WO2021186770A1 - 間仕切壁と床版の接続構造とその施工方法 - Google Patents

間仕切壁と床版の接続構造とその施工方法 Download PDF

Info

Publication number
WO2021186770A1
WO2021186770A1 PCT/JP2020/037445 JP2020037445W WO2021186770A1 WO 2021186770 A1 WO2021186770 A1 WO 2021186770A1 JP 2020037445 W JP2020037445 W JP 2020037445W WO 2021186770 A1 WO2021186770 A1 WO 2021186770A1
Authority
WO
WIPO (PCT)
Prior art keywords
floor
stud
runner
partition wall
floor slab
Prior art date
Application number
PCT/JP2020/037445
Other languages
English (en)
French (fr)
Inventor
渉 大内
Original Assignee
吉野石膏株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 吉野石膏株式会社 filed Critical 吉野石膏株式会社
Priority to CN202080092325.0A priority Critical patent/CN114981508B/zh
Priority to BR112022013661A priority patent/BR112022013661A2/pt
Priority to KR1020227032025A priority patent/KR20220137122A/ko
Priority to US17/759,650 priority patent/US20230085256A1/en
Priority to AU2020436409A priority patent/AU2020436409B2/en
Priority to EP20925988.6A priority patent/EP4098823A4/en
Priority to MX2022011211A priority patent/MX2022011211A/es
Priority to JP2022508038A priority patent/JP7465577B2/ja
Priority to CA3164279A priority patent/CA3164279A1/en
Publication of WO2021186770A1 publication Critical patent/WO2021186770A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/94Protection against other undesired influences or dangers against fire
    • E04B1/941Building elements specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • E04B2/82Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal

Definitions

  • This disclosure relates to the connection structure between the partition wall and the floor slab and its construction method.
  • the fire protection performance of the walls that make up the building is stipulated in the Building Standards Law, and it is necessary to comply with the interior restrictions and fire protection performance stipulated in the Building Standards Law for the structure and constituent materials of the walls.
  • the Building Standards Law stipulates the structure of the entire building as a fireproof building or semi-fireproof building based on the purpose and scale of the building, area designation, etc., as well as the use and scale of the building, prevention of fire spread, and evacuation. From the viewpoint of smoke exhaust, fire extinguishing, etc., the fireproof performance of interior materials, inner wall structures, fitting structures, pipe penetrations, etc. is regulated.
  • the non-combustible performance of building interior materials is classified into predetermined non-combustible grades (non-combustible materials, semi-non-combustible materials, and flame-retardant materials).
  • the fire protection performance of the walls of buildings is classified into predetermined structural types (fireproof structure, semi-fireproof structure, fireproof structure, semi-fireproof structure, etc.).
  • a fireproof partition wall by a dry method to which a fireproof board such as gypsum board or calcium silicate board is attached is provided between the pit section and the adjacent space. It is applied as a partition wall.
  • This pit section includes an elevator shaft, a staircase, and the like, and the adjacent space adjacent to them includes an elevator hall, a passage, a living room, and the like.
  • the vertical hole section is partitioned by a partition wall, and the upper and lower floor rooms are arranged above and below the reinforced concrete floor slab adjacent to the vertical hole section. Construction errors are often present. Therefore, a runner is installed flush with the pit section side end face of the floor slab to build the stud (thus, the stud is also flush with the pit section side end face of the floor slab), and the wall material facing the pit section on the stud. Is difficult to construct. Therefore, the upper and lower runners are installed on the floor slab in a state where the upper and lower runners are projected from the pit section side end face of the floor slab to the pit section side, studs are built in the upper and lower runners, and the upper and lower studs face the pit section. The method of constructing wall materials has been applied.
  • FIG. 1 is a vertical cross section showing an example of a connection structure between the partition wall and the floor slab that separates the conventional vertical hole section from the upper and lower floor chambers above and below the floor slab adjacent to the pit section. It is a figure.
  • FIG. 1 on the left side of the vertical hole section 10, there is a floor slab 20 made of reinforced concrete to be constructed on site, which is supported by a floor beam 25 formed of a shaped steel material such as H-shaped steel.
  • the upper first partition wall 30 and the lower second partition wall 40 which separate the upper floor room 13 and the lower floor room 15 above and below the floor slab 20 from the vertical hole section 10, are connected to the floor slab 20 and the floor beam 25, respectively. By doing so, a connecting structure 90 between the partition wall and the floor slab is formed.
  • the floor slab 20 made of reinforced concrete has irregularities on the pit section side end surface 21 due to a construction error. This unevenness exists not only in the vertical direction shown in FIG. 1 but also in the depth direction of the paper surface of FIG. Therefore, on the upper surface of the floor slab 20, the lower runner 31 which constitutes the upper first partition wall 30 and is formed of the building steel base material is stretched from the pit section side end surface 21 to the pit section side by a width t1. It is arranged in a put-out state, and is fixed to the floor slab 20 by a fixing member 70 such as a screw or a stud.
  • a fixing member 70 such as a screw or a stud.
  • the runner receiving members 37A and 37B are fixed to the vertical hole section side of the web 25b by welding or the like. Further, with respect to the runner receiving materials 37A and 37B, the runners 35 in the upper and lower floor beams formed of the building steel base material face each other with the openings of the fixing members 70 such as screws and tapping screws. It is fixed. Then, inside the upper and lower floor beam runners 35, the floor beam studs 36 are arranged. These upper and lower floor beam runners 35 are also attached to the runner receiving members 37A and 37B in a state of projecting from the vertical hole section side end surface 21 of the floor slab 20 to the vertical hole section side by a width t1.
  • the runner receiving material 37C is fixed to the lower surface of the flange 25a below the floor beam 25 by welding or the like. Then, the upper runner 33, which constitutes the lower second partition wall 40 with respect to the runner receiving material 37C and is formed of the building steel base material, is stretched from the vertical hole section side end surface 21 to the vertical hole section side by a width t1. It is arranged in a protruding state, and is attached to the runner receiving member 37C by a fixing member 70 such as a screw or a tapping screw.
  • first partition wall 30 a plurality of first studs 32 are built between the upper runner (not shown) and the lower runner 31 at intervals in the width direction of the wall (depth direction in FIG. 1).
  • the second wall material 60A is attached to the indoor side of each first stud 32.
  • a plurality of second studs 34 are built between the lower lower runner (not shown) and the upper runner 33 at intervals in the width direction of the wall (depth direction in FIG. 1).
  • the third wall material 60B is attached to the indoor side of each second stud 34.
  • the first stud 32 extends over the second stud 34 and faces the pit section 10.
  • One wall material 50 is attached.
  • the first wall material 50, the second wall material 60A, and the third wall material 60B all have a laminated structure in which, for example, the underlaying materials 51, 61, 64 and the upholstery materials 52, 62, 65 are laminated in the wall thickness direction. It has, and is fixed to the first stud 32, the second stud 34, and the stud 36 in the floor beam by a fixing member 70 such as a screw or a tapping screw.
  • the underlaying material 51, 61, 64 and the upholstery material 52, 62, 65 may both be formed of gypsum board, or the underlaying material 51, 61, 64 and the upholstery material 52, 62, 65 may be formed.
  • One may be formed of gypsum board and the other may be formed of calcium silicate board or the like.
  • the first partition wall 30 is composed of the second wall material 60A forming the upper floor room, the first stud 32, the lower runner 31 and the upper runner (not shown), and the first wall material 50.
  • the second partition wall 40 is composed of the third wall material 60B forming the lower floor room, the second stud 34, the upper runner 33 and the lower runner (not shown), and the first wall material 50. .. Then, the fireproof coating material 28 is sprayed around the floor beam 25 to form a connection structure 90 between the partition wall and the floor slab having fireproof performance.
  • the first stud 32, the second stud 34, and the stud in the floor beam are located at the inner corners of the lower runner 31, the upper runner 33, and the runner in the floor beam 35 on the overhang side, which are formed of the steel base material for construction.
  • a pushing force P due to an out-of-plane moment from 36 may act.
  • at least a part of the first stud 32, the second stud 34, and the stud 36 in the floor beam is displaced further toward the pit section than the width t1, and the lower runner 31, the upper runner 33, and the floor beam are displaced.
  • At least a part of the overhanging portion of the inner runner 35 is bent and deformed downward or upward (deformation ⁇ ).
  • the upper end of the second stud 34 is fitted with a clearance with respect to the upper runner 33. This also applies when the upper end of the first stud 32 is fitted to the upper runner (not shown) and the upper end of the floor beam inner stud 36 is fitted to the upper floor beam runner 35.
  • the upper ends of the first stud 32, the second stud 34, and the stud 36 in the floor beam are likely to come off from the upper runner, the upper runner 33, and the upper floor beam runner 35 (not shown), which are large as described above.
  • the first stud 32, the second stud 34, and the stud 36 in the floor beam also come off from the upper runner, the upper runner 33, and the upper floor beam runner 35 (not shown).
  • the connection structure 90 can be damaged.
  • connection structure 90 in which the first partition wall 30 and the lower second partition wall 40 are connected is formed, there is a possibility that the connection structure 90 may be damaged in the event of a large earthquake or the like.
  • a fire-resistant joint material is provided to prevent the local deterioration of the fire-resistant performance that may occur at the joint intersection between the horizontal joint of the base surface material and the vertical joint of the interior decorative board, and improve the fire-resistant performance of the partition wall.
  • Fireproof partition walls have been proposed.
  • the refractory joint material is inserted into the vertical joint of the refractory partition wall extending between the upper and lower horizontal refractory compartments, and the partition wall is formed with a vertical frame member extending between the horizontal refractory compartments and the horizontal direction. It is composed of a base surface material oriented in a direction and an interior decorative board formed on the base surface material.
  • the fire-resistant joint material includes an insertion portion inserted between the edge of the interior decorative board and the base surface material, and a joint bottom portion that hides the joint bottom of the vertical joint of the interior decorative board. , At least at the intersection of the horizontal joint and the vertical joint, it is arranged in the vertical joint and closes the joint base of the vertical joint (see, for example, Patent Document 1).
  • the runner even when a pushing force is applied from the stud to the runner in the event of a large earthquake or the like, the runner is not deformed and the connection structure is not damaged, and the wall material facing the vertical hole section is accurately attached to the stud. It provides a connection structure between a partition wall and a floor slab and its construction method.
  • the connection structure between the partition wall and the floor slab is The upper first partition wall and the lower second partition wall that separate the vertical hole section and the upper and lower floor rooms above and below the floor slab adjacent to the vertical hole section are connected to the floor slab. It is a connection structure between the partition wall and the floor slab. Above the floor slab, a lower runner in which the lower end of the first stud forming the first partition wall is housed is installed. Below the deck, an upper runner is installed to accommodate the upper end of the second stud that forms the second partition wall. In the pit section, the first wall material extending from the first stud over the second stud is fixed to the first stud via the first floor plate and is fixed to the first stud via the second floor plate.
  • the second wall material forming the upper floor chamber, the first stud, the lower runner, and the first wall material form the first partition wall.
  • the third wall material forming the lower floor chamber, the second stud, the upper runner, and the first wall material form the second partition wall.
  • connection structure between the partition wall and the floor slab is described.
  • the upper first partition wall and the lower second partition wall that separate the vertical hole section and the upper and lower floor rooms above and below the floor slab adjacent to the vertical hole section are connected to the floor slab.
  • It is a construction method of the connection structure between the partition wall and the floor slab. It has a runner installation process, a stud building process, and a partition wall forming process.
  • the runner installation process is Above the deck, a lower runner is installed to accommodate the lower end of the first stud that forms the first partition wall, and below the deck, the upper end of the second stud that forms the second partition wall.
  • the partition wall forming step is In the pit section, the first wall material extending from the first stud over the second stud is fixed to the first stud via the first floor plate, and the second floor plate is formed. Fixed to the second stud through The second wall material forming the upper floor chamber is fixed to the first stud, and the first partition wall is formed by the second wall material, the first stud, the lower runner, and the first wall material. Form and The third wall material forming the lower floor chamber is fixed to the second stud, and the second partition wall is formed by the third wall material, the second stud, the upper runner, and the first wall material. To form.
  • the runner is not deformed and the connection structure is not damaged, and the wall material facing the pit section is accurately attached to the stud. It is possible to provide a connection structure between the partition wall and the floor slab.
  • FIG. 3 is a vertical cross-sectional view showing an example of the connection structure between the partition wall and the floor slab according to the embodiment.
  • connection structure 100 between the partition wall and the floor slab shown in the figure is an upper first partition that separates the vertical hole section 10 from the upper floor chamber 13 and the lower floor room 15 adjacent to the vertical hole section 10 and above and below the floor slab 20.
  • the wall 30 and the lower second partition wall 40 are formed by being connected to the deck 20 and the floor beam 25, respectively.
  • the vertical hole section 10 to which the connection structure 100 is applied includes an elevator shaft, a staircase, a duct shaft, a piping shaft, and the like, and the upper floor room 13 and the lower floor room 15 which are adjacent spaces adjacent to them include an elevator. Includes halls, passages, living rooms, conference rooms, administration rooms, etc.
  • the building to which the connection structure 100 is applied can be applied not only to steel-framed buildings, but also to RC (Reinforced Concrete) buildings, wooden buildings, etc., and can be applied to factories, warehouses, buildings, condominiums, and general buildings. Detached houses, etc. are applicable.
