CN107464055A - Schedule estimation method and device - Google Patents

Schedule estimation method and device Download PDF

Info

Publication number
CN107464055A
CN107464055A CN201710646155.6A CN201710646155A CN107464055A CN 107464055 A CN107464055 A CN 107464055A CN 201710646155 A CN201710646155 A CN 201710646155A CN 107464055 A CN107464055 A CN 107464055A
Authority
CN
China
Prior art keywords
current
building
construction
built
buildings models
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710646155.6A
Other languages
Chinese (zh)
Inventor
张金团
蔡德所
于冬升
胡琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hezhou University
Original Assignee
Hezhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hezhou University filed Critical Hezhou University
Priority to CN201710646155.6A priority Critical patent/CN107464055A/en
Publication of CN107464055A publication Critical patent/CN107464055A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The present invention provides a kind of schedule estimation method and device.Methods described includes:Obtain the condition of construction of current building site;Current schedules are estimated according to the BUILDINGS MODELS of the condition of construction of current building site and building to be built;Current schedules are shown, and preset strategy is performed according to current schedules.Thus, estimated according to current condition of construction, obtain current construction speed, to realize the real-time control to engineering project, lift engineering management level.

Description

Schedule estimation method and device
Technical field
The present invention relates to technical field of data processing, in particular to a kind of schedule estimation method and device.
Background technology
Can engineering project be delivered for use in the given time, be directly connected to the performance of project economic and social benefit. The purpose of project scheduling management is exactly to ensure the schedule objective of engineering by control.Progress monitoring scope is from approving and initiate a project to item In the full stage that mesh is completed and transferred, include all specialized engineerings of project, such as, main structural engineering, appurtenant work, road and Pipe engineering etc., it is related to design, scientific research, material supply, component and fitting supply etc..
With new technology, the emergence of new material, new technology, the project that modern project is extensive, form is complicated is more next More, simultaneously because market competition is increasingly fierce, requirement of the owner to project parties face further improves so that project management Work is more complicated and more challenge.The uncertainty of many influence factors and these factors, the project of determining are entered Spend the difficulty of management.Due to the enough data of construction-engineering project scheduling shortage and scheduling is random big, flow Arrange unreasonable, progress out-of-control phenomenon is serious.
The content of the invention
In order to overcome above-mentioned deficiency of the prior art, the technical problems to be solved by the invention are to provide a kind of progress and estimated Method and device is calculated, it can be estimated according to current condition of construction, obtain current construction speed, to realize to engineering The real-time control of project, is advantageous to project cost control and quality control.
Present pre-ferred embodiments provide a kind of schedule estimation method, and applied to computing device, methods described includes:
Obtain the condition of construction of current building site;
Current schedules are estimated according to the BUILDINGS MODELS of the condition of construction of current building site and building to be built;
The current schedules are shown, and preset strategy is performed according to the current schedules.
Present pre-ferred embodiments also provide a kind of schedule estimation device, and applied to computing device, described device includes:
Acquisition module, for obtaining the condition of construction of current building site;
Estimation block, it is current for the estimation of the BUILDINGS MODELS of the condition of construction according to current building site and building to be built Progress;
Display module, preset strategy is performed for showing the current schedules, and according to the current schedules.
In terms of existing technologies, the invention has the advantages that:
Present pre-ferred embodiments provide a kind of schedule estimation method and device.Methods described is applied to computing device.Obtain The condition of construction of current building site is taken, and then according to the estimation of the BUILDINGS MODELS of the condition of construction and building to be built when advance Degree.After estimation obtains current schedules, current schedules are shown, and preset strategy is performed according to the current schedules.By This, can realize the real-time control to engineering project, so as to realize project cost control and quality control by methods described.
To enable the above-mentioned purpose of invention, feature and advantage to become apparent, present pre-ferred embodiments cited below particularly, and Accompanying drawing appended by cooperation, is described in detail below.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below by embodiment it is required use it is attached Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, therefore be not construed as pair The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this A little accompanying drawings obtain other related accompanying drawings.
