US20060108084A1 - Casting procedure, particularly for engine cylinder head - Google Patents

Casting procedure, particularly for engine cylinder head Download PDF

Info

Publication number
US20060108084A1
US20060108084A1 US10/530,196 US53019605A US2006108084A1 US 20060108084 A1 US20060108084 A1 US 20060108084A1 US 53019605 A US53019605 A US 53019605A US 2006108084 A1 US2006108084 A1 US 2006108084A1
Authority
US
United States
Prior art keywords
core
cores
casting
dissolve
intake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US10/530,196
Other languages
English (en)
Inventor
Bruno Bassi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meccanica Bassi SpA
Original Assignee
Meccanica Bassi SpA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meccanica Bassi SpA filed Critical Meccanica Bassi SpA
Assigned to MECCANICA BASSI S.P.A. reassignment MECCANICA BASSI S.P.A. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BASSI, BRUNO
Publication of US20060108084A1 publication Critical patent/US20060108084A1/en
Priority to US11/565,394 priority Critical patent/US20080017346A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22CFOUNDRY MOULDING
    • B22C9/00Moulds or cores; Moulding processes
    • B22C9/10Cores; Manufacture or installation of cores
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22CFOUNDRY MOULDING
    • B22C7/00Patterns; Manufacture thereof so far as not provided for in other classes
    • B22C7/02Lost patterns
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22CFOUNDRY MOULDING
    • B22C7/00Patterns; Manufacture thereof so far as not provided for in other classes
    • B22C7/06Core boxes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22CFOUNDRY MOULDING
    • B22C9/00Moulds or cores; Moulding processes
    • B22C9/02Sand moulds or like moulds for shaped castings
    • B22C9/04Use of lost patterns
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22CFOUNDRY MOULDING
    • B22C9/00Moulds or cores; Moulding processes
    • B22C9/10Cores; Manufacture or installation of cores
    • B22C9/103Multipart cores

Definitions

  • the present invention relates in general to the technology for producing cast parts.
  • it relates to gravity chills and low-pressure processes that use cores to obtain inside cavities in the casting.
  • a typical example of such casting process is that used for obtaining engine cylinder heads, where internal cores are necessary for obtaining the water jacket for the engine cooling water, the intake and exhaust ducts, and any other secondary cavity.
  • chill a fixed outside mould
  • cores are required, which are inserted (assembled) into the chill to form a single body ready for casting.
  • the main difficulty consists in perfectly collimating the inside of the part to be cast, that is the cores, with the outside, that is the chill, so as to obtain the required dimensional accuracy.
  • the cores are obtained in corresponding moulds, called core boxes, and then they are normally pre-assembled in the proximity of the chill.
  • the group of pre-assembled cores is collected by automatic devices (grippers and jigs) and laid (assembled) into the chill. At this point it is possible to cast the molten metal which will fill the volume comprised between the sand cores and the chill.
  • Sand projections are obtained onto the cores to keep the core group assembled in the desired position. Such prints are laid into the chill and do not constitute part of the object resulting from the casting.
  • cores for intake and exhaust ducts of an engine cylinder head whose surfaces form the end shape of the casting
  • such cores are inserted into the water jacket core and during the step of moving the cores group to the chill, if the assembly is performed manually they are free due to the effect of the gaps that will be occupied by the metal thickness. Then, they laid by gravity into the lower zone of the corresponding passages provided into the water jacket core. When the duct cores are in contact with the drag (lower base) of the chill, they get the final position.
  • the ducts cores are held into suitable positions relative to the water jacket by a special automatic device, but normally only by the side of the flange coupling to the intake and exhaust manifolds. The entire operation requires an approach that should be carried out carefully.
  • the water jacket core box interior must also be provided with all of the other parts resulting from the outside thickness of the cast-internal parts (ducts, etc.) and that are intended to house—during the subsequent core assembly—the other cores.
  • ducts cast-internal parts
  • the ducts outside parts do not undergo drafting as they normally are at half the height of the water jacket, mobile parts are currently used, controlled by gears, camshafts or, in the best case, by pneumatic cylinders, almost always moving on inclined axes.
  • the problem of making the duct cores pass through the openings obtained in the water jacket cores is solved by dividing the latter horizontally into two halves, which are then attached to each other by an adhesive after inserting the ducts.
  • Lost Foam Another casting process, called Lost Foam, consists in realising multiple polystyrene sectors using special dies. Once such sectors have been attached to one another, they match the part to be cast.
  • the polystyrene model thus obtained is coated and then put into a container, which is then filled by vibration with common sand or a similar material.
  • the molten metal is poured into the container. As polystyrene burns, it is replaced by the metal, so as to form the desired casting.
  • Object of the present invention is to obviate the disadvantages of the prior art mentioned above, by proposing a new casting procedure which allows obtaining higher quality castings, thereby reducing the number of the cast scrap due to dimensional defects, and further introducing new design prospects.
  • Another object of the invention is to provide a casting procedure which allows a perfect relative positioning between each core and an easy insertion of the cores into the mould or into another core, whichever their shape.
  • Another object of the finding is to provide a casting procedure which allows a considerable simplification of the core boxes, that is, without any complex shapes, undercuts and connected moving parts, and which is therefore cheaper, more reliable and easier to maintain.
  • Another object of the invention is to provide a chilling casting process for engine cylinder heads which allows obtaining cores for intake and exhaust ducts without any deformation on the outside thickness and with the most varied and complex shapes, which may result in better engine performance and ecologically more advanced engines as regards exhaust gases, as allowed by the new casting technology.
  • Yet another object of the invention is to provide a casting procedure for engine cylinder heads which allows embedding inserts for the ducts into the casting, made of a material capable of standing the heat generated by the molten metal in order to obtain perfectly smooth ducts which should contribute to improving the engine efficiency.
  • FIG. 1 shows sand and polymerised resin cores for realising the intake and exhaust ducts of an engine cylinder head
  • FIG. 2 shows a section view of the core boxes for moulding the cores of FIG. 1 , in a variant with inserts around the intake and exhaust ducts;
  • FIG. 3 shows the duct cores with inserts obtained with the core box of FIG. 2 ;
  • FIG. 4 shows a section of the duct cores inserted into the die for their coating with foamed material
  • FIG. 5 shows the group of valve seats and duct cores coated with foamed material
  • FIG. 6 shows the water jacket core box still empty
  • FIG. 7 shows the core box ( FIG. 6 ) with the group of duct cores of FIG. 5 inserted therein;
  • FIG. 8 shows the group of cores, valve seats and foamed coating obtained by moulding the water jacket core in the core box of the previous Figure, with the valve guides inserted into the coating;
  • FIG. 9 shows a complete chill core assembly scheme of the core group of the previous Figure
  • FIGS. 9 a and 9 b show two enlarged details of the core assembly scheme, where black parts denote the difference in the shape and volume of the water jacket dimensions that can be obtained by the casting procedure under discussion compared to the current art;
  • FIG. 10 shows the core assembly scheme in the variant with inserts.
  • the present invention relates to a casting procedure for obtaining castings provided with inside cavities.
  • cavities are obtained by laying in a mould, such as a chill, intended to receive the molten metal, one or more cores made or sand and polymerized resin or other material.
  • cores are previously obtained into special moulds, called core boxes.
  • core boxes In the case of more cores, these are obtained separately, each into a relative core box, and then they are assembled each other before being laid (assembled) into the mould or chill.
  • the cores are usually provided with complementary projections and cavities, called positive and negative prints, to support one another, and with other sand projections intended to lay into the suitable seats into the chill, which do not form part of the casting.
  • the procedure according to the present invention provides for coating one or more cores made of sand or other material with a layer of foamed material, such as polystyrene, only in the shaped zones, using a special die and then laying them into the chill.
  • foamed material such as polystyrene
  • the core coating material is intended to dissolve in contact with the casting metal, which replaces it thereby determining the required casting thickness, so that the finished casting surface will be determined by the quality of the core surface.
  • the main core box In order to receive the secondary cores already coated with foamed material, the main core box will be empty at the shapes of said secondary cores since shapes and thickness are replaced by the cores and by the coating layer. As a consequence, the main core box is much easier and cheaper to be realised since it allows eliminating any inside undercut and any moving parts required to realised the containments of secondary cores.
  • the main core box only has the outside prints of the secondary cores, which will be pre-assembled into the same. Following the moulding of the main core box with sand and polymerised resin, a single monolithic body is obtained, already assembled and exhibiting a considerable geometric accuracy , consisting of the main core and of the secondary cores, which are integral with the main core through the coating that forms the casting thickness.
  • Such monolithic body can then be easily carried and laid into the mould or chill.
  • the casting procedure under discussion can be applied to thin hollow inserts consisting of heat resistant material, such as metal or composite material, and intended to be embedded into the casting for making the inside surfaces of the cavities perfectly smooth.
  • the main core box is capable of receiving both sand cores or inserts coated with foamed material.
  • inserts of metal or other material are to be embedded into the casting, and these inserts have an inside void and where such void is corresponding to the core design, they must be laid into a specific core box which only considers the insert thickness in addition, and then it is moulded.
  • the resulting core will be provided with prints and embedded inserts, only in the shaped zone, and besides serving as support for the inserts, such core will also prevent the molten material from penetrating into the void part of the embedded inserts.
  • the casting designer is provided with a new technology that allows obtaining castings which can even embed other adjacent parts currently casted separately, according to the constraints of the current traditional casting technology.
  • Such new technology can also be used for obtaining stiffening by pre-coating fragile cores with foamed material in order to facilitate handling or for a greater protection against breakage after pre-assembly into the mould, or for restricting the effect of metallostatic pressure.
  • the coating thickness may be equal to or smaller than the casting thickness, or by laying the pre-coated cores into another core box yet to be moulded, and in this case the coating must be equal to the casting thickness.
  • the die is constructed with all core print seats equal to the core boxes, to moulds or chills, considering the specific tolerances and thermal expansions.
  • the casting procedure described is especially but not exclusively adapted to be applied to a chill casting process of an engine cylinder head.
  • the main core 11 is the water jacket core that is that intended to realise the coolant circulation passages, whereas secondary cores mainly are those relating to the intake 12 and exhaust 13 duct.
  • valve seats 14 , 15 for the intake and exhaust valves may be previously laid into said die, at special references.
  • the die may be provided with mobile cylindrical pins 16 , 17 intended to realise seats 16 ′, 17 ′. ( FIG. 5 ) for the valve guides 16 ′′, 17 ′′.
  • Polystyrene 18 or equivalent material, injected into the die, only envelops the shaped zones of the cores inserted therein, with the required casting thickness, thereby excluding the core prints 12 ′, 13 ′.
  • the valve seats onto the outside diameter are embedded, whereas inside they will be aligned on the conical edges of the duct cores.
  • the valve seats 14 , 15 must have the proper machining stock on the inside diameter.
  • the outside diameter of the valve seats is realised with a taper equal to the inside one, and such taper is required for the coating material to support and held into position the valve seats during further handling, up to the assembly into the chill or die. The metal will then finally block the valve seats onto the casting.
  • the group consisting of ducts 12 , 13 and of the valve seats 14 , 15 , all coated with foamed material 18 , and therefore consisting of a single body ( FIG. 5 ) is then laid (pre-assembled) into the water jacket core box 20 ( FIGS. 6, 7 ).
  • the water jacket core box 20 exhibits very simple structure since it is free from the shapes corresponding to the outside thickness of pre-assembled secondary cores.
  • the water jacket core box is filled with sand and polymerised resin, thereby obtaining a very accurate monolithic group wherein the water jacket core 11 envelops and holds the outside thickness of the duct cores consisting of the foamed material on the shaped zones ( FIG. 8 ). A perfect relative positioning between each core is therefore obtained as well.
  • valve guides 16 ′′, 17 ′′ can be automatically inserted into the suitable seats 16 ′, 17 ′obtained in the foamed material.
  • Special sealing members are applied to the junctions between foamed material and upper half water jacket core box in order to prevent sand infiltrations into the guide seats during moulding.
  • valve guides will be solid (without central holes) since mechanical machining for inserting the valve stems is performed with valve guides embedded into the casting. Among the other things, this allows preventing the use of traditional stiffening bosses around the valve guide into the duct cores.
  • valve guides will be provided with a negative circular groove at the portions embedded in the foamed material, which will hold into position the valve guides in the casting metal when the latter replaces the foamed material.
  • valve guide In the upper portion of the valve guide there is often another core 21 for the oil gallery, as in the case shown in FIG. 10 , or a core for the tappet compartment, which realises the risers (casting metal feeding during the shrinkage by cooling).
  • valve guides will always be guided into a suitable seat realised into said upper core 21 or into the tappet compartment core, and therefore blocked into the correct position, even when the casting metal has dissolved or is dissolving the foamed material around the valve guides, without making the same valve guides collapse.
  • the valve guides are inserted and stopped into suitable seats 22 obtained in the duct cores ( FIG. 3 ).
  • the monolithic group comprising the water jacket core 11 , the secondary cores, the valve seats, the valve guides, the foamed material along with other cores, such as core 21 , can be laid assembled into the chill ( FIGS. 9, 10 ).
  • the molten metal will dissolve and replace the foamed material, determining the required thickness and embedding the valve seats and the valve guides.
  • FIG. 10 shows the same assembly scheme described above, but where the duct cores consist of metal hollow inserts 23 (or made of another material capable of standing the heat generated by the casting metal), filled with sand and polymerised resin having a support function as well as serving to prevent any penetration of molten metal into the inserts.
  • the interior of such inserts has the same dimensional features of sand cores.
  • Polymerised sand cores and inserts 23 are moulded into a specific core box 10 which must keep into account the thickness of said inserts ( FIG. 2 ).
  • the inserts end against the valve seats whereas as the opposed end, they end flush with the casting raw flange. Since the intake and exhaust duct cores 12 , 13 and any other secondary cores are laid (pre-assembled) after having been coated with foamed material 18 in the water jacket core box 11 , there is no design limit for the ducts or for other secondary cores.
  • the intake ducts may be connected to one another with a single chamber without any interruption in the horizontal direction to the upper parts of the valve seats. Such chamber may even reach the intake manifold coupling flange and form a single chamber integral with the same manifold, without implying any problems of assembly with the water jacket. Such concept may also be extended to inserts made of another material and embedded into the casting.
  • the head designer will have a wide freedom of design since the current design constraints are eliminated, such as the forced passage of the ducts through the water jacket.
  • the water jacket compartment can be realised with more rounded design (black parts) in place of the current inclined surfaces and sharp edges to allow drafting.
  • the outside duct core thickness is also free from deformations, with a constant and perfect thickness exactly as drawing specification.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Molds, Cores, And Manufacturing Methods Thereof (AREA)
  • Cylinder Crankcases Of Internal Combustion Engines (AREA)
US10/530,196 2002-10-04 2002-12-09 Casting procedure, particularly for engine cylinder head Abandoned US20060108084A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US11/565,394 US20080017346A1 (en) 2002-10-04 2006-11-30 Casting Procedure, Particularly for an Engine Cylinder Head

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
IT000088A ITBS20020088A1 (it) 2002-10-04 2002-10-04 Procedimento di fusione, in particolare per testa cilindri di motori
PCT/IT2002/000771 WO2004035245A1 (en) 2002-10-04 2002-12-09 Casting procedure, particularly for engine cylinder head

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
PCT/IT2002/000771 Continuation-In-Part WO2004035245A1 (en) 2002-10-04 2002-12-09 Casting procedure, particularly for engine cylinder head

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US11/565,394 Continuation US20080017346A1 (en) 2002-10-04 2006-11-30 Casting Procedure, Particularly for an Engine Cylinder Head

Publications (1)

Publication Number Publication Date
US20060108084A1 true US20060108084A1 (en) 2006-05-25

Family

ID=32104757

Family Applications (2)

Application Number Title Priority Date Filing Date
US10/530,196 Abandoned US20060108084A1 (en) 2002-10-04 2002-12-09 Casting procedure, particularly for engine cylinder head
US11/565,394 Abandoned US20080017346A1 (en) 2002-10-04 2006-11-30 Casting Procedure, Particularly for an Engine Cylinder Head

Family Applications After (1)

Application Number Title Priority Date Filing Date
US11/565,394 Abandoned US20080017346A1 (en) 2002-10-04 2006-11-30 Casting Procedure, Particularly for an Engine Cylinder Head

Country Status (17)

Country Link
US (2) US20060108084A1 (ja)
EP (1) EP1545811A1 (ja)
JP (1) JP2006502009A (ja)
KR (1) KR20050060070A (ja)
CN (1) CN1671493A (ja)
AR (1) AR038665A1 (ja)
AU (1) AU2002368287A1 (ja)
BR (1) BR0215900A (ja)
CA (1) CA2500794A1 (ja)
DE (1) DE20221850U1 (ja)
IT (1) ITBS20020088A1 (ja)
MX (1) MXPA05002557A (ja)
NO (1) NO20052175L (ja)
RU (1) RU2306194C2 (ja)
TW (1) TW200405836A (ja)
WO (1) WO2004035245A1 (ja)
ZA (1) ZA200501275B (ja)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080283210A1 (en) * 2007-05-15 2008-11-20 Jong Bae Kim Method of manufacturing cylinder head system for vehicle
US8434546B1 (en) 2010-03-30 2013-05-07 Honda Motor Co., Ltd. Casting mold core retention device and method
US20140305408A1 (en) * 2011-12-13 2014-10-16 Caterpillar Motoren Gmbh & Co. Kg Cylinder head with fuel guiding portion
CN105478667A (zh) * 2014-02-28 2016-04-13 郑州思辩科技有限公司 一种水套式排气歧管铸造砂型的制作方法
CN106216638A (zh) * 2016-07-25 2016-12-14 河南理工大学 耐磨件的制备方法
US20170241370A1 (en) * 2016-02-24 2017-08-24 Toyota Jidosha Kabushiki Kaisha Assembling method of cores
US10144055B2 (en) 2015-05-29 2018-12-04 Nissan Motor Co., Ltd. Device for casting cylinder head and method for casting cylinder head
CN111673046A (zh) * 2020-06-20 2020-09-18 百色皓海碳素有限公司 一种新型节能电解铝用的阳极钢爪制造方法
CN114799117A (zh) * 2022-04-29 2022-07-29 广汽本田汽车有限公司 一种冷却型芯及其压铸模具
CN116079007A (zh) * 2023-04-07 2023-05-09 蓬莱金创精密铸造有限公司 一种用于汽车排气接头的铸造模具及制造工艺
CN117773059A (zh) * 2024-01-18 2024-03-29 烟台冰轮智能机械科技有限公司 一种缸盖的裸浇铸造工艺

Families Citing this family (38)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4327681B2 (ja) 2004-08-04 2009-09-09 トヨタ自動車株式会社 樹脂製シリンダヘッドカバー
EP1836014B1 (en) * 2005-01-14 2009-05-20 Meccanica Bassi S.P.A. Lost foam casting method, in particular for an engine cylinder head
FR2888288A3 (fr) * 2005-07-08 2007-01-12 Renault Sas Cloison de separation pour conduit d'admission de culasse realisee venue de matiere par moulage avec la culasse
CN100444988C (zh) * 2005-11-02 2008-12-24 沈阳铸造研究所 一种制备整体制芯模具的方法
DE102005054616B3 (de) * 2005-11-16 2006-11-09 Hydro Aluminium Mandl&Berger Gmbh Dauergießform und Gießformeinsatz
CN100404168C (zh) * 2005-12-30 2008-07-23 广西玉柴机器股份有限公司 柴油机四气门缸盖重力铸造模具及铸造方法
ITBS20060050A1 (it) * 2006-03-03 2007-09-04 Bassi Techonology S R L Anima composita di fonderia e metodo di fusione impiegante detta anima
KR101163692B1 (ko) 2006-11-14 2012-07-09 현대자동차주식회사 실린더 헤드용 연소실 인서트 금형
US8419713B1 (en) 2012-08-01 2013-04-16 The University Of Utah Research Foundation Carrier assembly with caps for medical connectors
IT1396907B1 (it) 2009-05-22 2012-12-20 Freni Brembo Spa Attrezzatura per la realizzazione di anime da fonderia
US8231587B2 (en) 2009-10-30 2012-07-31 Catheter Connections Disinfecting caps for medical male luer connectors
WO2011066565A1 (en) 2009-11-30 2011-06-03 Catheter Connections, Inc. Disinfecting caps having an extendable feature and related systems and methods
DE102010026597A1 (de) * 2010-07-08 2012-01-12 Mahle International Gmbh Verfahren zur Herstellung eines Zylinders für einen Zweitaktmotor sowie Gusskern hierfür
CN101961768A (zh) * 2010-11-18 2011-02-02 沪东重机有限公司 一种铸钢气缸盖的铸造方法
CN102476165A (zh) * 2010-11-23 2012-05-30 广西玉柴机器股份有限公司 砂型铸造中手工造型异型排气孔的制作方法
CN102019359A (zh) * 2010-12-22 2011-04-20 宁夏共享集团有限责任公司 一种超大型砂芯结构铸件的砂芯造型方法
CN102328028A (zh) * 2011-07-13 2012-01-25 中核苏阀横店机械有限公司 大口径低磅级阀盖铸件改进结构
CN102328020A (zh) * 2011-08-31 2012-01-25 刘天平 一种快速开发铸造产品样件的工艺方法
CN103182477B (zh) * 2011-12-31 2015-07-08 上海爱仕达汽车零部件有限公司 一种用于发动机缸盖浇铸的模具
CN103706764B (zh) * 2013-12-17 2015-06-17 四川制动科技股份有限公司 一种铁路车辆制动阀体内腔砂芯结构
CN103978160A (zh) * 2014-04-25 2014-08-13 河南省汤阴县华兴机械制造有限公司 一种铸造箱体本体芯、孔芯及补芯整体制芯工艺方法
US11628288B1 (en) 2014-07-14 2023-04-18 Merit Medical Systems, Inc. Disinfecting cap for needleless injection sites
CA2967392C (en) 2014-11-24 2023-04-25 Merit Medical Systems, Inc. Disinfecting cap for medical connectors
CN104493132B (zh) * 2015-01-22 2016-06-08 德盛镁汽车部件(芜湖)有限公司 一种汽车发动机缸盖铸造模具
US10036346B2 (en) * 2015-09-10 2018-07-31 Ford Global Technologies, Llc Lubrication circuit and method of forming
EP3377420A4 (en) 2015-11-16 2019-07-10 Merit Medical Systems, Inc. DISINFECTION CAP FOR LUER MALE
CN106050463B (zh) * 2016-06-29 2018-08-17 中国北方发动机研究所(天津) 一种组合式气缸盖
CN106630744B (zh) * 2016-11-23 2018-10-26 江苏雨燕模塑有限公司 一种汽车方向盘模具材料及其制备方法
EP3573699B1 (en) 2017-01-27 2022-08-10 Merit Medical Systems, Inc. Disinfecting luer cap and method of use
CN106984770B (zh) * 2017-03-17 2019-04-02 共享装备股份有限公司 棒类铸件砂芯芯盒及制芯方法
EP3691741A4 (en) 2017-10-04 2021-07-28 Merit Medical Systems, Inc. DISINFECTING CAP FOR VALVE CONNECTOR AND METHOD OF USE
CN108746502A (zh) * 2018-08-09 2018-11-06 江苏力源金河铸造有限公司 一种工程机械后盖浇铸用分体式砂芯
DE102019114493A1 (de) 2019-05-29 2020-12-03 Nemak, S.A.B. De C.V. Verfahren zum Herstellen eines verlorenen Gießkerns
CN110496938B (zh) * 2019-09-16 2024-04-02 洛阳刘氏模具有限公司 铝合金排气管类产品的自动粘接模具
CN110791750A (zh) * 2019-10-15 2020-02-14 中北大学 一种提高铝-钢双金属固液复合铸造界面结合强度的方法
IT202000014458A1 (it) * 2020-06-17 2021-12-17 Ferrari Spa Metodo di produzione di una testata per un motore a combustione interna
US11548060B2 (en) * 2020-09-18 2023-01-10 GM Global Technology Operations LLC High heat-absorption core for manufacturing of castings
US11654476B2 (en) * 2020-09-28 2023-05-23 GM Global Technology Operations LLC Hybrid core for manufacturing of castings

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4093018A (en) * 1976-10-19 1978-06-06 Deere & Company Casting methods with composite molded core assembly
US4691754A (en) * 1985-12-31 1987-09-08 Deere & Company Method for forming castings having inserts

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58184040A (ja) * 1982-04-22 1983-10-27 Nissan Motor Co Ltd 内燃機関のシリンダブロツク用中子及びその造型方法
FR2613659A1 (fr) * 1987-04-13 1988-10-14 Peugeot Procede de fabrication de pieces rigides et creuses presentant ou non des contre depouilles
US6305458B1 (en) * 1999-03-17 2001-10-23 Baker Hughes Incorporated Lost foam and sand cores stage manufacturing technology

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4093018A (en) * 1976-10-19 1978-06-06 Deere & Company Casting methods with composite molded core assembly
US4691754A (en) * 1985-12-31 1987-09-08 Deere & Company Method for forming castings having inserts

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080283210A1 (en) * 2007-05-15 2008-11-20 Jong Bae Kim Method of manufacturing cylinder head system for vehicle
US20100230068A1 (en) * 2007-05-15 2010-09-16 Hyundai Motor Company Method and mold for manufacturing cylinder head system for vehicle
US8434546B1 (en) 2010-03-30 2013-05-07 Honda Motor Co., Ltd. Casting mold core retention device and method
US9617950B2 (en) * 2011-12-13 2017-04-11 Caterpillar Motoren Gmbh & Co. Kg Cylinder head with fuel guiding portion
US20140305408A1 (en) * 2011-12-13 2014-10-16 Caterpillar Motoren Gmbh & Co. Kg Cylinder head with fuel guiding portion
CN105478667A (zh) * 2014-02-28 2016-04-13 郑州思辩科技有限公司 一种水套式排气歧管铸造砂型的制作方法
US10144055B2 (en) 2015-05-29 2018-12-04 Nissan Motor Co., Ltd. Device for casting cylinder head and method for casting cylinder head
US20170241370A1 (en) * 2016-02-24 2017-08-24 Toyota Jidosha Kabushiki Kaisha Assembling method of cores
US10533515B2 (en) * 2016-02-24 2020-01-14 Toyota Jidosha Kabushiki Kaisha Assembling method of cores
CN106216638A (zh) * 2016-07-25 2016-12-14 河南理工大学 耐磨件的制备方法
CN111673046A (zh) * 2020-06-20 2020-09-18 百色皓海碳素有限公司 一种新型节能电解铝用的阳极钢爪制造方法
CN114799117A (zh) * 2022-04-29 2022-07-29 广汽本田汽车有限公司 一种冷却型芯及其压铸模具
CN116079007A (zh) * 2023-04-07 2023-05-09 蓬莱金创精密铸造有限公司 一种用于汽车排气接头的铸造模具及制造工艺
CN117773059A (zh) * 2024-01-18 2024-03-29 烟台冰轮智能机械科技有限公司 一种缸盖的裸浇铸造工艺

Also Published As

Publication number Publication date
TW200405836A (en) 2004-04-16
BR0215900A (pt) 2005-08-09
RU2306194C2 (ru) 2007-09-20
CN1671493A (zh) 2005-09-21
WO2004035245A1 (en) 2004-04-29
ZA200501275B (en) 2006-07-26
DE20221850U1 (de) 2008-11-20
RU2005109149A (ru) 2005-10-10
AU2002368287A1 (en) 2004-05-04
AR038665A1 (es) 2005-01-26
NO20052175L (no) 2005-05-03
EP1545811A1 (en) 2005-06-29
MXPA05002557A (es) 2005-05-05
JP2006502009A (ja) 2006-01-19
ITBS20020088A1 (it) 2004-04-05
US20080017346A1 (en) 2008-01-24
KR20050060070A (ko) 2005-06-21
CA2500794A1 (en) 2004-04-29

Similar Documents

Publication Publication Date Title
US20060108084A1 (en) Casting procedure, particularly for engine cylinder head
CN100439008C (zh) 铸型组装设备和方法
CA1085136A (en) Metal casting methods, tooling and processes
GB2073094A (en) Injection moulding thermoplastic patterns having ceramic cores
US20020148589A1 (en) Ceramic core with locators and method
EP1836014B1 (en) Lost foam casting method, in particular for an engine cylinder head
US10391551B2 (en) Mold body with integrated chill
US10155265B2 (en) Method for positioning core by soluble wax in investment casting
JP5442349B2 (ja) 金型の冷却プレート及びその製造方法
CN116352055A (zh) 便于排气的电机壳体铸件低压组芯铸造模具及铸造工艺
US6363995B1 (en) Device and method for manufacturing an engine block
JPS58184040A (ja) 内燃機関のシリンダブロツク用中子及びその造型方法
US6354357B1 (en) Lost foam method of casting a cylinder liner with water jacket
KR101350431B1 (ko) 쉘 몰드를 이용하여 일체형 터빈하우징을 주조하기 위한 정밀주조용 주형
USRE31488E (en) Casting methods with composite molded core assembly
US20040099398A1 (en) Equipment for moulding foundry parts with improved means positioning sand cores, and related positioning method
US5704412A (en) Self-aligning sand mold insert assembly
CN111590024A (zh) 一种3d打印砂型铸造预埋冷铁的方法
CN110548835A (zh) 一种避免汽缸盖缩松的方法
CN219151507U (zh) 一种钢制送料板铸造模具
CN112846080B (zh) 一种大型船用舵叶铸件的整体式铸造控制方法
JP3196623B2 (ja) 中子の支持装置
JPS63281760A (ja) 内燃機関用シリンダヘッドの製造方法
CN217666225U (zh) 一种可锻铸铁件覆膜砂壳型浇铸装置
CN219169551U (zh) 一种铸钢定子压圈的铸造模具

Legal Events

Date Code Title Description
AS Assignment

Owner name: MECCANICA BASSI S.P.A., ITALY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BASSI, BRUNO;REEL/FRAME:016670/0276

Effective date: 20050308

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION