CN102330414A - 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 - Google Patents
大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 Download PDFInfo
- Publication number
- CN102330414A CN102330414A CN201110227133A CN201110227133A CN102330414A CN 102330414 A CN102330414 A CN 102330414A CN 201110227133 A CN201110227133 A CN 201110227133A CN 201110227133 A CN201110227133 A CN 201110227133A CN 102330414 A CN102330414 A CN 102330414A
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- cast
- place
- construction
- bed die
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 52
- 239000000725 suspension Substances 0.000 claims abstract description 16
- 238000005266 casting Methods 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 claims description 4
- 230000003014 reinforcing Effects 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 241000893018 Armeria Species 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000005086 pumping Methods 0.000 description 2
- 210000001367 Arteries Anatomy 0.000 description 1
- 210000001503 Joints Anatomy 0.000 description 1
- 230000006399 behavior Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000001360 synchronised Effects 0.000 description 1
Abstract
本发明涉及跨越铁路、公路、市政、人员密集区及施工地形陡峭的大跨连续刚构梁施工,具体为一种大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法。本发明解决了现有大跨连续刚构梁边跨现浇梁段在跨越铁路、公路、市政、人员密集区及施工地形陡峭的地方施工时因支架搭设困难、行车干扰大、安全风险大导致施工周期长、成本高以及给周围环境带来不便的问题。大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法由如下步骤实现:施工1#、2#现浇段;解除内外滑移梁吊点,将挂篮主构架、挂篮底模整体后移;安装3#现浇段底模;前移挂篮主构架至2#现浇段施工3#现浇段。本发明所述的施工方法操作简单,广泛适用于大跨连续刚构梁的边跨现浇梁段施工。
Description
大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
技术领域
[0001] 本发明涉及跨越铁路、公路、市政、人员密集区及施工地形陡峭的大跨连续刚构梁施工,具体为一种大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法。
背景技术
[0002] 在跨越铁路、公路、市政、人员密集区及施工地形陡峭的桥梁悬臂刚构施工领域, 尤其是高墩大跨连续刚构梁施工,边跨现浇梁段较长;目前采用的方法是膺架法和托架法, 即施工时必须搭设支架或托架来支撑。膺架法存在如下问题:⑴过渡墩处(连续刚构方向) 需要搭设现浇支架,而在人员密集区或交通要道会侵占道路、影响交通,从而给周围环境带来不便;⑵在地势陡峭或软土地基上施工时不利于膺架基础的平整和处理,且费用较高; ⑶对于超过50m以上的膺架,其整体承载能力、稳定性要求更高,所以经济成本急增;⑷膺架法施工需进行支架预压,施工周期长,存在较大安全风险。而托架法存在如下问题:⑴托架法施工为防止过渡墩偏压承受巨大的剪应力,在浇筑现浇段混凝土时,边浇筑混凝土边在墩身的另一侧加配重;配重的施加与混凝土浇筑重量同步,施工中配重的吊装比较繁琐, 且速度缓慢;⑵混凝土浇筑一般采用泵送混凝土,速度较快,而配重吊装采用塔吊速度较慢,在配重时难以与混凝土浇筑保持同步,需混凝土暂停泵送,这也极易造成堵管,延长现浇段浇筑时间;⑶在边跨合龙后需拆除配重,由于配重的添加和拆除,耗费大量的机具、人力、物力,施工成本大大增加;⑷由于受过渡墩结构、托架变形的限制,采用托架法施工现浇段一般不超过細,对于超过細的现浇段只能改用其它方法施工。综上所述,上述两种常规施工方法均不适合在跨越铁路、公路、市政、人员密集区及施工地形陡峭的地方施工,会出现支架搭设困难、行车干扰大以及安全风险大等问题。