Fig. 1 is the communication scheme of the computing device that present pre-ferred embodiments provide and user terminal.
Fig. 2 is the block diagram for the computing device that present pre-ferred embodiments provide.
Fig. 3 is one of schematic flow sheet of schedule estimation method that present pre-ferred embodiments provide.
Fig. 4 is the schematic flow sheet of the sub-step that step S130 includes in Fig. 3.
Fig. 5 is the schematic flow sheet of the sub-step that step S140 includes in Fig. 3.
Fig. 6 is the two of the schematic flow sheet for the schedule estimation method that present pre-ferred embodiments provide.
Fig. 7 is the schematic flow sheet of the sub-step that step S110 includes in Fig. 6.
Fig. 8 is the block diagram for the schedule estimation device that present pre-ferred embodiments provide.
Icon:100- computing devices;110- memories;120- storage controls;130- processors;140- display units; 200- user terminals;300- schedule estimation devices;310- builds module;320- acquisition modules;330- estimation blocks;340- is shown Module;350- adjusting modules.
Embodiment
Below in conjunction with accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Ground describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.Generally exist The component of the embodiment of the present invention described and illustrated in accompanying drawing can be configured to arrange and design with a variety of herein.Cause This, the detailed description of the embodiments of the invention to providing in the accompanying drawings is not intended to limit claimed invention below Scope, but it is merely representative of the selected embodiment of the present invention.Based on embodiments of the invention, those skilled in the art are not doing The every other embodiment obtained on the premise of going out creative work, belongs to the scope of protection of the invention.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi It is defined, then it further need not be defined and explained in subsequent accompanying drawing in individual accompanying drawing.Meanwhile the present invention's In description, term " first ", " second " etc. are only used for distinguishing description, and it is not intended that instruction or hint relative importance.
Below in conjunction with the accompanying drawings, some embodiments of the present invention are elaborated.It is following in the case where not conflicting Feature in embodiment and embodiment can be mutually combined.
Fig. 1 is refer to, Fig. 1 is that the communication of computing device 100 and user terminal 200 that present pre-ferred embodiments provide is shown It is intended to.The computing device 100 communicates to connect with the user terminal 200.The computing device 100 is in the construction according to acquisition After situation estimates current schedules, the current schedules can be sent to user terminal 200.The user terminal 200 docks The information of receipts is shown, so that workmen grasps the real-time progress of project.Wherein, the computing device 100 can pass through Network is realized with the user terminal 200 and connected.
Fig. 2 is refer to, Fig. 2 is the block diagram for the computing device 100 that present pre-ferred embodiments provide.It is of the invention real Apply computing device 100 described in example may be, but not limited to, server, computer, smart mobile phone etc..The computing device 100 wraps Include:Memory 110, storage control 120, processor 130, display unit 140 and schedule estimation device 300.
Between the memory 110,140 each element of storage control 120, processor 130 and display unit directly or Ground connection is electrically connected with, to realize the transmission of data or interaction.For example, these elements can pass through one or more communication between each other Bus or signal wire, which are realized, to be electrically connected with.Schedule estimation device 300, the schedule estimation device 300 are stored with memory 110 Including at least one software function mould that can be stored in the form of software or firmware (firmware) in the memory 110 Block.The processor 130 is stored in software program and module in memory 110 by operation, in the embodiment of the present invention Schedule estimation device 300, so as to perform various function application and data processing, that is, realize the progress in the embodiment of the present invention Evaluation method.
Wherein, the memory 110 may be, but not limited to, random access memory (Random Access Memory, RAM), read-only storage (Read Only Memory, ROM), programmable read only memory (Programmable Read-Only Memory, PROM), erasable read-only memory (Erasable Programmable Read-Only Memory, EPROM), electricallyerasable ROM (EEROM) (Electric Erasable Programmable Read-Only Memory, EEPROM) etc..Wherein, memory 110 is used for storage program, the processor 130 after execute instruction is received, Perform described program.The processor 130 and other access of possible component to memory 110 can be in the storage controls Carried out under the control of device 120.
The processor 130 is probably a kind of IC chip, has the disposal ability of signal.Above-mentioned processor 130 can be general processor, including central processing unit (Central Processing Unit, CPU), network processing unit (Network Processor, NP) etc..It can also be digital signal processor (DSP), application specific integrated circuit (ASIC), scene Programmable gate array (FPGA) either other PLDs, discrete gate or transistor logic, discrete hardware group Part.It can realize or perform disclosed each method, step and the logic diagram in the embodiment of the present invention.General processor can be with It is microprocessor or the processor can also be any conventional processor etc..
The display unit 140 is used to show estimated obtained progress msg, so that monitoring personnel or workmen Current progress situation is obtained from the computing device 100.
It is appreciated that structure shown in Fig. 2 is only to illustrate, computing device 100 may also include it is more more than shown in Fig. 2 or Less component, or there is the configuration different from shown in Fig. 2.Each component shown in Fig. 2 can use hardware, software or its Combination is realized.
The user terminal 200 can be tablet personal computer, smart mobile phone etc..It is aobvious that the user terminal 200 can include one Show device, the progress msg that the user terminal 200 receives is shown.Also, the display device can also with One input and output interface are provided simultaneously between family terminal 200 and workmen.Display device is used to show to workmen Information of interface and input etc..Display device can also receive the input of workmen, such as, the gesture operation such as click, slip. The technology of detection input can be based on resistance-type, condenser type or other any possible touch control detection technologies.Display device Instantiation can include but is not limited to liquid crystal display or light emitting polymer displays.
Fig. 3 is refer to, Fig. 3 is one of schematic flow sheet of schedule estimation method that present pre-ferred embodiments provide.Under Idiographic flow in face of schedule estimation method is described in detail.
Step S120, obtain the condition of construction of current building site.
In the present embodiment, the computing device 100 (for example can be taken the photograph by user terminal 200 or other collecting devices Camera) obtain the condition of construction of current building site.
Specifically, workmen is shot by user terminal 200 at the construction field (site), so as to obtain condition of construction.Or Person, the construction drawing picture timing of collection is sent to the computing device 100 by the collecting device for being arranged on building site, so as to calculate Equipment 100 obtains condition of construction.Or the computing device 100 includes sampler (such as camera), passes through collector Part obtains the condition of construction of job site.
Step S130, according to the estimation of the BUILDINGS MODELS of the condition of construction of current building site and building to be built when advance Degree.
Fig. 4 is refer to, Fig. 4 is the schematic flow sheet of the sub-step that step S130 includes in Fig. 3.The step S130 can be with Including sub-step S131 and sub-step S132.
In the present embodiment, the condition of construction can include the construction drawing picture of current building site.The computing device 100 can estimate current progress according to the construction drawing picture.
Sub-step S131, topography corresponding with the construction drawing picture is found in the BUILDINGS MODELS.
In this embodiment, the computing device 100 is after the construction drawing picture of current building site is obtained, from memory 110 It is middle to obtain BUILDINGS MODELS corresponding with the construction drawing picture.The angle of the BUILDINGS MODELS is adjusted, to obtain and the construction drawing As similar topography.The similar topography and the construction drawing picture are contrasted, obtain similar topography with The similarity of the construction drawing picture.By the similarity compared with default similarity, phase is judged whether according to comparative result Whether it is topography corresponding with construction drawing picture like topography.Wherein, default similarity can be carried out according to actual conditions Setting.
When the similarity is less than default similarity, it is not corresponding with construction drawing picture local to characterize similar topography Image is, it is necessary to continue to search for topography corresponding with the construction drawing picture.
When the similarity is more than the default similarity, it is that construction drawing is local as corresponding to characterize similar topography Image, thus, obtain construction drawing topography as corresponding to.
