CN103670508A - 一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 - Google Patents
一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 Download PDFInfo
- Publication number
- CN103670508A CN103670508A CN201310721064.6A CN201310721064A CN103670508A CN 103670508 A CN103670508 A CN 103670508A CN 201310721064 A CN201310721064 A CN 201310721064A CN 103670508 A CN103670508 A CN 103670508A
- Authority
- CN
- China
- Prior art keywords
- filling
- jack
- division board
- lifting
- isolating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种煤矿膏体充填开采的摆动式隔离装置及隔离方法,属于充填采煤的隔离装置及方法。装置的伸缩机构的一端与抬升机构的一端铰接,抬升机构的另一端连接在支架底座上,伸缩机构的另一端与支架底座之间连接有摆动千斤顶,支架底座的尾部有滑道;方法:在进行充填隔离准备工作时,只需通过液压操纵阀操作摆动千斤顶调整隔离板位置,在抬升千斤顶作用下,利用抬升座挤压底密封条密封底板,在伸缩千斤顶作用下升起伸缩箱挤压顶密封条密封顶板,另辅以少量人工辅助措施,全工作面隔离装置依次操作,即可在支架尾部形成充填隔离挡墙。优点:在充填采煤中,快速设置待充填区隔离,取消工人人工搭建隔离模板的工作,减少人工劳动,提高充填整体工作效率。
Description
技术领域
本发明涉及一种充填采煤的隔离装置及方法,特别是一种煤矿膏体充填开采的摆动式隔离装置及隔离方法。
背景技术
膏体充填技术作为煤矿绿色开采技术体系之一,其主要目的是解决“三下一上”压煤,提高煤矿资源采出率,延长矿井服务年限。
目前,待充填区的隔离堵漏问题是制约膏体充填开采技术的主要难点之一。若单纯采用人工方式进行隔离堵漏工作,不仅操作繁琐,工人劳动强度大,且耗时长,效率低,而传统综采支架并未设有密封充填料浆的隔离装置,同样需要采用人工方式建造隔离挡墙,机械化程度低下,严重制约膏体充填采煤效率的提高。
因此,膏体充填开采技术中隔离准备工作机械化程度不高,效率低下,成为本领域技术人员亟待解决的问题。
发明内容
为了解决上述技术问题,本发明提供了一种煤矿膏体充填开采的摆动式隔离装置及隔离方法,解决现在煤矿回填时待充填区隔离的问题。能够以机械方式实现待充填区隔离作业,提高充填隔离效率。
有鉴于此,本发明的目的是这样实现的,一种摆动式隔离装置及隔离方法,用于待充填区隔离作业,技术方案如下:
所述的充填隔离装置包括:伸缩机构、隔离板、抬升机构、摆动千斤顶和支架底座;伸缩机构的一端与抬升机构的一端铰接,抬升机构的另一端连接在支架底座上,伸缩机构的另一端与支架底座之间连接有摆动千斤顶,支架底座的尾部有滑道。
所述的伸缩机构包括:顶密封条、伸缩箱和伸缩千斤顶;所述顶密封条安装在伸缩箱顶部;所述伸缩箱装在隔离板内;伸缩千斤顶一端与隔离板铰接,伸缩千斤顶另一端与伸缩箱铰接。
所述的抬升机构包括:抬升座、底密封条和抬升千斤顶;所述抬升座安装在底座尾部,所述抬升座与隔离板底部铰接;底密封条安装在抬升座底部;抬升千斤顶一端与抬升座铰接,另一端与底座铰接;所述抬升座前部有导轨,抬升座的导轨插在底座滑道内。
所述的隔离板是箱型结构,或是框架结构。
所述的伸缩箱是箱型结构,或是框架结构。
所述的隔离方法包含以下步骤:
(1)在隔离装置移架前,伸缩箱在伸缩千斤顶作用下完全收入隔离板内,抬升座在抬升千斤顶作用下升起到最大高度,防止在移架过程中损坏底密封条;
(2)在进行充填准备工作时,隔离板在摆动千斤顶作用下前后摆动,为充填准备工作提供足够空间;
(3)当底板密封准备工作完成后,抬升座在抬升千斤顶控制下下压至底板挤压底密封条,实现底密封;
(4)当密封准备工作完成,进行充填工作前,隔离板调整到垂直与底板状态,并使整个工作面隔离板相互对齐;
(5)隔离板调整至待充填工作状态时,伸缩箱从隔离板内伸出直至顶板挤压顶密封条,实现顶密封;
(6)在全工作面支架尾部形成完整密封隔离挡墙,准备进行充填工作。
(7)充填完成后,待充填膏体凝固,满足支撑要求后,隔离装置前移,准备进行下一次充填。
有益效果:由于采用上述方案,顶密封条安装在伸缩箱顶部,伸缩箱装在隔离板内,伸缩箱在伸缩千斤顶控制下可从隔离板内伸出,隔离板底部与抬升座铰接,隔离板在摆动千斤顶作用下可前后摆动,底密封条安装在抬升座底部,抬升座前部有导轨,底座尾部有滑道,抬升座的导轨插在底座滑道内,抬升座受抬升千斤顶控制可相对于底座上下运动。
在进行充填隔离准备工作时,只需通过液压操纵阀操作摆动千斤顶调整隔离板位置,在抬升千斤顶作用下,利用抬升座挤压底密封条密封底板,在伸缩千斤顶作用下升起伸缩箱挤压顶密封条密封顶板,另辅以少量人工辅助措施,全工作面隔离装置依次操作,即可在支架尾部形成充填隔离挡墙,解决了在煤矿回填时待充填区隔离的问题,达到了本发明目的。
优点:能够快速设置充填隔离挡墙,保证充填隔离效果,满足充填作业要求。适用于各种膏体充填工作面。可在充填采煤中,以机械化方式设置充填隔离,保证隔离板有效密封,防止充填膏体流入工作面,有效缩短充填准备工作时间,减少人工劳动,提高膏体充填整体工作效率。
在充填采煤中,快速设置待充填区隔离,取消工人人工搭建隔离模板的工作,减少人工劳动,提高充填整体工作效率。
附图说明
图1是本发明侧视结构图。
图2是本发明整体结构立体图。
图中,1、伸缩机构;2、隔离板;3、抬升机构;4、摆动千斤顶;5、支架底座;101、顶密封条;102、伸缩箱;103、伸缩千斤顶;301、抬升座;302、底密封条;303、抬升千斤顶。
具体实施方式
下面将对本发明实施例作进一步地详细描述。
实施例1:一种摆动式隔离装置及隔离方法,用于待充填区隔离作业,技术方案如下:
所述的充填隔离装置包括:伸缩机构1、隔离板2、抬升机构3、摆动千斤顶4和支架底座5;伸缩机构1的一端与抬升机构3的一端铰接,抬升机构3的另一端连接在支架底座5上,伸缩机构1的另一端与支架底座5之间连接有摆动千斤顶4,支架底座5的尾部有滑道。
所述的伸缩机构1包括:顶密封条101、伸缩箱102和伸缩千斤顶103;所述顶密封条101安装在伸缩箱102顶部;所述伸缩箱102装在隔离板2内;伸缩千斤顶103一端与隔离板2铰接,伸缩千斤顶103另一端与伸缩箱102铰接。
所述的抬升机构3包括:抬升座301、底密封条302和抬升千斤顶303;所述抬升座301安装在底座5尾部,所述抬升座301与隔离板2底部铰接;底密封条302安装在抬升座301底部;抬升千斤顶303一端与抬升座301铰接,另一端与底座5铰接;所述抬升座301前部有导轨,抬升座301的导轨插在底座5滑道内。
所述的隔离板2是箱型结构,或是框架结构。
所述的伸缩箱102是箱型结构,或是框架结构。
所述的隔离方法包含以下步骤:
(1)在隔离装置移架前,伸缩箱102在伸缩千斤顶103作用下完全收入隔离板2内,抬升座301在抬升千斤顶303作用下升起到最大高度,防止在移架过程中损坏底密封条302;
(2)在进行充填准备工作时,隔离板2在摆动千斤顶4作用下前后摆动,为充填准备工作提供足够空间;
(3)当底板密封准备工作完成后,抬升座301在抬升千斤顶303控制下下压至底板挤压底密封条302,实现底密封;
(4)当密封准备工作完成,进行充填工作前,隔离板2调整到垂直与底板状态,并使整个工作面隔离板2相互对齐;
(5)隔离板2调整至待充填工作状态时,伸缩箱102从隔离板2内伸出直至顶板挤压顶密封条101,实现顶密封;
(6)在全工作面支架尾部形成完整密封隔离挡墙,准备进行充填工作。
(7)充填完成后,待充填膏体凝固,满足支撑要求后,隔离装置前移,准备进行下一次充填。
本发明的隔离装置,其较佳的具体实施方式是:顶密封条101安装在伸缩箱102顶部,伸缩箱102装在隔离板2内,伸缩箱102在伸缩千斤顶103控制下可从隔离板2内伸出,隔离板2底部与抬升座301铰接,隔离板2在摆动千斤顶4作用下可前后摆动,底密封条302安装在抬升座301底部,抬升座301前部有导轨,底座5尾部有滑道,抬升座301的导轨插在底座5滑道内,抬升座301受抬升千斤顶303控制可相对于底座5上下运动。
具体功能的实施步骤:
移架前准备工作。在液压支架移架前,伸缩箱102在伸缩千斤顶103作用下完全收入隔离板2内,抬升座301在抬升千斤顶303作用下升起到最大高度,防止在移架过程中损坏底密封条302。
为隔离准备工作提供必要空间。在进行充填准备工作时,隔离板2可在摆动千斤顶4作用下前后摆动,为充填准备工作提供足够空间。
底板隔离密封功能的实现。当底板密封准备工作完成后,抬升座301在抬升千斤顶303控制下下压至底板挤压底密封条302,以此实现底密封功能。
顶板隔离密封功能的实现。当密封准备工作完成,进行充填工作前,将隔离板2调整到垂直与底板状态,并使整个工作面隔离板2相互对齐,伸缩箱102从隔离板2内伸出直至顶板挤压顶密封条101,以此实现顶密封功能。
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明的保护范围之中。
Claims (6)
1. 一种煤矿膏体充填开采的摆动式隔离装置,其特征在于:该充填隔离装置包括:伸缩机构、隔离板、抬升机构、摆动千斤顶和支架底座;伸缩机构的一端与抬升机构的一端铰接,抬升机构的另一端连接在支架底座上,伸缩机构的另一端与支架底座之间连接有摆动千斤顶,支架底座的尾部有滑道。
2.根据权利要求1所述的一种煤矿膏体充填开采的摆动式隔离装置,其特征在于:所述的伸缩机构包括:顶密封条、伸缩箱和伸缩千斤顶;所述顶密封条安装在伸缩箱顶部;所述伸缩箱装在隔离板内;伸缩千斤顶一端与隔离板铰接,伸缩千斤顶另一端与伸缩箱铰接。
3.根据权利要求1所述的一种煤矿膏体充填开采的摆动式隔离装置,其特征在于:所述的抬升机构包括:抬升座、底密封条和抬升千斤顶;所述抬升座安装在底座尾部,所述抬升座与隔离板底部铰接;底密封条安装在抬升座底部;抬升千斤顶一端与抬升座铰接,另一端与底座铰接;所述抬升座前部有导轨,抬升座的导轨插在底座滑道内。
4.根据权利要求1所述的一种煤矿膏体充填开采的摆动式隔离装置,其特征在于:所述的隔离板是箱型结构,或是框架结构。
5.根据权利要求1所述的一种煤矿膏体充填开采的摆动式隔离装置,其特征在于:所述的伸缩箱是箱型结构,或是框架结构。
6.采用权利要求1所述的一种煤矿膏体充填开采的摆动式隔离装置的隔离方法,其特征在于:所述的隔离方法包含以下步骤:
在隔离装置移架前,伸缩箱在伸缩千斤顶作用下完全收入隔离板内,抬升座在抬升千斤顶作用下升起到最大高度,防止在移架过程中损坏底密封条;
在进行充填准备工作时,隔离板在摆动千斤顶作用下前后摆动,为充填准备工作提供足够空间;
当底板密封准备工作完成后,抬升座在抬升千斤顶303控制下下压至底板挤压底密封条,实现底密封;
当密封准备工作完成,进行充填工作前,隔离板调整到垂直与底板状态,并使整个工作面隔离板相互对齐;
隔离板调整至待充填工作状态时,伸缩箱从隔离板内伸出直至顶板挤压顶密封条,实现顶密封;
在全工作面支架尾部形成完整密封隔离挡墙,准备进行充填工作;
充填完成后,待充填膏体凝固,满足支撑要求后,隔离装置前移,准备进行下一次充填。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310721064.6A CN103670508B (zh) | 2013-12-24 | 2013-12-24 | 一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310721064.6A CN103670508B (zh) | 2013-12-24 | 2013-12-24 | 一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103670508A true CN103670508A (zh) | 2014-03-26 |
CN103670508B CN103670508B (zh) | 2015-10-07 |
Family
ID=50309197
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310721064.6A Active CN103670508B (zh) | 2013-12-24 | 2013-12-24 | 一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103670508B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252729A (zh) * | 2018-01-30 | 2018-07-06 | 临沂矿业集团有限责任公司 | 一种防治高压突水点无压封堵墙 |
CN109209479A (zh) * | 2018-10-29 | 2019-01-15 | 华北科技学院 | 一种巷道掘进工作面灾害隔离方法 |
CN109252891A (zh) * | 2018-11-05 | 2019-01-22 | 徐州中矿大贝克福尔科技股份有限公司 | 一种膏体充填连续柔性密封装置及隔离方法 |
CN109555544A (zh) * | 2019-01-22 | 2019-04-02 | 徐州中矿大贝克福尔科技股份有限公司 | 一种煤矿膏体充填端头液压支架 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2033450A (en) * | 1978-03-14 | 1980-05-21 | Coal Industry Patents Ltd | Shuttering system |
CN202023586U (zh) * | 2011-04-08 | 2011-11-02 | 郑州四维机电设备制造有限公司 | 用于膏体充填液压支架的后挡板机构 |
CN202325668U (zh) * | 2011-11-22 | 2012-07-11 | 徐州中矿大贝克福尔科技有限公司 | 一种带有密封垫的充填隔离板 |
CN202325590U (zh) * | 2011-11-22 | 2012-07-11 | 徐州中矿大贝克福尔科技有限公司 | 煤矿回填的充填液压支架 |
CN202451215U (zh) * | 2012-02-21 | 2012-09-26 | 淮南长壁煤矿机械有限责任公司 | 刮板输送机的防轧底防漂溜装置 |
CN203655351U (zh) * | 2013-12-24 | 2014-06-18 | 徐州中矿大贝克福尔科技有限公司 | 一种煤矿膏体充填开采的摆动式隔离装置 |
-
2013
- 2013-12-24 CN CN201310721064.6A patent/CN103670508B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2033450A (en) * | 1978-03-14 | 1980-05-21 | Coal Industry Patents Ltd | Shuttering system |
CN202023586U (zh) * | 2011-04-08 | 2011-11-02 | 郑州四维机电设备制造有限公司 | 用于膏体充填液压支架的后挡板机构 |
CN202325668U (zh) * | 2011-11-22 | 2012-07-11 | 徐州中矿大贝克福尔科技有限公司 | 一种带有密封垫的充填隔离板 |
CN202325590U (zh) * | 2011-11-22 | 2012-07-11 | 徐州中矿大贝克福尔科技有限公司 | 煤矿回填的充填液压支架 |
CN202451215U (zh) * | 2012-02-21 | 2012-09-26 | 淮南长壁煤矿机械有限责任公司 | 刮板输送机的防轧底防漂溜装置 |
CN203655351U (zh) * | 2013-12-24 | 2014-06-18 | 徐州中矿大贝克福尔科技有限公司 | 一种煤矿膏体充填开采的摆动式隔离装置 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252729A (zh) * | 2018-01-30 | 2018-07-06 | 临沂矿业集团有限责任公司 | 一种防治高压突水点无压封堵墙 |
CN109209479A (zh) * | 2018-10-29 | 2019-01-15 | 华北科技学院 | 一种巷道掘进工作面灾害隔离方法 |
CN109209479B (zh) * | 2018-10-29 | 2020-09-15 | 华北科技学院 | 一种巷道掘进工作面灾害隔离方法 |
CN109252891A (zh) * | 2018-11-05 | 2019-01-22 | 徐州中矿大贝克福尔科技股份有限公司 | 一种膏体充填连续柔性密封装置及隔离方法 |
CN109252891B (zh) * | 2018-11-05 | 2023-09-19 | 徐州中矿大贝克福尔科技股份有限公司 | 一种膏体充填连续柔性密封装置及隔离方法 |
CN109555544A (zh) * | 2019-01-22 | 2019-04-02 | 徐州中矿大贝克福尔科技股份有限公司 | 一种煤矿膏体充填端头液压支架 |
Also Published As
Publication number | Publication date |
---|---|
CN103670508B (zh) | 2015-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204646285U (zh) | 一种煤矿膏体充填开采高效隔离液压支架 | |
CN103670508A (zh) | 一种煤矿膏体充填开采的摆动式隔离装置及隔离方法 | |
CN101289939A (zh) | 沿空留巷综合支护装置 | |
CN204186410U (zh) | 一种煤矿充填用横式端头液压支架 | |
CN201554481U (zh) | 充填支护液压支架 | |
CN203655351U (zh) | 一种煤矿膏体充填开采的摆动式隔离装置 | |
CN103924994B (zh) | 自移式锚杆钻机平台 | |
CN103775124A (zh) | 一种综采工作面设备自移列车 | |
CN201539278U (zh) | 充填模板支架 | |
CN104018868A (zh) | 门式整体超前支架 | |
CN203655316U (zh) | 一种煤矿充填支架的顶部隔离装置 | |
CN204002884U (zh) | 软岩巷道超前支架防扎底装置 | |
CN208966359U (zh) | 一种煤矿膏体充填开采液压隔离支架 | |
CN204283455U (zh) | 新型薄煤层充填液压支架 | |
CN203655331U (zh) | 一种用于煤矿膏体充填开采的液压支架 | |
CN203655332U (zh) | 一种伸缩隔离式煤矿充填悬移支架 | |
CN207632432U (zh) | 一种井下移动液压支架至支护点的装置 | |
CN109057846A (zh) | 一种煤矿膏体充填开采液压隔离支架 | |
CN208996751U (zh) | 一种膏体充填液压支架用隔离装置 | |
CN103231925A (zh) | 一种井下矿车液压倒矿装置 | |
CN107879287A (zh) | 一种井下移动液压支架至支护点的装置 | |
CN203655321U (zh) | 一种搭接隔离式煤矿充填开采的悬移支架 | |
CN102086771A (zh) | 充填模板支架 | |
CN208040444U (zh) | 一种综采用液压自移式辅运设备车组的自移及支撑机构 | |
CN209483423U (zh) | 一种膏体充填端头液压支架隔离板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 221008, room 11, building 1213, Xuzhou software park north of Jinshan East Road, Jiangsu, Xuzhou Patentee after: XUZHOU CUMT BACKFILL TECHNOLOGY CO., LTD. Address before: 221008 Jiangsu city in Xuzhou Province, the liberation of South Park Mine Technology Pioneering Park Room 216 Patentee before: Xuzhou Zhongkuangda Baker Sherlock Technology Co.,Ltd. |