WO2013088798A1 - 電力供給システム - Google Patents

電力供給システム Download PDF

Info

Publication number
WO2013088798A1
WO2013088798A1 PCT/JP2012/072842 JP2012072842W WO2013088798A1 WO 2013088798 A1 WO2013088798 A1 WO 2013088798A1 JP 2012072842 W JP2012072842 W JP 2012072842W WO 2013088798 A1 WO2013088798 A1 WO 2013088798A1
Authority
WO
WIPO (PCT)
Prior art keywords
power
conversion device
power conversion
interconnection
load
Prior art date
Application number
PCT/JP2012/072842
Other languages
English (en)
French (fr)
Inventor
小新 博昭
田村 秀樹
Original Assignee
パナソニック株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by パナソニック株式会社 filed Critical パナソニック株式会社
Priority to EP12858275.6A priority Critical patent/EP2793345B1/en
Priority to ES12858275.6T priority patent/ES2612653T3/es
Publication of WO2013088798A1 publication Critical patent/WO2013088798A1/ja

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/34Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
    • H02J7/35Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/062Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for AC powered loads
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/22The renewable source being solar energy
    • H02J2300/24The renewable source being solar energy of photovoltaic origin
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/30The power source being a fuel cell
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • H02J2310/12The local stationary network supplying a household or a building
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/388Islanding, i.e. disconnection of local power supply from the network
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/70Hybrid systems, e.g. uninterruptible or back-up power supplies integrating renewable energies
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/10Applications of fuel cells in buildings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E70/00Other energy conversion or management systems reducing GHG emissions
    • Y02E70/30Systems combining energy storage with energy generation of non-fossil origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/248UPS systems or standby or emergency generators

