CN104453228A - 一种大跨度超大截面钢板墙梁施工方法 - Google Patents
一种大跨度超大截面钢板墙梁施工方法 Download PDFInfo
- Publication number
- CN104453228A CN104453228A CN201410545193.9A CN201410545193A CN104453228A CN 104453228 A CN104453228 A CN 104453228A CN 201410545193 A CN201410545193 A CN 201410545193A CN 104453228 A CN104453228 A CN 104453228A
- Authority
- CN
- China
- Prior art keywords
- steel plate
- steel
- plate wall
- wall beam
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种大跨度超大截面钢板墙梁施工方法,该方法是采用分段吊装的方式,依次吊装钢板墙梁各段H型钢,架设于两侧型钢柱及临时支撑胎架上;悬空区域无法进行临时支撑,故采用钢拉杆构件拉结悬空开间的H型钢;钢板墙梁外包箍筋采用两根U形钢筋对抱焊接的形式;浇筑自密实混凝土完成钢板墙梁施工。该方法采用分段吊装技术、双U形钢筋对抱焊接技术、钢拉杆临时固定技术,有效地解决了钢梁吊装、钢筋绑扎、模板支设、混凝土浇筑等难题。本发明具有施工可靠、安全性高、成型效果好、综合成本低等诸多优点,很好地解决了大跨度超大截面钢板墙梁的施工难题,取得了良好的经济效益和社会效益。
Description
技术领域
本发明涉及一种大跨度超大截面钢板墙梁施工方法,属于建筑工程中大跨度带悬空区域钢板墙梁钢梁吊装及钢筋混凝土施工的技术领域。
背景技术
在建筑工程施工中,为了保证某层楼层的大开间要求,需设置大跨度超大截面转换梁结构,以满足其建筑功能要求。目前,在施工时大跨度梁所采用的结构通常有钢结构桁架、预应力混凝土等,但前者无法满足转换梁受力要求,后者在梁跨度截面较大的情况下施工较为困难,且成本较高。劲性混凝土梁同样可满足大跨度梁的受力及施工要求,但在梁下悬空或无有效支撑面的情况下尚无较为理想的施工方式。
发明内容
本发明的目的在于提供一种大跨度超大截面钢板墙梁施工方法,以解决建筑施工过程中大跨度超大截面钢板墙梁钢梁吊装及钢筋混凝土施工的难题,确保施工安全和施工质量,从而克服现有技术的不足。
本发明采用的技术方案如下:
一种大跨度超大截面钢板墙梁施工方法,采用分段吊装的方式,依次吊装钢板墙梁各段H型钢,架设于两侧型钢柱及临时支撑胎架上;悬空区域无法进行临时支撑,故采用钢拉杆构件拉结悬空开间的H型钢;钢板墙梁外包箍筋采用两根U形钢筋对抱焊接的形式;浇筑自密实混凝土完成钢板墙梁施工;所述临时支撑胎架为独立焊接H型钢,下端焊接自带螺栓孔洞的钢板及加劲板,上端同钢板墙梁连接;所述钢拉杆构件利用H型钢作为主立杆,下端同已安装钢板墙梁焊接;主立杆两侧各焊接一根H型钢作为拉杆,两根拉杆另一头分别同已安装钢板墙梁及悬空区域内钢板墙梁焊接。
所述外包箍筋采用两根U形钢筋上下连接(同一截面接头率≤50%),另鉴于箍筋直径较大,采用搭接连接方式钢筋耗量较大,故采用单面焊形式,焊缝长度≥10d。
所述混凝土浇筑需采取先浇筑半边,待梁底部邻边混凝土透过后再浇筑邻边的方式。
与现有技术相比,本发明采用分段吊装技术、双U形钢筋对抱焊接技术、钢拉杆临时固定技术,有效地解决了钢梁吊装、钢筋绑扎、模板支设、混凝土浇筑等难题,确保施工安全和施工质量。本发明经在贵阳花果园项目办公一号楼的施工中应用检验,证明本发明具有施工可靠、安全性高、成型效果好、综合成本低等诸多优点,很好地解决了大跨度超大截面钢板墙梁的施工难题,取得了良好的经济效益和社会效益。
附图说明
图1是本发明的钢板墙梁吊装示意图;
图2是胎架示意图;
图3是钢拉杆示意图;
图4是箍筋对抱焊接示意图
附图中的标号为:1-胎架,2-钢柱牛腿,3-主体部分钢板墙梁,4-承台钢柱,5-桩基钢柱,6-钢马凳,7-基础部分钢板墙梁,8-主体部分柱后钢梁,9-桩基钢柱处钢梁,10-钢拉杆,11-悬空区域中部钢梁,12- 主支撑,13-加劲板,14-底部钢板,15-加劲板,16-立杆,17-拉杆,18-各段钢板墙梁,19-U形钢筋。