  • the floor slab 20 made of reinforced concrete is formed by on-site construction, and has irregularities on the pit section side end surface 21 due to a construction error. This unevenness exists not only in the vertical direction shown in the drawing but also in the depth direction of the paper surface shown in FIG.
  • the lower runner 31 forming the upper first partition wall 30 and formed of the building steel base material has a width closer to the upper floor room side than the vertical hole section side end surface 21 of the floor slab 20. It is arranged at a position where only t3 is set back, and is fixed to the floor slab 20 by a fixing member 70 such as a screw or a stud.
  • runner receiving materials 37A and 37B are fixed to the vertical hole section side of the web 25b by welding or the like, and the runner receiving materials 37A and 37B are made of steel for construction.
  • the upper and lower floor beam runners 35 formed of the base material are fixed by fixing members 70 such as screws and tapping screws in a posture in which both openings face each other. Then, the studs 36 in the floor beams are arranged inside the runners 35 in the upper and lower floor beams.
  • the vertical hole section side flanges 35a of the upper and lower floor beam runners 35 are arranged at positions set back by a width t3 on the lower floor chamber side of the vertical hole section side end surface 21 of the floor slab 20, and the upper and lower runner receiving members 37A. , 37B is fixed by a fixing member 70 such as a screw or a tapping screw.
  • the vertical hole section side flanges 35a of the upper and lower floor beam runners 35 are arranged on the lower floor chamber side between the upper runner receiving material 37A and the lower runner receiving material 37B.
  • a runner receiving material 37C is fixed to the lower surface of the flange 25a below the floor beam 25 by welding or the like.
  • the upper runner 33 which constitutes the lower second partition wall 40 with respect to the runner receiving material 37C and is formed of the building steel base material, is on the lower floor room side of the vertical hole section side end surface 21 of the floor slab 20. It is arranged at a position where only the width t3 is set back, and is fixed to the runner receiving member 37C by a fixing member 70 such as a screw or a tapping screw.
  • first partition wall 30 there is an interval between the upper runner (not shown) and the lower runner 31 in the width direction of the wall (depth direction in FIG. 3) (for example, at intervals of 606 mm or less, 606 mm, 455 mm, etc.).
  • a plurality of first studs 32 formed of a steel base material for construction with a lip are built in.
  • a second wall material 63 is attached to the indoor side of each first stud 32.
  • the second partition wall 40 there is an interval (for example, an interval of 606 mm or less, 606 mm) between the lower lower runner (not shown) and the upper runner 33 in the width direction of the wall (depth direction in FIG. 3). (455 mm, etc.) are placed, and a plurality of second studs 34 formed of a steel base material for construction with a lip are built. A third wall material 66 is attached to the indoor side of each second stud 34.
  • the first stud 32, the second stud 34, and the stud 36 in the floor beam may be formed of square steel in addition to the building steel base material with a lip.
  • the building steel base materials applied to the first stud 32, the second stud 34, and the stud 36 in the floor beam include lightweight shaped steel for general structure (JIS G 3350) and hot-dip galvanized steel sheet (JIS G 3302). Etc. can be applied.
  • a material having a thickness of 0.4 mm or more of 45 to 500 ⁇ 45 to 75 ⁇ 8 to 32 can be applied, and the shape and dimensions of the square steel are 45 to 500 ⁇ 40 to 350.
  • a thickness of 0.4 mm or more can be applied.
  • the building steel base material applied to the lower runner 31, the upper runner 33, and the floor beam runner 35 includes lightweight shaped steel for general structure (JIS G 3350), hot-dip galvanized steel sheet (JIS G 3302), and the like. Can be applied, and those having a size of 45 to 500 ⁇ 35 to 75 and a thickness of 0.4 mm or more can be applied.
  • the first wall material 50 extending from the first stud 32 to the second stud 34 is attached. There is.
  • the first wall material 50, the second wall material 63, and the third wall material 66 all have a laminated structure in which, for example, the underlaying materials 51, 61, 64 and the upholstery members 52, 62, 65 are laminated in the wall thickness direction. It has, and is fixed to the first stud 32, the second stud 34, and the stud 36 in the floor beam by a fixing member 70 such as a screw or a tapping screw.
  • the underlaying materials 51, 61, 64 and the upholstery materials 52, 62, 65 may be formed of gypsum plate or gypsum board, or the underlaying materials 51, 61, 64 and the upholstery material 52,
  • One of 62 and 65 may be formed of gypsum board or gypsum board, and the other may be formed of calcium silicate board or the like.
  • a gypsum board having a thickness of 9.5 mm to 25 mm specified in JIS A 6901 can be applied to the gypsum board.
  • "Tiger board (registered trademark) type Z" manufactured by Yoshino Gypsum Co., Ltd. Can be applied.
  • underlaying materials 51, 61, 64 and the upholstery materials 52, 62, 65 are adhered to each other by an adhesive.
  • a vinyl acetate resin adhesive, an acrylic resin adhesive, a urethane adhesive, an epoxy resin adhesive, a silicone adhesive, or the like can be applied to this adhesive.
  • one or both of the underlaying material 51 and the upholstery material 52 constituting the first wall material 50 have a width of 10 mm or less.
  • a watermark may be provided. Then, the watermark may be filled with a sealing material such as polyurethane, acrylic, or silicone.
  • a floor finishing material is applied on the floor slab 20, and the surfaces of the upholstery members 62 and 65 are given an interior finish by cloth, painting, etc., and the interior finishing surface is on the indoor side. Is exposed to. Then, although not shown, the skirting board is constructed so as to straddle the floor finishing material and the interior finishing surface constructed above the floor slab 20.
  • the first wall material 50 and the first stud 32 are mutually fixed by fixing members 70 such as screws, tapping screws, and staples via a first floor plate 80A having a thickness of t2. .. Further, the first wall material 50 and the second stud 34 are fixed to each other by the fixing member 70 via the second floor plate 80B having the same thickness t2. Further, the first wall material 50 and the stud 36 in the floor beam are fixed to each other by the fixing member 70 via the third floor plate 80C having the same thickness t2.
  • the first floor board 80A, the second floor board 80B, and the third floor board 80C are gypsum board, gypsum board, reinforced gypsum board, non-combustible laminated gypsum board, fiber reinforced cement board, glass wool, rock wool. , Glass fiber felt, rock wool felt, etc., with a thickness of about 25 mm or less and a width of 40 mm or more can be applied.
  • the first floor plate 80A, the second floor plate 80B, and the third floor plate 80C may have a thickness of more than 25 mm as a whole by stacking two or more floor plates. good.
  • the first stud 32 and the second stud 34, and the stud 36 in the floor beam are the first floor board 80A and the second floor, respectively. Only the thickness t2 of the perforated board 80B and the third floor board 80C is set back on the upper floor room side and the lower floor room side.
  • the lower runner 31, the upper runner 33, and the runner in the floor beam 35 are all located on the upper floor room side and the lower floor room side of the floor slab 20 on the vertical hole section side end surface 21. Each is arranged at a position set back by the width t3. As a result, as shown in FIG.
  • a horizontal force H acts on the first partition wall 30 and the second partition wall 40 at the time of an earthquake, and the lower runner 31 and the upper runner 33 from the first stud 32, the second stud 34, etc. Even when the pushing force P acts on the lower runner 31 and the upper runner 33, the lower runner 31 and the upper runner 33 are not deformed. Therefore, it is possible to prevent damage to the connection structure 100 due to deformation of the lower runner 31 and the upper runner 33.
  • first floor plate 80A, the second floor plate 80B, and the third floor plate 80C are placed between the first stud 32, the second stud 34, the stud 36 in the floor beam, and the first wall material 50. It is intervening. With this configuration, even if the reinforced concrete floor slab 20 to be constructed on-site has irregularities on the vertical hole section side end surface 21 due to a construction error, the first stud 32, the second stud 34, and the inside of the floor beam The first wall material 50 can be attached to the stud 36 with high accuracy.
  • connection structure 100 the gap formed between the vertical hole section side end surface 21 and the first wall material 50 in the floor slab 20 is filled with the refractory material 85 formed of rock wool or the like. Further, a fireproof coating material 28 is formed around the floor beam 25 by spraying or the like.
  • the fireproof coating material 28 is formed of, for example, a laminated body of heat-resistant rock wool molded into a felt shape and a flame-retardant non-woven fabric.
  • the fireproof coating material 28 is provided around the floor beam 25, and the vertical hole section side end surface 21 and the first in the floor slab 20. Since the gap between the wall materials 50 is filled with the refractory material 85, the connection structure 100 having excellent fire resistance is formed.
  • FIGS. 4, 5 and 3 are vertical cross-sectional views for explaining an example of a method of constructing a connection structure between the partition wall and the floor slab according to the embodiment in order.
  • the construction method according to the embodiment includes a floor slab construction process, a runner installation process, a stud building process, and a partition wall forming process.
  • the floor slab 20 made of reinforced concrete is constructed on-site so as to be supported by the floor beam 25 formed of H-shaped steel (floor slab construction process).
  • the lower runner 31 in which the lower end of the first stud 32 forming the first partition wall 30 is accommodated is fixed by the fixing member 70.
  • the upper runner 33 in which the upper end of the second stud 34 forming the second partition wall 40 is housed is fixed by the fixing member 70.
  • runner receiving materials 37A and 37B are fixed to the vertical hole section side of the web 25b by welding or the like, and the runners in the upper and lower floor beams are fixed to the runner receiving materials 37A and 37B.
  • the 35 is fixed by the fixing member 70 in a posture in which both openings face each other.
  • floor beam studs 36 are arranged inside the upper and lower floor beam runners 35.
  • the lower runner 31, the upper runner 33, and the floor beam runner 35 are respectively from the starting point Q on the installation line L1.
  • Only the thickness t2 of the first floor plate 80A, the second floor plate 80B, and the third floor plate 80C is installed at the positions set back on the upper floor room side and the lower floor room side (the above is the runner installation process). ).
  • a fireproof coating material 28 is formed around the floor beam 25 by spraying or the like, and the fireproof material 85 is filled on the side of the vertical hole section side end surface 21 of the floor slab 20. ..
  • the lower end of the first stud 32 is housed in the lower runner 31 and built.
  • the upper end of the first stud 32 is fitted into the upper runner (not shown).
  • the first floor plate 80A is attached to the vertical hole section side of the first stud 32.
  • the upper end of the second stud 34 is housed in the upper runner 33 and built.
  • the lower end of the second stud 34 is fitted into the lower runner (not shown).
  • the second floor plate 80B is attached to the vertical hole section side of the second stud 34.
  • a third floor plate 80C is installed on the side surface of the stud 36 in the floor beam on the vertical hole section side.
  • the first floor plate 80A, the second floor plate 80B, and the third floor plate 80C are adhesive tapes (both sides). Temporarily fastened with adhesive (including adhesive tape), adhesive, tapping screw, etc.
  • a pressure-sensitive adhesive such as an acrylic resin type, a polyamide type, a natural rubber type, or a synthetic rubber type can be applied, and an adhesive tape having a thickness of 3 mm or less and a width of 100 mm or less can be applied.
  • the third floor plate 80C is temporarily fixed to the stud 36 in the floor beam in advance, and when the stud 36 in the floor beam is installed in the runner installation process, the installation of the third floor plate 80C is completed at the same time. It may be (the above is the stud building process).
  • the first wall material 50 extending from the first stud 32 to the second stud 34 is attached to the fixing member 70 via the first floor plate 80A. It is fixed to the first stud 32, fixed to the second stud 34 by the fixing member 70 via the second floor plate 80B, and fixed to the second stud 34 by the fixing member 70 via the third floor plate 80C. Fix to. By fixing with these fixing members 70, the first floor plate 80A or the like temporarily fixed to the first stud 32 or the like is firmly fixed to the first stud 32 or the like.
  • the second wall material 63 forming the upper floor chamber 13 to the first stud 32 with the fixing member 70, the second wall material 63, the first stud 32, the lower runner 31 and the upper runner ( (Not shown) and the first wall material 50 form the first partition wall 30.
  • the second partition wall 40 is formed by the first wall material 50, and the connection structure 100 is constructed (the above is the partition wall forming step).
  • the lower runner 31, the upper runner 33, and the like set a predetermined amount on the floor slab 20 from the vertical hole section side end surface 21 having the unevenness to the upper floor room side and the lower floor room side. It is installed in the back position. As a result, damage to the lower runner 31 and the like during an earthquake or the like can be eliminated, and the first wall material 50 is accurately attached to the first stud 32 and the like via the first floor plate 80A and the like. It becomes possible to efficiently construct the existing connection structure 100.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Building Environments (AREA)
  • Load-Bearing And Curtain Walls (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Floor Finish (AREA)