Definitions

  • the present invention relates to a power supply system that supplies power from a power generation device or a storage battery to a load in linkage with a power system.
  • a power supply system has been proposed that includes a power conversion device that converts DC power from a power generation device such as a solar cell into AC power, and can supply power to the load from the power conversion device as well as the power system of a commercial power supply (for example, Japanese Patent Laid-Open Publication No. 9-135577; hereinafter referred to as Patent Document 1).
  • the system (distributed power supply system) described in Patent Document 1 is configured to be able to switch between an interconnected operation in which a power converter (power conditioner) is interconnected to an electric power system and a standalone operation separated from the electric power system. ing.
  • the power conversion device converts direct current power from a power generation device (generating power source) into alternating current power by an inverter during linked operation, and supplies the alternating current power to a load (connected load). At this time, insufficient power that can not be covered by the output power from the power conversion device is supplied from the power system. In addition, the power conversion device shifts to a self-sustaining operation at the time of a power failure or the like, converts the power from the power generation device into AC power by an inverter and supplies it to a load (self-sustaining load).
  • the power generation device when the power generation device is a solar cell, when surplus power is generated (when the output power of the solar cell is larger than the power consumption of the load), the surplus power is generally reversely flowed to the power system and sold to the power company It is electric.
  • the power generation device in Japan, for example, if the power generation device is a fuel cell other than a solar battery, reverse power flow to the power grid is not permitted even if surplus power is generated.
  • a storage battery in combination with a solar cell is also proposed, reverse flow of power from the storage battery to the power grid is not permitted.
  • the reverse flowable power is actively sold, and the reverse flowable power is aggressively transferred to the load. It is considered to be desirable from the point of view of saving of electricity charges.
  • the power supplied to the load is preferentially used by the generated power of the solar cell, and the discharge power of the storage battery is the power consumption of the load of the solar cell. It is used to compensate for the shortfall when generating power is exceeded.
  • the present invention has been made in view of the above, and power supply system capable of aggressively selling power capable of reverse flow to the power system and capable of actively supplying load capable of reverse flowable power is disclosed. Intended to be provided.
  • the power supply system is a first power conversion device connected to a first power generation device that generates power capable of reverse flow to the power system, and performing power conversion of the power generated by the first power generation device;
  • a second power converter connected to a storage battery to charge and discharge the storage battery, and a second power generation device to generate power that can not reverse power flow to the power system, the power generated by the second power generation device
  • the third power conversion device is connected such that the first power conversion device is on the most upstream side with respect to the interconnection feeding path, and the power supply system is configured to First power converter connection point and the above 2 and a third power conversion device provided between the connection point of the one power conversion device connected on the upstream side, and detecting reverse flow power flowing on the upstream side in the interconnection feeding path
  • the second power conversion device controls charging and discharging of the storage battery such that the reverse flow power detected by the first detector becomes
  • the second and third power converters are connected such that the second power converter is on the upstream side with respect to the interconnection feeding path, and the power supply is performed.
  • the system is provided between a connection point of the second power conversion device and a connection point of the third power conversion device in the interconnection feed path, and a reverse flow flowing through the interconnection feed path on the upstream side
  • a second detector for detecting power is further provided, wherein the second power conversion device is connected to the first detector such that the reverse flow power detected by the first detector is zero.
  • the third power converter is connected to the second detector, and the series is such that reverse flow power detected by the second detector is zero. It is desirable to control the output power to the system feedline.
  • one of the second and third power converters connected on the upstream side is connected to the first detector, and the second and third power converters are connected.
  • the power converter controls the charge and discharge of the storage battery such that the reverse flow power detected by the first detector becomes zero by communicating with each other, and the third power converter It is more desirable to control the output power to the grid feed.
  • the second power generation apparatus be a cogeneration system that generates electrical energy and thermal energy simultaneously.
  • the first power generation device is a solar cell
  • the second power generation device is a fuel cell
  • the first power conversion device is configured to receive surplus power generated by the solar cell. It is more desirable to reverse power flow to the power system.
  • a disconnection device provided on the upstream side of a connection point with the first power conversion device in the interconnection feeding path and a disconnection of the disconnection device when an abnormality in the power system is detected
  • an abnormality detection unit for transmitting an abnormality detection signal to one power conversion device among the first to third power conversion devices, and the one power conversion device receives the abnormality detection signal.
  • a constant voltage control is performed to maintain the output voltage to the interconnection feed path at a predetermined target value, and another power conversion device detects the voltage of the interconnection feed path and outputs a current according to the voltage It is more desirable to perform control.
  • each of the first to third power conversion devices includes an interconnection operation for supplying power to the load via the interconnection feed path, and a self-supporting feed path separated from the electric power system. It is possible to switch over to a stand-alone operation for supplying power to the load via one of the first to third power conversion devices, and one of the power converters of the first to third power converters performs an output voltage to the stand-alone power feed path during the stand-alone operation. It is more desirable that constant voltage control is performed to maintain a predetermined target value, and another power conversion device performs current control that detects the voltage of the stand-alone power feed path during the stand-alone operation and outputs current in accordance with the voltage. .
  • one power converter among the first to third power converters is separated from the grid operation for supplying power to the load via the grid feed path, and the power system. It is possible to switch between the stand-alone operation of supplying power to the load via the stand-alone power feed path, and the other power conversion device switches an external switch which switches the connection destination between the interconnected feed path and the stand-alone power feed path. Is connected to the grid feed path and the stand-alone feed path, and the one power conversion device performs constant voltage control to maintain the output voltage to the stand-alone feed path at a predetermined target value during the stand-alone operation. It is more preferable to perform current control in which the external switching device is switched to the self-supporting feed path side, and the other power conversion device detects a voltage of the self-supporting feed path and outputs a current according to the voltage.
  • this power supply system there are a plurality of loads, and a load breaker inserted in a power supply path to each of the plurality of loads, a storage unit storing priority of the plurality of loads, and It is more desirable to further include a load selection unit that shuts off the load breaker in order from the load with the lower priority according to the power supplied to the plurality of loads.
  • the first power generation device generates power capable of reverse flow to the power system
  • the second power generation device generates power not capable of reverse flow to the power system
  • the power supply system of the present invention is connected to the first power generation device, and the first power conversion device that performs power conversion of the generated power of the first power generation device, and the storage battery, charging and discharging the storage battery And a third power conversion device connected to the second power generation device and performing power conversion of the generated power of the second power generation device, and the power system is connected upstream
  • the conversion device is connected so as to be on the most upstream side, and the power supply system includes a connection point of the first power conversion device in the interconnection feeding path and the second and third power conversion devices.
  • the present invention has the advantage that power capable of reverse flow to the power system can be actively sold and power not capable of reverse flow can be actively supplied to the load.
  • FIG. 1 is a block diagram showing a configuration of a power supply system according to a first embodiment.
  • FIG. 6 is an explanatory diagram of an operation of the power supply system according to the first embodiment.
  • 3A to 3C are explanatory diagrams of the operation of the power supply system according to the first embodiment.
  • 5 is a block diagram showing another configuration of the power supply system according to Embodiment 1.
  • FIG. FIG. 1 is a circuit diagram showing a main part of a power supply system according to a first embodiment.
  • FIG. 7 is a block diagram showing a configuration of a power supply system according to a second embodiment.
  • FIG. 7 is a block diagram showing a configuration of a power supply system according to a third embodiment.
  • FIG. 14 is a block diagram showing another configuration of the power supply system according to Embodiment 3.
  • 9A and 9B are block diagrams showing the main parts of the power supply system according to the third embodiment.
  • the power supply system 1 of the present embodiment includes a solar cell 2, a first power converter 3 connected to the solar cell 2, a storage battery 4, and a second connection connected to the storage battery 4. And a third power converter 7 connected to the fuel cell 6. That is, the solar cell 2 as a first power generation device is connected to the first power conversion device 3, and the fuel cell 6 as a second power generation device is connected to the third power conversion device 7.
  • this embodiment demonstrates the case where the power supply system 1 is used for the consumer consisting of a general detached house as an example, not only this but the power supply system 1 is each dwelling unit and facility of an apartment house. , And may be used by consumers consisting of business establishments and the like.
  • Storage battery 4 is made of, for example, a lead storage battery or a lithium ion battery.
  • Each of the first to third power conversion devices 3, 5, and 7 is configured to be capable of linked operation linked to a power system (commercial system) 8 of a commercial power source. Furthermore, the first power conversion device 3 has an interconnection output end 31 that becomes an output end of electric power during interconnection operation. Similarly, the second power conversion device 5 has an interconnection output end 51 which becomes an output end of electric power in interconnection operation, and the third power conversion device 7 becomes an output end of electric power in interconnection operation. An interconnection output end 71 is provided. The configuration of each power converter will be described later.
  • the first to third power conversion devices 3, 5 and 7 connect the interconnection output terminals 31, 51 and 71 to the interconnection feed path 11 to which the electric power system 8 is connected. That is, the interconnection output terminals 31, 51, 71 of the first power conversion device 3, the second power conversion device 5, and the third power conversion device 7 are connected to each other through the interconnection power feeding path 11. There is.
  • the second power generation apparatus including the fuel cell 6 constitutes a cogeneration system that generates electric energy and heat energy at the same time by using exhaust heat at the time of power generation. Also, for example, in Japan, the first power generation device including the solar cell 2 is permitted to sell the generated power to the power company, whereas the second power generation device including the fuel cell 6 is It is not permitted to sell the generated power.
  • a load 9 is connected to the interconnection feed path 11.
  • the load 9 is various electric devices such as a lighting fixture, a refrigerator, a television, a medical device, a charger of a mobile phone terminal, and here, an alternating current that operates by receiving the supply of alternating current power from the power conversion device or the power system 8. It consists of a drive-type electrical device.
  • the interconnection power feeding path 11 is directly connected to the load 9 made of an electric device, and may be connected to an outlet (not shown) to which the load 9 can be detachably connected.
  • the first power conversion device 3 includes a DCDC converter 33 connected to the solar cell 2, a DCAC converter 34 for converting DC power into AC power, a control unit 35 for controlling each part, and a relay side switching switch made of a relay. And a vessel 36.
  • a DCAC converter 34 is connected to a terminal of the DCDC converter 33 opposite to the solar cell 2.
  • the output terminal of AC power in the DCAC converter 34 is connected to the interconnection output end 31 via the interconnection side switch 36.
  • the DCDC converter 33 boosts the DC power from the solar cell 2 and outputs the DC power to the DCAC converter 34.
  • the DCAC converter 34 is a unidirectional converter (inverter) that converts DC power from the DCDC converter 33 into AC power synchronized with the voltage of the power system 8 and outputs the AC power to the interconnection output end 31. That is, the DCDC converter 33 and the DCAC converter 34 constitute the conversion circuit 30 which converts the power from the solar cell 2 and outputs the converted power to the interconnection feeding path 11.
  • the control unit 35 mainly includes a microcomputer, and implements the functions for controlling the operation of the conversion circuit 30 by executing a program stored in a memory (not shown).
  • the control unit 35 performs maximum power point tracking (MPPT) control of the DCDC converter 33. That is, since the solar cell 2 has a characteristic that the generated power is not constant but changes according to the output voltage, it is desirable that the solar cell 2 operate at the optimum point (maximum power point) at which the generated power is maximum.
  • MPPT maximum power point tracking
  • the operating point of the solar cell 2 always has the maximum power point with respect to fluctuations in output voltage and output current caused by temperature changes of the solar cell 2 and changes in solar radiation intensity.
  • maximum power point tracking control is performed to extract the output of the solar cell 2 to the maximum.
  • the whole of the first power conversion device 3 performs current control that detects the voltage of the interconnection feeding path 11 and outputs a current in accordance with the voltage. Since the maximum power point tracking control is a known technique, the detailed description is omitted.
  • control unit 35 connects the grid-side switch 36 during grid-connected operation, and shuts off the grid-side switch 36 when an abnormality such as a power failure occurs in the electric power system 8 or when the first power conversion device 3 has an abnormality. Prevent unnecessary operation and the influence on the outside (power system 8).
  • the power generated by the solar cell (first power generation device) 2 connected to the first power conversion device 3 is the power permitted to be sold by the power company, the first power conversion is performed. If there is a surplus of the power generated by the solar cell 2, the device 3 causes the power system 8 to reverse power flow and sell it.
  • the second power conversion device 5 includes a DCDC converter 53 connected to the storage battery 4, a DCAC converter 54 for converting DC power into AC power, a control unit 55 for controlling each part, and an interconnection side switch consisting of a relay. And 56.
  • a DCAC converter 54 is connected to a terminal of the DCDC converter 53 opposite to the storage battery 4.
  • the output terminal of AC power in the DCAC converter 54 is connected to the interconnection output end 51 via the interconnection side switch 56.
  • the DCDC converter 53 boosts DC power from the storage battery 4 and outputs the DC power to the DCAC converter 54. Further, the DCDC converter 53 is a bi-directional converter that controls DC power from the DCAC converter 54 to an optimal charging voltage and current according to the state of the storage battery 4 and outputs the DC power to the storage battery 4 when the storage battery 4 is charged.
  • the DCAC converter 54 converts DC power from the DCDC converter 53 into AC power synchronized with the voltage of the power system 8 and outputs the AC power to the interconnection output terminal 51.
  • the DCAC converter 54 is a bi-directional converter that converts AC power from the interconnection output terminal 51 into DC power and outputs the DC power to the DCDC converter 53 when the storage battery 4 is charged.
  • the DCDC converter 53 and the DCAC converter 54 convert electric power bidirectionally between the storage battery 4 and the interconnection feeding path 11 to configure a charge / discharge circuit 50 for charging / discharging the storage battery 4.
  • the operation of the charge / discharge circuit 50 when converting the output of the storage battery 4 into alternating current power and supplying it to the interconnected feeding path 11 is in the discharge mode, and conversely the power from the interconnected feeding path 11 is converted into direct current power
  • the operation when supplying the battery 4 to the storage battery 4 is called a charge mode.
  • the control unit 55 mainly includes a microcomputer, and implements the functions for controlling the operation of the charge and discharge circuit 50 by executing a program stored in a memory (not shown).
  • the control unit 55 sets a target value of the output current of the charge / discharge circuit 50, and controls the operation of the charge / discharge circuit 50 so that the output current of the charge / discharge circuit 50 matches the target value.
  • the second power conversion device 5 as a whole performs current control in which the voltage of the interconnection feeding path 11 is detected and the current is output in accordance with the voltage.
  • control unit 55 connects the grid-side switch 56 during grid-connected operation, and shuts off the grid-side switch 56 when the power system 8 is abnormal such as a power failure or the second power conversion device 5 is abnormal. Prevent unnecessary operation and the influence on the outside (power system 8).
  • the third power conversion device 7 includes a DCDC converter 73 connected to the fuel cell 6, a DCAC converter 74 for converting DC power into AC power, a control unit 75 for controlling each part, and an interconnection side switching switch made of a relay. And a vessel 76.
  • a DCAC converter 74 is connected to a terminal of the DCDC converter 73 opposite to the fuel cell 6.
  • the output terminal of AC power in the DCAC converter 74 is connected to the interconnection output end 71 via the interconnection side switch 76.
  • the DCDC converter 73 boosts the DC power from the fuel cell 6 and outputs the DC power to the DCAC converter 74.
  • the DCAC converter 74 is a unidirectional converter (inverter) that converts DC power from the DCDC converter 73 into AC power synchronized with the voltage of the power system 8 and outputs the AC power to the interconnection output end 71. That is, the DCDC converter 73 and the DCAC converter 74 constitute a conversion circuit 70 which converts the electric power from the fuel cell 6 and outputs the electric power to the interconnection feeding path 11.
  • the third power converter 7 is integrated with the fuel cell 6 to constitute a fuel cell system 700, but the third power converter 7 is a separate body from the fuel cell 6. May be
  • the control unit 75 has a microcomputer as a main component, and implements each function for controlling the operation of the conversion circuit 70 by executing a program stored in a memory (not shown).
  • the controller 75 sets a target value of the output current of the conversion circuit 70, and controls the operation of the conversion circuit 70 so that the output current of the conversion circuit 70 matches the target value.
  • the entire third power conversion device 7 performs current control that detects the voltage of the interconnection feeding path 11 and outputs a current in accordance with the voltage.
  • control unit 75 outputs not only the conversion circuit 70 but also the operating conditions corresponding to the accessories (a pump for adjusting gas, air, water, etc., a valve, a blower, etc.) for driving the fuel cell 6 Alternatively, the operation of the auxiliary machinery may be controlled. Furthermore, the control unit 75 connects the grid-side switch 76 during grid-connected operation, and shuts off the grid-side switch 76 when the power system 8 is abnormal such as a power failure or the third power conversion device 7 is abnormal. Prevent unnecessary operation and the influence on the outside (power system 8).
  • the first to third power conversion devices with the connection point with the power system 8 in the interconnection feed path 11 as the uppermost stream and the connection point with the load 9 as the most downstream. 3, 5, and 7 are individually connected between the uppermost stream and the lowermost stream of the interconnection feed path 11.
  • the first to third power converters 3, 5 and 7 are the first power converter 3, the second power converter 5, and the third power converter from the upstream side. It is connected to the interconnection feed path 11 in the order of 7.
  • the power supply system 1 includes the first detector 14 and the second detector 15 on the interconnection feed path 11 in order to detect the power flow in the interconnection feed path 11. .
  • the first detector 14 is connected to the second power converter 5, and the second detector 15 is connected to the third power converter 7.
  • the first detector 14 is provided at a location on the upstream side of a connection point of the interconnection power feeding path 11 with the second power conversion device 5 and is formed of a current sensor that detects a current flowing through the location.
  • the second detector 15 is provided at a location on the upstream side of the connection point with the third power conversion device 7 in the interconnection power feeding path 11, and includes a current sensor that detects the current flowing in this location.
  • the first detector 14 is provided between the first power conversion device 3 and the second power conversion device 5, and the second power conversion device 5 and the third power conversion device 5 are provided. Between the power conversion device 7 and the second detector 15 is provided. In other words, the first detector 14 is connected to the connection point of the first power conversion device 3 in the interconnection feed path 11 and to the upstream side of the second power conversion device 5 and the third power conversion device 7 And the connection point of one of the power converters (the second power converter 5 in the present embodiment).
  • the control unit 55 of the second power conversion device 5 monitors the voltage waveform of the interconnection feeding path 11, and determines the phase difference between this voltage waveform and the current waveform detected by the first detector 14. Thereby, the direction (whether reverse power flow or not) of the power flow in the portion where the first detector 14 is provided is determined.
  • the control unit 75 of the third power conversion device 7 monitors the voltage waveform of the interconnection feeding path 11, and determines the phase difference between this voltage waveform and the current waveform detected by the second detector 15. Thereby, the direction (whether reverse power flow or not) of the power flow in the portion where the second detector 15 is provided is determined.
  • control unit 55 detects the direction of the power flow between the first power conversion device 3 and the second power conversion device 5 in the interconnection power feeding path 11, and the control unit 75 The direction of power flow between the second power conversion device 5 and the third power conversion device 7 in the feed path 11 is detected.
  • the control unit 55 is connected from the second power conversion device 5 to the grid feed path 11 in a range where the reverse flow toward the upstream side becomes zero at the location where the first detector 14 is provided in the grid feed path 11.
  • the target value is set so that the output power becomes as large as possible, and the operation of the charge and discharge circuit 50 is controlled.
  • the control unit 55 monitors the remaining capacity of the storage battery 4 and switches the charge / discharge circuit 50 to the charging mode to start charging of the storage battery 4 when the remaining capacity falls below a predetermined charging threshold.
  • the controller 55 detects a reverse flow toward the upstream side at the point where the first detector 14 is provided, the operation of the charge / discharge circuit 50 is set to the charge mode when the storage battery 4 has a vacant capacity. You may switch.
  • the control unit 75 is connected from the third power conversion device 7 to the grid feed path 11 in a range where the reverse flow toward the upstream side becomes zero at the location where the second detector 15 is provided in the grid feed path 11.
  • the target value is set so that the output power becomes as large as possible, and the operation of the conversion circuit 70 is controlled.
  • the control unit 55 of the second power conversion device 5 controls the charge and discharge of the storage battery 4 such that the reverse flow power detected by the first detector 14 becomes zero. .
  • the control unit 75 of the third power conversion device 7 connects the second power generation device (fuel cell 6) to the interconnection power feeding path so that the reverse flow power detected by the first detector 14 becomes zero. It will be controlling the output power to 11. At this time, the control unit 75 may control the operation of the accessories as well. The control unit 75 may shut off the connection-side switch 76 when the reverse flow toward the upstream side is detected at the location where the second detector 15 is provided.
  • FIGS. 2 and 3 showing an example of an operation pattern of the power supply system 1.
  • the horizontal axis represents time (0 to 24 o'clock)
  • the vertical axis represents power
  • power used by the entire consumer is represented by used power P1
  • power sold is represented by sold power P2.
  • illustration of the 1st-3rd power converters 3, 5, and 7 is abbreviate
  • the solar cell 2 is "PV”
  • the storage battery 4 is "SB”
  • the fuel cell 6 is "SC”.
  • the load 9 is represented by "Ls”.
  • the second and third power conversion devices 5 and 7 stop the output to the interconnection feed line 11.
  • the power consumption of the load 9 is entirely covered by purchased power (indicated by “A1” in FIG. 2) supplied from the power system 8.
  • the second power conversion device 5 uses the purchased power from the electric power system 8 (indicated by "A2" in FIG. 2).
  • the storage battery 4 is charged. That is, from 20 o'clock to 6 o'clock, as shown in FIG. 3A, the power from the electric power system 8 is supplied to the load 9 and the storage battery 4 through the interconnection feeding path 11.
  • the third power conversion device 7 operates and outputs the power generated by the fuel cell 6 to the interconnection feed path 11. At this time, the third power conversion device 7 limits the output power so that the output power does not reversely flow in the interconnection feeding path 11 upstream. As a result, if the power consumption of the load 9 is less than or equal to the generated power of the fuel cell 6, the output power of the third power conversion device 7 (indicated by "A3" in FIG. 2) follows the power consumption of the load 9. The power consumption of the load 9 changes as the upper limit.
  • the electric power generated by the solar cell 2 is actively reversely transmitted to the electric power system 8 as the sale electric power P2.
  • the power (power consumption of the load 9) required on the downstream side of the connection point with the first power conversion device 3 in the interconnection feeding path 11 is all sufficient with the outputs of the fuel cell 6 and the storage battery 4. Therefore, the first power conversion device 3 sells all the generated power of the solar cell 2 which becomes surplus power. That is, if the consumed power of the load 9 is equal to or less than the generated power of the fuel cell 6 from 6 o'clock to 20 o'clock, the electric power from the fuel cell 6 passes through the interconnection feeding path 11 as shown in FIG. The power generated by the solar cell 2 is reversely transmitted to the power system 8.
  • the second power conversion device 5 operates and outputs the power stored in the storage battery 4 to the interconnection feed path 11 Do. At this time, the second power conversion device 5 limits the output power so that the output power does not reversely flow in the interconnection feeding path 11 upstream.
  • the insufficient power which is the difference between the power consumption of the load 9 and the output power of the third power conversion device 7 is the discharged power supplied from the second power conversion device 5 to the interconnection power feeding path 11 (see FIG. 2) It is covered by "A4".
  • the consumed power of the load 9 exceeds the generated power of the fuel cell 6 from 6 o'clock to 20 o'clock, as shown in FIG. 3C, the electric power from the fuel cell 6 and the storage battery 4 is interconnected and fed.
  • the load 9 is supplied to the load 9 through the path 11, and the generated power of the solar cell 2 is reversely transmitted to the power system 8.
  • the first portion is The power converter 3 supplies the generated power of the solar cell 2 to the load 9.
  • the power conversion device 3 of 1 is reversely fed to the power system 8 and is sold.
  • the above-described operation can be performed, for example, by providing appropriate timers (not shown) for the second power conversion device 5 and the third power conversion device 7 respectively, and setting the operations of the control units 35, 55, and 75 appropriately. It is feasible.
  • control unit 35, 55, and 75 of the first to third power conversion devices 3, 5, and 7 56 and 76 are shut off to stop the output to the interconnected feeding path 11.
  • control unit 55 of second power conversion device 5 connects connection side switch 56 and operates charge / discharge circuit 50 in the charge mode. , Charging the storage battery 4 using purchased power from the power system 8.
  • the second power conversion device 5 reaches a predetermined second time (3 o'clock in the above example) or the remaining capacity of the storage battery 4 exceeds a predetermined upper limit (the storage battery 4 is fully charged In the case of (1), the connection-side switch 56 is shut off and charging of the storage battery 4 is completed.
  • the control unit 75 of the third power conversion device 7 connects the interconnection side switch 76 and starts output to the interconnection feed path 11. .
  • the power consumption of the load 9 is covered by the purchased power from the electric power system 8.
  • the control unit 75 of the third power conversion device 7 makes the reverse flow power detected by the second detector 15 be zero.
  • the operation of the conversion circuit 70 and the opening / closing of the interconnection side switch 76 are controlled so that the output power from the third power conversion device 7 to the interconnection feeding path 11 becomes as large as possible in the range.
  • the control unit 55 of the second power conversion device 5 sets the second power conversion device 5 within a range in which the reverse flow power detected by the first detector 14 is zero.
  • the operation of the charge / discharge circuit 50 and the opening / closing of the interconnection side switch 56 are controlled so that the output power to the interconnection feeding path 11 becomes as large as possible.
  • the control unit 75 of the third power conversion device 7 controls the operation of the conversion circuit 70 so that the output current becomes smaller when the second detector 15 detects the reverse flow toward the upstream side (or the control unit 75 shuts off the connection side switch 76).
  • the third power conversion device 7 prevents the reverse power flow at the location where the second detector 15 is provided as described above, the first detection is performed. There is a possibility that reverse power flow may occur at the location where the vessel 14 is provided.
  • the second power conversion device 5 controls the charge / discharge circuit 50 so that the output power is reduced, when the power is output and the first detector 14 detects the reverse flow toward the upstream side Or switch to charge mode).
  • the control unit 35 of the first power conversion device 3 detects the voltage of the interconnection feed path 11 and converts the electric power back to the electric power system 8.
  • the operation of the circuit 30 and the opening and closing of the connection side switch 36 are controlled.
  • the first power conversion device 3 is disconnected from the interconnection feeding path 11, and the second power conversion device 5 operates in the charge mode.
  • the third power conversion device 7 is disconnected from the interconnection feeding path 11.
  • the control unit 75 of the third power conversion device 7 sets the reverse flow power detected by the second detector 15 in a range where The operation of the conversion circuit 70 and the opening and closing of the interconnection side switch 36 are controlled so that the output power from the power conversion device 7 of 3 to the interconnection feeding path 11 becomes as large as possible.
  • the control unit 55 of the second power conversion device 5 outputs the output power from the second power conversion device 5 to the interconnection power feeding path 11 in a range where the reverse flow power detected by the first detector 14 is zero.
  • the operation of the charge / discharge circuit 50 and the opening / closing of the interconnection side switch 56 are controlled so as to be as large as possible.
  • the control unit 35 of the first power conversion device 3 detects the voltage of the interconnection feeding path 11 and operates the conversion circuit 30 so as to reverse the power flow to the electric power system 8 and opens / closes the interconnection side switch 36. Control.
  • the first to third power conversion devices 3, 5 and 7 are disconnected from the interconnection feeding path 11.
  • the second and third power conversion devices 5 and 7 connected to the downstream side of the interconnection feed path 11 go to the upstream side of the interconnection feed path 11.
  • the reverse power flow is prevented, and power is preferentially supplied to the load 9. That is, for the power consumption of the load 9 in the customer, the outputs from the storage battery 4 and the fuel cell 6 connected to the second and third power converters 5 and 7 are preferentially used. Therefore, the first power conversion device 3 can actively sell power by reversely flowing the generated power of the solar cell 2 to the power grid 8. Also, when the power consumption of the load 9 exceeds the sum of the power generated by the fuel cell 6 and the discharge power of the storage battery 4, the first power conversion device 3 loads the power generated by the solar cell 2 so as to cover the shortage. 9 can be supplied.
  • the fuel cell 6 which comprises the cogeneration system which generate
  • the power generated by the sellable solar cell 2 is actively sold, as a result, according to this power supply system, it is possible to reduce the cost of utilities and reduce the amount of CO 2 emissions. .
  • second power conversion device 5 when the power generated by the fuel cell 6 falls below the power consumption of the load 9, the second power conversion device 5 outputs the power stored in the storage battery 4 to compensate for the shortage, so the power system 8 supplies the power.
  • the amount of received power (purchased power) can be reduced.
  • second power conversion device 5 uses purchased electric power from electric power system 8 in the late-night time zone (from 0 o'clock to 3 o'clock) when the electricity rate unit price is low. Since the storage battery 4 is charged, it contributes to the further reduction of the power cost.
  • the output of the fuel cell 6 can cover the power consumption of the load 9. Therefore, the amount of power (purchased power) supplied from the power system 8 can be suppressed to a small amount, and the light and heat expenses can be reduced.
  • the power supply system 1 includes presence / absence of abnormality of the power grid 8 such as a power disconnection device 81 provided on the interconnection feeding path 11 as shown in FIG.
  • An anomaly detection unit 82 may be further included.
  • the disconnector 81 is provided on the upstream side of the connection point with the first power conversion device 3 in the interconnection feeding path 11.
  • the power supply system 1 of this configuration is provided with a voltage detector 83 on the further upstream side of the decoupler 81 in the interconnection feeding path 11.
  • the abnormality detection unit 82 of this configuration receives the output of the voltage detector 83, and detects the presence or absence of an abnormality in the power system 8, such as a power failure.
  • the abnormality detection unit 82 When the abnormality detection unit 82 detects an abnormality in the power system 8, the abnormality detection unit 82 controls the disconnector 81 to shut off the power system 8, and at the same time, one of the power of the first to third power converters 3, 5, 7 An abnormality detection signal is transmitted to the converter (the second or third power converter 5, 7 in the example of FIG. 4).
  • the power conversion device (in this case, the second power conversion device 5) that has received the abnormality detection signal performs control such that constant voltage control is performed to maintain the output voltage to the interconnection power supply path 11 at a predetermined target value.
  • the operation mode of the unit 55 is switched. That is, the second power conversion device 5 normally performs current control that detects the voltage of the interconnection power feeding path 11 and outputs a current according to the voltage, but when receiving the abnormality detection signal from the abnormality detection unit 82 Switch to constant voltage control.
  • the target value at the time of constant voltage control may be variable.
  • the other power conversion devices detect the voltage of the interconnection feeding path 11 even when the power system 8 is abnormal, and adjust the current according to the voltage. Continue current control to output.
  • the first and third power conversion devices 3 and 7 can not continue the operation by the current control when the reference voltage on the grid feed path 11 disappears, the second grid The output voltage from the power converter 5 is applied. Therefore, the first and third power conversion devices 3 and 7 are configured such that the output voltage of the second power conversion device 5 is converted to a pseudo power system (reference voltage) in a state where the power system 8 is disconnected from the interconnection feeding path 11.
  • the power supply to the load 9 is performed by current control.
  • the balance of the output power of each of the first to third power conversion devices 3, 5 and 7 at the time of abnormality of the power system 8 preferentially uses the generated power in the order of the solar cell 2 and the fuel cell 6.
  • the first power conversion device 3 operates to extract the maximum generated power of the solar cell 2 by performing maximum power point tracking control
  • the third power conversion device 7 generates power consumption of the load 9.
  • the power generated by the fuel cell 6 is used to cover the shortage of the power generated by the solar cell 2.
  • the second power conversion device 5 charges the storage battery 4 with surplus power when the power generated by the solar cell 2 and the fuel cell 6 exceeds the power consumption of the load 9 and falls below the power consumption of the load 9. In this case, it operates to discharge the insufficient power from the storage battery 4.
  • one of the first to third power conversion devices 3, 5 and 7 receives an abnormality detection signal and switches to constant voltage control.
  • the other power electronics devices can continue to operate in current control. Therefore, even when the power system 8 is abnormal, not only the discharge power of the storage battery 4 but also the generated power of the solar cell 2 and the fuel cell 6 can be supplied to the load 9 and stable power supply to the load 9 is possible. Become. Furthermore, fuel consumption in the fuel cell 6 can be suppressed by preferentially using the power generated by the solar cell 2.
  • the power conversion device that receives an abnormality detection signal and switches to constant voltage control when the power system 8 is abnormal is the second or third power conversion in which the output voltage is more stable than the first power conversion device 3 Devices 5, 7 are desirable.
  • the “one power converter” is preferably one of the second or third power converters 5 and 7. That is, the second or third power conversion devices 5 and 7 do not stop their output due to the external environment (the amount of solar radiation) as in the first power conversion device 3, and current control of other power conversion devices is performed. It is possible to stably output the reference voltage.
  • the “one power converter” is more preferably the second power converter 5 connected to the storage battery 4.
  • FIG. 5 shows the circuit configuration of the DCDC converter 33 and the DCAC converter 34 in the first power converter 3.
  • similar configurations can be adopted in the second and third power converters 5 and 7 as well. .
  • the DCDC converter 33 is a boost chopper circuit including a series circuit of an inductor 331 and a switching element 332 connected to the solar cell 2 and a series circuit of a diode 333 and a capacitor 334.
  • the inductor 331 and the switching element 332 are connected to the solar cell 2 such that the inductor 331 is on the positive electrode side of the solar cell 2 and the switching element 332 is on the negative electrode side of the solar cell 2.
  • the diode 333 and the capacitor 334 are configured to connect the anode of the diode 333 to the connection point of the inductor 331 and the switching element 332.
  • a terminal of the capacitor 334 opposite to the diode 333 is connected to a connection point between the negative electrode side of the solar cell 2 and the switching element 332.
  • the switching element 332 is formed of an insulated gate bipolar transistor (IGBT) here, and a diode 335 is connected in reverse parallel.
  • a charging switching element 336 formed of an IGBT is connected in parallel to the diode 333.
  • the DC-DC converter 33 generates a DC voltage after boosting at both ends of the capacitor 334 by the control unit 35 performing on / off control of the switching element 332 at a high frequency in a state where power is supplied from the solar cell 2.
  • the DCDC converter 53 of the second power conversion device 5 turns off the switching element 332 and performs on / off control of the charging switching element 336 at a high frequency, thereby the DCAC converter 54. And the storage battery 4 is charged.
  • the DCAC converter 34 is a full bridge inverter circuit in which four switching elements 341 to 344 are connected to the output end (both ends of the capacitor 334) of the DCDC converter 33.
  • the DCAC converter 34 includes an LC filter formed of a series circuit of an inductor 345, a capacitor 346, and an inductor 347 between the connection point of the switching elements 341 and 342 and the connection point of the switching elements 343 and 344.
  • Each of the switching elements 341 to 344 is formed of an IGBT here, and a diode 348 is connected in reverse parallel.
  • the DCAC converter 34 generates an alternating voltage at both ends of the capacitor 346 by the control unit 35 performing on / off control of the switching elements 341 to 344 while power is supplied from the DCDC converter 33.
  • the output end (both ends of the capacitor 346) of the DCAC converter 34 is connected to the interconnection output end 31 via the interconnection-side switch 36 cut off at two points.
  • the DCAC converter 54 of the second power conversion device 5 turns on and off the DC-DC converter 53 by the control unit 55 turning on and off the switching elements 341 to 344. Output.
  • the switching elements 341 to 344 turn on and off, the grid side from the grid side Power conversion (charging) can be performed.
  • the first to third power converters 3, 5, 7 are provided one by one, but the present invention is not limited to this example, and the first to third power converters may be provided. A plurality of three, five and seven may be provided. That is, the power supply system 1 is configured to include at least one first power converter 3, at least one second power converter 5, and at least one third power converter 7. Good.
  • the power supply system 1 of the present embodiment is different from the power supply system 1 of the first embodiment in that the second power conversion device 5 and the third power conversion device 7 are configured to be communicable.
  • the same components as in the first embodiment are denoted by the same reference numerals, and the description thereof will be appropriately omitted.
  • the second power conversion device 5 and the third power conversion device 7 are connected by the communication path 16, and the control unit 55 of the second power conversion device 5 Communication with the control unit 75 of the third power conversion device 7 is configured via the communication path 16.
  • Communication between the second power conversion device 5 and the third power conversion device 7 is not limited to wired communication but may be wireless communication, or even using the interconnected feeding path 11 as a communication path. Good.
  • the second power conversion device 5 and the third power conversion device 7 communicate with each other by the control units 55 and 75 so that each output power (second power) to the interconnection feed path 11 In the converter 5, the input power at the time of charge of the storage battery 4 is also adjusted.
  • the second detector 15 (see FIG. 1) is omitted, and the control unit 75 of the third power conversion device 7 cooperates with the control unit 55 of the second power conversion device 5
  • the target value is set so that the reverse flow toward the upstream side becomes zero at a point where the first detector 14 in 11 is provided.
  • both control units 55 and 75 the output power to interconnection power supply path 11 becomes as large as possible in the range where the reverse flow at the location where first detector 14 is provided in interconnection power supply path 11 becomes zero.
  • the upper limit of the output power of the second and third power converters 5 and 7 is determined.
  • both control units 55 and 75 are configured such that the total of the powers supplied from the second and third power conversion devices 5 and 7 to the interconnection feeding path 11 does not exceed the power consumption of the load 9. And the upper limit of the output power of the third power conversion devices 5 and 7 may be limited.
  • both control units 55 and 75 detect the remaining capacity of storage battery 4 and have a free capacity, both control units 55 and 75 use the load 9 of the power used by second power conversion device 5 for charging storage battery 4.
  • the upper limit of the output power of the third power conversion device 7 is determined. That is, when the output power from the third power conversion device 7 to the grid feed path 11 exceeds the power consumption of the load 9, the surplus power may flow backward from the grid feed path 11 to the upstream side. .
  • the second power conversion device 5 uses the surplus power reversely flowed from the third power conversion device 7 to charge the storage battery 4, thereby providing the first detector 14 in the interconnection power feeding path 11. At the location, it is possible to prevent the occurrence of reverse power flow on the upstream side.
  • the reverse flow of the interconnection power feeding path 11 to the upstream side is not completely prohibited but is used for charging the storage battery 4 In the case reverse flow is also acceptable.
  • the difference from the first embodiment is that, if the storage battery 4 has a free capacity, the second power conversion device 5 charges the storage battery 4 for the reduction of the power consumption when the power consumption of the load 9 temporarily decreases.
  • the output power of the third power conversion device 7 can be kept constant by using the same. That is, by using the surplus power of the fuel cell 6 for charging the storage battery 4, the second power converter 5 changes the power consumption of the load 9 without changing the output power of the third power converter 7. It can correspond.
  • the third power conversion device 7 advances the power generation stop timing of the fuel cell 6 earlier than a predetermined time, and the second power conversion device 5 outputs the discharge power of the storage battery 4 to the interconnection power feeding path 11 Thus, the power consumption of the load 9 after the generation of the fuel cell 6 is stopped is covered.
  • the storage battery 4 and the fuel cell 6 are used in combination, and the storage battery 4 can be used as a buffer of the load 9.
  • the fuel cell 6 can be operated continuously in a relatively efficient output region, and the efficiency of the entire power supply system 1 can be improved.
  • the order of the second power conversion device 5 and the third power conversion device 7 in the interconnection feed path 11 may be reversed. That is, in the above-described example, the second power conversion device 5 and the third power conversion device 7 are connected to the interconnection power feeding path 11 so that the second power conversion device 5 is on the upstream side.
  • the third power conversion device 7 may be on the upstream side.
  • the first to third power converters 3, 5, 7 are interconnected in the order of the first power converter 3, the third power converter 7, and the second power converter 5 from the upstream side.
  • the first detector 14 is connected to the feed path 11 and provided between the first power converter 3 and the third power converter 7.
  • both control units 55 and 75 are configured to maximize the output power to the interconnected feeding path 11 within a range where the reverse flow at the location where the first detector 14 is provided in the interconnected feeding path 11 is zero.
  • the upper limit of the output power of the second and third power electronics devices 5 and 7 is determined to be larger.
  • the power supply system 1 of the present embodiment is the power supply system of the embodiment 1 in that the self-supporting feed line 12 separated from the power system 8 is provided separately from the interconnection feed line 11 as shown in FIG. It is different from 1.
  • the same components as in the first embodiment are denoted by the same reference numerals, and the description thereof will be appropriately omitted.
  • each of the first to third power conversion devices 3, 5 and 7 has two operation states: interconnection operation in which the electric power system 8 is interconnected and independent operation in which the electric power system 8 is disconnected. Is configured to be switchable.
  • the first power conversion device 3 has a stand-alone output end 32 which becomes an output end of power during stand-alone operation separately from the interconnection output end 31.
  • the second power conversion device 5 has a stand-alone output end 52 which becomes an output end of the power during the stand-alone operation separately from the interconnection output end 51
  • the third power conversion device 7 has the power during the stand-alone operation.
  • the self-supporting output end 72 which becomes the output end of is separately provided from the interconnection output end 71.
  • the first to third power conversion devices 3, 5 and 7 respectively connect the free standing output ends 32, 52 and 72 to the free standing feed path 12, and the free standing output ends 32 and 52 via the free standing feed path 12. , 72 are connected.
  • Each of the power conversion devices 3, 5 and 7 has a free standing side switch (not shown).
  • the output terminals of the AC power of each DCAC converter 34, 54, 74 are connected to the interconnection output terminals 31, 51, 71 via interconnection side switches 36, 56, 76, and are self-sustaining via the freestanding side switches. It is connected to the output terminals 32, 52, 72.
  • the respective control units 35, 55, 75 connect the interconnection side switches 36, 56, 76 at the time of interconnection operation to shut off the freestanding side switches, and connect the autonomous side switches at the time of independent operation to connect the interconnection side
  • the switches 36, 56, 76 are shut off.
  • the first to third power conversion devices 3, 5, and 7 each have an abnormality detection unit (not shown) that detects the presence or absence of an abnormality in the power system 8 such as a power failure, and the detection results of the abnormality detection unit Automatic switching between grid-connected operation and self-sustaining operation accordingly. That is, each control unit 35, 55, 75 selects the interconnected operation when the power system 8 is normal, and switches to the independent operation when the power system 8 is abnormal such as a power failure.
  • a load 9 is connected to each of the interconnection feed path 11 and the independent feed path 12.
  • a switch 13 is provided between the grid feed path 11 and the stand-alone feed path 12 and the load 9 to switch the connection destination of the load 9 between the grid feed path 11 and the stand-alone feed path 12. ing.
  • the load 9 is connected to the interconnection feeding path 11 during interconnection operation, and the switch 13 is switched so that the load 9 is connected to the autonomous transmission path 12 during autonomous operation, thereby eliminating the trouble of connecting the load 9. be able to.
  • the switching unit 13 may be configured to be manually switched by a person's operation, but in the present embodiment, a configuration to be automatically switched without depending on a person's operation is adopted.
  • the switching unit 13 is formed of a relay, and the coil is excited using the power supplied from the electric power system 8 through the interconnection feeding path 11 to connect the connection destination of the load 9 to the interconnection feeding path 11. And the self-supporting feed line 12. That is, when the power system 8 is normal, the switching unit 13 excites the coil by the supplied power from the power system 8 to connect the load 9 to the interconnection power feeding path 11. Are connected to the self-supporting feed line 12.
  • the stand-alone power feeding path 12 is directly connected to the load 9 made of an electric device, and may be connected to an outlet (not shown) to which the load 9 can be detachably connected.
  • the switch 13 may be omitted, and the load 9 and the outlet may be individually connected to each of the interconnection feeding path 11 and the independent feeding path 12.
  • an outlet usable at the time of interconnection operation of each power conversion device is connected to interconnection power feeding path 11, and an independent dedicated outlet usable at the time of autonomous operation of each power conversion device is connected to Ru.
  • one of the first to third power conversion devices 3, 5, and 7 (one power of the first to third power conversion devices 3, 5, and 7) Conversion device; here, the second power conversion device 5 performs constant voltage control to maintain the output voltage of the self-supporting power supply line 12 at a predetermined target value during the self-sustaining operation.
  • the other power conversion devices (here, the first and third power conversion devices 3 and 7) perform current control that detects the voltage of the independent power feeding path 12 and outputs current in accordance with the voltage during the independent operation.
  • the target value at the time of constant voltage control may be variable.
  • the second power conversion device 5 when the second power conversion device 5 detects an abnormality in the power system 8, the second power conversion device 5 switches the operation mode of the control unit 55 from current control to constant voltage control. That is, the second power conversion device 5 performs current control that detects the voltage of the interconnection feeding path 11 and outputs the current according to the voltage during the interconnection operation, but detects an abnormality of the electric power system 8 to stand by. When switched to operation, it switches to constant voltage control automatically.
  • the first and third power conversion devices 3 and 7 detect an abnormality in the power system 8 and switch to the stand-alone operation, they detect the voltage of the stand-alone power feed line 12 and output the current according to the voltage. Take control.
  • the output voltage from the second power conversion device 5 is applied to the self-supporting power feed line 12. Therefore, the first and third power conversion devices 3 and 7 regard the output voltage of the second power conversion device 5 as a pseudo power system (reference voltage), and perform power supply to the load 9 by current control. .
  • one of the first to third power conversion devices 3, 5 and 7 switches to constant voltage control when there is an abnormality in the power system 8 such as a power failure, and thereby another power conversion is performed.
  • the device can continue to operate in current control. Therefore, even when the power system 8 is abnormal, not only the discharge power of the storage battery 4 but also the generated power of the solar cell 2 and the fuel cell 6 can be supplied to the load 9 and stable power supply to the load 9 is possible. Become.
  • the power conversion devices 3, 5, and 7 have a function (abnormality detection unit) for detecting an abnormality in the power system 8, there is no need to separately provide a device for detecting the presence or absence of an abnormality in the power system 8
  • the configuration can be simplified.
  • the “one power conversion device (power conversion device that performs constant voltage control at the time of self-sustaining operation)” is any one of the second and third power conversion devices 5 and 7 whose output voltage is stable. Is preferable.
  • the “one power converter” is preferably the second power converter 5 connected to the storage battery 4.
  • the switching unit 13 since the switching unit 13 is provided to switch the connection destination of the load 9 between the grid feed path 11 and the stand-alone feed path 12 during the grid connection operation and the stand-alone operation, the time and effort to switch the load 9 is eliminated. Can. Moreover, since the switching unit 13 automatically switches the connection destination of the load 9 according to the presence or absence of an abnormality in the power system 8, it does not take time for a person to switch the switching unit 13.
  • the switching unit 13 receives a switching signal from one of the first to third power electronics devices 3, 5 and 7 (here, the second power electronics device 5), The connection destination of the load 9 may be switched between the interconnected feeding path 11 and the independent feeding path 12.
  • the first to third power conversion devices 3, 5, and 7 are connected to only some of the power conversion devices (here, the second power conversion device 5). It may be configured to be switchable between two operation states of system operation and self-sustaining operation.
  • the power conversion devices here, the first and third power conversion devices 3 and 7 that do not have the switching function between the interconnection operation and the independent operation are relays 17 as external switches. , 18 are connected to the interconnected feed path 11 and the independent feed path 12.
  • the relays 17 and 18 as external switching devices are controlled by the second power conversion device 5, and the connection destination of the connection output end 31 of the first and third power conversion devices 3 and 7 is connected to the connection power feeding path 11 It switches with the self-supporting feed line 12.
  • the second power conversion device 5 capable of switching between the grid connection operation and the stand-alone operation performs constant voltage control to maintain the output voltage to the stand-alone power feed path 12 at a predetermined target value during stand-alone operation.
  • the other power conversion devices (here, the first and third power conversion devices 3 and 7) detect the voltage of the interconnection power supply line 11 or the independent power supply line 12 and output the current according to the voltage. Do.
  • the target value at the time of constant voltage control may be variable.
  • the second power conversion device 5 switches the operation mode of the control unit 55 from current control to constant voltage control. That is, the second power conversion device 5 performs current control that detects the voltage of the interconnection feeding path 11 and outputs the current according to the voltage during the interconnection operation, but detects an abnormality of the electric power system 8 to stand by. When switched to operation, it switches to constant voltage control automatically. At this time, the second power conversion device 5 controls the relays 17 and 18 as external switches to connect the connection destination of the connection output end 31 of the first and third power conversion devices 3 and 7 to the connection destination. The feed line 11 is switched to the independent feed line 12.
  • the first and third power converters 3 and 7 perform current control that detects the voltage of the independent power feeding path 12 and outputs a current according to the voltage.
  • the output voltage from the second power conversion device 5 is applied to the self-supporting power feed line 12. Therefore, the first and third power conversion devices 3 and 7 regard the output voltage of the second power conversion device 5 as a pseudo power system (reference voltage), and perform power supply to the load 9 by current control. .
  • the power conversion device capable of switching the operation state and the power conversion device that can not be switched. Therefore, even when the power system 8 is abnormal, not only the discharge power of the storage battery 4 but also the generated power of the solar cell 2 and the fuel cell 6 can be supplied to the load 9 and stable power supply to the load 9 is possible.
  • the “one power conversion device (power conversion device having a switching function between the interconnection operation and the self-sustaining operation)” is one of the second and third power conversion devices 5 and 7 whose output voltage is stable. It is preferable that it is either one.
  • the “one power converter” is preferably the second power converter 5 connected to the storage battery 4.
  • the electric power supply system 1 may be equipped with the structure for selecting the load 9 used as the object of electric power supply, when multiple loads 9 are connected to the interconnection power feeding path 11 or the stand-alone electric power feeding path 12.
  • the power supply system 1 includes a current sensor 111 for detecting power supplied to the plurality of loads 91 to 93, and a load selection unit controlling the load breaker 113 according to the power supplied to the loads 91 to 93.
  • the load selection unit 112 has a storage unit (not shown) that stores the priorities set in advance for the plurality of loads 91 to 93.
  • the load selection unit 112 monitors the supplied power (total) to the plurality of loads 91 to 93 detected by the current sensor 111, and when the supplied power exceeds a predetermined threshold, priority is given.
  • the load breaker 113 is disconnected in order from the loads 91 to 93 with the lowest rank. For example, when the priority is set to be higher in the order of the loads 91, 92, and 93, the load selection unit 112 first disconnects the load 91 to which the lowest priority load 91 is connected when the supplied power exceeds the threshold. Power supply to the load 91 is shut off. Even in this state, if the supplied power still exceeds the threshold value, the load selection unit 112 cuts off the load breaker 113 to which the load 92 with the next lower priority is connected, and stops the power supply to the load 92.
  • the load selection unit 112 is incorporated in the first to third power conversion devices 3, 5, and 7, and the first to third power conversions are performed as shown in FIG. 9B.
  • the load shutoff unit 113 may be controlled by control signals from the devices 3, 5, 7.
  • the load selection units in the first to third power conversion devices 3, 5, and 7 output power of each of the power conversion devices 3, 5, and 5, and supply power (total) to the load 9. Both are monitored.
  • the load selecting unit cuts off the load breaker 113 in order from the loads 91 to 93 with low priorities.
  • the power supply system 1 has a limited upper limit of the power that can be supplied to the load 9 at the time of self-sustaining operation and the like by providing the configuration for selecting the load 9 to be the target of the power supply. In this case, stable power supply is possible for the high priority load 9.
  • the present embodiment may be combined with the second embodiment in which the second power conversion device 5 and the third power conversion device 7 can communicate.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

 第1~第3の電力変換装置は上流側から第1の電力変換装置、第2の電力変換装置、第3の電力変換装置の順で連系給電路に接続されている。第1の検出器は、太陽電池を接続した第1の電力変換装置と蓄電池を接続した第2の電力変換装置との間に設けられ、連系給電路上の逆潮流電力を検出する。第2の検出器は、第2の電力変換装置と燃料電池を接続した第3の電力変換装置との間に設けられ、連系給電路上の逆潮流電力を検出する。第2の電力変換装置は、第1の検出器で検出される逆潮流電力がゼロとなるように動作し、第3の電力変換装置は、第2の検出器で検出される逆潮流電力がゼロとなるように動作する。

Description

電力供給システム
 本発明は、電力系統と連系して発電装置や蓄電池からの電力を負荷に供給する電力供給システムに関する。
 太陽電池等の発電装置からの直流電力を交流電力に変換する電力変換装置を備え、商用電源の電力系統だけでなく電力変換装置からも負荷に電力供給できる電力供給システムが提案されている(たとえば日本国特許公開平9-135577号公報参照;以下特許文献1と称する)。特許文献1に記載のシステム(分散型電源システム)は、電力変換装置(パワーコンディショナ)を電力系統に連系させた連系運転と、電力系統から切り離した自立運転とを切替可能に構成されている。
 そのため、電力変換装置は、連系運転時には発電装置(発電源)からの直流電力をインバータにて交流電力に変換し、この交流電力を負荷(連系負荷)に供給する。このとき、電力変換装置からの出力電力で賄えない不足分の電力は、電力系統から供給される。また、電力変換装置は、停電時等には自立運転に移行し、電力系統と切り離された状態で発電装置からの電力をインバータで交流電力に変換して負荷(自立負荷)に供給する。
 ところで、発電装置が太陽電池の場合、余剰電力の発生時(太陽電池の出力電力が負荷の消費電力よりも大きいとき)には、一般的に余剰電力は電力系統に逆潮流され電力会社に売電される。一方、例えば日本国においては、発電装置が太陽電池以外の燃料電池等であれば、余剰電力が発生しても、この余剰電力を電力系統に逆潮流することは許可されていない。また、太陽電池と組み合わせて蓄電池を用いることも提案されているが、蓄電池からの電力を電力系統に逆潮流することも許可されていない。
 電力系統へ逆潮流可能な電力と逆潮流不可能な電力とが混在する電力供給システムにおいては、逆潮流可能な電力は積極的に売電し、逆潮流不可能な電力については負荷へ積極的に供給することが、電気料金の節約の観点からは望ましいと考えられる。しかし、一般的には、たとえば太陽電池と蓄電池とを併用する場合、負荷への電力供給は太陽電池の発電電力が優先的に用いられ、蓄電池の放電電力は、負荷の消費電力が太陽電池の発電電力を上回る場合に不足分を補うために用いられる。したがって、太陽電池の発電電力が負荷の消費電力を上回らない限り、太陽電池で十分な電力が発生している場合でも、売電を行うことができず、電気料金の節約につながりにくいという問題がある。
 本発明は上記事由に鑑みて為されており、電力系統へ逆潮流可能な電力は積極的に売電し、逆潮流不可能な電力は積極的に負荷に供給することができる電力供給システムを提供することを目的とする。
 本発明の電力供給システムは、電力系統へ逆潮流可能な電力を発生させる第1の発電装置に接続され、当該第1の発電装置の発電電力の電力変換を行う第1の電力変換装置と、蓄電池に接続され当該蓄電池の充放電を行う第2の電力変換装置と、前記電力系統へ逆潮流不可能な電力を発生させる第2の発電装置に接続され、当該第2の発電装置の発電電力の電力変換を行う第3の電力変換装置とを備え、上流に前記電力系統が接続された連系給電路の下流に接続されている負荷に電力供給する電力供給システムであって、前記第1~第3の電力変換装置は、前記連系給電路に対して前記第1の電力変換装置が最上流側となるように接続されており、前記電力供給システムは、前記連系給電路における前記第1の電力変換装置の接続点と前記第2および前記第3の電力変換装置のうち前記上流側に接続された一方の電力変換装置の接続点との間に設けられ、前記連系給電路を前記上流側に流れる逆潮流電力を検出する第1の検出器を備えており、前記第2の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、前記第3の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記連系給電路への出力電力を制御することを特徴とする。
 この電力供給システムにおいて、前記第2および前記第3の電力変換装置は、前記連系給電路に対して前記第2の電力変換装置が前記上流側となるように接続されており、前記電力供給システムは、前記連系給電路における前記第2の電力変換装置の接続点と前記第3の電力変換装置の接続点との間に設けられ、前記連系給電路を前記上流側に流れる逆潮流電力を検出する第2の検出器をさらに備え、前記第2の電力変換装置は、前記第1の検出器に接続され、当該第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、前記第3の電力変換装置は、前記第2の検出器に接続され、当該第2の検出器で検出される逆潮流電力がゼロとなるように前記連系給電路への出力電力を制御することが望ましい。
 この電力供給システムにおいて、前記第2および前記第3の電力変換装置のうち前記上流側に接続された一方の電力変換装置は、前記第1の検出器に接続され、前記第2および前記第3の電力変換装置は、互いに通信することにより、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、且つ前記第3の電力変換装置から前記連系給電路への出力電力を制御することがより望ましい。
 この電力供給システムにおいて、前記第2の発電装置は、電気エネルギーと熱エネルギーとを同時に発生するコージェネレーションシステムであることがより望ましい。
 この電力供給システムにおいて、前記第1の発電装置は太陽電池であって、前記第2の発電装置は燃料電池であり、前記第1の電力変換装置は、前記太陽電池の発電電力の余剰分を前記電力系統に逆潮流することがより望ましい。
 この電力供給システムにおいて、前記連系給電路における前記第1の電力変換装置との接続点よりも上流側に設けられた解列器と、前記電力系統の異常を検知すると前記解列器を遮断し、且つ前記第1~第3の電力変換装置のうち一の電力変換装置に異常検知信号を送信する異常検知部とをさらに備え、前記一の電力変換装置は、前記異常検知信号を受信すると前記連系給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、他の電力変換装置は、前記連系給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことがより望ましい。
 この電力供給システムにおいて、前記第1~第3の電力変換装置は、いずれも前記連系給電路を介して前記負荷に電力供給する連系運転と、前記電力系統から切り離された自立給電路を介して前記負荷に電力供給する自立運転とを切替可能であって、前記第1~第3の電力変換装置のうち一の電力変換装置は、前記自立運転時に前記自立給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、他の電力変換装置は、前記自立運転時に前記自立給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことがより望ましい。
 この電力供給システムにおいて、前記第1~第3の電力変換装置のうち一の電力変換装置は、前記連系給電路を介して前記負荷に電力供給する連系運転と、前記電力系統から切り離された自立給電路を介して前記負荷に電力供給する自立運転とを切替可能であって、他の電力変換装置は、接続先を前記連系給電路と前記自立給電路とで切り替える外部切替器を介して前記連系給電路および前記自立給電路に接続されており、前記一の電力変換装置は、前記自立運転時に前記自立給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、且つ前記外部切替器を前記自立給電路側に切り替え、前記他の電力変換装置は、前記自立給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことがより望ましい。
 この電力供給システムにおいて、前記負荷は複数あって、前記複数の前記負荷の各々への電力供給路に挿入された負荷遮断器と、前記複数の前記負荷について優先順位を記憶する記憶部と、前記複数の前記負荷への供給電力に応じて前記優先順位の低い前記負荷から順に前記負荷遮断器を遮断する負荷選択部とをさらに備えることがより望ましい。
 なお、「第1の発電装置が、電力系統へ逆潮流可能な電力を発生させること」および「第2の発電装置が、前記電力系統へ逆潮流不可能な電力を発生させること」は、発明の必須要件ではない。「第1の発電装置」および「第2の発電装置」は、発電を行う発電装置であればよい。
 つまり、本発明の電力供給システムは、第1の発電装置に接続され、当該第1の発電装置の発電電力の電力変換を行う第1の電力変換装置と、蓄電池に接続され当該蓄電池の充放電を行う第2の電力変換装置と、第2の発電装置に接続され、当該第2の発電装置の発電電力の電力変換を行う第3の電力変換装置とを備え、上流に前記電力系統が接続された連系給電路の下流に接続されている負荷に電力供給する電力供給システムであって、前記第1~第3の電力変換装置は、前記連系給電路に対して前記第1の電力変換装置が最上流側となるように接続されており、前記電力供給システムは、前記連系給電路における前記第1の電力変換装置の接続点と前記第2および前記第3の電力変換装置のうち前記上流側に接続された一方の電力変換装置の接続点との間に設けられ、前記連系給電路を前記上流側に流れる逆潮流電力を検出する第1の検出器を備えており、前記第2の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、前記第3の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記連系給電路への出力電力を制御するものであればよい。そして、第1の発電装置が太陽電池であって、第2の発電装置が燃料電池であることが望ましい。
 本発明は、電力系統へ逆潮流可能な電力は積極的に売電し、逆潮流不可能な電力は積極的に負荷に供給できるという利点がある。
実施形態1に係る電力供給システムの構成を示すブロック図である。 実施形態1に係る電力供給システムの動作の説明図である。 図3A~図3Cは、実施形態1に係る電力供給システムの動作の説明図である。 実施形態1に係る電力供給システムの他の構成を示すブロック図である。 実施形態1に係る電力供給システムの要部を示す回路図である。 実施形態2に係る電力供給システムの構成を示すブロック図である。 実施形態3に係る電力供給システムの構成を示すブロック図である。 実施形態3に係る電力供給システムの他の構成を示すブロック図である。 図9A,図9Bは、実施形態3に係る電力供給システムの要部を示すブロック図である。
 (実施形態1)
 本実施形態の電力供給システム1は、図1に示すように、太陽電池2と、太陽電池2に接続された第1の電力変換装置3と、蓄電池4と、蓄電池4に接続された第2の電力変換装置5と、燃料電池6と、燃料電池6に接続された第3の電力変換装置7とを備えている。つまり、第1の電力変換装置3には第1の発電装置としての太陽電池2が接続され、第3の電力変換装置7には第2の発電装置としての燃料電池6が接続されている。なお、本実施形態では、電力供給システム1が一般的な戸建住宅からなる需要家に用いられる場合を例として説明するが、これに限らず、電力供給システム1は集合住宅の各住戸や施設、事業所等からなる需要家に用いられてもよい。蓄電池4は、たとえば鉛蓄電池やリチウムイオン電池などからなる。
 第1~第3の電力変換装置3,5,7は、いずれも商用電源の電力系統(商用系統)8と連系する連系運転可能に構成されている。さらに、第1の電力変換装置3は、連系運転時に電力の出力端になる連系出力端31を有している。同様に、第2の電力変換装置5は、連系運転時に電力の出力端になる連系出力端51を有し、第3の電力変換装置7は、連系運転時に電力の出力端になる連系出力端71を有している。各電力変換装置の構成については後述する。
 第1~第3の電力変換装置3,5,7は、いずれも電力系統8が接続された連系給電路11に連系出力端31,51,71を接続している。つまり、第1の電力変換装置3と第2の電力変換装置5と第3の電力変換装置7とは、連系給電路11を介して連系出力端31,51,71同士が接続されている。
 燃料電池6からなる第2の発電装置は、発電時の排熱を利用可能な構成とすることにより、電気エネルギーと熱エネルギーとを同時に発生するコージェネレーションシステムを構成している。また、例えば日本国では、太陽電池2からなる第1の発電装置は、その発電電力を電力会社に売電することが許可されているのに対し、燃料電池6からなる第2の発電装置はその発電電力を売電することが許可されていない。
 連系給電路11には負荷9が接続される。負荷9は、照明器具や冷蔵庫、テレビ、医療器具、携帯電話端末の充電器など様々な電気機器であって、ここでは、電力変換装置あるいは電力系統8から交流電力の供給を受けて動作する交流駆動型の電気機器からなる。なお、連系給電路11は、電気機器からなる負荷9に直接接続されることは必須ではなく、負荷9を着脱可能に接続可能なコンセント(図示せず)に接続されてもよい。
 以下に、図1を参照して第1~第3の電力変換装置3,5,7の構成および動作について説明する。
 第1の電力変換装置3は、太陽電池2に接続されたDCDCコンバータ33と、直流電力を交流電力に変換するDCACコンバータ34と、各部を制御する制御部35と、リレーからなる連系側開閉器36とを備えている。DCDCコンバータ33における太陽電池2と反対側の端子にはDCACコンバータ34が接続されている。DCACコンバータ34における交流電力の出力端子は、連系側開閉器36を介して連系出力端31に接続されている。
 DCDCコンバータ33は、太陽電池2からの直流電力を昇圧してDCACコンバータ34に出力する。DCACコンバータ34は、DCDCコンバータ33からの直流電力を、電力系統8の電圧に同期させた交流電力に変換して連系出力端31に出力する単方向のコンバータ(インバータ)である。つまり、DCDCコンバータ33およびDCACコンバータ34は、太陽電池2からの電力を変換して連系給電路11に出力する変換回路30を構成する。
 制御部35はマイコン(マイクロコンピュータ)を主構成としており、メモリ(図示せず)に記憶されているプログラムを実行することによって、変換回路30の動作を制御するための各機能を実現する。ここで、制御部35は、DCDCコンバータ33を最大電力点追従(MPPT:Maximum PowerPoint Tracking)制御する。つまり、太陽電池2は、発電電力が一定ではなく出力電圧に応じて発電電力が変化する特性を持つので、発電電力が最大となる最適点(最大電力点)で動作することが望ましい。
 そこで、本実施形態の第1の電力変換装置3は、太陽電池2の温度変化や日射強度の変化に伴う出力電圧や出力電流の変動に対し、太陽電池2の動作点が常に最大電力点を追従して、太陽電池2の出力を最大限に引き出す最大電力点追従制御を行う。このとき、第1の電力変換装置3全体としては、連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことになる。最大電力点追従制御は周知の技術であるから、詳しい説明は省略する。さらに、制御部35は、連系運転時には連系側開閉器36を接続し、停電などの電力系統8の異常時や第1の電力変換装置3の異常時には連系側開閉器36を遮断して不要動作や外部(電力系統8)への影響を防止する。
 また、第1の電力変換装置3に接続された太陽電池(第1の発電装置)2の発電電力は、電力会社に売電することが許可されている電力であるので、第1の電力変換装置3は太陽電池2の発電電力の余剰分があれば電力系統8に逆潮流させて売電する。
 第2の電力変換装置5は、蓄電池4に接続されたDCDCコンバータ53と、直流電力を交流電力に変換するDCACコンバータ54と、各部を制御する制御部55と、リレーからなる連系側開閉器56とを備えている。DCDCコンバータ53における蓄電池4と反対側の端子にはDCACコンバータ54が接続されている。DCACコンバータ54における交流電力の出力端子は、連系側開閉器56を介して連系出力端51に接続されている。
 DCDCコンバータ53は、蓄電池4の放電時には蓄電池4からの直流電力を昇圧してDCACコンバータ54に出力する。また、このDCDCコンバータ53は、蓄電池4の充電時にはDCACコンバータ54からの直流電力を蓄電池4の状態に応じた最適な充電電圧、電流に制御して蓄電池4に出力する双方向のコンバータである。DCACコンバータ54は、蓄電池4の放電時にはDCDCコンバータ53からの直流電力を、電力系統8の電圧に同期させた交流電力に変換して連系出力端51に出力する。また、このDCACコンバータ54は、蓄電池4の充電時には連系出力端51からの交流電力を直流電力に変換してDCDCコンバータ53に出力する双方向のコンバータである。
 つまり、DCDCコンバータ53およびDCACコンバータ54は、蓄電池4と連系給電路11との間で双方向に電力を変換し、蓄電池4の充放電を行う充放電回路50を構成する。以下では、蓄電池4の出力を交流電力に変換して連系給電路11へ供給するときの充放電回路50の動作を放電モード、反対に連系給電路11からの電力を直流電力に変換して蓄電池4へ供給するときの動作を充電モードという。
 制御部55はマイコン(マイクロコンピュータ)を主構成としており、メモリ(図示せず)に記憶されているプログラムを実行することによって、充放電回路50の動作を制御するための各機能を実現する。ここで、制御部55は、蓄電池4の放電時には、充放電回路50の出力電流の目標値を設定し、充放電回路50の出力電流が目標値に合うように充放電回路50の動作を制御する。このとき、第2の電力変換装置5全体としては、連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことになる。さらに、制御部55は、連系運転時には連系側開閉器56を接続し、停電などの電力系統8の異常時や第2の電力変換装置5の異常時には連系側開閉器56を遮断して不要動作や外部(電力系統8)への影響を防止する。
 第3の電力変換装置7は、燃料電池6に接続されたDCDCコンバータ73と、直流電力を交流電力に変換するDCACコンバータ74と、各部を制御する制御部75と、リレーからなる連系側開閉器76とを備えている。DCDCコンバータ73における燃料電池6と反対側の端子にはDCACコンバータ74が接続されている。DCACコンバータ74における交流電力の出力端子は、連系側開閉器76を介して連系出力端71に接続されている。
 DCDCコンバータ73は、燃料電池6からの直流電力を昇圧してDCACコンバータ74に出力する。DCACコンバータ74は、DCDCコンバータ73からの直流電力を、電力系統8の電圧に同期させた交流電力に変換して連系出力端71に出力する単方向のコンバータ(インバータ)である。つまり、DCDCコンバータ73およびDCACコンバータ74は、燃料電池6からの電力を変換して連系給電路11に出力する変換回路70を構成する。なお、図1の例では、第3の電力変換装置7は燃料電池6と一体化され燃料電池システム700を構成しているが、第3の電力変換装置7は燃料電池6と別体であってもよい。
 制御部75はマイコン(マイクロコンピュータ)を主構成としており、メモリ(図示せず)に記憶されているプログラムを実行することによって、変換回路70の動作を制御するための各機能を実現する。ここで、制御部75は、変換回路70の出力電流の目標値を設定し、変換回路70の出力電流が目標値に合うように変換回路70の動作を制御する。このとき、第3の電力変換装置7全体としては、連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことになる。また、制御部75は、変換回路70だけでなく、燃料電池6を駆動する補機類(ガスや空気や水等の調節用ポンプ、弁、ブロア等)に対しても対応する動作条件を出力し、補機類の動作も制御する構成であってもよい。さらに、制御部75は、連系運転時には連系側開閉器76を接続し、停電などの電力系統8の異常時や第3の電力変換装置7の異常時には連系側開閉器76を遮断して不要動作や外部(電力系統8)への影響を防止する。
 上記構成により、電力系統8の正常時(連系運転時)には、第1の電力変換装置3と第2の電力変換装置5と第3の電力変換装置7と電力系統8との少なくとも一つからの電力が、連系給電路11を通して負荷9に供給される。
 ところで、本実施形態の電力供給システム1においては、連系給電路11における電力系統8との接続点を最上流、負荷9との接続点を最下流として、第1~第3の電力変換装置3,5,7は連系給電路11の最上流と最下流との間に個別に接続されている。ここで、第1~第3の電力変換装置3,5,7は、図1に示すように上流側から第1の電力変換装置3、第2の電力変換装置5、第3の電力変換装置7の順で連系給電路11に接続されている。
 また、本実施形態の電力供給システム1は、連系給電路11における電力潮流を検出するために、第1の検出器14および第2の検出器15を連系給電路11上に備えている。本実施形態では、第1の検出器14は第2の電力変換装置5に接続され、第2の検出器15は第3の電力変換装置7に接続されている。第1の検出器14は、連系給電路11における第2の電力変換装置5との接続点の上流側の箇所に設けられ、この箇所を流れる電流を検出する電流センサからなる。第2の検出器15は、連系給電路11における第3の電力変換装置7との接続点の上流側の箇所に設けられ、この箇所を流れる電流を検出する電流センサからなる。つまり、連系給電路11において、第1の電力変換装置3と第2の電力変換装置5との間には第1の検出器14が設けられ、第2の電力変換装置5と第3の電力変換装置7との間には第2の検出器15が設けられている。言い換えれば、第1の検出器14は、連系給電路11における第1の電力変換装置3の接続点と、第2の電力変換装置5および第3の電力変換装置7のうち上流側に接続された一方の電力変換装置(本実施形態では第2の電力変換装置5)の接続点と、の間に設けられている。
 第2の電力変換装置5の制御部55は、連系給電路11の電圧波形をモニタしており、この電圧波形と第1の検出器14で検出された電流波形との位相差を判別することにより、第1の検出器14が設けられた箇所の電力潮流の向き(逆潮流か否か)を判断する。第3の電力変換装置7の制御部75は、連系給電路11の電圧波形をモニタしており、この電圧波形と第2の検出器15で検出された電流波形との位相差を判別することにより、第2の検出器15が設けられた箇所の電力潮流の向き(逆潮流か否か)を判断する。このようにして、制御部55は、連系給電路11における第1の電力変換装置3と第2の電力変換装置5との間の電力潮流の向きを検出し、制御部75は、連系給電路11における第2の電力変換装置5と第3の電力変換装置7との間の電力潮流の向きを検出する。
 制御部55は、連系給電路11における第1の検出器14を設けた箇所で上流側への逆潮流がゼロとなる範囲で、第2の電力変換装置5から連系給電路11への出力電力が極力大きくなるように目標値を設定し、充放電回路50の動作を制御する。言い換えれば、第2の電力変換装置5は、基本的に連系給電路11への出力電力を極力大きくしながらも、出力電力が連系給電路11を上流側に逆潮流しないように出力電力を制限する。ただし、制御部55は蓄電池4の残容量を監視しており、残容量が所定の充電閾値を下回った場合には充放電回路50を充電モードに切り替えて蓄電池4の充電を開始する。なお、制御部55は、第1の検出器14を設けた箇所で上流側への逆潮流を検出した場合で、蓄電池4に空き容量が存在する場合、充放電回路50の動作を充電モードに切り替えてもよい。
 制御部75は、連系給電路11における第2の検出器15を設けた箇所で上流側への逆潮流がゼロとなる範囲で、第3の電力変換装置7から連系給電路11への出力電力が極力大きくなるように目標値を設定し、変換回路70の動作を制御する。言い換えれば、第3の電力変換装置7は、基本的に連系給電路11への出力電力を極力大きくしながらも、出力電力が連系給電路11を上流側に逆潮流しないように出力電力を制限する。ここで、上述のように、第2の電力変換装置5の制御部55は、第1の検出器14で検出される逆潮流電力がゼロとなるように蓄電池4の充放電を制御している。したがって、第3の電力変換装置7の制御部75は、第1の検出器14で検出される逆潮流電力がゼロとなるように、第2の発電装置(燃料電池6)から連系給電路11への出力電力を制御していることになる。なお、このとき、制御部75は補機類の動作も併せて制御してもよい。なお、制御部75は、第2の検出器15を設けた箇所で上流側への逆潮流を検出した場合、連系側開閉器76を遮断してもよい。
 次に、本実施形態の電力供給システム1の動作について、電力供給システム1の運用パターンの一例を示す図2および図3を参照して説明する。なお、図2では横軸を時刻(0~24時)とし、縦軸を電力として、需要家全体で使用される電力を使用電力P1、売電される電力を売電電力P2で表している。また、図3A~図3Cでは第1~第3の電力変換装置3,5,7の図示を省略し、太陽電池2を「PV」、蓄電池4を「SB」、燃料電池6を「SC」、負荷9を「Ls」で表している。
 この例では、20時から6時までの間においては、負荷9の消費電力が比較的少ないため、第2および第3の電力変換装置5,7は連系給電路11への出力を停止し、負荷9の消費電力は電力系統8から供給される買電電力(図2に「A1」で示す)で全て賄われる。さらに、電気料金単価が安くなる深夜時間帯(0時~3時)には、第2の電力変換装置5は、電力系統8からの買電電力(図2に「A2」で示す)を用いて蓄電池4を充電する。つまり、20時から6時までの間は、図3Aに示すように、電力系統8からの電力が連系給電路11を通って負荷9および蓄電池4に供給される。
 一方、6時から20時の間においては、第3の電力変換装置7が動作し燃料電池6で生成された電力を連系給電路11へ出力する。このとき、第3の電力変換装置7は、その出力電力が連系給電路11を上流側に逆潮流しないように出力電力を制限する。結果的に、負荷9の消費電力が燃料電池6の発電電力以下であれば、第3の電力変換装置7の出力電力(図2に「A3」で示す)は、負荷9の消費電力を追従するように、負荷9の消費電力を上限として変化する。
 さらに、6時から20時の間において、太陽電池2で発電された電力は、積極的に売電電力P2として電力系統8に逆潮流される。図2の例では、連系給電路11における第1の電力変換装置3との接続点より下流側で必要な電力(負荷9の消費電力)は、燃料電池6および蓄電池4の出力で全て足りているので、第1の電力変換装置3は、余剰電力となる太陽電池2の発電電力を全て売電する。つまり、6時から20時までの間で、負荷9の消費電力が燃料電池6の発電電力以下であれば、図3Bに示すように、燃料電池6からの電力が連系給電路11を通って負荷9に供給され、太陽電池2の発電電力は電力系統8に逆潮流される。
 また、6時から20時の間において、負荷9の消費電力が燃料電池6の発電電力を超える場合、第2の電力変換装置5が動作し蓄電池4に蓄積された電力を連系給電路11へ出力する。このとき、第2の電力変換装置5は、その出力電力が連系給電路11を上流側に逆潮流しないように出力電力を制限する。結果的に、負荷9の消費電力と第3の電力変換装置7の出力電力との差分である不足電力は、第2の電力変換装置5から連系給電路11に供給される放電電力(図2に「A4」で示す)によって賄われる。つまり、6時から20時までの間で、負荷9の消費電力が燃料電池6の発電電力を超えていれば、図3Cに示すように、燃料電池6および蓄電池4からの電力が連系給電路11を通って負荷9に供給され、太陽電池2の発電電力は電力系統8に逆潮流される。
 また、太陽電池2で十分な発電電力が得られる場合に、負荷9の消費電力が燃料電池6の発電電力と蓄電池4の放電電力との合計を超えるときには、不足分を賄うように、第1の電力変換装置3は太陽電池2の発電電力を負荷9に供給する。この場合、負荷9の消費電力が燃料電池6の発電電力と蓄電池4の放電電力と太陽電池2の発電電力との合計より小さく、太陽電池2に余剰電力が生じる場合、この余剰電力については第1の電力変換装置3が電力系統8に逆潮流して売電する。なお、負荷9の消費電力が燃料電池6の発電電力と蓄電池4の放電電力と太陽電池2の発電電力との合計を超えるときには、不足分は電力系統8から供給される買電電力で賄われる。
 上記の動作は、例えば、第2の電力変換装置5及び第3の電力変換装置7にそれぞれ適宜のタイマー(図示せず)を設け、制御部35,55,75の動作を適宜設定することで実現可能である。
 例えば、所定の第4時刻(図2の例では20時)になると、第1~第3の電力変換装置3,5,7の制御部35,55,75は、連系側開閉器36,56,76を遮断して連系給電路11への出力を停止する。所定の第1時刻(上記の例では0時)になると、第2の電力変換装置5の制御部55は、連系側開閉器56を接続し且つ充放電回路50を充電モードで動作させて、電力系統8からの買電電力を用いて蓄電池4を充電する。また第2の電力変換装置5は、所定の第2時刻(上記の例では3時)となるか、蓄電池4の残容量が所定の上限値を上回った場合(蓄電池4が満充電となった場合)には、連系側開閉器56を遮断して蓄電池4の充電を終了する。所定の第3時刻(上記の例では6時)になると、第3の電力変換装置7の制御部75は、連系側開閉器76を接続して連系給電路11への出力を開始する。このように、第4時刻から第3時刻までの期間(20時~6時)においては、負荷9の消費電力は、電力系統8からの買電電力で賄われる。
 第3時刻から第4時刻までの期間(6時~20時)においては、第3の電力変換装置7の制御部75は、第2の検出器15で検出される逆潮流電力がゼロとなる範囲で第3の電力変換装置7から連系給電路11への出力電力が極力大きくなるように、変換回路70の動作および連系側開閉器76の開閉を制御する。この期間(6時~20時)において、第2の電力変換装置5の制御部55は、第1の検出器14で検出される逆潮流電力がゼロとなる範囲で第2の電力変換装置5から連系給電路11への出力電力が極力大きくなるように、充放電回路50の動作および連系側開閉器56の開閉を制御する。なお、第3の電力変換装置7から電力を出力している状態において、負荷9での消費電力が急減したときには、第3の電力変換装置7から上流側への逆潮流が発生する可能性がある。第3の電力変換装置7の制御部75は、第2の検出器15で上流側への逆潮流を検出した場合、出力電流が小さくなるように変換回路70の動作を制御する(或いは制御部75は、連系側開閉器76を遮断する)。なお、負荷9での消費電力が急減したときには、第3の電力変換装置7が上記のように第2の検出器15を設けた箇所での逆潮流を防止していても、第1の検出器14を設けた箇所で逆潮流が発生してしまう可能性がある。第2の電力変換装置5は、電力を出力していて第1の検出器14で上流側への逆潮流を検出した場合には、出力電力が小さくなるように充放電回路50を制御する(或いは、充電モードに切り替える)。また、この期間(6時~20時)において、第1の電力変換装置3の制御部35は、連系給電路11の電圧を検出して、電力系統8へ電力を逆潮流させるように変換回路30の動作および連系側開閉器36の開閉を制御する。
 つまり、第1期間(図2の場合、0時~3時)では、第1の電力変換装置3は連系給電路11から遮断され、第2の電力変換装置5は充電モードで動作し、第3の電力変換装置7は連系給電路11から遮断される。
 第2期間(図2の場合、3時~6時)では、第1~第3の電力変換装置3,5,7は連系給電路11から遮断される。
 第3期間(図2の場合、6時~20時)では、第3の電力変換装置7の制御部75は、第2の検出器15で検出される逆潮流電力がゼロとなる範囲で第3の電力変換装置7から連系給電路11への出力電力が極力大きくなるように、変換回路70の動作および連系側開閉器36の開閉を制御する。第2の電力変換装置5の制御部55は、第1の検出器14で検出される逆潮流電力がゼロとなる範囲で第2の電力変換装置5から連系給電路11への出力電力が極力大きくなるように、充放電回路50の動作および連系側開閉器56の開閉を制御する。第1の電力変換装置3の制御部35は、連系給電路11の電圧を検出して、電力系統8へ電力を逆潮流させるように変換回路30の動作および連系側開閉器36の開閉を制御する。
 第4期間(図2の場合、20時~0時)では、第1~第3の電力変換装置3,5,7は連系給電路11から遮断される。
 以上説明した本実施形態の電力供給システム1によれば、連系給電路11の下流側に接続された第2および第3の電力変換装置5,7は、連系給電路11の上流側への逆潮流が防止されているので、負荷9に対して優先的に電力供給することになる。すなわち、需要家内の負荷9の消費電力には、第2および第3の電力変換装置5,7に接続された蓄電池4および燃料電池6からの出力が優先的に用いられる。したがって、第1の電力変換装置3は、太陽電池2の発電電力を電力系統8に逆潮流することで積極的に売電できる。また、負荷9の消費電力が燃料電池6の発電電力と蓄電池4の放電電力との合計を超えるときには、不足分を賄うように、第1の電力変換装置3は太陽電池2の発電電力を負荷9に供給することができる。
 また、本実施形態では、第3の電力変換装置7に接続された第2の発電装置として、電気エネルギーと熱エネルギーとを発生するコージェネレーションシステムを構成する燃料電池6を用いている。したがって、需要家内の負荷9に対して第3の電力変換装置7が最も優先的に電力供給することにより、需要家内で使用される電気エネルギーだけでなく熱エネルギーに関しても、効率的に供給することができる。一方で、売電可能な太陽電池2の発電電力は積極的に売電されるので、結果的に、この電力供給システムによれば光熱費の削減、CO2排出量の削減を図ることができる。
 しかも、第2の電力変換装置5は、燃料電池6の発電電力が負荷9の消費電力を下回るときには、蓄電池4に蓄えた電力を出力して不足分を補完するので、電力系統8から供給を受ける電力(買電電力)量を少なく抑えることができる。とくに、図2に例示した運用パターンにおいては、第2の電力変換装置5は、電気料金単価が安くなる深夜時間帯(0時~3時)に、電力系統8からの買電電力を用いて蓄電池4を充電するので、さらなる光熱費の削減に寄与する。
 また、上記構成によれば、夜間や悪天候時などで太陽電池2にて十分な発電電力が見込めないときでも、上述したように電気料金単価が安くなる深夜時間帯に充電した蓄電池4の放電電力と、燃料電池6の出力とで負荷9の消費電力を賄うことができる。したがって、電力系統8から供給を受ける電力(買電電力)量を少なく抑えることができ、光熱費を削減できる。
 ところで、本実施形態の他の構成として、電力供給システム1は、図4に示すように連系給電路11上に設けられた解列器81と、停電等の電力系統8の異常の有無を検知する異常検知部82とをさらに備えていてもよい。解列器81は、連系給電路11における第1の電力変換装置3との接続点よりも上流側に設けられている。また、本構成の電力供給システム1は、連系給電路11における解列器81よりもさらに上流側に電圧検出器83を備えている。本構成の異常検知部82は、電圧検出器83の出力を受け、停電等の電力系統8の異常の有無を検知する。異常検知部82は、電力系統8の異常を検知すると、電力系統8を遮断するよう解列器81を制御し、同時に第1~第3の電力変換装置3,5,7のうち一の電力変換装置(図4の例では第2または第3の電力変換装置5,7)に異常検知信号を送信する。
 異常検知信号を受信した電力変換装置(ここでは第2の電力変換装置5とする)は、連系給電路11への出力電圧を所定の目標値に維持する定電圧制御を行うように、制御部55の動作モードを切り替える。つまり、第2の電力変換装置5は、通常時には連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うが、異常検知部82からの異常検知信号を受信すると、定電圧制御に切り替わる。なお、定電圧制御時の目標値は可変であってもよい。
 一方、他の電力変換装置(ここでは第1および第3の電力変換装置3,7)は、電力系統8の異常時でも、連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を継続する。ここで、第1および第3の電力変換装置3,7は、連系給電路11上の基準となる電圧がなくなると電流制御による動作を継続できないが、連系給電路11には第2の電力変換装置5からの出力電圧が印加されている。そのため、第1および第3の電力変換装置3,7は、連系給電路11から電力系統8が遮断された状態で、第2の電力変換装置5の出力電圧を擬似系統(基準電圧)とみなし、電流制御により負荷9への電力供給を行うことになる。
 ここにおいて、電力系統8の異常時における第1~第3の各電力変換装置3,5,7の出力電力のバランスは、太陽電池2、燃料電池6の順にその発電電力を優先的に使用するように設定される。すなわち、第1の電力変換装置3は、最大電力点追従制御を行うことにより太陽電池2の発電電力を最大限取り出すように動作し、第3の電力変換装置7は、負荷9の消費電力からの太陽電池2の発電電力の不足分を燃料電池6の発電電力で賄うように動作する。また、第2の電力変換装置5は、太陽電池2および燃料電池6の発電電力が負荷9の消費電力を超えている場合には余剰電力で蓄電池4を充電し、負荷9の消費電力を下回る場合には不足電力を蓄電池4から放電するように動作する。
 この構成によれば、停電等の電力系統8の異常時、第1~第3の電力変換装置3,5,7のうち一の電力変換装置が異常検知信号を受けて定電圧制御に切り替わることにより、他の電力変換装置は電流制御での動作を継続することができる。そのため、電力系統8の異常時においても、蓄電池4の放電電力だけでなく太陽電池2および燃料電池6の発電電力も負荷9に供給することができ、負荷9への安定した電力供給が可能になる。さらに、太陽電池2の発電電力を優先的に使用することにより、燃料電池6での燃料消費を抑えることができる。
 また、電力系統8の異常時に、異常検知信号を受信して定電圧制御に切り替わる電力変換装置は、第1の電力変換装置3よりも出力電圧が安定している第2または第3の電力変換装置5,7であることが望ましい。言い換えれば、上記“一の電力変換装置”は、第2または第3の電力変換装置5,7のうちのいずれか一方で有ることが好ましい。つまり、第2または第3の電力変換装置5,7は、第1の電力変換装置3のように外部環境(日射量)により出力が停止するようなことなく、他の電力変換装置の電流制御の基準となる電圧を安定して出力することが可能である。とくに、第2の電力変換装置2においては、太陽電池2および燃料電池6の発電電力が負荷9の消費電力を超えている場合、余剰電力を蓄電池4に蓄えて電力不足時に使用することができるという利点もある。つまり、上記“一の電力変換装置”は、蓄電池4に接続された第2の電力変換装置5であることがより好ましい。
 さらに、以下では図5を参照して第1~第3の電力変換装置3,5,7の具体的な構成例を示す。図5は、第1の電力変換装置3におけるDCDCコンバータ33およびDCACコンバータ34の回路構成を示しているが、第2,3の電力変換装置5,7においても同様の構成を採用することができる。
 DCDCコンバータ33は、太陽電池2に接続されたインダクタ331およびスイッチング素子332の直列回路と、ダイオード333およびコンデンサ334の直列回路とを備えた昇圧チョッパ回路からなる。インダクタ331およびスイッチング素子332は、インダクタ331を太陽電池2の正極側、スイッチング素子332を太陽電池2の負極側とするように、太陽電池2に接続されている。ダイオード333およびコンデンサ334は、インダクタ331とスイッチング素子332との接続点にダイオード333のアノードを接続するように構成されている。また、コンデンサ334におけるダイオード333と反対側の端子が、太陽電池2の負極側とスイッチング素子332との接続点に接続されている。スイッチング素子332は、ここでは絶縁ゲートバイポーラトランジスタ(IGBT)からなり、逆並列にダイオード335が接続されている。さらにダイオード333にはIGBTからなる充電用スイッチング素子336が並列に接続されている。
 このDCDCコンバータ33は、太陽電池2から電力が供給されている状態で、制御部35がスイッチング素子332を高周波でオンオフ制御することにより、コンデンサ334の両端に昇圧後の直流電圧を発生する。なお、第2の電力変換装置5のDCDCコンバータ53は、蓄電池4の充電時(充電モード)には、スイッチング素子332をオフ、充電用スイッチング素子336を高周波でオンオフ制御することにより、DCACコンバータ54からの入力を受けて蓄電池4を充電する。
 DCACコンバータ34は、DCDCコンバータ33の出力端(コンデンサ334の両端)に4つのスイッチング素子341~344が接続されたフルブリッジ型のインバータ回路からなる。DCACコンバータ34は、スイッチング素子341,342の接続点と、スイッチング素子343,344の接続点との間に、インダクタ345、コンデンサ346、インダクタ347の直列回路からなるLCフィルタを有している。各スイッチング素子341~344は、ここではIGBTからなり、それぞれ逆並列にダイオード348が接続されている。
 このDCACコンバータ34は、DCDCコンバータ33から電力が供給されている状態で、制御部35がスイッチング素子341~344をオンオフ制御することにより、コンデンサ346の両端に交流電圧を発生する。DCACコンバータ34の出力端(コンデンサ346の両端)は、2点切りの連系側開閉器36を介して連系出力端31に接続されている。なお、第2の電力変換装置5のDCACコンバータ54は、蓄電池4の充電時(充電モード)においては、制御部55がスイッチング素子341~344をオンオフ制御することにより、DCDCコンバータ53に直流電圧を出力する。直流側(蓄電池4側)から系統側(連系給電路11側)へ出力するときとPWM(オンオフ)パターンを逆位相にすることで、スイッチング素子341~344のオンオフによって、系統側から直流側への電力変換(充電)を行うことができる。
 なお、上記実施形態では、第1~第3の電力変換装置3,5,7は1台ずつ設けられている例を示したが、この例に限らず、第1~第3の電力変換装置3,5,7は複数台ずつ設けられていてもよい。すなわち、電力供給システム1は、少なくとも一つの第1の電力変換装置3と、少なくとも一つの第2の電力変換装置5と、少なくとも一つの第3の電力変換装置7とを備える構成であってもよい。
 (実施形態2)
 本実施形態の電力供給システム1は、第2の電力変換装置5と第3の電力変換装置7とが通信可能に構成されている点で実施形態1の電力供給システム1と相違する。以下、実施形態1と同様の構成については共通の符号を付して適宜説明を省略する。
 本実施形態では、図6に示すように第2の電力変換装置5と第3の電力変換装置7とが通信路16にて接続されており、第2の電力変換装置5の制御部55と第3の電力変換装置7の制御部75とは、通信路16を介して通信可能に構成されている。なお、第2の電力変換装置5と第3の電力変換装置7との間の通信は、有線に限らず無線式であってもよいし、あるいは連系給電路11を通信路として用いてもよい。
 ここにおいて、第2の電力変換装置5と第3の電力変換装置7とは、制御部55,75同士が互いに通信を行うことにより、連系給電路11に対する各々の出力電力(第2の電力変換装置5では蓄電池4の充電時の入力電力も含む)を調節する。第2の検出器15(図1参照)は省略されており、第3の電力変換装置7の制御部75は、第2の電力変換装置5の制御部55と連携して、連系給電路11における第1の検出器14を設けた箇所で上流側への逆潮流がゼロとなるように目標値を設定する。
 すなわち、両制御部55,75は、連系給電路11における第1の検出器14を設けた箇所での逆潮流がゼロとなる範囲で、連系給電路11への出力電力が極力大きくなるように、第2および第3の電力変換装置5,7の出力電力の上限を決定する。このとき、両制御部55,75は、第2および第3の電力変換装置5,7から連系給電路11に供給される電力の合計が、負荷9の消費電力を超えないように第2および第3の電力変換装置5,7の出力電力の上限を制限すればよい。
 そのため、両制御部55,75は、蓄電池4の残容量を検出して空き容量がある場合には、蓄電池4の充電用に第2の電力変換装置5で使用される電力分を負荷9の消費電力に上乗せして、第3の電力変換装置7の出力電力の上限を決定する。つまり、第3の電力変換装置7から連系給電路11への出力電力が負荷9の消費電力を超えている場合、その余剰電力が連系給電路11を上流側へ逆潮流することがある。このとき、第3の電力変換装置7から逆潮流された余剰電力を第2の電力変換装置5が蓄電池4の充電に使うことにより、連系給電路11における第1の検出器14を設けた箇所においては上流側に逆潮流が生じることを防止できる。要するに、本実施形態では、第3の電力変換装置7の出力電力について、連系給電路11を上流側に逆潮流することが完全に禁止されるのではなく、蓄電池4の充電に使用される場合には逆潮流も許容される。
 次に、本実施形態の電力供給システム1の動作について、電力供給システム1の運用パターンの一例を示して説明する。基本的な動作は、実施形態1において図2および図3に示した運用パターンと同様である。
 実施形態1と異なる点としては、蓄電池4に空き容量があれば、負荷9の消費電力が一時的に減少する際に、第2の電力変換装置5が消費電力の減少分を蓄電池4の充電に用いることにより、第3の電力変換装置7の出力電力を一定に保つことができる。つまり、第2の電力変換装置5は燃料電池6の余剰電力を蓄電池4の充電に用いることにより、第3の電力変換装置7の出力電力を変動させることなく、負荷9の消費電力の変動に対応できる。
 また、毎日決まった時間帯(たとえば深夜時間帯)に電力系統8からの電力で蓄電池4を充電する運用パターンを採用している場合、蓄電池4の残容量が過多であれば、蓄電池4の放電電力を積極的に使うようにしてもよい。たとえば、第3の電力変換装置7が所定の時刻よりも燃料電池6の発電停止のタイミングを早め、且つ、第2の電力変換装置5が蓄電池4の放電電力を連系給電路11に出力することで燃料電池6の発電停止後の負荷9の消費電力を賄う。
 以上説明した本実施形態の電力供給システム1によれば、蓄電池4と燃料電池6とが組み合わされて使用されることになり、蓄電池4を負荷9のバッファとして用いることができる。これにより、燃料電池6を比較的効率のよい出力領域で継続的に動作させることができ、電力供給システム1全体としての効率の向上を図ることができる。
 また、本実施形態では、連系給電路11における第2の電力変換装置5、第3の電力変換装置7の順番が逆であってもよい。すなわち、上述の例では、第2の電力変換装置5と第3の電力変換装置7とは、第2の電力変換装置5が上流側となるように連系給電路11に接続されているが、第3の電力変換装置7が上流側であってもよい。この場合、第1~第3の電力変換装置3,5,7は、上流側から第1の電力変換装置3、第3の電力変換装置7、第2の電力変換装置5の順で連系給電路11に接続され、第1の検出器14は第1の電力変換装置3と第3の電力変換装置7との間に設けられる。この構成でも、両制御部55,75は、連系給電路11における第1の検出器14を設けた箇所での逆潮流がゼロとなる範囲で、連系給電路11への出力電力が極力大きくなるように、第2および第3の電力変換装置5,7の出力電力の上限を決定する。
 その他の構成および機能は実施形態1と同様である。
 (実施形態3)
 本実施形態の電力供給システム1は、図7に示すように、電力系統8から切り離された自立給電路12が連系給電路11とは別に設けられている点で実施形態1の電力供給システム1と相違する。以下、実施形態1と同様の構成については共通の符号を付して適宜説明を省略する。
 図7の例では、第1~第3の電力変換装置3,5,7は、いずれも電力系統8と連系する連系運転と、電力系統8から切り離される自立運転との2つの運転状態を切替可能に構成されている。さらに、第1の電力変換装置3は、自立運転時に電力の出力端になる自立出力端32を連系出力端31とは別に有している。同様に、第2の電力変換装置5は、自立運転時に電力の出力端になる自立出力端52を連系出力端51とは別に有し、第3の電力変換装置7は、自立運転時に電力の出力端になる自立出力端72を連系出力端71とは別に有している。
 第1~第3の電力変換装置3,5,7は、いずれも自立給電路12に自立出力端32,52,72を接続しており、自立給電路12を介して自立出力端32,52,72同士が接続されている。また、各電力変換装置3,5,7はそれぞれ自立側開閉器(図示せず)を有している。各DCACコンバータ34,54,74の交流電力の出力端子は、連系側開閉器36,56,76を介して連系出力端31,51,71に接続され、自立側開閉器を介して自立出力端32,52,72に接続されている。各制御部35,55,75は、連系運転時には連系側開閉器36,56,76を接続して自立側開閉器を遮断し、自立運転時には自立側開閉器を接続して連系側開閉器36,56,76を遮断する。
 第1~第3の電力変換装置3,5,7は、停電等の電力系統8の異常の有無を検知する異常検知部(図示せず)を有しており、異常検知部の検知結果に応じて連系運転・自立運転を自動的に切り替える。つまり、各制御部35,55,75は、電力系統8の正常時には連系運転を選択し、停電等の電力系統8の異常時に自立運転に切り替える。
 連系給電路11と自立給電路12とのそれぞれには負荷9が接続される。図7の例では、連系給電路11および自立給電路12と負荷9との間には、負荷9の接続先を連系給電路11と自立給電路12とで切り替える切替器13が設けられている。これにより、連系運転時には負荷9を連系給電路11に接続し、自立運転時には負荷9を自立給電路12に接続するように切替器13を切り替えることによって、負荷9をつなぎ替える手間を省くことができる。
 切替部13は、人の操作により手動で切り替わる構成であってもよいが、本実施形態では人の操作によらずに自動的に切り替わる構成を採用する。具体的には、切替部13はリレーからなり、連系給電路11を通して電力系統8から供給される電力を利用してコイルが励磁されることにより、負荷9の接続先を連系給電路11と自立給電路12とで切り替える。つまり、切替部13は、電力系統8の正常時には、電力系統8からの供給電力によりコイルが励磁されて負荷9を連系給電路11に接続し、停電等の電力系統8の異常時には負荷9を自立給電路12に接続する。
 なお、自立給電路12は、電気機器からなる負荷9に直接接続されることは必須ではなく、負荷9を着脱可能に接続可能なコンセント(図示せず)に接続されてもよい。また、切替器13が省略され、負荷9およびコンセントは連系給電路11と自立給電路12とのそれぞれに個別に接続されていてもよい。この場合、連系給電路11には各電力変換装置の連系運転時に使用可能なコンセントが接続され、自立給電路12には各電力変換装置の自立運転時に使用可能な自立専用コンセントが接続される。
 ここにおいて、本実施形態では、第1~第3の電力変換装置3,5,7のうち1台の電力変換装置(第1~第3の電力変換装置3,5,7のうち一の電力変換装置;ここでは第2の電力変換装置5とする)は、自立運転時に、自立給電路12へ出力電圧を所定の目標値に維持する定電圧制御を行う。他の電力変換装置(ここでは第1および第3の電力変換装置3,7)は、自立運転時に、自立給電路12の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行う。なお、定電圧制御時の目標値は可変であってもよい。
 すなわち、第2の電力変換装置5は、電力系統8の異常を検知すると、制御部55の動作モードを電流制御から定電圧制御に切り替える。つまり、第2の電力変換装置5は、連系運転時には連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うが、電力系統8の異常を検知して自立運転に切り替わると、自動的に定電圧制御に切り替わる。
 一方、第1および第3の電力変換装置3,7は、電力系統8の異常を検知して自立運転に切り替わると、自立給電路12の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行う。ここで、自立給電路12には第2の電力変換装置5からの出力電圧が印加されている。そのため、第1および第3の電力変換装置3,7は、第2の電力変換装置5の出力電圧を擬似系統(基準電圧)とみなし、電流制御により負荷9への電力供給を行うことになる。
 この構成によれば、停電等の電力系統8の異常時、第1~第3の電力変換装置3,5,7のうち一の電力変換装置が定電圧制御に切り替わることにより、他の電力変換装置は電流制御での動作を継続することができる。そのため、電力系統8の異常時においても、蓄電池4の放電電力だけでなく太陽電池2および燃料電池6の発電電力も負荷9に供給することができ、負荷9への安定した電力供給が可能になる。さらに、電力変換装置3,5,7は、電力系統8の異常を検知する機能(異常検知部)を有するので、別途、電力系統8の異常の有無を検知する装置を設ける必要がなく、システム構成の簡略化を図ることができる。なお、上記“一の電力変換装置(自立運転時に定電圧制御を行う電力変換装置)”は、出力電圧が安定している第2または第3の電力変換装置5,7のうちのいずれか一方で有ることが好ましい。特に、上記“一の電力変換装置”は、蓄電池4に接続された第2の電力変換装置5であることが好ましい。
 また、連系運転時と自立運転時とで負荷9の接続先を連系給電路11と自立給電路12とで切り替える切替部13が設けられているので、負荷9をつなぎ替える手間を省くことができる。しかも、切替部13は、電力系統8の異常の有無に応じて負荷9の接続先を自動的に切り替えるので、人が切替部13を切り替える手間もかからない。なお、切替部13は、第1~第3の電力変換装置3,5,7のうち1台の電力変換装置(ここでは第2の電力変換装置5とする)からの切替信号を受信し、負荷9の接続先を連系給電路11と自立給電路12とで切り替える構成であってもよい。
 ここにおいて、本実施形態の他の例として、第1~第3の電力変換装置3,5,7は、一部の電力変換装置(ここでは第2の電力変換装置5とする)のみが連系運転と自立運転との2つの運転状態を切替可能に構成されていてもよい。この場合、連系運転と自立運転との切替機能を持たない電力変換装置(ここでは第1および第3の電力変換装置3,7)は、図8に示すように外部切替器としてのリレー17,18を介して、連系給電路11および自立給電路12に接続される。外部切替器としてのリレー17,18は、第2の電力変換装置5により制御され、第1および第3の電力変換装置3,7の連系出力端31の接続先を連系給電路11と自立給電路12とで切り替える。
 図8の例では、連系運転と自立運転とを切替可能な第2の電力変換装置5は、自立運転時に、自立給電路12へ出力電圧を所定の目標値に維持する定電圧制御を行う。他の電力変換装置(ここでは第1および第3の電力変換装置3,7)は、連系給電路11または自立給電路12の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行う。なお、定電圧制御時の目標値は可変であってもよい。
 すなわち、第2の電力変換装置5は、電力系統8の異常を検知すると、制御部55の動作モードを電流制御から定電圧制御に切り替える。つまり、第2の電力変換装置5は、連系運転時には連系給電路11の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うが、電力系統8の異常を検知して自立運転に切り替わると、自動的に定電圧制御に切り替わる。このとき、第2の電力変換装置5は、外部切替器としてのリレー17,18を制御して、第1および第3の電力変換装置3,7の連系出力端31の接続先を連系給電路11から自立給電路12へ切り替える。
 一方、第1および第3の電力変換装置3,7は、自立給電路12の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行う。ここで、自立給電路12には第2の電力変換装置5からの出力電圧が印加されている。そのため、第1および第3の電力変換装置3,7は、第2の電力変換装置5の出力電圧を擬似系統(基準電圧)とみなし、電流制御により負荷9への電力供給を行うことになる。
 この構成によれば、停電等の電力系統8の異常時、運転状態を切替可能な電力変換装置と切替不可能な電力変換装置とを組み合わせて動作させることができる。そのため、電力系統8の異常時においても、蓄電池4の放電電力だけでなく太陽電池2および燃料電池6の発電電力も負荷9に供給することができ、負荷9への安定した電力供給が可能になる。なお、上記“一の電力変換装置(連系運転と自立運転との切替機能を有する電力変換装置)”は、出力電圧が安定している第2または第3の電力変換装置5,7のうちのいずれか一方で有ることが好ましい。特に、上記“一の電力変換装置”は、蓄電池4に接続された第2の電力変換装置5であることが好ましい。
 ところで、電力供給システム1は、連系給電路11または自立給電路12に負荷9が複数接続されている場合、電力供給の対象となる負荷9を選択するための構成を備えていてもよい。
 すなわち、図9Aに示すように、連系給電路11に複数(ここでは3つ)の負荷91~93が接続されている場合、連系給電路11と各負荷91~93との間には、負荷遮断器113が挿入される。さらに、この電力供給システム1は、複数の負荷91~93への供給電力を検出するための電流センサ111と、負荷91~93への供給電力に応じて負荷遮断器113を制御する負荷選択部112とを備えている。ここで、負荷選択部112は、複数の負荷91~93について予め設定された優先順位を記憶する記憶部(図示せず)を有している。
 図9Aの構成では、負荷選択部112は、電流センサ111で検出される複数の負荷91~93への供給電力(合計)を監視し、この供給電力が所定の閾値を超えた場合に、優先順位の低い負荷91~93から順に負荷遮断器113を遮断する。たとえば、負荷91,92,93の順に高くなるように優先順位が設定されている場合、負荷選択部112は、供給電力が閾値を超えるとまず優先順位の最も低い負荷91が接続された負荷遮断器113を遮断し、負荷91への電力供給を停止する。この状態でもなお供給電力が閾値を超えていると、負荷選択部112は次に優先順位の低い負荷92が接続された負荷遮断器113を遮断し、負荷92への電力供給を停止する。
 また、他の例として、電力供給システム1は、負荷選択部112が第1~第3の電力変換装置3,5,7に内蔵され、図9Bに示すように第1~第3の電力変換装置3,5,7からの制御信号により負荷遮断部113が制御されるように構成されていてもよい。図9Bの構成では、第1~第3の電力変換装置3,5,7内の負荷選択部は、各電力変換装置3,5,7の出力電力と負荷9への供給電力(合計)との両方を監視している。負荷選択部は、出力電力と供給電力との差分が所定の閾値以下になると、優先順位の低い負荷91~93から順に負荷遮断器113を遮断する。
 上述したように、電力供給の対象となる負荷9を選択するための構成が設けられていることにより、電力供給システム1は、自立運転時等で負荷9に供給可能な電力の上限が限られている場合に、優先順位の高い負荷9に対して安定した電力供給が可能になる。
 その他の構成および機能は実施形態1と同様である。また、本実施形態は、第2の電力変換装置5と第3の電力変換装置7とが通信可能な実施形態2と組み合わされてもよい。

Claims (9)

  1.  電力系統へ逆潮流可能な電力を発生させる第1の発電装置に接続され、当該第1の発電装置の発電電力の電力変換を行う第1の電力変換装置と、蓄電池に接続され当該蓄電池の充放電を行う第2の電力変換装置と、前記電力系統へ逆潮流不可能な電力を発生させる第2の発電装置に接続され、当該第2の発電装置の発電電力の電力変換を行う第3の電力変換装置とを備え、上流に前記電力系統が接続された連系給電路の下流に接続されている負荷に電力供給する電力供給システムであって、
     前記第1~第3の電力変換装置は、前記連系給電路に対して前記第1の電力変換装置が最上流側となるように接続されており、
     前記電力供給システムは、前記連系給電路における前記第1の電力変換装置の接続点と前記第2および前記第3の電力変換装置のうち前記上流側に接続された一方の電力変換装置の接続点との間に設けられ、前記連系給電路を前記上流側に流れる逆潮流電力を検出する第1の検出器を備えており、
     前記第2の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、前記第3の電力変換装置は、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記連系給電路への出力電力を制御することを特徴とする電力供給システム。
  2.  前記第2および前記第3の電力変換装置は、前記連系給電路に対して前記第2の電力変換装置が前記上流側となるように接続されており、
     前記電力供給システムは、前記連系給電路における前記第2の電力変換装置の接続点と前記第3の電力変換装置の接続点との間に設けられ、前記連系給電路を前記上流側に流れる逆潮流電力を検出する第2の検出器をさらに備え、
     前記第2の電力変換装置は、前記第1の検出器に接続され、当該第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、
     前記第3の電力変換装置は、前記第2の検出器に接続され、当該第2の検出器で検出される逆潮流電力がゼロとなるように前記連系給電路への出力電力を制御することを特徴とする請求項1に記載の電力供給システム。
  3.  前記第2および前記第3の電力変換装置のうち前記上流側に接続された一方の電力変換装置は、前記第1の検出器に接続され、
     前記第2および前記第3の電力変換装置は、互いに通信することにより、前記第1の検出器で検出される逆潮流電力がゼロとなるように前記蓄電池の充放電を制御し、且つ前記第3の電力変換装置から前記連系給電路への出力電力を制御することを特徴とする請求項1に記載の電力供給システム。
  4.  前記第2の発電装置は、電気エネルギーと熱エネルギーとを同時に発生するコージェネレーションシステムであることを特徴とする請求項1~3のいずれか1項に記載の電力供給システム。
  5.  前記第1の発電装置は太陽電池であって、前記第2の発電装置は燃料電池であり、
     前記第1の電力変換装置は、前記太陽電池の発電電力の余剰分を前記電力系統に逆潮流することを特徴とする請求項1~4のいずれか1項に記載の電力供給システム。
  6.  前記電力供給システムは、前記連系給電路における前記第1の電力変換装置との接続点よりも上流側に設けられた解列器と、前記電力系統の異常を検知すると前記解列器を遮断し、且つ前記第1~第3の電力変換装置のうち一の電力変換装置に異常検知信号を送信する異常検知部とをさらに備え、
     前記一の電力変換装置は、前記異常検知信号を受信すると前記連系給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、他の電力変換装置は、前記連系給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことを特徴とする請求項1~5のいずれか1項に記載の電力供給システム。
  7.  前記第1~第3の電力変換装置は、いずれも前記連系給電路を介して前記負荷に電力供給する連系運転と、前記電力系統から切り離された自立給電路を介して前記負荷に電力供給する自立運転とを切替可能であって、
     前記第1~第3の電力変換装置のうち一の電力変換装置は、前記自立運転時に前記自立給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、他の電力変換装置は、前記自立運転時に前記自立給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことを特徴とする請求項1~5のいずれか1項に記載の電力供給システム。
  8.  前記第1~第3の電力変換装置のうち一の電力変換装置は、前記連系給電路を介して前記負荷に電力供給する連系運転と、前記電力系統から切り離された自立給電路を介して前記負荷に電力供給する自立運転とを切替可能であって、他の電力変換装置は、接続先を前記連系給電路と前記自立給電路とで切り替える外部切替器を介して前記連系給電路および前記自立給電路に接続されており、
     前記一の電力変換装置は、前記自立運転時に前記自立給電路への出力電圧を所定の目標値に維持する定電圧制御を行い、且つ前記外部切替器を前記自立給電路側に切り替え、前記他の電力変換装置は、前記自立給電路の電圧を検出し当該電圧に合わせて電流を出力する電流制御を行うことを特徴とする請求項1~5のいずれか1項に記載の電力供給システム。
  9.  前記負荷は複数あって、
     前記複数の前記負荷の各々への電力供給路に挿入された負荷遮断器と、前記複数の前記負荷について優先順位を記憶する記憶部と、前記複数の前記負荷への供給電力に応じて前記優先順位の低い前記負荷から順に前記負荷遮断器を遮断する負荷選択部とをさらに備えることを特徴とする請求項1~8のいずれか1項に記載の電力供給システム。
PCT/JP2012/072842 2011-12-15 2012-09-07 電力供給システム WO2013088798A1 (ja)

Priority Applications (2)

Application Number Priority Date Filing Date Title
EP12858275.6A EP2793345B1 (en) 2011-12-15 2012-09-07 Electric power supply system
ES12858275.6T ES2612653T3 (es) 2011-12-15 2012-09-07 Sistema de suministro de energía eléctrica

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2011275023A JP5914821B2 (ja) 2011-12-15 2011-12-15 電力供給システム
JP2011-275023 2011-12-15

Publications (1)

Publication Number Publication Date
WO2013088798A1 true WO2013088798A1 (ja) 2013-06-20

Family

ID=48612257

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2012/072842 WO2013088798A1 (ja) 2011-12-15 2012-09-07 電力供給システム

Country Status (4)

Country Link
EP (1) EP2793345B1 (ja)
JP (1) JP5914821B2 (ja)
ES (1) ES2612653T3 (ja)
WO (1) WO2013088798A1 (ja)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015019621A1 (ja) * 2013-08-08 2015-02-12 パナソニックIpマネジメント株式会社 電力供給システム、電力変換装置、分電盤
WO2015029431A1 (ja) * 2013-08-30 2015-03-05 京セラ株式会社 分散電源システム、パワーコンディショナ
WO2015083373A1 (ja) * 2013-12-02 2015-06-11 京セラ株式会社 電力制御システム、電力制御装置及び電力制御システムの制御方法
WO2016024406A1 (ja) * 2014-08-11 2016-02-18 京セラ株式会社 電力供給機器、電力供給システム、および電力供給方法
EP3095172A4 (en) * 2014-01-13 2017-12-06 Rogers, Gregory Neville Zero export relay
EP3168952A4 (en) * 2014-07-10 2018-03-14 Kyocera Corporation Control method for power generation system, power generation system, and power generation device
CN115066819A (zh) * 2020-02-10 2022-09-16 维谛公司 与一个或多个不同的公用事业代理一起使用的电力供应管理系统和方法

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5933318B2 (ja) * 2012-04-09 2016-06-08 トヨタホーム株式会社 建物の電力制御システム及び居住エリアの電力管理システム
JP6096635B2 (ja) * 2012-11-16 2017-03-15 本田技研工業株式会社 コージェネレーション装置
JP6000144B2 (ja) * 2013-01-29 2016-09-28 大阪瓦斯株式会社 分散型電源システム
JP6144616B2 (ja) * 2013-12-24 2017-06-07 京セラ株式会社 電力制御装置、電力制御システム、および電力制御方法
JP6655805B2 (ja) * 2014-02-07 2020-02-26 パナソニックIpマネジメント株式会社 エネルギー管理装置、およびエネルギー管理方法
US10243367B2 (en) 2014-05-19 2019-03-26 Kyocera Corporation Power supply system, control method of power supply system, and power supply apparatus
JP6663632B2 (ja) * 2014-05-26 2020-03-13 大和ハウス工業株式会社 電力供給システム
JP6452331B2 (ja) * 2014-07-10 2019-01-16 京セラ株式会社 発電システムの制御方法、発電システム、及び発電装置
JP6416533B2 (ja) * 2014-07-29 2018-10-31 京セラ株式会社 電力制御システムの制御方法、電力制御システム、及び電力制御装置
JP6299510B2 (ja) * 2014-07-31 2018-03-28 株式会社デンソー 電力供給システム
JP6299514B2 (ja) * 2014-08-01 2018-03-28 株式会社デンソー 電力供給システム
JP6453581B2 (ja) * 2014-08-11 2019-01-16 京セラ株式会社 電力供給機器、電力供給システム、および電力供給方法
JP6475945B2 (ja) * 2014-09-26 2019-02-27 京セラ株式会社 電力供給機器、電力供給方法、及び電力供給システム
JP6415259B2 (ja) * 2014-11-14 2018-10-31 シャープ株式会社 パワーコンディショナ、およびその制御装置
JP6415260B2 (ja) * 2014-11-14 2018-10-31 シャープ株式会社 パワーコンディショナ、その制御装置および電力システム
JP6472646B2 (ja) * 2014-11-27 2019-02-20 京セラ株式会社 電力供給システム、電力供給機器及び電力供給システムの制御方法
US20160190808A1 (en) * 2014-12-29 2016-06-30 Lg Cns Co., Ltd. Method and system for managing electric power
US20180026446A1 (en) * 2015-02-06 2018-01-25 United Technologies Corporation Seamless transition between grid connected and islanded modes
JP6423746B2 (ja) * 2015-03-20 2018-11-14 積水化学工業株式会社 充放電システム
JP2017028883A (ja) * 2015-07-23 2017-02-02 京セラ株式会社 蓄電システム及び蓄電池制御方法
US9793755B2 (en) * 2015-07-28 2017-10-17 Garrity Power Services Llc Uninterruptible power supply and method for managing power flow in a grid-tied photovoltaic system
JP2017221082A (ja) * 2016-06-10 2017-12-14 住友電気工業株式会社 蓄電システム
JP6795968B2 (ja) * 2016-12-22 2020-12-02 大和ハウス工業株式会社 電力供給システム
WO2020047227A1 (en) * 2018-08-30 2020-03-05 Bloom Energy Corporation Power source communication with downstream device by changing output voltage on a power bus
JP7438667B2 (ja) * 2019-03-20 2024-02-27 大和ハウス工業株式会社 電力供給システム
JP7438668B2 (ja) * 2019-03-20 2024-02-27 大和ハウス工業株式会社 電力供給システム
WO2021070146A1 (en) * 2019-10-11 2021-04-15 Westhill Innovation Inc. Solar power distribution and control system for movable storage containers
US11258294B2 (en) 2019-11-19 2022-02-22 Bloom Energy Corporation Microgrid with power equalizer bus and method of operating same
KR20230052034A (ko) * 2021-10-12 2023-04-19 엘지전자 주식회사 에너지 저장장치

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09135577A (ja) 1995-11-06 1997-05-20 Omron Corp パワーコンディショナおよび分散型電源システム
JP2002247765A (ja) * 2001-02-16 2002-08-30 Yanmar Diesel Engine Co Ltd パワーコンディショナの運転制御装置とその運転制御方法
JP2003087978A (ja) * 2001-09-07 2003-03-20 Toshiba Corp 発電装置、分電盤及びそれらを用いた電源供給システム
WO2008041311A1 (fr) * 2006-10-02 2008-04-10 Otaki Gas Corporation Système de génération d'alimentation électrique hybride
JP2008278700A (ja) * 2007-05-02 2008-11-13 Ntt Facilities Inc 分散型発電装置及び電力品質維持制御方法

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4837632B2 (ja) * 2007-07-24 2011-12-14 フジプレアム株式会社 電力貯蔵型太陽光発電システム
JP4856692B2 (ja) * 2008-11-28 2012-01-18 株式会社正興電機製作所 電力供給システム及び電力切替装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09135577A (ja) 1995-11-06 1997-05-20 Omron Corp パワーコンディショナおよび分散型電源システム
JP2002247765A (ja) * 2001-02-16 2002-08-30 Yanmar Diesel Engine Co Ltd パワーコンディショナの運転制御装置とその運転制御方法
JP2003087978A (ja) * 2001-09-07 2003-03-20 Toshiba Corp 発電装置、分電盤及びそれらを用いた電源供給システム
WO2008041311A1 (fr) * 2006-10-02 2008-04-10 Otaki Gas Corporation Système de génération d'alimentation électrique hybride
JP2008278700A (ja) * 2007-05-02 2008-11-13 Ntt Facilities Inc 分散型発電装置及び電力品質維持制御方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP2793345A4

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015035893A (ja) * 2013-08-08 2015-02-19 パナソニックIpマネジメント株式会社 電力供給システム、電力変換装置、分電盤
WO2015019621A1 (ja) * 2013-08-08 2015-02-12 パナソニックIpマネジメント株式会社 電力供給システム、電力変換装置、分電盤
EP3032682A4 (en) * 2013-08-08 2016-07-20 Panasonic Ip Man Co Ltd POWER SUPPLY SYSTEM, ELECTRIC CONVERSION DEVICE, AND DISTRIBUTION BOARD
WO2015029431A1 (ja) * 2013-08-30 2015-03-05 京セラ株式会社 分散電源システム、パワーコンディショナ
US10079491B2 (en) 2013-08-30 2018-09-18 Kyocera Corporation Dispersed power supply system and power conditioner
WO2015083373A1 (ja) * 2013-12-02 2015-06-11 京セラ株式会社 電力制御システム、電力制御装置及び電力制御システムの制御方法
JPWO2015083373A1 (ja) * 2013-12-02 2017-03-16 京セラ株式会社 電力制御システム、電力制御装置及び電力制御システムの制御方法
EP3095172A4 (en) * 2014-01-13 2017-12-06 Rogers, Gregory Neville Zero export relay
EP3168952A4 (en) * 2014-07-10 2018-03-14 Kyocera Corporation Control method for power generation system, power generation system, and power generation device
US10566796B2 (en) 2014-07-10 2020-02-18 Kyocera Corporation Control method of power generation system, power generation system, and power generation apparatus
WO2016024406A1 (ja) * 2014-08-11 2016-02-18 京セラ株式会社 電力供給機器、電力供給システム、および電力供給方法
EP3182548A4 (en) * 2014-08-11 2018-02-21 Kyocera Corporation Power supply device, power supply system and power supply method
US10541537B2 (en) 2014-08-11 2020-01-21 Kyocera Corporation Power supply apparatus, power supply system, and power supply method
JPWO2016024406A1 (ja) * 2014-08-11 2017-04-27 京セラ株式会社 電力供給機器、電力供給システム、および電力供給方法
CN115066819A (zh) * 2020-02-10 2022-09-16 维谛公司 与一个或多个不同的公用事业代理一起使用的电力供应管理系统和方法
CN115066819B (zh) * 2020-02-10 2024-05-28 维谛公司 与一个或多个不同的公用事业代理一起使用的电力供应管理系统和方法

Also Published As

Publication number Publication date
EP2793345A4 (en) 2015-04-29
JP5914821B2 (ja) 2016-05-11
EP2793345B1 (en) 2016-11-02
ES2612653T3 (es) 2017-05-18
EP2793345A1 (en) 2014-10-22
JP2013126339A (ja) 2013-06-24

Similar Documents

Publication Publication Date Title
WO2013088798A1 (ja) 電力供給システム
JP5905557B2 (ja) パワーコンディショナシステム及び蓄電パワーコンディショナ
JP5903622B2 (ja) 電力供給システムおよび充放電用パワーコンディショナ
US8587251B2 (en) Switching circuit, control apparatus, and power generation system
JP2011200096A (ja) 蓄電システム
JP6174410B2 (ja) 電力制御装置、電力制御方法、および電力制御システム
JP6158562B2 (ja) 電力変換装置、制御システム、及び制御方法
JP2011211885A (ja) 蓄電システム
WO2011152249A1 (ja) 系統連系システム、及び分配器
JP5756903B2 (ja) 配電システム
US20130257152A1 (en) Dc power supply system
KR101020789B1 (ko) 무정전 기능을 가진 계통연계형 하이브리드 태양광 발전 시스템
WO2011039588A1 (ja) 配電装置
JP2014131422A (ja) 電力供給システムおよびパワーコンディショナ
JP2014121151A (ja) 蓄電システム及び電力供給システム
JP6677186B2 (ja) 直流給電システム
JP6385207B2 (ja) 蓄電池システム
WO2012002449A1 (ja) エネルギー管理システム
JP2013090456A (ja) パワーコンディショナ

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12858275

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

REEP Request for entry into the european phase

Ref document number: 2012858275

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2012858275

Country of ref document: EP