具体实施方式
下面结合附图对本发明作进一步的详细说明,但不作为对本发明的任何限制。
参见附图,一种大跨度超大截面钢板墙梁施工方法,采用分段吊装的方式,依次吊装钢板墙梁各段H型钢,架设于两侧型钢柱及临时支撑胎架上;悬空区域无法进行临时支撑,故采用钢拉杆构件拉结悬空开间的H型钢;钢板墙梁外包箍筋采用两根U形钢筋对抱焊接的形式;浇筑自密实混凝土完成钢板墙梁施工;所述临时支撑胎架为独立焊接H型钢,下端焊接自带螺栓孔洞的钢板及加劲板,上端同钢板墙梁连接;所述钢拉杆构件利用H型钢作为主立杆,下端同已安装钢板墙梁焊接;主立杆两侧各焊接一根H型钢作为拉杆,两根拉杆另一头分别同已安装钢板墙梁及悬空区域内钢板墙梁焊接,外包箍筋采用两根U形钢筋上下连接(同一截面接头率≤50%),另鉴于箍筋直径较大,采用搭接连接方式钢筋耗量较大,故采用单面焊形式,焊缝长度≥10d,混凝土浇筑需采取先浇筑半边,待梁底部邻边混凝土透过后再浇筑邻边的方式。
实施例
本例中各部件的规格如下:
钢马凳6采用12根110x12角钢组装焊接而成,由于基础场地场平不平整,具体钢马凳长度以现场实际为准进行制作;钢拉杆10由立杆16及拉杆17焊接而成,立杆16为1200×400×25×40mm H型钢,拉杆17为600×300×20×20mm H型钢;胎架1由主支撑12、底部钢板14、加劲板13及加劲板15焊接而成,主支撑12为H600*300*20*20工字钢梁,加劲板13为100(220)*350*20mm钢板,加劲板15为200*220*20mm钢板,底部钢板规格为1000*1000*20mm。
具体实施时,可以如图1-图4所示,按以下步骤实施:
1、主体部分钢板墙梁安装
下层混凝土楼板达到强度,开始安装转换梁独立H型钢支撑胎架1,需控制胎架1安装位置精度,保证其与两侧钢柱牛腿2在同一轴线上,安装偏差≤5mm,以保证主体部分钢板墙梁3安装精度。
采用起重设备完成各段主体部分钢板墙梁3的吊装工作,安装过程中先进行临时连接,同时配合搭设缆风绳进行稳定,之后运用全站仪或水准仪进行测量校正,合格后开始下一段钢板墙梁与牛腿2或前段钢板墙梁的焊接工作。主体部分钢板墙梁3安装焊接工作之后,开始胎架1的卸载和主体部分钢板墙梁3的探伤工作。
2、基础部分钢板墙梁安装
安装完成承台钢柱4及桩基钢柱5,并视现场平整情况,可在基础部分钢梁分段连接处安装钢马凳6,调整好基础部分钢板墙梁7标高。采用分段吊装的方式进行基础部分钢板墙梁7安装。
3、悬空区域钢板墙梁安装
使用起重设备安装主体部分柱后钢梁8及桩基钢柱处钢梁9,校正合格后安装钢拉杆10进行固定,钢拉杆10两端对称拉设,钢拉杆10与钢板墙梁(7、9、8、3)焊接连接。
悬空区域中部钢梁11安装过程中,先将其同主体部分柱后钢梁8及桩基钢柱处钢梁9进行临时连接,校正合格后用连接板连接。安装完成后再进行校正(校正误差≤5mm)及探伤工序。
4、钢马凳及钢拉杆拆除
各段钢板墙梁探伤合格后,进行钢马凳6及钢拉杆10的拆除,基础区域及悬空区域转换梁安装施工完毕。
5、模板支设及钢筋绑扎
转换钢梁安装完毕后,支设满堂架系统进行模板支撑。
梁板模板支设完毕后进行钢筋绑扎工序。转换梁截面尺寸较大,现场钢筋长度无法满足箍筋下料长度要求,故需变换箍筋形式,采用两根U形钢筋上下连接(同一截面接头率≤50%);另鉴于箍筋直径较大,采用搭接连接方式钢筋耗量较大,故采用单面焊形式,焊缝长度≥10d。
6、浇筑混凝土
钢板墙梁截面面积较大,钢筋密集,混凝土浇筑存在较大难度,需从施工工艺进行控制,并采用自密实混凝土浇筑,免去振动棒无法插入及振捣不实带来的质量隐患。因钢筋密集,为防止梁底部排气不通畅导致浇筑有空心情况,浇筑需采取半边先浇筑,待梁底部邻边混凝土透过后再浇筑邻边,并指派专人进行两侧模板敲打,保证混凝土成型质量。
Claims (3)
1.一种大跨度超大截面钢板墙梁施工方法,其特征在于:采用分段吊装的方式,依次吊装钢板墙梁各段H型钢,架设于两侧型钢柱及临时支撑胎架上;悬空区域无法进行临时支撑,故采用钢拉杆构件拉结悬空开间的H型钢;钢板墙梁外包箍筋采用两根U形钢筋对抱焊接的形式;浇筑自密实混凝土完成钢板墙梁施工;所述临时支撑胎架为独立焊接H型钢,下端焊接自带螺栓孔洞的钢板及加劲板,上端同钢板墙梁连接;所述钢拉杆构件利用H型钢作为主立杆,下端同已安装钢板墙梁焊接;主立杆两侧各焊接一根H型钢作为拉杆,两根拉杆另一头分别同已安装钢板墙梁及悬空区域内钢板墙梁焊接。
2.根据权利要求1所述施工方法,其特征在于:所述外包箍筋采用两根U形钢筋上下连接(同一截面接头率≤50%),另鉴于箍筋直径较大,采用搭接连接方式钢筋耗量较大,故采用单面焊形式,焊缝长度≥10d。
3.根据权利要求1所述施工方法,其特征在于:所述混凝土浇筑需采取先浇筑半边,待梁底部邻边混凝土透过后再浇筑邻边的方式。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410545193.9A CN104453228A (zh) | 2014-10-15 | 2014-10-15 | 一种大跨度超大截面钢板墙梁施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410545193.9A CN104453228A (zh) | 2014-10-15 | 2014-10-15 | 一种大跨度超大截面钢板墙梁施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104453228A true CN104453228A (zh) | 2015-03-25 |
Family
ID=52899917
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410545193.9A Pending CN104453228A (zh) | 2014-10-15 | 2014-10-15 | 一种大跨度超大截面钢板墙梁施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104453228A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105040991A (zh) * | 2015-07-03 | 2015-11-11 | 中国建筑第八工程局有限公司 | 大跨度钢结构分段吊装的支撑结构及支撑方法 |
CN110040632A (zh) * | 2019-04-01 | 2019-07-23 | 杭州通达集团有限公司 | 一种大跨度型钢梁的分段吊装施工方法 |
CN111794521A (zh) * | 2020-06-11 | 2020-10-20 | 中国华冶科工集团有限公司 | 屈曲约束支撑埋件部位梁钢筋安装方法 |
CN114016757A (zh) * | 2021-10-21 | 2022-02-08 | 广东二十冶建设有限公司 | 一种钢板剪力墙现场拼装焊接的施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008255636A (ja) * | 2007-04-04 | 2008-10-23 | Kajima Corp | Rc大梁の施工方法 |
CN102155050A (zh) * | 2011-03-28 | 2011-08-17 | 广州市建筑集团有限公司 | 型钢混凝土梁与型钢柱的搭接方法及搭接装置 |
CN102363979A (zh) * | 2011-11-15 | 2012-02-29 | 福州大学 | 一种通过角钢连接的高延性钢结构梁柱节点及其施工方法 |
-
2014
- 2014-10-15 CN CN201410545193.9A patent/CN104453228A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008255636A (ja) * | 2007-04-04 | 2008-10-23 | Kajima Corp | Rc大梁の施工方法 |
CN102155050A (zh) * | 2011-03-28 | 2011-08-17 | 广州市建筑集团有限公司 | 型钢混凝土梁与型钢柱的搭接方法及搭接装置 |
CN102363979A (zh) * | 2011-11-15 | 2012-02-29 | 福州大学 | 一种通过角钢连接的高延性钢结构梁柱节点及其施工方法 |
Non-Patent Citations (1)
Title |
---|
罗宗礼等: "大跨度超大截面钢板墙梁施工技术", 《建筑》, no. 23, 31 December 2013 (2013-12-31), pages 68 - 70 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105040991A (zh) * | 2015-07-03 | 2015-11-11 | 中国建筑第八工程局有限公司 | 大跨度钢结构分段吊装的支撑结构及支撑方法 |
CN110040632A (zh) * | 2019-04-01 | 2019-07-23 | 杭州通达集团有限公司 | 一种大跨度型钢梁的分段吊装施工方法 |
CN111794521A (zh) * | 2020-06-11 | 2020-10-20 | 中国华冶科工集团有限公司 | 屈曲约束支撑埋件部位梁钢筋安装方法 |
CN114016757A (zh) * | 2021-10-21 | 2022-02-08 | 广东二十冶建设有限公司 | 一种钢板剪力墙现场拼装焊接的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9016025B2 (en) | Constructing method for concrete cylinder of construction steel bar of high-rise steel structure | |
CN103741601B (zh) | 一种塔、梁以及索同步成桥工艺 | |
CN106906955B (zh) | 一种剪力墙整体预制钢筋网结构及其施工方法 | |
CN103850363B (zh) | 预制通孔装配式钢筋混凝土剪力墙的施工方法 | |
CN204098463U (zh) | 悬挑脚手架 | |
CN202227476U (zh) | 一种高空大跨度悬挑连廊型钢混凝土结构 | |
CN103410320B (zh) | 圆筒仓柔性平台双筒连滑施工方法 | |
CN102444203A (zh) | 一种高空大跨度悬挑连廊型钢混凝土结构及施工方法 | |
CN101538896A (zh) | 高层建筑之高空悬挑结构的施工工法 | |
CN102535845A (zh) | 一种连廊结构承重架的施工方法 | |
CN104480922B (zh) | 空间桁架支模系统及其施工方法 | |
JP2008274586A (ja) | 柱頭部の施工方法 | |
CN104060542B (zh) | 组合梁斜拉桥横桥向预应力施加装置及其施加方法 | |
US20170275901A1 (en) | Construction process of structures with empty segments and construction system of structures with empty segments | |
CN104453228A (zh) | 一种大跨度超大截面钢板墙梁施工方法 | |
CN105525753A (zh) | 一种构造柱与主体结构同时施工的方法及结构 | |
CN111455837B (zh) | 一种薄壁空心墩浇筑连接结构及其施工方法 | |
CN105463997A (zh) | 一种节段梁的架设方法 | |
CN103194982B (zh) | 桥梁边跨现浇段短悬臂支架施工方法 | |
CN108316150B (zh) | 斜拉桥主塔及钢锚梁的施工系统和施工方法 | |
CN102777044B (zh) | 尿素造粒塔钢结构喷淋层吊装方法 | |
CN103993739B (zh) | 造粒塔喷淋层劲性梁的施工方法 | |
CN102691267A (zh) | 一种外置整体操作平台高墩施工方法 | |
CN109267489B (zh) | 一种斜拉桥索塔锚固区施工方法 | |
CN109812001A (zh) | 一种超高层双层工字钢悬挑支撑体系的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150325 |
|
RJ01 | Rejection of invention patent application after publication |