CN104484524B - A kind of method and system interacted based on BIM simulation models with site operation - Google Patents

A kind of method and system interacted based on BIM simulation models with site operation Download PDF

Info

Publication number
CN104484524B
CN104484524B CN201410776029.9A CN201410776029A CN104484524B CN 104484524 B CN104484524 B CN 104484524B CN 201410776029 A CN201410776029 A CN 201410776029A CN 104484524 B CN104484524 B CN 104484524B
Authority
CN
China
Prior art keywords
simulation model
construction
site operation
node
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410776029.9A
Other languages
Chinese (zh)
Other versions
CN104484524A (en
Inventor
张家驰
桑煜
高祥发
陈武练
黄超华
陈世清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410776029.9A priority Critical patent/CN104484524B/en
Publication of CN104484524A publication Critical patent/CN104484524A/en
Application granted granted Critical
Publication of CN104484524B publication Critical patent/CN104484524B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a kind of method and system interacted based on BIM simulation models with site operation, the present invention sets up monitoring node corresponding with site operation in BIM simulation model, and the corresponding acceptance criteria for meeting simulation model progress is set up to node, then can construct to set up between simulation model at the scene by the grasp to site operation interior joint information contacts.The problem of similarities and differences between progress msg and acceptance criteria according to represented by node can find and handle in the construction stage in time, so as to adjust simulation model or site operation progress, so that simulation model can not only support the construction of building yet to be built in theory, and can equally control construction speed when constructing at the scene, not only increase site operation in advance with disposal ability in thing, and substantially increase the credibility of simulation model.

Description

A kind of method and system interacted based on BIM simulation models with site operation
Technical field
The present invention relates to building trade, more particularly to a kind of monitoring site builds management method and the management of real-time progress System.
Background technology
In current building trade, it is frequently utilized that BIM (Building Information Modeling) sets up yet to be built in advance The simulation model of building, and corresponding construction plan is set up on the basis of the simulation model, finally further according to the construction meter Scratch beginning site operation.Although its simulation model is to accident in construction material, building cost, building completion date and building etc. Item required for one building of building has consideration, but it is also only theoretic planning, not in actual field Effective contact is set up between construction and simulation model or is managed, can not be gone adjustment imitative again according to the concrete condition of site operation True mode.No matter therefore how the emulation module early stage emulates and plans, the actual conditions of real scene still may with it is pre- Phase produces larger gap, once and project enters the construction stage, often because one or several key nodes it is out of control, Cause the serious problems such as whole project delay or rejection and waste.
The content of the invention
The management method of real-time progress is built it is an object of the present invention to provide a kind of monitoring site.
Another purpose of the present invention is to provide the management system that a kind of monitoring site builds real-time progress.
Especially, the present invention provides a kind of method interacted based on BIM simulation models with site operation, including following step Suddenly;
Step 1. sets up the simulation model of building yet to be built based on BIM;
The architectural process of the building yet to be built is divided into multiple construction stages by step 2. according to the simulation model, and The node of site operation progress in the construction stage is embodied as appointing for the construction contents selection in each construction stage Business, and the acceptance criteria for applying the plan that man-hour requirement meets the simulation model at the scene is set up for each node;
Step 3. is at the scene in work progress, and the node for obtaining the current construction stage by defined proof cycle and time point is believed Breath, is then uploaded to management platform acceptance criteria corresponding with the node of the construction stage and is contrasted:
Step 4. continues executing with next construction stage when nodal information meets the acceptance criteria of the node;
Otherwise, comparing result is forwarded to treatment people and tracks result, until acceptance criteria meets the requirements;
Step 5. repeat step 3,4 is until the building yet to be built completes site operation by the simulation model.
Further, the node in each construction stage has multiple and each node to correspond to described apply respectively The different structure of construction structure in the work stage.
Further, the nodal information by preset device or specified collector at the appointed time when pass through video recording, shine Phase, recording or text mode are obtained, and the nodal information is to be worked as by the node shown in photo, video recording, voice and/or word Preceding state.
Further, the mode of the upload includes wireless, wired, LAN or cell phone network.
Further, the simulation model also includes going out for the live progress of node described in each construction stage Exception treatment scheme during existing problem, the exception treatment scheme provides each described problem corresponding pretreatment opinion.
Further, the simulation model also includes early warning analysis, and the early warning analysis is saved in being constructed according to current live The influence that point is caused after going wrong, provides the suggestion for adjusting the simulation model follow-up plan.
Further, in addition to according to the nodal information of the site operation of acquisition the building yet to be built is progressively set up Progress simulation model the step of, the progress simulation model be used for embody each construction stage site operation it is actual enter Degree.
The present invention also provides a kind of system interacted based on BIM simulation models with site operation, including:
Schedule module, the simulation model for working out building yet to be built, the simulation model is by the building yet to be built Architectural process is divided into multiple construction stages, and the construction stage is embodied for the construction contents selection in each construction stage The node of interior site operation progress sets up each node and applies the meter that man-hour requirement meets the simulation model at the scene as task The acceptance criteria drawn;
Instruction module, for being sent in the stipulated time to premise equipment or specified collector in collection current live construction Specify the instruction of nodal information;The nodal information of collection is received simultaneously;
Comparison module, by testing for the nodal information of the reception node corresponding with the construction stage in the simulation model Receipts standard is contrasted, obtain current site operation construction speed whether meet the simulation model plan result;
Control module, when the nodal information meets acceptance criteria, then enters corresponding with next construction stage The building yet to be built site operation;When the nodal information does not meet the acceptance criteria, then sent out to treatment people Send and do not meet information and wait result, described applied with next until current node information meets to enter back into after acceptance criteria The site operation of the work stage corresponding building yet to be built;Until performing complete simulation model.
Further, the system also includes emulation module, is obtained during for according to the site operation of the building yet to be built The nodal information taken sets up corresponding stage simulation model.
Further, the system also includes exception treatment module, and produced problem is provided during for constructing at the scene It is recommended that;With
Warning module, the relation of nodal information and current construction conditions during for comprehensive analysis site operation, and to pre- Meter produced problem provides warning or solution in advance.
The present invention sets up monitoring node corresponding with site operation in BIM simulation model, and sets up corresponding to node The acceptance criteria for meeting simulation model progress, then can be constructed at the scene by the grasp to site operation interior joint information Set up and contact between simulation model.The similarities and differences between progress msg and acceptance criteria according to represented by node can be timely It was found that and processing the construction stage in the problem of, so as to adjust simulation model or site operation progress so that simulation model not only exists The construction of building yet to be built can be supported in theory, and can equally control construction speed when constructing at the scene, not only improved Site operation in advance with disposal ability in thing, and substantially increase the credibility of simulation model.
According to the accompanying drawings to the detailed description of the specific embodiment of the invention, those skilled in the art will be brighter Above-mentioned and other purposes, the advantages and features of the present invention.
Brief description of the drawings
Some specific embodiments of the present invention are described in detail by way of example, and not by way of limitation with reference to the accompanying drawings hereinafter. Identical reference denotes same or similar part or part in accompanying drawing.It should be appreciated by those skilled in the art that these What accompanying drawing was not necessarily drawn to scale.In accompanying drawing:
Fig. 1 is the flow of the method according to an embodiment of the invention interacted based on BIM simulation models with site operation Schematic diagram;
Fig. 2 is the flow of the system according to an embodiment of the invention interacted based on BIM simulation models with site operation Schematic diagram.
Embodiment
As shown in figure 1, being included in general manner based on the method that BIM simulation models are interacted with site operation for the present invention is as follows Step;
100. the simulation model of building yet to be built is set up based on BIM.
BIM (BIM Building Information Modeling) technology is that one kind is set applied to engineering Meter build management digitization instrument, it have visualization, harmony, simulation, optimization property and the big feature of figure five can be gone out.Its The simulation model of foundation covers all theoretical informations of building yet to be built, as reference during site operation, can make building Engineering significantly improves efficiency in its whole process, largely reduced risks.The present embodiment can be established having been based on BIM Simulation model on the basis of modify and realize or directly add this programme when BIM sets up simulation model Formed by simulation model.
The architectural process of building yet to be built is divided into multiple construction stages by 200. according to simulation model, and for each applying Construction contents selection in the work stage embodies the node of site operation progress in the construction stage as task, and is built for each node Need to meet the acceptance criteria of the plan of simulation model when standing in site operation.
The level of detail of the foundation of simulation model can be finally embodied in the control degree to site operation process, this reality Apply example to divide by the detailed segmentation to the architectural process of building yet to be built in simulation model, to simplify same time management scene Affairs content during construction.Also it is more conducive to pinpoint the problems and solve the problems, such as in time in advance or in thing simultaneously.In the different construction stages The number of nodes and content of the embodiment site operation progress of middle selection can be different, but the nodal information group in each construction stage The progress of site operation when allowing for embodying the construction stage after conjunction, sets up a scene by way of being concerned only with key node Contacting between construction and simulation model, makes site operation no longer depart from the control range of simulation model.Here acceptance criteria Refer within this construction stage, the standard completed is needed during site operation, and only node reaches that this acceptance criteria could illustrate now The progress of field construction has kept up with the plan of simulation model.
Further, the node in each construction stage can set multiple and each node to correspond to the construction building stage respectively The diverse location of interior construction structure.Such as, specific node can be the height of some main body wall in current live construction, OR gate The quantity of window, or floor laying etc..
300. at the scene in work progress, and the node for obtaining the current construction stage by defined proof cycle and time point is believed Breath, is then uploaded to management platform acceptance criteria corresponding with the node of the construction stage and is contrasted.
In the present embodiment, the node of the site operation of different construction stages needs to reflect entering for now site operation Degree.Therefore, the information for representing node can be that node is current at this using showing shown in photo, video recording, voice and/or word The content of state.Such as:The video of one section of reflection specified location or given content, or an image for reflecting specified location structure, Or the recording for that can not quantify and can only be illustrated with voice, or with corresponding measurement data, the consumption of material The content that can be expressed by word, numeral with surplus or number of turning out for work etc..And corresponding acceptance criteria is then to define pair The photo being consistent with corresponding node information, video recording, voice and/or the word letter reached is needed when answering node at the appointed time Breath.It can intuitively obtain whether current construction speed with simulation model is expected consistent result by the contrast of both information.
When building yet to be built starts to carry out site operation according to simulation model, nodal information is obtained in each construction stage Time and obtain the cycle it is all relevant with the site operation content in the construction stage.And specify the time to be to construction structure Building progress division, each specified time is a summary to current construction speed.The quantity and length for the time of specifying It is short to be consistent with the requirement in simulation model to the construction speed of the construction stage.
Further, the acquisition of nodal information can be by preset device or specified collector within a specified time to scene The respective nodes of construction obtain given content by shooting, photograph, voice or text mode etc..The preset device can be prior Monitoring device on construction site, such as images first-class or corresponding construction equipment, such as crane, mixer, digging Pick machine etc., its parameter after being used by itself weighs specific works amount to be used as nodal information.Specified collector can To be the people of special collection information or be acted by the construction personnel of corresponding construction site according to instruction.The equipment for gathering information can be with It is special instrument or smart machine, such as level meter, mobile phone, tablet personal computer.The nodal information of acquisition and the examination of the node The contrast of standard can be contrasted by management platform or monitoring personnel.When using management platform contrast, management platform will connect The specified nodal information received directly is contrasted with the acceptance criteria of the node and provides comparing result.Carried out when by monitoring personnel During contrast, it can directly be contrasted with the acceptance criteria in the nodal information and smart machine of acquisition and provide comparing result. The contrast of two ways includes the content contrast of video, content contrast, the typing of voice and the contrast of word content of photograph, and Comparing result is diagrammatically reflected.In addition, can also be by the side of remote field personnel when monitoring personnel is contrasted Formula, which is collected, specifies nodal information, and generates corresponding data file, recycles the section of the data file and corresponding construction stage The acceptance criteria of point is contrasted, and the construction stage should be reached so that it is determined that whether current construction speed meets in simulation model Construction period.The content of nodal information is not limited to related to building, can also be the influence weather of construction speed, personnel The information such as the rate of attendance and spillage of material degree.
It is provided with it is possible to further be uploaded to acquired information by wireless, wired, LAN or cell phone network The management platform of simulation model.
400., when nodal information meets the acceptance criteria of the node, continue executing with next construction stage;
Otherwise, comparing result is forwarded to treatment people and tracks result, until acceptance criteria meets the requirements.
Whether emulation is reached according to the construction speed for obtaining the current construction stage that the nodal information of acquisition can will be apparent that The expection of model, its result includes differential point and difference size between the node and acceptance criteria etc..Built as currently yet to be built Build the site operation progress of thing all the time expected synchronous with simulation model when, then building yet to be built can be monitored according to simulation model Site operation is until be completed.When such as pinpointing the problems, treatment people can be according to the timely process problem of concrete condition indicated, it is to avoid because The processing of the problem of for some nodes delays whole construction speed not in time.
500. repeat steps 300,400 are until building yet to be built completes site operation by simulation model.
The present embodiment realizes the real-time monitoring to building yet to be built by above-mentioned steps, by influenceing the section of construction speed The control of point reaches the purpose for holding whole scene construction.And can immediately find and properly be located when problem is just produced Reason.In addition the setting of the specified time to obtaining nodal information is passed through, additionally it is possible to avoid the accumulation of relevant issues.Further, Various nodal informations can make its specification by the way of abstract in the present embodiment, different nodal informations is quantified with Judged.The certain words included in the size of angle, photograph when such as taking pictures, voice, file size during upload Deng.Specific management platform can be remote monitoring center, its simulation model for including recording the building yet to be built and accordingly The information database of acceptance criteria, can be by the contrast including predetermined image, and the mode such as digital typing, voice response is realized Examination to the nodal information of upload.
In another embodiment of the present invention, it can also progressively be set up and treated according to the nodal information of the site operation of acquisition The progress simulation model of building is built, the progress simulation model can embody the actual field construction speed of each construction stage. The progress simulation model intuitively reflects the completeness and construction speed of current construction structure.
In one embodiment of the invention, the simulation model can also include showing for each construction stage interior joint Exception treatment scheme when field progress goes wrong, the exception treatment scheme provides corresponding pretreatment for each problem and anticipated See, be that treatment people solution problem points the direction, improve problem-solving ability in thing, it is to avoid the influence whole duration.
Further, the simulation model can also include early warning analysis, and the early warning analysis is saved in being constructed according to current live The influence that point is caused after going wrong, provides the suggestion of adjustment simulation model follow-up plan.The content of the early warning analysis can be wrapped Include the monitoring to future weather, the monitoring to construction material, to monitoring of builder's built speed etc., to find to ask in advance Topic, so as to improve in the thing to construction structure and pre-event management ability.Later repaiied again by the feedback to site operation problem Change simulation model, can avoid simulation model construct at the scene go wrong after depart from control to construction speed.
As shown in Fig. 2 the present invention also provides the management system that a kind of monitoring site builds progress, it is included such as in general manner Lower processing module:
Schedule module 10, the simulation model for working out building yet to be built, the simulation model is by the building of building yet to be built Process is divided into multiple construction stages, embodies scene in the construction stage for the construction contents selection in each construction stage and applies The node of work progress sets up each node and applies the examination mark that man-hour requirement meets the plan of simulation model at the scene as task It is accurate.
Instruction module 20, for sending collection current live construction to premise equipment or specified collector in the stipulated time In specify nodal information instruction;The nodal information of collection is received simultaneously.
Comparison module 30, by the acceptance criteria of corresponding node in the construction stage in the nodal information and simulation model of reception Contrasted, obtain current site operation construction speed whether meet simulation model plan result.
Control module 40, when nodal information meets acceptance criteria, then into corresponding with next construction stage yet to be built The site operation of building;When nodal information does not meet acceptance criteria, then sent to treatment people and do not meet information and wait Result, until current node information meets and building yet to be built corresponding with next construction stage is entered back into after acceptance criteria Site operation;Until completing whole simulation model.
Further, the management system can also include emulation module 50, and the emulation module 50 is used for according to building yet to be built The nodal information obtained during the site operation of thing sets up corresponding stage simulation model.
Further, the management system can also include the exception treatment that produced problem during to site operation provides suggestion Module 60, and nodal information during for comprehensive analysis site operation and current construction conditions relation and ask estimated Topic provides the warning module 70 of warning or solution in advance, and the exception treatment module 60 in the construction stage based on to occurring The problem of within drawing and outside plan, provides suggestion.The warning module provides modification emulation always according to site operation produced problem The suggestion of model, the plan of simulation model is adjusted with appearance of constructing at the scene, makes simulation model all the time in the case of uncontrollable The progress of site operation can be controlled.
The specific works mode of each module is described referring to the embodiment content above to method in said system, is not existed here Repeat.
So far, although those skilled in the art will appreciate that detailed herein have shown and described multiple showing for the present invention Example property embodiment, still, still can be direct according to present disclosure without departing from the spirit and scope of the present invention It is determined that or deriving many other variations or modifications for meeting the principle of the invention.Therefore, the scope of the present invention is understood that and recognized It is set to and covers other all these variations or modifications.

Claims (6)

1. a kind of method interacted based on BIM simulation models with site operation, is comprised the following steps;
Step 1. sets up the simulation model of building yet to be built based on BIM;
The architectural process of the building yet to be built is divided into multiple construction stages by step 2. according to the simulation model, and is directed to Construction contents selection in each construction stage embodies the node of site operation progress in the construction stage as task, and The acceptance criteria for applying the plan that man-hour requirement meets the simulation model at the scene is set up for each node;
The simulation model also includes early warning analysis, and the early warning analysis is constructed after interior joint goes wrong according to current live and made Into influence, provide the suggestion for adjusting the simulation model follow-up plan;
In work progress, the nodal information of current construction stage is obtained by defined proof cycle and time point at the scene for step 3., Then management platform acceptance criteria corresponding with the node of the construction stage is uploaded to be contrasted;
Also include emulating mould according to the progress that the nodal information of the site operation of acquisition progressively sets up the building yet to be built The step of type, the progress simulation model is used for the site operation actual progress for embodying each construction stage;
Step 4. continues executing with next construction stage when nodal information meets the acceptance criteria of the node;
Otherwise, comparing result is forwarded to treatment people and tracks result, until acceptance criteria meets the requirements;
Step 5. repeat step 3,4 is until the building yet to be built completes site operation by the simulation model.
2. the method as claimed in claim 1 interacted based on BIM simulation models with site operation, wherein, each construction The node in stage has multiple and each node to correspond to the different structure of construction structure in the construction stage respectively.
3. the method as claimed in claim 2 interacted based on BIM simulation models with site operation, wherein,
The nodal information by preset device or specified collector at the appointed time when pass through video recording, photograph, recording or word Mode is obtained, and the nodal information is by the node current state shown in photo, video recording, voice and/or word.
4. the method as claimed in claim 1 interacted based on BIM simulation models with site operation, wherein,
The mode of the upload includes wireless, wired, LAN or cell phone network.
5. the method as claimed in claim 1 interacted based on BIM simulation models with site operation, wherein,
The meaning when simulation model also includes going wrong for the live progress of node described in each construction stage Outer processing scheme, the exception treatment scheme provides each described problem corresponding pretreatment opinion.
6. a kind of system interacted based on BIM simulation models with site operation, including:
Schedule module, the simulation model for working out building yet to be built, the simulation model is by the building of the building yet to be built Process is divided into multiple construction stages, embodies existing in the construction stage for the construction contents selection in each construction stage The node of construction speed sets up each node and applies the plan that man-hour requirement meets the simulation model at the scene as task Acceptance criteria;
Instruction module, is specified for being sent in the stipulated time to premise equipment or specified collector in collection current live construction The instruction of nodal information;The nodal information of collection is received simultaneously;
Comparison module, by the examination mark of the nodal information of the reception node corresponding with the construction stage in the simulation model Standard contrasted, obtain current site operation construction speed whether meet the simulation model plan result;
Control module, when the nodal information meets acceptance criteria, then into institute corresponding with next construction stage State the site operation of building yet to be built;When the nodal information does not meet the acceptance criteria, then sent not to treatment people Meet information and wait result, until current node information meets and entered back into after acceptance criteria and next construction rank The site operation of the corresponding building yet to be built of section;Until performing complete simulation model;
Emulation module, the nodal information obtained during for according to the site operation of the building yet to be built sets up corresponding rank Section simulation model;
Exception treatment module, produced problem provides suggestion during for constructing at the scene;With
Warning module, the relation of nodal information and current construction conditions during for comprehensive analysis site operation, and to predicting Existing the problem of, provides warning or solution in advance.
CN201410776029.9A 2014-12-09 2014-12-09 A kind of method and system interacted based on BIM simulation models with site operation Active CN104484524B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410776029.9A CN104484524B (en) 2014-12-09 2014-12-09 A kind of method and system interacted based on BIM simulation models with site operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410776029.9A CN104484524B (en) 2014-12-09 2014-12-09 A kind of method and system interacted based on BIM simulation models with site operation

Publications (2)

Publication Number Publication Date
CN104484524A CN104484524A (en) 2015-04-01
CN104484524B true CN104484524B (en) 2017-08-01

Family

ID=52759065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410776029.9A Active CN104484524B (en) 2014-12-09 2014-12-09 A kind of method and system interacted based on BIM simulation models with site operation

Country Status (1)

Country Link
CN (1) CN104484524B (en)

Families Citing this family (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104978696A (en) * 2015-06-09 2015-10-14 广州市水电设备安装有限公司 Electronic acceptance and handover method based on BIM technology
CN104933265A (en) * 2015-07-07 2015-09-23 南通大学 Method for designing interior decoration of building based on BIM
CN105259783A (en) * 2015-10-16 2016-01-20 中国葛洲坝集团三峡建设工程有限公司 Visual preview system for water-and-power engineering construction process
CN105279609A (en) * 2015-10-26 2016-01-27 中国十七冶集团有限公司 Construction method of BIM (Building Information Modeling)-based cross-high-speed bridge construction traffic control
CN106096111A (en) * 2016-05-26 2016-11-09 陕西铁路工程职业技术学院 BIM technology application in high-speed railway CRTSIII plate-type Construction of Ballastless Track
CN106682325B (en) * 2016-12-30 2020-05-01 武汉英思工程科技股份有限公司 Dynamic fitting analysis method for deformation field in arch dam construction period based on BIM
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN107145851A (en) * 2017-04-28 2017-09-08 西南科技大学 Constructions work area dangerous matter sources intelligent identifying system
CN107464055A (en) * 2017-08-01 2017-12-12 贺州学院 Schedule estimation method and device
CN107515921A (en) * 2017-08-22 2017-12-26 北京恒华伟业科技股份有限公司 A kind of power engineering photo acquisition method and device
CN107688908B (en) * 2017-09-06 2018-12-14 北京城乡建设集团有限责任公司 Study and judge the method and device of construction safety risk
CN107798194A (en) * 2017-10-30 2018-03-13 毕埃慕(上海)建筑数据技术股份有限公司 The analogy method and device of engineering construction
CN108074032B (en) * 2017-10-31 2021-03-26 上海建工四建集团有限公司 Engineering quality acceptance device and method
CN107993000A (en) * 2017-11-27 2018-05-04 中国十九冶集团有限公司 The method of construction main flat face dynamic coordinate management based on BIM
CN107993057A (en) * 2017-12-29 2018-05-04 汪丁海 A kind of construction monitoring and managing method based on BIM
CN108090748A (en) * 2018-02-07 2018-05-29 墨点狗智能科技(东莞)有限公司 A kind of construction task management system of automation
CN109086530A (en) * 2018-08-07 2018-12-25 山东慧建天宝建筑工程科技有限公司 Construction data processing method, device, computer readable storage medium and terminal device
CN109558412A (en) * 2018-09-20 2019-04-02 中建科技有限公司深圳分公司 The data growing method and device of assembled architecture construct platform
CN110458421A (en) * 2019-07-19 2019-11-15 浙江龙腾畅想软件有限公司 A kind of quality safety management method, apparatus and storage device
CN111932049A (en) * 2020-05-26 2020-11-13 中建八局天津建设工程有限公司 Building assembly type component transportation simulation method based on BIM
CN111709081A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Construction cost control system based on BIM technology
CN111797522A (en) * 2020-06-29 2020-10-20 中建二局第一建筑工程有限公司 Automatic measurement system for building engineering
CN112101801A (en) * 2020-09-21 2020-12-18 三门核电有限公司 Construction quality unified supervision method and system based on Internet of things technology
CN112508340A (en) * 2020-11-10 2021-03-16 浙江鑫润工程管理有限公司 Project supervision project progress supervision method, system, device and storage medium
CN112381522A (en) * 2020-11-24 2021-02-19 正太集团有限公司 BIM-based site layout dynamic management and control method and system
CN112465381B (en) * 2020-12-11 2021-07-20 广东丰帆工程咨询有限公司 Building engineering construction progress data sharing scheduling management cloud platform based on cloud computing
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
CN113689136A (en) * 2021-09-02 2021-11-23 河南省育兴建设工程管理有限公司 BIM-based engineering supervision method and system
CN115048712B (en) * 2022-08-15 2022-10-25 北京迈平测绘技术开发有限公司 Monitoring method and system for railway construction site
CN116258610B (en) * 2023-05-15 2023-07-25 北京清科筑成科技股份公司 Construction project platform management method and system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102819621A (en) * 2011-06-10 2012-12-12 上海市电力公司 Device for conducting construction simulation through building information model (BIM)
CN102819622A (en) * 2011-06-10 2012-12-12 上海市电力公司 System device for establishing building information model (BIM)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2545478A4 (en) * 2010-03-09 2014-12-31 Autodesk Inc Systems and methods for construction field management and operations with building information modeling

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102819621A (en) * 2011-06-10 2012-12-12 上海市电力公司 Device for conducting construction simulation through building information model (BIM)
CN102819622A (en) * 2011-06-10 2012-12-12 上海市电力公司 System device for establishing building information model (BIM)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
基于 BIM 的清单式施工质量控制方法;肖梦琪;《项目管理技术》;20140731;第12卷(第7期);第64-67页 *

Also Published As

Publication number Publication date
CN104484524A (en) 2015-04-01

Similar Documents

Publication Publication Date Title
CN104484524B (en) A kind of method and system interacted based on BIM simulation models with site operation
Ma et al. Construction quality management based on a collaborative system using BIM and indoor positioning
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
Ding et al. BIM-based task-level planning for robotic brick assembly through image-based 3D modeling
US20210349476A1 (en) Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform
Kopsida et al. A review of automated construction progress monitoring and inspection methods
Hou et al. Towards a more extensive application of off-site construction: a technological review
Roh et al. An object-based 3D walk-through model for interior construction progress monitoring
CN110363852B (en) Three-dimensional digital beam field, construction method, computer equipment and storage medium
Yu et al. Smarter construction site management using the latest information technology.
CN106920049A (en) A kind of Project Management System platform based on BIM network technologies
KR100866830B1 (en) System and method for managing river using 3d based moving picture
CN105843834A (en) Work information modelling
CN108388711A (en) A kind of engineering design based on BIM and management system
CN110298768B (en) Road and bridge maintenance auxiliary decision-making system and maintenance method based on BIM and GIS
CN112685807B (en) Scaffold construction process application method and system based on BIM technology
Barki et al. BIM models generation from 2D CAD drawings and 3D scans: an analysis of challenges and opportunities for AEC practitioners
CN109214679A (en) A kind of projects management system based on Building Information Model
CN111062150A (en) Three-dimensional visual factory management system
Salamak et al. BrIM bridge inspections in the context of Industry 4.0 trends
CN116972855B (en) BIM-based coal preparation plant equipment three-dimensional roaming inspection method and system
CN112464494A (en) Construction system is built to wisdom
CN104850954A (en) System and method for processing construction information of architectural decoration project
CN109558047B (en) BIM lightweight model-based property repair method and device and terminal equipment
CN209486723U (en) A kind of construction management application platform based on BIM technology application

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Zhang Jiachi

Document name: Notification of Passing Examination on Formalities

GR01 Patent grant
GR01 Patent grant