发明内容
[0003] 本发明为了解决现有大跨连续刚构梁边跨现浇梁段在跨越铁路、公路、市政、人员密集区及施工地形陡峭的地方施工时因支架搭设困难、行车干扰大、安全风险大导致施工周期长、成本高以及给周围环境带来不便的问题,提供了一种大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法。
[0004] 本发明是采用如下技术方案实现的:大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法,由如下步骤实现:
(一)、在刚构梁中跨合龙后,将边跨单侧挂篮前移,调整挂篮中线,进行钢筋绑扎、预应力安装,利用边跨挂篮单侧悬浇过渡墩外侧的1#、姊现浇段,混凝土达到设计张拉强度和弹性模量后张拉预应力钢束,此时挂篮位于1#、2#已成梁段上;施工时,1#、姊现浇段的施工均采用现有的挂篮悬浇施工方法;
(二)、挂篮上墩,对3#现浇段进行施工作业:
步骤1 :解除挂篮的内外滑移梁吊点,从而将内外侧模、外滑移梁、内滑移梁与挂篮主构架分离;步骤2 :将挂篮主构架、挂篮底模整体后移,保证挂篮底模前吊点距离已成梁段底板的前缘彡50cm ;
步骤3、在已成梁段底板上串吊带,将挂篮底模悬吊于已成梁段底板上使挂篮底模脱离已成梁段底板45-60cm ;
步骤4:安装3#现浇段底模,3#现浇段底模的一端搭在挂篮底模的前横梁上,另一端搭在过渡墩上;将挂篮底模压紧,使3#现浇段底模的上表面与已成梁段底板密贴;
步骤5:解除挂篮主构架与挂篮底模的连接,前移挂篮主构架将主构架与内外滑移梁吊点连接;继续前移挂篮主构架至姊现浇段,调整挂篮模板,对3#现浇段进行绑扎钢筋、穿预应力管道、穿钢绞线、浇筑混凝土、养护、强张拉; 步骤6 :挂篮拆除。
[0005] 本发明具有如下有益效果:
(1)本发明施工时免去了膺架法中支架的搭设和拆除,也免去了托架法中托架预埋、安装、拆除、以及配重施工,极大地节约了成本。
[0006] (2)本发明操作简单,劳动力投入少、缩短了施工周期,节约了成本;同时降低了高支架搭设与拆除时高空作业强度,对车辆通行不产生任何影响,安全风险降到了最低。
[0007] (3)由于利用既有的施工挂篮,挂篮经受了悬臂浇筑的考验,边跨“现浇梁段”的施工不需要再对挂篮进行预压,免去了膺架法、托架法进行预压的繁琐工序,从而缩短了施工周期。
[0008] 本发明所述的施工方法操作简单、成本低,解决了现有大跨连续刚构梁边跨现浇梁段在跨越铁路、公路、市政、人员密集区及施工地形陡峭的地方施工时因支架搭设困难、 行车干扰大、安全风险大导致施工周期长、成本高以及给周围环境带来不便的问题,可广泛适用于跨越铁路、公路、市政、人员密集区及施工地形陡峭的大跨连续刚构梁的边跨现浇梁段施工。
附图说明
[0009] 图1是本发明第一步的结构示意图。
[0010] 图2是本发明第二步中步骤4的结构示意图。
[0011] 图3是本发明第二步中步骤5的结构示意图。
[0012] 图中:1-主构架;2-挂篮底模;3-已成梁段底板;4_3#现浇段底模;5_挂篮底模前横梁;6-过渡墩;7-外滑移梁;8-吊带。
具体实施方式
[0013] 实施例1 :
大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法,由如下步骤实现:
(一)、在刚构梁中跨合龙后,将边跨单侧挂篮前移,调整挂篮中线,进行钢筋绑扎、预应力安装,利用边跨挂篮单侧悬浇过渡墩外侧的1#、姊现浇段,混凝土达到设计张拉强度和弹性模量后张拉预应力钢束,此时挂篮位于1#、2#已成梁段上;
(二)、挂篮上墩,对3#现浇段进行施工作业:
步骤1 :解除内外滑移梁吊点,从而将内外侧模、外滑移梁7、内滑移梁与挂篮主构架1
4分离;
步骤2 :将挂篮主构架1、挂篮底模2整体后移,保证挂篮底模2前吊点距离已成梁段底板3的前缘50cm ;
步骤3、在已成梁段底板3上串吊带8,将挂篮底模2悬吊于已成梁段底板3上,使挂篮底模2脱离已成梁段底板3的高度为45cm ;
步骤4 :安装3#现浇段底模4,3#现浇段底模4的一端搭在挂篮底模2的前横梁5上, 另一端搭在过渡墩6上;将挂篮底模2压紧,使3#现浇段底模4的上表面与已成梁段底板 3密贴;
步骤5 :解除挂篮主构架1与挂篮底模2的连接,前移挂篮主构架1将主构架1与内外滑移梁吊点连接;继续前移挂篮主构架1至姊现浇段,调整挂篮模板,对3#现浇段进行绑扎钢筋、穿预应力管道、穿钢绞线、浇筑混凝土、养护、强张拉; 步骤6 :挂篮拆除。
