CN109903008A - A kind of subway work construction project progress visualization managing and control system and management-control method - Google Patents

A kind of subway work construction project progress visualization managing and control system and management-control method Download PDF

Info

Publication number
CN109903008A
CN109903008A CN201910073106.7A CN201910073106A CN109903008A CN 109903008 A CN109903008 A CN 109903008A CN 201910073106 A CN201910073106 A CN 201910073106A CN 109903008 A CN109903008 A CN 109903008A
Authority
CN
China
Prior art keywords
data
project progress
subway
progress
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910073106.7A
Other languages
Chinese (zh)
Other versions
CN109903008B (en
Inventor
崔伟
费洋
李芳芳
邹凯阳
张昆
朱微维
朱祁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nari Rail Transit Technology Co ltd
Nari Technology Co Ltd
Original Assignee
Nari Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nari Technology Co Ltd filed Critical Nari Technology Co Ltd
Priority to CN201910073106.7A priority Critical patent/CN109903008B/en
Publication of CN109903008A publication Critical patent/CN109903008A/en
Application granted granted Critical
Publication of CN109903008B publication Critical patent/CN109903008B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of subway work construction project progress visualization managing and control system and management-control method, and subway work construction project progress data is reconstructed into the data structure that this kind has equipment template and point template by data structure recombination module;And the subway work construction project progress data after recombination is transmitted by data transmission module, data are received by data receiver and memory module, and subway construction engineering progress data is parsed and stored according to the Message Protocol of agreement, it solves in traditional subway subway construction construction work progress control, the summary information of all monthly magazines is embodied in the form of two-dimensional table, the problem of engineering progress data feature is not easy identification and the form of expression is single, cannot classify in computer software using and by computer software showing interface.

Description

A kind of subway work construction project progress visualization managing and control system and management-control method
Technical field
This patent is related to carrying out the technical field of data visualization identification by computer software, and especially one kind is used for The visualization of subway work construction project progress data identifies field.
Background technique
The progress control of subway work construction project fills in all monthly magazines by acquiring construction Supervision, and project engineer audits Zhou Yue Report, then be summarized at planning materials and carry out artificial screening, statistics, conclusion by all monthly magazine data of the related personnel to the moon weekly, It is fabricated to corresponding project progress table.Peopleware is suffered from when in subway work construction project progress control, mentions report The limitation of all many conditions such as not in time, project progress visualization are just particularly important, and can see automatic remittance with simple, intuitive The project progress visualized data of assembly, and the states such as early warning, alarm, overdue are very clear.
Research and development and application deployment stage in subway work construction project progress visualization system are needed for subway line The characteristics of civil construction, carries out a large amount of modeling work.Built in subway work construction project progress visualization system database Vertical model data is mapped to each practice of construction unit, and is realized by emulation logic to subway construction project progress The emulation of the various work functions of visualization system.According to the actual conditions of different engineerings, the data volume of model data in database It is even more to can achieve points up to ten thousand.Modeling work generally requires several engineers and spends longer time that could complete.
The shortcomings that prior art: 1, in subway work construction project progress control, previous statistics summarize by manually into Row is made a report on and is summarized, since the irregular data finally summarized and actual project progress of often resulting in of peopleware have It is entered and left, and can not intuitively embody the relationship of current project progress and annual plan.
2, in subway work construction project progress visualization system, has sophisticated functions between the multi-site data of incidence relation Largely exist.By traditional data models and emulate in the way of, because it is towards the spies such as single-point functional configuration, distinguishing hierarchy be single Point has manufactured sizable workload and work to system research and development personnel in the initial stage research and development of the such function of realization, test phase Make complexity.
3, during the deployment of the later period of subway work construction project progress visualization system, debugging, maintenance, for not With the actual conditions of engineering, model data in database rank generally even more in points up to ten thousand.Data volume it is huge, add Multi-point there is different function logics, traditional artificial data maintenance mode causes huge system maintenance personnel Work difficulty and workload.
Summary of the invention
Goal of the invention: the present invention provides a kind of new visualization managing and control system, can be by subway work construction project progress The data of middle acquisition carry out structural remodeling to be suitable for the input and storage of computer software, in order to carry out by software interface It shows.
The present invention provides a kind of new visualization management-control method, the number that can will be acquired in subway work construction project progress It is suitable for the input and storage of computer software according to progress structural remodeling, in order to be shown by software interface, and It is capable of providing data operation reinforcement, data off-limit alarm, the modified data processing function of plan comparison.
Technical solution: for achieving the above object, the present invention, which visualizes managing and control system, can be used following technical scheme:
A kind of subway work construction project progress visualization managing and control system, comprising:
Data structure recombination module has equipment template and point template, the general-purpose attribute value of equipment template extraction equipment, point The general-purpose attribute value of template extraction point, to be recombinated to subway construction engineering progress data;One equipment template contains Corresponding point template, and a point template then contains the corresponding point data of equipment, the point data in the point template includes mould Analog quantity point and digital quantity point;
Data transmission module transmits mould in data to transmit to the subway work construction project progress data after recombination Identifier is added to the subway work construction project progress data after recombination in block, then by subway work construction project progress number It is transmitted by way of message according to according to the Message Protocol of agreement;
Data receiver and memory module, to receive the subway work construction project progress number of data transmission module transmission According to, and subway construction engineering progress data is parsed and stored according to the Message Protocol of agreement.
The utility model has the advantages that the present invention has designed and Implemented a set of based on point-to-point data structure, and subway work is built Engineering progress data is reconstructed into the data structure that this kind has equipment template and point template, solves traditional subway subway construction and applies In work Management of engineering schedule, the summary information of all monthly magazines is embodied in the form of two-dimensional table, and engineering progress data feature is not easy to distinguish The problem of knowing and the form of expression be single, cannot classifying in computer software using and by computer software showing interface.
For achieving the above object, the present invention, which visualizes management-control method, can be used following technical scheme:
A kind of subway work construction project progress visualization management-control method, comprising the following steps:
(1), equipment template and point template, the general-purpose attribute value of equipment template extraction equipment are set, and point template extracts point General-purpose attribute value, to be recombinated to subway construction engineering progress data;One equipment template contains corresponding point template, And a point template then contains the corresponding point data of equipment, the point data in the point template includes analog quantity point and digital quantity Point;
(2), to after recombination subway work construction project progress data transmit, in data transmission module to recombination after Subway work construction project progress data adds identifier, then by subway work construction project progress data according to the report of agreement Literary transport protocol is transmitted by way of message;
(3), the subway work construction project progress data of data transmission module transmission is received, and is passed according to the message of agreement Defeated agreement is parsed and is stored to subway construction engineering progress data;
(4), the subway work construction project progress data in data receiver and memory module is shown.
(5), the displaying of visual data, the displaying of statistical data, iteration level operation are completed;
The all monthly magazine data informations of informationization that wherein displaying of visual data will make a report on, by with digital quantity, simulation The association of point is measured, it is more intuitive in the visualization such as plan view, station sectional view, route progress chart AT STATION to show building enclosure drilling Stake, the bottom plate of the performance of diaphragm wall and main structure, middle plate, top plate schedule;
The displaying of statistical data is according to all monthly magazine information made a report on, by determining logical operation, by station civil engineering Total project progress, the total project progress of section civil engineering, the statistical information for the total project progress of total project progress, equipment of laying a railway track, in route Progress visualizes on figure, be shown '
Iteration level operation is i.e. by the iterative processing to data, more rounds processing, according to data existing in informationization, Obtain deeper data statistics;
(6), be arranged alarm, early warning, lag a variety of miscellaneous function alert data threshold values;I.e. delay is completed and the time does not surpass It crosses and determines the time, carry out early warning;Delay is completed and the time is more than to determine the time, carries out lag alarm.
(7), by Practical Project progress performance, the schedule with Management of engineering schedule side is compared;If by Comparison, needs to be adjusted the plan of project progress, then carries out plan modification.
The utility model has the advantages that the present invention has designed and Implemented a set of based on point-to-point data structure, and subway work is built Engineering progress data is reconstructed into the data structure that this kind has equipment template and point template, solves traditional subway subway construction and applies In work Management of engineering schedule, the summary information of all monthly magazines is embodied in the form of two-dimensional table, and engineering progress data feature is not easy to distinguish The problem of knowing and the form of expression be single, cannot classifying in computer software using and by computer software showing interface, and It includes data operation reinforcement, data off-limit alarm, the modified data processing function of plan comparison that offer, which can be crossed,.
Detailed description of the invention
Fig. 1 is model data control construction structure chart of the present invention.
Specific embodiment
Incorporated by reference to shown in Fig. 1, the present invention provides a kind of subway work construction project progress visualization managing and control system, comprising:
Data structure recombination module has equipment template and point template.That is, all devices must be derived from some equipment mould Plate;All the points all must be according to belonging to some equipment.The general-purpose attribute value of equipment template extraction equipment, point template extract the general of point Attribute value, to be recombinated to subway construction engineering progress data;One equipment template contains corresponding point template, and one A point template then contains the corresponding point data of equipment, and the point data in the point template includes analog quantity point and digital quantity point. When deriving from equipment, according to equipment template institute attribute value predetermined come generating device data;And what equipment was included Point then generates point data according to attribute value defined in corresponding point template.
Data transmission module transmits mould in data to transmit to the subway work construction project progress data after recombination Identifier is added to the subway work construction project progress data after recombination in block, then by subway work construction project progress number It is transmitted by way of message according to according to the Message Protocol of agreement.In the module, by current data state and report Literary record storage combines, i.e., while storing subway work construction project progress data by bivariate table, by corresponding message Record is also stored
Data receiver and memory module, to receive the subway work construction project progress number of data transmission module transmission According to, and subway construction engineering progress data is parsed and stored according to the Message Protocol of agreement.
Data display module, to carry out the subway work construction project progress data in data receiver and memory module It shows.The mode of one selectable displaying is, in conjunction with current SVG (scalable vector graphics) technology, to be based on original engineering Design CAD drawing realizes the automatic conversion to CAD diagram paper, so that bivariate table data are passed through Station Layout, station section A variety of visualized graphs such as figure are shown.By more with designing institute, unit in charge of construction, supervisor and Management of engineering schedule side Round exchange, also demonstrates, and in interpersonal interactive mode, visual presentation more meets user to the intuitional and experiential thinking of data.
Data operation reinforcing module, to complete the displaying of visual data, the displaying of statistical data, iteration level operation;
The all monthly magazine data informations of informationization that wherein displaying of visual data will make a report on, by with digital quantity, simulation The association of point is measured, it is more intuitive in the visualization such as plan view, station sectional view, route progress chart AT STATION to show building enclosure drilling Stake, the bottom plate of the performance of diaphragm wall and main structure, middle plate, top plate schedule;
The displaying of statistical data is according to all monthly magazine information made a report on, by determining logical operation, by station civil engineering Total project progress, the total project progress of section civil engineering, the statistical information for the total project progress of total project progress, equipment of laying a railway track, in route Progress visualizes on figure, is shown;
Iteration level operation is i.e. by the iterative processing to data, more rounds processing, according to data existing in informationization, Obtain deeper data statistics.Such as according to station actual borehole stake performance, interative computation first goes out the drilling of this station The completion total amount or completion rate of stake, then in conjunction with all stations of whole route/section drilled pile schedule, again to data It is iterated processing, calculates and obtains all fronts station/section engineering completion total amount/completion rate.
Data off-limit alarm module, to be arranged alarm, early warning, lag a variety of miscellaneous function alert data threshold values;I.e. Delay is completed and the time is no more than the determining time, carries out early warning;Delay is completed and the time is more than to determine the time, is lagged Alarm.
Plan comparison correction module carries out data reconstruction, interative computation based on having all monthly magazine data informations to informationization And off-limit alarm processing, the performance of project progress can be determined from deeper time.By Practical Project progress performance, with The schedule of Management of engineering schedule side compares and analyzes, whether reasonable, the project progress of confirmation construction program arrangement Lag details whether within the acceptable range.If needing to be adjusted the plan of project progress, then by comparative analysis It can refer to the project progress relevant parameter after interative computation, carry out plan modification.Meanwhile by the exhibition of information-based view Show and the foundation of data incidence relation between points, realization exchange whole revised plan and carry out prediction scheme deduction.
And corresponding above-mentioned visualization managing and control system, another embodiment of the invention are to provide a kind of subway work construction Project progress visualizes management-control method, comprising the following steps:
(1), equipment template and point template, the general-purpose attribute value of equipment template extraction equipment are set, and point template extracts point General-purpose attribute value, to be recombinated to subway construction engineering progress data;One equipment template contains corresponding point template, And a point template then contains the corresponding point data of equipment, the point data in the point template includes analog quantity point and digital quantity Point.
(2), to after recombination subway work construction project progress data transmit, in data transmission module to recombination after Subway work construction project progress data adds identifier, then by subway work construction project progress data according to the report of agreement Literary transport protocol is transmitted by way of message;.
(3), the subway work construction project progress data of data transmission module transmission is received, and is passed according to the message of agreement Defeated agreement is parsed and is stored to subway construction engineering progress data;In this step, current data state and message are remembered Address book stored combines, i.e., while storing subway work construction project progress data by bivariate table, by corresponding message accounting Also it is stored.
(4), the subway work construction project progress data in data receiver and memory module is shown.
(5), the displaying of visual data, the displaying of statistical data, iteration level operation are completed.
The all monthly magazine data informations of informationization that wherein displaying of visual data will make a report on, by with digital quantity, simulation The association of point is measured, it is more intuitive in the visualization such as plan view, station sectional view, route progress chart AT STATION to show building enclosure drilling Stake, the bottom plate of the performance of diaphragm wall and main structure, middle plate, top plate schedule;
The displaying of statistical data is according to all monthly magazine information made a report on, by determining logical operation, by station civil engineering Total project progress, the total project progress of section civil engineering, the statistical information for the total project progress of total project progress, equipment of laying a railway track, in route Progress visualizes on figure, is shown;
Iteration level operation is i.e. by the iterative processing to data, more rounds processing, according to data existing in informationization, Obtain deeper data statistics.
(6), be arranged alarm, early warning, lag a variety of miscellaneous function alert data threshold values;I.e. delay is completed and the time does not surpass It crosses and determines the time, carry out early warning;Delay is completed and the time is more than to determine the time, carries out lag alarm.
(7), by Practical Project progress performance, the schedule with Management of engineering schedule side is compared;If by Comparison, needs to be adjusted the plan of project progress, then carries out plan modification.

Claims (8)

1. a kind of subway work construction project progress visualizes managing and control system characterized by comprising
Data structure recombination module has equipment template and point template, the general-purpose attribute value of equipment template extraction equipment, point template The general-purpose attribute value for extracting point, to be recombinated to subway construction engineering progress data;One equipment template contains correspondence Point template, and a point template then contains the corresponding point data of equipment, and the point data in the point template includes analog quantity Point and digital quantity point;
Data transmission module, to be transmitted to the subway work construction project progress data after recombination, in data transmission module Identifier is added to the subway work construction project progress data after recombination, then presses subway work construction project progress data Message Protocol as agreed is transmitted by way of message;
Data receiver and memory module, to receive the subway work construction project progress data of data transmission module transmission, and Subway construction engineering progress data is parsed and stored according to the Message Protocol of agreement.
2. subway work construction project progress according to claim 1 visualizes managing and control system, which is characterized in that further include Data display module, the subway work construction project progress data in data receiver and memory module to be shown.
3. subway work construction project progress according to claim 1 visualizes managing and control system, which is characterized in that the number According in reception and memory module, current data state is combined with message accounting storage, i.e., subway is stored by bivariate table and applied While work construction project progress data, corresponding message accounting is also stored.
4. subway work construction project progress according to claim 1 visualizes managing and control system, which is characterized in that further include Data operation reinforcing module, to complete the displaying of visual data, the displaying of statistical data, iteration level operation;
The all monthly magazine data informations of informationization that wherein displaying of visual data will make a report on, by with digital quantity, analog quantity point Association, AT STATION plan view, station sectional view, route progress chart etc. visualization in it is more intuitive show building enclosure drilled pile, The bottom plate of the performance of diaphragm wall and main structure, middle plate, top plate schedule;
The displaying of statistical data is according to all monthly magazine information made a report on, by determining logical operation, by station civil engineering chief engineer Cheng Jindu, the total project progress of section civil engineering, the statistical information for the total project progress of total project progress, equipment of laying a railway track, in route progress It visualizes on figure, be shown '
I.e. by the iterative processing to data, more round processing are obtained according to data existing in informationization for iteration level operation Deeper data statistics.
5. crossing traffic state recognition method according to claim 1, which is characterized in that further include data off-limit alarm mould Block, to be arranged alarm, early warning, lag a variety of miscellaneous function alert data threshold values;I.e. delay is completed and the time is no more than really It fixes time, carries out early warning;Delay is completed and the time is more than to determine the time, carries out lag alarm.
6. crossing traffic state recognition method according to claim 1, which is characterized in that further include plan comparison amendment mould Block, by Practical Project progress performance, the schedule with Management of engineering schedule side is compared;If being needed by comparison The plan of project progress is adjusted, then carries out plan modification.
7. a kind of subway work construction project progress visualizes management-control method, which comprises the following steps:
(1), equipment template and point template, the general-purpose attribute value of equipment template extraction equipment are set, and point template extracts the general of point Attribute value, to be recombinated to subway construction engineering progress data;One equipment template contains corresponding point template, and one A point template then contains the corresponding point data of equipment, and the point data in the point template includes analog quantity point and digital quantity point;
(2), the subway work construction project progress data after recombination is transmitted, to the subway after recombination in data transmission module Construction engineering progress data adds identifier, then passes subway work construction project progress data according to the message of agreement Defeated agreement is transmitted by way of message;
(3), the subway work construction project progress data of data transmission module transmission is received, and is assisted according to the message transmissions of agreement View is parsed and is stored to subway construction engineering progress data;
(4), the subway work construction project progress data in data receiver and memory module is shown.
(5), the displaying of visual data, the displaying of statistical data, iteration level operation are completed;
The all monthly magazine data informations of informationization that wherein displaying of visual data will make a report on, by with digital quantity, analog quantity point Association, AT STATION plan view, station sectional view, route progress chart etc. visualization in it is more intuitive show building enclosure drilled pile, The bottom plate of the performance of diaphragm wall and main structure, middle plate, top plate schedule;
The displaying of statistical data is according to all monthly magazine information made a report on, by determining logical operation, by station civil engineering chief engineer Cheng Jindu, the total project progress of section civil engineering, the statistical information for the total project progress of total project progress, equipment of laying a railway track, in route progress It visualizes on figure, be shown '
I.e. by the iterative processing to data, more round processing are obtained according to data existing in informationization for iteration level operation Deeper data statistics;
(6), be arranged alarm, early warning, lag a variety of miscellaneous function alert data threshold values;I.e. delay is completed and the time is no more than really It fixes time, carries out early warning;Delay is completed and the time is more than to determine the time, carries out lag alarm.
(7), by Practical Project progress performance, the schedule with Management of engineering schedule side is compared;If by comparison, It needs to be adjusted the plan of project progress, then carries out plan modification.
8. subway work construction project progress according to claim 7 visualizes management-control method, which is characterized in that step (3) in, current data state is combined with message accounting storage, i.e., subway work construction project progress is stored by bivariate table While data, corresponding message accounting is also stored.
CN201910073106.7A 2019-01-25 2019-01-25 Visual management and control system and method for subway construction project progress Active CN109903008B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910073106.7A CN109903008B (en) 2019-01-25 2019-01-25 Visual management and control system and method for subway construction project progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910073106.7A CN109903008B (en) 2019-01-25 2019-01-25 Visual management and control system and method for subway construction project progress

Publications (2)

Publication Number Publication Date
CN109903008A true CN109903008A (en) 2019-06-18
CN109903008B CN109903008B (en) 2022-09-09

Family

ID=66944096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910073106.7A Active CN109903008B (en) 2019-01-25 2019-01-25 Visual management and control system and method for subway construction project progress

Country Status (1)

Country Link
CN (1) CN109903008B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110737713A (en) * 2019-08-27 2020-01-31 广东一码通信科技有限公司 Data platform-based visual project progress display method, equipment and medium
CN112053131A (en) * 2020-09-07 2020-12-08 中国路桥工程有限责任公司 Engineering project management system
CN117131561A (en) * 2023-07-31 2023-11-28 北京梦诚科技有限公司 CAD drawing and progress chart combined display method and system for invisible and undispersed tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106384191A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN106384190A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model
CN107085758A (en) * 2017-01-19 2017-08-22 北京恒华伟业科技股份有限公司 A kind of project management method, apparatus and system
CN108022292A (en) * 2017-12-08 2018-05-11 郑州云海信息技术有限公司 A kind of numeral subway 3D method for visualizing and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106384191A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN106384190A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model
CN107085758A (en) * 2017-01-19 2017-08-22 北京恒华伟业科技股份有限公司 A kind of project management method, apparatus and system
CN108022292A (en) * 2017-12-08 2018-05-11 郑州云海信息技术有限公司 A kind of numeral subway 3D method for visualizing and system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110737713A (en) * 2019-08-27 2020-01-31 广东一码通信科技有限公司 Data platform-based visual project progress display method, equipment and medium
CN112053131A (en) * 2020-09-07 2020-12-08 中国路桥工程有限责任公司 Engineering project management system
CN117131561A (en) * 2023-07-31 2023-11-28 北京梦诚科技有限公司 CAD drawing and progress chart combined display method and system for invisible and undispersed tunnel
CN117131561B (en) * 2023-07-31 2024-03-15 北京梦诚科技有限公司 CAD drawing and progress chart combined display method and system for invisible and undispersed tunnel

Also Published As

Publication number Publication date
CN109903008B (en) 2022-09-09

Similar Documents

Publication Publication Date Title
CN107844424B (en) Model-based testing system and method
CN103412975B (en) Dynamic traffic emulation platform and emulation mode thereof
CN109903008A (en) A kind of subway work construction project progress visualization managing and control system and management-control method
CN107402976A (en) Power grid multi-source data fusion method and system based on multi-element heterogeneous model
CN105574652A (en) Planning big data management and control system of smart power distribution network and method
CN103500371A (en) Change control method based on BIM
CN101930481B (en) Method used for generating CIM model describing power grid change in designated time slot and system thereof
CN108736465A (en) A kind of future-state electric network model construction method and device
CN103617576A (en) General fault detecting and maintenance method for equipment
CN102867091B (en) The quantitation modification method of a kind of electric network current diagram
CN106997511A (en) Railway beam course management system and railway beam a management method based on BIM technology
CN108595818B (en) Assembly type building management method and system based on BIM and cloud service
CN107562953A (en) A kind of river information system based on GIS geographical information technologies
CN109522661A (en) A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system
CN110110376A (en) A kind of hinge dam type scheme analysis method for quantitatively evaluating and device based on BIM
CN109583002A (en) Aviation electronics integral design method
CN109685558A (en) A kind of Cost for Electric Power Engineering evaluation system based on BIM technology
CN113887939A (en) BIMGIS-based cloud rendering energy storage hydraulic power plant digital delivery implementation method, system, storage medium and equipment
CN109784758A (en) Construction quality supervision early warning system and method based on BIM model
CN104809655A (en) Power grid monitoring auxiliary analysis method
CN107609794A (en) A kind of technology maturity evaluation information processing unit
CN104881739A (en) Marketing and distribution data consistency verification method based on IEC61970-61968 CIM standard
CN104537168A (en) Integrated supervisory control simulating training system model data management method for equipment functions
CN111401789A (en) Building construction intelligent supervision system based on BIM
CN116523401A (en) Method and device for constructing digital twin of oil reservoir

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221207

Address after: No. 19, Jiangning District, Jiangning District, Nanjing, Jiangsu

Patentee after: NARI TECHNOLOGY Co.,Ltd.

Patentee after: NARI Rail Transit Technology Co.,Ltd.

Address before: No. 19, Jiangning District, Jiangning District, Nanjing, Jiangsu

Patentee before: NARI TECHNOLOGY Co.,Ltd.