CN102425141A - 大悬臂叠合构件及其施工方法 - Google Patents

大悬臂叠合构件及其施工方法 Download PDF

Info

Publication number
CN102425141A
CN102425141A CN2011102461865A CN201110246186A CN102425141A CN 102425141 A CN102425141 A CN 102425141A CN 2011102461865 A CN2011102461865 A CN 2011102461865A CN 201110246186 A CN201110246186 A CN 201110246186A CN 102425141 A CN102425141 A CN 102425141A
Authority
CN
China
Prior art keywords
cantilever
gate pier
stage concrete
construction
big
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102461865A
Other languages
English (en)
Other versions
CN102425141B (zh
Inventor
扈晓雯
张春生
汤暘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN201110246186.5A priority Critical patent/CN102425141B/zh
Publication of CN102425141A publication Critical patent/CN102425141A/zh
Application granted granted Critical
Publication of CN102425141B publication Critical patent/CN102425141B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种大悬臂叠合构件。本发明的目的是提供一种大悬臂叠合构件,有效缩短施工时间、减小工程投资、降低施工风险和施工难度。本发明的技术方案是:大悬臂叠合构件,具有闸墩,其特征在于:所述闸墩一侧拟修建悬臂构件位置的下方预埋有施工钢平台,在施工钢平台上方浇筑与闸墩连为整体的一期混凝土悬臂构件,一期混凝土悬臂构件的上面是分期浇筑的二期混凝土构件。本发明适用于水利水电工程、交通桥梁工程、港口通航工程。

Description

大悬臂叠合构件及其施工方法
技术领域
本发明涉及一种大悬臂叠合构件及其施工方法。适用于水利水电工程 、交通桥梁工程、港口通航工程。
背景技术
在水利水电工程 、交通桥梁工程、港口通航工程中由于有坝顶平台、码头作业面、闸顶交通以及满足船舶通航净空等功能要求,为了节省投资、缩短工期,往往采用悬臂构件来解决上部板梁结构搭接搁置问题。一般悬臂构件都采用地面搭建脚手架、现场立模浇筑混凝土施工。这种传统方法工期长、投资大、由于是高空作业,施工困难并伴有安全风险,对大悬臂构件设计施工时问题更为突出。   
发明内容
本发明要解决的技术问题是:针对上述存在的问题,提供一种大悬臂叠合构件及其施工方法,有效缩短施工时间、减小工程投资、降低施工风险和施工难度。
本发明所采用的技术方案是:大悬臂叠合构件,具有闸墩,其特征在于:所述闸墩一侧拟修建悬臂构件位置的下方预埋有施工钢平台,在施工钢平台上方浇筑与闸墩连为整体的一期混凝土悬臂构件,一期混凝土悬臂构件的上面是分期浇筑的二期混凝土构件。
所述一期混凝土悬臂构件与二期混凝土构件之间设有键槽和键槽插筋。
所述一期混凝土悬臂构件内、靠近悬臂的底部设置悬臂受力钢筋,该钢筋的上端穿过一期与二期混凝土的接缝。
所述闸墩内、靠近悬臂侧设置闸墩受力钢筋。
本发明大悬臂叠合构件的施工方法,其特征在于采用了以下步骤:
a、进行闸墩的混凝土浇筑,并在闸墩内预留闸墩受力钢筋,同时在闸墩内、拟修建悬臂构件侧预留悬臂受力钢筋;
b、在闸墩的一侧、拟修建悬臂构件位置的下方预埋施工钢平台;
c、以施工钢平台为施工作业平台,搭建脚手架,立模浇筑一期混凝土悬臂构件,该悬臂构件的上表面设置有键槽,键槽内预留键槽插筋;
d、待一期混凝土悬臂构件达到混凝土龄期后,以该悬臂构件为模板,直接在上面浇筑二期混凝土构件直到闸顶部,形成大悬臂叠合构件;
e、切割拆除闸墩内预埋的施工钢平台。
本发明的有益效果是:本发明可以解决大悬臂构件上部板梁结构搭接搁置问题及现场施工的困难。本发明将悬臂结构分层设计与施工,一期混凝土悬臂构件强度满足二期混凝土构件承载要求时尽可能减轻自重,降低了对施工作业平台的要求,采用施工钢平台即可解决施工作业面;混凝土构件施工浇筑就像在地面施工一样方便,不需再搭建脚手架,避免了高空作业危险、工程质量安全有保证。
附图说明
图1为本发明的剖视图。
图2为本发明A-A剖视图。
图3为本发明B-B剖视图。   
具体实施方式
如图1、图3所示,本实施例在浇筑闸墩2时,在闸墩内靠近拟修建悬臂构件的一侧预留Ф28mm闸墩受力钢筋4和Ф32 mm悬臂受力钢筋3,同时在该侧预埋施工钢平台7,施工钢平台作为施工作业平台,材料选用钢材,可直接在钢平台上焊接钢管,搭建脚手架。以此钢平台作为施工作业平台,立模浇筑一期混凝土悬臂构件1,一期混凝土悬臂构件1的顶部为水平面并在顶面制有若干组键槽,键槽内预留Ф25 mm的键槽插筋5,待一期混凝土悬臂构件1达到混凝土龄期后,以此悬臂构件作为模板,像在地面施工一样浇筑二期混凝土构件6,不需再搭建脚手架,避免了高空作业危险。待全部大悬臂叠合构件完工后,最后切割拆除闸墩预埋的施工钢平台7。
所述悬臂受力钢筋3上端必须穿过一期混凝土悬臂构件1与二期混凝土构件6的接缝,以增加悬臂构件的强度。
 所述施工钢平台7顶部与一期混凝土悬臂构件1底部之间的距离,也就是作业的高度可根据现场需要来确定,在高度允许的情况下可不用搭建脚手架,外侧高度较大处可少量搭建脚手架。本发明不必从地面搭建脚手架、现场立模浇筑混凝土施工,工期省、投资少,避免了高空作业危险,工程质量有保证。
本例大悬臂叠合构件施工步骤如下:
a、进行闸墩2的混凝土浇筑,闸墩2内预留Φ32mm悬臂构件受力钢筋3和Φ28mm闸墩受力钢筋4;
b、在闸墩2一侧、拟修建悬臂构件位置的下方完成预埋施工钢平台7的施工;
c、以施工钢平台7为施工作业平台,搭建脚手架,立模浇筑一期混凝土悬臂构件1,一期混凝土悬臂构件1上面设有均匀布置的键槽,键槽内预留出键槽插筋5;
d、待一期混凝土悬臂构件1达到混凝土龄期后,利用该层作为模版浇筑二期混凝土构件6直到闸顶部,形成大悬臂叠合构件,并在其上方完成T型梁8的浇筑;
e、切割拆除闸墩上预埋的施工钢平台7。

Claims (5)

1.一种大悬臂叠合构件,具有闸墩(2),其特征在于:所述闸墩(2)一侧拟修建悬臂构件位置的下方预埋有施工钢平台(7),在施工钢平台(7)上方浇筑与闸墩(2)连为整体的一期混凝土悬臂构件(1),一期混凝土悬臂构件(1)的上面是分期浇筑的二期混凝土构件(6)。
2.根据权利要求1所述的大悬臂叠合构件,其特征在于:所述一期混凝土悬臂构件(1)与二期混凝土构件(6)之间设有键槽和键槽插筋(5)。
3.根据权利要求1或2所述的大悬臂叠合构件,其特征在于:所述一期混凝土悬臂构件(1)内、靠近悬臂的底部设置悬臂受力钢筋(3),该钢筋的上端穿过一期与二期混凝土的接缝。
4.根据权利要求1或2所述的大悬臂叠合构件,其特征在于:所述闸墩(2)内、靠近悬臂侧设置闸墩受力钢筋(4)。
5.一种如权利要求1所述的大悬臂叠合构件的施工方法,其特征在于采用了以下步骤:
a、进行闸墩(2)的混凝土浇筑,并在闸墩(2)内预留闸墩受力钢筋(4),同时在闸墩(2)内、拟修建悬臂构件侧预留悬臂受力钢筋(3);
b、在闸墩(2)的一侧、拟修建悬臂构件位置的下方预埋施工钢平台(7);
c、以施工钢平台(7)为施工作业平台,搭建脚手架,立模浇筑一期混凝土悬臂构件(1),该悬臂构件的上表面制有键槽,键槽内预留键槽插筋(5);
d、待一期混凝土悬臂构件(1)达到混凝土龄期后,以该悬臂构件为模板,直接在上面浇筑二期混凝土构件(6)直到闸顶部,形成大悬臂叠合构件;
e、切割拆除闸墩(2)内预埋的施工钢平台(7)。
CN201110246186.5A 2011-08-25 2011-08-25 大悬臂叠合构件的施工方法 Active CN102425141B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110246186.5A CN102425141B (zh) 2011-08-25 2011-08-25 大悬臂叠合构件的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110246186.5A CN102425141B (zh) 2011-08-25 2011-08-25 大悬臂叠合构件的施工方法

Publications (2)

Publication Number Publication Date
CN102425141A true CN102425141A (zh) 2012-04-25
CN102425141B CN102425141B (zh) 2014-08-13

Family

ID=45959167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110246186.5A Active CN102425141B (zh) 2011-08-25 2011-08-25 大悬臂叠合构件的施工方法

Country Status (1)

