EP3757264B1 - Method for operating a partially or fully automatic spinning machine for creating cross-wound spools - Google Patents

Method for operating a partially or fully automatic spinning machine for creating cross-wound spools Download PDF

Info

Publication number
EP3757264B1
EP3757264B1 EP20180356.6A EP20180356A EP3757264B1 EP 3757264 B1 EP3757264 B1 EP 3757264B1 EP 20180356 A EP20180356 A EP 20180356A EP 3757264 B1 EP3757264 B1 EP 3757264B1
Authority
EP
European Patent Office
Prior art keywords
batch
manual maintenance
maintenance activity
displayed
workstation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP20180356.6A
Other languages
German (de)
French (fr)
Other versions
EP3757264A1 (en
Inventor
Bernd Bahlmann
Romeo Pohn
Adalbert Stephan
Martin Zipperer
Franz Hüttinger
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RIETER AG
Original Assignee
Maschinenfabrik Rieter AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maschinenfabrik Rieter AG filed Critical Maschinenfabrik Rieter AG
Publication of EP3757264A1 publication Critical patent/EP3757264A1/en
Application granted granted Critical
Publication of EP3757264B1 publication Critical patent/EP3757264B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • DTEXTILES; PAPER
    • D01NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
    • D01HSPINNING OR TWISTING
    • D01H13/00Other common constructional features, details or accessories
    • D01H13/14Warning or safety devices, e.g. automatic fault detectors, stop motions ; Monitoring the entanglement of slivers in drafting arrangements
    • D01H13/16Warning or safety devices, e.g. automatic fault detectors, stop motions ; Monitoring the entanglement of slivers in drafting arrangements responsive to reduction in material tension, failure of supply, or breakage, of material
    • D01H13/18Warning or safety devices, e.g. automatic fault detectors, stop motions ; Monitoring the entanglement of slivers in drafting arrangements responsive to reduction in material tension, failure of supply, or breakage, of material stopping supply only
    • DTEXTILES; PAPER
    • D01NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
    • D01HSPINNING OR TWISTING
    • D01H13/00Other common constructional features, details or accessories
    • D01H13/14Warning or safety devices, e.g. automatic fault detectors, stop motions ; Monitoring the entanglement of slivers in drafting arrangements
    • DTEXTILES; PAPER
    • D01NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
    • D01HSPINNING OR TWISTING
    • D01H4/00Open-end spinning machines or arrangements for imparting twist to independently moving fibres separated from slivers; Piecing arrangements therefor; Covering endless core threads with fibres by open-end spinning techniques
    • D01H4/42Control of driving or stopping
    • D01H4/44Control of driving or stopping in rotor spinning
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H54/00Winding, coiling, or depositing filamentary material
    • B65H54/02Winding and traversing material on to reels, bobbins, tubes, or like package cores or formers
    • B65H54/06Winding and traversing material on to reels, bobbins, tubes, or like package cores or formers for making cross-wound packages
    • DTEXTILES; PAPER
    • D01NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
    • D01HSPINNING OR TWISTING
    • D01H4/00Open-end spinning machines or arrangements for imparting twist to independently moving fibres separated from slivers; Piecing arrangements therefor; Covering endless core threads with fibres by open-end spinning techniques
    • D01H4/42Control of driving or stopping
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H2701/00Handled material; Storage means
    • B65H2701/30Handled filamentary material
    • B65H2701/31Textiles threads or artificial strands of filaments

Definitions

  • the present invention relates to a method for operating a partially or fully automatic spinning machine for producing cross-wound bobbins, in particular an open-end rotor spinning machine, with a plurality of similar, at least partially self-sufficient work stations arranged next to one another, each of the work stations having a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin.
  • a spinning device for producing a thread
  • a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin.
  • Partially or fully automatic spinning machines are known in various designs from the state of the art.
  • the workstations of these spinning machines each have a spinning device, for example an open-end spinning rotor, for producing a thread, a winding device for winding the produced thread onto a cross-wound bobbin and a large number of other elements for producing the thread and for handling the produced thread and the fiber material provided.
  • the essential components for producing the thread are the so-called spinning means, which in a rotor spinning machine include the spinning rotor, the thread take-off nozzle and the opening roller.
  • EN 10 2004 044 551 A1 It is proposed that the advisory work that is required be divided into manual and machine-based work steps. In this way, the operating personnel can carry out the manual work steps at work stations that have already been shut down, while an automatic maintenance device carries out the work steps that are to be carried out mechanically. In the case of a centrally driven spinning machine, where the batch change is carried out simultaneously at a large number of work stations, this can result in considerable time savings.
  • the EP 2 955 143 A1 describes a semi-automatic spinning machine in which display means are arranged at the individual work stations to show the yarn batch produced at the work station.
  • the display means are preferably designed as LED lights.
  • the object of the present invention is to propose a method for operating a spinning machine and a spinning machine which has a enables batch changes to be made as quickly as possible, even at individual workstations.
  • each of the work stations has a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin.
  • the current batch is displayed at the workstations, especially by means of a color display.
  • the operating personnel can then quickly see which workstations are producing the same batch of yarn. This also helps to ensure that the Operating personnel are supported in determining a sensible sequence for carrying out manual maintenance. In addition, this makes it easier for operating personnel to check the condition and equipment of the respective work stations, for example whether the correct fiber material or the correct empty tubes are available for the yarn batch in question.
  • the need to carry out at least one manual maintenance activity at the work station which has reached the end of the batch can be indicated in various ways.
  • the need to carry out at least one manual maintenance activity is indicated by an occupancy status of the bobbin holder of the relevant work station.
  • the occupancy statuses of the bobbin holder can be, for example, "empty", "occupied” or "misoccupied”. If there is a discrepancy between the occupancy status of the bobbin holder and the display of the current batch at the work station, this signals to the operating personnel that at least one manual maintenance activity needs to be carried out. In this case, the display of the manual maintenance requirement is therefore carried out by components of the respective work stations themselves.
  • a storage position for empty tubes is provided at the work station, it is alternatively or additionally possible for the need to carry out at least one manual maintenance activity to be indicated by an occupancy status of the storage position for empty tubes.
  • the occupancy statuses "empty”, "occupied” or “misoccupied” are conceivable. If, for example, there is a discrepancy between the occupancy status of the storage position where an empty tube from the new batch is already located and the display of the still current, old batch at the work station, this in turn signals to the operating personnel a need to carry out at least one manual maintenance activity.
  • a wound cross-wound bobbin from a current batch is automatically removed and the need to carry out at least one manual maintenance activity is indicated by an empty bobbin holder.
  • the operating personnel can see from the empty bobbin holder that changeover work for a batch change must be carried out at this work station, because otherwise a new empty tube from the current batch would have been automatically inserted.
  • an empty tube from a new batch is provided in the supply position at the work station that has reached the end of the batch and the need to carry out at least one manual maintenance activity is indicated by the empty tube provided. Since the spool holder is still in the "empty" occupancy status, the operating personnel can see that manual maintenance activities must be carried out at this work station because otherwise the new empty tube would already have been inserted automatically. It is also possible that an empty tube from the new batch was provided in the supply position, but the current, old batch is displayed at the work station. From this discrepancy, the operating personnel can also see that there is a need to carry out at least one manual maintenance activity.
  • a wound cross-wound bobbin from a current batch is automatically removed and an empty tube from a new batch is automatically inserted.
  • the need to carry out at least one manual maintenance activity is indicated by an incorrectly occupied bobbin holder, since the empty tube of the new batch that has already been inserted does not match the display of the current batch at the work station.
  • the need to carry out at least one manual maintenance activity to be indicated by a combination of the three different indicators, namely the occupancy status of the spool holder, the occupancy status of the supply position and the display of the batch at the work station.
  • the three different indicators namely the occupancy status of the spool holder, the occupancy status of the supply position and the display of the batch at the work station.
  • the need to carry out at least one manual maintenance activity is indicated by an optical display element in the form of a graphic display assigned to the work station.
  • the operating personnel therefore do not have to draw conclusions from the prevailing constellation at the work station, as in the first two embodiments mentioned, but receive a direct and clear indication of the need to carry out at least one manual maintenance activity.
  • the need to carry out at least one manual maintenance activity is only indicated by a colored light or a specific flashing light, which of course must be different from the displays of other states at the work station.
  • the operating personnel must therefore know the exact meaning of the various colors and/or flashing signals in order to be able to assign them to different states on the spinning machine.
  • the optical display element is a graphic display, the operator is clearly and unambiguously informed in the form of text or graphic symbols that there is a need to carry out at least one manual maintenance activity.
  • the input device is a button on the display. In this case, the optical display element and the input device are combined in a touchscreen.
  • a further manual maintenance activity to be carried out is displayed on the display element.
  • the operator must therefore confirm that the first manual maintenance activity has been carried out and then receives precise information about which further specific maintenance activity is to be carried out. Of course, this can also be repeated several times so that the operator is guided step by step to carry out the necessary manual maintenance activities.
  • the confirmation of the execution of the respective maintenance activity is made using a button on the graphic display.
  • the operator can be instructed to replace the spinning rotor as the first maintenance task to be carried out, and to replace the fiber material as the second maintenance task.
  • Another maintenance task to be carried out can be to provide suitable empty tubes and, if necessary, replace the take-off nozzle.
  • a spinning agent exchange and/or a fiber material exchange is displayed as the manual maintenance activity to be carried out.
  • the operating personnel can immediately see from the "spinning agent exchange” or “fiber material exchange” display that several manual maintenance tasks have to be carried out and these particularly complex work areas are then given priority.
  • first and/or subsequent manual maintenance activities are displayed in the form of a text display and/or in the form of a graphic symbol.
  • the new batch is displayed at the relevant work station in addition to the current batch, in particular by means of a color display. This allows the operator to recognize before the end of the batch at the relevant work station that complex changeover work is pending and to have all the necessary new spinning agents, fiber materials, etc. ready. The time required for the batch change at the work station can thus be reduced even further.
  • the new batch is started at the work station, preferably started independently by the work station.
  • Manual confirmation of the execution of the required maintenance activities by the operator can ensure that all required steps have been carried out correctly. This avoids false detections, which can occur when control software queries them automatically.
  • a spinning machine for producing cross-wound bobbins in particular an open-end rotor spinning machine, with a plurality of similar work stations arranged next to one another is claimed.
  • Each of the work stations has a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin.
  • the spinning machine also has a control device and a display element for carrying out the method described above.
  • FIG 1 shows a schematic front view of a spinning machine 1 for producing cross-wound bobbins in an overview.
  • the spinning machine 1 is designed as an automatic or at least partially automatic spinning machine 1 and has a large number of similar work stations 2 arranged next to one another, which are arranged between two end frames not specified here.
  • Each of the work stations 2 has a feed device for a fiber material 7, which in the case of an open-end rotor spinning machine is designed as an opening roller 8 (see Figure 1 ).
  • each of the work stations 2 has a spinning device 3 for producing a thread 6, a take-off device 9 for drawing off the produced thread 6 and a winding device 4 for winding the produced thread 6 onto a cross-wound bobbin 10.
  • the work stations 2 are designed as at least partially self-sufficient work stations. This means that the individual work stations 2 have a large number of individual drives for driving their thread-producing organs, so that the individual work stations can also be operated independently of the other work stations 2 of the spinning machine 1. Furthermore, the work stations 2 can independently resolve at least some of the faults that occur during operation without the need for an operating robot or the intervention of an operator. Other components, not shown here, such as handling organs and maintenance organs, are therefore arranged at the work stations 2. Furthermore, a display element 12 is provided at each of the work stations 2, which can, for example, display various operating states of the work stations 2 or the respective yarn batch produced. As an alternative to the illustration shown, it is also conceivable that two work stations 2 are assigned a display element 12 together.
  • FIG. 2 shows a work station 2 of such a spinning machine 1 in a schematic side view.
  • the spinning machine 1 is designed as an open-end rotor spinning machine and therefore has an opening roller 8 as a feed device and a spinning rotor 13 as a spinning element of the spinning device 3.
  • the thread 6 produced in the spinning rotor 13 is drawn off via a take-off nozzle 14 and fed to the winding device 4.
  • the winding device 4 has a bobbin holder 5 in which an empty tube 11 (see Fig.9 and 10 ) which can then be wound into a cross-wound bobbin 10.
  • a winding roller 19 is provided to drive the winding device 4.
  • the individual drives of the at least partially self-sufficient work stations 2 as well as other handling and maintenance elements of the work stations 2 are in Figure 2 also not shown.
  • the manual maintenance requirement is indicated by an optical display element 12, as described below with reference to Figures 3 to 8
  • FIG 3 shows a view of an optical display element 12, which is designed as a graphic display 15.
  • the display 15 shows a first display that indicates a regular operating state of the workstation 2. In this regular operating state, the current batch, here designated "A", is shown by a color display 20 (shown here in light dots). Furthermore, the regular operating state itself is shown by an easily understandable graphic symbol 16.
  • the display element 12 is assigned an input device 17, by means of which the Operators can make inputs and communicate with a control unit of workstation 2 (not shown here) and/or a central control unit (also not shown). In the present case, the display element 12 or the display 15 and the input device 17 are combined in one structural unit, so that the input device 17 is formed by various buttons 18 of the display 15. In the display shown here, the display 15 has, for example, a button 18 for retrieving information. By pressing this button, the operator can access the menu of the control unit of workstation 2 and make various settings there.
  • Figure 4 shows a view of the display element 12 or the display 15, which indicates a need to carry out at least one manual maintenance activity when the end of the batch of the relevant work station 2 is reached.
  • the current batch is still shown by the color display 20.
  • the need to carry out at least one manual maintenance activity is shown here by another, easily understandable graphic symbol 16. The operating personnel can use this symbol to very quickly see that manual activities are to be carried out at this work station 2 and can therefore work on these work stations 2 preferentially or plan the maintenance of the relevant work stations better.
  • the display of the need to carry out at least one manual maintenance activity is again designed as a button 18 in the present case, which can be recognized both by the frame surrounding the button 18 and by the prompt to actuate it by means of the check mark. If the operator now presses this button 18, he receives more detailed information on which specific maintenance activities are to be carried out in a subsequent display.
  • Figure 5 now shows another display on the display 15, which the operator can see after pressing the button 18 of the previous display ( Figure 4 ) or, in the general case after actuating the input device 17, displays the manual maintenance activity to be carried out.
  • the task "Check Spinning Components" is displayed in the form of a display text. This and any subsequent displays inform the operator that he must check the spinning components and replace them if necessary.
  • the advantage here is that the same displays can be used for both faults in regular spinning operations that lead to a standstill at work station 2 and when maintenance is required due to an upcoming batch change.
  • the operator only needs to be informed that at least one manual maintenance activity needs to be carried out and is then guided through the menu and given step-by-step instructions.
  • the operator therefore does not need to differentiate between faults in regular operations and batch changes and does not need to think about which manual maintenance activities he needs to carry out in which case, but simply needs to follow the instructions that can be called up one after the other, as will be explained below.
  • the displays of the manual maintenance activities to be carried out also contain a button 18, by means of which the operator must confirm the execution of the maintenance activity after it has been completed. After the operator has confirmed the execution of the maintenance activity , another required manual maintenance activity may be displayed, which the operator must also confirm, whereupon another required manual maintenance activity may be displayed.
  • the operating personnel can thus see at first glance that the need to carry out at least one manual maintenance activity involves a batch change with a spinning agent change and can give priority to these work stations 2. This is particularly advantageous if specially trained personnel are required for such a spinning agent change. The personnel can thus immediately see whether simple manual maintenance activities are to be carried out or a spinning agent change for which specially trained personnel is required.
  • FIGS 9 to 11 finally show an alternative embodiment in which the need to carry out at least one manual maintenance activity is indicated by the occupancy state of the spool holder 5 or the occupancy state of a supply position 22 for empty tubes 11.
  • FIG. 9 a situation in which workstation 2 has reached the end of the batch and has already been shut down.
  • empty tubes 11 of the new batch are already provided at spinning machine 1.
  • the batch change has already been initiated by the control unit of workstation 2 and/or spinning machine 1 by inserting an empty tube 11 of the new batch into bobbin holder 5, as can be seen from the dark dotted color of the empty tube.
  • display element 12 still shows the color display 20 of the just finished, still current batch.
  • the inserted empty tube 11 does not match the displayed batch, so that bobbin holder 5 has the "incorrectly loaded” status. Operating personnel can therefore recognize from the idle workstation 2 and the incorrect occupancy of the bobbin holder that a batch change is pending and manual activities must be carried out.
  • Figure 11 shows a work station 2, which additionally has a supply position for empty tubes 11, whereby the need to carry out at least one manual maintenance activity is indicated by the empty tube 11 provided.
  • the work station 2 has again reached the end of the batch and has already been shut down.
  • empty tubes 11 of the new batch are already provided on the spinning machine 1.
  • the batch change has already been initiated by the control unit of the work station 2 and/or the spinning machine 1 by providing an empty tube 11 of the new batch (dark dotted color) in the supply position 22, but has not yet been inserted into the bobbin holder 5.
  • the bobbin holder 5 therefore has the "empty" occupancy status. The operating personnel can therefore recognize from the empty tube provided and the "empty" occupancy status of the bobbin holder that a batch change is pending and that manual activities must be carried out.
  • the color display 20 of the currently completed batch is also shown by the display element 12.
  • the empty tube 11 provided in the supply position 22 therefore does not match the displayed batch, from which the operating personnel can also recognize that a batch change is pending and manual activities must be carried out. are.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Textile Engineering (AREA)
  • Spinning Or Twisting Of Yarns (AREA)
  • Filamentary Materials, Packages, And Safety Devices Therefor (AREA)