Wherein, BUILDINGS MODELS can be BIM.BIM cover geometry, spatial relationship, Reason consulting, the property and quantity of various Constracture units.BIM can be used for showing whole building life cycle, build Interior various pieces, each system can show.Simultaneously inquiry can also be calculated automatically according to the data of structure The accurate information needed, information may have a variety of expression-forms, such as, the plan of building, facade, section, three-dimensional are vertical Stereogram etc..
Sub-step S132, according to position of the topography in the BUILDINGS MODELS to estimate current schedules.
In the present embodiment, current schedules are estimated according to the topography of acquisition and the BUILDINGS MODELS.
Step S140, the current schedules are shown, and preset strategy is performed according to the current schedules.
Fig. 5 is refer to, Fig. 5 is the schematic flow sheet of the sub-step that step S140 includes in Fig. 3.The step S140 can be with Including sub-step S142 and sub-step S143.
Sub-step S142, by the current schedules compared with default progress scope.
Sub-step S143, comparing result is sent to user terminal 200 and shown.
In the present embodiment, the computing device 100 communicates to connect with the user terminal 200.The computing device 100 Comparative result is sent to the user terminal 200, so that workmen understands current progress situation.Wherein, the construction Personnel can possess the staff for knowing progress situation authority.
If current schedules are less than the lower limit of default progress scope, it is backward, it is necessary to workmen's attention to characterize current schedules The situation, then the information that current schedules and progress fall behind is sent to user terminal 200 and shown, to inform workmen.
It is normal that if current schedules in the range of default progress, characterize current schedules, then current schedules and progress are normal Information is sent to user terminal 200 and shown, to inform workmen.
If current schedules are more than the higher limit of default progress scope, characterize current schedules and shift to an earlier date, then by current schedules and enter Spend advanced information and be sent to user terminal 200 and shown, to inform workmen.
Referring once again to Fig. 5, the step S140 can include sub-step S141.
Sub-step S141, default progress scope is obtained according to the condition of construction of current building site.
In the present embodiment, can be obtained according to the time and the BUILDINGS MODELS for obtaining current building site situation default Progress scope.It can also be obtained after the construction drawing according to current building site is as obtaining construction drawing topography as corresponding to Progress scope is preset corresponding to the topography, by current time compared with the default progress scope obtained, you can obtain Obtain current schedules situation.
Fig. 6 is refer to, Fig. 6 is the two of the schematic flow sheet for the schedule estimation method that present pre-ferred embodiments provide.Institute The method of stating can also include step S150.
Step S150, adjustment is sent to user terminal 200 according to the current schedules and default progress scope and suggested, so that Workmen is adjusted to construction speed.
In the present embodiment, the computing device 100 can also be according to current schedules, default progress scope and building mould Type, send rational adjustment to user terminal 200 and suggest.Such as in the case where current schedules shift to an earlier date, the computing device 100 can send the prompt message of management and control quality to user terminal 200, in the case of ensureing that progress is advanced, still ensure item Purpose instructs.Or in the case where current schedules fall behind, the computing device 100 can send to user terminal 200 and treat structure Certain part can accelerate the prompt message of progress in building.Thus, workmen can be according to prompt message and other factors (such as weather) makes rational adjustment, while progress is ensured, ensures the quality of project.
Referring once again to Fig. 6, methods described can also include step S110.
Step S110, build the BUILDINGS MODELS of building to be built.
Fig. 7 is refer to, Fig. 7 is the schematic flow sheet of the sub-step that step S110 includes in Fig. 6.The step S110 can be with Including sub-step S111 and sub-step S112.
Sub-step S111, obtain the model data for the BUILDINGS MODELS for building building to be built.
In the present embodiment, obtain and preserve the various information related to building building to be built, and then to the number of acquisition (for example the size of the building to be built is contracted by a certain percentage according to being handled with obtaining the data of BUILDINGS MODELS It is small).The model data can include the size and annexation of building element.
Sub-step S112, the BUILDINGS MODELS of building to be built is established according to the model data.
In the present embodiment, the computing device 100 can be by the size of building element, position coordinates, form parameter etc. Data are integrated, so as to obtain the BUILDINGS MODELS of building to be built.In addition, the computing device 100 can also receive other Information (such as the building flow of each building element, installation site information etc.), and will according to the information and model data of reception Each building element is formed together, so as to form BUILDINGS MODELS.
Fig. 8 is refer to, Fig. 8 is the block diagram for the schedule estimation device 300 that present pre-ferred embodiments provide.It is described Schedule estimation device 300 is applied to computing device 100.The schedule estimation device 300 includes:Acquisition module 320, estimation block 330 and display module 340.
Acquisition module 320, for obtaining the condition of construction of current building site.
In the present embodiment, acquisition module 320 is used to perform the step S120 in Fig. 3, on the specific of acquisition module 320 Description is referred to the description of step S120 in Fig. 3.
Estimation block 330, estimated for the BUILDINGS MODELS of the condition of construction according to current building site and building to be built Current schedules.
The condition of construction includes the construction drawing picture of current building site.The estimation block 330 is existing according to current building The condition of construction of field and the mode of the BUILDINGS MODELS estimation current schedules of building to be built include:
Topography corresponding with the construction drawing picture is found in the BUILDINGS MODELS;
According to position of the topography in the BUILDINGS MODELS to estimate current schedules.
In the present embodiment, estimation block 330 is used to perform the step S130 in Fig. 3, on the specific of estimation block 330 Description is referred to the description of step S130 in Fig. 3.
Display module 340, preset strategy is performed for showing the current schedules, and according to the current schedules.
In this example it is shown that module 340 is used to perform the step S140 in Fig. 3, on the specific of display module 340 Description is referred to the description of step S140 in Fig. 3.
Referring once again to Fig. 8, the schedule estimation device 300 can also include adjusting module 350.The computing device 100 communicate to connect with the user terminal 200.
The adjusting module 350, which is used to be sent to user terminal 200 according to the current schedules and default progress scope, to be adjusted Whole suggestion, so that workmen is adjusted to construction speed.
In the present embodiment, in the present embodiment, adjusting module 350 is used to perform the step S150 in Fig. 6, on adjustment The specific descriptions of module 350 are referred to the description of step S150 in Fig. 6.
Referring once again to Fig. 8, the schedule estimation device 300 can also include structure module 310.
Module 310 is built, for building the BUILDINGS MODELS of building to be built.
The mode for the BUILDINGS MODELS that the structure module 310 builds building to be built includes:
Obtain the model data for the BUILDINGS MODELS for building building to be built;
The BUILDINGS MODELS of building to be built is established according to the model data.
In the present embodiment, in the present embodiment, adjusting module 350 is used to perform the step S150 in Fig. 6, on adjustment The specific descriptions of module 350 are referred to the description of step S150 in Fig. 6.
In summary, the present invention provides a kind of schedule estimation method and device.Methods described is applied to computing device.Obtain The condition of construction of current building site, and then according to the estimation of the BUILDINGS MODELS of the condition of construction and building to be built when advance Degree.After estimation obtains current schedules, current schedules are shown, and preset strategy is performed according to the current schedules.By This, can realize the real-time control to engineering project, so as to realize project cost control and quality control, together by methods described When can avoid dragging, resource arranges situations such as unreasonable to occur with reasonable arrangement construction speed.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (10)

  1. A kind of 1. schedule estimation method, applied to computing device, it is characterised in that methods described includes:
    Obtain the condition of construction of current building site;
    Current schedules are estimated according to the BUILDINGS MODELS of the condition of construction of current building site and building to be built;
    The current schedules are shown, and preset strategy is performed according to the current schedules.
  2. 2. according to the method for claim 1, it is characterised in that the condition of construction includes the construction drawing of current building site The step of picture, the condition of construction of the current building site of basis and the BUILDINGS MODELS of building to be built estimate current schedules is wrapped Include:
    Topography corresponding with the construction drawing picture is found in the BUILDINGS MODELS;
    According to position of the topography in the BUILDINGS MODELS to estimate current schedules.
  3. 3. according to the method for claim 1, it is characterised in that the computing device is connected with user terminal communication, described The step of showing the current schedules, and performing preset strategy according to the current schedules includes:
    By the current schedules compared with default progress scope;
    If current schedules are less than the lower limit of default progress scope, the information that current schedules and progress fall behind is sent to user Terminal is shown, to inform workmen;
    If current schedules are sent to user terminal in the range of default progress, by current schedules and the normal information of progress and carried out It has been shown that, to inform workmen;
    If current schedules are more than the higher limit of default progress scope, the advanced information of current schedules and progress is sent to user Terminal is shown, to inform workmen.
  4. 4. according to the method for claim 3, it is characterised in that the display current schedules, and according to described current The step of progress execution preset strategy, also includes:
    Default progress scope is obtained according to the condition of construction of current building site.
  5. 5. according to the method for claim 3, it is characterised in that the current schedules are being shown, and according to described when advance After degree performs the step of preset strategy, methods described also includes:
    Adjustment is sent to user terminal according to the current schedules and default progress scope to suggest so that workmen to construct into Degree is adjusted.
  6. 6. according to the method for claim 1, it is characterised in that in the condition of construction step for obtaining current building site Before, methods described also includes:
    Build the BUILDINGS MODELS of building to be built;
    The step of BUILDINGS MODELS of the structure building to be built, includes:
    Obtain the model data for the BUILDINGS MODELS for building building to be built;
    The BUILDINGS MODELS of building to be built is established according to the model data.
  7. A kind of 7. schedule estimation device, applied to computing device, it is characterised in that described device includes:
    Acquisition module, for obtaining the condition of construction of current building site;
    Estimation block, for the estimation of the BUILDINGS MODELS of the condition of construction according to current building site and building to be built when advance Degree;
    Display module, preset strategy is performed for showing the current schedules, and according to the current schedules.
  8. 8. device according to claim 7, it is characterised in that the condition of construction includes the construction drawing of current building site Picture, the estimation block estimate current schedules according to the condition of construction of current building site and the BUILDINGS MODELS of building to be built Mode includes:
    Topography corresponding with the construction drawing picture is found in the BUILDINGS MODELS;
    According to position of the topography in the BUILDINGS MODELS to estimate current schedules.
  9. 9. device according to claim 7, it is characterised in that the computing device is connected with user terminal communication, described Device also includes:
    Adjusting module, suggest for sending adjustment to user terminal according to the current schedules and default progress scope, so as to apply Worker person is adjusted to construction speed.
  10. 10. device according to claim 7, it is characterised in that described device also includes:
    Module is built, for building the BUILDINGS MODELS of building to be built;
    The mode of the BUILDINGS MODELS of the structure module construction building to be built includes:
    Obtain the model data for the BUILDINGS MODELS for building building to be built;
    The BUILDINGS MODELS of building to be built is established according to the model data.
CN201710646155.6A 2017-08-01 2017-08-01 Schedule estimation method and device Pending CN107464055A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710646155.6A CN107464055A (en) 2017-08-01 2017-08-01 Schedule estimation method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710646155.6A CN107464055A (en) 2017-08-01 2017-08-01 Schedule estimation method and device

Publications (1)

Publication Number Publication Date
CN107464055A true CN107464055A (en) 2017-12-12

Family

ID=60547881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710646155.6A Pending CN107464055A (en) 2017-08-01 2017-08-01 Schedule estimation method and device

Country Status (1)

Country Link
CN (1) CN107464055A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109064134A (en) * 2018-07-28 2018-12-21 万翼科技有限公司 Calculation method, device and the storage medium of project safety coefficient
CN109559007A (en) * 2018-09-19 2019-04-02 中建科技有限公司深圳分公司 A kind of construction quality management method and device
CN110399513A (en) * 2019-03-15 2019-11-01 泰州三凯工程技术有限公司 Build data real-time query device
CN110460819A (en) * 2019-09-05 2019-11-15 河南城建学院 A kind of Project Management System engineering progress data input method
CN111241316A (en) * 2019-03-15 2020-06-05 泰州三凯工程技术有限公司 Real-time building data query method
CN112598367A (en) * 2020-12-03 2021-04-02 广东新禾道信息科技有限公司 Engineering project construction process monitoring method and system, intelligent terminal and storage medium
CN113822654A (en) * 2021-09-27 2021-12-21 苏州思萃融合基建技术研究所有限公司 Engineering project construction progress management method, device, equipment and storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (en) * 2014-12-09 2015-04-01 张家驰 Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN106886849A (en) * 2017-01-20 2017-06-23 深圳广田集团股份有限公司 Construction management-control method and system that a kind of BIM simulations are combined with taking photo by plane
CN106934595A (en) * 2017-02-23 2017-07-07 杭州仟金顶卓筑信息科技有限公司 Project Management System engineering progress data input method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (en) * 2014-12-09 2015-04-01 张家驰 Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN106886849A (en) * 2017-01-20 2017-06-23 深圳广田集团股份有限公司 Construction management-control method and system that a kind of BIM simulations are combined with taking photo by plane
CN106934595A (en) * 2017-02-23 2017-07-07 杭州仟金顶卓筑信息科技有限公司 Project Management System engineering progress data input method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109064134A (en) * 2018-07-28 2018-12-21 万翼科技有限公司 Calculation method, device and the storage medium of project safety coefficient
CN109559007A (en) * 2018-09-19 2019-04-02 中建科技有限公司深圳分公司 A kind of construction quality management method and device
CN110399513A (en) * 2019-03-15 2019-11-01 泰州三凯工程技术有限公司 Build data real-time query device
CN110399513B (en) * 2019-03-15 2020-04-14 广州市新誉工程咨询有限公司 Real-time query device for building data
CN111241316A (en) * 2019-03-15 2020-06-05 泰州三凯工程技术有限公司 Real-time building data query method
CN110460819A (en) * 2019-09-05 2019-11-15 河南城建学院 A kind of Project Management System engineering progress data input method
CN112598367A (en) * 2020-12-03 2021-04-02 广东新禾道信息科技有限公司 Engineering project construction process monitoring method and system, intelligent terminal and storage medium
CN113822654A (en) * 2021-09-27 2021-12-21 苏州思萃融合基建技术研究所有限公司 Engineering project construction progress management method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN107464055A (en) Schedule estimation method and device
TWI811208B (en) Information processing device, recording medium, and information processing method
CN104566998B (en) A kind of reservation control method of water heater, server and system
CN106920049A (en) A kind of Project Management System platform based on BIM network technologies
EP3905671A1 (en) Method and device for processing request
CN107682412A (en) A kind of wisdom vehicle washing system and wisdom car-washing method
CN106789563A (en) Electricity consumption business prompting method and device
US11257164B1 (en) Home assessment and issue probability generation
CN104412481A (en) Energy management server, energy management method, and program
JP2016521355A (en) Method and system for refining weather forecasts using point observation
MX2013014927A (en) Automated demand response system.
CN109727155A (en) Power consumption control method, apparatus, equipment and storage medium based on power quantity predicting
CN104751344A (en) Commodity information processing method, device and system
CN103019158A (en) System and method for managing and controlling green building facilities and equipment based on cloud computing
CN109029573A (en) A kind of pipeline method for inspecting and system
CN103781122A (en) Flow management device and method
CN207321306U (en) A kind of wisdom vehicle washing system
CN109389396A (en) Transportation card account automatic charging method, device, equipment and computer storage medium
CN107943570A (en) application management method, device, storage medium and electronic equipment
CN117035136A (en) Method, device, equipment and storage medium for reserving use of charging pile
CN112053484A (en) Door opening method and device of access control equipment, electronic equipment and medium
CN106302804B (en) Interactive method and system for electric power field operation
US11599812B2 (en) Condition determination system, condition determination method, decision-making support system, computer program, and storage medium
CN106408239A (en) Express delivery service information monitoring method, system, client and server
CN209785058U (en) Internet of things payment platform for diversified payment scenes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171212