WO2020261804A1 - ガイドレールの敷設方法及び回転防止治具 - Google Patents

ガイドレールの敷設方法及び回転防止治具 Download PDF

Info

Publication number
WO2020261804A1
WO2020261804A1 PCT/JP2020/019585 JP2020019585W WO2020261804A1 WO 2020261804 A1 WO2020261804 A1 WO 2020261804A1 JP 2020019585 W JP2020019585 W JP 2020019585W WO 2020261804 A1 WO2020261804 A1 WO 2020261804A1
Authority
WO
WIPO (PCT)
Prior art keywords
guide rail
guide
rotation prevention
hoistway
laying
Prior art date
Application number
PCT/JP2020/019585
Other languages
English (en)
French (fr)
Inventor
大介 松家
伊藤 雅人
服部 誠
利昭 波田野
悠太 浜田
Original Assignee
株式会社日立ビルシステム
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立ビルシステム filed Critical 株式会社日立ビルシステム
Publication of WO2020261804A1 publication Critical patent/WO2020261804A1/ja

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • B66B7/02Guideways; Guides

Definitions

  • the present invention relates to a guide rail laying method for laying an elevator guide rail in a hoistway and a rotation prevention jig used in the guide rail laying method.
  • a guide rail is installed in the hoistway of the elevator to guide the movement of the car and the balance weight.
  • the guide rail laying work is performed by the worker on the work scaffolding provided in the hoistway.
  • Patent Document 1 As a technique related to the laying work of the guide rail, for example, there is one described in Patent Document 1.
  • Patent Document 1 a workbench is installed on the floor leading to the entrance of the hoistway, and the required number of guide rails are laid down in order on the workbench and placed one after another in a series state, and the mutual ends of these guide rails are placed.
  • a technique for flexibly connecting with a connecting metal fitting is described.
  • Patent Document 1 it is necessary to secure a work space up to the floor leading to the entrance of the hoistway. Therefore, there is a problem that the work cannot be performed when the workbench cannot be installed on the floor or the building structure under construction.
  • the purpose of this purpose is to provide a guide rail laying method and a rotation prevention jig that can perform the guide rail laying work in the hoistway in consideration of the above problems.
  • the guide rail laying method is described in the following (1) to (3) in the guide rail laying method in which a plurality of guide rails are connected and erected in the hoistway of an elevator. ) Is included.
  • (1) A lifting process in which the guide rail is lifted by a lifting device in the hoistway.
  • (2) A connection process in which a new guide rail is connected to the lower part of the lifted guide rail.
  • the rotation prevention jig is a guide rail rotation prevention jig used in a method of laying a guide rail in which a plurality of guide rails are connected and erected in the hoistway of an elevator.
  • the rotation prevention jig includes a mounting portion that is mounted in the hoistway, and a guide portion that is continuous with the mounting portion and is provided with a guide recess into which the sliding surface portion of the guide rail is inserted.
  • the guide recesses are continuously formed along the vertical direction in the guide portion.
  • the guide rail laying work can be performed in the hoistway.
  • FIG. 3A shows the rail bracket of the car side guide rail
  • FIG. 3B shows the rail bracket of the weight side guide rail.
  • FIG. 1 is a schematic configuration diagram showing a state during the laying work in the guide rail laying method.
  • FIG. 2 is a plan view of the guide rail during the laying work.
  • a plurality of guide rails 10 for supporting the car so as to be able to move up and down are installed in the hoistway 100 in which the elevator is installed.
  • the plurality of guide rails 10 are connected by a connecting member 30 in the hoistway 100.
  • the plurality of guide rails 10 are erected in the hoistway 100 along the ascending / descending direction.
  • the guide rail 10 is fixed to the wall surface 102 of the hoistway 100 by the rail bracket 11.
  • the lowermost guide rail 10A is fixed to the pit base 130 installed in the pit 101 which is the bottom of the hoistway 100.
  • FIG. 3A is an explanatory view showing a rail bracket.
  • the rail bracket 11 for fixing the guide rail 10 to the wall surface 102 includes a first member 12, a second member 13 fixed to the first member 12, a rail clip 16, and a connecting bolt 17. , With a clip bolt 18.
  • the second member 13 is fixed to the wall surface 102 by anchor bolts (not shown). Before laying the guide rail 10, the second member 13 and the first member 12 are connected by the connecting bolt 17.
  • the fixing surface portion 10a of the guide rail 10 is fixed to the first member 12 by the rail clip 16 and the clip bolt 18. At this time, the fixed surface portion 10a of the guide rail 10 faces the wall surface 102. Then, the sliding surface portion 10b on the guide rail 10 on which the car slides projects in a direction orthogonal to the wall surface 102.
  • a weight side guide rail 20 is installed in the hoistway 100 to support the balance weight connected via the car and the main rope so as to be able to move up and down.
  • the weight-side guide rail 20 is connected by the connecting member 30 and is erected in the hoistway 100 in the same manner as the car-side guide rail 10 that guides the car. Further, the weight side guide rail 20 is fixed to the wall surface 102 of the hoistway 100 by the weight side rail bracket 21.
  • FIG. 3B is an explanatory view showing the rail bracket 21 of the weight side guide rail 20.
  • the rail bracket 21 includes a first member 22, a second member 23 fixed to the first member 22, a rail clip 26, and a connecting bolt 27, similarly to the rail bracket 11 on the car side. And a clip bolt 28.
  • the second member 23 is fixed to the wall surface 102 by anchor bolts (not shown). Before laying the weight side guide rail 20, the second member 23 and the first member 22 are connected by a connecting bolt 27.
  • the fixing surface portion 20a of the weight side guide rail 20 is fixed to the first member 22 by the rail clip 26 and the clip bolt 28. At this time, the fixed surface portion 20a of the weight side guide rail 20 is arranged in a direction orthogonal to the wall surface 102. Then, the sliding surface portion 20b on which the balance weight on the weight side guide rail 20 slides projects in a direction parallel to the wall surface 102.
  • the guide rail laying device includes a work scaffold 140 installed in the pit 101 of the hoistway 100, a lifting device 150 for lifting the guide rail 10, and a rotation prevention jig 160 for preventing the guide rail 10 from rotating. ..
  • the rotation prevention jig 160 is attached to the lowermost guide rail 10A.
  • the elevating device 150 is fixed to the support member 120 installed at the top of the hoistway 100.
  • the elevating device 150 has a rope 151 that is wound up by the elevating device 150, and a lifting employment 152.
  • the lifting employment 152 is provided at the end of the rope 151. Then, at the time of laying work, the lifting employment 152 is assembled to the uppermost guide rail 10B.
  • the elevating device 150 winds up the rope 151 to elevate and move the guide rail 10B assembled to the hoisting employment 152.
  • FIG. 4 shows an anti-rotation jig 160 attached to the guide rail 10 on the car side
  • FIG. 5 shows an anti-rotation jig 160B attached to the guide rail 20 on the weight side
  • FIG. 6 is a front view showing the guide portion 162 of the rotation prevention jigs 160 and 160B.
  • the rotation prevention jig 160 has a mounting portion 161 and a guide portion 162.
  • a mounting recess 163 is formed in the mounting portion 161.
  • the mounting recess 163 extends along the vertical direction in the mounting portion 161.
  • the vertical direction of the mounting portion 161 is parallel to the vertical direction of the hoistway 100.
  • the sliding surface portion 10b of the lowermost guide rail 10A is inserted into the mounting recess 163. Then, the mounting portion 161 is mounted on the lowermost guide rail 10A by the mounting bolt 164.
  • the guide portion 162 is continuously provided on the side surface portion of the mounting portion 161 that is orthogonal to the vertical direction. Specifically, when the rotation prevention jig 160 is attached to the guide rail 10A, the guide portion 162 is continuously provided on a surface orthogonal to the surface of the attachment portion 161 facing the work scaffold 140 (see FIG. 2). Has been done. Further, the guide portion 162 is provided in a direction orthogonal to the direction in which the mounting portion 161 faces the wall surface 102.
  • the guide portion 162 is provided with a guide recess 165.
  • the guide recess 165 is provided on the side surface portion of the guide portion 162 facing the work scaffold 140 and orthogonal to the side surface portion.
  • the guide recess 165 is continuously formed along the vertical direction of the guide portion 162.
  • Guide rails 10B and 10C are inserted into the guide recess 165 from below in the vertical direction. As a result, the rotation of the guide rails 10B and 10C inserted in the guide recess 165 is regulated by the rotation prevention jig 160.
  • the guide portion 162 has a plurality of first guide rollers 166a and a plurality of second guide rollers 166b.
  • the first guide roller 166a and the second guide roller 166b are rotatably arranged on both sides of the guide recess 165, respectively.
  • a part of the first guide roller 166a and the second guide roller 166b projects toward the guide recess 165.
  • the first guide roller 166a and the second guide roller 166b come into contact with the sliding surface portions 10b of the guide rails 10B and 10B inserted into the guide recesses 165. Then, by rotating the first guide roller 166a and the second guide roller 166b, the guide rails 10B and 10C can be smoothly guided in the vertical direction, that is, in the vertical direction.
  • first guide roller 166a is arranged on the opening end side of the guide recess 165 in the direction orthogonal to the vertical direction with respect to the second guide roller 166b, and the second guide roller 166b is arranged with respect to the first guide roller 166a. It is arranged in the inner part of the guide recess 165. Further, the first guide roller 166a projects more toward the inside of the guide recess 165 than the second guide roller 166b.
  • the first guide roller 166a comes into contact with the constricted portion of the sliding surface portion 10b. Then, the second guide roller 166b comes into contact with the sliding surface of the sliding surface portion 10b that protrudes from the constricted portion. As a result, it is possible to prevent the guide rails 10B and 10C inserted in the guide recess 165 from coming out of the opening in the guide recess 165.
  • first guide roller 166a and the second guide roller 166b arranged at the lower part of the guide portion 162 in the vertical direction projects downward from the lower part of the guide portion 162 in the vertical direction.
  • the first guide roller 166a and the second guide roller 166b arranged at the lower part in the vertical direction serve as a guide when the sliding surface portion 10b of the guide rails 10B and 10B is inserted into the guide recess 165 from below in the vertical direction.
  • the sliding surface portions 10b of the guide rails 10B and 10B can be smoothly inserted into the guide recess 165.
  • the rotation prevention jig 160B on the weight side has a mounting portion 161 and a guide portion 162.
  • the guide portion 162 is continuously provided on the surface of the mounting portion 161 that is orthogonal to the surface facing the work scaffold 140 (see FIG. 2). That is, the rotation prevention jig 160B on the weight side is provided with the guide portion 162 in the direction orthogonal to the direction in which the mounting portion 161 faces the wall surface 102, similarly to the rotation prevention jig 160.
  • the mounting portion 161 is provided with a mounting recess 163, and the sliding surface portion 20b of the lowermost weight side guide rail 20A is inserted. Then, the mounting portion 161 is mounted on the sliding surface portion 20b by the mounting bolt 164.
  • the guide portion 162 is provided with a guide recess 165 into which the sliding surface portion 20b of the weight side guide rails 20B and 20C is inserted.
  • the guide recess 165 is provided with a plurality of guide rollers 166 for guiding the weight side guide rails 20B and 20C.
  • the rotation prevention jig 160B on the weight side can also prevent the rotation of the weight side guide rails 20B and 20C inserted in the guide recess 165 of the guide portion 162.
  • FIG. 7 is a flowchart showing a method of laying the guide rail.
  • 8 and 9 are explanatory views showing a method of laying the guide rail.
  • the worker P1 first installs the work scaffold 140 in the pit 101, which is the bottom of the hoistway 100 (step S1).
  • the lowermost guide rail 10A is fixed to the pit base 130 installed in the pit 101 (step S2).
  • the rail bracket 11A is attached to the guide rail 10, and the rail bracket 11A is fixed to the wall surface 102.
  • the lowermost guide rail 10A is fixed to the hoistway 100.
  • the rotation prevention jig 160 is attached to the upper part of the lowermost guide rail 10A (step S3). Further, the rotation prevention jig 160 is attached at a position where the length from the lower part of the guide portion 162 in the vertical direction to the floor surface of the pit 101 is longer than the length in the longitudinal direction of the guide rail 10. That is, the rotation prevention jig 160 is installed at a position higher than the length of the guide rail 10 in the longitudinal direction.
  • step S4 lifting step
  • the operator P1 attaches the rail bracket 11 to the uppermost guide rail 10B.
  • step S5 connecting step
  • step S6 attachment step
  • step S7 the elevating device 150 is operated to further raise the lifted guide rails 10B and 10C
  • the rotation torque generated in the rope 151 may cause the guide rails 10B and 10C lifted by the elevating device 150 to rotate. Then, as the guide rails 10B and 10C rotate, the rail bracket 11 attached to the guide rails 10B and 10C may come into contact with other structures in the hoistway 100.
  • the rotation prevention jig 160 is used to prevent the guide rails 10B and 10C from rotating. This makes it possible to prevent the guide rails 10B and 10C from rotating and the rail bracket 11 from coming into contact with other structures in the hoistway 100.
  • the rotation prevention jig 160 provides the guide rails 10B and 10C with the fixed surface portions 10a of the guide rails 10B and 10C oriented in a direction orthogonal to the direction facing the wall surface 102. I support it. As a result, it is possible to prevent the rail bracket 11 attached to the fixed surface portion 10a from coming into contact with the wall surface 102.
  • the rotation prevention jig 160 supports the guide rails 10B and 10C with the fixed surface portion 10a and the rail bracket 11 oriented in a direction orthogonal to the direction facing the work scaffold 140.
  • the clip bolt 18 can be easily fastened from the work scaffold 140 side without being hidden by the first member 12 and the guide rails 10B and 10C.
  • the guide rails 10B and 10C can be smoothly raised by rotating the first guide roller 166a and the second guide roller 166b that come into contact with the sliding surface portions 10b of the guide rails 10B and 10C.
  • step S7 the operator P1 determines whether or not all the guide rails 10B and 10C except the lowermost guide rail 10A are connected (step S8). If the unconnected guide rail 10C remains in the process of step S8 (NO determination in step S8), the process returns to step 5. Then, the processes of steps S5 to S7 are repeated until all the guide rails 10B and 10C are connected and the rail bracket 11 is attached.
  • step S8 when it is determined that the connection work of all the guide rails 10B and 10C is completed (YES determination in step S8), the rotation prevention jig 160 is removed from the lowermost guide rail 10A.
  • the guide rail 10C lifted by the elevating device 150 is connected to the upper part of the lowermost guide rail 10A by the connecting member 30 (step S10).
  • step S11 the rail brackets 11 attached to the other guide rails 10B and 10C except for the lowermost guide rail 10A are fixed to the wall surface 102. As a result, the laying work of the guide rail 10 is completed.
  • the work of connecting the guide rail 10 and the work of attaching the rail bracket 11 can be performed in the work scaffold 140 or the pit 101. Therefore, the guide rail 10 and the rail bracket 11 used in the laying work are all carried into the pit 101 of the hoistway 100. As a result, it is not necessary to provide a work place on the floor leading to the hoistway, and the guide rail 10 can be laid in the hoistway 100.
  • the worker P1 rides on a lift that moves up and down in the hoistway 100.
  • the rail bracket 11 is attached by the work scaffold 140 or the pit 101 when connecting the guide rail 10. Therefore, it is not necessary to carry the rail bracket 11 into the lift, and the work space in the lift can be expanded.
  • step S11 can be performed by the robot.
  • the safety of the guide rail 10 laying work can be enhanced by the worker P1 performing the work in the low place and the robot performing the work in the high place of the lift in step S11.
  • FIG. 10 is a flowchart showing a method of laying the guide rail according to the second embodiment.
  • the guide rail laying method according to the second embodiment is different from the guide rail laying method according to the first embodiment in that the rail bracket 11 is attached to the work scaffold 140. .. Therefore, the description of the process common to the guide rail laying method according to the first embodiment will be omitted.
  • step S21 the worker P1 installs the work scaffold 140 in the pit 101, which is the bottom of the hoistway 100.
  • the lowermost guide rail 10A is fixed to the pit base 130 installed in the pit 101 (step S22).
  • the rotation prevention jig 160 is attached to the upper part of the lowermost guide rail 10A (step S23).
  • step S24 the lifting employee 152 is attached to the uppermost guide rail 10B, and the guide rail 10B is raised to a predetermined height (step S24). Then, as shown in FIG. 9, the next guide rail 10C is connected to the lower part of the guide rail 10B lifted on the work scaffold 140 by the connecting member 30 (step S25).
  • step S25 the connected and lifted guide rails 10B and 10C are further raised to a predetermined height (step S26). Then, the worker P1 attaches the rail bracket 11 to the guide rail 10C which is connected and lifted on the work scaffold 140 (step S27). Then, the elevating device 150 is operated to further raise the lifted guide rails 10B and 10C (step S28).
  • connection work of the guide rail 10 not only the connection work of the guide rail 10 but also the attachment work of the rail bracket 11 can be performed on the work scaffold 140.
  • the number of times the worker P1 reciprocates between the work scaffold 140 and the floor surface of the pit 101 for the work of connecting the guide rail 10 and the work of attaching the rail bracket 11 can be reduced, and the work time can be reduced. It can be shortened.
  • FIG. 11 is an explanatory diagram showing a method of laying the guide rail according to the third embodiment.
  • FIG. 12 is a plan view showing a positioning jig used in the guide rail laying method according to the third embodiment.
  • the difference between the guide rail laying method according to the third embodiment and the guide rail laying method according to the first embodiment is that the alignment jig is provided. Therefore, here, the alignment jig will be described, and the same reference numerals will be given to the parts common to the guide rail laying method according to the first embodiment, and duplicate description will be omitted.
  • the alignment jig 190 is attached to the intermediate portion of the lowermost guide rail 10A.
  • the alignment jig 190 includes the sliding surface portion 10b of the guide rails 10B and 10C and the guide recess 165 of the rotation prevention jig 160. Align.
  • the alignment jig 190 is formed with a mounting recess 193 and a alignment recess 195.
  • the mounting recess 193 and the alignment recess 195 are recesses formed continuously in the vertical direction of the alignment jig 190.
  • the sliding surface portion 10b of the lowermost guide rail 10A is inserted into the mounting recess 193.
  • the alignment jig 190 is attached to the lowermost guide rail 10A by the attachment bolt 194.
  • the alignment recess 195 faces the guide recess 165 of the rotation prevention jig 160 arranged above in the vertical direction.
  • the sliding surface portions 10b of the guide rails 10B and 10C to be connected are inserted into the alignment recess 195. Further, the sliding surface portion 10b is inserted into the positioning recess 195 from a direction orthogonal to the vertical direction. As a result, the sliding surface portions 10b of the guide rails 10B and 10C face the guide recess 165 of the rotation prevention jig 160 arranged above in the vertical direction.
  • the alignment jig 190 can align the sliding surface portion 10b of the guide rails 10B and 10C with the guide recess 165 of the rotation prevention jig 160. As a result, the sliding surface portions 10b of the guide rails 10B and 10C can be smoothly inserted into the guide recesses 165 of the rotation prevention jig 160 from below in the vertical direction. As a result, the workability of the laying work of the guide rail 10 can be improved.
  • the rotation prevention jig 160 is attached to the lowermost guide rail 10A, but the present invention is not limited to this, and the rotation prevention jig 160 is installed in the hoistway 100. It may be attached to a member different from the guide rail 10A provided. When the rotation prevention jig 160 is attached to a member different from the lowermost guide rail 10A, the lowermost guide rail 10A is fixed in the hoistway 100 after the connection work of the other guide rails 10B and 10C is completed. You may.
  • the present invention is not limited to this, and the guide rollers 166a and 166b may not be provided in the guide recesses 165.
  • the alignment jig 190 shown in FIG. 12 may be applied as a rotation prevention jig.
  • the height at which the rotation prevention jig is installed may be lower than the length of the guide rail 10 in the longitudinal direction.
  • the opening shape of the guide recess 165 may be made to correspond to the shape of the constricted portion of the sliding surface portion 10b of the guide rail 10, and a part of the opening width may be narrowed.
  • the guide rail 10 may be provided with a mark indicating the mounting position of the rail bracket 11.
  • the mark is provided on the guide rail 10 by, for example, a marking line or printing.

Abstract

ガイドレールの敷設方法は、昇降路内においてガイドレールを吊り上げる工程と、ガイドレールの下部に、ガイドレールを接続する工程と、ガイドレールに、レールブラケットを取り付ける工程と、を含む。そして、吊り上げ工程、接続工程及び取付工程を繰り返し行う。

Description

ガイドレールの敷設方法及び回転防止治具
 本発明は、エレベーターのガイドレールを昇降路内に敷設するガイドレールの敷設方法及びこのガイドレールの敷設方法で用いられる回転防止治具に関するものである。
 一般に、エレベーターの昇降路内には、乗りかごや釣合おもりの移動をガイドするガイドレールが設置されている。ガイドレールの敷設作業は、作業者が昇降路内に設けられた作業足場上で行われる。このガイドレールの敷設作業に関する技術としては、例えば、特許文献1に記載されているようなものがある。
 特許文献1には、昇降路の入口に通じるフロア上に作業台を設置し、この作業台上に所要本数のガイドレールを順番に寝かせて直列状態に次々載せると共に、これらガイドレール相互端部を連結金具により屈曲可能に連結する技術が記載されている。
特開平5-178561号公報
 しかしながら、特許文献1に記載された技術では、昇降路の入口に通じるフロアにまで作業スペースを確保する必要があった。そのため、建設中の建築構造物や、フロアに作業台を設置することができない場合等では、作業を行うことができない、という問題を有していた。
 本目的は、上記の問題点を考慮し、ガイドレールの敷設作業を昇降路内で行うことができるガイドレールの敷設方法及び回転防止治具を提供することにある。
 上記課題を解決し、目的を達成するため、ガイドレールの敷設方法は、複数のガイドレールを連結し、エレベーターの昇降路内に立設させるガイドレールの敷設方法において、以下(1)から(3)に示す工程を含む。
(1)昇降路内においてガイドレールを昇降装置により吊り上げる吊り上げ工程。
(2)吊り上げられたガイドレールの下部に、新たなガイドレールを接続する接続工程。(3)接続したガイドレールに、昇降路の壁面に固定されるレールブラケットを取り付ける取付工程。
 そして、吊り上げ工程、接続工程及び取付工程を繰り返し行う。
 また、回転防止治具は、複数のガイドレールを連結し、エレベーターの昇降路内に立設させるガイドレールの敷設方法で用いられるガイドレールの回転防止治具である。
 回転防止治具は、昇降路内に取り付けられる取付部と、取付部に連続し、ガイドレールの摺動面部が挿入されるガイド凹部が設けられたガイド部と、を備えている。そして、ガイド凹部は、ガイド部における上下方向に沿って連続して形成されている。
 上記構成のガイドレールの敷設方法及び回転防止治具によれば、ガイドレールの敷設作業を昇降路内で行うことができる。
第1の実施の形態例にかかるガイドレールの敷設方法における敷設作業中の状態を示す概略構成図である。 第1の実施の形態例にかかるガイドレールの敷設方法における敷設作業中の状態を示す平面である。 レールブラケットを示すもので、図3Aはかご側ガイドレールのレールブラケットを示し、図3Bはおもり側ガイドレールのレールブラケットを示す。 第1の実施の形態例にかかる回転防止治具を示す説明図である。 第1の実施の形態例にかかる回転防止治具を示すものでおもり側ガイドレールに用いられる回転防止治具を示す説明図である。 第1の実施の形態例にかかる回転防止治具を示す正面図である。 第1の実施の形態例にかかるガイドレールの敷設方法を示すフローチャートである。 第1の実施の形態例にかかるガイドレールの敷設方法を示す説明図である。 第1の実施の形態例にかかるガイドレールの敷設方法を示す説明図である。 第2の実施の形態例にかかるガイドレールの敷設方法を示すフローチャートである。 第3の実施の形態例にかかるガイドレールの敷設方法を示す説明図である。 第3の実施の形態例にかかるガイドレールの敷設方法で用いられる位置合わせ治具を示す平面図である。
 以下、実施の形態例にかかるガイドレールの敷設方法及び回転防止治具について、図1~図12を参照して説明する。なお、各図において共通の部材には、同一の符号を付している。
1.第1の実施の形態例
1-1.ガイドレールの構成例及びガイドレールの敷設装置
 まず、エレベーターのガイドレール及びガイドレールの敷設装置の第1の実施の形態例(以下、「本例」という。)について、図1~図5を参照して説明する。
 図1は、ガイドレールの敷設方法における敷設作業中の状態を示す概略構成図である。図2は、ガイドレールの敷設作業中の状態における平面図である。
 図1に示すように、エレベーターが設置される昇降路100内には、乗りかごを昇降可能に支持する複数のガイドレール10が設置される。複数のガイドレール10は、昇降路100内において連結部材30により連結される。そして、複数のガイドレール10は、昇降路100内において昇降方向に沿って立設している。図2に示すように、ガイドレール10は、レールブラケット11によって昇降路100の壁面102に固定される。また、最下段のガイドレール10Aは、昇降路100の底部であるピット101に設置されたピットベース130に固定される。
 図3Aは、レールブラケットを示す説明図である。
 図3Aに示すように、ガイドレール10を壁面102に固定するレールブラケット11は、第1部材12と、第1部材12に固定される第2部材13と、レールクリップ16と、連結ボルト17と、クリップボルト18とを有している。第2部材13は、不図示のアンカーボルトにより壁面102に固定される。ガイドレール10の敷設作業を行う前に、第2部材13と第1部材12は、連結ボルト17により連結される。
 第1部材12には、ガイドレール10の固定面部10aがレールクリップ16及びクリップボルト18により固定される。このとき、ガイドレール10の固定面部10aは、壁面102と対向する。そして、ガイドレール10における乗りかごが摺動する摺動面部10bは、壁面102に対して直交する方向に向けて突出する。
 また、図2に示すように、昇降路100内には、乗りかごと主ロープを介して連結される釣合おもりを昇降可能に支持するおもり側ガイドレール20が設置される。おもり側ガイドレール20は、乗りかごをガイドするかご側のガイドレール10と同様に、連結部材30により連結されて、昇降路100内に立設される。また、おもり側ガイドレール20は、おもり側レールブラケット21によって昇降路100の壁面102に固定される。
 図3Bは、おもり側ガイドレール20のレールブラケット21を示す説明図である。 図3Bに示すように、レールブラケット21は、かご側のレールブラケット11と同様に、第1部材22と、第1部材22に固定される第2部材23と、レールクリップ26と、連結ボルト27と、クリップボルト28とを有している。第2部材23は、不図示のアンカーボルトにより壁面102に固定される。おもり側ガイドレール20の敷設作業を行う前に、第2部材23と第1部材22は、連結ボルト27により連結される。
 第1部材22には、おもり側ガイドレール20の固定面部20aがレールクリップ26及びクリップボルト28により固定される。このとき、おもり側ガイドレール20の固定面部20aは、壁面102に対して直交する方向に配置される。そして、おもり側ガイドレール20における釣合おもりが摺動する摺動面部20bは、壁面102と平行をなす方向に突出する。
 次に、ガイドレールの敷設方法で用いられるガイドレール敷設装置について説明する。 ガイドレール敷設装置は、昇降路100のピット101に設置される作業足場140と、ガイドレール10を吊り上げる昇降装置150と、ガイドレール10の回転を防止する回転防止治具160とを有している。回転防止治具160は、最下段のガイドレール10Aに取り付けられる。
 昇降装置150は、昇降路100の頂部に設置された支持部材120に固定される。昇降装置150は、昇降装置150により巻き上げられるロープ151と、吊り上げ雇152とを有している。吊り上げ雇152は、ロープ151の端部に設けられている。そして、敷設作業時において、吊り上げ雇152は、最上段のガイドレール10Bに組み付けられる。昇降装置150は、ロープ151を巻き上げることで、吊り上げ雇152に組み付けられたガイドレール10Bを昇降移動させる。
 次に、図4~図6を参照して回転防止治具160の構成について説明する。
 図4は、かご側のガイドレール10に取り付けられる回転防止治具160を示し、図5は、おもり側ガイドレール20に取り付けられる回転防止治具160Bを示している。図6は、回転防止治具160、160Bのガイド部162を示す正面図である。
 図4に示すように、回転防止治具160は、取付部161と、ガイド部162とを有している。取付部161には、取付凹部163が形成されている。取付凹部163は、取付部161における上下方向に沿って延在している。なお、取付部161の上下方向は、昇降路100の昇降方向と平行をなす。
 取付凹部163には、最下段のガイドレール10Aの摺動面部10bが挿入される。そして、取付部161は、取付ボルト164により最下段のガイドレール10Aに取り付けられる。
 ガイド部162は、取付部161における上下方向と直交する側面部に連続して設けられている。具体的には、ガイド部162は、回転防止治具160をガイドレール10Aに取り付けた際に、取付部161における作業足場140(図2参照)と対向する面と直交する面に連続して設けられている。また、ガイド部162は、取付部161が壁面102と対向する方向と直交する方向に設けられる。
 ガイド部162には、ガイド凹部165が設けられている。回転防止治具160を最下段のガイドレール10Aに取り付けた際に、ガイド凹部165は、ガイド部162における作業足場140と対向する側面部と直交する側面部に設けられている。ガイド凹部165は、ガイド部162の上下方向に沿って連続して形成されている。このガイド凹部165には、ガイドレール10B、10Cが上下方向の下方から挿入される。これにより、ガイド凹部165に挿入されたガイドレール10B、10Cの回転は、回転防止治具160により規制される。
 図4及び図6に示すように、ガイド部162は、複数の第1ガイドローラ166aと、複数の第2ガイドローラ166bを有している。第1ガイドローラ166aと第2ガイドローラ166bは、それぞれガイド凹部165の両側に回転可能に配置されている。そして、第1ガイドローラ166a及び第2ガイドローラ166bの一部は、ガイド凹部165に向けて張り出している。第1ガイドローラ166a及び第2ガイドローラ166bは、ガイド凹部165に挿入されたガイドレール10B、10Bの摺動面部10bに接触する。そして、第1ガイドローラ166a及び第2ガイドローラ166bが回転することで、ガイドレール10B、10Cを上下方向、すなわち昇降方向に沿ってスムーズにガイドすることができる。
 また、第1ガイドローラ166aは、第2ガイドローラ166bよりもガイド凹部165における上下方向と直交する方向の開口端側に配置されており、第2ガイドローラ166bは、第1ガイドローラ166aよりもガイド凹部165の奥部に配置されている。また、第1ガイドローラ166aは、第2ガイドローラ166bよりもガイド凹部165の内側に向けて張り出している。
 第1ガイドローラ166aは、摺動面部10bのくびれ部に接触する。そして、第2ガイドローラ166bは、摺動面部10bにおけるくびれ部から突出する摺動面に接触する。これにより、ガイド凹部165に挿入されたガイドレール10B、10Cがガイド凹部165における開口から抜け出ることを防ぐことができる。
 また、ガイド部162における上下方向の下部に配置される第1ガイドローラ166a及び第2ガイドローラ166bは、その一部がガイド部162の下部から上下方向の下方に向けて張り出している。この上下方向の下部に配置された第1ガイドローラ166a及び第2ガイドローラ166bが、ガイドレール10B、10Bの摺動面部10bを上下方向の下方からガイド凹部165に挿入する際のガイドとなる。これにより、ガイドレール10B、10Bの摺動面部10bをスムーズにガイド凹部165に挿入することができる。
 図5に示すように、おもり側の回転防止治具160Bは、取付部161と、ガイド部162とを有している。ガイド部162は、取付部161における作業足場140(図2参照)と対向する面と直交する面に連続して設けられている。すなわち、おもり側の回転防止治具160Bは、回転防止治具160と同様に、取付部161が壁面102と対向する方向と直交する方向にガイド部162が設けられる。
 取付部161には、取付凹部163が設けられており、最下段のおもり側ガイドレール20Aの摺動面部20bが挿入される。そして、取付部161は、取付ボルト164により摺動面部20bに取り付けられる。
 ガイド部162には、おもり側ガイドレール20B、20Cの摺動面部20bが挿入されるガイド凹部165が設けられている。そして、ガイド凹部165には、おもり側ガイドレール20B、20Cをガイドする複数のガイドローラ166が設けられている。
 その他の構成は、上述したかご側の回転防止治具160と同様であるため、その説明は省略する。このおもり側の回転防止治具160Bによっても、ガイド部162のガイド凹部165に挿入されたおもり側ガイドレール20B、20Cの回転を防止することができる。
1-2.ガイドレールの敷設方法
 次に、ガイドレールの敷設方法について図1、図7~図9を参照して説明する。
 図7は、ガイドレールの敷設方法を示すフローチャートである。図8及び図9は、ガイドレールの敷設方法を示す説明図である。
 図7に示すように、まず作業者P1は、昇降路100の底部であるピット101に作業足場140を設置する(ステップS1)。次に、最下段のガイドレール10Aをピット101に設置されたピットベース130に固定する(ステップS2)。また、ステップS2の処理では、ガイドレール10にレールブラケット11Aを取り付け、このレールブラケット11Aを壁面102に固定する。これにより、最下段のガイドレール10Aが昇降路100に固定される。
 次に、最下段のガイドレール10Aの上部に回転防止治具160を取り付ける(ステップS3)。また、ガイド部162の上下方向の下部からピット101の床面までの長さがガイドレール10の長手方向の長さよりも長くなる位置に、回転防止治具160が取り付けられる。すなわち、回転防止治具160は、ガイドレール10の長手方向の長さよりも高い位置に設置される。
 次に、図8に示すように、最上段のガイドレール10Bを回転防止治具160に挿入し、最上段のガイドレール10Bに昇降装置150の吊り上げ雇152を取り付ける。そして、最上段のガイドレール10Bを昇降装置150によって所定の高さまで上昇させる(ステップS4:吊り上げ工程)。また、ステップS4の処理では、作業者P1は、最上段のガイドレール10Bにレールブラケット11を取り付ける。
 次に、図9に示すように、作業者P1は、作業足場140上において最上段のガイドレール10Bの下部に次のガイドレール10Cを連結部材30によって接続させる(ステップS5:接続工程)。次に、作業者P1は、ピット101に移動し、接続したガイドレール10Cにレールブラケット11を取り付ける(ステップS6:取付工程)。そして、昇降装置150を操作し、吊り上げたガイドレール10B、10Cをさらに上昇させる(ステップS7)。
 なお、ロープ151に発生する回転トルクによって、昇降装置150により吊り上げられたガイドレール10B、10Cが回転するおそれがある。そして、ガイドレール10B、10Cが回転することで、ガイドレール10B、10Cに取り付けたレールブラケット11が昇降路100内の他の構造物に接触する可能性がある。これに対して、本例のガイドレールの敷設方法では、回転防止治具160を用いてガイドレール10B、10Cの回転を防止している。これにより、ガイドレール10B、10Cが回転し、レールブラケット11が昇降路100内の他の構造物に接触することを防ぐことができる。
 また、図2及び図4に示すように、回転防止治具160は、ガイドレール10B、10Cの固定面部10aを壁面102と対向する方向と直交する方向に向けた状態でガイドレール10B、10Cを支持している。これにより、固定面部10aに取り付けられたレールブラケット11が壁面102に接触することを防ぐことができる。
 さらに、回転防止治具160は、固定面部10a及びレールブラケット11を作業足場140と対向する方向と直交する方向に向けて、ガイドレール10B、10Cを支持している。これにより、クリップボルト18が第1部材12やガイドレール10B、10Cによって隠れることなく、クリップボルト18の締結作業を作業足場140側から容易に行うことができる。
 また、ガイドレール10B、10Cの摺動面部10bに接触する第1ガイドローラ166a及び第2ガイドローラ166bが回転することで、ガイドレール10B、10Cをスムーズに上昇させることができる。
 ステップS7の処理が完了すると、最下段のガイドレール10Aを除く全てのガイドレール10B、10Cを接続したか否かを作業者P1が判断する(ステップS8)。ステップS8の処理において、接続されていないガイドレール10Cが残っている場合(ステップS8のNO判定)、ステップ5の処理に戻る。そして、全てのガイドレール10B、10Cの接続及びレールブラケット11の取り付け作業が完了するまで、ステップS5からステップS7の処理を繰り返す。
 また、ステップS8の処理において、全てのガイドレール10B、10Cの接続作業が完了したと判断した場合(ステップS8のYES判定)、最下段のガイドレール10Aから回転防止治具160を取り外す。次に、最下段のガイドレール10Aの上部に、昇降装置150によって吊り上げたガイドレール10Cを連結部材30によって接続する(ステップS10)。
 次に、最下段のガイドレール10Aを除く他のガイドレール10B、10Cに取り付けたレールブラケット11を壁面102に固定する(ステップS11)。これにより、ガイドレール10の敷設作業が完了する。
 上述したように、ガイドレール10の接続作業及びレールブラケット11の取り付け作業を、作業足場140やピット101内で行うことができる。そのため、敷設作業で用いられるガイドレール10やレールブラケット11は、全て昇降路100のピット101内に搬入される。これにより、昇降路に通じるフロア等に作業場を設ける必要がなくなり、昇降路100内でガイドレール10の敷設作業を行うことができる。
 また、ステップS11の処理におけるレールブラケット11の壁面への固定作業では、作業者P1が昇降路100内を昇降移動するリフトに乗って行われる。上述したように、レールブラケット11は、ガイドレール10を接続する際に、作業足場140やピット101で取り付けられている。そのため、リフトにレールブラケット11を搬入する必要がなくなり、リフトでの作業スペースを広げることができる。
 さらに、リフトでの作業スペースを広げることができるため、リフトにロボットを載置するスペースができ、ステップS11の処理をロボットによって行うことができる。これにより、低所での作業を作業者P1が行い、ステップS11におけるリフトの高所の作業をロボットが行うことで、ガイドレール10の敷設作業の安全性を高めることができる。
 おもり側ガイドレール20の敷設方法は、上述したかご側のガイドレール10の敷設方法と同様であるため、その説明は省略する。
2.第2の実施の形態例
 次に、ガイドレールの敷設方法の第2の実施の形態例について図10を参照して説明する。
 図10は、第2の実施の形態例にかかるガイドレールの敷設方法を示すフローチャートである。
 この第2の実施の形態例にかかるガイドレールの敷設方法が第1の実施の形態例にかかるガイドレールの敷設方法と異なる点は、レールブラケット11の取り付け作業を作業足場140で行う点である。そのため、第1の実施の形態例にかかるガイドレールの敷設方法と共通する工程の説明は省略する。
 図10に示すように、まず作業者P1は、昇降路100の底部であるピット101に作業足場140を設置する(ステップS21)。次に、最下段のガイドレール10Aをピット101に設置されたピットベース130に固定する(ステップS22)。そして、最下段のガイドレール10Aの上部に回転防止治具160を取り付ける(ステップS23)。
 次に、最上段のガイドレール10Bに吊り上げ雇152を取り付け、ガイドレール10Bを所定の高さまで上昇させる(ステップS24)。そして、図9に示すように、作業足場140上において吊り上げたガイドレール10Bの下部に次のガイドレール10Cを連結部材30によって接続させる(ステップS25)。
 この第2の実施の形態例にかかる敷設方法では、ステップS25の処理の後に、接続し、かつ吊り上げたガイドレール10B、10Cをさらに所定の高さまで上昇させる(ステップS26)。そして、作業者P1は、作業足場140上において、接続し、かつ吊り上げたガイドレール10Cにレールブラケット11を取り付ける(ステップS27)。そして、昇降装置150を操作し、吊り上げたガイドレール10B、10Cをさらに上昇させる(ステップS28)。
 なお、以下の工程は、上述した第1の実施の形態例にかかるガイドレールの敷設方法と同様であるため、その説明は省略する。このような第2の実施の形態例にかかるガイドレールの敷設方法においても、上述した第1の実施の形態例にかかるガイドレールの敷設方法と同様の作用及び効果を得ることができる。
 この第2の実施の形態例にかかるガイドレール10の敷設方法によれば、ガイドレール10の接続作業だけでなく、レールブラケット11の取り付け作業も作業足場140上で行うことができる。これにより、作業者P1がガイドレール10の接続作業と、レールブラケット11の取り付け作業のために、作業足場140とピット101の床面との間を往復する回数を削減することがき、作業時間の短縮を図ることができる。
3.第3の実施の形態例
 次に、図11及び図12を参照して第3の実施の形態例にかかるガイドレールの敷設方法について説明する。
 図11は、第3の実施の形態例にかかるガイドレールの敷設方法を示す説明図である。図12は、第3の実施の形態例にかかるガイドレールの敷設方法で用いられる位置合わせ治具を示す平面図である。
 この第3の実施の形態例にかかるガイドレールの敷設方法が第1の実施の形態例にかかるガイドレールの敷設方法と異なる点は、位置合わせ治具を設けた点である。のため、ここでは、位置合わせ治具について説明し、第1の実施の形態例にかかるガイドレールの敷設方法と共通する部分には同一の符号を付して重複した説明を省略する。
 図11に示すように、最下段のガイドレール10Aの上部に回転防止治具160を取り付ける際に、最下段のガイドレール10Aの中間部には、位置合わせ治具190が取り付けられる。回転防止治具160に上下方向の下方からガイドレール10B、10Cを挿入する際に、位置合わせ治具190は、ガイドレール10B、10Cの摺動面部10bと回転防止治具160のガイド凹部165との位置合わせを行う。
 図12に示すように、位置合わせ治具190は、取付凹部193と、位置合わせ凹部195が形成されている。取付凹部193及び位置合わせ凹部195は、位置合わせ治具190の上下方向に連続して形成された凹部である。取付凹部193には、最下段のガイドレール10Aの摺動面部10bが挿入される。そして、位置合わせ治具190は、取付ボルト194により最下段のガイドレール10Aに取り付けられる。
 位置合わせ凹部195は、上下方向の上方に配置される回転防止治具160のガイド凹部165を臨む。位置合わせ凹部195には、接続するガイドレール10B、10Cの摺動面部10bが挿入される。また、摺動面部10bは、上下方向と直交する方向から位置合わせ凹部195に差し込まれる。これにより、ガイドレール10B、10Cの摺動面部10bが、上下方向の上方に配置された回転防止治具160のガイド凹部165を臨む。
 位置合わせ治具190によってガイドレール10B、10Cの摺動面部10bと、回転防止治具160のガイド凹部165との位置合わせを行うことができる。これにより、ガイドレール10B、10Cの摺動面部10bを回転防止治具160のガイド凹部165に上下方向の下方からスムーズに挿入することができる。その結果、ガイドレール10の敷設作業の作業性を向上させることができる。
 このような第2の実施の形態例にかかるガイドレールの敷設方法においても、上述した第1の実施の形態例にかかるガイドレールの敷設方法と同様の作用及び効果を得ることができる。
 なお、本発明は上述しかつ図面に示した実施の形態に限定されるものではなく、請求の範囲に記載した発明の要旨を逸脱しない範囲内で種々の変形実施が可能である。
 上述した実施の形態例では、回転防止治具160を最下段のガイドレール10Aに取り付ける例を説明したが、これに限定されるものではなく、回転防止治具160は、昇降路100内に設置されているガイドレール10Aとは異なる部材に取り付けてもよい。回転防止治具160を最下段のガイドレール10Aとは異なる部材に取り付ける場合、他のガイドレール10B、10Cの接続作業が完了してから、最下段のガイドレール10Aを昇降路100内に固定してもよい。
 また、ガイド凹部165にガイドローラ166a、166bを設けた回転防止治具160について説明したが、これに限定されるものではなく、ガイド凹部165にガイドローラ166a、166bを設けなくてもよい。また、図12に示す位置合わせ治具190を回転防止治具として適用してもよい。なお、図12に示す位置合わせ治具190を回転防止治具として適用する場合、回転防止治具を設置する高さは、ガイドレール10の長手方向の長さよりも低い位置であってもよい。
 また、ガイド凹部165の開口形状を、ガイドレール10の摺動面部10bのくびれ部の形状に対応させて、一部の開口幅を狭く形成してもよい。これにより、ガイドレール10をガイド凹部165に挿入した際に、ガイドレール10における上下方向と直交する方向の移動を規制することができ、ガイドレール10が作業者の意図に反してガイド凹部165から抜け出ることを防ぐことができる。
 さらに、ガイドレール10には、レールブラケット11の取り付け位置を示す印を設けてもよい。印は、例えば、ケガキ線や、印字等によりガイドレール10に設けられる。
 10、10A、10B、10C…ガイドレール、 10a…固定面部、 10b…摺動面部、 11、11A…レールブラケット、 12…第1部材、 13…第2部材、 16…レールクリップ、 17…連結ボルト、 18…クリップボルト、 30…連結部材、 100…昇降路、 101…ピット、 102…壁面、 120…支持部材、 130…ピットベース、 140…作業足場、 150…昇降装置、 151…ロープ、 152…吊り上げ雇、 160、160B…回転防止治具、 161…取付部、 162…ガイド部、 163…取付凹部、 164…取付ボルト、 165…ガイド凹部、 166a、166b、166…ガイドローラ、 190…位置合わせ治具(回転防止治具)、 193…取付凹部、 194…取付ボルト、 195…位置合わせ凹部、 P1…作業者

Claims (12)

  1.  複数のガイドレールを連結し、エレベーターの昇降路内に立設させるガイドレールの敷設方法において、
     前記昇降路内において前記ガイドレールを昇降装置により吊り上げる吊り上げ工程と、
     吊り上げられた前記ガイドレールの下部に、新たなガイドレールを接続する接続工程と、
     接続した前記ガイドレールに、前記昇降路の壁面に固定されるレールブラケットを取り付ける取付工程と、を含み、
     前記吊り上げ工程、前記接続工程及び前記取付工程を繰り返し行う
     ガイドレールの敷設方法。
  2.  前記取付工程は、前記ガイドレールを前記昇降装置により所定の高さまで上昇させてから行われる
     請求項1に記載のガイドレールの敷設方法。
  3.  前記吊り上げ工程、前記接続工程及び前記取付工程を行う際、前記ガイドレールにおける前記レールブラケットが固定される固定面部が前記昇降路の壁面と向き合わない位置で、前記ガイドレールは吊り上げられる
     請求項1又は2に記載のガイドレールの敷設方法。
  4.  前記ガイドレールの回転を防止する回転防止治具が前記昇降路内に取り付けられる
     請求項3に記載のガイドレールの敷設方法。
  5.  前記回転防止治具には、前記ガイドレールの摺動面部が上下方向の下方から挿入されるガイド凹部が設けられている
     請求項4に記載のガイドレールの敷設方法。
  6.  前記回転防止治具における前記昇降路の床面からの設置高さは、前記ガイドレールの長手方向の長さよりも長く設定される
     請求項5に記載のガイドレールの敷設方法。
  7.  前記ガイドレールの前記摺動面部と、前記回転防止治具の前記ガイド凹部との位置を合わせる位置合わせ治具が前記昇降路内に取り付けられる
     請求項5に記載のガイドレールの敷設方法。
  8.  前記吊り上げ工程の前に、複数の前記ガイドレールのうち最下段に配置される最下段ガイドレールが前記昇降路の床面に固定され、
     前記回転防止治具は、前記最下段ガイドレールに取り付けられる
     請求項4に記載のガイドレールの敷設方法。
  9.  複数のガイドレールを連結し、エレベーターの昇降路内に立設させるガイドレールの敷設方法で用いられるガイドレールの回転防止治具において、
     前記昇降路内に取り付けられる取付部と、
     前記取付部に連続し、前記ガイドレールの摺動面部が挿入されるガイド凹部が設けられたガイド部と、を備え、
     前記ガイド凹部は、前記ガイド部における上下方向に沿って連続して形成されている
     回転防止治具。
  10.  前記ガイド凹部は、前記ガイド部における、前記昇降路のピットに設置された作業足場と対向する側面部と直交する側面部に形成されている
     請求項9に記載の回転防止治具。
  11.  前記ガイド凹部は、前記摺動面部のくびれ部の形状に対応させて、一部の開口幅が狭く形成されている
     請求項9に記載の回転防止治具。
  12.  前記ガイド部には、前記ガイド凹部に一部が張り出し、前記摺動面部と接触するガイドローラが設けられている
     請求項9に記載の回転防止治具。
PCT/JP2020/019585 2019-06-24 2020-05-18 ガイドレールの敷設方法及び回転防止治具 WO2020261804A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019-116058 2019-06-24
JP2019116058A JP7372765B2 (ja) 2019-06-24 2019-06-24 ガイドレールの据付方法

Publications (1)

Publication Number Publication Date
WO2020261804A1 true WO2020261804A1 (ja) 2020-12-30

Family

ID=73994755

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/019585 WO2020261804A1 (ja) 2019-06-24 2020-05-18 ガイドレールの敷設方法及び回転防止治具

Country Status (2)

Country Link
JP (1) JP7372765B2 (ja)
WO (1) WO2020261804A1 (ja)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61127583A (ja) * 1984-11-28 1986-06-14 株式会社日立ビルシステムサービス エレベ−タのガイドレ−ル芯出し装置
JPH05178561A (ja) * 1991-12-25 1993-07-20 Toshiba Corp エレベータのガイドレール付設方法
JPH06156926A (ja) * 1992-11-20 1994-06-03 Mitsubishi Electric Corp 油圧エレベーターのガイドレール芯出し方法
JP2003155179A (ja) * 2001-11-20 2003-05-27 Fujitec Co Ltd エレベータの据付工法
WO2017203699A1 (ja) * 2016-05-27 2017-11-30 三菱電機株式会社 ガイドレール支持装置及びガイドレール支持方法
JP2018070362A (ja) * 2016-11-02 2018-05-10 株式会社日立ビルシステム エレベータの据付方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61127583A (ja) * 1984-11-28 1986-06-14 株式会社日立ビルシステムサービス エレベ−タのガイドレ−ル芯出し装置
JPH05178561A (ja) * 1991-12-25 1993-07-20 Toshiba Corp エレベータのガイドレール付設方法
JPH06156926A (ja) * 1992-11-20 1994-06-03 Mitsubishi Electric Corp 油圧エレベーターのガイドレール芯出し方法
JP2003155179A (ja) * 2001-11-20 2003-05-27 Fujitec Co Ltd エレベータの据付工法
WO2017203699A1 (ja) * 2016-05-27 2017-11-30 三菱電機株式会社 ガイドレール支持装置及びガイドレール支持方法
JP2018070362A (ja) * 2016-11-02 2018-05-10 株式会社日立ビルシステム エレベータの据付方法

Also Published As

Publication number Publication date
JP2021001059A (ja) 2021-01-07
JP7372765B2 (ja) 2023-11-01

Similar Documents

Publication Publication Date Title
US7997000B2 (en) Arrangement and method for positioning the alignment plumb lines of the guide rails of an elevator
KR20070037995A (ko) 승강실 및 승강로에 승강실의 지지 수단을 설치하는 방법
CN102216545A (zh) 移动式悬臂平台及其安装方法
JP6167025B2 (ja) 重量物の階段揚重装置及び階段揚重方法
WO2020142001A1 (en) A moveable platform
WO2020261804A1 (ja) ガイドレールの敷設方法及び回転防止治具
KR102294219B1 (ko) 가이드부재를 갖는 자동 거푸집 인양 장치 및 이를 이용한 자동 거푸집 인양 방법
JP2007210703A (ja) マシンルームレスエレベータの巻上機据付装置および据付工法
JP5955280B2 (ja) エレベータ重量物用揚重方法
JP6621732B2 (ja) 作業床装置
EP1647512B1 (en) Working scaffold system of elevator
US20190100419A1 (en) Elevator machine lifting assembly
WO2015159319A1 (ja) エレベータのピット出入り装置
JP5169604B2 (ja) エレベータの据付作業床装置及びその組立方法
JP2008285260A (ja) 機械室レスエレベータのガイドレール据え付け工法
JP2008179469A (ja) エレベータ装置におけるガイドレールの配設方法
JP2017071488A (ja) 重量物の階段揚重装置及び階段揚重方法
JP6382391B1 (ja) エレベーター釣合おもり枠の補強材取付支援装置及びエレベーター釣合おもり枠の補強材取付方法
JP6789836B2 (ja) 重量物運搬装置、及び重量物運搬方法
JP2001335255A (ja) エレベーターの据付工法及びエレベーターの据付用ユニット
JP4978218B2 (ja) エレベータの据付装置及び据付方法
JP3444816B2 (ja) エレベータ主索の交換方法
JP6984795B1 (ja) エレベーター据付用作業床装置及びエレベーター据付用作業床装置の設置方法
JP6525328B2 (ja) エレベータ機器搬出入方法およびエレベータ機器搬出入装置
JP2002356289A (ja) 斜行昇降機の工事用装置および据付工事方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20830767

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20830767

Country of ref document: EP

Kind code of ref document: A1