Description

Die vorliegende Erfindung betrifft ein Verfahren zum Betreiben einer teil- oder vollautomatischen, kreuzspulenherstellenden Spinnmaschine, insbesondere einer Offenend-Rotorspinnmaschine, mit einer Vielzahl gleichartiger, nebeneinander angeordneter, zumindest teilweise autarker Arbeitsstellen, wobei jede der Arbeitsstellen eine Spinnvorrichtung zur Herstellung eines Fadens sowie eine einen Spulenhalter aufweisende Spulvorrichtung zum Aufwickeln des Fadens auf eine Kreuzspule aufweist. Dabei wird bei Erreichen eines Partieendes einer der Arbeitsstellen die betreffende Arbeitsstelle stillgesetzt.The present invention relates to a method for operating a partially or fully automatic spinning machine for producing cross-wound bobbins, in particular an open-end rotor spinning machine, with a plurality of similar, at least partially self-sufficient work stations arranged next to one another, each of the work stations having a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin. When one of the work stations reaches the end of a batch, the work station in question is stopped.

Teil- oder vollautomatische Spinnmaschinen sind aus dem Stand der Technik in verschiedenen Ausführungen bekannt. Die Arbeitsstellen dieser Spinnmaschinen verfügen dabei jeweils über eine Spinnvorrichtung, beispielsweise einen Offenend-Spinnrotor, zur Herstellung eines Fadens, eine Spulvorrichtung zum Aufwickeln des produzierten Fadens auf eine Kreuzspule sowie eine Vielzahl weiterer Elemente zum Herstellen des Fadens sowie zum Handhaben des hergestellten Fadens und des vorgelegten Fasermaterials. Wesentliche Komponenten für die Herstellung des Fadens sind dabei die sogenannten Spinnmittel, welche bei einer Rotorspinnmaschine unter anderem den Spinnrotor, die Fadenabzugsdüse und die Auflösewalze umfassen.Partially or fully automatic spinning machines are known in various designs from the state of the art. The workstations of these spinning machines each have a spinning device, for example an open-end spinning rotor, for producing a thread, a winding device for winding the produced thread onto a cross-wound bobbin and a large number of other elements for producing the thread and for handling the produced thread and the fiber material provided. The essential components for producing the thread are the so-called spinning means, which in a rotor spinning machine include the spinning rotor, the thread take-off nozzle and the opening roller.

Soll nun an einer Spinnmaschine bzw. an einer einzelnen Arbeitsstelle ein sogenannter Partiewechsel durchgeführt werden, d. h. ein Garn mit anderen Eigenschaften als bisher produziert werden, sind an den einzelnen Arbeitsstellen zahlreiche Umrüstarbeiten erforderlich. Im einfachsten Fall müssen lediglich andere Leerhülsen bereitgestellt werden und einige Betriebsparameter der Spinnmaschine bzw. der Arbeitsstelle geändert werden. In der Regel müssen jedoch auch das vorgelegte Fasermaterial sowie zumindest einige der vorgenannten Spinnelemente durch eine Bedienperson ausgetauscht werden.If a so-called batch change is to be carried out on a spinning machine or at an individual work station, i.e. a yarn with different properties than before is to be produced, a lot of conversion work is required at the individual work stations. In the simplest case, only other empty tubes have to be provided and some operating parameters of the spinning machine or the work station have to be changed. As a rule However, the fibre material provided and at least some of the aforementioned spinning elements must also be replaced by an operator.

Bei zentral angetriebenen Spinnmaschinen ist es dabei stets erforderlich, den Partiewechsel an allen gemeinsam angetriebenen Arbeitsstellen gleichzeitig durchzuführen. Demgegenüber ist es bei Spinnmaschinen mit sogenannten zumindest teilweise autarken Arbeitsstellen, welche einen Großteil der anfallenden Wartungstätigkeiten mittels an den Arbeitsstellen angeordneter Bedienelemente selbstständig durchführen können, möglich, an den einzelnen Arbeitsstellen auch verschiedene Garnpartien herzustellen. In jedem Fall aber ist das Umrüsten der Arbeitsstellen auf die neue Partie mit einem erheblichen Zeitaufwand verbunden, was zu längeren Stillstandszeiten der Arbeitsstellen und damit verbundenen Produktivitätseinbußen führt.In the case of centrally driven spinning machines, it is always necessary to carry out the batch change at all jointly driven workstations at the same time. In contrast, in the case of spinning machines with so-called at least partially self-sufficient workstations, which can carry out a large part of the maintenance work independently using control elements arranged at the workstations, it is possible to produce different yarn batches at the individual workstations. In any case, however, converting the workstations to the new batch takes a considerable amount of time, which leads to longer downtimes at the workstations and the associated loss of productivity.

Um den Zeitaufwand für das Warten mehrerer Arbeitsstellen bzw. das Umrüsten der Arbeitsstellen bei einem Partiewechsel zu reduzieren, wurde in der DE 10 2004 044 551 A1 vorgeschlagen, die jeweils anfallende Beratungstätigkeit in manuell und maschinell auszuführende Arbeitsschritte aufzuteilen. Auf diese Weise kann das Bedienpersonal an bereits stillgesetzten Arbeitsstellen die manuell auszuführenden Arbeitsschritte durchführen, während parallel dazu eine automatische Wartungsvorrichtung die maschinell auszuführenden Arbeitsschritte durchführt. Bei einer zentral angetriebenen Spinnmaschine, bei der der Partiewechsel zeitgleich an einer Vielzahl von Arbeitsstellen durchgeführt wird, kann hierdurch eine erhebliche Zeitersparnis erreicht werden.In order to reduce the time required for servicing several workstations or for resetting the workstations when changing batches, EN 10 2004 044 551 A1 It is proposed that the advisory work that is required be divided into manual and machine-based work steps. In this way, the operating personnel can carry out the manual work steps at work stations that have already been shut down, while an automatic maintenance device carries out the work steps that are to be carried out mechanically. In the case of a centrally driven spinning machine, where the batch change is carried out simultaneously at a large number of work stations, this can result in considerable time savings.

Die EP 2 955 143 A1 beschreibt eine semi-automatische Spinnmaschine, bei der an den einzelnen Arbeitsstellen Anzeigemittel angeordnet sind, die die jeweils hergestellte Garnpartie an der Arbeitsstelle anzeigen. Die Anzeigemittel sind bevorzugt als LED-Leuchte ausgebildet.The EP 2 955 143 A1 describes a semi-automatic spinning machine in which display means are arranged at the individual work stations to show the yarn batch produced at the work station. The display means are preferably designed as LED lights.

Aus der DE 10 2014 018 628 A1 ist es weiterhin bekannt, an den Arbeitsstellen einer Spinnmaschine jeweils eine LED-Lichtschiene anzuordnen. Die Lichtschiene zeigt die jeweils hergestellte Garnpartie und/oder Betriebszustände an der jeweiligen Arbeitsstelle an. Das Bedienungspersonal kann hierdurch an einer Spinnmaschine mit Mehrpartienbelegung, an welcher mehrere Garnpartien gleichzeitig hergestellt werden, schnell erkennen, welche Arbeitsstellen dieselbe Garnpartie produzieren. Ebenso kann das Bedienungspersonal anhand der verschiedenfarbigen LED-Leuchten erkennen, welches Problem an welcher Arbeitsstelle vorliegt und daraus eine vorteilhafte Reihenfolge für die Abarbeitung der Probleme festlegen.From the EN 10 2014 018 628 A1 It is also known to arrange an LED light rail at each work station on a spinning machine. The light rail shows the yarn batch produced and/or operating status at the respective work station. This allows the operating personnel to quickly identify which work stations are producing the same yarn batch on a spinning machine with multiple batches, on which several yarn batches are produced at the same time. The operating personnel can also use the different colored LED lights to identify which problem is present at which work station and use this to determine an advantageous sequence for dealing with the problems.

Aus der EP 2 762 617 A1 ist es weiterhin bekannt, mittels eines blinkenden LED-Signals anzuzeigen, dass die betreffende Arbeitsstelle das Partieende erreicht hat. Bei der D1 ist nun vorgesehen, dass an einer Arbeitsstelle, die das Partieende erreicht hat, die der Arbeitsstelle zugeordnete LED zu blinken beginnt. Der Bediener kann an dem Blinken erkennen, dass die betreffende Arbeitsstelle das Partieende erreicht hat, er hat daraus jedoch keine Informationen dazu, ob er an dieser Arbeitsstelle tätig werden muss oder nicht und welche Tätigkeiten er ggf. durchführen muss.From the EP 2 762 617 A1 It is also known to use a flashing LED signal to indicate that the work station in question has reached the end of the batch. The D1 now provides that the LED assigned to a work station that has reached the end of the batch begins to flash. The operator can tell from the flashing that the work station in question has reached the end of the batch, but this does not give him any information as to whether or not he needs to work on this work station and what activities he may need to carry out.

Aus der nachveröffentlichten EP 3 511 452 A1 ist es weiterhin bekannt, an den Arbeitsstellen grafische Anzeigeelemente anzuordnen, die jeweils mehreren Arbeitsstellen zugeordnet sind. Die einzelnen Anzeigeflächen des Displays können dabei in ihrer Größe angepasst werden können. Die Schrift beschreibt weiterhin, dass die Anzeige im Normalbetrieb u.a. auch den Wartungsbedarf der Arbeitsstellen anzeigen kann. Zum Erreichen des Partieendes wird jedoch nichts gesagt.From the republished EP 3 511 452 A1 It is also known to arrange graphic display elements at the workstations, each of which is assigned to several workstations. The individual display areas of the display can be adjusted in size. The document also describes that the display can also show the maintenance requirements of the workstations during normal operation . However, nothing is said about reaching the end of the game.

Aufgabe der vorliegenden Erfindung ist es, ein Verfahren zum Betreiben einer Spinnmaschine sowie eine Spinnmaschine vorzuschlagen, welche einen möglichst schnellen Partiewechsel auch an einzelnen Arbeitsstellen ermöglicht.The object of the present invention is to propose a method for operating a spinning machine and a spinning machine which has a enables batch changes to be made as quickly as possible, even at individual workstations.

Die Aufgabe wird gelöst durch ein Verfahren mit den Merkmalen des Patentanspruchs 1.The problem is solved by a method having the features of patent claim 1.

Bei dem Verfahren zum Betreiben einer teil- oder vollautomatischen, kreuzspulenherstellenden Spinnmaschine, insbesondere einer Offenend-Rotorspinnmaschine, mit einer Vielzahl gleichartiger, nebeneinander angeordneter Arbeitsstellen, weist jede der Arbeitsstellen eine Spinnvorrichtung zur Herstellung eines Fadens sowie eine einen Spulenhalter aufweisende Spulvorrichtung zum Aufwickeln des Fadens auf eine Kreuzspule auf. Bei Erreichen eines Partieendes einer der Arbeitsstellen wird die betreffende Arbeitsstelle stillgesetzt.In the method for operating a partially or fully automatic spinning machine for producing cross-wound bobbins, in particular an open-end rotor spinning machine, with a plurality of similar work stations arranged next to one another, each of the work stations has a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin. When a batch end is reached at one of the work stations, the work station in question is stopped.

Es wird vorgeschlagen, dass an der Arbeitsstelle, welche das Partieende erreicht hat, ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit angezeigt wird. Das Bedienpersonal kann hierdurch sehr schnell erkennen, an welchen Arbeitsstellen manuelle Tätigkeiten erforderlich sind und kann diese daher schnell und bevorzugt abarbeiten. Somit können auch die Arbeitsstellen, welche für einen Partiewechsel umgerüstet werden müssen, sehr schnell von der Bedienperson abgearbeitet werden. Die Arbeitsstellen können dadurch ihre Produktion schnell wiederaufnehmen und Stillstandzeiten der betreffenden Arbeitsstellen können geringgehalten werden.It is proposed that a requirement to carry out at least one manual maintenance activity be indicated at the work station that has reached the end of the batch. This enables the operating personnel to quickly identify which work stations require manual activities and can therefore carry out these activities quickly and preferentially. This means that the work stations that need to be converted for a batch change can also be processed very quickly by the operator. The work stations can then resume production quickly and downtimes at the work stations concerned can be kept to a minimum.

Vorteile bringt es zudem mit sich, wenn an den Arbeitsstellen die jeweils aktuelle Partie angezeigt wird, insbesondere durch eine Farbanzeige angezeigt wird. Das Bedienpersonal kann hierdurch schnell erkennen, welche Arbeitsstellen dieselbe Garnpartie produzieren. Auch dies trägt dazu bei, dass das Bedienpersonal darin unterstützt wird, eine sinnvolle Reihenfolge für die Abarbeitung von manuellen Wartungen festzulegen. Zudem kann hierdurch das Bedienpersonal den Zustand und die Ausstattung der jeweiligen Arbeitsstellen leichter kontrollieren, also beispielsweise ob das richtige Fasermaterial oder die richtigen Leerhülsen für die betreffende Garnpartie vorhanden sind.It is also advantageous if the current batch is displayed at the workstations, especially by means of a color display. The operating personnel can then quickly see which workstations are producing the same batch of yarn. This also helps to ensure that the Operating personnel are supported in determining a sensible sequence for carrying out manual maintenance. In addition, this makes it easier for operating personnel to check the condition and equipment of the respective work stations, for example whether the correct fiber material or the correct empty tubes are available for the yarn batch in question.

Die Anzeige des Bedarfs zur Durchführung mindestens einer manuellen Wartungstätigkeit an der Arbeitsstelle, welche das Partieende erreicht hat, kann prinzipiell auf verschiedene Weise erfolgen.In principle, the need to carry out at least one manual maintenance activity at the work station which has reached the end of the batch can be indicated in various ways.

So wird nach einer ersten Ausführung des Verfahrens der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch einen Belegungszustand des Spulenhalters der betreffenden Arbeitsstelle angezeigt. Die Belegungszustände des Spulenhalters können beispielsweise sein "leer", "belegt" oder "fehlbelegt". Besteht nun eine Diskrepanz zwischen dem Belegungszustand des Spulenhalters und der Anzeige der aktuellen Partie an der Arbeitsstelle, so wird hierdurch dem Bedienpersonal ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit signalisiert. Die Anzeige des manuellen Wartungsbedarfs erfolgt somit in diesem Fall durch Komponenten der jeweiligen Arbeitsstellen selbst.After a first execution of the method, the need to carry out at least one manual maintenance activity is indicated by an occupancy status of the bobbin holder of the relevant work station. The occupancy statuses of the bobbin holder can be, for example, "empty", "occupied" or "misoccupied". If there is a discrepancy between the occupancy status of the bobbin holder and the display of the current batch at the work station, this signals to the operating personnel that at least one manual maintenance activity needs to be carried out. In this case, the display of the manual maintenance requirement is therefore carried out by components of the respective work stations themselves.

Ist an der Arbeitsstelle eine Vorratsposition für Leerhülsen vorgesehen, so ist es alternativ oder zusätzlich auch möglich, dass der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch einen Belegungszustand der Vorratsposition für Leerhülsen angezeigt wird. Auch hier sind die Belegungszustände "leer", "belegt" oder "fehlbelegt" denkbar. Besteht beispielsweise eine Diskrepanz zwischen dem Belegungszustand der Vorratsposition, an der bereits eine Leerhülse der neuen Partie liegt, und der Anzeige der noch aktuellen, alten Partie an der Arbeitsstelle, so wird hierdurch wiederum dem Bedienpersonal ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit signalisiert.If a storage position for empty tubes is provided at the work station, it is alternatively or additionally possible for the need to carry out at least one manual maintenance activity to be indicated by an occupancy status of the storage position for empty tubes. Here too, the occupancy statuses "empty", "occupied" or "misoccupied" are conceivable. If, for example, there is a discrepancy between the occupancy status of the storage position where an empty tube from the new batch is already located and the display of the still current, old batch at the work station, this in turn signals to the operating personnel a need to carry out at least one manual maintenance activity.

Beispielsweise wird an der Arbeitsstelle, welche das Partieende erreicht hat, eine bewickelte Kreuzspule einer noch aktuellen Partie automatisch entnommen und der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch einen leeren Spulenhalter angezeigt. Das Bedienungspersonal kann anhand des leeren Spulenhalters erkennen, dass an dieser Arbeitsstelle Umrüstarbeiten für einen Partiewechsel durchzuführen sind, weil andernfalls eine neue Leerhülse der noch aktuellen Partie automatisch eingelegt worden wäre.For example, at the work station that has reached the end of the batch, a wound cross-wound bobbin from a current batch is automatically removed and the need to carry out at least one manual maintenance activity is indicated by an empty bobbin holder. The operating personnel can see from the empty bobbin holder that changeover work for a batch change must be carried out at this work station, because otherwise a new empty tube from the current batch would have been automatically inserted.

Ebenfalls möglich ist es, dass an der Arbeitsstelle, welche das Partieende erreicht hat, eine Leerhülse einer neuen Partie in der Vorratsposition bereitgestellt wird und der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch die bereitgestellte Leerhülse angezeigt wird. Da nämlich zugleich der Spulenhalter noch den Belegungszustand "leer" aufweist, kann das Bedienpersonal erkennen, dass an dieser Arbeitsstelle manuelle Wartungstätigkeiten durchzuführen sind, weil andernfalls die neue Leerhülse bereits automatisch eingelegt worden wäre. Ebenso ist es möglich, dass zwar eine Leerhülse der neuen Partie in der Vorratsposition bereitgestellt wurde, an der Arbeitsstelle jedoch die noch aktuelle, alte Partie angezeigt wird. Auch aus dieser Diskrepanz kann das Bedienpersonal wiederum erkennen, dass ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit besteht.It is also possible that an empty tube from a new batch is provided in the supply position at the work station that has reached the end of the batch and the need to carry out at least one manual maintenance activity is indicated by the empty tube provided. Since the spool holder is still in the "empty" occupancy status, the operating personnel can see that manual maintenance activities must be carried out at this work station because otherwise the new empty tube would already have been inserted automatically. It is also possible that an empty tube from the new batch was provided in the supply position, but the current, old batch is displayed at the work station. From this discrepancy, the operating personnel can also see that there is a need to carry out at least one manual maintenance activity.

Nach einer anderen Ausführung wird an der Arbeitsstelle, welche das Partieende erreicht hat, eine bewickelte Kreuzspule einer noch aktuellen Partie automatisch entnommen und eine Leerhülse einer neuen Partie automatisch eingelegt. Der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit wird in diesem Fall durch einen fehlbelegten Spulenhalter angezeigt, da die bereits eingelegte Leerhülse der neuen Partie nicht mit der Anzeige der noch aktuellen Partie an der Arbeitsstelle übereinstimmt.According to another design, at the work station that has reached the end of the batch, a wound cross-wound bobbin from a current batch is automatically removed and an empty tube from a new batch is automatically inserted. In this case, the need to carry out at least one manual maintenance activity is indicated by an incorrectly occupied bobbin holder, since the empty tube of the new batch that has already been inserted does not match the display of the current batch at the work station.

Natürlich ist es auch möglich, dass der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch eine Kombination der drei verschiedenen Indikatoren, nämlich des Belegungszustandes des Spulenhalters, des Belegungszustandes der Vorratsposition und der Anzeige der Partie an der Arbeitsstelle, angezeigt wird. Hier sind verschiedene Kombinationen möglich.Of course, it is also possible for the need to carry out at least one manual maintenance activity to be indicated by a combination of the three different indicators, namely the occupancy status of the spool holder, the occupancy status of the supply position and the display of the batch at the work station. Various combinations are possible here.

Erfindungsgemäß wird der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch ein der Arbeitsstelle zugeordnetes optisches Anzeigeelement, in Form eines grafischen Displays, angezeigt. Das Bedienungspersonal muss hierdurch nicht wie in den beiden erstgenannten Ausführungen Rückschlüsse aus der vorherrschenden Konstellation an der Arbeitsstelle ziehen, sondern erhält eine direkte und eindeutige Anzeige des Bedarfs zur Durchführung mindestens einer manuellen Wartungstätigkeit. Nicht gemäß der Erfindung ist es denkbar, dass der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit lediglich durch eine farbige Leuchte oder ein bestimmtes Blinklicht angezeigt wird, die sich natürlich von den Anzeigen anderer Zustände an der Arbeitsstelle unterscheiden müssen. Das Bedienpersonal muss hierdurch die Bedeutung der verschiedenen Farben und/oder Blinkzeichen genau kennen, um diesen verschiedene Zustände an der Spinnmaschine zuordnen zu können. Da das optische Anzeigeelement hingegen ein grafisches Display ist, wird dem Bediener klar und unmissverständlich in Form von Texten oder grafischen Symbolen mitgeteilt werden, dass ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit besteht.According to the invention, the need to carry out at least one manual maintenance activity is indicated by an optical display element in the form of a graphic display assigned to the work station. The operating personnel therefore do not have to draw conclusions from the prevailing constellation at the work station, as in the first two embodiments mentioned, but receive a direct and clear indication of the need to carry out at least one manual maintenance activity. It is not conceivable according to the invention that the need to carry out at least one manual maintenance activity is only indicated by a colored light or a specific flashing light, which of course must be different from the displays of other states at the work station. The operating personnel must therefore know the exact meaning of the various colors and/or flashing signals in order to be able to assign them to different states on the spinning machine. Since the optical display element, on the other hand, is a graphic display, the operator is clearly and unambiguously informed in the form of text or graphic symbols that there is a need to carry out at least one manual maintenance activity.

Besondere Vorteile bringt es daher auch mit sich, wenn der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit in Form eines grafischen Symbols angezeigt wird. Derartige grafische Symbole können unabhängig von der Sprache des Bedienpersonals problemlos verstanden werden.It is therefore particularly advantageous if the need to carry out at least one manual maintenance task is indicated in the form of a graphic symbol. Such graphic symbols can be easily understood regardless of the language of the operating personnel.

Ebenfalls vorteilhaft ist es, wenn nach Betätigung einer dem Anzeigeelement zugeordneten Eingabevorrichtung zumindest eine erste durchzuführende manuelle Wartungstätigkeit durch das Anzeigeelement angezeigt wird. Die Bedienperson kann hierdurch durch Betätigen der Eingabevorrichtung erfahren, welche manuelle Wartungstätigkeit konkret durchgeführt werden muss. Vorteilhaft ist es dabei, wenn die Eingabevorrichtung eine Schaltfläche des Displays ist. Das optische Anzeigeelement und die Eingabevorrichtung sind in diesem Fall in einem Touchscreen kombiniert.It is also advantageous if, after actuating an input device assigned to the display element, at least a first manual maintenance activity to be carried out is displayed by the display element. The operator can thus find out which manual maintenance activity specifically needs to be carried out by actuating the input device. It is advantageous if the input device is a button on the display. In this case, the optical display element and the input device are combined in a touchscreen.

Weiterhin ist es vorteilhaft, wenn nach Bestätigung der Durchführung der ersten manuellen Wartungstätigkeit durch die Bedienperson eine weitere durchzuführende manuelle Wartungstätigkeit durch das Anzeigeelement angezeigt wird. Die Bedienperson muss somit die Durchführung der ersten manuellen Wartungstätigkeit bestätigen und erhält anschließend eine genaue Angabe, welche weitere konkrete Wartungstätigkeit durchzuführen ist. Natürlich kann sich dies auch mehrfach wiederholen, sodass die Bedienperson Schritt für Schritt angeleitet wird, die erforderlichen manuellen Wartungstätigkeiten vorzunehmen. Vorteilhaft ist es auch hier wieder, wenn die Bestätigung der Durchführung der jeweiligen Wartungstätigkeit mittels einer Schaltfläche des grafischen Displays erfolgt.It is also advantageous if, after the operator has confirmed that the first manual maintenance activity has been carried out, a further manual maintenance activity to be carried out is displayed on the display element. The operator must therefore confirm that the first manual maintenance activity has been carried out and then receives precise information about which further specific maintenance activity is to be carried out. Of course, this can also be repeated several times so that the operator is guided step by step to carry out the necessary manual maintenance activities. Here, too, it is advantageous if the confirmation of the execution of the respective maintenance activity is made using a button on the graphic display.

Beispielsweise kann der Bedienperson als erste durchzuführende Wartungstätigkeit der Austausch des Spinnrotors vorgegeben werden und als zweite Wartungstätigkeit der Austausch des Fasermaterials. Als weitere durchzuführende Wartungstätigkeit kann noch das Bereitstellen passender Leerhülsen vorgegeben werden und ggf. ein Austausch der Abzugsdüse.For example, the operator can be instructed to replace the spinning rotor as the first maintenance task to be carried out, and to replace the fiber material as the second maintenance task. Another maintenance task to be carried out can be to provide suitable empty tubes and, if necessary, replace the take-off nozzle.

Nach einer alternativen Ausführung des Verfahrens wird als durchzuführende manuelle Wartungstätigkeit ein Spinnmitteltausch und/oder ein Fasermaterialtausch angezeigt. Das Bedienungspersonal kann an der Anzeige "Spinnmitteltausch" oder "Fasermaterialtausch" wiederum gleich erkennen, dass mehrere manuelle Wartungstätigkeiten durchzuführen sind und diese besonders aufwändigen Arbeitsstellen dann bevorzugt behandeln.After an alternative execution of the procedure, a spinning agent exchange and/or a fiber material exchange is displayed as the manual maintenance activity to be carried out. The operating personnel can immediately see from the "spinning agent exchange" or "fiber material exchange" display that several manual maintenance tasks have to be carried out and these particularly complex work areas are then given priority.

Um den bei einem Spinnmitteltausch besonders hohen Umrüstaufwand dem Bediener möglichst frühzeitig und schnell anzuzeigen, kann es daher in Abweichung von dem vorliegenden Verfahren auch vorteilhaft sein, den Spinnmitteltausch direkt als Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit anzuzeigen. Dies bedeutet, dass das Bedienungspersonal bereits im Vorbeigehen und ohne das Betätigen der Eingabevorrichtung erkennen kann, dass aufwändige Umrüstarbeiten erforderlich sind.In order to indicate to the operator as early and as quickly as possible the particularly high conversion effort required when changing the spinning agent, it can therefore also be advantageous, in deviation from the present method, to indicate the spinning agent change directly as a requirement to carry out at least one manual maintenance activity. This means that the operating personnel can already recognize as they walk past and without operating the input device that complex conversion work is required.

Besondere Vorteile bringt es mit sich, wenn die erste und/oder die weitere manuelle Wartungstätigkeit in Form einer Textanzeige und/oder in Form eines grafischen Symbols angezeigt wird.It is particularly advantageous if the first and/or subsequent manual maintenance activities are displayed in the form of a text display and/or in the form of a graphic symbol.

Des Weiteren ist es vorteilhaft, wenn im Falle eines bevorstehenden Partiewechsels an der betreffenden Arbeitsstelle zusätzlich zu der aktuellen Partie auch die neue Partie angezeigt wird, insbesondere durch eine Farbanzeige angezeigt wird. Die Bedienperson kann hierdurch bereits vor Erreichen des Partieendes der jeweiligen Arbeitsstelle erkennen, dass aufwändige Umrüstarbeiten anstehen und bereits alle erforderlichen neuen Spinnmittel, Fasermaterialien usw. bereithalten. Der Zeitaufwand für den Partiewechsel an der Arbeitsstelle kann hierdurch nochmals reduziert werden.Furthermore, it is advantageous if, in the event of an impending batch change, the new batch is displayed at the relevant work station in addition to the current batch, in particular by means of a color display. This allows the operator to recognize before the end of the batch at the relevant work station that complex changeover work is pending and to have all the necessary new spinning agents, fiber materials, etc. ready. The time required for the batch change at the work station can thus be reduced even further.

Schließlich ist es vorteilhaft, wenn nach Bestätigung der Durchführung der ersten und/oder der wenigstens einen weiteren manuellen Wartungstätigkeit durch die Bedienperson die neue Partie an der Arbeitsstelle gestartet wird, vorzugsweise selbstständig durch die Arbeitsstelle gestartet wird. Durch die manuelle Bestätigung der Durchführung der erforderlichen Wartungstätigkeiten durch den Bediener kann sichergestellt werden, dass alle erforderlichen Schritte korrekt durchgeführt wurden. Fehlerkennungen, wie Sie beim automatischen Abfragen durch eine Steuerungssoftware auftreten können, werden hierdurch vermieden.Finally, it is advantageous if, after confirmation of the execution of the first and/or at least one further manual maintenance activity by the operator, the new batch is started at the work station, preferably started independently by the work station. Manual confirmation of the execution of the required maintenance activities by the operator can ensure that all required steps have been carried out correctly. This avoids false detections, which can occur when control software queries them automatically.

Weiterhin wird eine kreuzspulenherstellende Spinnmaschine, insbesondere Offenend-Rotorspinnmaschine, mit einer Vielzahl gleichartiger, nebeneinander angeordneter Arbeitsstellen beansprucht. Dabei weist jede der Arbeitsstellen eine Spinnvorrichtung zur Herstellung eines Fadens sowie eine einen Spulenhalter aufweisende Spulvorrichtung zum Aufwickeln des Fadens auf eine Kreuzspule auf. Die Spinnmaschine weist weiterhin eine Steuervorrichtung und ein Anzeigeelement zur Durchführung des oben beschriebenen Verfahrens auf.Furthermore, a spinning machine for producing cross-wound bobbins, in particular an open-end rotor spinning machine, with a plurality of similar work stations arranged next to one another is claimed. Each of the work stations has a spinning device for producing a thread and a winding device having a bobbin holder for winding the thread onto a cross-wound bobbin. The spinning machine also has a control device and a display element for carrying out the method described above.

Weitere Vorteile der Erfindung sind in den nachfolgenden Ausführungsbeispielen beschrieben. Es zeigen:

Figur 1
eine Vorderansicht einer kreuzspulenherstellenden Spinnmaschine in Form einer Übersichtsdarstellung,
Figur 2
eine schematische Seitenansicht einer Arbeitsstelle einer kreuzspulenherstellenden Spinnmaschine,
Figur 3
eine Ansichtsdarstellung eines optischen Anzeigeelements mit einer ersten Anzeige,
Figur 4-8
eine Ansichtsdarstellung eines optischen Anzeigeelements mit verschiedenen weiteren Anzeigen,
Figur 9
eine schematische Seitenansicht einer Arbeitsstelle einer kreuzspulenherstellenden Spinnmaschine mit einem Spulenhalter mit einem ersten Belegungszustand,
Figur 10
eine schematische Seitenansicht einer Arbeitsstelle einer kreuzspulenherstellenden Spinnmaschine mit einem Spulenhalter mit einem zweiten Belegungszustand, sowie
Figur 11
eine schematische Seitenansicht einer Arbeitsstelle einer kreuzspulenherstellenden Spinnmaschine mit einer Vorratsposition für Leerhülsen.
Further advantages of the invention are described in the following embodiments. They show:
Figure 1
a front view of a cross-wound bobbin spinning machine in the form of an overview,
Figure 2
a schematic side view of a workstation of a cross-wound bobbin spinning machine,
Figure 3
a view of an optical display element with a first display,
Figure 4-8
a view of an optical display element with various other displays,
Figure 9
a schematic side view of a workstation of a cross-wound bobbin spinning machine with a bobbin holder with a first loading state,
Figure 10
a schematic side view of a workstation of a cross-wound bobbin spinning machine with a bobbin holder with a second loading state, and
Figure 11
a schematic side view of a work station of a cross-wound bobbin spinning machine with a storage position for empty tubes.

Bei der nachfolgenden Beschreibung der Figuren werden für Merkmale, die bei den einzelnen Ausführungen bzw. den einzelnen Figuren jeweils identisch oder zumindest vergleichbar sind, gleiche Bezugszeichen verwendet. Einige der Merkmale werden daher nur bei ihrer ersten Erwähnung bzw. nur einmal anhand einer geeigneten Figur erläutert. Sofern diese Merkmale in Verbindung mit den weiteren Figuren nicht nochmals gesondert erläutert werden, entspricht deren Ausgestaltung und/oder Wirkweise der Ausgestaltung und Wirkweise der identischen oder vergleichbaren, beschriebenen Merkmale. Aus Gründen der Übersichtlichkeit ist weiterhin bei mehreren identischen Merkmalen oder Bauteilen in einer Figur nur eines oder sind nur wenige dieser identischen Merkmale beschriftet.In the following description of the figures, the same reference symbols are used for features that are identical or at least comparable in the individual versions or the individual figures. Some of the features are therefore only explained when they are first mentioned or only once using a suitable figure. If these features are not explained again separately in connection with the other figures, their design and/or mode of operation corresponds to the design and mode of operation of the identical or comparable features described. For reasons of clarity, if there are several identical features or components in a figure, only one or only a few of these identical features are labeled.

Figur 1 zeigt eine schematische Vorderansicht einer kreuzspulenherstellenden Spinnmaschine 1 in einer Übersichtsdarstellung. Die Spinnmaschine 1 ist als automatische oder zumindest teilautomatische Spinnmaschine 1 ausgebildet und weist eine Vielzahl gleichartiger, nebeneinander angeordneter Arbeitsstellen 2 auf, die zwischen zwei hier nicht näher bezeichneten Endgestellen angeordnet sind. Jede der Arbeitsstellen 2 weist eine Zuführvorrichtung für ein Fasermaterial 7 auf, die im Falle einer Offenend-Rotorspinnmaschine als Auflösewalze 8 (siehe Figur 1) ausgebildet ist. Weiterhin weist jede der Arbeitsstellen 2 eine Spinnvorrichtung 3 zur Herstellung eines Fadens 6, eine Abzugsvorrichtung 9 zum Abziehen des produzierten Fadens 6 sowie eine Spulvorrichtung 4 zum Aufspulen des produzierten Fadens 6 auf eine Kreuzspule 10 auf. Die Arbeitsstellen 2 sind dabei als zumindest teilweise autarke Arbeitsstellen ausgebildet. Dies bedeutet, dass die einzelnen Arbeitsstellen 2 über eine Vielzahl von Einzelantrieben zum Antrieb ihrer fadenproduzierenden Organe verfügen, so dass die einzelnen Arbeitsstellen auch unabhängig von den anderen Arbeitsstellen 2 der Spinnmaschine 1 betrieben werden können. Weiterhin können die Arbeitsstellen 2 zumindest einen Teil der im Betrieb auftretenden Störungen selbstständig beheben, ohne dass hierfür ein Bedienroboter oder das Eingreifen einer Bedienperson erforderlich wäre. An den Arbeitsstellen 2 sind daher noch weitere, hier nicht dargestellte Komponenten wie Handlingsorgane und Wartungsorgane angeordnet. Weiterhin ist an jeder der Arbeitsstellen 2 ein Anzeigeelement 12 vorgesehen, das beispielsweise verschiedene Betriebszustände der Arbeitsstellen 2 oder die jeweils produzierte Garnpartie anzeigen kann. Alternativ zu der gezeigten Darstellung ist es auch denkbar, dass jeweils zwei Arbeitsstellen 2 gemeinsam ein Anzeigeelement 12 zugeordnet ist. Figure 1 shows a schematic front view of a spinning machine 1 for producing cross-wound bobbins in an overview. The spinning machine 1 is designed as an automatic or at least partially automatic spinning machine 1 and has a large number of similar work stations 2 arranged next to one another, which are arranged between two end frames not specified here. Each of the work stations 2 has a feed device for a fiber material 7, which in the case of an open-end rotor spinning machine is designed as an opening roller 8 (see Figure 1 ). Furthermore, each of the work stations 2 has a spinning device 3 for producing a thread 6, a take-off device 9 for drawing off the produced thread 6 and a winding device 4 for winding the produced thread 6 onto a cross-wound bobbin 10. The work stations 2 are designed as at least partially self-sufficient work stations. This means that the individual work stations 2 have a large number of individual drives for driving their thread-producing organs, so that the individual work stations can also be operated independently of the other work stations 2 of the spinning machine 1. Furthermore, the work stations 2 can independently resolve at least some of the faults that occur during operation without the need for an operating robot or the intervention of an operator. Other components, not shown here, such as handling organs and maintenance organs, are therefore arranged at the work stations 2. Furthermore, a display element 12 is provided at each of the work stations 2, which can, for example, display various operating states of the work stations 2 or the respective yarn batch produced. As an alternative to the illustration shown, it is also conceivable that two work stations 2 are assigned a display element 12 together.

Figur 2 zeigt eine Arbeitsstelle 2 einer solchen Spinnmaschine 1 in einer schematischen Seitenansicht. Die Spinnmaschine 1 ist vorliegend als Offenend-Rotorspinnmaschine ausgebildet und weist daher als Zuführeinrichtung eine Auflösewalze 8 und als Spinnelement der Spinnvorrichtung 3 einen Spinnrotor 13 auf. Der im Spinnrotor 13 produzierte Faden 6 wird über eine Abzugsdüse 14 abgezogen und der Spulvorrichtung 4 zugeführt. Die Spulvorrichtung 4 weist einen Spulenhalter 5 auf, in welchem eine Leerhülse 11 (s. Fig. 9 und 10) aufgenommen ist, welche dann zu einer Kreuzspule 10 bewickelt werden kann. Zum Antreiben der Spulvorrichtung 4 ist vorliegend eine Spulwalze 19 vorgesehen. Die Einzelantriebe der zumindest teilweise autarken Arbeitsstellen 2 sowie weitere Handlingsorgane und Wartungsorgane der Arbeitsstellen 2 sind in Figur 2 ebenfalls nicht dargestellt. Figure 2 shows a work station 2 of such a spinning machine 1 in a schematic side view. The spinning machine 1 is designed as an open-end rotor spinning machine and therefore has an opening roller 8 as a feed device and a spinning rotor 13 as a spinning element of the spinning device 3. The thread 6 produced in the spinning rotor 13 is drawn off via a take-off nozzle 14 and fed to the winding device 4. The winding device 4 has a bobbin holder 5 in which an empty tube 11 (see Fig.9 and 10 ) which can then be wound into a cross-wound bobbin 10. A winding roller 19 is provided to drive the winding device 4. The individual drives of the at least partially self-sufficient work stations 2 as well as other handling and maintenance elements of the work stations 2 are in Figure 2 also not shown.

An derartigen Spinnmaschinen 1 mit zumindest teilweise autarken Arbeitsstellen 2 ist es möglich, mehrere Garnpartien gleichzeitig an verschiedenen Arbeitsstellen 2 herzustellen. Ein Partiewechsel von einer alten, noch aktuellen Garnpartie auf eine neue Garnpartie kann daher auch an einer einzelnen Arbeitsstelle 2 durchgeführt werden. Um einen Partiewechsel durchzuführen, sind nach dem Stillsetzen der Arbeitsstelle 2 in der Regel zahlreiche Umrüstarbeiten erforderlich, welche beispielsweise das Austauschen des vorgelegten Fasermaterials 7 sowie zumindest eines Teils der Spinnmittel, die hier durch den Spinnrotor 13, die Auflösewalze 8 sowie die Abzugsdüse 14 gebildet werden, umfassen. Weiterhin ist meist auch das Bereitstellen anderer Leerhülsen 11 (s. Fig. 9 und 10) erforderlich. Um die Stillstandszeiten und die damit verbundenen Produktionsausfälle der für einen Partiewechsel vorgesehenen Arbeitsstellen 2 möglichst gering zu halten, ist vorgesehen, dass an einer Arbeitsstelle 2, welche das Partieende erreicht hat, ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit angezeigt wird.On such spinning machines 1 with at least partially self-sufficient work stations 2, it is possible to produce several yarn batches simultaneously at different work stations 2. A batch change from an old, still current yarn batch to a new yarn batch can therefore also be carried out at a single work station 2. In order to carry out a batch change, numerous conversion operations are usually required after the work station 2 has been shut down, which include, for example, replacing the fiber material 7 provided and at least some of the spinning means, which here are formed by the spinning rotor 13, the opening roller 8 and the take-off nozzle 14. Furthermore, the provision of other empty tubes 11 (see Fig.9 and 10 ) is required. In order to keep the downtimes and the associated production losses of the work stations 2 intended for a batch change as low as possible, it is intended that a need to carry out at least one manual maintenance activity is indicated at a work station 2 which has reached the end of the batch.

Vorzugsweise erfolgt die Anzeige des manuellen Wartungsbedarfs durch ein optisches Anzeigeelement 12, wie im Folgenden anhand der Figuren 3 bis 8 erläutert wird. Alternativ ist es jedoch auch möglich, den Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch einen Belegungszustand des Spulenhalters 5 anzuzeigen, wie anhand der Figuren 9 und 10 beschrieben wird.Preferably, the manual maintenance requirement is indicated by an optical display element 12, as described below with reference to Figures 3 to 8 Alternatively, however, it is also possible to indicate the need to carry out at least one manual maintenance activity by an occupancy state of the coil holder 5, as can be seen from the Figures 9 and 10 described.

Figur 3 zeigt eine Ansicht eines optischen Anzeigeelements 12, welches vorliegend als grafisches Display 15 ausgebildet ist. Figur 3 zeigt dabei das Display 15 mit einer ersten Anzeige, die einen regulären Betriebszustand der Arbeitsstelle 2 anzeigt. In diesem regulären Betriebszustand wird die jeweils aktuelle Partie, hier bezeichnet mit "A", durch eine Farbanzeige 20 (hier hell gepunktet dargestellt) angezeigt. Weiterhin wird der reguläre Betriebszustand selbst durch ein leicht verständliches grafisches Symbol 16 angezeigt. Dem Anzeigeelement 12 ist eine Eingabevorrichtung 17 zugeordnet, mittels der der Bediener Eingaben vornehmen und mit einer hier nicht dargestellten Steuereinheit der Arbeitsstelle 2 und/oder einer ebenfalls nicht dargestellten zentralen Steuereinheit kommunizieren kann. Vorliegend sind das Anzeigeelement 12 bzw. das Display 15 und die Eingabevorrichtung 17 in einer Baueinheit kombiniert, sodass entsprechend die Eingabevorrichtung 17 durch verschiedene Schaltflächen 18 des Displays 15 gebildet wird. In der hier gezeigten Anzeige weist das Display 15 beispielsweise eine Schaltfläche 18 für den Informationsabruf auf. Durch Betätigen dieser Schaltfläche kann der Bediener in das Menü der Steuereinheit der Arbeitsstelle 2 gelangen und dort verschiedene Einstellungen vornehmen. Figure 3 shows a view of an optical display element 12, which is designed as a graphic display 15. Figure 3 The display 15 shows a first display that indicates a regular operating state of the workstation 2. In this regular operating state, the current batch, here designated "A", is shown by a color display 20 (shown here in light dots). Furthermore, the regular operating state itself is shown by an easily understandable graphic symbol 16. The display element 12 is assigned an input device 17, by means of which the Operators can make inputs and communicate with a control unit of workstation 2 (not shown here) and/or a central control unit (also not shown). In the present case, the display element 12 or the display 15 and the input device 17 are combined in one structural unit, so that the input device 17 is formed by various buttons 18 of the display 15. In the display shown here, the display 15 has, for example, a button 18 for retrieving information. By pressing this button, the operator can access the menu of the control unit of workstation 2 and make various settings there.

Figur 4 zeigt demgegenüber eine Ansicht des Anzeigeelements 12 bzw. des Displays 15, mit der bei Erreichen des Partieendes der betreffenden Arbeitsstelle 2 ein Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit angezeigt wird. Die noch aktuelle Partie wird nach wie vor durch die Farbanzeige 20 angezeigt. Der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit wird vorliegend durch ein weiteres, leicht verständliches grafisches Symbol 16 angezeigt. Das Bedienpersonal kann anhand dieses Symbols sehr schnell erkennen, dass an dieser Arbeitsstelle 2 manuelle Tätigkeiten durchzuführen sind und dadurch diese Arbeitsstellen 2 bevorzugt abarbeiten bzw. die Wartung der betreffenden Arbeitsstellen besser planen. Die Anzeige des Bedarfs zur Durchführung mindestens einer manuellen Wartungstätigkeit ist im vorliegenden Fall wiederum als Schaltfläche 18 ausgeführt, was vorliegend sowohl an dem die Schaltfläche 18 umgebenden Rahmen als auch an der Aufforderung zur Betätigung durch das Häkchen erkennbar ist. Betätigt der Bediener nun dieser Schaltfläche 18, so erhält er in einer folgenden Anzeige genauere Informationen dazu, welche konkreten Wartungstätigkeiten durchzuführen sind. Figure 4 shows a view of the display element 12 or the display 15, which indicates a need to carry out at least one manual maintenance activity when the end of the batch of the relevant work station 2 is reached. The current batch is still shown by the color display 20. The need to carry out at least one manual maintenance activity is shown here by another, easily understandable graphic symbol 16. The operating personnel can use this symbol to very quickly see that manual activities are to be carried out at this work station 2 and can therefore work on these work stations 2 preferentially or plan the maintenance of the relevant work stations better. The display of the need to carry out at least one manual maintenance activity is again designed as a button 18 in the present case, which can be recognized both by the frame surrounding the button 18 and by the prompt to actuate it by means of the check mark. If the operator now presses this button 18, he receives more detailed information on which specific maintenance activities are to be carried out in a subsequent display.

Figur 5 zeigt nun eine weitere Anzeige des Displays 15, welche dem Bediener nach Betätigung der Schaltfläche 18 der vorhergehenden Anzeige (Figur 4) oder, im allgemeinen Fall nach Betätigung der Eingabevorrichtung 17, die durchzuführende manuelle Wartungstätigkeit anzeigt. Im vorliegenden Beispiel wird dabei in Form eines Anzeigetextes die Aufgabe "Spinnmittel prüfen" (Check Spinning Components) angezeigt. Der Bediener erhält dadurch und ggf. durch Folgeanzeigen den Hinweis, dass er die Spinnmittel überprüfen und gegebenenfalls austauschen muss. Figure 5 now shows another display on the display 15, which the operator can see after pressing the button 18 of the previous display ( Figure 4 ) or, in the general case after actuating the input device 17, displays the manual maintenance activity to be carried out. In the present example, the task "Check Spinning Components" is displayed in the form of a display text. This and any subsequent displays inform the operator that he must check the spinning components and replace them if necessary.

Vorteilhaft dabei ist es, dass sowohl für Störungen im regulären Spinnbetrieb, welche zu einem Stillstand der Arbeitsstelle 2 führen, als auch bei einem Wartungsbedarf aufgrund eines anstehenden Partiewechsels dieselben Anzeigen verwendet werden können. Dem Bediener muss lediglich der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit angezeigt werden und er wird dann durch das Menü geführt und erhält Schritt für Schritt konkrete Handlungsanweisungen. Der Bediener muss daher nicht zwischen Störungen des regulären Betriebs und Partiewechsel unterscheiden und darüber nachdenken, welche manuellen Wartungstätigkeiten er in welchem Fall ausführen muss, sondern muss lediglich den nacheinander abrufbaren Handlungsanweisungen folgen, wie im Folgenden noch dargelegt wird.The advantage here is that the same displays can be used for both faults in regular spinning operations that lead to a standstill at work station 2 and when maintenance is required due to an upcoming batch change. The operator only needs to be informed that at least one manual maintenance activity needs to be carried out and is then guided through the menu and given step-by-step instructions. The operator therefore does not need to differentiate between faults in regular operations and batch changes and does not need to think about which manual maintenance activities he needs to carry out in which case, but simply needs to follow the instructions that can be called up one after the other, as will be explained below.

Natürlich wäre es ebenfalls denkbar, die durchzuführende manuelle Wartungstätigkeit nicht wie in Figur 5 in Form eines Anzeigetextes, sondern ebenfalls durch ein grafisches Symbol anzuzeigen. So ist beispielsweise in Figur 6 eine Anzeige des Displays 15 dargestellt, welche dem Bediener nach Betätigung der Schaltfläche 18 der vorhergehenden Anzeige (Figur 4) die Aufgabe "Spinnmittel tauschen" als durchzuführende manuelle Wartungstätigkeit anzeigt.Of course, it would also be conceivable not to perform the manual maintenance work as in Figure 5 in the form of a display text, but also by a graphic symbol. For example, in Figure 6 a display on the display 15 is shown, which the operator can see after pressing the button 18 of the previous display ( Figure 4 ) displays the task "Replace spinning device" as a manual maintenance activity to be performed.

Auch die Anzeigen der durchzuführenden manuellen Wartungstätigkeiten (Figuren 5 und 6) enthalten wiederum eine Schaltfläche 18, mittels welcher der Bediener nach Erledigung der Wartungstätigkeit deren Durchführung bestätigen muss. Nachdem der Bediener die Durchführung der Wartungstätigkeit bestätigt hat, kann ggf. noch eine weitere erforderliche manuelle Wartungstätigkeit angezeigt werden, deren Durchführung der Bediener ebenfalls wieder bestätigen muss, woraufhin gegebenenfalls eine weitere erforderliche manuelle Wartungstätigkeit angezeigt wird. Wenn dann alle erforderlichen manuellen Wartungstätigkeiten durchgeführt worden sind und durch den Bediener bestätigt worden sind, kann die Arbeitsstelle 2 selbstständig die Produktion wieder aufnehmen und die neue Partie starten.The displays of the manual maintenance activities to be carried out (Figures 5 and 6) also contain a button 18, by means of which the operator must confirm the execution of the maintenance activity after it has been completed. After the operator has confirmed the execution of the maintenance activity , another required manual maintenance activity may be displayed, which the operator must also confirm, whereupon another required manual maintenance activity may be displayed. Once all required manual maintenance activities have been carried out and confirmed by the operator, work station 2 can resume production independently and start the new batch.

Da der Austausch von Spinnmitteln im Falle eines Partiewechsels zeitaufwendig ist, kann es auch vorteilhaft sein, dem Bediener direkt den erforderlichen Spinnmitteltausch anzuzeigen. Dies ist in der Anzeige der Figur 7 dargestellt. Dabei wird die erforderliche Wartungstätigkeit "Spinnmittel tauschen" dem Bediener durch ein grafisches Symbol 16 angezeigt. Die Anzeige der erforderlichen Wartungstätigkeit ist dabei wiederum als Schaltfläche 18 ausgeführt, mittels welcher der Bediener die Durchführung der Wartungstätigkeit direkt bestätigen kann. In Display 15 wird weiterhin nach wie vor die noch aktuelle Partie mit der Farbanzeige 20 angezeigt. Auch die Schaltfläche 18 für den Informationsabruf ist enthalten. Dabei ist es denkbar, dass der Bediener diese Anzeige erhält, nachdem er die Schaltfläche der Figur 4 betätigt hat. Alternativ ist es aber auch möglich, dass die Anzeige "Spinnmittel tauschen" direkt erscheint, wenn die betreffende Arbeitsstelle 2 das Partieende erreicht hat. Das Bedienpersonal kann hierdurch auf den ersten Blick erkennen, dass der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit einen Partiewechsel mit Spinnmitteltausch betrifft und kann diese Arbeitsstellen 2 bevorzugt behandeln. Dies ist insbesondere auch dann von Vorteil, wenn für einen solchen Spinnmitteltausch besonders geschultes Personal erforderlich ist. Das Personal kann somit sofort erkennen, ob einfache manuelle Wartungstätigkeiten durchzuführen sind oder ein Spinnmitteltausch, für den das besonders geschulte Personal erforderlich ist.Since the exchange of spinning agents in the event of a batch change is time-consuming, it can also be advantageous to display the required spinning agent exchange directly to the operator. This is shown in the display of the Figure 7 The required maintenance activity "Replace spinning device" is displayed to the operator by a graphic symbol 16. The display of the required maintenance activity is again shown as a button 18, by means of which the operator can directly confirm that the maintenance activity has been carried out. The current batch is still shown in display 15 with the color display 20. The button 18 for retrieving information is also included. It is conceivable that the operator receives this display after he has pressed the button for the Figure 4 Alternatively, it is also possible for the "Change spinning agent" display to appear directly when the relevant work station 2 has reached the end of the batch. The operating personnel can thus see at first glance that the need to carry out at least one manual maintenance activity involves a batch change with a spinning agent change and can give priority to these work stations 2. This is particularly advantageous if specially trained personnel are required for such a spinning agent change. The personnel can thus immediately see whether simple manual maintenance activities are to be carried out or a spinning agent change for which specially trained personnel is required.

Um den Zeitaufwand für das Umrüsten der Arbeitsstellen 2 im Falle eines Partiewechsels weiter zu reduzieren, kann es zudem vorteilhaft sein, bereits im Vorfeld anzuzeigen, dass an der betreffenden Arbeitsstelle 2 ein Partiewechsel ansteht. Dies ist in der Anzeige der Figur 8 dargestellt. Die Arbeitsstelle 2 befindet sich noch im regulären Betrieb, was anhand des grafischen Symbols 16 erkennbar ist. Ebenso wie in Figur 4 ist zudem die Schaltfläche 18 für den Informationsabruf zu sehen. Im oberen Bereich des Displays 15 ist jedoch im Unterschied zur Darstellung der Figur 4 neben der Farbanzeige 20 der aktuellen Partie (hell gepunktet und mit "A" bezeichnet) auch die Farbanzeige 21 der neuen Partie (dunkel gepunktet und mit "B" bezeichnet) zu sehen. Der Bediener kann hierdurch bereits alle notwendigen Spinnmittel und dergleichen bereithalten und nach Beendigung der Partie, was durch die Anzeige gemäß der Figur 4 oder 7 erkennbar ist, den Spinnmitteltausch und alle sonstigen notwendigen Schritte durchführen.In order to further reduce the time required for retooling workstations 2 in the event of a batch change, it may also be advantageous to indicate in advance that a batch change is pending at the relevant workstation 2. This is indicated in the display of the Figure 8 Workstation 2 is still in regular operation, which can be seen from the graphic symbol 16. Just as in Figure 4 The button 18 for retrieving information is also visible. In the upper part of the display 15, however, in contrast to the representation of the Figure 4 In addition to the colour display 20 of the current batch (light dotted and marked "A"), the colour display 21 of the new batch (dark dotted and marked "B") can also be seen. The operator can thus have all the necessary spinning materials and the like ready and after the batch has been finished, which is indicated by the display according to the Figure 4 or 7 is recognizable, carry out the spinning agent exchange and all other necessary steps.

Die Figuren 9 bis 11 zeigen schließlich noch eine alternative Ausführung, bei der der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch den Belegungszustand des Spulenhalters 5 oder den Belegungszustand einer Vorratsposition 22 für Leerhülsen 11 angezeigt wird.The Figures 9 to 11 finally show an alternative embodiment in which the need to carry out at least one manual maintenance activity is indicated by the occupancy state of the spool holder 5 or the occupancy state of a supply position 22 for empty tubes 11.

So zeigt Figur 9 eine Situation, in welcher die Arbeitsstelle 2 das Partieende erreicht hat und bereits stillgesetzt wurde. In diesem Fall sind Leerhülsen 11 der neuen Partie bereits an der Spinnmaschine 1 bereitgestellt. Durch die Steuereinheit der Arbeitsstelle 2 und/oder der Spinnmaschine 1 wurde weiterhin der Partiewechsel bereits eingeleitet, indem eine Leerhülse 11 der neuen Partie in den Spulenhalter 5 eingelegt wurde, wie anhand der dunkel gepunkteten Farbe der Leerhülse erkennbar. Das Anzeigeelement 12 zeigt jedoch nach wie vor die Farbanzeige 20 der gerade beendeten, noch aktuellen Partie an. Die eingelegte Leerhülse 11 stimmt somit nicht mit der angezeigten Partie überein, sodass der Spulenhalter 5 den Zustand "Fehlbelegung" innehat. Das Bedienungspersonal kann somit anhand der stillstehenden Arbeitsstelle 2 sowie der Fehlbelegung des Spulenhalters erkennen, dass ein Partiewechsel ansteht und manuelle Tätigkeiten durchzuführen sind.This shows Figure 9 a situation in which workstation 2 has reached the end of the batch and has already been shut down. In this case, empty tubes 11 of the new batch are already provided at spinning machine 1. The batch change has already been initiated by the control unit of workstation 2 and/or spinning machine 1 by inserting an empty tube 11 of the new batch into bobbin holder 5, as can be seen from the dark dotted color of the empty tube. However, display element 12 still shows the color display 20 of the just finished, still current batch. The inserted empty tube 11 does not match the displayed batch, so that bobbin holder 5 has the "incorrectly loaded" status. Operating personnel can therefore recognize from the idle workstation 2 and the incorrect occupancy of the bobbin holder that a batch change is pending and manual activities must be carried out.

In ähnlicher Weise ist in Figur 10 die Arbeitsstelle 2 nach Erreichen des Partieendes und Stillsetzung gezeigt. Es wurde jedoch noch keine neue Leerhülse 11 eingelegt. Der Spulenhalter 5 hat somit den Belegungszustand "leer" inne. Das Bedienungspersonal kann nun wiederum anhand des Belegungszustandes "leer" sowie der Anzeige der noch aktuellen Partie erkennen, dass ein Partiewechsel ansteht und manuelle Tätigkeiten durchzuführen sind.Similarly, in Figure 10 the work station 2 is shown after the end of the batch has been reached and the machine has stopped. However, no new empty tube 11 has been inserted. The bobbin holder 5 is therefore in the "empty" state. The operating personnel can now see from the "empty" state and the display of the current batch that a batch change is pending and that manual activities must be carried out.

Figur 11 zeigt eine Arbeitsstelle 2, welche zusätzlich noch eine Vorratsposition für Leerhülsen 11 aufweist, wobei der Bedarf zur Durchführung mindestens einer manuellen Wartungstätigkeit durch die bereitgestellte Leerhülse 11 angezeigt wird. Die Arbeitsstelle 2 hat hier wiederum das Partieende erreicht und wurde bereits stillgesetzt. Ebenso wie bei Fig. 9 sind Leerhülsen 11 der neuen Partie bereits an der Spinnmaschine 1 bereitgestellt. Durch die Steuereinheit der Arbeitsstelle 2 und/oder der Spinnmaschine 1 wurde der Partiewechsel bereits eingeleitet, indem eine Leerhülse 11 der neuen Partie (dunkel gepunktete Farbe) in der Vorratsposition 22 bereitgestellt wurde, jedoch noch nicht in den Spulenhalter 5 eingelegt wurde. Der Spulenhalter 5 hat somit den Belegungszustand "leer" inne. Das Bedienungspersonal kann somit anhand der bereitgestellten Leerhülse und des Belegungszustandes "leer" des Spulenhalters erkennen, dass ein Partiewechsel ansteht und manuelle Tätigkeiten durchzuführen sind. Figure 11 shows a work station 2, which additionally has a supply position for empty tubes 11, whereby the need to carry out at least one manual maintenance activity is indicated by the empty tube 11 provided. Here, the work station 2 has again reached the end of the batch and has already been shut down. Just as with Fig.9 empty tubes 11 of the new batch are already provided on the spinning machine 1. The batch change has already been initiated by the control unit of the work station 2 and/or the spinning machine 1 by providing an empty tube 11 of the new batch (dark dotted color) in the supply position 22, but has not yet been inserted into the bobbin holder 5. The bobbin holder 5 therefore has the "empty" occupancy status. The operating personnel can therefore recognize from the empty tube provided and the "empty" occupancy status of the bobbin holder that a batch change is pending and that manual activities must be carried out.

Vorliegend wird zusätzlich noch die Farbanzeige 20 der gerade beendeten, noch aktuellen Partie durch das Anzeigeelement 12 angezeigt. Die in der Vorratsposition 22 bereitgestellte Leerhülse 11 stimmt somit nicht mit der angezeigten Partie überein, woraus das Bedienungspersonal ebenso erkennen kann, dass ein Partiewechsel ansteht und manuelle Tätigkeiten durchzuführen sind.In the present case, the color display 20 of the currently completed batch is also shown by the display element 12. The empty tube 11 provided in the supply position 22 therefore does not match the displayed batch, from which the operating personnel can also recognize that a batch change is pending and manual activities must be carried out. are.

Die Erfindung ist nicht auf die dargestellten Ausführungsbeispiele beschränkt. Abwandlungen, wie eine Kombination der Merkmale, auch wenn diese in unterschiedlichen Ausführungsbeispielen dargestellt und beschrieben sind, sind im Rahmen der Patentansprüche möglich.The invention is not limited to the embodiments shown. Modifications, such as a combination of features, even if these are shown and described in different embodiments, are possible within the scope of the patent claims.

BezugszeichenlisteList of reference symbols

11
Spinnmaschinespinning machine
22
Arbeitsstelleplace of work
33
SpinnvorrichtungSpinning device
44
SpulvorrichtungWinding device
55
SpulenhalterSpool holder
66
Fadenthread
77
FasermaterialFibre material
88th
AuflösewalzeOpening roller
99
AbzugsvorrichtungExtractor
1010
KreuzspuleCross-wound bobbin
1111
LeerhülseEmpty tube
1212
AnzeigeelementDisplay element
1313
SpinnrotorSpinning rotor
1414
AbzugsdüseExtractor nozzle
1515
DisplayDisplay
1616
grafisches Symbolgraphic symbol
1717
EingabevorrichtungInput device
1818
Schaltflächebutton
1919
SpulwalzeSpool roller
2020
Farbanzeige der aktuellen PartieColor display of the current game
2121
Farbanzeige der neuen PartieColor display of the new batch
2222
VorratspositionStock position

Claims (13)

  1. Method for operating a partially or fully automatic cross-wound bobbin-producing spinning machine (1), in particular an open-end rotor spinning machine, having a plurality of identical workstations (2) which are arranged next to one another and are at least partially self-sufficient, wherein each of the workstations (2) has a spinning device (3) for producing a thread (6) and a winding device (4), which has a bobbin holder (5), for winding the thread (6) onto a cross-wound bobbin (10), and wherein, when a batch end of one of the workstations (2) is reached, the relevant workstation (2) is stopped, characterized in that , at the workstation (2) which has reached the batch end, a requirement for carrying out at least one manual maintenance activity in the form of text or a graphic symbol (16) is displayed by an optical display element (12), which is assigned to the workstation (2) and is in the form of a graphic display (15).
  2. Method according to the preceding claim, characterized in that the respectively current batch is displayed at the workstations (2), in particular by a color indication (20).
  3. Method according to one of the preceding claims, characterized in that the requirement for carrying out at least one manual maintenance activity is displayed by an occupancy state of the bobbin holder (5) and/or by an occupancy state of an inventory position (22) for empty tubes (11) of the relevant workstation (2).
  4. Method according to one of the preceding claims, characterized in that, at the workstation (2) which has reached the batch end, a wound cross-wound bobbin (10) of a still current batch is automatically removed and the requirement for carrying out at least one manual maintenance activity is displayed by an empty bobbin holder (5).
  5. Method according to one of the preceding claims, characterized in that, at the workstation (2) which has reached the batch end, an empty tube (11) of a new batch is provided in the inventory position and the requirement for carrying out at least one manual maintenance activity is displayed by the provided empty tube (11).
  6. Method according to one of the preceding claims, characterized in that, at the workstation (2) which has reached the batch end, a wound cross-wound bobbin (10) of a still current batch is automatically removed and the empty tube (11) of the new batch is automatically inserted and the requirement for carrying out at least one manual maintenance activity is displayed by an incorrectly occupied bobbin holder (5).
  7. Method according to one of the preceding claims, characterized in that, after an input device (17), in particular a first push button (18), which is assigned to the display element (12) has been actuated, at least one first manual maintenance activity which is to be carried out is displayed by the display element (12).
  8. Method according to one of the preceding claims, characterized in that, after the operator has confirmed that the first manual maintenance activity has been carried out, in particular after a further push button (18) of the graphic display (15) has been actuated, a further manual maintenance activity which is to be carried out is displayed by the display element (12).
  9. Method according to one of the preceding claims, characterized in that a change of spinning means and/or a change of fiber material is displayed as a requirement for carrying out at least one manual maintenance activity or as a manual maintenance activity which is to be carried out.
  10. Method according to one of the preceding claims, characterized in that the first and/or the further manual maintenance activity is displayed in the form of a text display and/or in the form of a graphic symbol (16).
  11. Method according to one of the preceding claims, characterized in that, in the event of an imminent batch change at the relevant workstation (2), the new batch is also displayed, in particular by a color indication (21), in addition to the current batch.
  12. Method according to one of the preceding claims, characterized in that, after the operator has confirmed that the first and/or the at least one further manual maintenance activity has been carried out, the new batch is started at the workstation (2), preferably started independently by the workstation (2).
  13. Partially or fully automatic cross-wound bobbin-producing spinning machine (1), in particular an open-end rotor spinning machine, having a plurality of identical workstations (2) which are arranged next to one another and are at least partially self-sufficient, wherein each of the workstations (2) has a spinning device (3) for producing a thread (6) and a winding device (4), which has a bobbin holder (5), for winding the thread (6) onto a cross-wound bobbin (10), and having a control device and a display element (12) for carrying out the method according to one of the preceding claims.
EP20180356.6A 2019-06-19 2020-06-16 Method for operating a partially or fully automatic spinning machine for creating cross-wound spools Active EP3757264B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102019116646.2A DE102019116646A1 (en) 2019-06-19 2019-06-19 Method for operating a partially or fully automatic spinning machine that produces cross-wound bobbins

Publications (2)

Publication Number Publication Date
EP3757264A1 EP3757264A1 (en) 2020-12-30
EP3757264B1 true EP3757264B1 (en) 2024-08-07

Family

ID=71105285

Family Applications (1)

Application Number Title Priority Date Filing Date
EP20180356.6A Active EP3757264B1 (en) 2019-06-19 2020-06-16 Method for operating a partially or fully automatic spinning machine for creating cross-wound spools

Country Status (5)

Country Link
US (1) US20200399793A1 (en)
EP (1) EP3757264B1 (en)
JP (1) JP2021008699A (en)
CN (1) CN112111815B (en)
DE (1) DE102019116646A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102020129172A1 (en) 2020-11-05 2022-05-05 Maschinenfabrik Rieter Ag Process for maintaining at least one work station of a spinning machine
DE102020134251A1 (en) 2020-12-18 2022-06-23 Maschinenfabrik Rieter Ag Method for operating a partially or fully automatic spinning machine, in particular an open-end rotor spinning machine, and spinning machine
DE102021127096A1 (en) * 2021-10-19 2023-04-20 Maschinenfabrik Rieter Ag Cross-bobbin-producing textile machine with a large number of similar work stations arranged next to one another and an operating device that can be moved along the work stations, as well as a method for operating such a cross-bobbin-producing textile machine

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3139324A1 (en) * 2015-09-04 2017-03-08 Murata Machinery, Ltd. Textile machinery management system
DE102017104337A1 (en) * 2017-03-02 2018-09-06 Maschinenfabrik Rieter Ag Method for servicing workstations of a textile machine

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19648215A1 (en) * 1996-11-21 1998-06-18 Schlafhorst & Co W Open end spinning batch change
JPH11107075A (en) * 1997-10-02 1999-04-20 Murata Mach Ltd Machine stage control system in fiber machinery
DE19930714C5 (en) * 1999-07-02 2015-04-09 Rieter Ingolstadt Gmbh Textile machine with a variety of similar jobs
DE10142976A1 (en) * 2001-09-01 2003-03-20 Rieter Ingolstadt Spinnerei Control of textile plant with several multi-position machines and service units involves communication of control parameters between memory devices
DE102004044551B4 (en) * 2004-09-15 2017-08-31 Rieter Ingolstadt Gmbh Method for operating a spinning machine and spinning machine for carrying out this method
US7697850B2 (en) * 2005-10-31 2010-04-13 Infoprint Solutions Company, Llc Image-based printer system monitoring
DE102006014475A1 (en) * 2006-03-29 2007-10-04 Rieter Ingolstadt Spinnereimaschinenbau Ag Procedure for controlling a spinning preparation machine e.g. carding engine, drawing frame/rotor spinning machine, by determining input variables of a control device of the spinning machine so that parameter of the machine is optimized
DE102006045237A1 (en) * 2006-09-26 2008-04-03 Oerlikon Textile Gmbh & Co. Kg Winding machine comprises multiple winding points operated independently, and winding point calculator is provided, which is assigned to winding points
DE102008056288A1 (en) * 2008-11-08 2010-05-12 Oerlikon Textile Gmbh & Co. Kg Method for operating an open-end spinning machine and open-end spinning machine
JP2011037572A (en) * 2009-08-10 2011-02-24 Murata Machinery Ltd Spinning machine
DE102010044901A1 (en) * 2010-09-09 2012-03-15 Oerlikon Textile Gmbh & Co. Kg A method of operating a cheese-producing textile machine and cheese-producing textile machine
DE102013001599A1 (en) * 2013-01-30 2014-07-31 Saurer Germany Gmbh & Co. Kg Method for optimizing a lot change on an open-end spinning machine
DE102014008814A1 (en) * 2014-06-11 2015-12-17 Saurer Germany Gmbh & Co. Kg Semiautomatic open-end rotor spinning machine
DE102014008802A1 (en) * 2014-06-11 2015-12-17 Saurer Germany Gmbh & Co. Kg Semiautomatic open-end rotor spinning machine
DE102014018628A1 (en) * 2014-12-13 2016-06-16 Saurer Germany Gmbh & Co. Kg Multi-position textile machine
DE102015106470A1 (en) * 2015-04-27 2016-10-27 Maschinenfabrik Rieter Ag Method for operating a workstation of a textile machine and operating device
DE102015012214A1 (en) * 2015-09-17 2017-03-23 Saurer Germany Gmbh & Co. Kg A method of adjusting a factory design of an open end rotor spinning machine that concerns a yarn lot production
DE102015014429A1 (en) * 2015-11-10 2017-05-11 Saurer Germany Gmbh & Co. Kg Method for operating a cheese-producing textile machine
DE102017105700A1 (en) * 2017-03-16 2018-09-20 Maschinenfabrik Rieter Ag Textile machine with a variety of spinning or winding units and a method for operating the textile machine
DE102018100362A1 (en) * 2018-01-09 2019-07-11 Maschinenfabrik Rieter Ag Method for controlling displays of a spinning or winding machine

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3139324A1 (en) * 2015-09-04 2017-03-08 Murata Machinery, Ltd. Textile machinery management system
DE102017104337A1 (en) * 2017-03-02 2018-09-06 Maschinenfabrik Rieter Ag Method for servicing workstations of a textile machine

Also Published As

Publication number Publication date
DE102019116646A1 (en) 2020-12-24
JP2021008699A (en) 2021-01-28
CN112111815B (en) 2023-11-07
US20200399793A1 (en) 2020-12-24
CN112111815A (en) 2020-12-22
EP3757264A1 (en) 2020-12-30

Similar Documents

Publication Publication Date Title
EP3757264B1 (en) Method for operating a partially or fully automatic spinning machine for creating cross-wound spools
EP3802927B1 (en) Ring-spinning line and process thereof
EP3760772B1 (en) Optimization of the operation of a spinning machine
DE19930714C5 (en) Textile machine with a variety of similar jobs
EP3144418B1 (en) Method for adapting a work-side design of an open ended rotor spinning machine related to yarn section production
EP3239084A1 (en) Textile machine and method for operating the same
EP4215656A1 (en) Method for a spinning machine and spinning machine
EP3178975A1 (en) Method for producing elastic core yarn with a ring spinning machine
EP3617108B1 (en) Textile machine and method for controlling a textile machine
EP0329614B1 (en) Method and device for loading the bobbin creel of a winding machine
DE102018118654A1 (en) Method for operating a textile machine and textile machine
DE102015118987A1 (en) Method for operating a spinning machine with a fully automatic piecing device and spinning machine with a fully automatic piecing device
WO2005077801A1 (en) Device for winding up several bunches of threads
EP4015684A1 (en) Spinning machine and method for operating a partially or fully automatic spinning machine, in particular an open-end rotor spinning machine
DE10349094A1 (en) Textile machine and method for improving the production process
DE202021102188U1 (en) Spinning or winding machine
DE102004042115A1 (en) Method and device for optimizing winding and splicing parameters on a workstation of a textile machine producing cross-wound bobbins
DE102020004953A1 (en) texturing machine
EP3769966A1 (en) Colour assisted automatic control menu guide
EP4101958A1 (en) Spinning machine and method for operating a partially or fully automatic spinning machine, in particular an open-end rotor spinning machine
EP4169859A1 (en) Textile machine producing crosswound bobbins with a plurality of similar working units arranged side by side and a service device movable along the working units and method of operating such a textile machine
DE102020129172A1 (en) Process for maintaining at least one work station of a spinning machine
EP3875647B1 (en) Spinning machine and method for operating same
DE102009030677A1 (en) Method for operating a workstation and workstation of an open-end rotor spinning machine
DE102022126365A1 (en) Method for operating a spinning machine with a plurality of similar work stations arranged next to one another and spinning machine with a plurality of similar work stations arranged next to one another

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20210615

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20221021

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20240418

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

P01 Opt-out of the competence of the unified patent court (upc) registered

Free format text: CASE NUMBER: APP_41985/2024

Effective date: 20240716

RAP4 Party data changed (patent owner data changed or rights of a patent transferred)

Owner name: RIETER AG

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502020008785

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: DE

Ref legal event code: R081

Ref document number: 502020008785

Country of ref document: DE

Owner name: RIETER AG, CH