CN109918810A - Based on BIM technology to the method and system of expressway construction management - Google Patents
Based on BIM technology to the method and system of expressway construction management Download PDFInfo
- Publication number
- CN109918810A CN109918810A CN201910191467.1A CN201910191467A CN109918810A CN 109918810 A CN109918810 A CN 109918810A CN 201910191467 A CN201910191467 A CN 201910191467A CN 109918810 A CN109918810 A CN 109918810A
- Authority
- CN
- China
- Prior art keywords
- construction
- expressway
- expressway construction
- management platform
- bim technology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
This application provides a kind of based on BIM technology to the method and system of expressway construction management.It is described based on BIM technology to the method for expressway construction management, comprising: by network, so that obtaining the construction relevant information that generates in Expressway Construction of Intelligent target equipment based on the expressway construction management platform that BIM technology is established;The construction relevant information of the Intelligent target equipment got is compared with corresponding preset control parameters in expressway construction management platform;It is based on comparison as a result, expressway construction management platform executes corresponding response events.Compared with the existing technology based on the present invention, by using BIM technology as the important means for implementing expressway works construction lifecycle management theory, the industrial upgrading for pushing entire transportation industry to carry out realizes wisdom traffic, promotes the level of current expressway construction management.
Description
Technical field
The present invention relates to expressway construction administrative skill fields, more particularly to a kind of BIM technology that is based on is to highway
The method and system of implementation management.
Background technique
Currently, being managed the extensive mode for mainly relying on traditional people pipe people, this biography for expressway construction
Defect existing for the extensive mode of system is more and more obvious: (1) efficiency of management is low, and information during implementation management is conveyed too late
When, low efficiency, inaccuracy, when something goes wrong, cannot the root of clear problem, problem in time person liable;(2) construction
Low efficiency, be easy to appear practice of construction situation and drawing has gap but and the gap that cannot find to cause to construct in time, construct into
Spend low reason.Thus it is badly in need of solving the problems, such as in the efficiency of management and quality in current expressway construction management process.
Summary of the invention
To solve at least one technical problem in above-mentioned, the present invention provides one kind to be based on BIM (Building
Information Modeling, i.e. architecture information model) technology to the method and system of expressway construction management, passes through
Using BIM technology as the important means for implementing expressway works construction lifecycle management theory, entire traffic row is pushed
The industrial upgrading that industry carries out realizes wisdom traffic, promotes the level of current expressway construction management.
According to a first aspect of the embodiments of the present invention, a kind of side based on BIM technology to expressway construction management is provided
Method, comprising: by network, exist so that obtaining Intelligent target equipment based on the expressway construction management platform that BIM technology is established
The construction relevant information generated in Expressway Construction;By the construction relevant information of the Intelligent target equipment got
It is compared with corresponding preset control parameters in expressway construction management platform;It is based on comparison as a result, the height
Fast highway construction administration platform executes corresponding response events.
Optionally, the Intelligent target equipment includes the intelligent roller for being equipped with GPS, described by network, so that base
Obtain what Intelligent target equipment generated in Expressway Construction in the expressway construction management platform that BIM technology is established
The step of relevant information of constructing includes: to be positioned by GPS network network, so that the expressway construction management established based on BIM technology
Platform obtain intelligent pressure machine generated in Expressway Construction it is following in one or more information: roadbed filling pressure
The start position of reality, final position, filling-up thickness, compacting counting, travel speed, exciting force.
Optionally, the Intelligent target equipment includes being equipped with the intelligence brill stake equipment of GPS and sensor, described to pass through net
Network, so that obtaining Intelligent target equipment in highway construction mistake based on the expressway construction management platform that BIM technology is established
The step of construction relevant information generated in journey includes: to be positioned by GPS network network, so that public based on the high speed that BIM technology is established
Implementation management platform in road obtains in the drilled pile position coordinate, vertical angle, advanced depth of the sensor acquisition of intelligence brill stake equipment
One or more information.
Optionally, the Intelligent target equipment includes being equipped with Weight-measuring sensor, temperature sensor and timer
Intelligent mixing station, it is described by network, so that obtaining Intelligent target based on the expressway construction management platform that BIM technology is established
The step of construction relevant information that equipment generates in Expressway Construction includes: by network, so that being based on BIM technology
The expressway construction management platform of foundation obtains actual amount, duration of mixing, the mix temperature of the mix material of intelligent mixing station
One or more information in degree.
