WO2017206411A1 - 全预制叠合装配式地下综合管廊及其连接节点 - Google Patents

全预制叠合装配式地下综合管廊及其连接节点 Download PDF

Info

Publication number
WO2017206411A1
WO2017206411A1 PCT/CN2016/101680 CN2016101680W WO2017206411A1 WO 2017206411 A1 WO2017206411 A1 WO 2017206411A1 CN 2016101680 W CN2016101680 W CN 2016101680W WO 2017206411 A1 WO2017206411 A1 WO 2017206411A1
Authority
WO
WIPO (PCT)
Prior art keywords
prefabricated
layer
wall
pipe gallery
sandwich
Prior art date
Application number
PCT/CN2016/101680
Other languages
English (en)
French (fr)
Inventor
张剑
Original Assignee
长沙远大住宅工业集团股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 长沙远大住宅工业集团股份有限公司 filed Critical 长沙远大住宅工业集团股份有限公司
Publication of WO2017206411A1 publication Critical patent/WO2017206411A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Definitions

  • the invention belongs to the technical field of municipal engineering, and particularly relates to a full prefabricated superimposed assembled underground integrated pipe gallery and a connecting node thereof.
  • the on-site cast-in-place underground pipe gallery has a wide excavation site to ensure sufficient construction operation space on both sides, so the earthwork excavation volume is large and the backfilling volume is also large; since all work is done on site, the side wall and roof plate
  • the template must be configured, and the roof formwork must be removed after the concrete has reached full strength.
  • the construction period is long and the labor demand is large. All the raw materials are transported to the site in bulk form, polluting the environment, pouring on the concrete site, and requiring high manual vibration. If the vibrating is not true, there will be hidden dangers of water leakage, and the on-site concrete curing conditions are poor, and the possibility of micro-cracks in the concrete is large, and the micro-cracks will seep in the later stage.
  • the traditional prefabricated pipe gallery is made up of a section of prefabricated pipe gallery at the scene. There are many stitching joints. The waterproofing requirements of the joints are high and difficult. Especially for transportation and lifting, it is necessary to transport large vehicles and large lifting equipment. The construction cost is high; since one section of the prefabricated pipe gallery is prefabricated as a whole factory, The mold is complex, can not be produced by the assembly line, the production efficiency is low, and the prefabricated pipe gallery takes up a large space, so the small-vehicle transportation volume is small, which affects the construction speed.
  • the technical problem to be solved by the present invention is to solve the problems of the above background art, and to provide a full prefabricated superimposed assembled underground integrated pipe gallery and its connecting nodes, which are partially prefabricated by the factory, and a part of the on-site superimposed cast-in-place is fully exerted.
  • the factory has good prefabrication quality, high efficiency, good on-site cast-in-place integrity and high structural strength. It overcomes the shortcomings of the two, and changes the backward production conditions of traditional prefabricated pipe gallery with low production efficiency and difficult transportation, realizing no-template construction on site, and environmental protection. , material, high quality, high efficiency, and has excellent waterproof performance.
  • the technical solution adopted by the invention is: a full prefabricated superimposed assembled underground integrated pipe gallery, the bottom plate of which is a prefabricated laminated bottom plate, the side wall or the side wall and the intermediate wall are prefabricated sandwich wall, and the top plate is prefabricated.
  • the top plate, the bottom wall, the side wall or the side wall are connected with the middle wall and the top plate through the cast-in-place to form an integrated underground integrated pipe gallery.
  • the connecting node of the full prefabricated assembled underground integrated pipe gallery comprises a connection structure of the prefabricated sandwich wall and the prefabricated laminated floor, a connection structure of the prefabricated sandwich wall and the prefabricated top plate; the prefabricated sandwich is superposed
  • the wall includes a prefabricated layer on both sides and an intermediate sandwich cast-in-place layer, the prefabricated laminated bottom plate comprising a bottom layer precast layer and a bottom plate cast-in-place layer, the prefabricated top plate comprising a top plate precast layer and a top plate cast-in-place layer; a prefabricated sandwich stack
  • the vertical reinforcement in the prefabricated layer on one side of the wall protrudes from the bottom end of the prefabricated layer, bends and turns into the prefabricated layer on the other side to become the vertical reinforcement, or the vertical reinforcement in the prefabricated layer on both sides of the prefabricated sandwich wall After extending from the bottom end of the prefabricated layer, the joint is bent into a whole, and the bent rebar extending from the bottom end of the prefabricated layer is anchored into the cast-in
  • the vertical reinforcing bars in the prefabricated layer protrude from the top of the prefabricated layer and are bent After turning, it enters the other side of the prefabricated layer to become vertical steel bar, or the vertical reinforcing bars in the prefabricated layer on both sides of the prefabricated sandwich wall are extended from the top of the prefabricated layer and then connected into a bending and turning whole, and the top of the prefabricated layer protrudes.
  • the bent rebar is anchored into the cast-in-place layer of the top plate of the prefabricated superposed roof.
  • the inner side of the bent rotating reinforcing bar is fixedly connected with a plurality of horizontal reinforcing bars.
  • the prefabricated sandwich wall comprises a prefabricated layer on both sides and a sandwich cast-in-place layer in the middle, and a precast layer of the prefabricated sandwich wall is pre-embedded with a steel mesh, and the reinforcing mesh in the prefabricated layer on both sides The piece is fixed by tying it to the truss.
  • the side wall or the side wall and the bottom end of the intermediate wall and the bottom plate are connected with a water-stopping steel plate.
  • the steel cage is installed from top to bottom, and the upper end of the steel cage is anchored into the cast-in-place layer of the prefabricated top plate, and the lower end of the steel cage is anchored into the cast-in-place layer of the prefabricated laminated bottom plate.
  • connection node of the full prefabricated assembled underground integrated pipe gallery further comprises a connection node of the prefabricated laminated bottom plate and the prefabricated laminated bottom plate: the ends of the two adjacent prefabricated laminated bottom plates protrude from the prefabricated layer
  • the reserved reinforcing bars are overlapped with each other and the concrete is fixed by pouring.
  • the construction process of the above-mentioned fully prefabricated superimposed assembled underground integrated pipe gallery includes:
  • the concrete should be covered with a single layer of steel mesh to meet the requirements of the prefabricated layer thickness of the prefabricated sandwich wall, vibrating concrete; curing;
  • the concrete should be covered with a single layer of steel mesh to meet the requirements of the prefabricated layer thickness of the prefabricated sandwich wall, and the first produced prefabricated layer is buckled back to the second poured concrete.
  • the upper end of the prefabricated sandwich wall is made into a structure in which the prefabricated layer is higher than the prefabricated layer on the other side, and the height is adapted to the thickness of the designed underground pipe roof;
  • the upper and lower ends of the prefabricated sandwich wall have vertical reinforcing bars protruding from the prefabricated layers on both sides and bent and turned into integral steel bars;
  • Preparation of prefabricated superimposed roof Binding the single-layer steel mesh to the truss, then placing the single-layer steel mesh into the mold downwards, and pouring concrete.
  • the thickness of the poured concrete should cover the steel mesh and meet the prefabricated layer of the roof. Thickness requirements, concrete vibrating, curing, demoulding;
  • the prefabricated laminated bottom plate in the above step 3) is also produced by referring to the process of this step;
  • the prefabricated layer of the prefabricated superimposed top plate is lifted by a crane and mounted on the prefabricated sandwich wall end and the top plate support; the connection between the top plate and the top plate is reinforced, and the prefabricated sandwich wall is bent from the top of the two prefabricated layers.
  • the rotating integral steel bar is anchored into the cast-in-place layer of the prefabricated laminated top plate, and the connecting steel bar of the top plate connecting the reinforcing bar and the prefabricated sandwiching wall is bundled;
  • the cast-in-place layer of the prefabricated sandwich wall is a sandwich layer before the concrete is poured on site.
  • the invention has outstanding substantive features and remarkable effects:
  • the roof is made of factory prefabricated parts, assembled on site, the foundation pit is not wide, the amount of earthwork is small, and the backfilling volume is small.
  • the underground pipe gallery of the traditional technology is all cast on site, and all the workload is completed on site. Therefore, the side wall and the bottom and the roof are to be configured with templates, and the formwork must be removed after the concrete reaches the strength completely. The amount of the formwork is huge.
  • the labor demand is large and the construction period is long.
  • most of the outer wall and the bottom plate and the lower part of the invention are factory prefabricated parts, assembled on site, no need to configure templates, less on-site workload, small manual demand, short construction period, and construction. Fast and efficient.
  • the underground pipe gallery of traditional technology is cast on site.
  • the side wall, floor and roof are concrete cast and artificially vibrated.
  • the quality is difficult to control. If the vibration is not true, it will leave hidden dangers, plus on-site concrete maintenance. Poor conditions, the possibility of micro-cracks in concrete is greater, and the phenomenon of water seepage through micro-cracks is serious in the later stage.
  • the side wall and the bottom plate and the top plate of the invention are all prefabricated by the factory, the machine is vibrated, the quality is controllable, the production efficiency is high, the micro crack is not formed, and the waterproof performance is good.
  • the mold is complex, can not be pipelined, so the production efficiency is low, and the prefabricated underground pipe gallery is bulky and bulky, difficult to transport, can only be made into a short section of the prefabricated pipe
  • the splicing of the gallery site because the prefabricated pipe gallery is prefabricated as a whole, taking up a lot of space, so the transportation of bicycles is small.
  • the prefabricated pipe gallery is spliced on site, and it is required to be equipped with large hoisting machinery.
  • One section of the prefabricated pipe gallery has many seams, high waterproofing requirements for the splicing joints, difficult handling and poor waterproof performance.
  • the invention only prefabricates the sandwich laminated wall board and the prefabricated laminated board in the factory, and the board and the board can be stacked and transported to the site for convenient transportation, on-site assembly, partially poured concrete, no joint seam, and thus the waterproof performance is guaranteed, and Lifting wall panels, floor panels and roof panels eliminates the need for large lifting machinery operations, saving equipment and construction costs.
  • the invention is a novel underground pipe gallery technical system, which overcomes the shortcomings and deficiencies of the two by prefabricating a part of the factory and superimposing a part of the on-site overlay, thereby overcoming the shortcomings and deficiencies of the two, especially overcoming
  • the traditional prefabricated pipe gallery has low production efficiency and small transportation volume, and can make the site without template construction, environmental protection, energy saving, high efficiency, and excellent waterproof performance. It is an underground comprehensive pipe gallery with international advanced level and invested in China. Operations provide implementation techniques.
  • Figure 1 is a schematic view of the overall structure of the present invention
  • Embodiment 1 is a schematic structural view of Embodiment 1 of a joint node of a prefabricated sandwich stack wall and a prefabricated laminated bottom plate according to the present invention
