WO2021142701A1 - 一种混凝土砌块砌体构件装配化施工方法及施工装置 - Google Patents
一种混凝土砌块砌体构件装配化施工方法及施工装置 Download PDFInfo
- Publication number
- WO2021142701A1 WO2021142701A1 PCT/CN2020/072421 CN2020072421W WO2021142701A1 WO 2021142701 A1 WO2021142701 A1 WO 2021142701A1 CN 2020072421 W CN2020072421 W CN 2020072421W WO 2021142701 A1 WO2021142701 A1 WO 2021142701A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- lashing
- lifting
- rope
- hoisting
- block
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
Definitions
- the invention relates to a structural form of wall construction technology, in particular to an assembled construction technology of a concrete block masonry structure wall, which belongs to the technical field of building construction.
- the assembly-based production method occupies a certain share in the construction market due to its fast construction speed, low cost, and easy quality control.
- Masonry materials such as hollow bricks and small concrete hollow blocks have been constructed on-site for many years due to complex processes and a wide variety of products.
- Small concrete hollow block as an industrialized product made of dry hard concrete, has not been free from traditional construction for many years.
- Analysis of the reason why it is difficult to apply in reinforced block masonry structure is that the connecting nodes cannot be processed.
- the masonry is the hollow block wall masonry is completed first, and then the steel reinforcement and concrete pouring are carried out.
- the assembly construction is carried out according to the reinforced concrete method, which is more difficult than the former. Therefore, for many years, the construction of reinforced block masonry has been using the traditional method of on-site masonry and then pouring.
- the traditional method has many drawbacks.
- the cleaning port will also be used as a channel for connecting steel bars, so the space is small and difficult to construct.
- the masonry is completed manually, which greatly increases the labor intensity of the workers, and the construction speed is also greatly affected.
- the quality of the walls is also affected by subjective factors such as the technical level and sense of responsibility of the construction workers. These have greatly restricted the development of this structural system of houses, and are also inconsistent with the current labor shortage and the soaring environmental protection requirements.
- the purpose of the present invention is to solve the cumbersome operation of adjusting the sliders on the balance beam and the lashing beam each time in the existing "two-point" hoisting method, and to provide an assembly construction method for concrete block masonry components. That is to say, when hoisting, only the slider on the binding beam needs to be adjusted, and the position of the hoisting point on it is set to implement hoisting.
- This feasible, simple, safe and efficient construction method provides technical support and solutions for the popularization and application of prefabricated masonry structures.
- the present invention proposes an assembly construction method for concrete block masonry components, which specifically includes the following steps:
- Step 1 Place the base under the block wall, and place the lashing beam above, and then tie the lashing beam, the block wall and the base together with a lashing rope in the vertical direction;
- Step 2 Determine the horizontal position of the hook and calculate the position of the center of gravity of the block wall to be hoisted, that is, the horizontal position of the hook;
- Step 3 Select the positions of the two hanging points A1 and A2 in the plan, make the center of gravity of the block wall piece on the line connecting the two hanging points A1 and A2, and ensure that the two hanging points A1 and A2 are at the center of gravity Are equal in distance;
- Step 4 Fix the position of the slider on the lashing beam with a pin, and measure and record the length between the two lifting points A1 and A2;
- Step 5 Check the distance between the two corresponding lifting points A1 and A2 on the balance beam before hoisting. When the distance between this distance and the distance between the two sliding blocks of the lashing beam 8 exceeds 10% of the length of the lower hoisting rope ( At this time, the two hoisting ropes form a certain angle, which is less than 80°). It is required to re-select the appropriate hoisting point on the balance beam to ensure that the angle between the two hoisting ropes and the lashing beam is 80° ⁇ 90°. Just try to keep it vertical;
- Step 6 Move the hook to the top of the block wall, connect the balance beam with a hoisting rope, and then connect the lashing beam with a lower hoisting rope;
- Step 7 After everything is ready, the block wall pieces are hoisted.
- the location of the lifting point in the second step is required to avoid the location of the vertical steel bars in the block hole.