Optionally, described based on comparison as a result, expressway construction management platform executes corresponding response events
If the step of include: the Intelligent target equipment got construction relevant information be more than corresponding preset control parameters,
The expressway construction management platform is then set to execute corresponding alert event, early warning event or/and obtain highway
The real-time progress msg of construction.
According to a second aspect of the embodiments of the present invention, it provides and a kind of is to expressway construction management based on BIM technology
System, comprising: information acquisition unit, for being obtained so that managing platform based on the expressway construction that BIM technology is established by network
The construction relevant information for taking Intelligent target equipment to generate in Expressway Construction;Comparing unit is used for the acquisition
To Intelligent target equipment construction relevant information and the expressway construction management platform in corresponding preset control parameters
It is compared;Execution unit, for based on comparison as a result, the expressway construction management platform is made to execute corresponding response
Event.
The technical solution that the embodiment of the present invention provides may be implemented following the utility model has the advantages that the present invention is based on BIM technologies pair
Expressway construction is effectively managed, and Internet of Things and expressway construction management are firmly bound together, even if construction is real
Apply base and administrative staff be far apart ten thousand li, also can Intelligent target equipment through the invention by construction information by network in real time
It is transmitted to BIM management platform, the information interchange of administrative staff and Intelligent target device end are realized, to realize highway construction
Digitlization, visualization and the intelligence of management.Moreover, administrative staff can also pass through BIM mould during expressway construction
Type carries out real-time tracking and management to construction speed.
It should be understood that above general description and following detailed description be only it is exemplary and explanatory, not
It can the limitation present invention.
Detailed description of the invention
By reading a detailed description of non-restrictive embodiments in the light of the attached drawings below, the application's is other
Feature, objects and advantages will become more apparent upon:
Fig. 1 is a kind of method based on BIM technology to expressway construction management shown according to an exemplary embodiment
Flow chart;
Fig. 2 is that a kind of BIM technology that is based on shown according to an exemplary embodiment establishes expressway construction management platform
Method flow chart;
Fig. 3 is that present invention one kind shown according to an exemplary embodiment is based on BIM technology to expressway construction management
System block diagram;
The same or similar appended drawing reference represents the same or similar structure in attached drawing.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
It is only to be not intended to limit the invention merely for for the purpose of describing particular embodiments in terminology used in the present invention.
It is also intended in the present invention and the "an" of singular used in the attached claims, " described " and "the" including majority
Form, unless the context clearly indicates other meaning.It is also understood that term "and/or" used herein refers to and wraps
Including one or more associated any or all of project listed may combine.
As shown in Figure 1, Fig. 1 is a kind of BIM technology that is based on shown according to an exemplary embodiment to expressway construction
The flow chart of the method for management, this method can be applied in electronic equipment.It will be understood by those skilled in the art that the electronics is set
It is standby to can include but is not limited to such as single computer, multiple stage computers, server cluster, Cloud Server etc..This method packet
Include following steps:
In step s101, by network, so that obtaining mesh based on the expressway construction management platform that BIM technology is established
The construction relevant information that mark smart machine generates in Expressway Construction.
Specifically, the expressway construction management platform established based on BIM technology is considered as highway correlation
Manager and Intelligent target equipment carry out the computer system of information exchange, carry in the computer system based on BIM technology
Highway three-dimensional structure, construction speed information.
In one example, referring to FIG. 2, the expressway construction management platform established based on BIM technology can be with
It is established by following steps:
Step S201, according to specific criteria by Expressway Construction involved in product unit classified,
And establish BIM information module corresponding with the product unit classified.
Wherein, the specific criteria is for example including " Road Engineering Quality Checking And Evaluation standard " (JTG F80/1-2017),
It include especially in " Road Engineering Quality Checking And Evaluation standard " (JTG F80/1-2017) appendix A to construction unit, partitioned project
And the standard of the Engineering Division of subdivisional work.The present invention can be reference with the standard, can also be fully according to the standard, will be high
Related products unit is classified during fast construction of the highway, can adaptively be adjusted as the case may be in practice
It is whole.
Wherein, related product unit includes but is not limited to during the highway practice of construction: the high speed
Road involved in during highway practice of construction, bridge, intercommunication, culvert, draining, the production in protection in one or more engineerings
Article unit.By taking road as an example comprising product unit be, for example, roadbed section;By taking culvert as an example comprising product unit
For example, foundation, culvert bottom plate, culvert case body, culvert aileron etc..
It in one example, will be involved in Expressway Construction referring to " Road Engineering Quality Checking And Evaluation standard "
Subgrade engineering included by product unit classified, subgrade engineering is divided into the partitioned project and next stage of level-one
Subdivisional work, as shown in table 1 below.
Table 1
Certainly, the classification in table 1 is only that an example of the invention is referred to other marks in other examples
Standard divides product unit included by engineering involved during the highway practice of construction and engineering, divides
Granularity can be thicker, can also be thinner, according to the actual situation depending on.
Further, it after product unit involved in Expressway Construction being given classification, establishes and has divided
The corresponding BIM information module of product unit of grade classification.The data structure of the multiple BIM information module can be and product list
The corresponding tree of classification of member is also possible to the structure of set or other forms.With the BIM information mould of tree
It further include that every level-one product unit is corresponding in addition to the product unit title of classification as shown in Table 1 for block
Attribute information, such as the product unit " Tetranychus turkestani " of minimum level-one in table 1, in addition to the corresponding product of upper level
The name information etc. of unit " roadbed earthwork " or/and the corresponding product unit of upper upper level " subgrade engineering ", can be with
Including attribute informations such as width of subgrade corresponding with the same level classification, raising, horizontal slope, unit in charge of construction, construction times.Certainly, for
The setting of attribute information can be with continued reference to the step S202 being detailed below.
In order to enable the highway BIM model finally established has more uniformity and normalization, herein for constituting BIM
The BIM information module of model is preferably standard, unified BIM information module, i.e., establishes BIM information mould according to unified standard
Block.I.e. for mutually isostructural product unit, the structure of corresponding BIM information module is also identical, such as identical structure
Tetranychus turkestani comprising attribute classification be it is identical, only the specifying information in attribute classification can be different.More
Specifically for example, for number be respectively 1 and 2 Tetranychus turkestani comprising attribute type be all width of subgrade, raising, cross
Slope, unit in charge of construction, construction time, treatment of soft foundation thickness, the CBR value of each layer filler, compactness, water content and placement in layers are thick
Degree, but every attribute information can be different in Tetranychus turkestani 1 and Tetranychus turkestani 2, such as the water content of Tetranychus turkestani 1 is
10.7%, the water content of Tetranychus turkestani 2 is 10.8%.
Step S202 is configured the attribute of BIM information module, and the attribute includes name of product, product number, production
It is product source, product formula, construction information, geometric dimension, material properties, mechanical index, one or more in engineering quantity.
Specifically, for example, for the product unit of the bridge pier component included by the science of bridge building, corresponding BIM letter
The attribute for ceasing module, cement producer, reinforcing bar manufacturer, reinforcing bar model for example including bridge pier building, sandstone dosage, cement are used
The attribute informations such as match ratio, the slump of concrete, the construction temperature of amount, sandstone and cement and water etc..
It certainly, is not for different BIM information modules, such as Tetranychus turkestani and the corresponding BIM information module of bridge pier component
With comprising attribute classification be also possible to it is different or identical, it is not limited here.
Step S203 establishes highway BIM threedimensional model based on the setting of the attribute to BIM information module.
Specifically, after the attribute to multiple BIM information modules is configured, can based on multiple BIM information modules it
Between connection, establish highway BIM threedimensional model, be by the data heap of multiple BIM information modules just as BIM threedimensional model
Made of product.
As described above, each BIM information module can be in addition to the product list including classification as shown in Table 1
First title further includes the corresponding attribute information of every level-one product unit, and then can be according to corresponding to every BIM information module
The space geometry information of product unit, such as upper level belonging to each product unit are any structures, if including next stage
Structure and next level structure are specifically the other structures of what and upper level structure, this level structure or lower structures and peer
With the presence or absence of connection relationship (such as whether the bridge and road of certain a road section at the same level are spatially connected) spatially,
BIM information module to have space geometry to contact carries out the link in data, and then establishes highway BIM three-dimensional mould
Type.
Certainly, the method for highway BIM threedimensional model being established to the setting of the attribute based on BIM information module at this
And without limitation, it can be realized using the prior art.
Step S204 is based on established highway BIM threedimensional model, establishes freeway management platform.
Specifically, in one example, highway can be determined according to established highway BIM threedimensional model
The Intelligent target equipment that each engineering structure is related in process of construction obtains mesh by wireless networks such as wifi, 3G, 4G, 5G
The real time data or/and image information for marking smart machine collection in worksite, by real time data collected or/and image information with
Minor structure (such as BIM information module) in BIM threedimensional model is corresponded to, and is directed to the relative parameters setting of different minor structures
Preset value, and then data or/and image information by comparing the acquisition of Intelligent target device context are established compared with preset value,
Whether occur abnormal conditions to obtain site operation, whether need to alarm or carry out whether early warning, construction speed meet
It is expected that etc. analysis result freeway management platform.
Certainly, the process of the above-mentioned expressway construction management platform established based on BIM technology is only of the invention one
Example can also establish expressway construction management platform, it is not limited here by existing relevant art.
Further, it is applied for what Intelligent target equipment described in step S101 generated in Expressway Construction
Work relevant information can refer to following multiple examples.
In one implementation, the Intelligent target equipment includes the intelligent roller for being equipped with GPS, described to pass through net
Network, so that obtaining Intelligent target equipment in highway construction mistake based on the expressway construction management platform that BIM technology is established
The step of construction relevant information generated in journey includes: to be positioned by GPS network network, so that public based on the high speed that BIM technology is established
Road implementation management platform obtain intelligent pressure machine generated in Expressway Construction it is following in one or more information:
The start position of roadbed filling compacting, final position, filling-up thickness, compacting counting, travel speed, exciting force.
In another implementation, the Intelligent target equipment includes being equipped with the intelligence of GPS and sensor to bore stake and set
It is standby, it is described by network, so that obtaining Intelligent target equipment in height based on the expressway construction management platform that BIM technology is established
The step of construction relevant information generated during fast construction of the highway includes: to be positioned by GPS network network, so that being based on BIM technology
The expressway construction management platform of foundation obtains intelligence and bores drilled pile position coordinate, the vertical angle that the sensor of stake equipment acquires
One or more information in degree, advanced depth.
In another implementation, the Intelligent target equipment include be equipped with Weight-measuring sensor, temperature sensor and
The intelligent mixing station of timer, it is described by network, so that managing platform based on the expressway construction that BIM technology is established
The step of obtaining the construction relevant information that Intelligent target equipment generates in Expressway Construction includes: to be made by network
It obtains the actual amount of the mix material of the intelligent mixing station of expressway construction management platform acquisition established based on BIM technology, mix
One or more information in conjunction time, mix temperature.
In step s 102, the construction relevant information of the Intelligent target equipment got is built with the highway
If corresponding preset control parameters are compared in management platform.
Specifically, for example, the start position for the roadbed filling compacting that the intelligent roller that will acquire uploads, terminal position
It sets, the multinomial information of filling-up thickness, compacting counting, travel speed, exciting force is compared with corresponding preset control parameters.
Wherein, corresponding default control generally joins in expressway construction management platform for each single item information
Number, if a certain item or multinomial information do not have corresponding preset control parameters, can be added to by related management personnel are subsequent
Expressway construction manages platform, to constantly update and supplement the data in expressway construction management platform.Certainly, at other
In example, related management personnel can also variation according to the actual situation, preset control parameters are adaptively adjusted, with more
Reasonably expressway construction is managed.
It is in step s 103, based on comparison that as a result, the expressway construction manages, platform execution is corresponding to respond thing
Part.
Specifically, in one example, it is based on comparison as a result, if the construction of the Intelligent target equipment got
Relevant information is more than corresponding preset control parameters, then the expressway construction management platform is made to execute corresponding alarm thing
Part, early warning event or/and obtain the real-time progress msg of construction of highway.In another example, the high speed is public
Road implementation management platform can be according to the construction speed of sub- engineering corresponding in the interpretation of result highway of comparison, if analyzed
It is inconsistent with target advance to actual progress, then issue lag warning information.
More specifically, for example, intelligent roller is uploaded to expressway construction in real time by 4G network manages platform
The start position of roadbed filling compacting, final position, filling-up thickness, compacting counting, travel speed, exciting force this multinomial information,
After being compared with corresponding preset control parameters, if compare the result is that wherein two or more information is significantly larger than default
Control parameter, then expressway construction management platform carrys out reminding platform to execute the events such as sending caution sound, pop-up pop-up
Administrative staff's intelligent roller abnormal conditions have occurred during construction, thus administrative staff be based on the highway build
If management platform and can quickly position the position of abnormal conditions generation and different with the Intelligent target equipment of the Platform communication
The information such as normal parameter.So that platform intelligent process control is managed by expressway construction, so that previous insoluble
Super thick fills, the compactness FAQs such as not enough, is fundamentally kept under strict control.
For another example, intelligence bores stake equipment, by GPS positioning and sensor these internet of things equipment, to drilled pile position coordinate, hangs down
Squareness, the data of advanced depth are acquired in real time with " centimetre class precision ", pass through 4G network transmission to expressway construction management
Among platform, the data of the Internet transmission and corresponding preset control parameters are compared by platform, if it exceeds default control
Parameter but in a certain range, then early warning.
For another example, equipped with the intelligent mixing station of the internet of things equipment such as Weight-measuring sensor, temperature, timer, pass through 4G net
The actual amount of mix material, duration of mixing, mix temperature are transferred among expressway construction management platform by network, while high
Fast highway construction administration platform transfers the related data of third-party platform by internet, when to match ratio, mix temperature, mix
Between etc. production processes carry out real-time tracking and effectively control.
Certainly, smart machine of the invention is not limited to intelligent roller above, intelligence bores stake equipment, intelligent mix
It stands, can also include other smart machines, such as further include intelligent paver, what intelligent paver can send the base station GNSS
The elevation information of differential signal and laser transmitter projects carries out processing resolving, realize real-time GNSS plane Centimeter Level and
The positioning of elevation grade.It improves flatness, realize without stake, digitlization, precision construction.
Information is uploaded into expressway construction by a variety of smart machines and manages platform, which can effectively dynamically
Relevant information in recording and storage work progress, and these information are effectively managed.
Further, the expressway construction management platform can also be by the road designed in work progress, bridge etc.
Model is dissolved into geographical information platform GIS, and combines practical highway construction situation, is generated in combination with smart machine
Data simulate the progress of highway construction, store to the data generated in construction, show roadbed, roadbed etc.
Situation is filled, and early warning is carried out to roadbed extra-fill data.
It should be noted that although describing the operation of the method for the present invention in the accompanying drawings with particular order, this is not required that
Or hint must execute these operations in this particular order, or have to carry out operation shown in whole and be just able to achieve the phase
The result of prestige.On the contrary, the step of describing in flow chart can change and execute sequence.Additionally or alternatively, it is convenient to omit certain
Multiple steps are merged into a step and executed, and/or a step is decomposed into execution of multiple steps by step.
With it is aforementioned corresponding based on embodiment of the method for the BIM technology to expressway construction management, the present invention also provides
It is a kind of based on BIM technology to the embodiment of the system of expressway construction management.
As shown in figure 3, Fig. 3 is that the present invention is shown according to an exemplary embodiment a kind of public to high speed based on BIM technology
The system block diagram of road implementation management, the system are applied to electronic equipment, comprising: information acquisition unit 201,202 and of comparing unit
Execution unit 203.
Wherein, information acquisition unit 201 are configured as through network, so that being built based on the highway that BIM technology is established
If management platform obtains the construction relevant information that Intelligent target equipment generates in Expressway Construction.
Comparing unit 202 is configured as the construction relevant information of the Intelligent target equipment got and the height
Corresponding preset control parameters are compared in fast highway construction administration platform.
Execution unit 203 is configured as based on comparison as a result, executing the expressway construction management platform accordingly
Response events.
Optionally, the Intelligent target equipment includes the intelligent roller for being equipped with GPS, the information acquisition unit 201
It is specifically used for: is positioned by GPS network network, so that obtains intelligence pressure based on the expressway construction management platform that BIM technology is established
Power machine generated in Expressway Construction it is following in one or more information: roadbed filling compacting start position,
Final position, filling-up thickness, compacting counting, travel speed, exciting force.
Optionally, the Intelligent target equipment includes being equipped with the intelligence brill stake equipment of GPS and sensor, and the information obtains
It takes unit 201 to be specifically used for: being positioned by GPS network network, so that being obtained based on the expressway construction management platform that BIM technology is established
Intelligence is taken to bore one or more information in the drilled pile position coordinate, vertical angle, advanced depth of the sensor acquisition of stake equipment.
Optionally, the Intelligent target equipment includes being equipped with Weight-measuring sensor, temperature sensor and timer
Intelligent mixing station, the information acquisition unit 201 are specifically used for: by network, so that the highway established based on BIM technology
Implementation management platform obtains the actual amount of the mix material of intelligent mixing station, duration of mixing, one or more in mix temperature
Item information.
Optionally, the execution unit 203 is specifically used for: if the construction of the Intelligent target equipment got is related
Information is more than corresponding preset control parameters, then expressway construction management platform is made to execute corresponding alert event, pre-
It warns prompt event or/and obtains the real-time progress msg of construction of highway.
It should be appreciated that above system can be preset in the electronic device, can also be loaded by modes such as downloadings
Into electronic equipment.Corresponding units in above system can in electronic equipment unit or/and module cooperate with reality
Now corresponding function.
For system embodiments, since it corresponds essentially to embodiment of the method, so related place is referring to method reality
Apply the part explanation of example.System embodiment described above is only schematical, wherein described be used as separation unit
The unit of explanation may or may not be physically separated.Can select according to the actual needs part therein or
Whole modules realize the purpose of the present invention program.Those of ordinary skill in the art without creative efforts,
It can understand and implement.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention.
Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.
It is obvious to a person skilled in the art that the application is not limited to the details of above-mentioned exemplary embodiment, Er Qie
In the case where without departing substantially from spirit herein or essential characteristic, the application can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and scope of the present application is by appended power
Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims
Variation is included in the application.Any reference signs in the claims should not be construed as limiting the involved claims.
Claims (10)
1. it is a kind of based on BIM technology to the method for expressway construction management, comprising:
By network, so that obtaining Intelligent target equipment in high speed based on the expressway construction management platform that BIM technology is established
The construction relevant information generated during construction of the highway;
The construction relevant information of the Intelligent target equipment got is corresponding with expressway construction management platform
Preset control parameters be compared;
It is based on comparison as a result, expressway construction management platform executes corresponding response events.
2. the method according to claim 1, wherein the Intelligent target equipment includes being equipped with the intelligence of GPS
Road roller, it is described by network, so that obtaining Intelligent target equipment based on the expressway construction management platform that BIM technology is established
The step of construction relevant information generated in Expressway Construction includes:
It is positioned by GPS network network, is existed so that obtaining intelligent pressure machine based on the expressway construction management platform that BIM technology is established
Generated in Expressway Construction it is following in one or more information: roadbed filling compacting start position, terminal position
It sets, filling-up thickness, compacting counting, travel speed, exciting force.
3. the method according to claim 1, wherein the Intelligent target equipment includes being equipped with GPS and sensing
The intelligence of device bores stake equipment, described by network, so that obtaining mesh based on the expressway construction management platform that BIM technology is established
Mark smart machine generated in Expressway Construction construction relevant information the step of include:
It is positioned by GPS network network, so that obtaining intelligence based on the expressway construction management platform that BIM technology is established bores stake equipment
Sensor acquisition drilled pile position coordinate, vertical angle, one or more information in advanced depth.
4. the method according to claim 1, wherein the Intelligent target equipment includes being equipped with weight calculation sensing
The intelligent mixing station of device, temperature sensor and timer, it is described by network, so that the high speed established based on BIM technology
Highway construction administration platform obtains the step of construction relevant information that Intelligent target equipment generates in Expressway Construction
Include:
By network, so that obtaining the mix material of intelligent mixing station based on the expressway construction management platform that BIM technology is established
The actual amount of material, duration of mixing, one or more information in mix temperature.
5. the method according to claim 1, wherein described based on comparison as a result, the expressway construction
Managing the step of platform executes corresponding response events includes:
If the construction relevant information of the Intelligent target equipment got is more than corresponding preset control parameters, make described
Expressway construction management platform executes corresponding alert event, early warning event or/and obtains the construction reality of highway
When progress msg.
6. it is a kind of based on BIM technology to the system of expressway construction management, comprising:
Information acquisition unit, for passing through network, so that obtaining mesh based on the expressway construction management platform that BIM technology is established
The construction relevant information that mark smart machine generates in Expressway Construction;
Comparing unit, for by the construction relevant information of the Intelligent target equipment got and the expressway construction pipe
Corresponding preset control parameters are compared in platform;
Execution unit, for based on comparison as a result, the expressway construction management platform is made to execute corresponding response events.
7. system according to claim 6, which is characterized in that the Intelligent target equipment includes being equipped with the intelligence of GPS
Road roller, the information acquisition unit are specifically used for:
It is positioned by GPS network network, is existed so that obtaining intelligent pressure machine based on the expressway construction management platform that BIM technology is established
Generated in Expressway Construction it is following in one or more information: roadbed filling compacting start position, terminal position
It sets, filling-up thickness, compacting counting, travel speed, exciting force.
8. system according to claim 6, which is characterized in that the Intelligent target equipment includes being equipped with GPS and sensing
The intelligence of device bores stake equipment, and the information acquisition unit is specifically used for:
It is positioned by GPS network network, so that obtaining intelligence based on the expressway construction management platform that BIM technology is established bores stake equipment
Sensor acquisition drilled pile position coordinate, vertical angle, one or more information in advanced depth.
9. system according to claim 6, which is characterized in that the Intelligent target equipment includes being equipped with weight calculation sensing
The intelligent mixing station of device, temperature sensor and timer, the information acquisition unit are specifically used for:
By network, so that obtaining the mix material of intelligent mixing station based on the expressway construction management platform that BIM technology is established
The actual amount of material, duration of mixing, one or more information in mix temperature.
10. system according to claim 6, which is characterized in that the execution unit is specifically used for:
If the construction relevant information of the Intelligent target equipment got is more than corresponding preset control parameters, make described
Expressway construction management platform executes corresponding alert event, early warning event or/and obtains the construction reality of highway
When progress msg.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910191467.1A CN109918810A (en) | 2019-03-14 | 2019-03-14 | Based on BIM technology to the method and system of expressway construction management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910191467.1A CN109918810A (en) | 2019-03-14 | 2019-03-14 | Based on BIM technology to the method and system of expressway construction management |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109918810A true CN109918810A (en) | 2019-06-21 |
Family
ID=66964732
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910191467.1A Pending CN109918810A (en) | 2019-03-14 | 2019-03-14 | Based on BIM technology to the method and system of expressway construction management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109918810A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110414063A (en) * | 2019-06-29 | 2019-11-05 | 万翼科技有限公司 | Model restorative procedure and Related product |
CN110488782A (en) * | 2019-08-26 | 2019-11-22 | 中电建路桥集团有限公司 | Cement concrete batching plant back court intelligent monitor system based on BIM platform |
CN111061805A (en) * | 2019-11-19 | 2020-04-24 | 四川高路交通信息工程有限公司 | Information management service platform applied to highway construction |
CN111593625A (en) * | 2020-05-07 | 2020-08-28 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | Operation method and system based on roadbed filling intelligent command system |
CN115880103A (en) * | 2023-02-21 | 2023-03-31 | 山东铁路投资控股集团有限公司 | Visual management method, device, equipment and medium for railway engineering progress |
CN116108541A (en) * | 2023-03-10 | 2023-05-12 | 安徽省交通建设股份有限公司 | Visual stay cable bridge construction management system and method based on BIM |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20170132568A1 (en) * | 2015-11-06 | 2017-05-11 | Benjamin F. GLUNZ | Method and system for gps enabled model and site interaction and collaboration for bim and other design platforms |
CN107146065A (en) * | 2017-03-20 | 2017-09-08 | 中国铁道科学研究院电子计算技术研究所 | Railway engineering management platform system |
CN107423865A (en) * | 2017-03-10 | 2017-12-01 | 中铁四局集团有限公司 | High-speed railway KXG based on BIM |
-
2019
- 2019-03-14 CN CN201910191467.1A patent/CN109918810A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20170132568A1 (en) * | 2015-11-06 | 2017-05-11 | Benjamin F. GLUNZ | Method and system for gps enabled model and site interaction and collaboration for bim and other design platforms |
CN107423865A (en) * | 2017-03-10 | 2017-12-01 | 中铁四局集团有限公司 | High-speed railway KXG based on BIM |
CN107146065A (en) * | 2017-03-20 | 2017-09-08 | 中国铁道科学研究院电子计算技术研究所 | Railway engineering management platform system |
Non-Patent Citations (1)
Title |
---|
狼毒花34466: "双洮建设项目BIM应用-wm手机版(百度播放器)", 《HTTPS://V.YOUKU.COM/V_SHOW/ID_XNDAWMJMYNJC3NG==.HTML》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110414063A (en) * | 2019-06-29 | 2019-11-05 | 万翼科技有限公司 | Model restorative procedure and Related product |
CN110488782A (en) * | 2019-08-26 | 2019-11-22 | 中电建路桥集团有限公司 | Cement concrete batching plant back court intelligent monitor system based on BIM platform |
CN111061805A (en) * | 2019-11-19 | 2020-04-24 | 四川高路交通信息工程有限公司 | Information management service platform applied to highway construction |
CN111593625A (en) * | 2020-05-07 | 2020-08-28 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | Operation method and system based on roadbed filling intelligent command system |
CN111593625B (en) * | 2020-05-07 | 2021-01-29 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | Roadbed filling based intelligent command system and operation method thereof |
CN115880103A (en) * | 2023-02-21 | 2023-03-31 | 山东铁路投资控股集团有限公司 | Visual management method, device, equipment and medium for railway engineering progress |
CN116108541A (en) * | 2023-03-10 | 2023-05-12 | 安徽省交通建设股份有限公司 | Visual stay cable bridge construction management system and method based on BIM |
CN116108541B (en) * | 2023-03-10 | 2023-07-25 | 安徽省交通建设股份有限公司 | Visual stay cable bridge construction management system and method based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109918810A (en) | Based on BIM technology to the method and system of expressway construction management | |
CN111125821B (en) | BIM+GIS foundation and foundation subsection engineering analysis and type selection method | |
Montaser et al. | Truck+ for earthmoving operations | |
CN107783463A (en) | A kind of base pit engineering intellectuality construction and monitoring system based on BIM technology | |
CN105825335A (en) | BIM (Building Information Modeling) based construction onsite vehicle and device management system and method | |
CN106997511A (en) | Railway beam course management system and railway beam a management method based on BIM technology | |
CN109635058A (en) | A kind of freeway management system and method using BIM technology and GIS technology | |
CN112580833B (en) | Rural highway maintenance informatization management system | |
CN111125820B (en) | BIM+GIS-based construction site space virtual construction method | |
CN105652835A (en) | Intelligent system for intelligent compaction monitoring of road subgrade and pavement | |
CN110008591A (en) | A kind of continuous rigid frame bridge construction management control method based on BIM | |
Wang et al. | Research on the construction of highway traffic digital twin system based on 3D GIS technology | |
CN107506953A (en) | A kind of Collapse by Mining ground environment remediation decision-making assistant information acquisition methods | |
CN108007428A (en) | High ferro sedimentation monitoring system | |
CN111191307A (en) | Earthwork virtual construction method based on BIM + GIS technology | |
CN114201799A (en) | Visual tunnel construction progress management analysis system | |
CN107423455A (en) | A kind of highway method for automatic modeling and system | |
CN109409827A (en) | The monitoring method of construction speed in a kind of engineering construction based on virtual-real comparison | |
CN106052553A (en) | Civil engineering temporary works design optimization method and device based on three-dimensional laser scanning | |
CN113946980B (en) | Step earth and stone volume calculation method and system for large strip mine excavation engineering | |
CN117171862B (en) | Bridge engineering land investigation drilling point position checking method and equipment | |
Li et al. | Study on filling support design and ground pressure monitoring scheme for gob-side entry retention by roof cutting and pressure relief in high-gas thin coal seam | |
CN109918811A (en) | Block-based concept establishes the method and system of highway BIM model | |
CN104504756A (en) | Dynamic updating method of ore deposit three dimension geology model | |
Naik et al. | GIS based 4D model development for planning and scheduling of a construction project |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190621 |
|