  • Embodiment 3 is a schematic structural view of Embodiment 2 of a prefabricated sandwich stack wall and a prefabricated laminated bottom plate connecting node according to the present invention
  • Embodiment 4 is a schematic structural view of Embodiment 3 of a prefabricated sandwich stack wall and a prefabricated laminated bottom plate connecting node according to the present invention
  • Figure 5 is a schematic view showing a joint joint node of a prefabricated sandwich stack wall and a prefabricated sandwich wall;
  • Embodiment 1 is a schematic structural view of Embodiment 1 of a prefabricated sandwich stack wall and a prefabricated top plate connecting node according to the present invention
  • Embodiment 7 is a schematic structural view of Embodiment 2 of a prefabricated sandwich stack wall and a prefabricated top plate connecting node according to the present invention
  • FIG. 8 is a schematic structural view of a joint node of a prefabricated laminated bottom plate and a prefabricated laminated bottom plate according to the present invention.
  • the fully prefabricated and assembled underground integrated pipe gallery of the present invention has a bottom plate which is a prefabricated laminated bottom plate, and the side wall or the side wall and the intermediate wall are prefabricated sandwich walls, and the top plate is prefabricated.
  • the top plate, the bottom plate, the side wall or the side wall and the intermediate wall and the top plate are connected by integral casting into an integrated underground integrated pipe gallery.
  • the connecting node of the full prefabricated assembled underground integrated pipe gallery comprises a connection structure of the prefabricated sandwich wall and the prefabricated laminated floor, a connection structure of the prefabricated sandwich wall and the prefabricated top plate; the prefabricated sandwich is superposed
  • the wall includes a prefabricated layer on both sides and an intermediate sandwich cast-in-place layer, the prefabricated laminated bottom plate comprising a bottom layer precast layer and a bottom plate cast-in-place layer, the prefabricated top plate comprising a top plate precast layer and a top plate cast-in-place layer; a prefabricated sandwich stack
  • the vertical reinforcement in the prefabricated layer on one side of the wall protrudes from the bottom end of the prefabricated layer, bends and turns into the prefabricated layer on the other side to become the vertical reinforcement, or the vertical reinforcement in the prefabricated layer on both sides of the prefabricated sandwich wall After extending from the bottom end of the prefabricated layer, the joint is bent into a whole, and the bent rebar extending from the bottom end of the prefabricated layer is anchored into the cast-in
  • the vertical reinforcing bars in the prefabricated layer protrude from the top of the prefabricated layer, bend and turn into the prefabricated layer on the other side to become vertical reinforcing bars, or the vertical reinforcing bars in the prefabricated layers on both sides of the prefabricated sandwich wall extend from the top of the prefabricated layer.
  • the bent rotating steel bar protruding from the top end of the prefabricated layer is anchored into the cast-in-place layer of the top plate of the prefabricated top plate; the inner side of the bent rotating reinforcing bar is fixedly connected with a plurality of horizontal reinforcing bars;
  • the sandwich stacking wall comprises a prefabricated layer on both sides and a sandwich cast-in-place layer in the middle.
  • the prefabricated layer of the prefabricated sandwich wall is pre-embedded with a steel mesh, and the steel mesh in the prefabricated layer on both sides is fixed by binding on the truss.
  • a sealing steel plate is installed at a joint between the side wall or the side wall and the bottom end of the intermediate wall and the prefabricated laminated bottom plate; and the prefabricated sandwich laminated wall is connected with the prefabricated sandwich wall
  • a steel cage is installed in the cast-in-place layer of the two prefabricated sandwich walls. The steel cage is installed from top to bottom, and the upper end of the steel cage is anchored into the cast-in-place layer of the prefabricated top plate, and the lower end of the steel cage is anchored into the cast-in-place layer of the prefabricated laminated bottom plate.
  • the construction process of the above-mentioned fully prefabricated superimposed assembled underground integrated pipe gallery includes:
  • the concrete should be covered with a single layer of steel mesh to meet the requirements of the prefabricated layer thickness of the prefabricated sandwich wall, vibrating concrete; curing;
  • the concrete should be covered with a single layer of steel mesh to meet the requirements of the prefabricated layer thickness of the prefabricated sandwich wall, and the first produced prefabricated layer is buckled back to the second poured concrete.
  • the upper end of the prefabricated sandwich wall is made into a structure in which the prefabricated layer is higher than the prefabricated layer on the other side, and the height is adapted to the thickness of the designed underground pipe roof;
  • the upper and lower ends of the prefabricated sandwich wall have vertical reinforcing bars protruding from the prefabricated layers on both sides and bent and turned into integral steel bars;
  • the single-layer steel mesh is ligated with the truss, and then the single-layer steel mesh is facing down. Positioning in the mold, pouring concrete, the thickness of the poured concrete should cover the steel mesh, and meet the thickness requirements of the prefabricated layer of the roof, concrete vibrating, curing, demoulding;
  • the prefabricated laminated bottom plate in the above step 3) is also produced by referring to the process of this step;
  • the prefabricated layer of the prefabricated superimposed top plate is lifted by a crane and mounted on the prefabricated sandwich wall end and the top plate support; the connection between the top plate and the top plate is reinforced, and the prefabricated sandwich wall is bent from the top of the two prefabricated layers.
  • the rotating integral steel bar is anchored into the cast-in-place layer of the prefabricated laminated top plate, and the connecting steel bar of the top plate connecting the reinforcing bar and the prefabricated sandwiching wall is bundled;
  • the cast-in-place layer of the prefabricated sandwich wall is a sandwich layer before the concrete is poured on site.

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种全预制叠合装配式地下综合管廊及其连接节点,其地下综合管廊底板为预制叠合底板(5),其侧墙或侧墙与中间墙体为预制夹心叠合墙(3),其顶板为预制叠合板(4),底板、侧墙或侧墙与中间墙体、顶板三者通过现浇连接成整体地下综合管廊。通过工厂预制一部分,现场叠合现浇一部分,克服了传统预制管廊生产效率低、运输量小的缺点,实现现场无模板化施工,环保、节材、优质、高效,并具有优良的防水性能。

Description

全预制叠合装配式地下综合管廊及其连接节点 技术领域:
本发明属于市政工程技术领域,具体涉及一种全预制叠合装配式地下综合管廊及其连接节点。
背景技术:
国务院办公厅关于推进城市地下综合管廊建设的指导意见(国办发〔2015〕61号)于2015年8月10日公布。工作目标是到2020年,建成一批具有国际先进水平的地下综合管廊并投入运营,反复开挖地面的“马路拉链”问题明显改善,管线安全水平和防灾抗灾能力明显提升,逐步消除主要街道蜘蛛网式架空线,城市地面景观明显好转。全国各省市的地下综合管廊建设一时之间成为热点。传统的地下管廊建设有两种方式:一、现场现浇,二、工厂预制。
现场现浇地下管廊现场开挖较宽,以保证两侧留有足够的施工操作空间,因此土方开挖量大,回填量也较大;由于所有工作均在现场完成,所以侧墙及顶板均要配置模板,且顶板模板必须要在混凝土完全达到强度后才能拆除,施工周期长,人工需求量大,所有原材料均以散装形式运到现场,污染环境,混凝土现场浇注,人工振捣要求高,如果振捣不实,会留下漏水隐患,而且现场混凝土养护条件差,混凝土出现微裂纹的可能性较大,后期会通过微裂纹渗水。
传统预制管廊由一节一节预制管廊在现场拼接而成,拼接缝较多,拼接缝处的防水要求高,难度大,特别是运输吊装困难,需要大型运输车辆和大型吊装设备,施工成本高;由于一节一节预制管廊是整体工厂预制, 模具复杂,不能流水线生产,制作效率低,而且预制管廊占用空间大,所以单车次运输量小,影响建设速度。
发明内容:
本发明所要解决的技术问题是:解决上述背景技术存在的问题,而提供一种全预制叠合装配式地下综合管廊及其连接节点,通过工厂预制一部分,现场叠合现浇一部分,充分发挥工厂预制质量好、效率高和现场现浇整体性好、结构强度高的优势,克服两者的缺点,改变传统预制管廊生产效率低、运输困难的落后状况,实现现场无模板化施工,环保、节材、优质、高效,并具有优良的防水性能。
本发明采用的技术方案是:一种全预制叠合装配式地下综合管廊,其底板为预制叠合底板,其侧墙或侧墙与中间墙体为预制夹心叠合墙,其顶板为预制叠合顶板,底板、侧墙或侧墙与中间墙体、顶板三者通过现浇连接成整体地下综合管廊。
上述全预制叠合装配式地下综合管廊的连接节点,包括预制夹心叠合墙与预制叠合底板的连接结构、预制夹心叠合墙与预制叠合顶板的连接结构;所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层,所述预制叠合底板包括底板预制层和底板现浇层,所述预制叠合顶板包括顶板预制层和顶板现浇层;预制夹心叠合墙一侧预制层内的竖向钢筋从预制层底端伸出,弯折回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层底端伸出后连接成弯折回转整体,上述预制层底端伸出的弯折回转钢筋锚入预制叠合底板的底板现浇层内;同理,预制夹心叠合墙一侧预制层内的竖向钢筋从预制层顶端伸出,弯折 回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层顶端伸出后连接成弯折回转整体,上述预制层顶端伸出的弯折回转钢筋锚入预制叠合顶板的顶板现浇层内。
上述技术方案中,所述的弯折回转钢筋内侧与多根水平钢筋连接固定。
上述技术方案中,所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层,预制夹心叠合墙的预制层内预埋有钢筋网片,两侧的预制层内钢筋网片通过绑扎在桁架上连接固定。
上述技术方案中,所述的侧墙或侧墙与中间墙体的底端与底板的连接处安装有止水钢板。
上述技术方案中,所述的预制夹心叠合墙与预制夹心叠合墙连接的拼缝节点处,跨接两预制夹心叠合墙的夹心现浇层内安装有钢筋笼。
上述技术方案中,所述的钢筋笼从上至下安装,钢筋笼上端锚入预制叠合顶板的现浇层内,钢筋笼下端锚入预制叠合底板的现浇层内。
上述技术方案中,所述全预制叠合装配式地下综合管廊的连接节点还包括预制叠合底板与预制叠合底板的连接节点:两相邻预制叠合底板端头从预制层内伸出的预留钢筋互相搭接,浇注混凝土连接固定。
上述全预制叠合装配式地下综合管廊的施工工艺,包括:
1)开挖地下管廊;
按略宽于地下管廊宽度开挖地下管廊基坑,并在地下管廊基坑两侧做好护壁;
2)在地下管廊基坑上铺好垫层;
3)用吊车吊起预制叠合底板安装在上述垫层上;
4)预制夹心叠合墙的制备:
a将底层的单层钢筋网片与桁架绑扎,然后单层钢筋网朝下放入模具内定位;
b在模具内浇注混凝土,混凝土应覆盖单层钢筋网片,满足设计的预制夹心叠合墙预制层厚度要求,振捣混凝土;养护;
c养护后,在桁架上面绑扎上层的单层钢筋网片;
d用专用设备吊起上述预制夹心叠合墙的一层预制层及桁架,脱模,并整体翻转;
e第二次在模具内浇注混凝土,同样混凝土应覆盖单层钢筋网片,满足预制夹心叠合墙的预制层厚度要求,将第一次生产好的预制层反扣在第二次浇注的混凝土上;振捣混凝土;养护;
f整体脱模,制成预制夹心叠合墙板;
g预制夹心叠合墙的上端制成一边预制层高出另一边预制层的结构,高出的尺寸与设计的地下管廊顶板厚度相适应;
h预制夹心叠合墙的上下两端都有竖向钢筋从两侧预制层内伸出并弯折回转成整体钢筋;
4)预制叠合顶板的制备:将单层钢筋网片与桁架绑扎,然后单层钢筋网片朝下放入模具内定位,浇注混凝土,浇注混凝土厚度应覆盖钢筋网片,并满足顶板预制层厚度要求,混凝土振捣,养护,脱模;
上述步骤3)中的预制叠合底板也参照本步骤工艺制作;
5)用吊车吊起预制夹心叠合墙,安装在地下管廊预制叠合底板上,并使预制夹心叠合墙从底端两预制层伸出的弯折回转整体钢筋锚入预制叠合 底板现浇层中;
6)架设顶板支撑;
7)用吊车吊起预制叠合顶板的预制层安装在预制夹心叠合墙上端和顶板支撑上;顶板与顶板的连接钢筋绑扎,预制夹心叠合墙的从两预制层顶端伸出的弯折回转整体钢筋锚入预制叠合顶板的现浇层中,顶板连接钢筋与预制夹心叠合墙的连接钢筋绑扎;
8)顶板的现浇部分和预制夹心叠合墙的夹心部分浇注混凝土,振捣;养护;
9)做好防水工程;
10)土方回填。
上述技术方案中,所述的预制夹心叠合墙的现浇层在现场浇注混凝土前为夹心层。
本发明与传统技术相比,具有突出的实质性特点和显著效果:
一、由于传统技术的地下管廊全部现场浇注,因此两侧需要留出足够施工操作空间,基坑开挖较宽,土方开挖量大,回填量也大;而本发明的侧墙和底板、顶板都为工厂预制件,现场装配,基坑开挖不宽,土方量小,回填量小。
二、传统技术的地下管廊全部现场浇注,所有工作量都在现场完成,所以浇注侧墙及底部、顶板均要配置模板,且模板必须要在混凝土完全达到强度后才能拆除,模板量巨大,人工需求量大,施工周期长,而本发明的外墙大部和底板、顶板下部都为工厂预制件,现场装配,无需配置模板,现场工作量少,人工需求量小,施工周期短,建设速度快,效率高。
三、传统技术的地下管廊全部现场浇注,侧墙、底板和顶板均是混凝土现场浇注、人工振捣,质量难以控制,如果振捣不实,就会留下漏水隐患,加上现场混凝土养护条件差,混凝土出现微裂纹的可能性较大,后期通过微裂纹渗水现象严重。而本发明的侧墙和底板、顶板大部都是工厂预制,机器振捣,质量可控,生产效率高,无微裂纹,防水性能好。
四、由于传统技术的工厂预制地下管廊,模具复杂,不能流水线作业,所以生产效率低,而且预制地下管廊体积庞大笨重,运输困难,只能制成很短的一节一节的预制管廊现场拼接,因为预制管廊整体预制,占用空间大,所以单车次的运输小。而这一节一节的预制管廊现场拼接,需配备大型吊装机械作业,一节一节预制管廊拼接缝多,对拼接缝的防水要求高,处理难度大,防水性能差。本发明只在工厂预制夹心叠合墙板和预制叠合板,板与板之间可叠放运输到现场,方便运输,现场组装,部分浇注混凝土,无拼接缝,因而防水性能有保障,而吊装墙板、底板和顶板,无需大型吊装机械作业,节约设备和施工成本。
本发明是一种新型的地下管廊技术体系,通过工厂预制一部分、现场叠合现浇一部分,充分发挥工厂预制和现场浇注两者的优势,克服两者的缺点和不足,特别是既克服了传统预制管廊生产效率低和运输量小的不足,又能让现场无模板化施工,环保节能,效率高,并具有优良的防水性能,为我国建设具有国际先进水平的地下综合管廊并投入运营提供了实施技术。
附图说明:
图1为本发明整体结构示意图;
图2为本发明预制夹心叠合墙与预制叠合底板连接节点实施例1结构示意图;
图3为本发明预制夹心叠合墙与预制叠合底板连接节点实施例2结构示意图;
图4为本发明预制夹心叠合墙与预制叠合底板连接节点实施例3结构示意图;
图5为本发明预制夹心叠合墙与预制夹心叠合墙连接拼缝节点示意图;
图6为本发明预制夹心叠合墙与预制叠合顶板连接节点实施例1结构示意图;
图7为本发明预制夹心叠合墙与预制叠合顶板连接节点实施例2结构示意图;
图8为本发明预制叠合底板与预制叠合底板连接节点结构示意图。
附图标注说明:
1—顶板现浇层,2—顶板预制层,3—预制夹心叠合墙,4—预制叠合顶板,
5—预制叠合底板,6—钢筋笼,7—连接节点,8—单层钢筋网片,9—桁架,10—预制夹心叠合墙的预制层,11—预制夹心叠合墙的现浇层,12—预制叠合底板的预制层,13—预制叠合底板的现浇层,14—预留钢筋,14—止水钢板,15—预埋钢筋,16—雨水箱涵,17—预留钢筋。
具体实施方式:
参见附图,本发明的全预制叠合装配式地下综合管廊,其底板为预制叠合底板,其侧墙或侧墙与中间墙体为预制夹心叠合墙,其顶板为预制叠 合顶板,底板、侧墙或侧墙与中间墙体、顶板三者通过现浇连接成整体地下综合管廊。
上述全预制叠合装配式地下综合管廊的连接节点,包括预制夹心叠合墙与预制叠合底板的连接结构、预制夹心叠合墙与预制叠合顶板的连接结构;所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层,所述预制叠合底板包括底板预制层和底板现浇层,所述预制叠合顶板包括顶板预制层和顶板现浇层;预制夹心叠合墙一侧预制层内的竖向钢筋从预制层底端伸出,弯折回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层底端伸出后连接成弯折回转整体,上述预制层底端伸出的弯折回转钢筋锚入预制叠合底板的底板现浇层内;同理,预制夹心叠合墙一侧预制层内的竖向钢筋从预制层顶端伸出,弯折回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层顶端伸出后连接成弯折回转整体,上述预制层顶端伸出的弯折回转钢筋锚入预制叠合顶板的顶板现浇层内;所述的弯折回转钢筋内侧与多根水平钢筋连接固定;所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层,预制夹心叠合墙的预制层内预埋有钢筋网片,两侧的预制层内钢筋网片通过绑扎在桁架上连接固定;所述的侧墙或侧墙与中间墙体的底端与预制叠合底板的连接处安装有止水钢板;所述的预制夹心叠合墙与预制夹心叠合墙连接的拼缝节点中,跨接两预制夹心叠合墙的夹心现浇层内安装有钢筋笼。所述的钢筋笼从上至下安装,钢筋笼上端锚入预制叠合顶板的现浇层内,钢筋笼下端锚入预制叠合底板的现浇层内。
上述全预制叠合装配式地下综合管廊的施工工艺,包括:
1)开挖地下管廊;
按略宽于地下管廊宽度开挖地下管廊基坑,并在地下管廊基坑两侧做好护壁;
2)在地下管廊基坑上铺好垫层;
3)用吊车吊起预制叠合底板安装在上述垫层上;
4)预制夹心叠合墙的制备:
a将底层的单层钢筋网片与桁架绑扎,然后单层钢筋网朝下、桁架在上放入模具内定位;
b在模具内浇注混凝土,混凝土应覆盖单层钢筋网片,满足设计的预制夹心叠合墙预制层厚度要求,振捣混凝土;养护;
c养护后,在桁架上面绑扎上层的单层钢筋网片;
d用专用设备吊起上述预制夹心叠合墙的一层预制层及桁架,脱模,并整体翻转;
e第二次在模具内浇注混凝土,同样混凝土应覆盖单层钢筋网片,满足预制夹心叠合墙的预制层厚度要求,将第一次生产好的预制层反扣在第二次浇注的混凝土上;振捣混凝土;养护;
f整体脱模,制成预制夹心叠合墙板;
g预制夹心叠合墙的上端制成一边预制层高出另一边预制层的结构,高出的尺寸与设计的地下管廊顶板厚度相适应;
h预制夹心叠合墙的上下两端都有竖向钢筋从两侧预制层内伸出并弯折回转成整体钢筋;
4)顶板的制备:将单层钢筋网片与桁架绑扎,然后单层钢筋网片朝下 放入模具内定位,浇注混凝土,浇注混凝土厚度应覆盖钢筋网片,并满足顶板预制层厚度要求,混凝土振捣,养护,脱模;
上述步骤3)中的预制叠合底板也参照本步骤工艺制作;
5)用吊车吊起预制夹心叠合墙,安装在地下管廊预制叠合底板上,并使预制夹心叠合墙两预制层底端伸出的弯折回转整体钢筋锚入预制叠合底板现浇层中;
6)架设顶板支撑;
7)用吊车吊起预制叠合顶板的预制层安装在预制夹心叠合墙上端和顶板支撑上;顶板与顶板的连接钢筋绑扎,预制夹心叠合墙的从两预制层顶端伸出的弯折回转整体钢筋锚入预制叠合顶板的现浇层中,顶板连接钢筋与预制夹心叠合墙的连接钢筋绑扎;
8)顶板的现浇部分和预制夹心叠合墙的夹心部分浇注混凝土,振捣;养护;
9)做好防水工程;
10)土方回填。
所述的预制夹心叠合墙的现浇层在现场浇注混凝土前为夹心层。

Claims (7)

  1. 一种全预制叠合装配式地下综合管廊,其特征在于:其底板为预制叠合底板,其侧墙或侧墙与中间墙体为预制夹心叠合墙,其顶板为预制叠合顶板,底板、侧墙或侧墙与中间墙体、顶板三者通过现浇连接成整体地下综合管廊。
  2. 一种全预制叠合装配式地下综合管廊的连接节点,其特征在于:包括预制夹心叠合墙与预制叠合底板的连接结构、预制夹心叠合墙与预制叠合顶板的连接结构;所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层,所述预制叠合底板包括底板预制层和底板现浇层,所述预制叠合顶板包括顶板预制层和顶板现浇层;预制夹心叠合墙一侧预制层内的竖向钢筋从预制层底端伸出,弯折回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层底端伸出后连接成弯折回转整体,上述预制层底端伸出的弯折回转钢筋锚入预制叠合底板的底板现浇层内;同理,预制夹心叠合墙一侧预制层内的竖向钢筋从预制层顶端伸出,弯折回转后进入另一侧预制层内成为竖向钢筋,或者预制夹心叠合墙两侧预制层内的竖向钢筋从预制层顶端伸出后连接成弯折回转整体,上述预制层顶端伸出的弯折回转钢筋锚入预制叠合顶板的顶板现浇层内。
  3. 根据权利要求2所述的全预制叠合装配式地下综合管廊的连接节点,其特征在于:所述的弯折回转钢筋内侧与多根水平钢筋连接固定。
  4. 根据权利要求2所述的全预制叠合装配式地下综合管廊的连接节点,其特征在于:所述预制夹心叠合墙包括两侧的预制层和中间的夹心现浇层, 预制夹心叠合墙的预制层内预埋有钢筋网片,两侧的预制层内钢筋网片通过绑扎在桁架上连接固定。
  5. 根据权利要求2所述的全预制叠合装配式地下综合管廊的连接节点,其特征在于:所述的侧墙或侧墙与中间墙体的底端与预制叠合底板的连接处安装有止水钢板。
  6. 根据权利要求2所述的全预制叠合装配式地下综合管廊的连接节点,其特征在于:所述的预制夹心叠合墙与预制夹心叠合墙连接的拼缝节点处,跨接两预制夹心叠合墙的夹心现浇层内安装有钢筋笼;所述的钢筋笼从上至下安装,钢筋笼上端锚入预制叠合顶板的现浇层内,钢筋笼下端锚入预制叠合底板的现浇层内。
  7. 根据权利要求2所述的全预制叠合装配式地下综合管廊的连接节点,其特征在于:所述全预制叠合装配式地下综合管廊的连接节点还包括预制叠合底板与预制叠合底板的连接节点:两相邻预制叠合底板端头从预制层内伸出的预留钢筋互相搭接,浇注混凝土连接固定。
PCT/CN2016/101680 2016-06-03 2016-10-10 全预制叠合装配式地下综合管廊及其连接节点 WO2017206411A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610385639.5A CN105839666A (zh) 2016-06-03 2016-06-03 全预制叠合装配式地下综合管廊及其连接节点
CN201610385639.5 2016-06-03

Publications (1)

Publication Number Publication Date
WO2017206411A1 true WO2017206411A1 (zh) 2017-12-07

Family

ID=56596102

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2016/101680 WO2017206411A1 (zh) 2016-06-03 2016-10-10 全预制叠合装配式地下综合管廊及其连接节点

Country Status (2)

Country Link
CN (1) CN105839666A (zh)
WO (1) WO2017206411A1 (zh)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457404A (zh) * 2018-03-30 2018-08-28 中冶建工集团有限公司 叠合墙体的错扣式单片预制墙板
CN108661237A (zh) * 2018-07-13 2018-10-16 中国建筑标准设计研究院有限公司 适用于多层装配式建筑的预制墙板及其施工方法
CN108677963A (zh) * 2018-05-23 2018-10-19 中铁第四勘察设计院集团有限公司 一种用于基坑工程的钢支撑留撑接头结构及其施工方法
CN109024684A (zh) * 2018-09-06 2018-12-18 贵州省绿筑科建住宅产业化发展有限公司 一种两段装配式地下人行通道及其施工方法
CN109295849A (zh) * 2018-10-31 2019-02-01 福州大学 一种带有锚固板的空心板铰缝构造及其施工方法
CN109339105A (zh) * 2018-12-10 2019-02-15 三江学院 一种方拱形管廊安装支座及管廊系统和管廊系统安装方法
CN110080285A (zh) * 2019-04-23 2019-08-02 中铁第四勘察设计院集团有限公司 一种地下结构预制侧墙定位连接结构及连接方法
CN110685382A (zh) * 2019-11-06 2020-01-14 宝业集团股份有限公司 现浇暗柱与预制构件连接结构及施工方法
CN111027128A (zh) * 2019-12-27 2020-04-17 三一筑工科技有限公司 一种确定叠合梁端头参数的方法、装置及计算设备
CN112761182A (zh) * 2021-01-19 2021-05-07 沈阳建筑大学 一种注浆节点的装配式综合管廊
CN113026807A (zh) * 2021-03-23 2021-06-25 中铁第四勘察设计院集团有限公司 预制侧墙中板节点板及装配式地下车站
CN113136942A (zh) * 2021-03-30 2021-07-20 中国建筑第八工程局有限公司 免灌浆装配式墙体及其施工方法
CN113152762A (zh) * 2021-04-06 2021-07-23 江苏华源建筑设计研究院股份有限公司 一种装配式建筑叠合板与现浇板的连接结构及其施工工艺
CN113374071A (zh) * 2021-07-28 2021-09-10 朱彦达 软土地区地下室建造方法
CN113898007A (zh) * 2021-09-02 2022-01-07 中建一局集团建设发展有限公司 一种沿街大跨度连廊结构半逆作施工方法
CN114215248A (zh) * 2021-12-21 2022-03-22 南京长江都市建筑设计股份有限公司 单向叠合板成型方法、成型模具及单向叠合板
CN114575385A (zh) * 2022-03-25 2022-06-03 四川仟坤建设集团有限责任公司 市政综合管廊及其施工方法
CN114809074A (zh) * 2022-04-20 2022-07-29 浙江交工金筑交通建设有限公司 现浇底板卧式预制装配式箱型通道施工方法
CN114960620A (zh) * 2021-02-26 2022-08-30 中能(厦门)智慧科技有限公司 一种地下连续空腹墙的施工方法
CN115142466A (zh) * 2022-06-17 2022-10-04 中国建筑第八工程局有限公司 一种地连墙钢筋与内衬墙钢筋立体转换装置及其施工方法
CN115354861A (zh) * 2022-08-24 2022-11-18 中铁十六局集团北京轨道交通工程建设有限公司 一种墙板钢筋互锚施工方法及墙板结构
CN115387382A (zh) * 2022-08-26 2022-11-25 中国建筑第二工程局有限公司 综合管廊下出线节点施工方法
CN116770891A (zh) * 2023-06-26 2023-09-19 中国水利水电第三工程局有限公司 一种骨料堆存场地下全断面预制廊道施工方法

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839666A (zh) * 2016-06-03 2016-08-10 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊及其连接节点
CN105862916A (zh) * 2016-06-03 2016-08-17 长沙远大住宅工业集团股份有限公司 叠合装配式地下管廊体系及施工制作工艺
CN106193127A (zh) * 2016-08-31 2016-12-07 长沙远大住宅工业集团股份有限公司 叠合夹心墙侧墙与现浇底板的连接节点
CN106193337A (zh) * 2016-08-31 2016-12-07 长沙远大住宅工业集团股份有限公司 叠合夹心墙侧墙与预制底板的连接节点
CN106193116B (zh) * 2016-08-31 2019-02-19 长沙远大住宅工业集团股份有限公司 叠合装配式地下管廊墙板定位装置
CN106592630B (zh) * 2016-12-30 2019-02-26 中铁第四勘察设计院集团有限公司 现浇与预制相结合的综合管廊结构及其施工方法
CN106703077B (zh) * 2017-01-17 2020-02-07 深圳市路桥建设集团有限公司 预制装配整体式地下综合管廊结构
CN106677210B (zh) * 2017-01-25 2019-09-06 中冶建工集团有限公司 一种地下综合管廊结构
CN106703078A (zh) * 2017-01-25 2017-05-24 中冶建工集团有限公司 一种叠合装配式地下综合管廊
CN106836280A (zh) * 2017-02-08 2017-06-13 大连三川建筑科技有限公司 一种装配整体式综合管廊、排水沟渠或洪沟渠
CN106638671A (zh) * 2017-02-08 2017-05-10 大连三川建筑科技有限公司 一种高低舱装配整体式综合管廊或排水沟渠
CN108661080A (zh) * 2017-04-01 2018-10-16 周兆弟 装配式地下一体走廊的制造方法
CN106894445B (zh) * 2017-04-11 2018-04-06 吉林森煌建筑材料集团有限公司 一种装配叠合式综合管廊及其建造方法
CN106930391B (zh) * 2017-04-22 2023-01-24 郑州市市政工程总公司 无模施工顶板现浇排水渠结构及施工方法
CN107142962A (zh) * 2017-06-07 2017-09-08 扬州工业职业技术学院 一种综合管廊及其施工方法
CN107905801B (zh) * 2017-12-19 2023-05-12 中冶京诚工程技术有限公司 盾构管廊系统及其施工方法
CN108301441A (zh) * 2018-04-20 2018-07-20 长春工程学院 一种装配式预制地下综合管廊箱涵
CN108797638A (zh) * 2018-06-01 2018-11-13 中国建筑股份有限公司 基于复合底板的一体化装配式管廊及其施工方法
CN111088816A (zh) * 2020-01-06 2020-05-01 山西省工业设备安装集团有限公司 一种叠合装配式综合管廊的结构
CN111851328B (zh) * 2020-07-06 2021-08-27 海门市帕源路桥建设有限公司 箱涵类砼结构钢筋模块化、标准化预制、拼装施工工艺
CN114232674A (zh) * 2021-12-22 2022-03-25 北京工业大学 组合壳管廊顶部t型节点及其施工方法
CN115182382A (zh) * 2022-07-26 2022-10-14 中铁建(无锡)工程科技发展有限公司 一种装配式地铁站底板与侧墙的连接节点以及施工工艺

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (ja) * 2003-01-30 2004-08-19 Taisei Corp 半プレキャスト式アーチカルバートの構造及びその施工方法
JP2006097429A (ja) * 2004-09-30 2006-04-13 Cti Engineering Co Ltd 構造物
CN104196054A (zh) * 2014-07-25 2014-12-10 南京长江都市建筑设计股份有限公司 一种地下室双层叠合预制外墙
CN104805866A (zh) * 2015-04-30 2015-07-29 黑龙江宇辉新型建筑材料有限公司 预制的综合管廊及施工方法
CN205276316U (zh) * 2015-12-28 2016-06-01 南京明麓建筑工程有限公司 组合式预制管廊
CN105839666A (zh) * 2016-06-03 2016-08-10 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊及其连接节点
CN105839667A (zh) * 2016-06-03 2016-08-10 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊的施工制作工艺

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105178357B (zh) * 2015-07-16 2017-01-11 中国建筑股份有限公司 一种基坑明挖条件下预制装配式地下结构及其施工方法
CN105019475B (zh) * 2015-08-06 2018-05-04 湖北宇辉新型建筑材料有限公司 预制装配整体式混凝土综合管廊及施工工法
CN205742265U (zh) * 2016-06-03 2016-11-30 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊及其连接节点

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (ja) * 2003-01-30 2004-08-19 Taisei Corp 半プレキャスト式アーチカルバートの構造及びその施工方法
JP2006097429A (ja) * 2004-09-30 2006-04-13 Cti Engineering Co Ltd 構造物
CN104196054A (zh) * 2014-07-25 2014-12-10 南京长江都市建筑设计股份有限公司 一种地下室双层叠合预制外墙
CN104805866A (zh) * 2015-04-30 2015-07-29 黑龙江宇辉新型建筑材料有限公司 预制的综合管廊及施工方法
CN205276316U (zh) * 2015-12-28 2016-06-01 南京明麓建筑工程有限公司 组合式预制管廊
CN105839666A (zh) * 2016-06-03 2016-08-10 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊及其连接节点
CN105839667A (zh) * 2016-06-03 2016-08-10 长沙远大住宅工业集团股份有限公司 全预制叠合装配式地下综合管廊的施工制作工艺

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457404A (zh) * 2018-03-30 2018-08-28 中冶建工集团有限公司 叠合墙体的错扣式单片预制墙板
CN108457404B (zh) * 2018-03-30 2024-01-30 中冶建工集团有限公司 叠合墙体的错扣式单片预制墙板
CN108677963A (zh) * 2018-05-23 2018-10-19 中铁第四勘察设计院集团有限公司 一种用于基坑工程的钢支撑留撑接头结构及其施工方法
CN108661237A (zh) * 2018-07-13 2018-10-16 中国建筑标准设计研究院有限公司 适用于多层装配式建筑的预制墙板及其施工方法
CN108661237B (zh) * 2018-07-13 2023-11-21 中国建筑标准设计研究院有限公司 适用于多层装配式建筑的预制墙板及其施工方法
CN109024684A (zh) * 2018-09-06 2018-12-18 贵州省绿筑科建住宅产业化发展有限公司 一种两段装配式地下人行通道及其施工方法
CN109295849A (zh) * 2018-10-31 2019-02-01 福州大学 一种带有锚固板的空心板铰缝构造及其施工方法
CN109339105A (zh) * 2018-12-10 2019-02-15 三江学院 一种方拱形管廊安装支座及管廊系统和管廊系统安装方法
CN110080285A (zh) * 2019-04-23 2019-08-02 中铁第四勘察设计院集团有限公司 一种地下结构预制侧墙定位连接结构及连接方法
CN110685382A (zh) * 2019-11-06 2020-01-14 宝业集团股份有限公司 现浇暗柱与预制构件连接结构及施工方法
CN111027128A (zh) * 2019-12-27 2020-04-17 三一筑工科技有限公司 一种确定叠合梁端头参数的方法、装置及计算设备
CN112761182A (zh) * 2021-01-19 2021-05-07 沈阳建筑大学 一种注浆节点的装配式综合管廊
CN114960620A (zh) * 2021-02-26 2022-08-30 中能(厦门)智慧科技有限公司 一种地下连续空腹墙的施工方法
CN113026807A (zh) * 2021-03-23 2021-06-25 中铁第四勘察设计院集团有限公司 预制侧墙中板节点板及装配式地下车站
CN113136942A (zh) * 2021-03-30 2021-07-20 中国建筑第八工程局有限公司 免灌浆装配式墙体及其施工方法
CN113136942B (zh) * 2021-03-30 2023-02-28 中国建筑第八工程局有限公司 免灌浆装配式墙体及其施工方法
CN113152762A (zh) * 2021-04-06 2021-07-23 江苏华源建筑设计研究院股份有限公司 一种装配式建筑叠合板与现浇板的连接结构及其施工工艺
CN113374071A (zh) * 2021-07-28 2021-09-10 朱彦达 软土地区地下室建造方法
CN113898007A (zh) * 2021-09-02 2022-01-07 中建一局集团建设发展有限公司 一种沿街大跨度连廊结构半逆作施工方法
CN113898007B (zh) * 2021-09-02 2022-09-27 中建一局集团建设发展有限公司 一种沿街大跨度连廊结构半逆作施工方法
CN114215248A (zh) * 2021-12-21 2022-03-22 南京长江都市建筑设计股份有限公司 单向叠合板成型方法、成型模具及单向叠合板
CN114575385B (zh) * 2022-03-25 2023-10-31 四川仟坤建设集团有限责任公司 市政综合管廊及其施工方法
CN114575385A (zh) * 2022-03-25 2022-06-03 四川仟坤建设集团有限责任公司 市政综合管廊及其施工方法
CN114809074A (zh) * 2022-04-20 2022-07-29 浙江交工金筑交通建设有限公司 现浇底板卧式预制装配式箱型通道施工方法
CN115142466A (zh) * 2022-06-17 2022-10-04 中国建筑第八工程局有限公司 一种地连墙钢筋与内衬墙钢筋立体转换装置及其施工方法
CN115142466B (zh) * 2022-06-17 2024-04-26 中国建筑第八工程局有限公司 一种地连墙钢筋与内衬墙钢筋立体转换装置及其施工方法
CN115354861A (zh) * 2022-08-24 2022-11-18 中铁十六局集团北京轨道交通工程建设有限公司 一种墙板钢筋互锚施工方法及墙板结构
CN115354861B (zh) * 2022-08-24 2024-03-22 中铁十六局集团北京轨道交通工程建设有限公司 一种墙板钢筋互锚施工方法及墙板结构
CN115387382A (zh) * 2022-08-26 2022-11-25 中国建筑第二工程局有限公司 综合管廊下出线节点施工方法
CN115387382B (zh) * 2022-08-26 2024-03-26 中国建筑第二工程局有限公司 综合管廊下出线节点施工方法
CN116770891A (zh) * 2023-06-26 2023-09-19 中国水利水电第三工程局有限公司 一种骨料堆存场地下全断面预制廊道施工方法

Also Published As

Publication number Publication date
CN105839666A (zh) 2016-08-10

Similar Documents

Publication Publication Date Title
WO2017206411A1 (zh) 全预制叠合装配式地下综合管廊及其连接节点
WO2017206412A1 (zh) 叠合装配式地下管廊体系及施工制作工艺
CN105839667B (zh) 全预制叠合装配式地下综合管廊的施工制作工艺
CN105178357B (zh) 一种基坑明挖条件下预制装配式地下结构及其施工方法
CN104805866B (zh) 预制的综合管廊及施工方法
CN109235499B (zh) 一种明挖地下建筑结构装配式施工方法
CN105781125B (zh) 一种装配式建筑的安装方法
CN102168455B (zh) 装配剪力墙结构水平缝u型闭合筋连接构造
CN205662947U (zh) 叠合装配式地下管廊体系
CN106968381B (zh) 用组合式灌浆套筒连接的装配式预制剪力墙与叠合板节点
CN106854873A (zh) 一种预制拼接的沉井式停车库的工程方法及停车库
WO2018028041A1 (zh) 无梁楼盖体系与梁柱体系结合的叠合装配整体式地下室
CN203924471U (zh) 预制混凝土外墙板
CN205894281U (zh) 一种无梁楼盖体系的叠合装配整体式地下室
CN205742265U (zh) 全预制叠合装配式地下综合管廊及其连接节点
CN106245753A (zh) 一种装配式预制结构墙板的钢筋混凝土连接体系
WO2018028042A1 (zh) 一种无梁楼盖体系的叠合装配整体式地下室
WO2018028040A1 (zh) 一种楼盖梁柱体系的叠合装配整体式地下室
CN204753627U (zh) 预制的综合管廊
CN110409492A (zh) 一种含叠合构件多结构组合装配式管廊及其施工方法
CN110158645A (zh) 预制构件混合连接拼装混凝土综合管廊
WO2018028043A1 (zh) 梁柱体系与无梁楼盖体系结合的叠合装配整体式地下室
CN109853625B (zh) 混合方式连接装配整体式混凝土综合管廊
CN113833162B (zh) 一种高预制率低成本剪力墙结构体系及施工方法
CN205894280U (zh) 一种空心楼盖梁柱体系的叠合装配整体式地下室

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16903793

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 16903793

Country of ref document: EP

Kind code of ref document: A1