- the base includes a bottom beam and a number of backing plates
- the bottom beam is a channel steel with the same width as the block wall, with the flange end facing upwards, and four bolt sets are welded on the outside of the channel steel flange.
- the nut is welded on the channel steel, and the ground is supported by a screw rod.
- the height of the channel steel is variable in the vertical direction by rotating the screw rod to achieve the purpose of adjusting the height of the channel steel at this point.
- a number of the backing plates are placed on the bottom beam laterally.
- the lashing beam includes a cross-shaped standard section and a number of standard lashing beam sections, and the four end faces of the cross-shaped standard section are used to connect a number of standard lashing beam sections, so as to adapt to the lashing of L-shaped and T-shaped block wall pieces. .
- the lashing beam further includes a slideway, a number of sliding blocks, a number of positioning holes, and a number of pins.
- the cross-shaped standard section and a number of standard lashing beam sections are provided with slideways, and the sliding blocks move along the slideways.
- a number of positioning holes at equal intervals are provided on the slideway, and a number of pins are inserted into the positioning holes to limit the position of the sliding block.
- a number of steel rings are provided on the side of the lashing beam, and the steel rings are connected with the lashing rope.
- the assembly construction method of concrete block masonry components of the present invention implements quick assembly construction for the vertical component of the block masonry structure—the wall.
- the main innovation is that only the lashing beams need to be installed. Lifting point, no need to adjust the lifting point on the balance beam, you can hoist any three-dimensional wall piece;
- the assembly construction method of concrete block masonry components of the present invention proposes a corresponding simplified method for balancing beams to reduce costs, meet the requirements of the simplified hoisting method, and make the production simpler, safer, easier to guarantee, and cost-effective.
- the concrete block masonry component assembly construction method of the present invention proposes an improved plan for binding beams, so that the simplified method can be implemented smoothly, which not only guarantees the construction speed, but also ensures the construction safety, so as to meet the needs of the method;
- the assembly construction method of concrete block masonry components of the present invention puts forward the concept and method of double-sided lashing, which solves the problem of unbalanced force of the steel wire ropes on both sides when single-sided lashing, insufficient range of the wire tensioner, and inconvenience to tighten the wire rope Other issues make it more convenient to lash the wall, and it can better ensure the balance of the force on the wall under the lashing;
- the assembly construction method of concrete block masonry components of the present invention puts forward the concept and method of lashing rope protection, which prevents the wire rope from falling off during evacuation and guarantees the construction safety during hoisting;
- the assembling construction method of concrete block masonry components of the present invention proposes a simple method of wall masonry base, which makes the wall masonry more free and improves the reuse rate of tools.
- Figure 1 is a schematic structural diagram of the assembly construction device for concrete block masonry components according to the present invention
- FIG. 2 is a schematic diagram of the base of the present invention; wherein (a) is a schematic diagram of the structure of the bottom beam, (b) is a schematic diagram of the structure of the backing plate;
- Figure 3 is a schematic diagram of the structure of the block wall of the present invention built on the bottom beam;
- Figure 4 is a schematic structural diagram of the lashing beam according to the present invention.
- FIG. 5 is a schematic diagram of the structure of the banded wall piece of the present invention.
- Figure 6 is a schematic diagram of the hoisting installation of the concrete block masonry component assembly construction device according to the present invention.
- Figure 7 is a schematic diagram of the principle of determining the lifting point of the lashing beam according to the present invention.
- A1 and A2 are the positions of the lifting points on the lashing beam and the corresponding balance beam of the method, and B1 and B2 are any one that meets the conditions when the traditional two-point method is hoisted Group lifting point position, a is the distance from the two lifting points to the hook in this method; b1 and b2 are the distances from the two lifting points to the hook in traditional two-point lifting.
- Figure 8 is a schematic diagram of the original two-point method
- Figure 9 shows what happens when the lifting point setting is restricted
- Figure 10 is a schematic diagram of improving the unsatisfactory lifting point by lengthening the balance beam and lashing the lower lifting rope between the beams;
- Figure 11 is a schematic diagram of the structure of the balance beam according to the present invention.
- Figure 12 is a structural schematic diagram of a balance beam with multiple lower lifting lugs
- Figure 13 is a schematic diagram of the lashing beam being too close to the wall hanging point, where a) the lashing beam is set up against the wall; b) the lashing beam is set off the wall;
- Figure 14 is a schematic diagram of the use of the cross-shaped standard section of the lashing beam, where a) is the case where the standard section is not used, and b) is the case where the standard section is used;
- Figure 15 is a schematic diagram of the structure of the original technology of double-sided lashing and the steel ring added in this application, where a) is the case of no rigid ring, and b) is the case of rigid ring;
- Figure 16 is a schematic diagram of different arrangements of one rope and two ropes, in which a) is the case of one line, and b) is the case of two lines;
- Step 1 Place the base under the block wall 11, and place the lashing beam 8 above, and then tie the lashing beam 8, the block wall 11 and the base together in the vertical direction with the lashing rope 7:
- Step 2 Determine the horizontal position of hook 1 and calculate the position of the center of gravity of the block wall 11 to be hoisted, that is, the horizontal position of hook 1;
- Step 3 Select the positions of the two hanging points A1 and A2 in the plan, make the center of gravity of the block wall 11 on the line connecting the two hanging points A1 and A2, and ensure that the two hanging points A1 and A2 reach The distance of the center of gravity is equal;
- Figure 7 shows the drawing situation when selecting the lifting point
- Step 4 Fix the position of the slider on the lashing beam 8 with a pin, and measure and record the length between the two hanging points A1 and A2;
- Step 5 Check the distance between the two corresponding lifting points A1 and A2 on the balance beam 4 before hoisting, when the distance between the distance and the distance between the two sliding blocks of the lashing beam 8 exceeds 10% of the length of the lower hoisting rope 6
- the two hoisting ropes form a certain angle at this time, that is, when the angle between the two hoisting ropes 6 and the lashing beam 8 is less than 80°, it is required to re-select a suitable hoisting point on the balance beam 4 to ensure the two hoisting ropes
- the angle between 6 and lashing beam 8 is 80° ⁇ 90°;
- Step 6 Move the hook 1 above the block wall 11, connect the balance beam 4 through the hoisting rope 2, and then connect the lashing beam 8 through the lower hoisting rope 6;
- Step 7 After everything is ready, the block wall piece 11 is hoisted.
- the location of the lifting point is required to avoid the position of the vertical steel bar in the block hole.
- the hook 1 When hoisting, the hook 1 hangs a balance beam 4 through two symmetrical lifting points, and the balance beam 4 hangs the lashing beam 8 through two lifting points A1 and A2.
- the lashing beam 8 is tied to the block wall to be hoisted.
- FIG 7 shows the drawing situation when the hanging points are selected. It can be seen from the figure that the lifting point of the lashing beam is determined according to the ordinary "two-point" method, which has great flexibility. The obtained lifting points B1 and B2 only need to ensure that the connection is over the center of gravity, while this method It is necessary to ensure that the distances from the two lifting points A1 and A2 to the center of gravity are equal. The position of the lifting point should avoid the position of the vertical reinforcement in the hole.
- Figure 8 shows a schematic diagram of the existing "two-point” hoisting method
- this method only adjusts the position of the lifting point on the lashing beam to achieve the coincidence of the center of gravity of the hook 1, the balance beam 4, and the block wall 11, and finds the only one that meets the conditions in the design in exchange for an adjustment in the construction (only adjust the lashing Beam slider position), this method is more convenient for construction.
- This method actually fixes the distance between the two lifting points, and the distances from the two lifting points to the center of gravity are equal.
- the "two-point” method there are countless straight lines passing through the center of gravity of the wall (also the center of gravity of hook 1 and balance beam 4). You can choose any one of them, but this method is to take two of the hanging points to the wall The only one with the same distance between the center of gravity of the film.
- the lifting point determined by the only straight line selected according to the above method is inconvenient to set up the lifting point, the lifting point can be moved a certain distance in a small range to change the possible lifting state of the predetermined position of the lifting point, that is, it should be two vertical steels.
- the chain is tilted, and the situation shown in Figure 9 occurs. It is possible that the center of gravity of the wall piece does not completely coincide with the hook 1, causing the wall piece to tilt slightly. According to practical tests, a small deviation will not affect the lifting installation under the condition that the bearing capacity of the lashing beam 8 is satisfied.
- the lower hoisting rope 6 can generally be made longer, so that at the same time It will also bring convenience to the work of the steel bar penetrating the wall, because the length of the lower hoisting rope 6 is the movable space of the bar penetrating guide tube.
- a hoisting device used in the assembly construction method of the concrete block masonry component includes a hook 1, a hoisting rope 2, two upper ears 3, a balance beam 4, n lower ears 5, and a lower hoisting rope 6.
- the lashing rope 7, the lashing beam 8 and the base, where n 2, 4 or 6; two upper lifting eyes 3 are installed on the balance beam 4, and n lower lifting eyes 5 are installed under the balance beam 4,
- the hook 1 is located above the balance beam 4 and is connected to the two upper lifting lugs 3 on the balance beam 4 by a lifting rope 2
- the lashing beam 8 is located below the balance beam 4 and is connected to the lower balance beam 4 by a lower lifting rope 6
- Binding beams 8 are placed below the block wall piece 11, the block wall piece 11 is placed under the binding beam 8, the base is located below the block wall piece 11, and the lashing rope 7
- the lashing beam 8, the block wall piece 11 and the base are vertically integrated.
- the base includes a bottom beam 9 and a number of backing plates 10.
- the bottom beam 9 is a channel steel with the same width as the wall, with the flange end facing upwards. On the outside of the channel steel flange, four bolt sets are welded, and the nuts are welded on On the channel steel, the ground is supported by a screw rod, and the height of the channel steel in the vertical direction is variable by rotating the screw rod to achieve the purpose of adjusting the height of the channel steel at this point.
- a number of the backing plates 10 are placed on the bottom beam 9 laterally.
- the adjustable masonry base not only needs to support the wall, but also provides lashing space for the prefabricated block masonry components.
- the present invention uses an adjustable bottom beam 9 and a non-fixed backing plate 10, as shown in FIG. 2.
- the adjustable bottom beam 9 is made of channel steel with the same width as the wall, with the flange end facing upward, and the two flanges provide support for the backing plate 10.
- weld four high-strength bolt kits weld the nut on the channel steel, support the ground with a screw, and rotate the screw to make the channel steel variable in the vertical direction, and then adjust the channel steel at this point. high.
- Each channel beam can be provided with four bolt sets, which can not only meet the needs of adjustment, but also ensure the reliability of the support. The method of use is shown in Figure 3.
- the backing plate 10 can be provided with a limiting strip on one side, so that the backing plate 10 can be simply centered when the strip is against the channel steel flange.
- the limit bar When the limit bar is not set, it can still meet the requirements that its position can be freely set, reused, and standardized production.
- the lashing beam 8 includes a cross-shaped standard section 14 and a number of standard lashing beam sections 15.
- the four end faces of the cross-shaped standard section 14 are used to connect a number of standard lashing beam sections 15 so as to be suitable for lashing L-shaped and T-shaped blocks.
- Wall piece 11 is used to connect a number of standard lashing beam sections 15 so as to be suitable for lashing L-shaped and T-shaped blocks.
- the lashing beam 8 also includes a slideway, a number of sliders, a number of positioning holes, and a number of pins.
- the cross-shaped standard section 14 and a number of standard lashing beam sections 15 are provided with slideways, and the sliders move along the slideways.
- a number of positioning holes at equal intervals are provided on the slideway, and a number of pins are inserted into the positioning holes to limit the position of the sliding block.
- the concrete hollow block wall 11 must be packed on the binding beam 8 to solve the problem that the mortar bonding strength is not enough to resist the tensile stress caused by hoisting.
- the lashing beam 8 is placed on the top of the wall.
- the lashing beam 8 of this hoisting device is composed of a cross-shaped standard connecting section 14 and a straight standard lashing beam section 15.
- the standard lashing beam section 15 of different lengths can meet different requirements. Lifting requirements for the length of the wall.
