The content of the invention
It is an object of the invention to provide a kind of KXG of the high speed railway prefabricating Liang Chang based on BIM, with
Solve the problem of existing railway prefabricated beam management information transmission is inaccurate.
To realize object above, the technical solution adopted by the present invention is:A kind of high speed railway prefabricating beam based on BIM is provided
The KXG of field, the system includes:Server end and client;
Described server end includes construction task generation module, the first sending module, the first receiving module and knock-down module;
Construction task generation module is set a roof beam in place according to Liang Chang applies group information, generation beam working procedure task;
Construction task generation module by the first sending module by the beam working procedure mission dispatching of generation to client so that
Client is initiated or closed procedure the process task received;
First receiving module is connected with client, receive client send to process tasks carrying initiate or closed procedure letter
Breath;
Knock-down module is connected to initiate process tasks carrying or the information of closed procedure is articulated in pair with the first receiving module
Should be on the BIM models of numbering box beam.
Compared with prior art, there is following technique effect in the present invention:The present invention is by using BIM
(Building Information Modeling, BIM), the server end and client of beam actual production management are built, by
Server end is realized the push of unjointed beam production schedule task and issued, the production schedule that client the reception server end is sent
Task, the synchronizing information initiated by client or closed per procedure task and every procedure is initiated and closed to server
The information, is articulated on corresponding BIM models by end by server.Construction production information is met to pass on accurately and rapidly
Need.Compared with the way to manage of traditional " people's pipe people ", not only reduce the error of information transmission, greatly improve information
The accuracy of transmission, and accelerate construction speed, save human cost.
Embodiment
With reference to shown in Fig. 1 to Fig. 2, the present invention is described in further detail.
As shown in figure 1, present embodiment discloses a kind of information system management system of the high speed railway prefabricating Liang Chang based on BIM
System, the system:Server end 10 and client 20;
Described server end 10 include construction task generation module 11, the first sending module 12, the first receiving module 13 and
Knock-down module 14;
Construction task generation module 11 is set a roof beam in place according to Liang Chang applies group information, generation beam working procedure task;
Construction task generation module 11 is by the first sending module 12 by the beam working procedure mission dispatching of generation to client
20 so that the process task that 20 pairs of client is received is initiated or closed procedure;
First receiving module 13 is connected with client 20, and receive the transmission of client 10 initiates process tasks carrying or close behaviour
The information of work;
Knock-down module 14 is connected that the information of the initiation of process tasks carrying or closed procedure will be mounted with the first receiving module 13
On the BIM models of reference numeral box beam.
It should be noted that the client in the present embodiment includes but is not limited to smart mobile phone, personal digital assistant
(PDA), tablet personal computer, notebook computer, vehicle-mounted computer(carputer), the client such as intelligent watch.
Further, the BIM models of box beam are to be based on BIM technology in the present embodiment, to high speed railway prefabricating beam two dimension
Design drawing carries out processing modeling and obtained.
Specifically, after the BIM models of precast beam box beam are set up, server end reads the number on the BIM models of box beam
According to and stored, for the later stage, user calls.
Further, described construction task generation module(11)Including:Construction plan task generation unit, determining unit
And memory cell;
Construction plan task generation unit is set a roof beam in place according to Liang Chang applies group information, generation beam construction plan task;
Determining unit is connected, according to the beam of generation construction plan task, to determine adjacent work with construction plan task generation unit
Sequence duration, the duration of box beam production and the structural data per procedure;
Wherein, the structural data per procedure mainly includes the pass between document required in production process, working procedure
Involved structural data in the whole production procedure such as system, mission dispatching interval.
Memory cell carries out packing storage to the structural data of every procedure task.
Specifically, the client 20 in the present embodiment can realize that the steel reinforcement cage in the process in beam actual production is tied up
Prick, wear rubber pulling rod rod, template cleaning, support plate install, lifting steel reinforcement cage, internal model install, install other built-in fittings, pour it is mixed
Soil, health are coagulated, internal model, pre- initial tensioning is torn open, rises and move the processes times such as beam, whole tensioning, mud jacking end-blocking, beam-ends waterproof, finished product beam outbound
The receiving and initiation of business, while being synchronized to server end.
Further, client 20 send to process tasks carrying initiate or closed procedure information, specifically include beam
Number, commencement date, working procedure, job location, detail design amount, construction actual amount and construction the deadline.
Explanation is needed exist for, client 20 is when initiating or closing working procedure task, and user can pass through client
Some information related to working procedure task are chosen at end 20, including:" ×× # beams ", " ×× process ", " job location ", " thing
The information such as part process ".These information contain the space attribute and physical attribute of working procedure task.Such as:Beam number:173#
Beam, commencement date:On December 16th, 2016 working procedure:Casting concrete, job location:5# beam making bench, design flow:317m
3rd, actual amount:320 cubic metres, pour the deadline:8 a.m. 50 grades.
Further, described knock-down module 14 is additionally operable to after the completion of per pass working procedure task, received server-side
The image data for the road working procedure task that client is sent and the BIM models that image data is articulated in reference numeral box beam
On.
It should be noted that image when server end 10 can construct to the per pass working procedure task that client 20 is uploaded
Data is stored, and in order to which the later stage is when there is mistake, reviews cause of accident.
Further, described server end 10 also includes the detection module being connected with BIM models;
Detection module detects BIM before the structural data by every procedure task is packed and is stored in server end
Whether the data on model meet the actual production flow of default Pin numbers box beam.
It should be noted that data in the present embodiment on BIM models include all work equipments that beam place is related to and
The parameter of equipment.
Specifically, in actual applications, when the data on BIM can not meet the Liang Chang of specific Pin numbers construction needs,
In order to ensure that the quality and safety of construction can not implement construction plan, therefore, in the structuring number to every procedure task
According to carrying out before packing storage, it is necessary to detected to the data on BIM models, to judge whether the data on BIM models expire
The need for a sufficient Pin or number Pin box beam actual production flows.
Further, as shown in Fig. 2 described client 20 includes:Second receiving module 21, the second sending module 22 with
And module 23 is initiated/closed to task;
Second receiving module 21 is connected the process task issued with the reception server end 10 with server end 10;
Task is initiated/closed module 23 and is connected that the process task received is initiated or closed with the second receiving module 21
Operation;
Module 23 is initiated/closed to task will be initiated or closed behaviour by the second sending module 22 to the process task received
The information of work is sent to server end 10.
Further, BIM technology and informationization technology are combined in the present embodiment, described BIM models are managed.It is main
If considering in actual applications, understanding the change according to railway prefabricated beam actual conditions, and to the three-dimensional mould of railway beam
Type is that BIM models are modified, the need for meeting actual production management.
The foregoing is only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and
Within principle, any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.