EP0894897A1 - Procédé de réalisation d'une voie - Google Patents
Procédé de réalisation d'une voie Download PDFInfo
- Publication number
- EP0894897A1 EP0894897A1 EP98810644A EP98810644A EP0894897A1 EP 0894897 A1 EP0894897 A1 EP 0894897A1 EP 98810644 A EP98810644 A EP 98810644A EP 98810644 A EP98810644 A EP 98810644A EP 0894897 A1 EP0894897 A1 EP 0894897A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- longitudinal
- sleepers
- spindles
- holes
- threshold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B3/00—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
- E01B3/28—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
- E01B3/38—Longitudinal sleepers; Longitudinal sleepers integral or combined with tie-rods; Combined longitudinal and transverse sleepers; Layers of concrete supporting both rails
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/005—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with sleeper shoes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/008—Drainage of track
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
- E01B2/003—Arrangement of tracks on bridges or in tunnels
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
- E01B29/005—Making of concrete parts of the track in situ
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/04—Direct mechanical or chemical fixing of sleepers onto underground
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/06—Height or lateral adjustment means or positioning means for slabs, sleepers or rails
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/09—Ballastless systems
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/10—Making longitudinal or transverse sleepers or slabs in situ or embedding them
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/13—Dowels for slabs, sleepers or rail-fixings
Definitions
- the invention relates to a method for creating a fixed Roadway with individual sleepers, with a stable surface created, laid the track, aligned and concreted becomes.
- the track is included in the track superstructure of this tunnel Provide two-block sleepers that were concreted in. To at one if necessary, replace the two-block sleepers can, they are each placed in a rubber shoe. To the The rails were laid in front of the tunnel with long rails attached Threshold blocks installed, driven into the tunnel on trains and finally with gantry cranes on the prepared one Roadway parked. After the long rails were laid these aligned and supported laterally on banquets. Subsequently became the space between the threshold blocks and the Top of the track bed filled with concrete. The disadvantage is this method in particular that the concrete works comparatively difficult and time-consuming and therefore expensive.
- the invention has for its object a method of the above Kind of creating a much simpler and allows faster track construction, especially for a tunnel section.
- the object is achieved according to claim 1 or 2.
- the slipform paver serves here at the same time also the track bracket.
- Such concreting in one Operation possible using a slipform paver a very quick and easy and therefore inexpensive Track construction, which is particularly suitable for railway tunnel construction.
- the invention also relates to a longitudinal threshold, a slab track and a train tunnel with such a slab Roadway.
- FIG. 1 shows a longitudinal threshold 28 that is still to be concreted, which is arranged at a distance from the top la of a sole 1.
- the sole 1 is part of a train tunnel.
- the sole 1 can also be another solid surface, for example an open route.
- the longitudinal threshold 28 is preferably made of concrete and has one Length of 2.4 m, for example.
- the ones not shown here further longitudinal sleepers 28 are lined up without gaps.
- a rail 13 is mounted on the top of the longitudinal threshold 28 .
- a plate Preferably resting the rail 13 according to Figure 3 on a plate, preferably is a rubber sheet.
- the attachment of the rail 3 on the Longitudinal threshold 28 is carried out in a known manner with bolts 23 and Clip 16.
- Figure 3 shows in detail a rail clamp 12, which is well known to the person skilled in the art and therefore not further here is explained.
- through holes 32 are machined into the longitudinal sleeper 28, which to accommodate two adjustment spindles 4 and 2 as Serve armature spindle 5. These through holes 32 are located each in a threshold compartment 40 between two anchor plates 22.
- the through holes 32 and those shown in Figure 3 Blind holes 36 for the bolts 23 are thus in the longitudinal direction the longitudinal threshold 28 arranged at a substantial distance from each other. This is essential for the strength of the longitudinal threshold 28.
- the holes 32 thus affect the strength of the Longitudinal threshold 28 is only insignificant.
- the armature spindles 5 and the adjusting spindles 4 are arranged diagonally. Under each through hole 36 is one in the sole 1 inserted anchor sleeve 6. The anchor spindles 5 are screwed with its lower end into such an anchor sleeve 6. The armature spindles 5 fix the longitudinal sleeper 28 the sole 1.
- the longitudinal threshold 8 is in a rubber shoe 18 set as an elastic intermediate layer.
- This has four Sealing sleeves 3, each in a through hole 32 and 36 intervene. These sealing sleeves 3 extend at least up to the upper edge 18a of the rubber shoe 18.
- In the through holes 32 are each a threaded sleeve 7, which has an internal thread 7a.
- the through holes 36 are each a guide sleeve 8 with a smooth Inner wall 8a used.
- FIGS. 7 and 10 are omitted in FIGS. 7 and 10.
- 32 adjustment spindles 4 are screwed into the through bores and thus the longitudinal sleepers 28 and those mounted thereon Rails 13 raised.
- the adjustment spindles 4 are these are each provided with a square neck 11 at the upper end.
- FIG. 8 shows only one adjustment spindle 4 shown.
- the second adjustment spindle, not shown here 4 is screwed diagonally into the longitudinal sleeper 28 here.
- every second longitudinal threshold 28 is a normal one Longitudinal threshold without through holes 32.
- FIG. 8 is under each through hole 36 in the sole 1 a blind hole 31 for receiving the anchor sleeve 6 mentioned above incorporated.
- each an armature spindle 5 is used.
- These anchor sleeves 5 each have an external thread 29 at the lower end for connection to the anchor sleeve 6 and at the top Male thread 39 on. There is a nut on the external thread 39 10 screwed, with which the longitudinal threshold 28 down be excited. After inserting the armature spindles 5 will be the longitudinal thresholds 28 fine-tuned in height. Go berserk the adjustment spindles 4, the longitudinal thresholds 28 are lowered or raised. The armature spindles 5 are turned accordingly the nuts 10 adapted to the height adjustment.
- FIG. 10 shows the concrete layer 33 that is brought in here as can be seen, does not go beyond the edge 18a.
- the tie rods not shown here are before continuously removed from the slipform paver and back again built-in.
- the slipform paver can do this at the same time be designed as a track holder.
- a suitable slipform paver is disclosed in applicant's EP-A-0 634 525.
- the longitudinal thresholds 28 are now a matter of course no longer movable. However, you can if necessary removed and replaced for repair. An expansion will made possible by the rubber shoe 18 and by a conical design the longitudinal sleepers 28 facilitated. This rubber shoe 18 can, however, also by other suitable means, for example with a suitable coating, for example with asphalt be replaced. In this case, the elastic intermediate layer, formed by the rubber shoe, in another place, for example between the rail and the threshold. Corrections in the position of the rails 13 are made later by appropriate settings of the rail clamp 12 possible.
- the method according to the invention is characterized by a very high performance. Especially when it comes to expensive tunnel construction save substantial costs due to the achievable higher performance.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CH1647/97 | 1997-07-07 | ||
CH164797 | 1997-07-07 |
Publications (1)
Publication Number | Publication Date |
---|---|
EP0894897A1 true EP0894897A1 (fr) | 1999-02-03 |
Family
ID=4215353
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP98810644A Withdrawn EP0894897A1 (fr) | 1997-07-07 | 1998-07-07 | Procédé de réalisation d'une voie |
Country Status (1)
Country | Link |
---|---|
EP (1) | EP0894897A1 (fr) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1039033A1 (fr) * | 1999-03-19 | 2000-09-27 | GSG Knape Gleissanierung GmbH | Méthode de réalisation d'une voie ferrée et son système d'alignement |
AT500110A1 (de) * | 2004-03-22 | 2005-10-15 | Wiener Linien Gmbh & Co Kg | Schotterloser hochschallgedämmter eisenbahnoberbau und verfahren zur herstellung desselben |
EP1775381A1 (fr) * | 2005-10-12 | 2007-04-18 | Volker Rail Nederland BV | Procédé pour le renouvellement de voies ferrées en tunnel |
EP2166149A2 (fr) * | 2008-09-22 | 2010-03-24 | edilon)(sedra GmbH | Unité de pièce de structure de voie ferrée |
CN101962924A (zh) * | 2010-09-30 | 2011-02-02 | 天津二十冶建设有限公司 | 焊接型轨道的安装方法 |
CN101967782A (zh) * | 2010-09-30 | 2011-02-09 | 中铁四局集团有限公司 | 城市轨道交通梯子形轨道施工方法 |
EP2740842A1 (fr) * | 2012-12-07 | 2014-06-11 | Sonneville AG | Procédé de transformation d'une voie ballastée dans une voie de circulation fixe |
GB2525940A (en) * | 2014-05-09 | 2015-11-11 | Lee Robb | DMCMD Railway |
CN107401091A (zh) * | 2017-09-19 | 2017-11-28 | 北京市轨道交通建设管理有限公司 | 一种装配式轨道结构及其施工方法 |
CN108411718A (zh) * | 2018-03-24 | 2018-08-17 | 安徽兴宇轨道装备有限公司 | 一种用于道床的调板工装 |
CN111270573A (zh) * | 2019-12-06 | 2020-06-12 | 中铁宝桥集团有限公司 | 一种中低速磁浮轨排锚固装置及安装调整方法 |
CN112900161A (zh) * | 2021-01-27 | 2021-06-04 | 中铁十二局集团有限公司 | 隧道套靴式弹性支承块整体道床施工工法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4007710A1 (de) * | 1990-03-10 | 1991-09-12 | Dyckerhoff & Widmann Ag | Verfahren zum herstellen eines eisenbahnoberbaus im tunnel |
EP0634525A1 (fr) | 1993-07-16 | 1995-01-18 | Walo Bertschinger AG | Machine à coffrage glissant |
EP0681061A2 (fr) * | 1994-05-02 | 1995-11-08 | Walter Bau-Aktiengesellschaft | Superstructure sans ballast pour voies ferrées et procédé pour sa fabrication |
FR2731238A1 (fr) * | 1995-03-02 | 1996-09-06 | Vagneux Traverses Beton | Procede de pose d'une voie ferree et dalle prefabriquee pour la mise en oeuvre de ce procede |
-
1998
- 1998-07-07 EP EP98810644A patent/EP0894897A1/fr not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4007710A1 (de) * | 1990-03-10 | 1991-09-12 | Dyckerhoff & Widmann Ag | Verfahren zum herstellen eines eisenbahnoberbaus im tunnel |
EP0634525A1 (fr) | 1993-07-16 | 1995-01-18 | Walo Bertschinger AG | Machine à coffrage glissant |
EP0681061A2 (fr) * | 1994-05-02 | 1995-11-08 | Walter Bau-Aktiengesellschaft | Superstructure sans ballast pour voies ferrées et procédé pour sa fabrication |
FR2731238A1 (fr) * | 1995-03-02 | 1996-09-06 | Vagneux Traverses Beton | Procede de pose d'une voie ferree et dalle prefabriquee pour la mise en oeuvre de ce procede |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1039033A1 (fr) * | 1999-03-19 | 2000-09-27 | GSG Knape Gleissanierung GmbH | Méthode de réalisation d'une voie ferrée et son système d'alignement |
AT500110A1 (de) * | 2004-03-22 | 2005-10-15 | Wiener Linien Gmbh & Co Kg | Schotterloser hochschallgedämmter eisenbahnoberbau und verfahren zur herstellung desselben |
AT500110B1 (de) * | 2004-03-22 | 2006-08-15 | Wiener Linien Gmbh & Co Kg | Schotterloser hochschallgedämmter eisenbahnoberbau und verfahren zur herstellung desselben |
EP1775381A1 (fr) * | 2005-10-12 | 2007-04-18 | Volker Rail Nederland BV | Procédé pour le renouvellement de voies ferrées en tunnel |
EP2166149A3 (fr) * | 2008-09-22 | 2011-06-15 | edilon)(sedra GmbH | Unité de pièce de structure de voie ferrée |
EP2166149A2 (fr) * | 2008-09-22 | 2010-03-24 | edilon)(sedra GmbH | Unité de pièce de structure de voie ferrée |
CN101962924B (zh) * | 2010-09-30 | 2012-02-08 | 天津二十冶建设有限公司 | 焊接型轨道的安装方法 |
CN101967782A (zh) * | 2010-09-30 | 2011-02-09 | 中铁四局集团有限公司 | 城市轨道交通梯子形轨道施工方法 |
CN101962924A (zh) * | 2010-09-30 | 2011-02-02 | 天津二十冶建设有限公司 | 焊接型轨道的安装方法 |
EP2740842A1 (fr) * | 2012-12-07 | 2014-06-11 | Sonneville AG | Procédé de transformation d'une voie ballastée dans une voie de circulation fixe |
US9260821B2 (en) | 2012-12-07 | 2016-02-16 | Sonneville Ag | Method for converting a ballasted track into a slab track |
GB2525940A (en) * | 2014-05-09 | 2015-11-11 | Lee Robb | DMCMD Railway |
GB2525940B (en) * | 2014-05-09 | 2021-03-10 | Robb Lee | DMCMD Railway (New railway compatible with existing railway infrastructure) |
CN107401091A (zh) * | 2017-09-19 | 2017-11-28 | 北京市轨道交通建设管理有限公司 | 一种装配式轨道结构及其施工方法 |
CN107401091B (zh) * | 2017-09-19 | 2023-08-18 | 北京市轨道交通建设管理有限公司 | 一种装配式轨道结构及其施工方法 |
CN108411718A (zh) * | 2018-03-24 | 2018-08-17 | 安徽兴宇轨道装备有限公司 | 一种用于道床的调板工装 |
CN111270573A (zh) * | 2019-12-06 | 2020-06-12 | 中铁宝桥集团有限公司 | 一种中低速磁浮轨排锚固装置及安装调整方法 |
CN112900161A (zh) * | 2021-01-27 | 2021-06-04 | 中铁十二局集团有限公司 | 隧道套靴式弹性支承块整体道床施工工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE19837360C2 (de) | Einbauverfahren für eine feste Schienenfahrbahn | |
DE3736943C1 (de) | Eisenbahnoberbau,insbesondere fuer sehr hohe Fahrgeschwindigkeiten | |
EP0894897A1 (fr) | Procédé de réalisation d'une voie | |
DE102006005376A1 (de) | Feste Fahrbahn für Schienenfahrzeuge | |
DE4415363C1 (de) | Eine feste Fahrbahn bildender Oberbau für Schienenbahnen, insb. für Brücken und Verfahren zu seiner Herstellung | |
DD284066A5 (de) | Anordnung zur ausbildung von eisenbahnoberbauten | |
DE19849266C2 (de) | Feste Fahrbahn für eine Straßenbahn | |
CH715209A2 (de) | Gleiskörperübergangseinheit zwischen einem Schottergleisabschnitt und einem schotterlosen Gleisabschnitt. | |
DE2503590A1 (de) | Blockschienen-gleissystem mit gummiabbindung | |
DE10236534B3 (de) | Feste Fahrbahn und Verfahren zu ihrer Herstellung | |
DE3824132A1 (de) | Verfahren zur verbindung eines gleisrostes mit einem eine feste fahrbahn bildenden oberbau fuer schienenbahnen | |
DE3440247A1 (de) | Schalung fuer serienfertigteile aus stahlbeton, vornehmlich fuer vorgespannte weichenschwellen | |
EP0456147B1 (fr) | Structure de voie ferrée | |
DE102004019083A1 (de) | Verfahren zum Verlegen eines Gleisstranges | |
AT505821B1 (de) | Verfahren und anordnung zum ausrichten vorgefertigter betontragplatten sowie tragbalkenelement zur verwendung in dem verfahren und der anordnung | |
EP1891271B1 (fr) | Traverse de levage et d'orientation | |
EP2800833B1 (fr) | Voie ferrée sans ballast | |
DE19620638C2 (de) | Gleisoberbau | |
DE102012103001A1 (de) | Feste Fahrbahn für Schienenfahrzeuge sowie Schienenbefestigungselement für eine feste Fahrbahn | |
DE69916641T2 (de) | Verbesserungen an oder in bezug auf bahnanlagen für schienenfahrzeuge | |
DE19608523C1 (de) | Befestigung einer Y-förmigen Stahlschwelle auf einer festen Fahrbahn und Verfahren zur Befestigung | |
DE4325869C2 (de) | Feste Fahrbahn für schienengebundenen Verkehr | |
DE4326306C2 (de) | Gleisüberwegplatte mit Spurrillenabdeckung | |
DE19920075A1 (de) | Lagerung einer Schiene für Schienenfahrzeuge | |
DE1220879B (de) | Unterfuehrungsbauwerk und Verfahren zu seinem nachtraeglichen Einbau |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT CH DE FR GB LI |
|
AX | Request for extension of the european patent |
Free format text: AL;LT;LV;MK;RO;SI |
|
17P | Request for examination filed |
Effective date: 19990628 |
|
AKX | Designation fees paid |
Free format text: AT CH DE FR GB LI |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20010201 |