CN110070284A - A kind of wisdom beam course management system based on BIM technology - Google Patents

A kind of wisdom beam course management system based on BIM technology Download PDF

Info

Publication number
CN110070284A
CN110070284A CN201910310334.1A CN201910310334A CN110070284A CN 110070284 A CN110070284 A CN 110070284A CN 201910310334 A CN201910310334 A CN 201910310334A CN 110070284 A CN110070284 A CN 110070284A
Authority
CN
China
Prior art keywords
module
production
server
wisdom
client
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910310334.1A
Other languages
Chinese (zh)
Inventor
董立功
魏星
覃先宁
徐宗泽
陈振
张恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Opening Construction Engineering Co Ltd
Original Assignee
Jiangsu Opening Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Opening Construction Engineering Co Ltd filed Critical Jiangsu Opening Construction Engineering Co Ltd
Priority to CN201910310334.1A priority Critical patent/CN110070284A/en
Publication of CN110070284A publication Critical patent/CN110070284A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/067Enterprise or organisation modelling

Abstract

The present invention relates to a kind of wisdom beam course management system based on BIM technology, it is related to the technical field of Liang Chang management, it solves and conveys the source of information unknown and transmission efficiency is low, inaccurate, when something goes wrong, the problem of not clear responsible person concerned comprising: server, three-dimensional modeling data storehouse, BIM3D application module, video monitoring module, Master Direction Center client, production management module, progress control module and divide command centre's client;BIM3D application module updates the whole visualization sand table model according to construction task information, construction task progress msg.What the present invention had a beam field production plan issues and uploads accurate, in time, the normal operation of forward beam field, improve management level and the efficiency of management, big, the inaccurate drawback of information transmission error in very good solution construction production process.

