结构受力明确,组装方便,安全可靠,使施工更为方便、快捷、可靠,打破了常规的0#块必须采用支架法施工的惯性思维理念,节约了大量的支架结构材料,达到了安全、高效、快速、节约目标。
使用说明书工序操作步骤为:
首先进行混凝土横梁支架的拼装施工;
进一步,进行支架线形、标高的调整;
进一步,进行横梁及先施工的那部分0#块混凝土施工;
进一步,张拉横向预应力束后,在已浇筑的0#段上进行挂篮的拼装施工;
进一步,进行挂篮线形、标高的调整;
进一步,安装精确调整后,即可锁定挂篮固定装置,确保安全牢固固结在0#块首半节段梁体上;
进一步,进行钢筋、预应力束安装施工;
进一步,进行0#块第二部分混凝土浇筑施工;
进一步,混凝土强度符合标准要求后,解除挂篮锁定装置,进行挂篮的前移,并拼装挂篮剩余体系,随后开始其它标准节段梁体的施工;
进一步,直至挂篮施工全部完成、大桥合拢。
所述的一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,其特征是:所述斜拉桥索塔施工中将塔梁固结0#块主梁分为两个部分施工,前半部分(TO-1段)采用支架法施工,后半部分(TO-2段)采用挂篮悬浇施工,即在已完成的0#块前半部分梁体作为挂篮的拼装及锚固平台,随后利用挂篮作为箱梁混凝土结构的支撑体系,进行0#块后半部分梁体的结构施工。
利用本发明型的塔梁固结0#块支架现浇与挂篮悬浇相结合的施工方法,具有如下优点:
一、采用支架与挂篮相结合进行0#块节段的施工,大幅度减少了0#块高支架系统的用量,缩短了施工周期,提高了安全系数,降低了安全风险,并为后续挂篮进行标准节段施工提供了便利条件,且使复杂工序更具简单化。
二、、整体加快了12%的施工进度。
三、降低了约16%的施工成本。
附图说明
图1主梁0#块示意图一
图2主梁0#块示意图一
图3顺桥向0#块挂篮安装支撑结构图
图4顺桥向0#块挂篮锚固及模板体系图
图5横桥向0#块挂篮支架结构受力及模板系统图
图60#块挂篮主桁架平面图
图中1——主梁,2——立杆,3——主桁,4——行走系统,5——锚固系统,6——吊挂锚点,7——悬吊系统,8——底模板,9——底托吊挂系统,10——安全护栏,11——液压电气设备,12——横梁。
具体实施方式
其技术内容如下:
一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,挂篮包括主梁1、立杆2、主桁3、行走系统4、锚固系统5、吊挂锚点6、悬吊系统7、底模板8、底托吊挂系统9、安全护栏10、液压电气设备11、横梁12在所述主桁、立杆、主梁采用销轴锚固方式固定在行走系统(轨道)上面,行走系统通过锚固系统固定在主梁混凝土梁体结构上面,底模板通过底托吊挂、悬吊、吊挂锚固系统体系锚固在主梁上,安全防护锚固在底模板周侧边位置。
下面结合附图具体说明:
如图1所示,本发明型塔梁固结0#块支架现浇与挂篮悬浇相结合施工方法,具体施工流程步序为:
首先进行混凝土横梁支架的拼装施工;
进一步,进行支架线形、标高的调整;
进一步,进行横梁及先施工的那部分0#块混凝土施工;
进一步,张拉横向预应力束后,在已浇筑的0#段上进行挂篮的拼装施工;
进一步,进行挂篮线形、标高的调整;
进一步,安装精确调整后,即可锁定挂篮固定装置,确保安全牢固固结在0#块首半节段梁体上;
进一步,进行钢筋、预应力束安装施工;
进一步,进行0#块第二部分混凝土浇筑施工;
进一步,混凝土强度符合标准要求后,解除挂篮锁定装置,进行挂篮的前移,并拼装挂篮剩余体系,随后开始其它标准节段梁体的施工;
进一步,直至挂篮施工全部完成、大桥合拢。
施工工艺流程:
一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法工艺流程如下:
1、混凝土横梁支架的拼装施工;
2、进行支架线形、标高的调整;
3、进行横梁及先施工的那部分0#块混凝土施工;
4、张拉横向预应力束后,在已浇筑的0#段上进行挂篮的拼装施工;
5、进行挂篮线形、标高的调整;
6、安装精确调整后,即可锁定挂篮固定装置,确保安全牢固固结在0#块首半节段梁体上;
7、进行钢筋、预应力束安装施工;
8、进行0#块第二部分混凝土浇筑施工;
9、混凝土强度符合标准要求后,解除挂篮锁定装置,进行挂篮的前移,并拼装挂篮剩余体系,随后开始其它标准节段梁体的施工;
10、直至挂篮施工全部完成、大桥合拢。以及挂篮的安全拆除。
使用本发明型一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,要注意严格控制施工荷载和均布荷载,尽量避免较大偏载现象,以确保挂篮设施安全。
以上本发明型一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,适用于大型结构桥梁0#块部分现浇混凝土箱梁施工,应用广泛,节约施工。
Claims (1)
1.一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法,其特征在于:0#块在纵桥向分两次施工,先采用大型超高钢管支架体系施工箱梁底板以下的横梁及横梁上主梁部分即TO-1段,张拉横向预应力束后再在已浇筑的TO-1段顶部设置挂篮,利用挂篮作为箱梁混凝土结构的支撑体系,浇筑剩余的TO-2段,所述TO-2段为两段,分别位于TO-1段的两侧;
所述挂篮包括主梁、立杆、主桁、行走系统、锚固系统、吊挂锚点、悬吊系统、底模板、底托吊挂系统和安全护栏;
所述主桁、立杆、主梁采用销轴锚固方式固定在行走系统上面,行走系统通过锚固系统固定在主梁混凝土梁体结构上面,底模板通过底托吊挂或悬吊系统体系锚固在主梁上,安全护栏锚固在底模板周侧边位置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310651665.4A CN103726445B (zh) | 2013-12-05 | 2013-12-05 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310651665.4A CN103726445B (zh) | 2013-12-05 | 2013-12-05 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103726445A CN103726445A (zh) | 2014-04-16 |
CN103726445B true CN103726445B (zh) | 2015-09-09 |
Family
ID=50450716
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310651665.4A Expired - Fee Related CN103726445B (zh) | 2013-12-05 | 2013-12-05 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103726445B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105069193B (zh) * | 2015-07-20 | 2020-04-07 | 南宁市政工程集团有限公司 | 有限元分析软件配合三角形挂篮施工工法 |
CN106149566A (zh) * | 2016-08-17 | 2016-11-23 | 王文龙 | 轨索牵引支承启闭系统 |
CN107386131A (zh) * | 2017-07-26 | 2017-11-24 | 中交公局第二工程有限公司 | 一种带底托梁的宽幅箱梁挂篮施工装置 |
CN108867345B (zh) * | 2018-09-11 | 2023-12-29 | 中建五局土木工程有限公司 | 一种节省城市桥梁下空间的钢桥梁隐形盖梁结构及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101446076A (zh) * | 2008-12-29 | 2009-06-03 | 中铁八局集团第一工程有限公司 | 一种塔梁固结斜拉桥长悬臂0#块现浇支架及其搭建方法 |
CN102330414A (zh) * | 2011-08-09 | 2012-01-25 | 中铁十二局集团第二工程有限公司 | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 |
CN103132460A (zh) * | 2011-11-28 | 2013-06-05 | 上海市基础工程有限公司 | 悬臂浇筑梁钢管混凝土临时固结系统 |
CN103243658A (zh) * | 2013-05-16 | 2013-08-14 | 中交路桥华南工程有限公司 | 斜拉桥牵索挂篮及其组拼方法 |
-
2013
- 2013-12-05 CN CN201310651665.4A patent/CN103726445B/zh not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101446076A (zh) * | 2008-12-29 | 2009-06-03 | 中铁八局集团第一工程有限公司 | 一种塔梁固结斜拉桥长悬臂0#块现浇支架及其搭建方法 |
CN102330414A (zh) * | 2011-08-09 | 2012-01-25 | 中铁十二局集团第二工程有限公司 | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 |
CN103132460A (zh) * | 2011-11-28 | 2013-06-05 | 上海市基础工程有限公司 | 悬臂浇筑梁钢管混凝土临时固结系统 |
CN103243658A (zh) * | 2013-05-16 | 2013-08-14 | 中交路桥华南工程有限公司 | 斜拉桥牵索挂篮及其组拼方法 |
Non-Patent Citations (1)
Title |
---|
矮塔斜拉桥塔梁固结施工技术;邵联银,杨卫红;《黑龙江交通科技》;20130131(第1期);全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN103726445A (zh) | 2014-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106702910B (zh) | 一种双塔双索面矮塔斜拉桥的主梁施工工艺 | |
CN103898836B (zh) | 斜拉桥h型索塔高上横梁钢斜腿预应力支架施工方法 | |
CN103726445B (zh) | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 | |
CN104213508B (zh) | 一种利用横撑和体外索控制塔柱位移的方法 | |
CN105839536A (zh) | 一种斜拉桥索塔的施工方法 | |
CN101220580A (zh) | 钢桁梁纵向多点连续拖拉施工方法 | |
CN103741601A (zh) | 一种塔、梁以及索同步成桥工艺 | |
CN103437299A (zh) | 大跨t构单墩一次转体的施工方法 | |
CN201506952U (zh) | 无支架临时索配合挂篮建筑混凝土斜拉桥 | |
CN103774560B (zh) | 悬挂式现浇模板弯桥施工工法 | |
CN102154990B (zh) | 一种边跨悬吊-中跨斜拉三塔自锚式组合索桥的架设方法 | |
CN103184721B (zh) | 预制节段拼装pc连续箱梁逐块悬挂、胶拼线形控制方法 | |
CN110080529B (zh) | 一种钢筋笼内安装钢柱的施工方法 | |
CN106320192B (zh) | 一种用于大跨径混凝土连续梁桥的梁段置换加固方法 | |
CN103993739B (zh) | 造粒塔喷淋层劲性梁的施工方法 | |
CN107130521B (zh) | 一种深坑崖壁段大截面梁贝雷支架吊模施工方法 | |
CN102493366A (zh) | 一种非对称拆除斜拉桥的方法 | |
CN104453228A (zh) | 一种大跨度超大截面钢板墙梁施工方法 | |
CN205557349U (zh) | 一种吊杆更换装置 | |
CN109487696B (zh) | 一种钢筋混凝土提篮拱桥的卸架方法和装置 | |
CN203729211U (zh) | 悬挂式弯桥面板现浇模板 | |
CN103758347A (zh) | 大跨度钢筋混凝土梁板结构后浇带支撑托换施工方法 | |
CN103806375A (zh) | 一种混凝土斜拉桥主梁施工浇筑过程免调索力施工方法 | |
RU2506367C2 (ru) | Способ разборки т-образной рамы пролетного строения моста и монтажная балка для осуществления этого способа | |
CN102493368B (zh) | 一种拆除斜拉桥预应力刚性斜拉杆的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150909 Termination date: 20191205 |
|
CF01 | Termination of patent right due to non-payment of annual fee |