Abstract

スタッドからランナーに押し込み力が作用した場合でもランナーが変形して接続構造が破損することがなく、竪穴区画に対向する壁材がスタッドに精度よく取り付けられている、間仕切壁と床版の接続構造とその施工方法を提供する。竪穴区画10と、竪穴区画10に隣接して床版20の上下にある上階室13及び下階室15と、を隔てる第一間仕切壁30及び第二間仕切壁40が床版20に接続されている接続構造100であり、床版20の上方に第一スタッド32の下端が収容される下ランナー31が設置され、床版20の下方に第二間仕切壁40を形成する第二スタッド34の上端が収容される上ランナー33が設置され、竪穴区画10において第一スタッド32から第二スタッド34に跨って延設する第一壁材50が、第一敷目板80Aを介して第一スタッド32に固定され、第二敷目板80Bを介して第二スタッド34に固定されている。

Description

間仕切壁と床版の接続構造とその施工方法
 本開示は、間仕切壁と床版の接続構造とその施工方法に関する。
 建築物を構成する壁の防耐火性能は建築基準法に規定されており、壁の構造や構成材料については、建築基準法に規定された内装制限や防耐火性能を遵守する必要がある。例えば、建築基準法は、建築物の用途や規模、地域指定等に基づき、耐火建築物もしくは準耐火建築物として建築物全体の構造を規定するとともに、建築物の用途や規模、延焼防止、避難、排煙、消火等の観点から、内装材料や内壁構造、建具構造、配管貫通部等に関する防耐火性能を規制している。現行の建築基準法の下では、建築物の内装材料の不燃性能は、所定の不燃等級(不燃材、準不燃材、及び難燃材)に分類されている。また、建築物の壁の防耐火性能は、所定の構造種別(耐火構造、準耐火構造、防火構造、準防火構造等)に分類されている。
 一方、建築物の軽量化の観点から、軽量鉄骨製のスタッドの両面において、石膏ボードもしくは珪酸カルシウム板等の耐火ボードが取り付けられた乾式工法による耐火間仕切壁が、竪穴区画とその隣接空間との仕切壁として適用されている。この竪穴区画には、エレベータシャフトや階段室等が含まれ、それらに隣接する隣接空間には、エレベータホールや通路、居室等が含まれる。
 ところで、竪穴区画を間仕切壁で仕切り、竪穴区画に隣接する鉄筋コンクリート製等の床版の上下に上階室と下階室が配置される、接続構造の施工に際し、現場施工される床版には施工誤差が往々にして存在する。そのため、床版の竪穴区画側端面と面一にランナーを設置してスタッドを建て込み(従って、スタッドも床版の竪穴区画側端面と面一になる)、スタッドに竪穴区画に対向する壁材を施工することは困難である。そこで、床版の竪穴区画側端面から竪穴区画側に上下のランナーを張り出させた状態で床版に設置し、上下のランナーにスタッドを建て込み、上下のスタッドに対して竪穴区画に対向する壁材を施工する方法が適用されている。
 このことを、図1を参照してより詳細に説明する。ここで、図1は、従来の、竪穴区画と、竪穴区画に隣接する床版の上下にある上階室及び下階室とを隔てる、間仕切壁と床版の接続構造の一例を示す縦断面図である。
 図1において、竪穴区画10の左側には、H形鋼等の形鋼材により形成される床梁25に支持される、現場にて施工される鉄筋コンクリート製の床版20がある。床版20の上下にある上階室13及び下階室15と竪穴区画10とを隔てる、上方の第一間仕切壁30と下方の第二間仕切壁40が床版20と床梁25にそれぞれ接続されることにより、間仕切壁と床版の接続構造90が形成される。
 鉄筋コンクリート製の床版20は、施工誤差により、その竪穴区画側端面21に凹凸を有している。この凹凸は、図1に示す縦方向に亘って存在する他にも、図1の紙面奥行き方向にも存在する。そのため、床版20の上面においては、上方の第一間仕切壁30を構成し、建築用鋼製下地材により形成される下ランナー31が、竪穴区画側端面21から幅t1だけ竪穴区画側に張り出させた状態で配設され、ビスや鋲等の固定部材70により床版20に固定される。
 一方、床梁25の上下のフランジ25aのうち、ウエブ25bよりも竪穴区画側には、ランナー受け材37A,37Bが溶接等により固定される。また、ランナー受け材37A,37Bに対して、建築用鋼製下地材により形成される上下の床梁内ランナー35が双方の開口を対向させた姿勢でビスやタッピンねじ等の固定部材70にて固定される。そして、上下の床梁内ランナー35の内部において、床梁内スタッド36が配設される。これら上下の床梁内ランナー35も、床版20の竪穴区画側端面21から幅t1だけ竪穴区画側に張り出させた状態で、ランナー受け材37A,37Bに取り付けられる。
 さらに、床梁25の下方のフランジ25aの下面には、ランナー受け材37Cが溶接等により固定される。そして、ランナー受け材37Cに対して、下方の第二間仕切壁40を構成し、建築用鋼製下地材により形成される上ランナー33が、竪穴区画側端面21から幅t1だけ竪穴区画側に張り出させた状態で配設され、ビスやタッピンねじ等の固定部材70によりランナー受け材37Cに取り付けられる。
 第一間仕切壁30では、上方の上ランナー(図示せず)と下ランナー31の間において、壁の幅方向(図1の奥行き方向)に間隔を置いて複数の第一スタッド32が建て込まれ、各第一スタッド32の室内側に第二壁材60Aが取り付けられる。一方、第二間仕切壁40では、下方の下ランナー(図示せず)と上ランナー33の間において、壁の幅方向(図1の奥行き方向)に間隔を置いて複数の第二スタッド34が建て込まれ、各第二スタッド34の室内側に第三壁材60Bが取り付けられる。
 そして、第一スタッド32、第二スタッド34、及び床梁内スタッド36の竪穴区画側の端面には、第一スタッド32から第二スタッド34に跨って延設し、竪穴区画10に対向する第一壁材50が取り付けられている。
 第一壁材50、第二壁材60A及び第三壁材60Bはいずれも、例えば、下張り材51,61,64と、上張り材52,62,65が壁厚方向に積層した積層構造を有しており、第一スタッド32、第二スタッド34、及び床梁内スタッド36に対してビスやタッピンねじ等の固定部材70にて固定されている。ここで、下張り材51,61,64と、上張り材52,62,65は、いずれも石膏ボードにより形成されてもよいし、下張り材51,61,64と上張り材52,62,65の一方が石膏ボードにより形成され、他方が珪酸カルシウム板等により形成されてもよい。
 上階室を形成する第二壁材60Aと、第一スタッド32と、下ランナー31及び上ランナー(図示せず)と、第一壁材50とにより第一間仕切壁30が構成される。一方、下階室を形成する第三壁材60Bと、第二スタッド34と、上ランナー33及び下ランナー(図示せず)と、第一壁材50とにより第二間仕切壁40が構成される。そして、床梁25の周囲に耐火被覆材28が吹き付け施工等されることにより、耐火性能を有する間仕切壁と床版の接続構造90が形成される。
 図2に示すように、第一間仕切壁30や第二間仕切壁40に対して、例えば大規模な地震の際の大きな水平力Hが作用する場合を検証する。下ランナー31や上ランナー33,床梁内ランナー35が、床版20の竪穴区画側端面21から幅t1だけ竪穴区画側に張り出している。そのため、第一間仕切壁30等に水平力Hが作用すると、第一間仕切壁30等には水平力Hに起因する面外方向へのモーメントが生じる。そして、建築用鋼製下地材により形成される下ランナー31や上ランナー33,床梁内ランナー35の張り出し側の内側隅角部には、第一スタッド32や第二スタッド34、床梁内スタッド36から面外方向へのモーメントに起因する押し込み力Pが作用し得る。そして、この押し込み力Pにより、第一スタッド32、第二スタッド34、床梁内スタッド36の少なくとも一部が、幅t1よりもさらに竪穴区画側にずれ、下ランナー31や上ランナー33,床梁内ランナー35の張り出し箇所の少なくとも一部が折れ曲がって下方や上方に変形する(変形δ)。この結果、第一スタッド32、第二スタッド34、床梁内スタッド36の少なくとも一部が、下ランナー31、上ランナー33,床梁内ランナー35から外れることにより、接続構造90の少なくとも一部が破損に至り得る。また、施工性を勘案して、第二スタッド34の上端は、上ランナー33に対してクリアランスを有した状態で嵌め込まれる。そして、このことは、第一スタッド32の上端を不図示の上ランナーに対してや、床梁内スタッド36の上端を上の床梁内ランナー35に対して嵌め込む際にも同様である。そのため、第一スタッド32、第二スタッド34、及び床梁内スタッド36の上端は不図示の上ランナーや上ランナー33、上の床梁内ランナー35から外れ易くなっており、上記するように大きな水平力Hが作用した際には、第一スタッド32、第二スタッド34、及び床梁内スタッド36が、不図示の上ランナーや上ランナー33、上の床梁内ランナー35から外れることによっても、接続構造90が破損に至り得る。
 このように、下ランナー31や上ランナー33等の一部を床版20の竪穴区画側端面21から張り出させることにより、床版20の施工誤差を許容しながら、床版20に対して上方の第一間仕切壁30と下方の第二間仕切壁40が接続された接続構造90を形成する場合、大地震時等において接続構造90が破損に至り得るといった恐れがある。
 ここで、下地面材の横目地と、内装化粧板の縦目地との目地交差部に生じ得る局所的な耐火性能の劣化を防止し、間仕切壁の耐火性能を向上させる耐火目地材を備えた耐火間仕切壁が提案されている。具体的には、耐火目地材は、上下の水平耐火区画の間に延びる耐火間仕切壁の縦目地に挿入され、間仕切壁は、水平耐火区画の間に延びる垂直な軸組部材と、横張り方向に配向された下地面材と、下地面材の上に形成される内装化粧板とにより構成される。耐火目地材は、内装化粧板の縁部と、下地面材との間に介挿される挿入部と、内装化粧板の縦目地の目地底を隠蔽する目地底部分とを備え、耐火目地材は、少なくとも横目地及び縦目地の交差部において縦目地内に配置され、縦目地の目地底を閉塞する(例えば、特許文献1参照)。
特開2002-309691号公報
 特許文献1に記載の耐火間仕切壁によれば、片側の室に火災が発生した際に、間仕切壁の裏面全域が比較的平均的に温度上昇し、局部的な高温域が発生せず、優れた耐火性能を発揮することができる。しかしながら、特許文献1に記載の耐火間仕切壁を適用したとしても、図2を参照して説明した上記課題、すなわち、床版の施工誤差を許容しながら、床版に設置されている上下のランナーの変形に起因する接続構造の破損を解消して、上下のスタッドに対して竪穴区画に対向する壁材を精度よく接続するといった課題を解消することはできない。
 本開示は、大地震時等において、スタッドからランナーに押し込み力が作用した場合でもランナーが変形して接続構造が破損することがなく、竪穴区画に対向する壁材がスタッドに精度よく取り付けられている、間仕切壁と床版の接続構造とその施工方法を提供する。
 本開示の一態様による間仕切壁と床版の接続構造は、
 竪穴区画と、該竪穴区画に隣接して床版の上下にある上階室及び下階室と、を隔てる上方の第一間仕切壁及び下方の第二間仕切壁が、前記床版に接続されている、間仕切壁と床版の接続構造であって、
 前記床版の上方には、前記第一間仕切壁を形成する第一スタッドの下端が収容される下ランナーが設置され、
 前記床版の下方には、前記第二間仕切壁を形成する第二スタッドの上端が収容される上ランナーが設置されており、
 前記竪穴区画において、前記第一スタッドから前記第二スタッドに跨って延設する第一壁材が、第一敷目板を介して前記第一スタッドに固定され、かつ第二敷目板を介して前記第二スタッドに固定されており、
 前記上階室を形成する第二壁材と、前記第一スタッドと、前記下ランナーと、前記第一壁材は前記第一間仕切壁を形成し、
 前記下階室を形成する第三壁材と、前記第二スタッドと、前記上ランナーと、前記第一壁材は前記第二間仕切壁を形成する。
 また、本開示の一態様による間仕切壁と床版の接続構造の施工方法は、
 竪穴区画と、該竪穴区画に隣接して床版の上下にある上階室及び下階室と、を隔てる上方の第一間仕切壁及び下方の第二間仕切壁が、前記床版に接続されている、間仕切壁と床版の接続構造の施工方法であって、
 ランナー設置工程と、スタッド建て込み工程と、間仕切壁形成工程と、を有し、
 前記ランナー設置工程は、
 前記床版の上方において、前記第一間仕切壁を形成する第一スタッドの下端が収容される下ランナーを設置し、前記床版の下方において、前記第二間仕切壁を形成する第二スタッドの上端が収容される上ランナーを設置し、
 前記スタッド建て込み工程は、
 前記第一スタッドの下端を前記下ランナーに収容して建て込んだ後、該第一スタッドの竪穴区画側に第一敷目板を取り付け、前記第二スタッドの上端を前記上ランナーに収容して建て込んだ後、該第二スタッドの竪穴区画側に第二敷目板を取り付け、
 前記間仕切壁形成工程は、
 前記竪穴区画において、前記第一スタッドから前記第二スタッドに跨って延設する第一壁材を、前記第一敷目板を介して前記第一スタッドに固定し、前記第二敷目板を介して前記第二スタッドに固定し、
 前記上階室を形成する第二壁材を前記第一スタッドに固定し、該第二壁材と、該第一スタッドと、前記下ランナーと、前記第一壁材とにより前記第一間仕切壁を形成し、
 前記下階室を形成する第三壁材を前記第二スタッドに固定し、該第三壁材と、該第二スタッドと、前記上ランナーと、前記第一壁材とにより前記第二間仕切壁を形成する。
 本開示によれば、大地震時等において、スタッドからランナーに押し込み力が作用した場合でもランナーが変形して接続構造が破損することがなく、竪穴区画に対向する壁材がスタッドに精度よく取り付けられている、間仕切壁と床版の接続構造を提供することができる。
従来の、竪穴区画と、竪穴区画に隣接する床版の上下にある上階室及び下階室とを隔てる、間仕切壁と床版の接続構造の一例を示す縦断面図である。 従来の間仕切壁と床版の接続構造において、地震時の水平力が間仕切壁に作用した際の、破損の一例を説明する縦断面図である。 実施形態に係る間仕切壁と床版の接続構造の一例を示す縦断面図である。 実施形態に係る間仕切壁と床版の接続構造の施工方法の一例を説明する工程図である。 図4に続いて、実施形態に係る間仕切壁と床版の接続構造の施工方法の一例を説明する工程図である。
 以下、実施形態に係る間仕切壁と床版の接続構造とその施工方法について、添付の図面を参照しながら説明する。尚、本明細書及び図面において、実質的に同一の構成要素については、同一の符号を付することにより重複した説明を省く場合がある。
 [実施形態に係る間仕切壁と床版の接続構造]
 まず、図3を参照して、実施形態に係る間仕切壁と床版の接続構造の一例について説明する。ここで、図3は、実施形態に係る間仕切壁と床版の接続構造の一例を示す縦断面図である。
 図示する間仕切壁と床版の接続構造100は、竪穴区画10と、竪穴区画10に隣接して床版20の上下にある上階室13及び下階室15と、を隔てる上方の第一間仕切壁30及び下方の第二間仕切壁40が、床版20と床梁25にそれぞれ接続されることにより形成される。
 接続構造100が適用される竪穴区画10には、エレベータシャフトや階段室、ダクトシャフト、配管シャフト等が含まれ、それらに隣接する隣接空間である上階室13と下階室15には、エレベータホールや通路、居室、会議室、管理室等が含まれる。そして、接続構造100が適用される建物は、鉄骨造の建物は勿論のこと、RC(Reinforced Concrete)造の建物、木造建物等にも適用することができ、工場や倉庫、ビルやマンション、一般の戸建て住宅等が適用対象となる。
 鉄筋コンクリート製の床版20は現場施工にて形成されており、施工誤差に起因して、その竪穴区画側端面21に凹凸を有している。この凹凸は、図示する縦方向に存在するととともに、図3の紙面奥行き方向にも存在する。
 床版20の上面において、上方の第一間仕切壁30を構成し、建築用鋼製下地材により形成される下ランナー31が、床版20における竪穴区画側端面21よりも上階室側に幅t3だけセットバックした位置に配設され、床版20に対してビスや鋲等の固定部材70により固定されている。
 一方、床梁25の上下のフランジ25aのうち、ウエブ25bよりも竪穴区画側には、ランナー受け材37A,37Bが溶接等により固定され、ランナー受け材37A,37Bに対して、建築用鋼製下地材により形成される上下の床梁内ランナー35が、双方の開口を対向させた姿勢でビスやタッピンねじ等の固定部材70にて固定されている。そして、上下の床梁内ランナー35の内部に床梁内スタッド36が配設される。これら上下の床梁内ランナー35の竪穴区画側フランジ35aが、床版20における竪穴区画側端面21よりも下階室側に幅t3だけセットバックした位置に配設され、上下のランナー受け材37A,37Bに対してビスやタッピンねじ等の固定部材70により固定されている。尚、上下の床梁内ランナー35の竪穴区画側フランジ35aは、上方のランナー受け材37Aと下方のランナー受け材37Bとの間において、下階室側に配設されている。
 さらに、床梁25の下方のフランジ25aの下面には、ランナー受け材37Cが溶接等により固定されている。このランナー受け材37Cに対して、下方の第二間仕切壁40を構成し、建築用鋼製下地材により形成される上ランナー33が、床版20における竪穴区画側端面21よりも下階室側に幅t3だけセットバックした位置に配設され、ビスやタッピンねじ等の固定部材70によりランナー受け材37Cに固定されている。
 第一間仕切壁30においては、上方の上ランナー(図示せず)と下ランナー31の間に壁の幅方向(図3の奥行き方向)に間隔(例えば606mm以下の間隔で、606mm、455mm等)を置いて、リップ付き建築用鋼製下地材により形成される複数の第一スタッド32が建て込まれている。そして、各第一スタッド32の室内側には、第二壁材63が取り付けられている。
 一方、第二間仕切壁40においては、下方の下ランナー(図示せず)と上ランナー33の間に、壁の幅方向(図3の奥行き方向)に間隔(例えば606mm以下の間隔で、606mm、455mm等)を置いて、リップ付き建築用鋼製下地材により形成される複数の第二スタッド34が建て込まれている。そして、各第二スタッド34の室内側には、第三壁材66が取り付けられている。
 尚、第一スタッド32、第二スタッド34、及び床梁内スタッド36は、リップ付き建築用鋼製下地材以外にも、角形鋼により形成されてもよい。第一スタッド32、第二スタッド34、及び床梁内スタッド36に適用される建築用鋼製下地材には、一般構造用軽量形鋼(JIS G 3350)、溶融亜鉛めっき鋼板(JIS G 3302)等が適用できる。また、建築用鋼製下地材としては、45乃至500×45乃至75×8乃至32で厚さ0.4mm以上のものが適用でき、角形鋼の形状寸法としては、45乃至500×40乃至350で厚さ0.4mm以上のものが適用できる。
 また、下ランナー31や上ランナー33、床梁内ランナー35に適用される建築用鋼製下地材には、一般構造用軽量形鋼(JIS G 3350)、溶融亜鉛めっき鋼板(JIS G 3302)等が適用でき、45乃至500×35乃至75で厚さ0.4mm以上のものが適用できる。
 そして、第一スタッド32、第二スタッド34、及び床梁内スタッド36の竪穴区画側の端面において、第一スタッド32から第二スタッド34に跨って延設する第一壁材50が取り付けられている。
 第一壁材50、第二壁材63及び第三壁材66はいずれも、例えば、下張り材51,61,64と、上張り材52,62,65が壁厚方向に積層した積層構造を有しており、第一スタッド32、第二スタッド34、及び床梁内スタッド36に対してビスやタッピンねじ等の固定部材70にて固定されている。ここで、下張り材51,61,64と、上張り材52,62,65は、いずれも石膏板や石膏ボードにより形成されてもよいし、下張り材51,61,64と上張り材52,62,65の一方が石膏板や石膏ボードにより形成され、他方が珪酸カルシウム板等により形成されてもよい。石膏ボードには、例えばJIS A 6901で規定される、厚みが9.5mm乃至25mmの石膏ボードが適用でき、具体的には、吉野石膏株式会社製の「タイガーボード(登録商標)・タイプZ」を適用することができる。また、下張り材51,61,64と、上張り材52,62,65は接着剤により相互に接着されている。この接着剤には、酢酸ビニル樹脂系接着剤やアクリル樹脂系接着剤、ウレタン系接着剤、エポキシ樹脂系接着剤、シリコーン系接着剤等が適用できる。
 また、図示を省略するが、第一壁材50における床梁25の下方位置において、第一壁材50を構成する下張り材51と上張り材52のいずれか一方、もしくは双方に、幅10mm以下の目透かしを設けてもよい。そして、この目透かしには、ポリウレタン系やアクリル系、シリコーン系等のシーリング材を充填してもよい。さらに、図示を省略するが、床版20の上には床仕上げ材が施工され、上張り材62,65の表面には、クロスや塗装等により内装仕上げが施され、内装仕上げ面が室内側に露出している。そして、図示を省略するが、床版20の上方に施工された床仕上げ材と内装仕上げ面に跨がるように、巾木が施工される。
 図3に示すように、第一壁材50と第一スタッド32は、厚みt2の第一敷目板80Aを介して相互にビスやタッピンねじ、ステープル等の固定部材70にて固定されている。また、第一壁材50と第二スタッド34は、同様の厚みt2の第二敷目板80Bを介して相互に固定部材70にて固定されている。さらに、第一壁材50と床梁内スタッド36は、同様の厚みt2の第三敷目板80Cを介して相互に固定部材70にて固定されている。
 ここで、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cは、石膏板、石膏ボード、強化石膏ボード、不燃積層石膏ボード、繊維強化セメント板、グラスウール、ロックウール、グラスファイバーフェルト、ロックウールフェルト等により形成され、厚みは25mm以下程度で幅40mm以上のものが適用できる。尚、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cは、それぞれ二枚以上の敷目板を重ねることにより、全体として厚みが25mmを超える形態であってもよい。
 竪穴区画10において第一壁材50が設置される設置ラインL1を起線として、第一スタッド32と第二スタッド34、及び床梁内スタッド36はそれぞれ、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cの厚みt2だけ、上階室側及び下階室側にセットバックしている。その結果、下ランナー31、上ランナー33,及び床梁内ランナー35(の竪穴区画側フランジ35a)はいずれも、床版20における竪穴区画側端面21よりも上階室側と下階室側にそれぞれ幅t3だけセットバックした位置に配設される。このことにより、図2に示すように、地震時に第一間仕切壁30や第二間仕切壁40に水平力Hが作用し、第一スタッド32や第二スタッド34等から下ランナー31や上ランナー33等に押し込み力Pが作用した場合でも、下ランナー31や上ランナー33等が変形することは無い。従って、下ランナー31や上ランナー33等の変形に起因する接続構造100の破損を防止できる。
 さらに、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cが、第一スタッド32と第二スタッド34と床梁内スタッド36、及び第一壁材50の間に介在している。この構成により、現場施工される鉄筋コンクリート製の床版20が施工誤差によってその竪穴区画側端面21に凹凸を有している場合であっても、第一スタッド32と第二スタッド34と床梁内スタッド36に対して、第一壁材50を精度よく取り付けることができる。
 接続構造100では、床版20における竪穴区画側端面21と第一壁材50の間に形成されている隙間に、ロックウール等により形成される耐火材85が充填されている。また、床梁25の周囲には、吹き付け施工等により、耐火被覆材28が形成されている。この耐火被覆材28は、例えばフェルト状に成形された耐熱ロックウールと、難燃性不織布の積層体により形成される。
 このように、耐火性能のある第一間仕切壁30と第二間仕切壁40を有し、床梁25の周囲に耐火被覆材28が設けられるとともに、床版20における竪穴区画側端面21と第一壁材50の間の隙間に耐火材85が充填されていることにより、耐火性能に優れた接続構造100が形成される。
 [実施形態に係る間仕切壁と床版の接続構造の施工方法]
 次に、図4及び図5を参照するとともに図3を再度参照することにより、実施形態に係る間仕切壁と床版の接続構造の施工方法の一例について説明する。ここで、図4、図5及び図3は順に、実施形態に係る間仕切壁と床版の接続構造の施工方法の一例を説明する縦断面図である。
 実施形態に係る施工方法は、床版施工工程と、ランナー設置工程と、スタッド建て込み工程と、間仕切壁形成工程とを有する。
 まず、図4に示すように、H形鋼により形成される床梁25に支持されるようにして、鉄筋コンクリート製の床版20を現場施工する(床版施工工程)。
 次に、床版20の上方において、第一間仕切壁30を形成する第一スタッド32の下端が収容される下ランナー31を固定部材70にて固定する。さらに、床版20を支持する床梁25の下フランジ25aにおいて、第二間仕切壁40を形成する第二スタッド34の上端が収容される上ランナー33を固定部材70にて固定する。
 床梁25の上下のフランジ25aのうち、ウエブ25bよりも竪穴区画側には、ランナー受け材37A,37Bを溶接等により固定し、ランナー受け材37A,37Bに対して、上下の床梁内ランナー35を双方の開口を対向させた姿勢で固定部材70にて固定する。これら上下の床梁内ランナー35の内部には、床梁内スタッド36を配設する。
 ここで、竪穴区画10において第一壁材50が設置される設置ラインL1を起線として、下ランナー31と上ランナー33、及び床梁内ランナー35をそれぞれ、設置ラインL1上の起点Qから、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cの厚みt2だけ、上階室側及び下階室側にセットバックさせた位置に設置する(以上、ランナー設置工程)。尚、ランナー設置工程に続いて、床梁25の周囲には、吹き付け施工等により耐火被覆材28を形成し、床版20における竪穴区画側端面21の側方には、耐火材85を充填する。
 次に、図5に示すように、第一スタッド32の下端を、下ランナー31に収容して建て込む。尚、図示しない上ランナーに対して第一スタッド32の上端が嵌め込まれる。そして、第一スタッド32の竪穴区画側に、第一敷目板80Aを取り付ける。
 また、第二スタッド34の上端を、上ランナー33に収容して建て込む。尚、図示しない下ランナーに対して第二スタッド34の下端が嵌め込まれる。そして、第二スタッド34の竪穴区画側に第二敷目板80Bを取り付ける。
 さらに、床梁内スタッド36の竪穴区画側側面に第三敷目板80Cを設置する。ここで、第一スタッド32、第二スタッド34、及び床梁内スタッド36に対して、第一敷目板80A、第二敷目板80B、及び第三敷目板80Cが、粘着テープ(両面粘着テープを含む)や接着剤、タッピンねじ等により仮留めされる。ここで、粘着剤の種類は、アクリル樹脂系、ポリアミド系、天然ゴム系、合成ゴム系等の粘着剤が適用でき、厚みが3mm以下、幅100mm以下の寸法の粘着テープが適用できる。
 尚、第三敷目板80Cが予め床梁内スタッド36に仮固定されていて、ランナー設置工程において、床梁内スタッド36を設置した際に第三敷目板80Cの設置も同時に完了していてもよい(以上、スタッド建て込み工程)。
 次に、図3に示すように、竪穴区画10において、第一スタッド32から第二スタッド34に跨って延設する第一壁材50を、第一敷目板80Aを介して固定部材70にて第一スタッド32に固定し、第二敷目板80Bを介して固定部材70にて第二スタッド34に固定し、第三敷目板80Cを介して固定部材70にて床梁内スタッド36に固定する。これらの固定部材70による固定により、第一スタッド32等に仮固定されていた第一敷目板80A等が、第一スタッド32等に対して強固に本固定される。
 さらに、上階室13を形成する第二壁材63を第一スタッド32に固定部材70にて固定することにより、第二壁材63と、第一スタッド32と、下ランナー31及び上ランナー(図示せず)と、第一壁材50とにより第一間仕切壁30を形成する。
 また、下階室15を形成する第三壁材66を第二スタッド34に固定部材70にて固定することにより、第三壁材66と、第二スタッド34と、上ランナー33及び下ランナー(図示せず)と、第一壁材50とにより第二間仕切壁40を形成し、接続構造100が施工される(以上、間仕切壁形成工程)。
 実施形態に係る施工方法によれば、下ランナー31や上ランナー33等が、床版20に対して、その凹凸を有する竪穴区画側端面21から上階室側と下階室側に所定量セットバックした位置に設置される。このことにより、地震時等における下ランナー31等の破損を解消することができ、かつ、第一敷目板80A等を介して第一壁材50が精度よく第一スタッド32等に取り付けられている接続構造100を効率的に施工することが可能になる。
 尚、上記実施形態に挙げた構成等に対し、その他の構成要素が組み合わされるなどした他の実施形態であってもよく、また、本開示はここで示した構成に何等限定されるものではない。この点に関しては、本開示の趣旨を逸脱しない範囲で変更することが可能であり、その応用形態に応じて適切に定めることができる。
 本国際出願は、2020年3月19日に出願した日本国特許出願第2020-049538号に基づく優先権を主張するものであり、当該出願の全内容を本国際出願に援用する。
 10:竪穴区画
 13:上階室
 15:下階室
 20:床版
 25:床梁
 28:耐火被覆材
 21:竪穴区画側端面
 30:第一間仕切壁
 31:下ランナー
 32:第一スタッド
 33:上ランナー
 34:第二スタッド
 35:床梁内ランナー
 36:床梁内スタッド
 37A:第一ランナー受け材(ランナー受け材)
 37B:第二ランナー受け材(ランナー受け材)
 37C:第三ランナー受け材(ランナー受け材)
 40:第二間仕切壁
 50:第一壁材
 51:下張り材
 52:上張り材
 60A,63:第二壁材
 60B,66:第三壁材
 61,64:下張り材
 62,65:上張り材
 70:固定部材
 80A:第一敷目板
 80B:第二敷目板
 80C:第三敷目板
 85:耐火材
 100:間仕切壁と床版の接続構造(接続構造)

Claims (10)

  1.  竪穴区画と、該竪穴区画に隣接して床版の上下にある上階室及び下階室と、を隔てる上方の第一間仕切壁及び下方の第二間仕切壁が、前記床版に接続されている、間仕切壁と床版の接続構造であって、
     前記床版の上方には、前記第一間仕切壁を形成する第一スタッドの下端が収容される下ランナーが設置され、
     前記床版の下方には、前記第二間仕切壁を形成する第二スタッドの上端が収容される上ランナーが設置されており、
     前記竪穴区画において、前記第一スタッドから前記第二スタッドに跨って延設する第一壁材が、第一敷目板を介して前記第一スタッドに固定され、かつ第二敷目板を介して前記第二スタッドに固定されており、
     前記上階室を形成する第二壁材と、前記第一スタッドと、前記下ランナーと、前記第一壁材は前記第一間仕切壁を形成し、
     前記下階室を形成する第三壁材と、前記第二スタッドと、前記上ランナーと、前記第一壁材は前記第二間仕切壁を形成する、間仕切壁と床版の接続構造。
  2.  前記下ランナーと前記上ランナーがそれぞれ、前記床版における竪穴区画側の端面よりも上階室側と下階室側に、前記第一敷目板と前記第二敷目板の厚み分だけセットバックしている、請求項1に記載の間仕切壁と床版の接続構造。
  3.  前記下ランナーは前記床版に対して固定部材により固定され、
     前記上ランナーはランナー受け材に対して固定部材により固定され、該ランナー受け材が前記床版に直接的もしくは間接的に固定されている、請求項1又は2に記載の間仕切壁と床版の接続構造。
  4.  前記床版が床梁に支持されており、
     前記床梁に前記ランナー受け材が固定され、該ランナー受け材に前記上ランナーが固定されている、請求項3に記載の間仕切壁と床版の接続構造。
  5.  前記床版における竪穴区画側の端面と、前記第一壁材との間に、耐火材が配設されている、請求項1乃至4のいずれか一項に記載の間仕切壁と床版の接続構造。
  6.  前記第一壁材と、前記第二壁材と、前記第三壁材がいずれも、下張り材と上張り材が壁厚方向に積層した積層構造を有している、請求項1乃至5のいずれか一項に記載の間仕切壁と床版の接続構造。
  7.  請求項1乃至6のいずれか一項に記載の間仕切壁と床版の接続構造を有する、建物。
  8.  竪穴区画と、該竪穴区画に隣接して床版の上下にある上階室及び下階室と、を隔てる上方の第一間仕切壁及び下方の第二間仕切壁が、前記床版に接続されている、間仕切壁と床版の接続構造の施工方法であって、
     ランナー設置工程と、スタッド建て込み工程と、間仕切壁形成工程と、を有し、
     前記ランナー設置工程は、
     前記床版の上方において、前記第一間仕切壁を形成する第一スタッドの下端が収容される下ランナーを設置し、前記床版の下方において、前記第二間仕切壁を形成する第二スタッドの上端が収容される上ランナーを設置し、
     前記スタッド建て込み工程は、
     前記第一スタッドの下端を前記下ランナーに収容して建て込んだ後、該第一スタッドの竪穴区画側に第一敷目板を取り付け、前記第二スタッドの上端を前記上ランナーに収容して建て込んだ後、該第二スタッドの竪穴区画側に第二敷目板を取り付け、
     前記間仕切壁形成工程は、
     前記竪穴区画において、前記第一スタッドから前記第二スタッドに跨って延設する第一壁材を、前記第一敷目板を介して前記第一スタッドに固定し、前記第二敷目板を介して前記第二スタッドに固定し、
     前記上階室を形成する第二壁材を前記第一スタッドに固定し、該第二壁材と、該第一スタッドと、前記下ランナーと、前記第一壁材とにより前記第一間仕切壁を形成し、
     前記下階室を形成する第三壁材を前記第二スタッドに固定し、該第三壁材と、該第二スタッドと、前記上ランナーと、前記第一壁材とにより前記第二間仕切壁を形成する、間仕切壁と床版の接続構造の施工方法。
  9.  前記ランナー設置工程では、前記下ランナーと前記上ランナーをそれぞれ、前記床版における竪穴区画側の端面よりも上階室側と下階室側に所定量セットバックさせて前記床版に設置し、
     前記所定量は、前記間仕切壁形成工程にて設置される前記第一壁材の設置位置を起点として、前記第一敷目板及び前記第二敷目板の厚みに相当する長さである、請求項8に記載の間仕切壁と床版の接続構造の施工方法。
  10.  床梁にて支持される前記床版を施工する床版施工工程をさらに有し、
     前記ランナー設置工程では、前記床梁に固定されているランナー受け材に対して前記上ランナーを固定する、請求項8又は9に記載の間仕切壁と床版の接続構造の施工方法。
PCT/JP2020/037445 2020-03-19 2020-10-01 間仕切壁と床版の接続構造とその施工方法 WO2021186770A1 (ja)

Priority Applications (9)

Application Number Priority Date Filing Date Title
CN202080092325.0A CN114981508B (zh) 2020-03-19 2020-10-01 隔墙和楼板的连接结构及其施工方法
BR112022013661A BR112022013661A2 (pt) 2020-03-19 2020-10-01 Estrutura de conexão entre parede divisória e piso, e método de construção da mesma
KR1020227032025A KR20220137122A (ko) 2020-03-19 2020-10-01 칸막이벽과 상판의 접속 구조 및 그 시공 방법
US17/759,650 US20230085256A1 (en) 2020-03-19 2020-10-01 Connection structure between partition walls and floor slab, and method for constructing same
AU2020436409A AU2020436409B2 (en) 2020-03-19 2020-10-01 Connection structure between partition wall and floor and construction method therefor
EP20925988.6A EP4098823A4 (en) 2020-03-19 2020-10-01 CONNECTION STRUCTURE BETWEEN A SEPARATION WALL AND A FLOOR AND ITS CONSTRUCTION METHOD
MX2022011211A MX2022011211A (es) 2020-03-19 2020-10-01 Estructura de conexion entre paredes divisorias y losa de piso y metodo de construccion de la misma.
JP2022508038A JP7465577B2 (ja) 2020-03-19 2020-10-01 間仕切壁と床版の接続構造とその施工方法
CA3164279A CA3164279A1 (en) 2020-03-19 2020-10-01 Connection structure between partition walls and floor slab, and method for constructing same

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2020049538 2020-03-19
JP2020-049538 2020-03-19

Publications (1)

Publication Number Publication Date
WO2021186770A1 true WO2021186770A1 (ja) 2021-09-23

Family

ID=77770762

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/037445 WO2021186770A1 (ja) 2020-03-19 2020-10-01 間仕切壁と床版の接続構造とその施工方法

Country Status (10)

Country Link
US (1) US20230085256A1 (ja)
EP (1) EP4098823A4 (ja)
JP (1) JP7465577B2 (ja)
KR (1) KR20220137122A (ja)
CN (1) CN114981508B (ja)
AU (1) AU2020436409B2 (ja)
BR (1) BR112022013661A2 (ja)
CA (1) CA3164279A1 (ja)
MX (1) MX2022011211A (ja)
WO (1) WO2021186770A1 (ja)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002309691A (ja) 2001-04-11 2002-10-23 Yoshino Gypsum Co Ltd 耐火間仕切壁の耐火目地材
JP2005273328A (ja) * 2004-03-25 2005-10-06 Taisei Corp 建物における重要室の避雷システム
JP2010071021A (ja) * 2008-09-22 2010-04-02 Takenaka Komuten Co Ltd 軽量鉄骨間仕切り壁とその構築方法
US20110296789A1 (en) * 2010-06-08 2011-12-08 Sustainable Living Technology, Llc Construction System and Method for Constructing Buildings Using Premanufactured Structures
JP2020049538A (ja) 2018-09-28 2020-04-02 マツダ株式会社 レーザ溶接方法及びレーザ溶接装置

Family Cites Families (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1346634A (fr) * 1963-01-31 1963-12-20 Knauf Geb Cloison démontable pour bâtiments
US3636672A (en) * 1969-12-12 1972-01-25 Steelcraft Mfg Co Snap-in jamb anchor
US4869037A (en) * 1985-10-25 1989-09-26 Murphy John J Wall construction
US5027572A (en) * 1989-08-17 1991-07-02 W. R. Grace & Co.-Conn. Moisture and vapor barrier in exterior insulation finish systems
US5113631A (en) * 1990-03-15 1992-05-19 Digirolamo Edward R Structural system for supporting a building utilizing light weight steel framing for walls and hollow core concrete slabs for floors and method of making same
US5761864A (en) * 1994-08-31 1998-06-09 Nonoshita; Tadamichi Thermally insulated building and a building panel therefor
DE19745840A1 (de) * 1997-10-16 1999-04-22 Goesele Karl Baugruppe, welche zwei flächige Gebäudeelemente umfaßt, sowie Gebäudeelemente zur Verwendung in einer solchen Baugruppe
CA2226595C (en) * 1998-01-12 2003-12-02 Emco Limited Composite vapour barrier panel
JP2000320050A (ja) * 1999-03-05 2000-11-21 Shimizu Corp 間仕切壁構造
CN100472016C (zh) * 2004-04-28 2009-03-25 吉野石膏株式会社 板式建材、板式建材的制造方法以及板式建材的施工方法
JP2007218009A (ja) * 2006-02-20 2007-08-30 Nippon Kenko Kk 内装材の取付構造
JP4658006B2 (ja) * 2006-08-30 2011-03-23 株式会社奥村組 既存建物の免震化工法およびそれに使用される仮設制震パネル
US7832174B2 (en) * 2007-10-15 2010-11-16 Way Alven J Multi-storey insulated concrete form structure and method of construction
US8950132B2 (en) * 2010-06-08 2015-02-10 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
WO2011155992A1 (en) * 2010-06-08 2011-12-15 Collins Arlan E Lift-slab construction system and method for constructing multi-story buildings using pre-manufactured structures
JP5613466B2 (ja) * 2010-06-09 2014-10-22 株式会社竹中工務店 コンクリート壁取付構造
US8839582B2 (en) * 2011-05-31 2014-09-23 Charbel Tannious Aboukhalil Wainscot wall panel system
JP6368551B2 (ja) * 2014-06-04 2018-08-01 大成建設株式会社 既存建物の免震化方法
WO2016096162A1 (en) * 2014-12-19 2016-06-23 Siniat International Sas Seismic protective structure for board partitions
CN106149922A (zh) * 2015-04-10 2016-11-23 北新集团建材股份有限公司 一种可拆装隐形隔墙系统及其拆装方法
CN205088820U (zh) * 2015-09-28 2016-03-16 中国建筑第八工程局有限公司 轻钢龙骨石膏板隔墙底部的支设结构
CN205348394U (zh) * 2015-11-18 2016-06-29 文登蓝岛建筑工程有限公司 一种钢结构整体装配式墙体及其钢梁包覆节点
CN205677114U (zh) * 2016-05-19 2016-11-09 山东大学 用于装配式内框轻质隔墙的安装节点
CN105888107A (zh) * 2016-05-23 2016-08-24 青岛海川建设集团有限公司 一种轻质隔墙竖向安装固定结构及其施工方法
US10472820B2 (en) * 2017-05-11 2019-11-12 Timothy Dennis Lutz Exterior insulated finish wall assembly
CA2980203A1 (en) * 2017-09-26 2019-03-26 Mod Panel Manufacturing Ltd. Pre-fabricated deflection absorbent modular wall system
CN107489212B (zh) * 2017-09-27 2023-01-03 杭州铁木辛柯建筑结构设计事务所有限公司 免承重力防剪切屈曲钢板剪力墙
CN207484757U (zh) * 2017-11-06 2018-06-12 四川福克斯建筑装饰工程有限公司 多厚度可调节全钢防火隔断墙结构
TWI791780B (zh) * 2018-03-04 2023-02-11 日商吉野石膏股份有限公司 隔間壁構造及其施工方法
US11105092B2 (en) * 2018-06-15 2021-08-31 Specified Technologies Inc. Fire blocking gasket for window wall conditions
US10995497B1 (en) * 2018-06-30 2021-05-04 James P. Horne Furring and flashing strip system
EP3839169B1 (en) * 2018-10-05 2023-07-19 Yoshino Gypsum Co., Ltd. Construction surface material with magnetic layer
CN109235634A (zh) * 2018-10-15 2019-01-18 沈阳建筑大学 薄壁工字钢轻木组合结构承重保温墙板-楼板节点
CN209339376U (zh) * 2018-12-10 2019-09-03 信息产业电子第十一设计研究院科技工程股份有限公司 砌体填充墙与梁的柔性连接结构
CN219411402U (zh) * 2023-03-10 2023-07-25 中机中联工程有限公司 一种装配式双层龙骨墙体及用于该墙体的隔声减振垫

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002309691A (ja) 2001-04-11 2002-10-23 Yoshino Gypsum Co Ltd 耐火間仕切壁の耐火目地材
JP2005273328A (ja) * 2004-03-25 2005-10-06 Taisei Corp 建物における重要室の避雷システム
JP2010071021A (ja) * 2008-09-22 2010-04-02 Takenaka Komuten Co Ltd 軽量鉄骨間仕切り壁とその構築方法
US20110296789A1 (en) * 2010-06-08 2011-12-08 Sustainable Living Technology, Llc Construction System and Method for Constructing Buildings Using Premanufactured Structures
JP2020049538A (ja) 2018-09-28 2020-04-02 マツダ株式会社 レーザ溶接方法及びレーザ溶接装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP4098823A4

Also Published As

Publication number Publication date
BR112022013661A2 (pt) 2022-09-27
EP4098823A1 (en) 2022-12-07
CA3164279A1 (en) 2021-09-23
US20230085256A1 (en) 2023-03-16
CN114981508A (zh) 2022-08-30
JP7465577B2 (ja) 2024-04-11
TW202136621A (zh) 2021-10-01
EP4098823A4 (en) 2024-01-31
MX2022011211A (es) 2022-10-07
AU2020436409A1 (en) 2022-08-04
CN114981508B (zh) 2024-03-08
JPWO2021186770A1 (ja) 2021-09-23
AU2020436409B2 (en) 2023-11-23
KR20220137122A (ko) 2022-10-11

Similar Documents

Publication Publication Date Title
US10240341B2 (en) Fire-resistant wooden I-joist
US7775006B2 (en) Fire stop system for wallboard and metal fluted deck construction
JP7246749B2 (ja) 間仕切壁構造及びその施工方法
JPH11247324A (ja) 耐火構造壁
JP4049564B2 (ja) 耐火間仕切壁及びその施工方法
WO2021186770A1 (ja) 間仕切壁と床版の接続構造とその施工方法
TWI837438B (zh) 隔牆與樓板的連接結構、其施工方法及建築物
JP3907424B2 (ja) 間仕切壁構造
JP2003171988A (ja) 耐火構造の耐力壁としての外壁および床
JP4426715B2 (ja) 区画壁の固定構造
RU2793696C1 (ru) Соединительная конструкция между перегородками и плитой перекрытия и способ для ее изготовления
JP3497617B2 (ja) パネルを用いた建物
US3707818A (en) Shaft cavity wall and stud
JP2002369891A (ja) 防火区画壁
JP4918333B2 (ja) 間仕切壁構造
JP2020026674A (ja) 間仕切壁
RU2794682C2 (ru) Монолитная акустическая система
JP7405548B2 (ja) 壁構造
Loebus et al. The multifunctional TES-façade joint
JP3147673B2 (ja) 鉄骨造り建築物における耐火性間仕切壁の設置工法
JPH0960250A (ja) Alc外壁の改修構造
JPH0868151A (ja) ユニット建物の天井構造
JPH06294174A (ja) 小屋裏界壁構造
WO2023140777A1 (en) A collaborating joist and suspended ceiling system and a method for assembling the system
GB2341400A (en) Mounting plasterboard panels

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20925988

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 3164279

Country of ref document: CA

REG Reference to national code

Ref country code: BR

Ref legal event code: B01A

Ref document number: 112022013661

Country of ref document: BR

ENP Entry into the national phase

Ref document number: 2022508038

Country of ref document: JP

Kind code of ref document: A

Ref document number: 2020436409

Country of ref document: AU

Date of ref document: 20201001

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 2020925988

Country of ref document: EP

Effective date: 20220829

ENP Entry into the national phase

Ref document number: 20227032025

Country of ref document: KR

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 112022013661

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20220708

WWE Wipo information: entry into national phase

Ref document number: 2022123868

Country of ref document: RU

NENP Non-entry into the national phase

Ref country code: DE