- Fig. 4 shows the assembled lashing beam 8, on which the sliding block can slide along the sliding track to a desired position, and the position of the sliding block is defined by inserting a pin into the positioning hole.
- the banded wall piece is shown in Figure 5.
- the lashing beam is provided with a sliding track, and the position of the lifting point can be determined by sliding and positioning the sliding block on it.
- the lashing beam 8 is used for lashing the wall and hoisting. Generally, it is better to set the lashing beam according to the shape of the wall, set the in-line lashing beam for the in-line wall, set the L-shaped lashing beam for the L-shaped wall, and set the T-shaped lashing for the T-shaped wall. Beam. But in some cases, especially the T-shaped wall piece, the center is biased to one side, and the T-shaped lashing beam is used to set the lifting point. When the two lifting points are approximately the same distance from the center of gravity, the distance between the two points is often too close, as shown in Figure 13a Shown.
- the lashing beam is set apart from the wall, that is, part of the lashing beam is suspended in the air, and there is no wall at the hanging point.
- the setting method is to set a "cross"-shaped standard section, as shown in Figure 13b, its two ends or three ends are connected with the in-line lashing beam section to form an L-shape and a T-shape, so it can replace the L-shaped standard section.
- Figure 14 shows the use of L-shaped wall and T-shaped wall when hoisting, so that this variable and adjustable lashing beam can adapt to the in-line wall, L-shaped wall and T-shaped wall at the same time, which is convenient to use ,save costs.
- the side of the lashing beam 8 is provided with a number of rigid rings, and the steel ring is connected with the lashing rope 7, and the lashing rope 7 is a steel wire rope.
- each lashing rope 7 can slide on the lashing beam 8 in the direction of gravity, but each lashing rope 7 only needs one rope length adjusting device (tightening device 13).
- the adjustment length of the tensioner 13 is generally limited, and the lashing rope 7 has a certain degree of elasticity. It requires a tensioner 13 to adjust a long distance to tighten, and it is often easy to exceed the work of the tensioner 13 Length brings difficulty to construction.
- one lashing rope 7 for each closed loop lashing can be changed into two sections, and each lashing rope 7 is individually fixed on the lashing beam 8.
- the simplest method is to set a rigid ring to fix the lashing rope 7, and there are many ways to fix the lashing rope 7 on the lashing beam.
- proper measures should be taken to avoid the displacement of the lashing beam when tightening from one side.
- a steel chain with greater rigidity can be used to replace the steel wire rope, which is essentially the same as the steel wire rope.
- the lashing rope 7 When a lashing rope 7 is used for a closed-loop lashing, the lashing rope 7 can slide along the direction of gravity on the beam, and may slip off when the lashing device is removed from the floor, which poses a safety hazard.
- a simple method is to use the positioning holes on the lashing beam 8 to hang the lashing rope 7 on the lashing beam 8 in the form of a hook.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
Claims (8)
- 一种混凝土砌块砌体构件装配化施工方法,其特征在于,具体包括以下步骤:第1步:在砌块墙片(11)的下方放置底座,上方放置绑扎梁(8),然后通过绑扎绳(7)将绑扎梁(8)、砌块墙片(11)和底座竖直方向绑扎在一起;第2步:确定吊钩(1)的水平位置计算出拟吊装砌块墙片(11)的重心位置,即吊钩(1)所在的水平位置;第3步:在平面图中选定两个吊点A1和A2的位置,使砌块墙片(11)的重心位置在两吊点A1和A2的连线上,保证这两个吊点A1和A2到重心的距离相等;第4步:通过销栓固定绑扎梁(8)上的滑块位置,并丈量记录两个吊点A1和A2之间的长度;第5步:吊装前校核平衡梁(4)上对应的两个吊点A1和A2之间的距离,当该距离与绑扎梁(8)两个滑块之间距离差值超过下吊装绳(6)长度的10%时,即两下吊装绳(6)与绑扎梁(8)的夹角小于80°时,要求在平衡梁(4)上重新选择位置恰当的吊点以保证两下吊装绳(6)与绑扎梁(8)的夹角为80°~90°;第6步:将吊钩(1)移到砌块墙片(11)上方,通过吊装绳(2)连接平衡梁(4),然后通过下吊装绳(6)连接绑扎梁(8);第7步:一切准备好后进行砌块墙片(11)吊装。
- 根据权利要求1所述的混凝土砌块砌体构件装配化施工方法,其特征在于,第2步中吊点的选位要求避开砌块孔中竖向钢筋的位置。
- 一种权利要求1-2所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,包括吊钩(1)、吊装绳(2)、两个上吊耳(3)、平衡梁(4)、n个下吊耳(5)、下吊装绳(6)、绑扎绳(7)、绑扎梁(8)和底座,其中n=2、4或6;所述平衡梁(4)上安装有两个上吊耳(3),所述平衡梁(4)下安装有n个下吊耳(5),所述吊钩(1)位于平衡梁(4)的上方并通过吊装绳(2)连接平衡梁(4)上的两个上吊耳(3),所述绑扎梁(8)位于平衡梁(4)的下方并通过下吊装绳(6)连接平衡梁(4)下的n个下吊耳(5),砌块墙片(11)的下方放置绑扎梁(8),所述绑扎梁(8)下方放置砌块墙片(11),所述底座位于砌块墙片(11)下方,所述绑扎绳(7)将绑扎梁(8)、砌块墙片(11)和底座进行竖向的整体绑扎。
- 根据权利要求1所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,所述底座包括底梁(9)和若干垫板(10),所述底梁(9)为与墙等宽的槽钢,翼缘端朝上,在槽钢翼缘外侧,焊接四个螺栓套件,将螺母焊接在槽钢上,以螺杆支地,通过旋转螺杆,使槽钢在垂直方向上高度可变,达到调节该点槽钢高度的目的,若干 所述垫板(10)横向放置在底梁(9)上。
- 根据权利要求1所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,所述绑扎梁(8)包括十字形标准节(14)和若干标准绑扎梁段(15),所述十字形标准节(14)的四个端面用于连接若干标准绑扎梁段(15),以便适应绑扎L形和T形砌块墙片(11)。
- 根据权利要求5所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,所述绑扎梁(8)还包括滑道、若干滑块、若干定位孔和若干销柱,所述十字形标准节(14)和若干标准绑扎梁段(15)上均设置有滑道,滑块沿滑道移动,所述滑道上设置有等间距的若干定位孔,若干销栓插入定位孔中,用于限定滑块的位置。
- 根据权利要求1所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,所述绑扎梁(8)侧面设置有若干刚环(12),所述刚环(12)与绑扎绳(7)连接。
- 根据权利要求7所述的混凝土砌块砌体构件装配化施工方法所使用的吊装装置,其特征在于,所述绑扎绳(7)为钢丝绳或者钢链。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/CN2020/072421 WO2021142701A1 (zh) | 2020-01-16 | 2020-01-16 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/CN2020/072421 WO2021142701A1 (zh) | 2020-01-16 | 2020-01-16 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021142701A1 true WO2021142701A1 (zh) | 2021-07-22 |
Family
ID=76863329
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2020/072421 WO2021142701A1 (zh) | 2020-01-16 | 2020-01-16 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
Country Status (1)
Country | Link |
---|---|
WO (1) | WO2021142701A1 (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111186763A (zh) * | 2020-01-16 | 2020-05-22 | 哈尔滨达城绿色建筑股份有限公司 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202006002664U1 (de) * | 2006-02-15 | 2006-05-11 | Müller, Siegfried | Hebevorrichtung für Schornsteine |
JP2009190820A (ja) * | 2008-02-13 | 2009-08-27 | Shimizu Corp | 揚重冶具および鉄筋の揚重方法 |
CN105197769A (zh) * | 2015-10-16 | 2015-12-30 | 重庆宝汇建筑材料有限公司 | 抓手上下及横向位置可调的钢板吊具 |
CN105438965A (zh) * | 2016-01-26 | 2016-03-30 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 集成模式砌体墙片两点对中吊装装置及其吊装方法 |
CN106592985A (zh) * | 2016-12-08 | 2017-04-26 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 一种集块建筑混凝土空心砌块墙片绑扎系统及其绑扎方法 |
CN206219045U (zh) * | 2016-12-08 | 2017-06-06 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 一种集块建筑混凝土空心砌块墙片绑扎系统用捆绑件 |
-
2020
- 2020-01-16 WO PCT/CN2020/072421 patent/WO2021142701A1/zh active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202006002664U1 (de) * | 2006-02-15 | 2006-05-11 | Müller, Siegfried | Hebevorrichtung für Schornsteine |
JP2009190820A (ja) * | 2008-02-13 | 2009-08-27 | Shimizu Corp | 揚重冶具および鉄筋の揚重方法 |
CN105197769A (zh) * | 2015-10-16 | 2015-12-30 | 重庆宝汇建筑材料有限公司 | 抓手上下及横向位置可调的钢板吊具 |
CN105438965A (zh) * | 2016-01-26 | 2016-03-30 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 集成模式砌体墙片两点对中吊装装置及其吊装方法 |
CN106592985A (zh) * | 2016-12-08 | 2017-04-26 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 一种集块建筑混凝土空心砌块墙片绑扎系统及其绑扎方法 |
CN206219045U (zh) * | 2016-12-08 | 2017-06-06 | 哈尔滨达城绿色建筑技术开发股份有限公司 | 一种集块建筑混凝土空心砌块墙片绑扎系统用捆绑件 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111186763A (zh) * | 2020-01-16 | 2020-05-22 | 哈尔滨达城绿色建筑股份有限公司 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
CN111186763B (zh) * | 2020-01-16 | 2024-05-10 | 哈尔滨达城绿色建筑股份有限公司 | 一种混凝土砌块砌体构件装配化施工方法及施工装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103410322B (zh) | 大跨度平行桁架钢连廊施工方法 | |
KR101462202B1 (ko) | 하로식 폼 트레블러 | |
CN211846850U (zh) | 装配式建筑安装用吊装装置 | |
CN212249274U (zh) | 一种装配式建筑中钢板剪力墙快速定位连接结构 | |
CN106241618A (zh) | 一种幕墙型材起吊装置 | |
WO2021142701A1 (zh) | 一种混凝土砌块砌体构件装配化施工方法及施工装置 | |
CN108570989A (zh) | 桩基钢格构柱的悬挂调垂居中体系及施工方法 | |
CN209455933U (zh) | 一种叠合板吊装用吊具 | |
CN111186763B (zh) | 一种混凝土砌块砌体构件装配化施工方法及施工装置 | |
CN112942661B (zh) | 一种带有柔性索网边界的斜拉索施工方法 | |
CN211569857U (zh) | 一种混凝土砌块砌体构件装配化施工吊装装置 | |
CN110683452A (zh) | 用于钢结构连廊整体提升的下吊点及其使用方法 | |
CN109626249B (zh) | 一种简易三维定位安装和负重装置及使用方法 | |
JP2016088729A (ja) | 吊搬用天秤 | |
CN110040632A (zh) | 一种大跨度型钢梁的分段吊装施工方法 | |
CN113636444A (zh) | 一种可以调节不同重量的吊装方法及工具 | |
CN209957212U (zh) | 一种梁下构件安装吊具及吊装系统 | |
CN203973093U (zh) | 一种组装式焊渣接盘 | |
CN208395664U (zh) | 滑轮式悬索桥吊杆张拉挂篮平台 | |
CN107916790B (zh) | 一种集块建筑装配化施工钢筋引导管拆除系统及拆除方法 | |
CN202248861U (zh) | 多层楼房浇灌混凝土楼板托吊模架代替支撑模架的装置 | |
JPH1160138A (ja) | クレーン用吊り具 | |
CN208869158U (zh) | 多功能吊具设备 | |
CN107700854B (zh) | 一种超高层核心筒的钢板墙滑移安装装置和安装方法 | |
CN210594932U (zh) | 一种t梁模板吊具 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20913386 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20913386 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20913386 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 06.09.2022) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20913386 Country of ref document: EP Kind code of ref document: A1 |