[0014] ①在所有预应力张拉完毕后拆除挂篮构件;
②内外侧模利用塔吊分块拆除吊装到过渡墩下;
③内外滑移梁因长度较长、重量较大,切割成二节进行分段吊装;
④主构架后移到挂篮底模位置,利用原悬吊系统将主构架与挂篮底模连接成一体,解除已成梁段底板吊带,使挂篮底模与已成梁段底板脱离;
⑤继续后退挂篮的主构架和底模,待不影响桥下通行时停止移挂篮(如桥下无车辆、人员通行可取消本步骤);
⑥安装3t额定起重千斤顶和组3动滑轮共四套,分别与底模前后横梁的边吊点相连;
⑦调试卷扬机刹车等工作性能,完好后拆除主构架与底模的悬吊系统,同时启动4个卷扬机,将挂篮底模平稳下放到桥下;
⑧塔吊拆除主构架。
[0015] 此挂篮拆除方法为现有挂篮悬浇施工方法所采用的技术。
[0016] 实施例2:
大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法,由如下步骤实现:
(一)、在刚构梁中跨合龙后,将边跨单侧挂篮前移,调整挂篮中线,进行钢筋绑扎、预应力安装,利用边跨挂篮单侧悬浇过渡墩外侧的1#、姊现浇段,混凝土达到设计张拉强度和弹性模量后张拉预应力钢束,此时挂篮位于1#、2#已成梁段上;
(二)、挂篮上墩,对3#现浇段进行施工作业:
步骤1 :解除内外滑移梁吊点,从而将内外侧模、外滑移梁7、内滑移梁与挂篮主构架1 分离;
步骤2 :将挂篮主构架1、挂篮底模2整体后移,保证挂篮底模2前吊点距离已成梁段底板3的前缘80cm ;
步骤3、在已成梁段底板3上串吊带8,将挂篮底模2悬吊于已成梁段底板3上,使挂篮底模2脱离已成梁段底板3的高度为60cm ;
步骤4 :安装3#现浇段底模4,3#现浇段底模4的一端搭在挂篮底模2的前横梁5上, 另一端搭在过渡墩6上;将挂篮底模2压紧,使3#现浇段底模4的上表面与已成梁段底板 3密贴;步骤5 :解除挂篮主构架1与挂篮底模2的连接,前移挂篮主构架1将主构架1与内外滑移梁吊点连接;继续前移挂篮主构架1至2#现浇段,调整挂篮模板,对3#现浇段进行绑扎钢筋、穿预应力管道、穿钢绞线、浇筑混凝土、养护、强张拉; 步骤6 :挂篮拆除。
Claims (1)
1.大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法,其特征在于:由如下步骤实现:(一)、在刚构梁中跨合龙后,将边跨单侧挂篮前移,调整挂篮中线,进行钢筋绑扎、预应力安装,利用边跨挂篮单侧悬浇过渡墩(6)外侧的1#、2#现浇段,混凝土达到设计张拉强度和弹性模量后张拉预应力钢束,此时挂篮位于1#、2#已成梁段上;(二)、挂篮上墩,对3#现浇段进行施工作业:步骤1 :解除挂篮的内外滑移梁吊点,从而将内外侧模、外滑移梁(7)、内滑移梁与挂篮主构架(1)分离;步骤2 :将挂篮主构架(1)、挂篮底模(2)整体后移,保证挂篮底模(2)前吊点距离已成梁段底板(3)的前缘彡50cm;步骤3、在已成梁段底板(3)上串吊带(8),将挂篮底模(2)悬吊于已成梁段底板(3)上使挂篮底模(2 )脱离已成梁段底板(3 ) 45-60cm ;步骤4 :安装3#现浇段底模(4),3#现浇段底模(4)的一端搭在挂篮底模(2)的前横梁 (5)上,另一端搭在过渡墩(6)上;将挂篮底模(2)压紧,使3#现浇段底模(4)的上表面与已成梁段底板(3)密贴;步骤5 :解除挂篮主构架(1)与挂篮底模(2 )的连接,前移挂篮主构架(1)将主构架(1) 与内外滑移梁吊点连接;继续前移挂篮主构架(1)至姊现浇段,调整挂篮模板,对3#现浇段进行绑扎钢筋、穿预应力管道、穿钢绞线、浇筑混凝土、养护、强张拉; 步骤6 :挂篮拆除。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102271339A CN102330414B (zh) | 2011-08-09 | 2011-08-09 | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102271339A CN102330414B (zh) | 2011-08-09 | 2011-08-09 | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102330414A true CN102330414A (zh) | 2012-01-25 |
CN102330414B CN102330414B (zh) | 2013-04-03 |
Family
ID=45482360
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102271339A Active CN102330414B (zh) | 2011-08-09 | 2011-08-09 | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102330414B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102758404A (zh) * | 2012-07-19 | 2012-10-31 | 中铁十六局集团第一工程有限公司 | 空间倒八字索斜拉桥前支点挂篮行走装置 |
CN103556578A (zh) * | 2013-10-14 | 2014-02-05 | 中铁十九局集团有限公司 | 连续梁直线段与边跨合拢段的浇筑模具系统及其搭建方法 |
CN103572708A (zh) * | 2013-10-29 | 2014-02-12 | 西南交通大学 | 大跨度混凝土连续梁桥边跨合拢装置及方法 |
CN103726445A (zh) * | 2013-12-05 | 2014-04-16 | 中交一公局第三工程有限公司 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
CN104294768A (zh) * | 2012-12-12 | 2015-01-21 | 中铁上海工程局有限公司 | 挂篮过接触网支柱基础的施工方法 |
CN104790302A (zh) * | 2015-05-08 | 2015-07-22 | 中南林业科技大学 | 一种高墩连续刚构桥边跨直线段挂篮配合盖梁支架整体施工法 |
CN106958206A (zh) * | 2017-04-07 | 2017-07-18 | 中交第二公路勘察设计研究院有限公司 | 拱梁组合式连续刚构桥双层底篮双层扣挂施工装置及方法 |
CN107974942A (zh) * | 2017-11-30 | 2018-05-01 | 中铁二十局集团有限公司 | 一种陡坡侧刚构连续梁边跨施工方法 |
CN111926720A (zh) * | 2020-08-12 | 2020-11-13 | 中建七局交通建设有限公司 | 适用于黄土地区连续钢构悬臂梁合龙的施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256521A (ja) * | 1998-03-09 | 1999-09-21 | Sumitomo Constr Co Ltd | 橋梁架設装置 |
JP2003027418A (ja) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | コンクリート構造物およびその施工方法 |
CN1916289A (zh) * | 2006-08-28 | 2007-02-21 | 杨秋利 | 菱形桁架式挂篮 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
-
2011
- 2011-08-09 CN CN2011102271339A patent/CN102330414B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256521A (ja) * | 1998-03-09 | 1999-09-21 | Sumitomo Constr Co Ltd | 橋梁架設装置 |
JP2003027418A (ja) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | コンクリート構造物およびその施工方法 |
CN1916289A (zh) * | 2006-08-28 | 2007-02-21 | 杨秋利 | 菱形桁架式挂篮 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102758404B (zh) * | 2012-07-19 | 2014-01-08 | 中铁十六局集团第一工程有限公司 | 空间倒八字索斜拉桥前支点挂篮行走装置 |
CN102758404A (zh) * | 2012-07-19 | 2012-10-31 | 中铁十六局集团第一工程有限公司 | 空间倒八字索斜拉桥前支点挂篮行走装置 |
CN104294768A (zh) * | 2012-12-12 | 2015-01-21 | 中铁上海工程局有限公司 | 挂篮过接触网支柱基础的施工方法 |
CN103556578B (zh) * | 2013-10-14 | 2015-05-13 | 中铁十九局集团有限公司 | 连续梁直线段与边跨合拢段的浇筑模具系统及其搭建方法 |
CN103556578A (zh) * | 2013-10-14 | 2014-02-05 | 中铁十九局集团有限公司 | 连续梁直线段与边跨合拢段的浇筑模具系统及其搭建方法 |
CN103572708A (zh) * | 2013-10-29 | 2014-02-12 | 西南交通大学 | 大跨度混凝土连续梁桥边跨合拢装置及方法 |
CN103572708B (zh) * | 2013-10-29 | 2015-06-03 | 西南交通大学 | 大跨度混凝土连续梁桥边跨合拢装置及方法 |
CN103726445A (zh) * | 2013-12-05 | 2014-04-16 | 中交一公局第三工程有限公司 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
CN103726445B (zh) * | 2013-12-05 | 2015-09-09 | 中交一公局第三工程有限公司 | 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法 |
CN104790302A (zh) * | 2015-05-08 | 2015-07-22 | 中南林业科技大学 | 一种高墩连续刚构桥边跨直线段挂篮配合盖梁支架整体施工法 |
CN106958206A (zh) * | 2017-04-07 | 2017-07-18 | 中交第二公路勘察设计研究院有限公司 | 拱梁组合式连续刚构桥双层底篮双层扣挂施工装置及方法 |
CN106958206B (zh) * | 2017-04-07 | 2018-10-12 | 中交第二公路勘察设计研究院有限公司 | 拱梁组合式连续刚构桥双层底篮双层扣挂施工装置及方法 |
CN107974942A (zh) * | 2017-11-30 | 2018-05-01 | 中铁二十局集团有限公司 | 一种陡坡侧刚构连续梁边跨施工方法 |
CN107974942B (zh) * | 2017-11-30 | 2019-03-15 | 中铁二十局集团有限公司 | 一种陡坡侧刚构连续梁边跨施工方法 |
CN111926720A (zh) * | 2020-08-12 | 2020-11-13 | 中建七局交通建设有限公司 | 适用于黄土地区连续钢构悬臂梁合龙的施工方法 |
CN111926720B (zh) * | 2020-08-12 | 2022-01-25 | 中建七局交通建设有限公司 | 适用于黄土地区连续钢构悬臂梁合龙的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102330414B (zh) | 2013-04-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102330414B (zh) | 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法 | |
CN102094392B (zh) | 桥梁施工中的下承式挂篮及其应用 | |
CN101210419A (zh) | 小半径曲线混凝土箱梁施工用内外梁系统造桥机及其施工方法 | |
CN101781878B (zh) | 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法 | |
CN110528402B (zh) | 一种超宽箱梁多桁片组合挂篮的施工方法 | |
KR20140084107A (ko) | 셀프-런칭 이동식 비계공법 | |
CN102797227A (zh) | 倒挂式三角斜爬挂篮的施工方法 | |
CN108103945B (zh) | 一种现浇箱梁用整体落地模架 | |
CN205954489U (zh) | 桥梁上跨营业线现浇空间钢构施工防护移动支架 | |
CN110468743B (zh) | 一种用于旧桥墩帽改造的移动式吊架及施工方法 | |
KR101632922B1 (ko) | 비자주식 빔 런처를 이용한 교량시공방법 | |
CN103669217B (zh) | 一种后支点挂篮及其整体换幅横移方法 | |
CN100542944C (zh) | 两台千斤顶串联下放超重结构的方法 | |
CN109083023B (zh) | 采用劲性骨架的连续刚构桥及其施工方法 | |
CN202170474U (zh) | 支座体系混合式结合梁斜拉桥 | |
CN201588172U (zh) | 独塔无背索斜拉桥主塔整体提升模板 | |
CN101368372A (zh) | 承重托架 | |
CN106087711A (zh) | 波腹工梁-钢砼顶板-体外预应力组合t型简支梁 | |
CN110820602A (zh) | 一种单台节段箱梁架桥机及其操作方法 | |
CN208815424U (zh) | 一种桥梁下行式挂篮 | |
CN208717748U (zh) | 一种大跨度钢混组合梁架桥机支腿装置 | |
CN109098094A (zh) | 无支架横向拼装波形钢腹板组合箱梁的施工方法 | |
CN211420881U (zh) | 钢混叠合梁悬挑翼板混凝土施工用移动模架 | |
CN107881926A (zh) | 一种带全回转吊机的组合式挂篮及其施工方法 | |
CN209430213U (zh) | 一种用于盾构隧道现浇车道板施工的偏重液压模板台车 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |