CN104372743B - 栈桥快速施工方法 - Google Patents
栈桥快速施工方法 Download PDFInfo
- Publication number
- CN104372743B CN104372743B CN201410600030.6A CN201410600030A CN104372743B CN 104372743 B CN104372743 B CN 104372743B CN 201410600030 A CN201410600030 A CN 201410600030A CN 104372743 B CN104372743 B CN 104372743B
- Authority
- CN
- China
- Prior art keywords
- trestle
- bailey beam
- floorings
- paragraph
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D15/00—Movable or portable bridges; Floating bridges
- E01D15/12—Portable or sectional bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种栈桥快速施工方法,属于固定建筑物的专用于架设桥梁的方法技术领域。该栈桥快速施工方法包括1)标准构件预制;2)第一段栈桥的架设;3)在第一段桥面板上放置吊机;4)后续段栈桥的钢管桩安装;5)后续段栈桥的桩顶承重梁的安装;6)后续段栈桥的贝雷梁的安装;7)后续段栈桥的桥面板的安装;8)依次重复上述4至7步骤,依次安装其余各段贝雷梁和其余各段桥面板,依此类推完成栈桥全桥贝雷梁和桥面板的安装。该栈桥快速施工方法可以快速且安全的建设栈桥。
Description
技术领域
本发明涉及一种栈桥施工方法,属于固定建筑物的专用于架设桥梁的方法技术领域。
背景技术
近年来,随着跨江、跨海大桥的建设,栈桥作为运输材料、设备、人员的临时工程越来越广泛应用,且设计荷载越来越大,逐步接近半永久性工程。
在温州市域铁路S1线一期工程SG14标段灵昆特大桥的施工中,据申请人了解,灵昆特大桥是一座大型四线双幅铁路桥梁工程,线路全长3363.30m,连接瓯江南岸与灵昆岛,其中跨瓯江段2450m。灵昆特大桥栈桥连接瓯江南北两岸,是桥梁主墩施工平台和陆地连接的纽带,也是南北两岸施工运输的唯一通道,是水上施工的生命线。栈桥在施工过程中起着举足轻重的作用,是整个大桥施工的基础条件和前提条件。为了保证工期,提高施工安全,栈桥建设必须快速且安全。
发明内容
本发明要解决的技术问题是,针对现有技术不足,提出一种栈桥建设快速且安全的栈桥快速施工方法。
本发明为解决上述技术问题提出的技术方案是:一种栈桥快速施工方法,该栈桥由下述的标准构件构成,包括以下步骤:
1)标准构件预制:
预先制备多个钢管桩、多个桩顶承重梁、用于架设在栈桥上的多段贝雷梁、多段桥面板和一个导向架,所述导向架包括设有钢管桩安装导向装置的平台和用于与架设在栈桥上的贝雷梁相连的连接梁,所述连接梁固定在平台的一侧边;
2)第一段栈桥的架设:
先在地基上设置第一段栈桥的桩体,在所述桩体上固定桩顶承重梁,在所述桩顶承重梁上固定第一段贝雷梁,在所述第一段贝雷梁上固定第一段桥面板;
3)在所述第一段桥面板上放置吊机;
4)后续段栈桥的钢管桩安装:
所述吊机先起吊所述导向架,将所述连接梁与所述第一段贝雷梁外端相连并固定;所述吊机再起吊所述钢管桩,先通过所述钢管桩安装导向装置将所述钢管桩导向定位后再插打固定在地基上;安装完毕所述钢管桩后,解除所述连接梁与所述第一段贝雷梁之间的连接,再通过所述吊机将所述导向架吊走;
5)后续段栈桥的桩顶承重梁的安装:
所述吊机将所述桩顶承重梁吊起并放置在安装完毕后的所述钢管桩上并固定;
6)后续段栈桥的贝雷梁的安装:
所述吊机首先吊装第二段贝雷梁在桩顶承重梁上并固定,将所述第二段贝雷梁与第一段贝雷梁进行连接并固定;
7)后续段栈桥的桥面板的安装:
所述吊机将第二段桥面板吊起并分别对应放置在已经安装好的第二段贝雷梁上并固定;
8)依次重复上述4至7步骤,依次安装其余各段贝雷梁和其余各段桥面板,依此类推完成栈桥全桥贝雷梁和桥面板的安装。
本发明采用上述技术方案的有益效果是:1)设置了导向架,可以与已架设好的栈桥段快速连接和拆除,在导向架的平台上设有钢管桩的安装导向装置对钢管桩安装进行导向定位,不仅保证了桩位的精确控制,还为施工人员提供了安全宽敞的操作平台,变水上作业为陆上作业,施工不受潮水影响,可全天候作业,缩短了施工周期,提高了工效,利用导向架作为施工平台,改善了施工环境,人员操作安全可靠;2)可以在后场预制钢管桩、桩顶承重梁、贝雷梁和桥面板,再运至现场安装,实现了栈桥施工的工厂化、标准化作业,施工不受天气和现场环境影响,大大提高了施工速度,改善了施工环境,真正实现了海洋栈桥工程快速化、陆地化、工厂化、标准化。
上述技术方案的改进是:每段桥面板均是混凝土预制桥面板。
由于桥面板采用混凝土预制面板,在后场预制好后,运输至现场装,与传统钢面板相比,减少了用钢量和现场焊接工程量,不仅节约了施工成本,还降低了行车时的噪音污染,减少了行车对栈桥的震动,提高了行车舒适度。
上述技术方案的改进是:每段贝雷梁是由多片贝雷梁单元组成,相邻两片贝雷梁单元之间通过剪刀撑进行连接固定。
上述技术方案的改进是:每段贝雷梁与桩顶承重梁之间焊接限位器将该段贝雷梁与桩顶承重梁进行固定。
上述技术方案的改进是:在上述步骤8后,还包括以下步骤:
9)附属设施的安装:将桥面栏杆、电缆、水管支架安装固定。
上述技术方案的改进是:在上述步骤7中,每段桥面板底部预埋有相对设置的两块钢板,两块钢板与所述贝雷梁之间通过U型连接器焊接固定。
上述技术方案的改进是:每段贝雷梁顶部铺设有橡胶防滑垫。
上述技术方案的改进是:所述吊机是履带吊机。
附图说明
下面结合附图对本发明作进一步说明:
图1是本发明实施例栈桥快速施工方法的施工示意图一。
图2是本发明实施例栈桥快速施工方法的施工示意图二。
图3是本发明实施例栈桥快速施工方法的施工示意图三。
图4是本发明实施例栈桥快速施工方法的施工示意图四。
图5是本发明实施例栈桥快速施工方法的施工示意图五。
图6是本发明实施例栈桥快速施工方法的施工示意图六。
图7是本发明实施例栈桥快速施工方法的导向架的结构示意图。
图8是图7的俯视图。
具体实施方式
本实施例的栈桥快速施工方法,如图1至图6所示,该栈桥由下述的标准构件构成,包括以下步骤:
1)标准构件预制:
预先制备多个钢管桩1、多个桩顶承重梁2、用于架设在栈桥上的多段贝雷梁3、多段桥面板4和一个导向架5。如图7和图8所示,导向架5包括设有钢管桩安装导向装置的平台5-1和用于与架设在栈桥上的贝雷梁相连的连接梁5-2,连接梁5-2固定在平台5-1的一侧边;为了更好地与架设在栈桥上的贝雷梁相连,连接梁5-2可以制为贝雷梁的形状,当然也可以制为其它可以快速与架设在栈桥上的贝雷梁相连的形状;
2)第一段栈桥的架设:
先在地基上设置第一段栈桥的桩体6,在桩体6上固定桩顶承重梁2,在桩顶承重梁2上固定第一段贝雷梁3,在第一段贝雷梁3上固定第一段桥面板4;桩体6可以是钢管桩1,也可以采用别的桩体;
桩顶承重梁2是固定在桩体6上的横梁,第一段贝雷梁3是固定在桩顶承重梁2上的纵梁;
3)在第一段桥面板4上放置吊机7;
4)后续段栈桥的钢管桩安装:
吊机7先起吊导向架5,将连接梁5-2与第一段贝雷梁3外端相连并固定;吊机7再起吊钢管桩1,先通过钢管桩安装导向装置将钢管桩1导向定位后再插打固定在地基上;安装完毕钢管桩1后,解除连接梁5-2与第一段贝雷梁3之间的连接,再通过吊机7将导向架5吊走;
5)后续段栈桥的桩顶承重梁的安装:
吊机7将桩顶承重梁2吊起并放置在安装完毕后的钢管桩1上并固定;
6)后续段栈桥的贝雷梁的安装:
吊机7首先吊装第二段贝雷梁8在桩顶承重梁2上并固定,将第二段贝雷梁8与第一段贝雷梁3进行连接并固定;
7)后续段栈桥的桥面板的安装:
吊机7将第二段桥面板9吊起并分别对应放置在已经安装好的第二段贝雷梁8上并固定;
8)依次重复上述4至7步骤,依次安装其余各段贝雷梁和其余各段桥面板,依此类推完成栈桥全桥贝雷梁和桥面板的安装。
本实施例的每段桥面板均是混凝土预制桥面板。
本实施例的每段贝雷梁是由多片贝雷梁单元组成,相邻两片贝雷梁单元之间通过剪刀撑进行连接固定。
本实施例的每段贝雷梁与桩顶承重梁之间焊接限位器将该段贝雷梁与桩顶承重梁进行固定。
本实施例在上述步骤8后,还包括以下步骤:
9)附属设施的安装:将桥面栏杆、电缆、水管支架安装固定。
本实施例在上述步骤7中,每段桥面板底部预埋有相对设置的两块钢板,两块钢板与所述贝雷梁之间通过U型连接器焊接固定。
本实施例的每段贝雷梁顶部铺设有橡胶防滑垫。
本实施例的吊机7是履带吊机。
本发明不局限于上述实施例。凡采用等同替换形成的技术方案,均落在本发明要求的保护范围。
Claims (8)
1.一种栈桥快速施工方法,该栈桥由下述的标准构件构成,其特征在于包括以下步骤:
1)标准构件预制:
预先制备多个钢管桩、多个桩顶承重梁、用于架设在栈桥上的多段贝雷梁、多段桥面板和一个导向架,所述导向架包括设有钢管桩安装导向装置的平台和用于与架设在栈桥上的贝雷梁相连的连接梁,所述连接梁固定在平台的一侧边;
2)第一段栈桥的架设:
先在地基上设置第一段栈桥的桩体,在所述桩体上固定桩顶承重梁,在所述桩顶承重梁上固定第一段贝雷梁,在所述第一段贝雷梁上固定第一段桥面板;
3)在所述第一段桥面板上放置吊机;
4)后续段栈桥的钢管桩安装:
所述吊机先起吊所述导向架,将所述连接梁与所述第一段贝雷梁外端相连并固定;所述吊机再起吊所述钢管桩,先通过所述钢管桩安装导向装置将所述钢管桩导向定位后再插打固定在地基上;安装完毕所述钢管桩后,解除所述连接梁与所述第一段贝雷梁之间的连接,再通过所述吊机将所述导向架吊走;
5)后续段栈桥的桩顶承重梁的安装:
所述吊机将所述桩顶承重梁吊起并放置在安装完毕后的所述钢管桩上并固定;
6)后续段栈桥的贝雷梁的安装:
所述吊机首先吊装第二段贝雷梁在桩顶承重梁上并固定,将所述第二段贝雷梁与第一段贝雷梁进行连接固定;
7)后续段栈桥的桥面板的安装:
所述吊机将第二段桥面板吊起并分别对应放置在已经安装好的第二段贝雷梁上并固定;
8)依次重复上述4至7步骤,依次安装其余各段贝雷梁和其余各段桥面板,依此类推完成栈桥全桥贝雷梁和桥面板的安装。
2.如权利要求1所述栈桥快速施工方法,其特征在于:每段桥面板均是混凝土预制桥面板。
3.如权利要求1或2所述栈桥快速施工方法,其特征在于:每段贝雷梁是由多片贝雷梁单元组成,相邻两片贝雷梁单元之间通过剪刀撑进行连接固定。
4.如权利要求1或2所述栈桥快速施工方法,其特征在于:每段贝雷梁与桩顶承重梁之间焊接限位器将该段贝雷梁与桩顶承重梁进行固定。
5.如权利要求1或2所述栈桥快速施工方法,其特征在于:在上述步骤8后,还包括以下步骤:
9)附属设施的安装:将桥面栏杆、电缆、水管支架安装固定。
6.如权利要求1或2所述栈桥快速施工方法,其特征在于:在上述步骤7中,每段桥面板底部预埋有相对设置的两块钢板,两块钢板与所述贝雷梁之间通过U型连接器焊接固定。
7.如权利要求1或2所述栈桥快速施工方法,其特征在于:每段贝雷梁顶部铺设有橡胶防滑垫。
8.如权利要求1或2所述栈桥快速施工方法,其特征在于:所述吊机是履带吊机。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410600030.6A CN104372743B (zh) | 2014-10-31 | 2014-10-31 | 栈桥快速施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410600030.6A CN104372743B (zh) | 2014-10-31 | 2014-10-31 | 栈桥快速施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104372743A CN104372743A (zh) | 2015-02-25 |
CN104372743B true CN104372743B (zh) | 2016-05-18 |
Family
ID=52551914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410600030.6A Active CN104372743B (zh) | 2014-10-31 | 2014-10-31 | 栈桥快速施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104372743B (zh) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105019360B (zh) * | 2015-07-22 | 2016-06-29 | 中国能源建设集团江苏省电力建设第三工程有限公司 | 一种基于高空履带吊栈桥的施工方法 |
CN108203903A (zh) * | 2016-12-18 | 2018-06-26 | 邬惠林 | 高架桥下的吊起的自行车车道的施工方法 |
CN108342984B (zh) * | 2018-01-15 | 2020-08-04 | 中铁大桥局集团有限公司 | 一种滩涂软弱地基栈桥及其安装沉降方法 |
CN108824432B (zh) * | 2018-07-25 | 2024-07-09 | 中铁五局集团贵州工程有限公司 | 水中贝雷梁栈桥钢管桩悬臂式可调定位架 |
CN109653101B (zh) * | 2019-02-25 | 2020-05-08 | 中交第三航务工程局有限公司 | 一种用于桥梁施工的栈桥的搭设方法 |
CN110468721B (zh) * | 2019-08-29 | 2021-04-20 | 中铁大桥局集团有限公司 | 一种大跨度栈桥悬臂施工方法 |
CN111593670A (zh) * | 2020-06-05 | 2020-08-28 | 中国铁建大桥工程局集团有限公司 | 一种跨航道大跨度栈桥施工方法 |
CN113636451B (zh) * | 2021-08-09 | 2023-05-16 | 北京市政建设集团有限责任公司 | 一种钢栈桥吊装装置 |
CN114717958A (zh) * | 2022-04-09 | 2022-07-08 | 中铁上海工程局集团第五工程有限公司 | 一种大型特制贝雷梁安装的方法 |
CN117051705B (zh) * | 2023-08-07 | 2024-06-14 | 保利长大工程有限公司 | 一种用于水域的栈桥施工方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201363154Y (zh) * | 2009-03-03 | 2009-12-16 | 中国水利水电第七工程局有限公司 | 一种移动栈桥 |
CN201428460Y (zh) * | 2009-06-22 | 2010-03-24 | 中国水利水电第七工程局有限公司 | 多功能装配式液压驱动移动栈桥 |
WO2010092562A1 (en) * | 2009-02-09 | 2010-08-19 | Bahat Ben Ibrahim S | Erection method by simple tower instrument devices of building upper bridge construction |
CN201581656U (zh) * | 2009-12-04 | 2010-09-15 | 中建四局第六建筑工程有限公司 | 大型复杂建筑工地用钢栈桥 |
CN201762651U (zh) * | 2010-07-19 | 2011-03-16 | 中铁十二局集团第二工程有限公司 | 隧道仰拱栈桥 |
CN102312442A (zh) * | 2011-07-01 | 2012-01-11 | 中铁大桥局股份有限公司 | 栈桥钢管桩基础的施工方法 |
US8448280B2 (en) * | 2010-03-15 | 2013-05-28 | Newton Bridge Solutions Ltd | Method of providing a parapet wall on a bridge |
CN104060547A (zh) * | 2014-07-10 | 2014-09-24 | 中交二航局第四工程有限公司 | 一种临时钢栈桥施工方法及其栈桥 |
-
2014
- 2014-10-31 CN CN201410600030.6A patent/CN104372743B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010092562A1 (en) * | 2009-02-09 | 2010-08-19 | Bahat Ben Ibrahim S | Erection method by simple tower instrument devices of building upper bridge construction |
CN201363154Y (zh) * | 2009-03-03 | 2009-12-16 | 中国水利水电第七工程局有限公司 | 一种移动栈桥 |
CN201428460Y (zh) * | 2009-06-22 | 2010-03-24 | 中国水利水电第七工程局有限公司 | 多功能装配式液压驱动移动栈桥 |
CN201581656U (zh) * | 2009-12-04 | 2010-09-15 | 中建四局第六建筑工程有限公司 | 大型复杂建筑工地用钢栈桥 |
US8448280B2 (en) * | 2010-03-15 | 2013-05-28 | Newton Bridge Solutions Ltd | Method of providing a parapet wall on a bridge |
CN201762651U (zh) * | 2010-07-19 | 2011-03-16 | 中铁十二局集团第二工程有限公司 | 隧道仰拱栈桥 |
CN102312442A (zh) * | 2011-07-01 | 2012-01-11 | 中铁大桥局股份有限公司 | 栈桥钢管桩基础的施工方法 |
CN104060547A (zh) * | 2014-07-10 | 2014-09-24 | 中交二航局第四工程有限公司 | 一种临时钢栈桥施工方法及其栈桥 |
Also Published As
Publication number | Publication date |
---|---|
CN104372743A (zh) | 2015-02-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104372743B (zh) | 栈桥快速施工方法 | |
CN101914897B (zh) | 单主缆斜吊杆地锚式悬索桥的施工方法 | |
CN104018426B (zh) | 一种钢桁梁安装方法 | |
CN105970836A (zh) | 一种大跨度下弦变桁高连续钢桁梁悬臂架设方法 | |
CN102605719B (zh) | 混凝土预制梁节段拼装及架设的施工方法 | |
JP2006161548A (ja) | 仮桟橋及び仮桟橋の架設方法並びにそれに用いる台車、仮桟橋を用いた杭打ち工法 | |
CN108999044B (zh) | 一种应用模块化路基箱的钢栈道平台结构及其施工方法 | |
CN110847062A (zh) | 80米跨宽幅钢箱梁厂内整孔拼装双幅架设施工方法 | |
CN108589568B (zh) | 一种狭小空间内上跨营业线棚洞t型梁快速施工方法 | |
CN105544409B (zh) | 双导梁架桥机架设组合梁现拼段钢梁施工工艺 | |
CN112211085A (zh) | 用于大型履带吊上混凝土楼板行走栈桥装置及其安装方法 | |
CN114875813B (zh) | 一种钢筋混凝土钢架拱桥拆除重建施工设备、施工方法 | |
CN103590839B (zh) | 地铁车站现浇结构门式支架施工工艺 | |
CN214573260U (zh) | 一种施工临时跨河钢栈桥 | |
CN109024306A (zh) | 山岭地区场地高墩骑墩式门架桥梁提升施工方法 | |
CN209873558U (zh) | 一种连接板-桥台背墙组合的伸缩缝构造 | |
CN107905379A (zh) | 超高层建筑核心筒内全封闭层施工方法 | |
CN114701949A (zh) | 一种泵站主厂房桥机主梁安装方法 | |
CN113482047A (zh) | 管廊安装方法 | |
CN204151662U (zh) | 一种一跨跨越河谷的临时栈桥 | |
CN113944106A (zh) | 一种陆地矮墩桥梁上桥用钢栈桥通道及其施工方法 | |
JP2006169927A (ja) | 現場接着連結によるプレハブ式鋼床版鋼桁橋 | |
CN109868744A (zh) | 免现浇铺装层的全预制混凝土桥面板 | |
CN203822330U (zh) | 地铁车站负三层中板浇筑的支撑体系 | |
CN113931074B (zh) | 铁路架桥机在营业线抢险极限状态下快速铺架的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |