CN106339490A - System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model - Google Patents

System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model Download PDF

Info

Publication number
CN106339490A
CN106339490A CN201610788265.1A CN201610788265A CN106339490A CN 106339490 A CN106339490 A CN 106339490A CN 201610788265 A CN201610788265 A CN 201610788265A CN 106339490 A CN106339490 A CN 106339490A
Authority
CN
China
Prior art keywords
data
progress
dimensional
module
work point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610788265.1A
Other languages
Chinese (zh)
Inventor
宁新稳
韩祖杰
王�华
赵文
刘小龙
范登科
王娇
黄漪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Railway Survey and Design Institute Group Corp
Original Assignee
Third Railway Survey and Design Institute Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Railway Survey and Design Institute Group Corp filed Critical Third Railway Survey and Design Institute Group Corp
Priority to CN201610788265.1A priority Critical patent/CN106339490A/en
Publication of CN106339490A publication Critical patent/CN106339490A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/29Geographical information databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/05Geographic models

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Software Systems (AREA)
  • Databases & Information Systems (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Remote Sensing (AREA)
  • Geometry (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Computer Graphics (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a system and a method for managing railway bridge construction progress based on a 3DGIS (Three-dimensional Geographic Information System) and an engineering three-dimensional model. The system comprises a user management module, an actual progress data collecting module, a construction and organization plan module, a three-dimensional image progress display module, a statistic analysis module, a progress early-warning module and a log record module, wherein the actual progress data collecting module has the functions of data filling and reporting, data auditing and storing; the construction and organization plan module is used for making and inputting a work point construction and organization plan; the three-dimensional image display module has the functions of three-dimensional image leading-in, bridge work point model leading-in, three-dimensional navigating and progress display; the statistic analysis module is used for carrying out statistic analysis on progress data and outputting a statistical form; the progress early-warning module has the functions of early-warning personnel allocation and short message reminding; the log record module is capable of recording user login information, progress filling and reporting information and audit information in real time. According to the system and the method, disclosed by the invention, refined and three-dimensional visual management of railway bridge construction progress can be realized.

Description

Railroad bridge construction project time management system based on 3dgis and engineering threedimensional model and Management method
Technical field
The invention belongs to the informationization technology field of railway and Construction of Urban Rail Traffic is and in particular to one kind is based on The railroad bridge construction project time management systems and management method of 3dgis and engineering threedimensional model.
Background technology
The fast development built with railway infrastructure, substantial amounts of large-scale and extra-large bridge constantly putting into operation, It is contemplated that the factor such as environment, soil, maintenance particularly in high speed railway construction, the proportion shared by bridge is increasing.Mesh The displaying of front Bridges in Our Country construction speed and management mainly adopt form and X-Y scheme mode, carry out data with this mode and adopt The standardization of collection and automaticity is low, Up-to-date state is poor, data granularity is thick, have that data acquisition is difficult, data statistic analysis not The problems such as convenient, progress shows visual in image.The complexity being continuously increased with information in work progress of bridge construction quantity And instantaneity, bring very big pressure to construction management, need the management means of modernization badly.
Content of the invention
It is an object of the present invention to provide a kind of standardization and high degree of automation, Up-to-date state are good, be easy to data acquisition Data statistical analysiss, progress show the visual in image railroad bridge construction speed pipe based on 3dgis and engineering threedimensional model Reason system.
It is a further object of the present invention to provide a kind of carry out railroad bridge construction project time management using above-mentioned management system Method.
For this reason, technical scheme is as follows:
A kind of railroad bridge construction project time management system based on 3dgis and engineering threedimensional model, including user management mould Block, actual progress data acquisition module, to apply group schedule module, three-dimensional image progress display module, statistical analysis module, progress pre- Alert module and logger module, described user management module is used for carrying out User logs in, cancellation, personal management and authority joining Put;Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and data loading;Described apply group plan mould Block is used for carrying out plan and plan typing;Described three-dimensional image progress display module is used for three-dimensional scenic loading, bridge work Point model imports, three-dimensional range and progress show;Described statistical analysis module is used for carrying out statistics analysis and report output; Described progress warning module is used for carrying out early warning personnel depaly and note is reminded;Described logger module is used for real time record and uses Family log-on message, progress make a report on information and msu message.
Described User logs in is user input username and password login system, and illegal account is unable to login system;Described Nullify the user account information preserving for user log off, system-kill;Described personal management is that system user is added Plus, delete and change;Described authority configuration is that system user authority is managed, and described system user authority includes manager Authority, data make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority.
Described data is made a report on and is made a report on the user of authority for having data and make a report on system using the construction data of X-Y scheme Make a report on progress data;Described data audits the construction data examination & verification using X-Y scheme for the user auditing authority for having data The progress data that system audit user makes a report on;Described data loading is that the user with data examination & verification authority will audit the number passing through According to input database.
Described plan is target advance, the plan on-stream time including work point component and the plan formulating bridge work point Deadline;Described plan typing is in the work point target advance input database that will formulate.
The three-dimensional geographic scenes that described three-dimensional scenic is loaded as real scene around rail track is rendered generation enter Row loads;
It is that science of bridge building threedimensional model is loaded in described three-dimensional scenic that described bridge work point model imports;Described three-dimensional Roaming is to carry out multi-angle to bridge work point display effect to browse;Described progress is shown as dragging time shafts, in three-dimensional scenic The progress of display bridge work point random time point.
It is in data base, work point actual progress data and target advance data to be inquired about that described statistics are analyzed And statistical analysiss, extract work point day, week, month, year, Kai Lei branch, subdivisional work data;Described report output is by statistics The result of analysis is output as form.
Described early warning personnel depaly is that configuration needs to send the personnel that short message warning is reminded;It is according to meter that described note is reminded The advanced or delayed work sky that the progress of drawing is gone out with actual progress comparing calculation, formulates advanced warning grade, and exceeding definition grade will send out automatically Note, to related personnel, carries out progress warning.
A kind of railroad bridge construction project time management method based on 3dgis and engineering threedimensional model, using claim 1-7 Any one of bridge construction carried out based on the railroad bridge construction project time management system of 3dgis and engineering threedimensional model enter Degree management, described management method includes: three-dimensional scenic is set up;Bridge work point model decomposes and imports;The adopting of actual progress data Collection;Target advance data loading;Three-dimensional image progress shows;Generate progress report and carry out progress early warning.
Described three-dimensional scenic is set up to include processing the digital image data in rail track region and is generated orthography, by number Word altitude data processes and generates digital elevation model, is then superimposed described orthography with digital elevation model and renders generation void Intend three-dimensional scenic.
Described bridge work point model decomposition is comprised the following steps with importing:
1) adopt parametric modeling mode, automatically extract work point design parameter from two-dimensional design in figure;
2) bridge work point model is decomposed, be classified as pile foundation, cushion cap, pier shaft, beam section and beam block;
3) interface that 3ds max provides is utilized to generate threedimensional model;
4) make the three-dimensional of bridge work point part and import table, including definition component numbering, calculate its geographical coordinate and attitude Parameter;
5) according to the geographical coordinate in described three-dimensional importing table and attitude parameter, work point model importing 3dgis platform is carried out Display and management.
The collection of described actual progress data comprises the following steps:
1) work extracted point design parameter is stored in underlying parameter data base;
2) obtain work point design parameter from data base, generate pile foundation, cushion cap, pier shaft, beam section, the two dimensional surface of beam block Figure, using openlayers provide assembly and interface realize work point vector figure Fast Drawing, render, Pan and Zoom;
3) vector element is clicked on from two-dimensional vector figure to carry out progress and make a report on, described pile foundation, cushion cap, beam section, the entering of beam block Degree is represented with completing and not completing two states, and pier shaft progress actually accomplishes highly to represent by input, carries after the completion of making a report on Give auditor;
4) auditor audits to the progress data made a report on, and underproof data is marked, and returns modification, such as Fruit all qualified then by data inputting actual progress data base.
Described target advance data loading is by the target advance input database of work point, specially adopts gunter drawing Method is formulated work point and is applied group plan input database.
Described three-dimensional image progress shows, is the actual progress data using described input database and target advance number According to, according to progress data calculate and change described bridge work point model each component color, realize bridge construction three-dimensional shaped As progress shows.
Described generation progress report, be described actual progress data and target advance data are carried out count, relative analyses, Extract work point day, week, month, year, open tired (having totaled since going into operation) branch, subdivisional work data, generate progress report.
Described carry out progress early warning, be that described actual progress data and target advance data are analyzed, calculate Before excess of export or the delayed duration, formulate advanced warning grade, to exceeding definition grade, automatically send short messages to related personnel, carry out progress report Alert.
The invention has the beneficial effects as follows,
1st, the present invention makes a report on system by patterned construction data, construction data collecting efficiency is greatly improved, significantly Decrease the input service amount of user, data normalization degree is high;
2nd, the present invention passes through patterned construction data auditing system, the progress data made a report on is audited, makes progress Examination & verification is very visual in image, easy to operate, reduces the labor intensity of auditor, has ensured the accuracy of data;
3rd, the progress data of present invention collection can drive science of bridge building threedimensional model, carries out three-dimensional shaped in 3dgis platform As progress display, the space-time characterisation of work progress can be shown comprehensive, visual in imagely, contribute to construction management person to project progress Grasp macroscopical;
4th, the present invention can carry out statistical analysiss to progress data, automatically generate various statistical report forms, drastically reduce the area use Family statistic analysis amount, improves bridge construction progress control level and efficiency;
5th, the present invention is analyzed to target advance and actual progress by progress warning module, calculates delayed or super Front work sky, sends an SMS to management personnel automatically according to advanced warning grade, ensures project progress.
Brief description
Fig. 1 is the functional block diagram group of the railroad bridge construction project time management system based on 3dgis and engineering threedimensional model Cheng Tu;
Fig. 2 is the flow chart of the railroad bridge construction project time management method based on 3dgis and engineering threedimensional model;
Fig. 3 is that the management method Bridge work point model of the present invention decomposes and guiding flow figure;
Fig. 4 be the present invention management method in actual progress collecting method flow chart.
Specific embodiment
Below in conjunction with the accompanying drawings the management system and management method of the present invention is described in detail.
As shown in figure 1, the railroad bridge construction project time management system bag based on 3dgis and engineering threedimensional model of the present invention Include: user management module, actual progress data acquisition module, apply group schedule module, three-dimensional image progress display module, statistical Analysis module and logger module.
Described user management module is used for carrying out User logs in, cancellation, personal management and authority configuration.Wherein:
User logs in refers to user input username and password login system, and illegal account is unable to login system, system root According to the username and password of user input, search from database user table, then login system that the match is successful;
Cancellation refers to user log off, the user account letter preserving in system-kill browser cookies and session Breath, needs after cancellation again to log in and could use system;
Personal management refers to that system manager user is added to system user, deletes, changing etc. operating, and data base uses The information such as user name, password, department are preserved, password is stored with the mode that md5 encrypts in the table of family;
Authority configuration refers to that system manager user is managed to system user authority, and described system user authority includes Administrator right, data make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority. Each user has the authority of oneself, has data and makes a report on the user of authority and can be made a report on using the construction data of X-Y scheme System makes a report on progress data;The user having data examination & verification authority can be filled out using the construction data examination & verification user of X-Y scheme The progress data of report;The user having plan authority can be made a plan using applying group schedule module;Have statistical analysiss The user of authority can carry out report output using statistical analysis module;The user having three dimensional navigation authority can log in Work point three-dimensional image progress checked by 3dgis platform.
Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and putting in storage.Wherein:
Data is made a report on to refer to have data and make a report on the user of authority and is filled out using the construction data system of making a report on of X-Y scheme Report progress data, specially selects work point, obtains work point parameter, provided using openlayers from underlying parameter data base Assembly and interface are realized the Fast Drawing of bridge work point vector figure, are rendered, translate, scaling, and click vector element carries out progress and fills out Report, submits to auditor and is audited after the completion of making a report on;
Data examination & verification refers to that the user with data examination & verification authority utilizes the construction data auditing system of X-Y scheme to examine The progress data that core user makes a report on, specially on two-dimentional work point vector figure, needs the highlighted expression of key element of examination & verification, clicks on key element Check progress msg, underproof data is marked, returns modification, if all qualified, enter next step, by data In typing actual progress data base;
Data loading refers to that the user with data examination & verification authority will audit the data inputting data base passing through, the number of warehouse-in Can not change again according to locked.
Described applying organizes formulation and the typing that schedule module applies group plan for work point, and the method using gunter drawing formulates work point Apply group plan, record in initial and the deadline, and input database of each task, work point part.
Described three-dimensional image progress display module is used for carrying out three-dimensional scenic loading, bridge work point model imports, three-dimensional unrestrained Trip and progress show.Wherein:
Three-dimensional scenic loads the three-dimensional geographical environment referring to for real scene around rail track render generation and loads Shown in 3dgis platform;
Bridge work point model imports and refers to science of bridge building threedimensional model is loaded in three-dimensional scenic, by making bridge work Point part is three-dimensional to import table, and including unit number definition, geographical coordinate calculates, attitude parameter calculates, and imports in table according to three-dimensional Geographical coordinate and attitude parameter, attitude parameter includes the angle of pitch, yaw angle and roll angle, realizes the seamless of bridge work point part Splicing and assembling;
Three-dimensional range refers in three-dimensional scenic, bridge work point display effect to be carried out comprehensive, multi-angle and browses;
Progress shows and refers to drag time shafts, obtain from data base the actual progress of current time work point and plan into Degree, calculates the completion statuses of each component of point model of going to work, and represents progress status by changing model color in three-dimensional scenic, As completed use blueness represents, do not start represents with Lycoperdon polymorphum Vitt, actual progress exceedes target advance redness and represents, actual enter Spend delayed target advance yellow to represent.
Described statistical analysis module is used for carrying out the statistical analysiss of progress data, from data base, progress data is united Meter inquiry, can extract day, week, month, year, open tired (having totaled since going into operation) branch and subdivisional work data, output statistics Form;
Described progress warning module is used for carrying out early warning personnel depaly and note is reminded.Wherein:
Early warning personnel depaly refers to configure to be needed to send the personnel that short message warning is reminded, the surname of record keeping personnel in data base Name and cell-phone number;
Note reminds the advanced or delayed work sky referring to go out according to target advance and actual progress comparing calculation, formulates early warning Grade, exceedes definition grade and is automatically sent short messages to related personnel, carry out progress warning.
Described logger module is used for real time record user login information, progress makes a report on information, msu message, these letters Breath is saved in data base it is ensured that each database manipulation has record can follow, and ensures data safety.
Referring to Fig. 2-Fig. 4, the railroad bridge construction project time management side based on 3dgis and engineering threedimensional model of the present invention Method, comprises the following steps: three-dimensional scenic is set up, bridge work point model decomposes and the construction data importing, setting up X-Y scheme Make a report on system, set up the construction data auditing system of X-Y scheme, set up actual progress data base, set up target advance data Storehouse, carry out three-dimensional image progress based on progress data driving model and show, generate progress report and carry out progress early warning.Concrete step Suddenly as follows:
1st, three-dimensional scenic is set up: the digital image data in rail track region is processed and generates orthography dom, by numeral Altitude data process generate digital elevation model dem, then orthography is superimposed with digital elevation model render generate virtual Three-dimensional scenic.
2nd, bridge work point model decomposes and imports: by engineering control decomposing, by bridge work point model be divided into pile foundation, cushion cap, Pier shaft, beam section and beam block, import and are shown in 3dgis platform and manage, bridge work point model adopts parametric modeling mode, Automatically extract parameter from two-dimensional design drawing, generate threedimensional model using the interface that 3ds max provides;From two-dimensional design drawing In automatically extract parameter, carry out secondary development under autocad platform, according to professionally-designed chart lateral model, set up interpreting blueprints rule, Interpreting blueprints rule according to definition is interpreted, with figure layer, color, line style as foundation, to annotation, component multistage in design drawing Line, cross section structure parameter are refined, and extract design parameter.In order to show pier shaft progress, pier shaft needs by highly dividing further Solution, typically can be decomposed by 3 meters one section, pile foundation, cushion cap, beam section, beam block etc. do not need to decompose further.Make bridge work Point part is three-dimensional to import table, and including unit number definition, geographical coordinate calculates and attitude parameter calculates, and imports in table according to three-dimensional Geographical coordinate and attitude parameter, realize the seamless spliced of bridge work point part and assembling.Unit number defines: its pile foundation, Cushion cap, the numbering of pier shaft are made up of work vertex type, work point numbering, unit type, bridge pier numbering, element type, unit number, beam Section, beam block number are made up of work vertex type, work point numbering, unit type, beam numbering, unit number, and such as numbering is 1-21-p-0- Z-0, wherein 1 expression bridge, 21 represent work point numbering, and p represents bridge pier, and 0 represents bridge pier numbering, and z represents drilled pile, 0 expression stake Numbering.
3rd, the construction data carrying out X-Y scheme is made a report on: the parameter automatically extracting in two-dimensional design drawing is stored in data Storehouse, obtains work point parameter, the assembly providing and interface realize the quick of work point vector figure using openlayers from data base Draw, render, roam and scale, click vector element carries out progress and makes a report on, and pile foundation, cushion cap, beam section and beam block progress are with completing Represent with undone two states, pier shaft progress actually accomplishes height by input and represents.In order to ensure the verity of data, use The progress data that family is made a report on need to audit ability input database by auditor, and usually unit in charge of construction's surveyor enters line number According to making a report on, supervisor auditor is audited.
4th, carry out the construction data examination & verification of X-Y scheme: the progress data that user makes a report on is audited, needs to audit Data be highlighted on vectogram, by click on check the progress msg made a report on, underproof data is marked, moves back Return something for repairs and change, if all qualified, enter next step, by data inputting actual progress data base.
5th, set up actual progress data base: in the progress data input database that examination & verification is passed through, it is right to need before warehouse-in Data carries out logical consistency inspection, and such as pier shaft does not complete, above beam section can not possibly complete.Data after warehouse-in can not be more Change.
6th, set up target advance data base: by the target advance input database of work point, particularly as follows: using gunter drawing Method is formulated work point and is applied group plan input database, when the plan initial time including each task and component and plan complete Between, the planned start time of such as No. 19 pier pier shafts is August in 2016 20, and Projected completion time is September in 2016 20.
7th, carry out three-dimensional image progress based on progress data driving model to show: lookup acquisition work point one day from data base Phase actual progress data and target advance data, calculate the completion statuses of work each component of point model according to progress data, according to The color of each component of status modifier, realizes bridge construction three-dimensional image progress and shows.As completed use blueness represents, do not open Begin represents with Lycoperdon polymorphum Vitt, actual progress exceedes target advance redness and represents, actual progress delayed target advance yellow represents.
8th, generate progress report: statistical query is carried out to progress data, day, week, month, year, Kai Lei branch can be extracted, divide Item project data, generates progress report.As can be with statistical query currently all bridge work point drilled piles, cushion cap, pier shaft, beam etc. Day, week, month, year, open tired quantity performed, volume residual etc..
9th, progress early warning: actual progress data and target advance data are analyzed, calculate advanced or delayed Duration, formulate advanced warning grade, when exceeding definition grade, automatically send short messages to related personnel, carry out progress warning.As red in defined Color, orange, yellow, blue level Four advanced warning grade, red delayed 60 days, orange delayed 40 days, delayed 20 days of yellow, blue delayed 10 days, when exceeding yellow advanced warning grade, automatically send short messages to related management personnel and reminded.

Claims (15)

1. a kind of railroad bridge construction project time management system based on 3dgis and engineering threedimensional model it is characterised in that: include use Family management module, actual progress data acquisition module, apply group schedule module, three-dimensional image progress display module, statistical analysiss mould Block, progress warning module and logger module,
Described user management module is used for carrying out User logs in, cancellation, personal management and authority configuration;
Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and data loading;
Described group schedule module of applying is used for carrying out plan and plan typing.
Described three-dimensional image progress display module is used for three-dimensional scenic loading, the importing of bridge work point model, three-dimensional range and progress Display;
Described statistical analysis module is used for carrying out statistics analysis and report output;
Described progress warning module is used for carrying out early warning personnel depaly and note is reminded;
Described logger module is used for real time record user login information, progress makes a report on information and msu message.
2. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described User logs in is user input username and password login system, and illegal account is unable to login system;
The described user account information nullified as user log off, system-kill preservation;
Described personal management is system user to be added, delete and changes;
Described authority configuration is that system user authority is managed, and described system user authority includes administrator right, data Make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority.
3. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described data is made a report on and is made a report on the user of authority for having data and made a report on using the construction data system of making a report on of X-Y scheme Progress data;
Described data audits the construction data auditing system examination & verification using X-Y scheme for the user auditing authority for having data The progress data that user makes a report on;
Described data loading is that the user with data examination & verification authority will audit the data inputting data base passing through.
4. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described plan is the target advance formulating bridge work point, and plan on-stream time and plan including work point component complete Time;
Described plan typing is in the work point target advance input database that will formulate.
5. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
The three-dimensional geographic scenes that described three-dimensional scenic is loaded as real scene around rail track is rendered generation carry out adding Carry;
It is that science of bridge building threedimensional model is loaded in described three-dimensional scenic that described bridge work point model imports;
Described three-dimensional range is to carry out multi-angle to bridge work point display effect to browse;
Described progress is shown as dragging time shafts, shows the progress of bridge work point random time point in three-dimensional scenic.
6. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
It is in data base, work point actual progress data and target advance data to be inquired about and unite that described statistics are analyzed Meter analysis, extracts work point day, week, month, year, Kai Lei branch, subdivisional work data;
Described report output is that the result analyzing statistics is output as form.
7. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described early warning personnel depaly is that configuration needs to send the personnel that short message warning is reminded;
Described note reminds the advanced or delayed work sky being to go out according to target advance and actual progress comparing calculation, formulates early warning etc. Level, exceedes definition grade and is automatically sent short messages to related personnel, carry out progress warning.
8. a kind of railroad bridge construction project time management method based on 3dgis and engineering threedimensional model it is characterised in that: using power Profit requires carrying out based on the railroad bridge construction project time management system of 3dgis and engineering threedimensional model any one of 1-7 Bridge construction progress control, described management method includes: three-dimensional scenic is set up;Bridge work point model decomposes and imports;Actual enter The collection of degrees of data;Target advance data loading;Three-dimensional image progress shows;Generate progress report and carry out progress early warning.
9. railroad bridge construction project time management method as claimed in claim 8 it is characterised in that: described three-dimensional scenic sets up bag Include to process the digital image data in rail track region and generate orthography, digital elevation data processing is generated digital elevation Then described orthography is superimposed with digital elevation model and renders generation virtual three-dimensional scene by model.
10. railroad bridge construction project time management method as claimed in claim 8 it is characterised in that: described bridge work point model Decompose and comprise the following steps with importing:
1) adopt parametric modeling mode, automatically extract work point design parameter from two-dimensional design in figure;
2) bridge work point model is decomposed, be classified as pile foundation, cushion cap, pier shaft, beam section and beam block;
3) interface that 3ds max provides is utilized to generate threedimensional model;
4) make the three-dimensional of bridge work point part and import table, including definition component numbering, calculate its geographical coordinate and attitude parameter;
5) according to the geographical coordinate in described three-dimensional importing table and attitude parameter, work point model importing 3dgis platform is shown And management.
11. railroad bridge construction project time management methods as claimed in claim 10 are it is characterised in that described actual progress data Collection comprise the following steps:
1) work extracted point design parameter is stored in underlying parameter data base;
2) obtain work point design parameter from data base, generate pile foundation, cushion cap, pier shaft, beam section, the 2 d plane picture of beam block, profit With openlayers provide assembly and interface realize work point vector figure Fast Drawing, render, Pan and Zoom;
3) vector element is clicked on from two-dimensional vector figure to carry out progress and make a report on, described pile foundation, cushion cap, beam section, the progress of beam block are used Complete and do not complete two states to represent, pier shaft progress actually accomplishes highly to represent by input, submits to after the completion of making a report on Auditor;
4) auditor audits to the progress data made a report on, and underproof data is marked, returns modification, if entirely Portion qualified then by data inputting actual progress data base.
12. railroad bridge construction project time management methods as claimed in claim 11 are it is characterised in that described target advance data Warehouse-in is by the target advance input database of work point, specially applies group using the method formulation work point of gunter drawing and plans and record Enter data base.
13. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described three-dimensional image progress Display, is the actual progress data using described input database and target advance data, is calculated according to progress data and changes The color of each component of described bridge work point model, realizes bridge construction three-dimensional image progress and shows.
14. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described generation progress report Table, be described actual progress data and target advance data are carried out count, relative analyses, extract work point day, week, month, year, open Tired branch, subdivisional work data, generate progress report.
15. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described to carry out progress pre- Alert, it is that described actual progress data and target advance data are analyzed, calculates the advanced or delayed duration, formulate pre- Alert grade, to exceeding definition grade, automatically sends short messages to related personnel, carries out progress warning.
CN201610788265.1A 2016-08-31 2016-08-31 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model Pending CN106339490A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610788265.1A CN106339490A (en) 2016-08-31 2016-08-31 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610788265.1A CN106339490A (en) 2016-08-31 2016-08-31 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

Publications (1)

Publication Number Publication Date
CN106339490A true CN106339490A (en) 2017-01-18

Family

ID=57822369

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610788265.1A Pending CN106339490A (en) 2016-08-31 2016-08-31 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

Country Status (1)

Country Link
CN (1) CN106339490A (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam course management system and railway beam a management method based on BIM technology
CN107133787A (en) * 2017-06-26 2017-09-05 山东奥联信息科技有限公司 Highway project management method and system
CN107590597A (en) * 2017-09-08 2018-01-16 太仓贝岭思拓软件科技有限公司 A kind of architectural engineering progress becomes more meticulous and various dimensions management method
CN107705100A (en) * 2017-11-02 2018-02-16 港珠澳大桥管理局 A kind of management system of Traffic Engineering Construction progress
CN107797824A (en) * 2017-11-08 2018-03-13 北京恒华伟业科技股份有限公司 A kind of project progress methods of exhibiting and device
CN109359125A (en) * 2018-08-27 2019-02-19 中铁建工集团有限公司 A kind of progress fine-grained management method and its system for construction project
CN109523182A (en) * 2018-11-27 2019-03-26 华规软件(上海)有限公司 A kind of beam field production management method, platform, computer equipment and storage medium
CN109558412A (en) * 2018-09-20 2019-04-02 中建科技有限公司深圳分公司 The data growing method and device of assembled architecture construct platform
CN109583852A (en) * 2018-12-29 2019-04-05 中铁局集团有限公司第三工程分公司 A kind of goods and materials for bridge cantilever pouring construction and progress msg management system
CN109903008A (en) * 2019-01-25 2019-06-18 国电南瑞科技股份有限公司 A kind of subway work construction project progress visualization managing and control system and management-control method
CN109949001A (en) * 2019-02-22 2019-06-28 上海市建设工程监理咨询有限公司 A kind of Project Supervision organization management system
CN110070284A (en) * 2019-04-17 2019-07-30 江苏开通建设工程有限公司 A kind of wisdom beam course management system based on BIM technology
CN110163509A (en) * 2019-05-23 2019-08-23 重庆渝高科技产业(集团)股份有限公司 A kind of big data platform project management system based on architectural engineering
CN110443480A (en) * 2019-07-26 2019-11-12 中铁四局集团第一工程有限公司 A kind of construction speed monitoring and early warning method and system
CN110766790A (en) * 2019-10-21 2020-02-07 中国铁路设计集团有限公司 Parameter-driven self-adaptive multi-level three-dimensional visualization method for high-speed railway bridge
CN111021265A (en) * 2020-01-16 2020-04-17 中铁十九局集团第一工程有限公司 BIM technology-based railway large-span continuous beam swivel construction control method
CN111160852A (en) * 2019-12-16 2020-05-15 温州电力建设有限公司 Intelligent engineering data writing system and method based on big data
CN111611204A (en) * 2020-04-30 2020-09-01 中国舰船研究设计中心 Distributed task progress data acquisition and analysis method
CN112365222A (en) * 2020-10-21 2021-02-12 中交第二航务工程局有限公司 Intelligent construction informatization system for cast-in-situ bored pile
CN112818455A (en) * 2021-02-22 2021-05-18 深圳市市政设计研究院有限公司 Bridge structure response monitoring method and system
CN113012288A (en) * 2021-04-02 2021-06-22 长江空间信息技术工程有限公司(武汉) Three-dimensional dynamic visualization method for long-distance engineering construction progress
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN113988820A (en) * 2021-11-23 2022-01-28 中国铁路通信信号上海工程局集团有限公司 Engineering project scheduling management system
WO2022040919A1 (en) * 2020-08-25 2022-03-03 南京翱翔信息物理融合创新研究院有限公司 Internet-based method for displaying three-dimensional road bridge progress
CN115798137A (en) * 2022-08-02 2023-03-14 中建铁路投资建设集团有限公司 Three-dimensional visual big data monitoring and early warning system based on Internet of things
CN116205411A (en) * 2023-04-27 2023-06-02 山东铁路投资控股集团有限公司 Material consumption checking method, device, equipment and medium based on big data

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101418542A (en) * 2008-11-21 2009-04-29 上海市政工程设计研究总院 Cable system construction method of spatial self-anchored rope-suspension bridge
CN101476291A (en) * 2009-01-21 2009-07-08 中铁一局集团有限公司 Segment-assembling simply supported box girder movable falsework construction method
DE102013005891A1 (en) * 2013-03-11 2014-09-11 Universität Kassel Generative method for producing a component having at least one cavity, in particular by 3D printing technology with a sand and a binder
CN105652830A (en) * 2015-12-25 2016-06-08 中国铁道科学研究院铁道建筑研究所 Bridge monitoring system based on BIM

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101418542A (en) * 2008-11-21 2009-04-29 上海市政工程设计研究总院 Cable system construction method of spatial self-anchored rope-suspension bridge
CN101476291A (en) * 2009-01-21 2009-07-08 中铁一局集团有限公司 Segment-assembling simply supported box girder movable falsework construction method
DE102013005891A1 (en) * 2013-03-11 2014-09-11 Universität Kassel Generative method for producing a component having at least one cavity, in particular by 3D printing technology with a sand and a binder
CN105652830A (en) * 2015-12-25 2016-06-08 中国铁道科学研究院铁道建筑研究所 Bridge monitoring system based on BIM

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
唐文波: "基于4D信息模型的大型桥梁施工进度仿真研究", 《中南大学》 *
王华 等: "高速铁路桥梁三维施工进度管理系统研发", 《铁路计算机应用》 *

Cited By (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam course management system and railway beam a management method based on BIM technology
CN107133787A (en) * 2017-06-26 2017-09-05 山东奥联信息科技有限公司 Highway project management method and system
CN107133787B (en) * 2017-06-26 2023-10-27 山东奥联信息科技有限公司 Highway engineering management method and system
CN107590597A (en) * 2017-09-08 2018-01-16 太仓贝岭思拓软件科技有限公司 A kind of architectural engineering progress becomes more meticulous and various dimensions management method
CN107705100A (en) * 2017-11-02 2018-02-16 港珠澳大桥管理局 A kind of management system of Traffic Engineering Construction progress
CN107705100B (en) * 2017-11-02 2022-04-26 港珠澳大桥管理局 Management system for traffic engineering construction progress
CN107797824A (en) * 2017-11-08 2018-03-13 北京恒华伟业科技股份有限公司 A kind of project progress methods of exhibiting and device
CN109359125A (en) * 2018-08-27 2019-02-19 中铁建工集团有限公司 A kind of progress fine-grained management method and its system for construction project
CN109558412A (en) * 2018-09-20 2019-04-02 中建科技有限公司深圳分公司 The data growing method and device of assembled architecture construct platform
CN109523182A (en) * 2018-11-27 2019-03-26 华规软件(上海)有限公司 A kind of beam field production management method, platform, computer equipment and storage medium
CN109583852A (en) * 2018-12-29 2019-04-05 中铁局集团有限公司第三工程分公司 A kind of goods and materials for bridge cantilever pouring construction and progress msg management system
CN109903008A (en) * 2019-01-25 2019-06-18 国电南瑞科技股份有限公司 A kind of subway work construction project progress visualization managing and control system and management-control method
CN109903008B (en) * 2019-01-25 2022-09-09 国电南瑞科技股份有限公司 Visual management and control system and method for subway construction project progress
CN109949001A (en) * 2019-02-22 2019-06-28 上海市建设工程监理咨询有限公司 A kind of Project Supervision organization management system
CN110070284A (en) * 2019-04-17 2019-07-30 江苏开通建设工程有限公司 A kind of wisdom beam course management system based on BIM technology
CN110163509A (en) * 2019-05-23 2019-08-23 重庆渝高科技产业(集团)股份有限公司 A kind of big data platform project management system based on architectural engineering
CN110443480A (en) * 2019-07-26 2019-11-12 中铁四局集团第一工程有限公司 A kind of construction speed monitoring and early warning method and system
CN110443480B (en) * 2019-07-26 2023-10-27 中铁四局集团第一工程有限公司 Construction progress monitoring and early warning method and system
CN110766790A (en) * 2019-10-21 2020-02-07 中国铁路设计集团有限公司 Parameter-driven self-adaptive multi-level three-dimensional visualization method for high-speed railway bridge
CN110766790B (en) * 2019-10-21 2023-06-23 中国铁路设计集团有限公司 Parameter-driven high-speed railway bridge self-adaptive multi-level three-dimensional visualization method
CN111160852A (en) * 2019-12-16 2020-05-15 温州电力建设有限公司 Intelligent engineering data writing system and method based on big data
CN111021265A (en) * 2020-01-16 2020-04-17 中铁十九局集团第一工程有限公司 BIM technology-based railway large-span continuous beam swivel construction control method
CN111611204A (en) * 2020-04-30 2020-09-01 中国舰船研究设计中心 Distributed task progress data acquisition and analysis method
CN111611204B (en) * 2020-04-30 2024-03-01 中国舰船研究设计中心 Distributed task progress data acquisition and analysis method
WO2022040919A1 (en) * 2020-08-25 2022-03-03 南京翱翔信息物理融合创新研究院有限公司 Internet-based method for displaying three-dimensional road bridge progress
CN112365222A (en) * 2020-10-21 2021-02-12 中交第二航务工程局有限公司 Intelligent construction informatization system for cast-in-situ bored pile
CN112818455A (en) * 2021-02-22 2021-05-18 深圳市市政设计研究院有限公司 Bridge structure response monitoring method and system
CN113012288B (en) * 2021-04-02 2022-04-22 长江空间信息技术工程有限公司(武汉) Three-dimensional dynamic visualization method for long-distance engineering construction progress
CN113012288A (en) * 2021-04-02 2021-06-22 长江空间信息技术工程有限公司(武汉) Three-dimensional dynamic visualization method for long-distance engineering construction progress
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN113988820A (en) * 2021-11-23 2022-01-28 中国铁路通信信号上海工程局集团有限公司 Engineering project scheduling management system
CN115798137A (en) * 2022-08-02 2023-03-14 中建铁路投资建设集团有限公司 Three-dimensional visual big data monitoring and early warning system based on Internet of things
CN115798137B (en) * 2022-08-02 2023-12-22 中建铁路投资建设集团有限公司 Three-dimensional visual big data monitoring and early warning system based on Internet of things
CN116205411A (en) * 2023-04-27 2023-06-02 山东铁路投资控股集团有限公司 Material consumption checking method, device, equipment and medium based on big data

Similar Documents

Publication Publication Date Title
CN106339490A (en) System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106384191A (en) Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN106384190A (en) Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model
LU501999A1 (en) Pumped storage power station comprehensive management method, platform and system, device and medium
CN111369158A (en) BIM-based informatization quality management method and system
CN111967077A (en) Engineering construction management digital platform based on BIM technology
WO2011072467A1 (en) Method and system for monitoring of wetlands resource and ecological environment
CN109671150B (en) Airport earthwork calculation method based on digital earth
Liapi 4D visualization of highway construction projects
CN104217384A (en) A nuclear accident emergency processing and auxiliary decision support system
CN111782712A (en) Natural resource asset audit comprehensive space analysis system and method
Pietsch GIS in landscape planning
CN111401726A (en) Building design method, device, system and storage medium
CN105354882A (en) Method for constructing big data architecture based three-dimensional panoramic display platform for large-spatial-range electricity transmission
Huang et al. The city management based on smart information system using digital technologies in China
CN114781827A (en) Environment sample investigation cloud management method based on geographic spatial information
CN117371233A (en) Reservoir flood control system based on UE technique
Shaw et al. High resolution LiDAR specifically for archaeology: Are we fully exploiting this valuable resource
Tiwari et al. 3D city model enabled e-governance for sustainable urbanization
Kevany GIS in the World Trade Center response: 10 years after
Duque et al. Building a digital twin of the Italian coasts
Galmarini et al. Real-time monitoring data for real-time multi-model validation: coupling ENSEMBLE and EURDEP
Li et al. Application of three-dimensional GIS to water resources
Zhang et al. Research on GIM-based 3D Digital Construction Management Scheme for Power Grid Engineering
Gorreja et al. 3D GIS for a Smart Management System Applied to Historical Villages Damaged by Earthquake

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination