CN110488782A - Cement concrete batching plant back court intelligent monitor system based on BIM platform - Google Patents

Cement concrete batching plant back court intelligent monitor system based on BIM platform Download PDF

Info

Publication number
CN110488782A
CN110488782A CN201910788327.2A CN201910788327A CN110488782A CN 110488782 A CN110488782 A CN 110488782A CN 201910788327 A CN201910788327 A CN 201910788327A CN 110488782 A CN110488782 A CN 110488782A
Authority
CN
China
Prior art keywords
concrete
data
cement
analysis
error
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910788327.2A
Other languages
Chinese (zh)
Inventor
姬同庚
张超
侯钦涛
陈宝光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Roadbridge Group Co Ltd
Original Assignee
PowerChina Roadbridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Roadbridge Group Co Ltd filed Critical PowerChina Roadbridge Group Co Ltd
Priority to CN201910788327.2A priority Critical patent/CN110488782A/en
Publication of CN110488782A publication Critical patent/CN110488782A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41875Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by quality surveillance of production
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32252Scheduling production, machining, job shop
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Graphics (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Quality & Reliability (AREA)
  • Automation & Control Theory (AREA)
  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

The invention discloses a kind of cement concrete batching plant back court intelligent monitor system based on BIM platform, the system passes through dynamic monitoring module, statistical analysis module and automatic alarm module, intelligent acquisition, shared, analysis, anticipation, storage are carried out to mixing station production information, the real time remote intelligent monitoring and management of concrete quality during mixing and stirring to cement concrete are realized, to ensure the quality safety of project subject structural concrete.The system makes full use of BIM platform storing data, solves the problems, such as that scarce capacity is locally stored in wireless terminal device, while the intercommunication with other system datas based on BIM may be implemented, to realize the efficient management control of construction quality.

Description

Cement concrete batching plant back court intelligent monitor system based on BIM platform
Technical field
The invention belongs to concrete mixing quality intelligent control fields, and in particular to a kind of cement based on BIM platform is mixed Solidifying soil batching plant back court intelligent monitor system.
Background technique
BIM(Building Information Model) it is the revolutionary platform of Transportation Infrastructure Construction industry, the platform is in engineering structure On the basis of solid threedimensional modeling, in addition mathematical information technology, so that buildings model digitlization and intelligence, it is one complete Architecture information abundant, logic library.Although having there is the BIM of comparison system theoretical at present, building letter is still suffered from It ceases model and applies monistic problem, do not extend further and extend its application, i.e., there are no maximum journeys for its application potential Degree it is mined.
Highway Construction Project Based project scale is huge, and construction site is complicated, uncertain very big, therefore reinforces construction site peace Full management reduces accident occurrence frequency, prevents various violation operations and uncivil construction, raising project delivery method, is existing rank Section is very urgent.And the quality monitoring of cement concrete then belongs to one of important link.
On the one hand, during concrete configures, influence factor is numerous, such as aggregate proportion, cement amount, fine coal ash quantity, The deviation of any one data can all directly affect concrete quality to the end;On the other hand, some concrete production producers In order to reduce cost, try to gain profit, there is the appearance of phenomena such as change proportion, use inferior materials and turn out substandard goods, cause concrete quality not up to standard.Coagulation The quality of geotechnological journey is formed in the construction process, the quality of concrete works from checking on afterwards, turns to Prior Control, real It now aims at prevention, it is necessary to reinforce the quality control in work progress, therefore the concrete process of mixing and stirring is monitored in real time very It is necessary to.
Summary of the invention
The purpose of the present invention is in view of the deficiencies of the prior art, a kind of cement concrete based on BIM platform is provided and is mixed and stirred Building back court intelligent monitor system, the intellectualizing system that BIM platform is combined with cement concrete batching plant, by being directed to mix Cement concrete was mixed and stirred in the scheme of the procedures such as the intelligent acquisition for production information of standing, shared, analysis, anticipation, storage, realization The real time remote intelligent monitoring and management of concrete quality in journey, to ensure the quality safety of project subject structural concrete.
The present invention solves technical problem by the following technical programs: a kind of cement concrete batching plant based on BIM platform Back court intelligent monitor system.The system includes dynamic monitoring module, statistical analysis module and automatic alarm module.The dynamic prison Control module can monitor in real time and automatic collection mixing station concrete production data, and passes through GPRS network for monitoring information data It is sent to statistical analysis module in real time.The statistical analysis module is by comparing point concrete production data and target value Analysis, when error amount exceeds allowable error range, relevant information is sent to quality control officer's by automatic alarm module in real time Mobile phone terminal, timely early warning.
Specifically, the mixing station concrete production data include mixing station production status, raw material ratio parameter, mix and stir The concrete raw material matching parameter cumulative errors that time, strength grade of concrete cumulative errors and transport vehicle are loaded.
Specifically, the mixing station production status includes that same day production is not controlled, the same day does not produce, the same day produces and controlled Deng three kinds of states.
Specifically, the raw material ratio parameter includes aggregate proportion, cement amount, coal amount, water-cement ratio, ginseng proportion, mixes Close the design parameters such as yield.The cement concrete batching plant back court intelligent monitoring based on BIM platform that present invention simultaneously provides above-mentioned The working method of system, specifically includes following steps.
1, creation data, error can float the information such as limit in advance typing: in systems shift to an earlier date typing cement concrete It mixes and stirs in the analysis of time, error statistics, transportational process that raw material ratio parameter, every biscuit needed for process mix and stir again Standard of the data such as error analysis as error analysis.Wherein raw material ratio parameter includes aggregate proportion, cement amount, fine coal again The design parameters such as amount, water-cement ratio, ginseng proportion, mix yield.Meanwhile to set error in systems and can float limit, generally It is expressed as a percentage, i.e., the percent value for allowing to float up and down on the basis of theoretical value.But it does not seek unity of standard for the mixing time, Therefore it needs that design value has been separately provided.Typing administrator contact method need to be shifted to an earlier date simultaneously to facilitate subsequent SMS alarm.
2, cement concrete batching plant real time data acquisition: in batching plant production process, for arrangement above standard Data, data acquisition is carried out for different data by distinct methods such as sensor, electronic components, by coagulating cement Native mixing station control room mounting industrial grade data acquisition hardware terminal cooperates corresponding software system, real-time, every a batch of automatic collection The truthful data of secondary production material, the data of required acquisition specifically include cement concrete and mix and stir raw material ratio needed for process Time that parameter, every biscuit mix and stir, error statistics analysis, error analysis again in transportational process etc..And raw material ratio is joined Number includes the design parameters such as aggregate proportion, cement amount, coal amount, water-cement ratio, ginseng proportion, mix yield again.
3, BIM platform database is transferred data to: by GPRS network that data are non-delay by wireless transmission terminal It is sent to system centre database, system carries out production status analysis to it.
4, data processing and cumulative errors analysis:, system automatically analyzes the data letter of every tray concrete of mixing station production Breath (aggregate proportion, cement amount, fine coal ash quantity, water-cement ratio, ginseng proportion, mix yield etc.) is simultaneously wanted with the technique of input system in advance Comparison is asked, while carrying out production status analysis, and is a certain automatically according to the strength grade of same day a part and according to the same day Cement concrete tank car license number carries out the analysis of accumulated error.
5, it SMS alarm: when the quality of production is not up to code requirement, is then sent out automatically by system to specified mobile phone number SMS alarm is sent, indicates the cement concrete quality dissatisfaction of corresponding position or corresponding vehicle.Wherein, the bound of SMS alarm Standard and phone number are also required in input system in advance.
The data of the system monitoring specifically include cement concrete and mix and stir raw material ratio parameter, every disk needed for process Expect the time mixed and stirred, error statistics analysis, error analysis again in transportational process etc..And raw material ratio parameter includes bone Expect the design parameters such as proportion, cement amount, coal amount, water-cement ratio, ginseng proportion, mix yield.
The function that the system need to be realized can be divided into two classes: basic function and specific function.Basic function is similar at this stage Related function, including creation data real time monitoring and SMS alarm prompt are had like system.And specific function is mainly For designed by Communication and Transportation Engineering and BIM platform, specifically include production status analysis, according to the tired of strength grade and position It counts error analysis, carry out accumulated error three functions of analysis according to concrete tank license number.
Concrete function is described below.
1, creation data monitors in real time: monitoring and acquire each concrete mixing station every biscuit mixing time in real time, material is used The data such as amount, and it is transferred to management platform, the automatic alert when dosage deviates is mixed with reaching monitored concrete With the purpose of time and proportion.
2, SMS alarm prompts: system is to each blending station SMS alarm project, each material utilization amount bound standard, alarm hand The information such as machine number are configured.All there are three standards for the alarm level of every kind of material, and the bound of 3 kinds of ranks can be respectively set Standard and alarm mobile phone number, are filled in from primary to advanced sequence.If you do not need to then only setting primary criteria is multistage standard Can, standard in percentage, i.e., the percent value for allowing to float up and down on the basis of theoretical value.Wherein the mixing time is not due to uniting One standard needs that design value is separately provided.
3, production status is analyzed: the system can count the life of each batching plant according to bid section, time range respectively Occurrence history category data and producing days, and production status is divided into following three kinds according to the case where creation data: the same day produces The not controlled, same day does not produce, the same day produces and controlled.The same day produces the not controlled creation data for referring to batching plant not when the sky Reach monitor supervision platform;The same day, which does not produce, refers to that the batching plant same day does not produce, therefore does not have the data on the same day on monitor supervision platform;The same day It produces and the controlled creation data for referring to batching plant is uploaded to monitor supervision platform in real time on the day of.
4, analyze according to the accumulated error at strength grade and position: the accumulation at a certain position misses on the day of system programming count Difference, if error exceeds allowed band, automatic short message alarm.
5, accumulated error analysis is carried out according to concrete tank license number: a certain bright concrete tank on the day of system programming count The accumulated error of the concrete loaded, if error exceeds allowed band, automatic information alarm.
Compared with prior art, the present invention compared with prior art, has following remarkable advantage.
1, BIM platform relevant to highway construction is combined closely, and passes through the new skills such as Internet of Things, communication cloud, BIM technology The comprehensive raising site management level of art, realize to people, machine, material comprehensive implementing monitoring, be transport development industry intelligence Energyization manages the much progress in Internet of Things application aspect.
2, the implementing monitoring of concrete quality during concrete batching and mixing plant mixes and stirs is realized, process can be collected in real time In all data, and timely feedback to administrative staff, to realize real time monitoring, improve the purpose of concrete management level.
3, for being unsatisfactory for the match ratio concrete of construction requirement and quality criteria requirements, do not allow to transport batching plant, it is real Now to effective control of concrete quality, prevent to use inferior materials and turn out substandard goods, it is ensured that the quality of highway construction project.Data in platform can have Effect saves, and system can be summarized to it and be carried out efficient system analysis, conducive to the sustained improvement and raising produced later.
4, the system function is powerful, with safe and secret, reliable, expansible, oncurrent processing ability is strong, service ability is powerful The advantages that.
Detailed description of the invention
Fig. 1 is the system block diagram of the embodiment of the present invention.
Fig. 2 is the cement concrete batching plant quality intelligent monitoring flow chart of the embodiment of the present invention.
Specific embodiment
The cement concrete batching plant back court intelligent monitor system based on BIM platform of the present embodiment is as shown in Figure 1, include Dynamic monitoring module, statistical analysis module and automatic alarm module three parts.The dynamic monitoring module real time monitoring is adopted automatically Collect mixing station concrete production data, and statistical analysis module is sent for monitoring information data by GPRS network in real time.Institute Statistical analysis module is stated by comparing and analyzing concrete production data with target value, when error amount exceeds allowable error model When enclosing, relevant information is sent to the mobile phone terminal of quality control officer, timely early warning by automatic alarm module in real time.
The method that system utilizes penetration quality dynamic management produces number to mixing station using the technology of Internet of things of software and hardware combining According to effectively being monitored, and the statistical analysis of each dimension is carried out to creation data, the long-range prison of concrete production may be implemented Control and management, have accomplished the Prior Control of concrete quality, it is ensured that the quality safety of project subject structural concrete.
Its specific monitoring flow chart in batching plant as shown in Fig. 2, obtain the every terms of information number in the techniques such as production, transport According to, and it is uploaded to BIM platform in real time, system automatically calculates data, handled and is analyzed, and according to the production of typing in advance Standard and error can float limit carry out error analysis, if exceed allowed band, system from trend specified mobile phone number issue Alarm message, to achieve the purpose that monitor cement concrete quality.
Specifically, first in systems shift to an earlier date typing cement concrete mix and stir raw material ratio parameter needed for process, The marks of the data as error analysis such as time that every biscuit mixes and stirs, error statistics analysis, error analysis again in transportational process It is quasi-.Wherein raw material ratio parameter includes the tools such as aggregate proportion, cement amount, coal amount, water-cement ratio, ginseng proportion, mix yield again Body parameter.Meanwhile the error upper limit is set in systems, it is generally expressed as a percentage, i.e., allows up and down on the basis of theoretical value The percent value of floating.But do not seek unity of standard for the mixing time, it is therefore desirable to design value be separately provided.
Secondly, for the data of arrangement above standard, passing through sensor, electronic component in batching plant production process Equal distinct methods carry out data acquisition for different data, by cement concrete batching plant control room mounting industrial series According to acquisition hardware middle section, cooperates corresponding software, data are uploaded to by GPRS network by BIM by wireless transmission terminal in time and are put down Platform central database is analyzed.It can carry out real time data acquisition and production status analysis daily for each batching plant.
After data collection and analysis, system will be automatically according to the strength grade of same day a part and according to the same day One cement concrete tank car license number carries out the analysis of accumulated error, if error analysis exceeds allowed band, automatically by System sends SMS alarm to specified mobile phone number, indicates the cement concrete quality dissatisfaction of corresponding position or corresponding vehicle. Wherein, the bound standard of SMS alarm and phone number are also required in input system in advance.

Claims (3)

1. a kind of cement concrete batching plant back court intelligent monitor system based on BIM platform, including it is arranged in cement concrete The intelligent monitoring and controlling device of batching plant production process, transportational process, it is characterised in that: using the method for penetration quality dynamic management, use The technology of Internet of things of software and hardware combining effectively monitors batching plant creation data, and carries out each dimension to creation data Statistical analysis, realize the Distant supervision and control of concrete production, accomplish the Prior Control of concrete quality, it is ensured that engineering master The quality safety of body structural concrete;
Its monitor process the following steps are included:
A. creation data, error can float the information such as limit in advance typing: in systems shift to an earlier date typing cement concrete mix and stir Time that raw material ratio parameter, every biscuit needed for process are mixed and stirred, error statistics analysis, the error again in transportational process The standards of the data as error analysis such as analysis;Wherein raw material ratio parameter include again aggregate proportion, cement amount, coal amount, The design parameters such as water-cement ratio, ginseng proportion, mix yield;Meanwhile to set error in systems and can float limit, generally with hundred Divide than indicating, i.e., the percent value for allowing to float up and down on the basis of theoretical value;But it does not seek unity of standard for the mixing time, therefore It needs that design value has been separately provided;
B. cement concrete batching plant real time data acquisition: in batching plant production process, for the number of arrangement above standard According to by distinct methods such as sensor, electronic components for different data progress data acquisitions, by being mixed in cement concrete Station control room mounting industrial grade data acquisition hardware terminal is closed, corresponding software system, real-time, each batch life of automatic collection are cooperated The truthful data of material is produced, the data of required acquisition specifically include cement concrete and mix and stir the ginseng of raw material ratio needed for process Time that several, every biscuit mixes and stirs, error statistics analysis, error analysis again in transportational process etc.;And raw material ratio parameter It again include the design parameters such as aggregate proportion, cement amount, coal amount, water-cement ratio, ginseng proportion, mix yield;
C. it transfers data to BIM platform database: relying on GPRS network by the non-delay transmission of data by wireless transmission terminal To system centre database, system carries out production status analysis to it;
D. data processing and cumulative errors analysis:, system automatically analyzes the data information (bone of every tray concrete of mixing station production Expect proportion, cement amount, fine coal ash quantity, water-cement ratio, ginseng proportion, mix yield etc.) and ratio is required with the technique of input system in advance It is right, while production status analysis is carried out, and automatically according to the strength grade of same day a part and according to a certain water of the same day The analysis of cement concrete tank car license number progress accumulated error;
E. it SMS alarm: when the quality of production is not up to code requirement, is then sent automatically by system to specified mobile phone number short Letter alarm indicates the cement concrete quality dissatisfaction of corresponding position or corresponding vehicle;Wherein, the bound standard of SMS alarm It is also required in input system in advance with phone number.
2. farm monitoring system after the cement concrete batching plant according to claim 1 based on BIM platform, feature exist In: the system needs to realize two class functions: basic function and specific function;Basic function is that similar system has at this stage Related function, including creation data real time monitoring and SMS alarm prompt;And specific function is primarily directed to communications and transportation Designed by engineering and BIM platform, specifically include production status analysis, analyzed according to the cumulative errors at strength grade and position, Accumulated error, which is carried out, according to concrete tank license number analyzes three functions.
3. farm monitoring system after the cement concrete batching plant according to claim 2 based on BIM platform, feature exist In five kinds of functions are specifically described as follows:
A. creation data monitors in real time: monitoring and acquire each concrete mixing station every biscuit mixing time, material utilization amount etc. in real time Data, and it is transferred to management platform, the automatic alert when dosage deviates, when being mixed and stirred with reaching monitored concrete Between and proportion purpose;
B. SMS alarm prompts: system is to each blending station SMS alarm project, each material utilization amount bound standard, alarm mobile phone number The information such as code are configured;All there are three standards for the alarm level of every kind of material, and the bound standard of 3 kinds of ranks can be respectively set With alarm mobile phone number, filled in from primary to advanced sequence;If you do not need to primary criteria, mark is then only arranged in multistage standard It is quasi- in percentage, i.e., the percent value for allowing to float up and down on the basis of theoretical value;Wherein the mixing time uniformly marks due to not having Standard needs that design value is separately provided;
C. production status is analyzed: the system can count the production shape of each batching plant according to bid section, time range respectively History category data and producing days, and production status is divided into following three kinds according to the case where creation data: same day production not by Control, the same day do not produce, the same day produces and controlled;The same day produces the not controlled creation data for referring to batching plant and is not uploaded on the day of Monitor supervision platform;The same day, which does not produce, refers to that the batching plant same day does not produce, therefore does not have the data on the same day on monitor supervision platform;Same day production And the controlled creation data for referring to batching plant is uploaded to monitor supervision platform in real time on the day of;
D. it is analyzed according to the accumulated error at strength grade and position: the accumulated error at a certain position on the day of system programming count, such as Fruit error exceeds allowed band, automatic short message alarm;
E. carry out accumulated error analysis according to concrete tank license number: a certain bright concrete tank is filled on the day of system programming count The accumulated error of the concrete of load, if error exceeds allowed band, automatic information alarm.
CN201910788327.2A 2019-08-26 2019-08-26 Cement concrete batching plant back court intelligent monitor system based on BIM platform Pending CN110488782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910788327.2A CN110488782A (en) 2019-08-26 2019-08-26 Cement concrete batching plant back court intelligent monitor system based on BIM platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910788327.2A CN110488782A (en) 2019-08-26 2019-08-26 Cement concrete batching plant back court intelligent monitor system based on BIM platform

Publications (1)

Publication Number Publication Date
CN110488782A true CN110488782A (en) 2019-11-22

Family

ID=68553897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910788327.2A Pending CN110488782A (en) 2019-08-26 2019-08-26 Cement concrete batching plant back court intelligent monitor system based on BIM platform

Country Status (1)

Country Link
CN (1) CN110488782A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111432035A (en) * 2020-04-24 2020-07-17 毕埃慕(上海)建筑数据技术股份有限公司 Building operation and maintenance monitoring and alarming system and method based on BIM
CN112650132A (en) * 2021-01-12 2021-04-13 许昌德通振动搅拌科技股份有限公司 Remote monitoring method for vibration stirring machine and remote monitoring system for vibration stirring station
CN112990499A (en) * 2021-03-26 2021-06-18 上海技信工业智能科技有限公司 Wastewater recycling system and method based on concentration monitoring and control and electronic equipment
CN114841594A (en) * 2022-05-18 2022-08-02 北京梦诚科技有限公司 Construction project site concrete section excess management method and system
CN115871109A (en) * 2022-12-15 2023-03-31 中铁大桥局集团有限公司 Mixing station concrete intelligent temperature adjusting system and method
CN116561598A (en) * 2023-04-07 2023-08-08 深圳市正业玖坤信息技术有限公司 CPS intelligent manufacturing management platform big data processing method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566618A (en) * 2009-05-22 2009-10-28 昆明理工大学 Raw material analysis method for rapidly monitoring concrete quality
CN102717437A (en) * 2012-07-10 2012-10-10 泉州博德机械有限公司 Discharging device of shaft end sealing device for concrete mixer
WO2012167267A2 (en) * 2011-06-03 2012-12-06 Ibd Resource Group, Ltd Building information tracking system and method of use
CN104503409A (en) * 2014-12-23 2015-04-08 江苏东交工程检测有限公司 Remote management and control system and method for cement concrete quality
CN104573932A (en) * 2014-12-23 2015-04-29 江苏东交工程检测有限公司 Real-time fluctuation concrete-quality management and control system and method
CN104898622A (en) * 2015-05-21 2015-09-09 河海大学 Concrete construction quality intelligent visualized monitoring system based on cloud technology platform
CN205281245U (en) * 2016-01-14 2016-06-01 国家电网公司 Three -dimensional hydropower construction uses management system based on visualization technology
CN107448022A (en) * 2017-08-29 2017-12-08 中国三冶集团有限公司 A kind of food stuff refrigerated storage large area overlength method for constructing terrace based on BIM
CN108984858A (en) * 2018-06-26 2018-12-11 贵州省水利水电勘测设计研究院 A kind of Construction of Rolled Concrete Dam intelligent management system
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109918810A (en) * 2019-03-14 2019-06-21 吉林省交通规划设计院 Based on BIM technology to the method and system of expressway construction management

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566618A (en) * 2009-05-22 2009-10-28 昆明理工大学 Raw material analysis method for rapidly monitoring concrete quality
WO2012167267A2 (en) * 2011-06-03 2012-12-06 Ibd Resource Group, Ltd Building information tracking system and method of use
CN102717437A (en) * 2012-07-10 2012-10-10 泉州博德机械有限公司 Discharging device of shaft end sealing device for concrete mixer
CN104503409A (en) * 2014-12-23 2015-04-08 江苏东交工程检测有限公司 Remote management and control system and method for cement concrete quality
CN104573932A (en) * 2014-12-23 2015-04-29 江苏东交工程检测有限公司 Real-time fluctuation concrete-quality management and control system and method
CN104898622A (en) * 2015-05-21 2015-09-09 河海大学 Concrete construction quality intelligent visualized monitoring system based on cloud technology platform
CN205281245U (en) * 2016-01-14 2016-06-01 国家电网公司 Three -dimensional hydropower construction uses management system based on visualization technology
CN107448022A (en) * 2017-08-29 2017-12-08 中国三冶集团有限公司 A kind of food stuff refrigerated storage large area overlength method for constructing terrace based on BIM
CN108984858A (en) * 2018-06-26 2018-12-11 贵州省水利水电勘测设计研究院 A kind of Construction of Rolled Concrete Dam intelligent management system
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109918810A (en) * 2019-03-14 2019-06-21 吉林省交通规划设计院 Based on BIM technology to the method and system of expressway construction management

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐勇戈: "《BIM概论》", 31 October 2016 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111432035A (en) * 2020-04-24 2020-07-17 毕埃慕(上海)建筑数据技术股份有限公司 Building operation and maintenance monitoring and alarming system and method based on BIM
CN112650132A (en) * 2021-01-12 2021-04-13 许昌德通振动搅拌科技股份有限公司 Remote monitoring method for vibration stirring machine and remote monitoring system for vibration stirring station
CN112990499A (en) * 2021-03-26 2021-06-18 上海技信工业智能科技有限公司 Wastewater recycling system and method based on concentration monitoring and control and electronic equipment
CN114841594A (en) * 2022-05-18 2022-08-02 北京梦诚科技有限公司 Construction project site concrete section excess management method and system
CN114841594B (en) * 2022-05-18 2022-12-23 北京梦诚科技有限公司 Construction project site concrete section excess management method and system
CN115871109A (en) * 2022-12-15 2023-03-31 中铁大桥局集团有限公司 Mixing station concrete intelligent temperature adjusting system and method
CN116561598A (en) * 2023-04-07 2023-08-08 深圳市正业玖坤信息技术有限公司 CPS intelligent manufacturing management platform big data processing method
CN116561598B (en) * 2023-04-07 2024-01-12 深圳市正业玖坤信息技术有限公司 CPS intelligent manufacturing management platform big data processing method

Similar Documents

Publication Publication Date Title
CN110488782A (en) Cement concrete batching plant back court intelligent monitor system based on BIM platform
CN102170464B (en) Dynamic monitoring system method of production process of concrete mixing station
EP3244271B1 (en) Ore dressing multi-production-index optimization decision making system and method based on cloud and mobile terminal
CN104175401B (en) A kind of concrete mixing plant match ratio dynamic debugging system
CN105415499A (en) Control method for proportioning and mixing of concrete
Zhong et al. Theoretical research on construction quality real-time monitoring and system integration of core rockfill dam
CN104503410A (en) Asphalt pavement construction quality control system and method
CN107551951A (en) One kind is gathered materials intelligent feed proportioning system and method
CN103903108A (en) Production scheduling management system and method for plain agriculture
CN110458975A (en) A kind of asphalt mixes and stirs process monitoring system and method
CN105538510A (en) Control system and method for concrete raw material mixture ratio
CN104552608A (en) Concrete batching stirring control system
CN109941697A (en) Horizontal transport vehicle and cable machine transport automatic identifying method in a kind of concrete construction
CN112327781A (en) Asphalt mixing station production quality remote monitoring management system based on internet of things technology
CN207115156U (en) A kind of long-range energy consumption monitoring system of concrete mixing plant
CN202257245U (en) Remote real-time management control device for on-site mixed loading explosive vehicle
CN208781278U (en) A kind of quotient's concrete quality-monitoring managing and control system
CN203680545U (en) Concrete preparing and stirring control system
CN113656975A (en) Method, device and equipment for analyzing construction progress of concrete faced rockfill dam in alpine and high-altitude areas
CN114433834A (en) Integrative intelligence control system of mulling molding pouring
CN112987633A (en) Bituminous paving work progress informationization management and control system
Huan Application Research of Computer Artificial Intelligence Technology in Safety Process Control System in Highway Construction
CN106758689A (en) Bituminous mixing plant selects storehouse system and method
CN111553585A (en) System and method for monitoring mixing quality of core wall asphalt mixture in real time
Sun et al. Quality control strategy and intelligent monitoring of a concrete mixing plant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20191122

WD01 Invention patent application deemed withdrawn after publication