Description

A kind of wisdom beam course management system based on BIM technology
Technical field
The present invention relates to the technical fields of Liang Chang management, manage more particularly, to a kind of wisdom Liang Chang based on BIM technology System.
Background technique
Precast beam is to use prefabrication, then be transported to construction site and carry out the fixed beam of installation by design requirement position, is Staple product during bridge construction.Workplace of the Liang Chang as precast beam, the supervision and oversight of production process are pre- The important leverage of beam quality and duration processed.
It is existing that production management is carried out mainly by the extensive mode of traditional people pipe people to precast beam field, pass through electricity The modes such as words, oral carry out exchanging the normality having become in entire construction and production management.
Prior art among the above has the following deficiencies: that the source of reception and registration information is unknown and transmission efficiency is low, inaccurate Really, when something goes wrong, not clear responsible person concerned.
Summary of the invention
The object of the present invention is to provide a kind of wisdom beam course management system based on BIM technology, under the production plan of beam field Hair and accurate, in time, the normal operation of forward beam field is uploaded, improve management level and the efficiency of management, very good solution is applied Big, the inaccurate drawback of information transmission error in work production process, greatly improves the accuracy rate and efficiency of information transmitting, adds Fast construction speed.
Foregoing invention purpose of the invention has the technical scheme that
A kind of wisdom beam course management system based on BIM technology, comprising:
Server, for carrying out data storage and data processing;
Three-dimensional modeling data storehouse connect with server and is stored with precast beam threedimensional model and beam field threedimensional model;
BIM3D application module is connect and for being appointed according to beam field threedimensional model, precast beam threedimensional model and construction with server Information of being engaged in generates whole visualization sand table model, and sends whole visualization sand table model to Master Direction Center client;
Video monitoring module is corresponded with workbench to track the production video of acquisition precast beam and will production video and corresponding Timestamp and workbench number are stored to server;
Master Direction Center client is connect and for receiving, showing whole visualization sand table model with server;
Production management module connect with Master Direction Center client and visualizes sand table model according to whole for project manager Publication construction task information is to BIM3D application module and divides command centre's client and by construction task information and correspondent time It stores to server;
Progress control module connect with Master Direction Center client and inputs construction task actual progress letter for project manager It ceases and construction task actual progress information is sent to BIM3D application module;
Divide command centre's client, is connect with server and quantity is at least one and is used to receive and show that construction task to be believed Breath;
The BIM3D application module updates the whole visualization sand table according to construction task information, construction task progress msg Model.
By using above-mentioned technical proposal, the information transmitting of Liang Chang is accurate, timely, high-efficient, and work distribution is scientific and reasonable, It is explicit that everyone has responsibility, and person liable can be directly found by going wrong, and reduces shifting responsibility onto others for responsibility, improves construction efficiency and money Source utilization rate.
The present invention is further arranged to: further including and the Master Direction Center client and described point of command centre client The voice call module that end is all connected with and is linked up for project manager and producers;
Described point of command centre's client and workbench correspond.
By using above-mentioned technical proposal, facilitate producers understand the blunt production task for understanding oneself content and In the period, reception and registration is accurate, clear, timely, improves the efficiency of information reception and registration;Facilitate project manager straight with producers simultaneously Capable communication is tapped into, is had some setbacks with solving the problems, such as to link up, improves the efficiency of communication.
The present invention is further arranged to: further including and the Master Direction Center client and described point of command centre's client It connects and for carrying out recording and numbering recording with corresponding timestamp and corresponding workbench to store to clothes to voice communication The recording module of business device.
By using above-mentioned technical proposal, the voice communication of project manager and producers are recorded and stored To server, the determining person liable of evidence obtaining is had access to facilitate the later period to go wrong, reduces and shifts responsibility onto others, improve work efficiency.
The present invention is further arranged to: further include:
Login module connect with Master Direction Center client and inputs log-on message for project manager;
Authentication module is connect and for showing validation problem and inputting answering for validation problem for project manager with login module Case;
The also default validation database for being stored with validation problem with corresponding Validation Answer Key in the authentication module;
If validation problem is consistent with the data in validation database with Validation Answer Key, allow to login access;Conversely, not allowing then Login access.
By using above-mentioned technical proposal, the safety in Master Direction Center client use process is improved, is reduced non- Project manager intervenes the appearance transmitted an order, it is ensured that the accuracy of pass down the line.
The present invention is further arranged to: the progress control module further include:
Schedule forecasting unit, whether the number of days prediction production plan started according to current production performance and production can be punctual Complete production;
Progress reminding unit, for reminding producers that can not complete on time with project manager's production plan;
Definition: current production performance is l, and the number of days for producing beginning is t, and the total amount of production plan is L, and plan number of days is T;
If l/t < L/T, progress reminding unit sends prompting message to corresponding producers and project manager;If l/t >=L/T, then progress reminding unit does not start.
By using above-mentioned technical proposal, manufacturing schedule is monitored in real time and is analyzed, when production can not be completed according to schedule When, remind project manager and producers to be adjusted plan, to ensure the smooth punctual completion of production task.
The present invention is further arranged to: the progress control mould further includes for judging production task urgency level and exporting The urgent judging unit of urgency level signal;
Pre-programmed emergency degree distinguishing value is a, b, 0 < a < b;
If (L-l)/(T-t)≤a, urgent judging unit starting sends three-level urgency signal to BIM3D application module, server The prefabricated beam model of correspondence of the whole visualization sand table model of control is in green;
If a < (L-l)/(T-t) < b, urgent judging unit starting send second level urgency signal to BIM3D application module, clothes The whole prefabricated beam model of correspondence for visualizing sand table model of device control be engaged in yellow;
If (L-l)/(T-t) >=b, urgent judging unit starting sends level-one urgency signal to BIM3D application module, server The prefabricated beam model of correspondence of the whole visualization sand table model of control takes on a red color.
By using above-mentioned technical proposal, the urgency level of production task is determined, facilitates project manager point Priority carries out processing adjustment, improves the working efficiency of project manager, and production task is made to assign more reasonable, can Ensure going on smoothly for production task.
The present invention is further arranged to: the progress control module further include:
Weather data library is networked to obtain following N days weather conditions, and the production correction value for presetting non-rain and snow weather is 1, sleet The production amendment empirical value of weather is x, and 0 < x < 1, the i.e. average productive capacity of rain and snow weather are l/t*x;
Plan rescheduling unit connect with weather data library and is obtained according to following N days weather conditions and schedule forecasting unit It analyzes comparing result and dynamic regulation is carried out to precast beam production plan.
By using above-mentioned technical proposal, existing plan is adjusted according to following N days weather conditions, makes to produce Task is assigned more reasonable, it can be ensured that production task is gone on smoothly.
The present invention is further arranged to: the progress reminding unit is Short message alarm.
By using above-mentioned technical proposal, producers and project manager are mentioned by way of sending short message It wakes up, reduces corresponding cost.
The present invention is further arranged to: further include RFID module, the RFID module include be embedded inside precast beam and For emitting the response unit of precast beam working procedure information and for receiving precast beam working procedure information and reading for user Read unit.
By using above-mentioned technical proposal, the working procedure information of precast beam is integrated in response unit, user can pass through Read unit receives and obtains the working procedure information of precast beam, and user is facilitated to understand the next step of precast beam.
The present invention is further arranged to: being provided with unique identification two dimensional code on default precast beam, two dimensional code is integrated with pre- Beam quality inspection information processed;
It further include the scan module for scanning the two-dimensional code to obtain precast beam quality inspection information.
By using above-mentioned technical proposal, user is facilitated to understand the quality inspection information of precast beam, it is simple and practical.
In conclusion advantageous effects of the invention are as follows:
Issuing and uploading for beam field production plan is accurate, timely, and the normal operation of forward beam field improves management level and management Efficiency, information transmission error is big in very good solution construction production process, drawback of inaccuracy, greatly improves information biography The accuracy rate and efficiency passed, accelerate construction speed.
Detailed description of the invention
Fig. 1 is a kind of system block diagram of wisdom beam course management system based on BIM technology of the invention.
Fig. 2 is a kind of production management flow chart of wisdom beam course management system based on BIM technology.
Fig. 3 is a kind of progress control flow chart of wisdom beam course management system based on BIM technology.
Fig. 4 is a point system block diagram for command centre's client.
Fig. 5 is the system block diagram of Master Direction Center client.
Fig. 6 is the system block diagram of progress control module.
Fig. 7 is the flow chart of RFID module.
Fig. 8 is a kind of flow chart of the scan module of wisdom beam course management system based on BIM technology.
In figure, 1, server;2, three-dimensional modeling data storehouse;3, BIM3D application module;4, Master Direction Center client;5, Video monitoring module;6, production management module;7, progress control module;8, divide command centre's client;41, voice communication mould Block;42, recording module;43, login module;44, authentication module;71, schedule forecasting unit;72, progress reminding unit;73, tight Anxious judging unit;74, weather data library;75, Plan rescheduling unit;8, RFID module;81, response unit;82, read unit; 9, scan module.
Specific embodiment
Below in conjunction with attached drawing 1-8, invention is further described in detail.
It referring to Fig.1, is a kind of wisdom beam course management system based on BIM technology disclosed by the invention, including server 1, Three-dimensional modeling data storehouse 2, BIM3D application module 3, video monitoring module 5, progress control module 7, production management module 6, main finger Wave center customer end 4 and point command centre's client 8.
Server 1 is for carrying out data storage and data processing;Three-dimensional modeling data storehouse 2 connect and stores with server 1 There are precast beam threedimensional model and beam field threedimensional model;BIM3D application module 3 connect with server 1 and for according to beam field three-dimensional Model, precast beam threedimensional model and construction task information generate whole visualization sand table model, and it is husky to send whole visualization Disk model to Master Direction Center client 4, entirety visualizes target advance, the actual progress of sand table model real-time display precast beam Etc. various data.
Video monitoring module 5 and workbench correspond, and each workbench has the number of oneself, video monitoring module 5 It stores for tracking the production video of acquisition precast beam, and by production video and correspondent time and workbench number to service Device 1, to facilitate the later period to carry out transferring use;Video monitoring module 5 covers live entrance, construction area, processing district, office comprehensively Area and beam body construction area, video monitoring module 5 carry out the inspection of building site routine, emergency management and rescue, hidden danger in combination with mobile individual soldier's equipment Investigation, the project acceptance inspection or organizes expert carry out remote guide.
Referring to Fig.1,2, Master Direction Center client 4 connect with server 1 and for receiving, showing whole visualization sand table Model, Master Direction Center client 4 can also show production video so that live project manager analyzes, decision and prison Pipe;Production management module 6 is connect with Master Direction Center client 4, and production management module 6 can according to entirety for project manager Target advance depending on changing sand table model issues construction task information to BIM3D modeler model and divides command centre's client 8, and will Construction task information and correspondent time are stored to server 1;Production management module 6 executes the information initiated to construction task, Beam number, working procedure, detail design amount and Construction Attention Points are specifically included, and are articulated in reference numeral for information is completed On the BIM model of box beam.
Referring to Fig.1,3, progress control module 7 is connect with Master Direction Center client 4, and progress control module 7 is for project pipe Reason personnel input construction task actual progress information, and construction task progress msg is sent to BIM3D application module 3, BIM3D Application module 3 updates whole visualization sand table model according to construction task information, construction task progress msg;Progress control module Actual progress information can also be compared with target advance and matched by 7, be reached to actual progress tracking, control and adjustment in real time Purpose.
Command centre's client 8 is divided to connect with server 1, dividing the quantity of command centre's client 8 is at least one, point finger Center customer end 8 is waved for receiving and showing construction task information has to facilitate producers to understand the production task of oneself Body component model, beam number, working procedure, detail design amount and Construction Attention Points.
Master Direction Center client 4 and divide command centre's client 8 include but is not limited to smart phone, tablet computer, pen Remember the clients such as this computer and electronics large-size screen monitors.
Referring to Fig. 4,5, the efficiency of communication is further contemplated, the quantity and workbench for dividing command centre's client 8 are one by one It is corresponding, to facilitate the producers of corresponding workbench that can get information about the production task of oneself;Server 1 is also connected with language Sound call module 41, voice call module 41 is all connected with Master Direction Center client 4 and point command centre's client 8, with side Just producers are directly docked with project manager, improve the efficiency of information reception and registration.
Referring to Fig. 4,5, clearly defining responsibilities people is further contemplated, server 1 is also connected with recording module 42, recording module 42 It is connect with Master Direction Center client 4 and point command centre's client 8, recording module 42 is for recording voice communication Sound, and recording is stored with corresponding timestamp and corresponding workbench number to server 1, to facilitate the later period to transfer using true Fix duty is let people.
The accuracy that Master Direction Center client 4 is issued an order is further contemplated, server 1 is also connected with login module 43 and authentication module 44;Login module 43 is connect with Master Direction Center client 4, and login module 43 is inputted for project manager Log-on message, authentication module 44 are used to show validation problem and input the answer of validation problem for project manager;Verify mould The also default validation database for being stored with validation problem with corresponding Validation Answer Key in block 44, if validation problem and Validation Answer Key with test The data demonstrate,proved in database are consistent, then allow to login access;Conversely, not allowing then to login access.
Referring to Fig.1,6, smoothly completing for production task is further contemplated, progress control module 7 further includes schedule forecasting Unit 71 and progress reminding unit 72;Schedule forecasting unit 71 is predicted according to the number of days that current production performance and production start Whether production plan can be completed on time produces;Progress reminding unit 72 is for reminding producers and project manager to produce Plan can not be completed on time.
Definition: current production performance is l, and the number of days for producing beginning is t, and the total amount of production plan is L, plans number of days For T.
If l/t < L/T, progress reminding unit 72 sends prompting message to producers and project manager;If l/t >=L/T, then progress reminding unit 72 does not start;Progress reminding unit 72 is preferably Short message alarm herein.
The urgency level of production task is further contemplated, progress control mould further includes for judging the urgent journey of production task Spend and export the urgent judging unit 73 of urgency level signal;Pre-programmed emergency degree distinguishing value is a, b, 0 < a < b;
If (L-l)/(T-t)≤a, the urgent starting of judging unit 73 sends three-level urgency signal to BIM3D application module 3, clothes Business device 1 controls the prefabricated beam model of correspondence of whole visualization sand table model in green;
If a < (L-l)/(T-t) < b, the urgent starting of judging unit 73 transmission second level urgency signal to BIM3D application module 3, Server 1 controls the prefabricated beam model of correspondence of whole visualization sand table model in yellow;
If (L-l)/(T-t) >=b, the urgent starting of judging unit 73 sends level-one urgency signal to BIM3D application module 3, clothes The prefabricated beam model of correspondence that business device 1 controls whole visualization sand table model takes on a red color;Specific color and urgency level can bases The own situation of user is set.
Referring to Fig.1,6, influence of the weather conditions to production is further contemplated, progress control module 7 further includes a day destiny According to library 74 and Plan rescheduling unit 75;Weather data library 74 is networked to obtain following N days weather conditions, and non-rain and snow weather is preset Production correction value be 1, the production of rain and snow weather amendment empirical value is x, 0 < x < 1, i.e. the average productive capacity of rain and snow weather is l/t*x;The analysis that Plan rescheduling unit 75 is used to be obtained according to following N days weather conditions and schedule forecasting unit 71 compares knot Fruit carries out dynamic regulation to precast beam production plan.
Referring to Fig.1,7, it further include RFID module, RFID module includes response unit and read unit, and response unit is embedded Inside precast beam and for emitting precast beam working procedure information, precast beam working procedure information includes into beam, factory, peace Dress;Read unit is for receiving precast beam working procedure information and reading for user.
Referring to Fig.1,8, it presets and is provided with unique identification two dimensional code on precast beam, two dimensional code is integrated with the matter of the precast beam Checking information to be measured, further includes scan module 9, scan module 9 is used to scan the two-dimensional code to obtain the quality inspection information of precast beam, User is facilitated to understand the quality inspection information of precast beam, user can be personnel outside factory and be also possible to personnel in field herein.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (10)

1. a kind of wisdom beam course management system based on BIM technology, it is characterised in that: include:
Server (1), for carrying out data storage and data processing;
Three-dimensional modeling data storehouse (2) connect with server (1) and is stored with precast beam threedimensional model and beam field threedimensional model;
BIM3D application module (3), connect with server (1) and for according to beam field threedimensional model, precast beam threedimensional model and Construction task information generates whole visualization sand table model, and sends whole visualization sand table model to Master Direction Center client (4);
Video monitoring module (5), with workbench correspond with track acquisition precast beam production video and will production video with Correspondent time and workbench number are stored to server (1);
Master Direction Center client (4) is connect and for receiving, showing whole visualization sand table model with server (1);
Production management module (6) is connect and husky according to whole visualization for project manager with Master Direction Center client (4) Disk model issues construction task information to BIM3D application module (3) and divides command centre's client (8) and by construction task information It stores with correspondent time to server (1);
Progress control module (7) connect with Master Direction Center client (4) and inputs construction task reality for project manager Construction task actual progress information is simultaneously sent to BIM3D application module (3) by progress msg;
Divide command centre's client (8), is connect with server (1) and quantity is at least one and appoints for receiving and showing to construct Business information;
The BIM3D application module (3) is whole visual according to construction task information, construction task actual progress information update Change sand table model.
2. a kind of wisdom beam course management system based on BIM technology according to claim 1, it is characterised in that: further include It connect and with the Master Direction Center client (4) and described point of command centre's client (8) for project manager and life The voice call module (41) that production personnel are linked up;
Described point of command centre's client (8) and workbench correspond.
3. a kind of wisdom beam course management system based on BIM technology according to claim 2, it is characterised in that: further include Be all connected with the Master Direction Center client (4) and described point of command centre's client (8) and for voice communication into Row recording simultaneously stores recording to the recording module of server (1) (42) with corresponding timestamp and corresponding workbench number.
4. a kind of wisdom beam course management system based on BIM technology according to claim 1, it is characterised in that: further include:
Login module (43) connect with Master Direction Center client (4) and inputs log-on message for project manager;
Authentication module (44) connect with login module (43) and verifies for showing validation problem and inputting for project manager The answer of problem;
The also default validation database for being stored with validation problem with corresponding Validation Answer Key in the authentication module (44);
If validation problem is consistent with the data in validation database with Validation Answer Key, allow to login access;Conversely, not allowing then Login access.
5. a kind of wisdom beam course management system based on BIM technology according to claim 1, it is characterised in that: it is described into It spends management module (7) further include:
Whether schedule forecasting unit (71), the number of days prediction production plan started according to current production performance and production can It is punctual to complete production;
Progress reminding unit (72), for reminding producers that can not complete on time with project manager's production plan;
Definition: current production performance is l, and the number of days for producing beginning is t, and the total amount of production plan is L, and plan number of days is T;
If l/t < L/T, progress reminding unit (72) sends prompting message to corresponding producers and project manager; If l/t >=L/T, progress reminding unit (72) does not start.
6. a kind of wisdom beam course management system based on BIM technology according to claim 5, it is characterised in that: it is described into Degree management mould further includes for judging production task urgency level and exporting the urgent judging unit (73) of urgency level signal;
Pre-programmed emergency degree distinguishing value is a, b, 0 < a < b;
If (L-l)/(T-t)≤a, urgent judging unit (73) starting sends three-level urgency signal to BIM3D application module (3), the prefabricated beam model of correspondence of the whole visualization sand table model of server (1) control is in green;
If a < (L-l)/(T-t) < b, urgent judging unit (73) starting send second level urgency signal to BIM3D application module (3), the prefabricated beam model of correspondence of the whole visualization sand table model of server (1) control is in yellow;
If (L-l)/(T-t) >=b, urgent judging unit (73) starting sends level-one urgency signal to BIM3D application module (3), the prefabricated beam model of correspondence of the whole visualization sand table model of server (1) control takes on a red color.
7. a kind of wisdom beam course management system based on BIM technology according to claim 5, it is characterised in that: it is described into It spends management module (7) further include:
Weather data library (74) is networked to obtain following N days weather conditions, and the production correction value for presetting non-rain and snow weather is 1, The production amendment empirical value of rain and snow weather is x, and 0 < x < 1, the i.e. average productive capacity of rain and snow weather are l/t*x;
Plan rescheduling unit (75) is connect and according to following N days weather conditions and schedule forecasting list with weather data library (74) The analysis comparing result that first (71) obtain carries out dynamic regulation to precast beam production plan.
8. a kind of wisdom beam course management system based on BIM technology according to claim 5, it is characterised in that: it is described into Spending reminding unit (72) is Short message alarm.
9. a kind of wisdom beam course management system based on BIM technology according to claim 1, it is characterised in that: further include RFID module (8), the RFID module (8) include being embedded inside precast beam and for emitting precast beam working procedure information Response unit (81) and for receive precast beam working procedure information and for user reading read unit (82).
10. a kind of wisdom beam course management system based on BIM technology according to claim 1, it is characterised in that: default pre- Unique identification two dimensional code is provided on beam processed, two dimensional code is integrated with precast beam quality inspection information;
It further include the scan module (9) for scanning the two-dimensional code to obtain precast beam quality inspection information.
CN201910310334.1A 2019-04-17 2019-04-17 A kind of wisdom beam course management system based on BIM technology Pending CN110070284A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910310334.1A CN110070284A (en) 2019-04-17 2019-04-17 A kind of wisdom beam course management system based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910310334.1A CN110070284A (en) 2019-04-17 2019-04-17 A kind of wisdom beam course management system based on BIM technology

Publications (1)

Publication Number Publication Date
CN110070284A true CN110070284A (en) 2019-07-30

Family

ID=67367876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910310334.1A Pending CN110070284A (en) 2019-04-17 2019-04-17 A kind of wisdom beam course management system based on BIM technology

Country Status (1)

Country Link
CN (1) CN110070284A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110658790A (en) * 2019-09-17 2020-01-07 广州市微柏软件股份有限公司 Precast beam production management system based on three-dimensional visual process management
CN112101760A (en) * 2020-09-04 2020-12-18 中铁大桥局集团有限公司 Beam yard production state visualization method and system based on GIS
CN112948950A (en) * 2021-04-07 2021-06-11 中铁广州工程局集团有限公司 Integrated information intelligent management system and management method based on BIM technology
CN113793117A (en) * 2021-08-27 2021-12-14 广东腾越建筑工程有限公司 BIM-based remote supervision method for building construction
CN114387881A (en) * 2021-12-30 2022-04-22 华能国际电力股份有限公司上海石洞口第一电厂 Engineering progress management method, device, equipment and medium
CN116011739A (en) * 2022-12-15 2023-04-25 北京市政路桥股份有限公司 Highway bridge precast beam information management system based on BIM
CN112948950B (en) * 2021-04-07 2024-05-10 中铁广州工程局集团有限公司 BIM technology-based integrated information intelligent management system and management method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103264717A (en) * 2013-05-21 2013-08-28 北京泰乐德信息技术有限公司 Rail transit comprehensive monitoring scheduling coordinating and operation and maintenance information-based system
CN105931029A (en) * 2016-05-17 2016-09-07 中建三局第建设工程有限责任公司 Production management system for girder fabrication yard based on BIM
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106348174A (en) * 2016-10-08 2017-01-25 上海建工五建集团有限公司 Method and system for locating and hoisting prefabricated components based on RFID (Radio Frequency Identification) technology
CN106991214A (en) * 2017-03-10 2017-07-28 中铁四局集团有限公司 The informatization management method of high speed railway prefabricating Liang Chang based on BIM
CN107025516A (en) * 2017-03-10 2017-08-08 中铁四局集团有限公司 The KXG of high speed railway prefabricating Liang Chang based on BIM
CN107423865A (en) * 2017-03-10 2017-12-01 中铁四局集团有限公司 High-speed railway KXG based on BIM
CN108573340A (en) * 2018-03-22 2018-09-25 广东长亨石业有限公司 A kind of stone pit manufacturing monitoring system and method
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM
CN109446664A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of scene progress control display device system
CN105912780B (en) * 2016-04-12 2019-03-29 天津大学 The method of underground hole group three dimensional design and construction speed simulation interactive

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103264717A (en) * 2013-05-21 2013-08-28 北京泰乐德信息技术有限公司 Rail transit comprehensive monitoring scheduling coordinating and operation and maintenance information-based system
CN105912780B (en) * 2016-04-12 2019-03-29 天津大学 The method of underground hole group three dimensional design and construction speed simulation interactive
CN105931029A (en) * 2016-05-17 2016-09-07 中建三局第建设工程有限责任公司 Production management system for girder fabrication yard based on BIM
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106348174A (en) * 2016-10-08 2017-01-25 上海建工五建集团有限公司 Method and system for locating and hoisting prefabricated components based on RFID (Radio Frequency Identification) technology
CN106991214A (en) * 2017-03-10 2017-07-28 中铁四局集团有限公司 The informatization management method of high speed railway prefabricating Liang Chang based on BIM
CN107025516A (en) * 2017-03-10 2017-08-08 中铁四局集团有限公司 The KXG of high speed railway prefabricating Liang Chang based on BIM
CN107423865A (en) * 2017-03-10 2017-12-01 中铁四局集团有限公司 High-speed railway KXG based on BIM
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM
CN108573340A (en) * 2018-03-22 2018-09-25 广东长亨石业有限公司 A kind of stone pit manufacturing monitoring system and method
CN109446664A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of scene progress control display device system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110658790A (en) * 2019-09-17 2020-01-07 广州市微柏软件股份有限公司 Precast beam production management system based on three-dimensional visual process management
CN112101760A (en) * 2020-09-04 2020-12-18 中铁大桥局集团有限公司 Beam yard production state visualization method and system based on GIS
CN112948950A (en) * 2021-04-07 2021-06-11 中铁广州工程局集团有限公司 Integrated information intelligent management system and management method based on BIM technology
CN112948950B (en) * 2021-04-07 2024-05-10 中铁广州工程局集团有限公司 BIM technology-based integrated information intelligent management system and management method
CN113793117A (en) * 2021-08-27 2021-12-14 广东腾越建筑工程有限公司 BIM-based remote supervision method for building construction
CN114387881A (en) * 2021-12-30 2022-04-22 华能国际电力股份有限公司上海石洞口第一电厂 Engineering progress management method, device, equipment and medium
CN116011739A (en) * 2022-12-15 2023-04-25 北京市政路桥股份有限公司 Highway bridge precast beam information management system based on BIM

Similar Documents

Publication Publication Date Title
CN110070284A (en) A kind of wisdom beam course management system based on BIM technology
CN103824340B (en) Unmanned plane power transmission line intelligent cruising inspection system and method for inspecting
CN103824233B (en) Unmanned plane power circuit polling dispatching platform and method based on GIS
CN103823450B (en) Unmanned plane power circuit polling dispatch terminal based on GIS and method
CN108189043B (en) Inspection method and inspection robot system applied to high-speed rail machine room
CN108564676B (en) Intelligent inspection system and method for hydraulic power plant
CN103823451B (en) Unmanned plane power circuit polling centralized dispatching system and method based on GIS
CN106056695B (en) A kind of intelligent mobile inspection terminal based on Internet of Things
CN107146065A (en) Railway engineering management platform system
CN103823449B (en) For Centralized Monitoring subsystem and the method for supervising of unmanned plane polling transmission line
CN108520342A (en) Platform of internet of things management method based on BIM and its system
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
Liu et al. Research on workshop-based positioning technology based on internet of things in big data background
CN109614697A (en) A kind of bridge management system based on BIM
CN109543992A (en) Intelligent polling method, device, intelligent terminal and server
CN109413188A (en) A kind of industrial equipment management system for internet of things and method
CN101556475B (en) Real-time tracking system for processing materials and production process based on radio frequency technique
CN108876658A (en) Prefabricated part hanging procedural information management method
CN103812052A (en) Centralized monitoring system for power transmission line routing inspection of unmanned aerial vehicles and monitoring method
CN107240166A (en) Point inspection terminal and its data processing method
CN107240164A (en) The data processing of security cruising inspection system and device
CN107239868A (en) End message processing method and processing device for security cruising inspection system
CN106774240A (en) A kind of service-oriented industrial production control and monitoring method and system
CN102880115A (en) Remote collaborative diagnosis system of numerical-control machine tool on basis of internet of things
CN107399063A (en) It is injection moulded machine management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190730