Country Link
CN (1) CN102425141B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105568933A (zh) * 2015-12-22 2016-05-11 黄河养护集团有限公司 一种混凝土浇筑闸门的施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3985480A (en) * 1972-08-18 1976-10-12 Dyckerhoff & Widmann Ag Apparatus for the sectional cantilever construction of bridge girder systems
WO1983004274A1 (en) * 1982-06-01 1983-12-08 O^/Stlandske Spennbetong A-S Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method
CN2231274Y (zh) * 1994-12-12 1996-07-17 中国水利水电第八工程局 拆装式交替上升全悬臂大型钢模板
CN201080597Y (zh) * 2007-08-13 2008-07-02 蒋临安 多功能现浇悬臂板施工支架
KR20100090229A (ko) * 2010-07-01 2010-08-13 (주)지아이에프 하프 프리캐스트 패널을 이용한 캔틸레버 바닥판 시공방법
CN201695674U (zh) * 2009-12-23 2011-01-05 中铁大桥局集团第一工程有限公司 模块式悬臂混凝土结构浇筑构架
JP2011006944A (ja) * 2009-06-26 2011-01-13 Tis&Partners Co Ltd 橋梁構造
CN202247798U (zh) * 2011-08-25 2012-05-30 中国水电顾问集团华东勘测设计研究院 大悬臂叠合构件

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3985480A (en) * 1972-08-18 1976-10-12 Dyckerhoff & Widmann Ag Apparatus for the sectional cantilever construction of bridge girder systems
WO1983004274A1 (en) * 1982-06-01 1983-12-08 O^/Stlandske Spennbetong A-S Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method
CN2231274Y (zh) * 1994-12-12 1996-07-17 中国水利水电第八工程局 拆装式交替上升全悬臂大型钢模板
CN201080597Y (zh) * 2007-08-13 2008-07-02 蒋临安 多功能现浇悬臂板施工支架
JP2011006944A (ja) * 2009-06-26 2011-01-13 Tis&Partners Co Ltd 橋梁構造
CN201695674U (zh) * 2009-12-23 2011-01-05 中铁大桥局集团第一工程有限公司 模块式悬臂混凝土结构浇筑构架
KR20100090229A (ko) * 2010-07-01 2010-08-13 (주)지아이에프 하프 프리캐스트 패널을 이용한 캔틸레버 바닥판 시공방법
CN202247798U (zh) * 2011-08-25 2012-05-30 中国水电顾问集团华东勘测设计研究院 大悬臂叠合构件

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
《云南水力发电》 20030630 姜琳 大朝山电站厂房混凝土分层分块的设计和施工 第39页 1-5 第19卷, 第02期 *
姜琳: "大朝山电站厂房混凝土分层分块的设计和施工", 《云南水力发电》, vol. 19, no. 02, 30 June 2003 (2003-06-30), pages 39 *
张正强: "大跨径预应力混凝土连续刚构桥悬臂施工技术研究", 《中国优秀硕士论文全文数据库》, no. 8, 15 May 2008 (2008-05-15) *
陈刚: "浅谈桥墩盖梁施工的几种支撑体系", 《水利水电技术》, vol. 39, no. 11, 20 November 2008 (2008-11-20), pages 55 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105568933A (zh) * 2015-12-22 2016-05-11 黄河养护集团有限公司 一种混凝土浇筑闸门的施工方法

Also Published As

Publication number Publication date
CN102425141B (zh) 2014-08-13

Similar Documents

Publication Publication Date Title
CN107975059A (zh) 一种装配式桩基码头结构及其施工方法
CN201217898Y (zh) 混凝土预制楼梯
CN106012960B (zh) 一种装配式高桩码头上部结构体系及其施工方法
CN103437300A (zh) 墩顶钢梁无墩旁托架架设双悬臂的施工方法
CN104372743B (zh) 栈桥快速施工方法
CN103374880B (zh) 一种预制桥墩与承台的连接构造及其对接式施工方法
CN102653938B (zh) 下行式移动模架海上拆除施工工法
CN105862597B (zh) 一种多片式组合梁桥上下部整体式结构施工方法
CN103321155B (zh) 高架桥桥墩施工平台体系及搭建该体系并浇注桥墩的方法
CN107034842A (zh) 一种模块化装配式桩基码头结构体系及其施工方法
CN111305081A (zh) 一种预制桥面板湿接缝连接结构的施工工艺
CN106149877A (zh) 混凝土框架结构预制柱与梁板节点处的对接结构及方法
CN202247798U (zh) 大悬臂叠合构件
CN106499211B (zh) 新增挑梁框架包钢锚拉法结构
CN102425141B (zh) 大悬臂叠合构件的施工方法
CN110528778B (zh) 一种新型抗拉剪的钢-混凝土组合梁结构及其制作工艺
CN207919582U (zh) 一种装配式桩基码头结构
CN204570446U (zh) 一种预制拼装t型简支梁
CN104594389A (zh) 一种带弹性止水条的后浇带外墙封堵结构
CN104947804B (zh) 一种钢托架及利用其构建梁柱节点结构的施工方法
CN207597341U (zh) 一种模块化装配式桩基码头结构体系
CN103243722B (zh) 基坑新型内支撑的施工方法
CN216108007U (zh) 混凝土梁式桥及其现浇隐盖梁
CN214301583U (zh) 一种可循环使用措施材料的靠船构件
CN205348592U (zh) 交叉预制混凝土梁底部钢筋连通专用连接件

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant