CN114201799A - Visual tunnel construction progress management analysis system - Google Patents
Visual tunnel construction progress management analysis system Download PDFInfo
- Publication number
- CN114201799A CN114201799A CN202111485040.6A CN202111485040A CN114201799A CN 114201799 A CN114201799 A CN 114201799A CN 202111485040 A CN202111485040 A CN 202111485040A CN 114201799 A CN114201799 A CN 114201799A
- Authority
- CN
- China
- Prior art keywords
- progress
- module
- days
- analysis
- project
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004458 analytical method Methods 0.000 title claims abstract description 40
- 238000010276 construction Methods 0.000 title claims abstract description 37
- 230000000007 visual effect Effects 0.000 title claims abstract description 20
- 238000007726 management method Methods 0.000 claims description 31
- 238000000034 method Methods 0.000 claims description 9
- 239000003086 colorant Substances 0.000 claims description 7
- 230000002354 daily effect Effects 0.000 claims description 6
- 239000011435 rock Substances 0.000 claims description 3
- 230000003203 everyday effect Effects 0.000 claims description 2
- 230000010354 integration Effects 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Computer Hardware Design (AREA)
- Operations Research (AREA)
- Pure & Applied Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Computational Mathematics (AREA)
- Evolutionary Computation (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a visual tunnel construction progress management and analysis system which is developed mainly based on a Web end and integrates four functional modules of progress overview, progress plan, progress filling and progress analysis, wherein the progress overview module is used as a system main data integration module and is used as a decision center of project management personnel, the progress plan module, the progress filling module and the progress analysis module are used as data sources of the system, the project personnel acquire data in a mode of filling in the progress filling module, and the progress analysis module calculates and deduces and analyzes the filled data to obtain relevant progress decision data. The intelligent construction site platform can monitor the progress condition of the whole linear project and the progress condition of each construction site in an all-around manner, thereby better serving project management personnel to manage and control the site progress, and meanwhile, the intelligent construction site platform can be deployed into the whole intelligent construction site system as a subsystem of the intelligent construction site platform to be developed for the intelligent construction site platform of the subsequent tunnel project once and reused for multiple times.
Description
Technical Field
The invention belongs to the technical field of tunnel engineering project management, and particularly relates to a visual tunnel construction progress management and analysis system.
Background
Progress management and control are one of the most important links in the whole process of engineering project management, and how to efficiently manage and control field progress by project management personnel is a key difficulty of project management and control, so that a tunnel construction progress management application and analysis system is required to be designed and developed.
Disclosure of Invention
The invention aims to provide a visual tunnel construction progress management and analysis system aiming at the defects in the prior art.
Therefore, the above purpose of the invention is realized by the following technical scheme:
the utility model provides a visual tunnel construction progress management analytic system which characterized in that: the visual tunnel construction progress management and analysis system comprises a progress overview module, a progress planning module, a progress reporting module and a progress analysis module;
the progress overview module is used as an overview page of the visual tunnel construction progress management and analysis system, three modules of progress planning, progress filling and progress analysis are arranged on two sides of the overview page, and a middle base map of the overview page is a BIM (building information modeling) model or a plane base map;
the progress planning module takes the filling of the progress filling module as data input, project managers form corresponding plan cross-road graphs on the progress planning module according to the project overall plan and construction procedures, the system automatically forms an overall progress plan and corresponding time nodes according to the filled data, and analyzes daily plan progress required to be completed every day according to the involved surrounding rock grades for decision reference of the project managers;
the progress filling module fills the engineering content of the whole linear engineering in a range mileage mode according to the engineering type of tunnel construction;
and the progress analysis module compares the planned progress with the actual progress and analyzes whether the current progress is in a lagging or leading state.
While adopting the technical scheme, the invention can also adopt or combine the following technical scheme:
as a preferred technical scheme of the invention: the data on the two sides of the overview page mainly comprise daily progress completion conditions, total progress completion percentages, comparison between actual progress completion conditions in nearly seven days and planned progress in nearly seven days, progress delay reminding, progress to-be-overdue reminding, delay days or ahead days and progress time nodes.
As a preferred technical scheme of the invention: the overview page center base map or the BIM model displays progress in a mode of overlapping layers with different colors, and according to data filled in the progress, the system automatically overlaps corresponding layers in corresponding areas to express different progresses with different colors.
As a preferred technical scheme of the invention: in the progress filling module, the project contents required to be filled include: the unit of the process is meter.
As a preferred technical scheme of the invention: the progress analysis module specifically performs the following analysis:
leading days X or lagging days X = (face footage-current planned face footage) ÷ (face footage/number of constructed days);
x > or =0, X representing the number of days of progress advance;
x is less than 0 and represents the number of days of progress delay;
therefore, progress deduction of the tunnel face is completed, managers can further analyze the progress conveniently, and corresponding measures are adopted to accelerate the progress.
The visual tunnel construction progress management and analysis system provided by the invention is mainly developed based on a Web end and integrates four functional modules of progress overview, progress plan, progress filling and progress analysis, wherein the progress overview module is used as a system main data integration module and is used as a decision center of project management personnel, the progress plan module, the progress filling module and the progress analysis module are used as data sources of the system, the project personnel acquire data by filling in the progress filling module, and the progress analysis module calculates and analyzes the filled data to obtain relevant progress decision data for decision making of the project management personnel. The visual tunnel construction progress management and analysis system provided by the invention can monitor the progress condition of the whole linear project and the progress condition of each work point in an all-around manner, thereby better serving project management personnel to control the field progress, and meanwhile, the visual tunnel construction progress management and analysis system can be deployed into the whole intelligent construction site system as a subsystem of the intelligent construction site platform to be developed for one time and reused for the intelligent construction site platform of the subsequent tunnel project.
Drawings
Fig. 1 is a functional block diagram of a visualized tunnel construction progress management analysis system provided by the present invention.
Fig. 2 is a field diagram of tunnel engineering progress.
Fig. 3 shows the progress of the near seven days.
Detailed Description
The invention is described in further detail with reference to the figures and specific embodiments.
The visual tunnel construction progress management and analysis system provided by the invention is mainly developed based on a Web end, mainly manages the progress of tunnel engineering, centers on the progress management of the tunnel engineering, and integrates four functional modules, namely a progress overview module, a progress planning module, a progress filling module and a progress analysis module, as shown in figure 1.
The progress overview module is used as an overview page of the system, the progress planning module, the progress filling module and the progress analysis module are integrated on two sides of the overview page, and the middle base map is a BIM model or a plane base map. The data on the two sides of the page mainly comprise daily progress completion conditions, total progress completion percentages, near seven-day actual progress completion conditions, near seven-day planned progress comparison, progress delay reminding, progress to-be-overdue reminding, delay days or ahead days and progress time nodes. The progress is displayed by adopting a mode of overlapping layers with different colors in a page center base map or a BIM model, and according to data filled in the progress, the system automatically overlaps corresponding layers in corresponding areas to express different progresses with different colors. The tunnel mainly shows progress fields as shown in fig. 2, and project management personnel can add related progress fields and set corresponding field colors according to project conditions in a customized manner and report the finished project amount.
The progress planning module mainly takes filling as a main part, project managers form corresponding plan cross-road graphs on the progress planning module according to construction procedures according to the overall plan of the project, the system automatically forms an overall progress plan and corresponding time nodes according to the filled data, and daily plan progress required to be completed is analyzed according to the related surrounding rock grades and is used for decision reference of the project managers.
The progress filling module divides the whole linear project into three filling project contents, namely a tunnel face process, a second lining process, an inverted arch process and the like in a range mileage mode according to the project type of tunnel construction, the unit is meter, the progress filling can be completed by clicking and submitting, and data is displayed in a progress overview in a seven-day progress mode, which is shown in detail in fig. 3. Meanwhile, the system updates the filled progress data on the BIM or the two-dimensional base map for data display, compares the data with the progress plan in the progress analysis and carries out progress deduction.
The progress analysis module compares the planned progress with the actual progress, analyzes whether the current progress is in a lagging or leading state, and according to a calculation formula:
leading days X or lagging days X = (face footage-current planned face footage) ÷ (face footage/number of constructed days);
x > or =0, X representing the number of days of progress advance;
x is less than 0 and represents the number of days of progress delay;
therefore, progress deduction of the tunnel face is completed, managers can further analyze the progress conveniently, and corresponding measures are adopted to accelerate the progress.
The field project manager adopts a mode of adopting a small program to fill data as bottom-layer data acquisition, the system automatically analyzes the filled data, generates corresponding progress display based on a chart, a crosswalk graph, a plane base map or a BIM model, and meanwhile deduces and calculates the progress condition and analyzes lag days or lead days.
The visual tunnel construction progress management and analysis system provided by the invention can more vividly provide decision basis for project management personnel through progress display and progress deduction and control the project field progress condition.
The above-described embodiments are intended to illustrate the present invention, but not to limit the present invention, and any modifications, equivalents, improvements, etc. made within the spirit of the present invention and the scope of the claims fall within the scope of the present invention.
Claims (5)
1. The utility model provides a visual tunnel construction progress management analytic system which characterized in that: the visual tunnel construction progress management and analysis system comprises a progress overview module, a progress planning module, a progress reporting module and a progress analysis module;
the progress overview module is used as an overview page of the visual tunnel construction progress management and analysis system, three modules of progress planning, progress filling and progress analysis are arranged on two sides of the overview page, and a middle base map of the overview page is a BIM (building information modeling) model or a plane base map;
the progress planning module takes the filling of the progress filling module as data input, project managers form corresponding plan cross-road graphs on the progress planning module according to the project overall plan and construction procedures, the system automatically forms an overall progress plan and corresponding time nodes according to the filled data, and analyzes daily plan progress required to be completed every day according to the involved surrounding rock grades for decision reference of the project managers;
the progress filling module fills the engineering content of the whole linear engineering in a range mileage mode according to the engineering type of tunnel construction;
and the progress analysis module compares the planned progress with the actual progress and analyzes whether the current progress is in a lagging or leading state.
2. The visual tunnel construction progress management and analysis system according to claim 1, characterized in that: the data on the two sides of the overview page mainly comprise daily progress completion conditions, total progress completion percentages, comparison between actual progress completion conditions in nearly seven days and planned progress in nearly seven days, progress delay reminding, progress to-be-overdue reminding, delay days or ahead days and progress time nodes.
3. The visual tunnel construction progress management and analysis system according to claim 1, characterized in that: the overview page center base map or the BIM model displays progress in a mode of overlapping layers with different colors, and according to data filled in the progress, the system automatically overlaps corresponding layers in corresponding areas to express different progresses with different colors.
4. The visual tunnel construction progress management and analysis system according to claim 1, characterized in that: in the progress filling module, the project contents required to be filled include: the unit of the process is meter.
5. The visual tunnel construction progress management and analysis system according to claim 1, characterized in that: the progress analysis module specifically performs the following analysis:
leading days X or lagging days X = (face footage-current planned face footage) ÷ (face footage/number of constructed days);
x > or =0, X representing the number of days of progress advance;
x is less than 0 and represents the number of days of progress delay;
therefore, progress deduction of the tunnel face is completed, managers can further analyze the progress conveniently, and corresponding measures are adopted to accelerate the progress.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111485040.6A CN114201799A (en) | 2021-12-07 | 2021-12-07 | Visual tunnel construction progress management analysis system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111485040.6A CN114201799A (en) | 2021-12-07 | 2021-12-07 | Visual tunnel construction progress management analysis system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114201799A true CN114201799A (en) | 2022-03-18 |
Family
ID=80651026
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111485040.6A Pending CN114201799A (en) | 2021-12-07 | 2021-12-07 | Visual tunnel construction progress management analysis system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114201799A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115439105A (en) * | 2022-11-04 | 2022-12-06 | 深圳市睿拓新科技有限公司 | User-oriented construction project progress supervision method and system |
CN116611795A (en) * | 2023-07-19 | 2023-08-18 | 深圳广信建设(集团)有限公司 | Construction progress intelligent management and control system suitable for garden construction |
CN117408643A (en) * | 2023-12-12 | 2024-01-16 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
CN117952573A (en) * | 2024-03-27 | 2024-04-30 | 四川蜀道电气化建设有限公司 | Four-electrical engineering construction management method and system based on GIS data |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105427091A (en) * | 2015-12-03 | 2016-03-23 | 国网浙江杭州市萧山区供电公司 | High-voltage business expansion overall process management and control system of power marketing |
CN106384191A (en) * | 2016-08-31 | 2017-02-08 | 铁道第三勘察设计院集团有限公司 | Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model |
CN107146065A (en) * | 2017-03-20 | 2017-09-08 | 中国铁道科学研究院电子计算技术研究所 | Railway engineering management platform system |
CN111768166A (en) * | 2020-06-08 | 2020-10-13 | 四川省红地科技有限责任公司 | Project progress management based method |
-
2021
- 2021-12-07 CN CN202111485040.6A patent/CN114201799A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105427091A (en) * | 2015-12-03 | 2016-03-23 | 国网浙江杭州市萧山区供电公司 | High-voltage business expansion overall process management and control system of power marketing |
CN106384191A (en) * | 2016-08-31 | 2017-02-08 | 铁道第三勘察设计院集团有限公司 | Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model |
CN107146065A (en) * | 2017-03-20 | 2017-09-08 | 中国铁道科学研究院电子计算技术研究所 | Railway engineering management platform system |
CN111768166A (en) * | 2020-06-08 | 2020-10-13 | 四川省红地科技有限责任公司 | Project progress management based method |
Non-Patent Citations (3)
Title |
---|
杨文军;杨青;于佳露;: "基于BIM技术的桥梁工程项目进度管理研究", 项目管理技术, no. 04, 10 April 2020 (2020-04-10) * |
栾卫江;: "工程管理曲线在公路工程中的应用", 价值工程, no. 12, 28 April 2011 (2011-04-28) * |
郭永峰;郭晓娜;: "南水北调中线干线工程进度管理的探索与实践", 南水北调与水利科技, no. 02, 15 April 2011 (2011-04-15) * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115439105A (en) * | 2022-11-04 | 2022-12-06 | 深圳市睿拓新科技有限公司 | User-oriented construction project progress supervision method and system |
CN116611795A (en) * | 2023-07-19 | 2023-08-18 | 深圳广信建设(集团)有限公司 | Construction progress intelligent management and control system suitable for garden construction |
CN117408643A (en) * | 2023-12-12 | 2024-01-16 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
CN117408643B (en) * | 2023-12-12 | 2024-03-22 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
CN117952573A (en) * | 2024-03-27 | 2024-04-30 | 四川蜀道电气化建设有限公司 | Four-electrical engineering construction management method and system based on GIS data |
CN117952573B (en) * | 2024-03-27 | 2024-06-11 | 四川蜀道电气化建设有限公司 | Four-electrical engineering construction management method and system based on GIS data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114201799A (en) | Visual tunnel construction progress management analysis system | |
CN111021265B (en) | BIM technology-based railway large-span continuous beam swivel construction control method | |
CN115860499B (en) | BIM technology-based multi-specialty work coordination construction management system | |
CN109710990B (en) | BIM technology-based roller compacted concrete dam construction progress-cost cooperative control method | |
CN105574652A (en) | Planning big data management and control system of smart power distribution network and method | |
CN111369158A (en) | BIM-based informatization quality management method and system | |
CN113807685B (en) | BIM-based hydraulic tunnel construction progress informatization management method | |
Han et al. | Construction quality evaluation of asphalt pavement based on BIM and GIS | |
CN106997511A (en) | Railway beam yard management system and railway beam yard management method based on BIM technology | |
CN109636616B (en) | Method for realizing project group progress master control management | |
CN113722797A (en) | Lightweight BIM prefabricated part full life cycle comprehensive information management system | |
CN111291994A (en) | Multi-project management system and method suitable for agile development mode in big data environment | |
CN111241620A (en) | Construction period prediction method and construction method based on tunnel engineering progress slope diagram | |
CN113011832A (en) | Engineering cost system based on BIM | |
CN117521231A (en) | Intelligent piling monitoring management method and system based on BIM and IOT | |
CN110909407A (en) | Cave laboratory and vertical shaft BIM model creation method based on BIM | |
CN116562802A (en) | Intelligent construction application platform of track traffic based on BIM | |
CN115187039A (en) | Construction progress management method and system based on BIM | |
CN116596483A (en) | Bridge construction organization method based on three-dimensional digital technology | |
Chacón et al. | Digital twinning of building construction processes. Case study: A reinforced concrete cast-in structure | |
Mitelman et al. | Implementing BIM for conventional tunnels-a proposed methodology and case study. | |
Li et al. | Study on filling support design and ground pressure monitoring scheme for gob-side entry retention by roof cutting and pressure relief in high-gas thin coal seam | |
Jiang et al. | Monitoring system for the construction of arch cover method Subway Station based on DT and IoT | |
CN109903008A (en) | A kind of subway work construction project progress visualization managing and control system and management-control method | |
CN112396296A (en) | Resource scheduling system based on BIM |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |