CN109558412A - The data growing method and device of assembled architecture construct platform - Google Patents

The data growing method and device of assembled architecture construct platform Download PDF

Info

Publication number
CN109558412A
CN109558412A CN201811101543.7A CN201811101543A CN109558412A CN 109558412 A CN109558412 A CN 109558412A CN 201811101543 A CN201811101543 A CN 201811101543A CN 109558412 A CN109558412 A CN 109558412A
Authority
CN
China
Prior art keywords
component
construction
information
bim model
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811101543.7A
Other languages
Chinese (zh)
Inventor
樊则森
张仲华
孙晖
苏世龙
李新伟
谭睿楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Technology Group Co Ltd Shenzhen Branch
Original Assignee
China Construction Science and Technology Co Ltd Shenzhen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Science and Technology Co Ltd Shenzhen Branch filed Critical China Construction Science and Technology Co Ltd Shenzhen Branch
Priority to CN201811101543.7A priority Critical patent/CN109558412A/en
Publication of CN109558412A publication Critical patent/CN109558412A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of data growing method of assembled architecture construct platform and devices.Wherein, the data growing method of the assembled architecture construct platform includes: to obtain the corresponding construction information of component;By the corresponding construction information of the component store to in the associated database of the component;According to the construction information stored in the database by corresponding element numeral in pre-designed BIM model be complete construction component, so that the BIM model can be shown respectively to construction part and unfinished construction part is completed, realize the data of BIM model and the building synchronous growth of construction site, user can be by checking that BIM model can grasp the construction progress of building, the function of enriching BIM model, the technical issues of being had a single function caused by solving existing BIM model because generating after completing initial designs there is no data.

Description

The data growing method and device of assembled architecture construct platform
Technical field
The invention belongs to assembled architecture technical fields more particularly to a kind of data of assembled architecture construct platform to grow Method and apparatus.
Background technique
Building Information Model (Building Information Model, BIM) is the collection based on 3-dimensional digital technology It is to engineering project relevant information digitlization table in detail at the data model of the various relevant informations of construction-engineering project It reaches.For arbitrarily presentation can be virtualized by BIM model realization for constructing the component of building, pass through BIM model energy Enough component informations truly, in figurative expression reality built.
However, existing BIM model, after completing initial designs, it to be only merely a kind of static state that there is no data generations Model, so that BIM model function is more single.
Summary of the invention
In view of this, being solved the present invention provides a kind of data growing method of assembled architecture construct platform and device The problem of existing BIM model has a single function.
The first aspect of the present invention provides a kind of data growing method of assembled architecture construct platform, comprising:
Obtain the corresponding construction information of component;
By the corresponding construction information of the component store to in the associated database of the component;
It is by corresponding element numeral in pre-designed BIM model according to the construction information stored in the database The component of completion construction, so that the BIM model is shown respectively to construction part and unfinished construction part is completed.
The second aspect of the present invention provides a kind of data grower of assembled architecture construct platform, comprising:
Module is obtained, for obtaining the corresponding construction information of component;
Memory module, for by the corresponding construction information of the component store to in the associated database of the component;
Display module, for will be right in pre-designed BIM model according to the construction information stored in the database The element numeral answered be complete construction component so that the BIM model to be completed construction part and do not complete construction part It is shown respectively.
The third aspect of the present invention provides a kind of terminal device, including memory, processor and is stored in above-mentioned deposit In reservoir and the computer program that can run on above-mentioned processor, above-mentioned processor are realized such as when executing above-mentioned computer program The step of method of upper first aspect.
The fourth aspect of the present invention provides a kind of computer readable storage medium, and above-mentioned computer readable storage medium is deposited Computer program is contained, above-mentioned computer program realizes the method for first aspect as above when being executed by processor the step of.
Therefore by obtaining the corresponding construction information of component in the embodiment of the present invention, and the component is corresponding Construction information is stored to the associated database of the component, then, is incited somebody to action according to the construction information stored in the database Corresponding element numeral is to complete the component of construction in pre-designed BIM model, so that the BIM model is applied to being completed The Ministry of worker point and unfinished construction part can be shown respectively, realize that the data of BIM model are synchronous with the building of construction site Growth, user can enrich the function of BIM model, solve by checking that BIM model can grasp the construction progress of building Existing BIM model is because there is no have a single function caused by data generation after completing initial designs.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention some Embodiment for those of ordinary skill in the art without any creative labor, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is the specific implementation schematic diagram of assembled architecture construct platform provided in an embodiment of the present invention;
Fig. 2 is the schematic diagram of the web interface of assembled architecture construct platform provided in an embodiment of the present invention;
Fig. 3 is the implementation process signal of the data growing method of assembled architecture construct platform provided in an embodiment of the present invention Figure;
Fig. 4 is another implementation process of the data growing method of assembled architecture construct platform provided in an embodiment of the present invention Schematic diagram;
Fig. 5 is the another implementation process of the data growing method of assembled architecture construct platform provided in an embodiment of the present invention Schematic diagram;
Fig. 6 is the schematic diagram of the data grower of assembled architecture construct platform provided in an embodiment of the present invention;
Fig. 7 is the schematic diagram of terminal device provided in an embodiment of the present invention.
Specific embodiment
In being described below, for illustration and not for limitation, the tool of such as particular system structure, technology etc is proposed Body details, to understand thoroughly the embodiment of the present invention.However, it will be clear to one skilled in the art that there is no these specific The present invention also may be implemented in the other embodiments of details.In other situations, it omits to well-known system, device, electricity The detailed description of road and method, in case unnecessary details interferes description of the invention.
It should be appreciated that ought use in this specification and in the appended claims, term " includes " instruction is described special Sign, entirety, step, operation, the presence of element and/or component, but be not precluded one or more of the other feature, entirety, step, Operation, the presence or addition of element, component and/or its set.
It is also understood that mesh of the term used in this description of the invention merely for the sake of description specific embodiment And be not intended to limit the present invention.As description of the invention and it is used in the attached claims, unless on Other situations are hereafter clearly indicated, otherwise " one " of singular, "one" and "the" are intended to include plural form.
It will be further appreciated that the term "and/or" used in description of the invention and the appended claims is Refer to any combination and all possible combinations of one or more of associated item listed, and including these combinations.
Fig. 1 shows the specific implementation schematic diagram of assembled architecture construct platform provided in an embodiment of the present invention, needs Bright, Fig. 1 provides only a kind of specific implementation framework of the assembled architecture construct platform, it is contemplated that other energy Enough realize that the system architecture of the relative theory of assembled architecture construct platform provided in an embodiment of the present invention may be used to realize This programme, therefore, the specific implementation framework that Fig. 1 embodiment provides are not used in the restriction present invention herein.
As shown in Figure 1, assembled architecture construct platform includes but is not limited to web station interface 101, database 102, server 103 and back-stage management interface 104.
Herein, web interface 101 is mainly used for user the input upload of information, the displaying of data, platform operation side pair The parameter setting etc. of terminal device.The parameter of terminal device includes the play time of information, screen resolution etc..
Database 102 uses relevant database MySQL, for storing the information and reception of user information, user's input The information etc. from terminal device arrived.Server 103 uses Tomcat, the release management for website.Back-stage management interface 104 make the control management, such as the deletion of flame etc. of the progress information publication of platform operation side.
The assembled architecture construct platform is around assembled architecture design, Systemizing production and construction in concrete project;Building, structure, Electromechanical, built-in integration and technology, management, industrial integration (referred to as three integrations) integrated needs built, systematicness collection At the technologies such as BIM, internet, Internet of Things, assembled architecture, innovation research and development building+internet platform.
It is a kind of structural representation of the web interface of assembled architecture construct platform provided in an embodiment of the present invention referring to fig. 2 Figure.The web interface of the assembled architecture construct platform includes that Digital Design module, cloud build online shopping module, intelligent plant mould Block, wisdom building site module and happy space module.
The Digital Design module includes project library and component and component part library.The project library is used for this platform pipe Reason all construction projects carry out Classification Management, wherein further include under each construction project catalogue panorama, high building, index bed, The subdirectories such as project component base and project component library.All items that the component and component part library are used to manage this platform Component used in mesh and component component carry out Classification Management, wherein the component is shown by way of two dimensional code, Yong Huke The two dimensional code is clicked by platform terminal and carries out the displaying of component material picture, or passes through two dimensional code described in mobile scanning terminal, Then it shows on mobile terminals.The component component is shown by three-dimensional live model image, and user can be in platform It is rotated in terminal by three-dimensional live model image of the mouse to the component component, so as to realize different angle pair The three-dimensional live model image is shown.
It includes that BIM Cost Management submodule and cloud build net module that the cloud, which builds online shopping module, wherein BIM Cost Management Module is used to carry out Cost Management to all items of the platform management, and the cost includes civil engineering, steel construction, light current Intelligent, metal Roof cost.The cloud build net module provided by way of online shopping mall bidding relevant to project, The interface of worker's recruitment, the purchase of component component.User directly can realize that online recruit is thrown by this assembled architecture construct platform Mark, worker's recruitment and the purchase of component and component.
The intelligent plant module includes PC (prestressed concrete) factory management system, Active Eyes, life Produce plan designing system, prefabricated components production information system.The PC factory management system is for providing the office of each factory The login interface of system.The Active Eyes is used to transfer the interface of the monitoring camera of different factories, Yong Huke To select corresponding factory in the Active Eyes of this platform, so that it may the monitoring camera in the factory is called, The production of factory, personnel status are monitored.The production plan designing system is currently being carried out for providing for user Project manufacturing plan sheet is provided, user can carry out plan design by production plan designing system, and by the design side Case is sent to corresponding responsible party.The prefabricated components production information system is used to carry out the component information of all plant produceds Summarize, user can check the relevant information of component, such as amount of concrete, structure in the prefabricated components production information system of platform Part weight, reinforcing bar volume, reinforcing bar weight, steel content, sleeve number, suspender number, sunpender, screw number, hole count through walls and electricity Box number etc..
Wisdom building site module includes remote monitoring unit, construction quality unit, site safety unit, contract planning list Member, cost accounting unit, component trace-back unit, personal management unit, point cloud scanning element.
The remote monitoring unit is used to carry out video monitoring to the different zones of construction site.The construction quality unit It is expired not rectify and improve quantity for showing quality related information, such as hidden danger quantity, quantity to be rectified and improved, quantity to be checked and accepted and Quantity is closed, and is classified to the hidden danger according to severity, is classified as major hidden danger, larger hidden danger and general hidden Suffer from.In this platform, shown by way of histogram by hidden danger that different subcontractors occur is strong.The site safety For showing the safety problem in building-site to user by way of chart, for example, by safety problem present in building site It is classified as high altitude operation, administration behaviour, falsework, hoisting machinery, four mouthfuls of Triratna, construction equipment, power supply for construction, external scaffolding And civilized construction, and above-mentioned safety problem is shown in the form of cake chart.The contract planning unit for pair Contract recruits the preposition pre-control for plan of adopting, and realizes the self energy monitoring for recruiting plan of adopting and task supervisor, it is ensured that and contract is correctly fulfiled, and It realizes the structured storage recruited and adopt contract, quick search, task supervisor and workflow examination and approval, realizes that data efficient is practical.It is described at This measuring and calculating unit is realized and is refined to subpackage, goods and materials, machinery, artificial and expense multi-level oil for being associated with project image progress Control, preposition early warning, correction assist business people to carry out whole process supervision to cost control, find risk, and take and accordingly arrange It applies, save the cost is generated profit.The component trace back block is realized by the component two dimensional code generated by BIM model to component It is traced from the Life cycle of design, production, examination, lifting.Using single component as basic unit body, the full Life Cycle of component is realized The information of phase summarizes.With docking BIM light weighed model, the real-time control to building-site progress is realized.By being based on lightweight The real-time mounting of component progress and model not only may be implemented in the virtual construction of BIM model, and segmentation, subregion carry out, according to color Subregion carries out progress simulation, also analog information can be associated with PROJECT, carries out target advance and reality by chart and model interaction The comparison of construction speed deviation is completed in the comparison of border progress.Key node payment plan in expansible docking commerce module simultaneously, Realize the one-to-one correspondence of engineering construction plan and commercial payment plan in engineering key node, the practical branch of the Zhi Fuyu that realizes a plan The real time contrast of the amount of money is paid, realize to the accurate control of cost caused by each node of engineering and provides auxiliary for project administrator and determines Plan information maximizes.
The personal management unit is big by completion personnel real name system, personnel positioning information, video monitoring information three The three-dimensional management to live labor service personnel may be implemented in combination of the data of function on platform.In conjunction with account permission Setting and critical data summarize, and manager is facilitated to pass through real-time control of the visualized data to live labor service personnel's situation.In conjunction with Front end bio-identification gate system carries out real-time remote monitoring to worker's number on the scene and personal information.Pass through analysis, cross simultaneously The digitization system management to project labor service worker is completed than personal information data.
Described cloud scanning element is scanned by infrared point cloud, it can be achieved that sweeping to completed indoor engineering Centimeter Level quality It retouches and is modeled with outdoor scene.Platform database is compared and is uploaded to BIM light weighed model for scanning result simultaneously to put on record, In conjunction with design information, construction deviation report is generated, provides data foundation for Construction Quality report.By the way that cloud scanning knot will be put Fruit input database is put on record, in conjunction with information is delivered, can also provide three-dimensional data for the house use of numerals specification of owner.
The happiness space module is based on VR, panoramic virtual reality technology, provides new home delivery, panorama building operation instruction The services such as book, panorama estate management navigation, panorama building physical examination.The VR and panorama experience sense for supporting mobile terminal are by auxiliary is checked and accepted Hand over room.It supports to identify the key messages such as property present position, surrounding enviroment, room number by mobile terminal barcode scanning, and Gao Pin can be based on It is made on the basis of matter is visual and selects room decision, select room result that can realize data statistics on platform.It is related during living Architectural drawing and household component library may be implemented on-line selection, the information of related maintenance facility may be implemented to visualize online and look into It askes.
As shown in figure 3, being a kind of data growing method of assembled architecture construct platform provided in an embodiment of the present invention Implementation process schematic diagram is applicable to the situation of the function of abundant BIM model, and the data growing method includes: step 301 To step 303.
Step 301, the corresponding construction information of component is obtained.
Above-mentioned component can refer in assembled architecture for assembling all prefabricated components of building.Such as: inner wall of building, Exterior wall, precast stair, laminated floor slab, composite beam and prefabricated balcony etc..
The type of the corresponding construction information of above-mentioned component can be set according to practical application, for example, above-mentioned construction is believed Breath includes that the practical material of component, actual size, installed date, construction target date, the identity information of construction personnel, construction are tested One or more information in the identity information of receipts personnel and the video information of construction site.
It include: to obtain each component in pre-designed BIM model before the corresponding construction information of above-mentioned acquisition component Component design information;Component mark information corresponding with each component is generated according to the component design information.
In the embodiment of the present application, pre-designed BIM model is a complete information model, can be by engineering project The engineering information of each different phase, process and resources integration pass through 3-dimensional digital skill in a model in Life cycle Real information possessed by art simulant building thing provides mutually coordinated, internally consistent information model for engineering design and construction.
The component design information of each component in the pre-designed BIM model of above-mentioned acquisition is designed according to the component Information generates component mark information corresponding with each component and refers to: will be in typing after the lossless lightweight of weight BIM model under line In the project library for stating assembled architecture construct platform, each minimum in the BIM model after obtaining lightweight controls control unit, That is component, and be automatically generated for being associated with the component mark information of the database of the control unit.
The component mark information can preset coding rule generates according to unique encodings.As a kind of reality of the present invention Mode is applied, preset coding rule can be coding rule in sequence, for example, WQ1, WQ2 and WQ3 etc..As the present invention Another embodiment, preset coding rule can be that the time of database is uploaded to according to component as coded object, raw At unique encodings.
Step 302, by the corresponding construction information of above-mentioned component store to in the associated database of above-mentioned component.
In the embodiment of the present application, to the associated database of the component for storing all information relevant with the component, For example, design information, procurement information, production information, transit information, construction information and maintenance information etc..Wherein, design information Including design drawing, structure attribute, material, size, component conservation requires and designer's information.
Optionally, it is above-mentioned by the corresponding construction information of the component store to wrapped in the associated database of the component It includes: obtaining the component mark information of the component, according to the component mark information searching and the associated database of the component, And by the construction information of the component store to in the associated database of the component.
Step 303, according to the construction information stored in above-mentioned database by corresponding structure in pre-designed BIM model Part labeled as complete construction component so that above-mentioned BIM model to be completed construction part and do not complete construction part respectively into Row display.
Component data corresponding to different life stages are not identical, that is to say, that different data has been reacted locating for component Different life stages.
In the embodiment of the present application, when the construction information of the component stored in getting database, the component has been indicated Construction is completed, therefore, can be to complete the component of construction by corresponding element numeral in pre-designed BIM model, make Obtaining the BIM model can show respectively to construction part and unfinished part of constructing is completed;For example, by BIM model In Virtual Building it is corresponding be completed construction part labeled as dark color, do not complete construction part be labeled as grey.Realize BIM mould The data of type and the building synchronous growth of construction site, user can be applied by checking that BIM model can grasp the entirety of building Work progress, enriches the function of BIM model, solves existing BIM model because there is no numbers after completing initial designs The technical issues of according to being had a single function caused by generation.
Optionally, as a kind of embodiment of the application, it is above-mentioned will be preparatory according to the construction information stored in database Corresponding element numeral is to complete construction in designed BIM model, comprising: interval preset duration obtains new in the database The construction information of deposit, and according to the construction information of the new deposit by component mark corresponding in pre-designed BIM model It is denoted as the component for completing construction.
That is, being to be updated at interval of preset duration, rather than gradually update to the update of BIM model, have Effect reduces the data operation quantity of assembled architecture construct platform, and allows user by periodically checking in BIM model Data, grasp newest construction progress.
Wherein, above-mentioned preset duration can carry out customized setting by user as needed, for example, above-mentioned preset duration is One day, two days or one week.
Optionally, as shown in figure 4, the data for above-mentioned BIM model tormulation more can intuitively find out whether deposit The case where exceeding the time limit the duration, the construction information being newly stored in the database is obtained in above-mentioned interval preset duration, and according to institute It states after corresponding element numeral in pre-designed BIM model is the component for completing construction by the construction information that is newly stored in, It include: step 401 to step 403.
Step 401, label in above-mentioned BIM model is counted for the component of construction, obtains construction progress information.
Above-mentioned construction progress information includes the component amount that construction part is completed and the component amount for not completing construction part.
Step 402, it by above-mentioned construction progress information and the construction progress information matches planned in advance, judges whether there is and applies Work is exceeded the time limit.
For example, the component that construction part is completed is compared with the component that should complete construction part planned in advance, When the component that should complete construction part planned in advance is in the state for not completing construction, it is determined that there are constructions to exceed the time limit.
Step 403, construction is exceeded the time limit if it exists, then by construction exceed the time limit corresponding element numeral be first exceed the time limit component so that Above-mentioned BIM model is to being completed construction part, do not complete construction part and construction part of exceeding the time limit is shown respectively.
Wherein, construction exceeds the time limit partially to refer to that should complete construction does not complete the corresponding component of construction but.
In the embodiment of the present application, by that will construct, corresponding element numeral of exceeding the time limit is first to exceed the time limit component, for example, by BIM The corresponding construction of Virtual Building in model exceeds the time limit part labeled as red.So that above-mentioned BIM model to be completed construction part, It does not complete construction part and construction part of exceeding the time limit is clearly showed that respectively, be conducive to user and carry out duration supervision and engineering knot It calculates.
It further, is then the by construction corresponding element numeral of exceeding the time limit as shown in figure 5, above-mentioned construction if it exists is exceeded the time limit One exceeds the time limit after component, further includes: step 404.
Step 404, it obtains above-mentioned first to exceed the time limit the corresponding construction information of component, and corresponding according to above-mentioned first component that exceeds the time limit Construction information by the above-mentioned first element numeral of exceeding the time limit be second to exceed the time limit component so that the BIM model is to being completed construction portion Point, do not complete construction part, construction exceeds the time limit part and to complete the part of construction after exceeding the time limit and shown respectively.
In the embodiment of the present application, get above-mentioned first exceed the time limit component corresponding construction information when, indicate above-mentioned first Exceed the time limit component one complete construction, at this point, in order to by its with complete on schedule construction component distinguish, construction can will be completed The first element numeral of exceeding the time limit be second to exceed the time limit component, for example, it is brown, table that the first of construction element numeral of exceeding the time limit, which will be completed, Show that the component is the component for completing construction after exceeding the time limit, user is further facilitated to carry out duration supervision and Engineering Settlement.
In the embodiment of foregoing description, the data growing method of assembled architecture construct platform further include: obtaining structure Before the corresponding construction information of part, further includes: obtain the corresponding component design information of component, procurement information, production information and/or Transit information;And the corresponding component design information of the component, procurement information, production information and/or transit information are deposited respectively In the associated database of component described in Chu Zhiyu.
That is, the data growth for being embodied in Virtual Building in BIM model of data growth not merely, further includes Component is in the corresponding data growth of the stages such as design, buying, production and/or transport.
For example, above-mentioned component design information includes but is not limited to the design attributes information of component.Wherein, design attributes information It may include the information such as the type, title, design material and size information of component;Dimension information may include the practical ruler of component Very little information, it should be noted that dimension information not only includes the actual size information of member profile profile, further include component or The actual size information of details profile such as punch or opened a window in component.
Illustratively, above-mentioned component design information by designing user by web interface be uploaded to server and be stored in The associated database of component.Therefore, it is possible to obtain the design information of component from the database.In addition, design information is also wrapped Design data after including the operation such as the data in database are modified, deleted that designing user is triggered by web interface.
When the data growth in the stages such as buying, the production and transportation of above-mentioned component includes: the unit price of procurement of component, buying Between, supplier information, component production size, the price of production and processing, production firm, the information such as date of manufacture and delivery date, And the information such as change in size and material transformation of component.
In the embodiment of the present application, by obtain component from design, buying, production, transport to construction Life cycle number According to the data of component are constantly enriched in realization assembled architecture construct platform, so that user can use these work on platform Dynamic data realize a variety of monitoring functions, enrich the function of architecture construction platform.
For example, design data is compared with creation data, the gap of design and production is known, so that it is determined that factory needs The direction to be improved, preferably control production procedure.Creation data is compared with site operation data, knows production and reality The gap on border, on the one hand, determine creation data correctness, instruct the improvement of factory in turn, subsequent plant data is avoided to go out It is wrong;On the other hand, know the deficiency in practice of construction process of construction, the progress of guiding construction preferably controls operational procedure, together When design in turn optimization.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each process Execution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limit It is fixed.
It is the schematic diagram of the data grower of assembled architecture construct platform provided in an embodiment of the present invention referring to Fig. 6, For ease of description, only parts related to embodiments of the present invention are shown;The data of the assembled architecture construct platform are grown Device, comprising: obtain module 601, memory module 602 and display module 603.
Module 601 is obtained, for obtaining the corresponding construction information of component;
Memory module 602, for by the corresponding construction information of the component store to the associated database of the component In;
Display module 603, for will be in pre-designed BIM model according to the construction information stored in the database Corresponding element numeral be complete construction component so that the BIM model to be completed construction part and unfinished construction portion Divide and is shown respectively.
Fig. 7 is the schematic diagram for the terminal device that one embodiment of the invention provides.As shown in fig. 7, the terminal of the embodiment is set Standby 7 include: processor 70, memory 71 and are stored in the meter that can be run in the memory 71 and on the processor 70 Calculation machine program 72.The processor 70 realizes above-mentioned each assembled architecture construct platform when executing the computer program 72 Step in data growing method embodiment, such as step 301 shown in Fig. 3 is to 303.Alternatively, the processor 70 executes institute Realize the function of each module/unit in above-mentioned each Installation practice when stating computer program 72, for example, module 601 shown in Fig. 6 to 603 function.
Illustratively, the computer program 72 can be divided into one or more module/units, it is one or Multiple module/units are stored in the memory 71, and are executed by the processor 70, to complete the present invention.Described one A or multiple module/units can be the series of computation machine program instruction section that can complete specific function, which is used for Implementation procedure of the computer program 72 in the terminal device 7 is described.
The terminal device 7 can be desktop PC, notebook, palm PC, cloud server or server etc. Calculate equipment.The terminal device may include, but be not limited only to, processor 70, memory 71.Those skilled in the art can manage Solution, Fig. 7 is only the example of terminal device 7, does not constitute the restriction to terminal device 7, may include more or more than illustrating Few component perhaps combines certain components or different components, such as the terminal device can also be set including input and output Standby, network access equipment, bus etc..
Alleged processor 70 can be central processing unit (Central Processing Unit, CPU), can also be Other general processors, digital signal processor (Digital Signal Processor, DSP), specific integrated circuit (Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field- Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic, Discrete hardware components etc..General processor can be microprocessor or the processor is also possible to any conventional processor Deng.
The memory 71 can be the internal storage unit of the terminal device 7, such as the hard disk or interior of terminal device 7 It deposits.The memory 71 is also possible to the External memory equipment of the terminal device 7, such as be equipped on the terminal device 7 Plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital, SD) card dodge Deposit card (Flash Card) etc..Further, the memory 71 can also both include the storage inside list of the terminal device 7 Member also includes External memory equipment.The memory 71 is for storing needed for the computer program and the terminal device Other programs and data.The memory 71 can be also used for temporarily storing the data that has exported or will export.
It is apparent to those skilled in the art that for convenience of description and succinctly, only with above-mentioned each function Can unit, module division progress for example, in practical application, can according to need and by above-mentioned function distribution by different Functional unit, module are completed, i.e., the internal structure of described device is divided into different functional unit or module, more than completing The all or part of function of description.Each functional unit in embodiment, module can integrate in one processing unit, can also To be that each unit physically exists alone, can also be integrated in one unit with two or more units, it is above-mentioned integrated Unit both can take the form of hardware realization, can also realize in the form of software functional units.In addition, each function list Member, the specific name of module are also only for convenience of distinguishing each other, the protection scope being not intended to restrict the invention.Above system The specific work process of middle unit, module, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In the above-described embodiments, it all emphasizes particularly on different fields to the description of each embodiment, is not described in detail or remembers in some embodiment The part of load may refer to the associated description of other embodiments.
Those of ordinary skill in the art may be aware that list described in conjunction with the examples disclosed in the embodiments of the present disclosure Member and algorithm steps can be realized with the combination of electronic hardware or computer software and electronic hardware.These functions are actually It is implemented in hardware or software, the specific application and design constraint depending on technical solution.Professional technician Each specific application can be used different methods to achieve the described function, but this realization is it is not considered that exceed The scope of the present invention.
In embodiment provided by the present invention, it should be understood that disclosed device/terminal device and method, it can be with It realizes by another way.For example, device described above/terminal device embodiment is only schematical, for example, institute The division of module or unit is stated, only a kind of logical function partition, there may be another division manner in actual implementation, such as Multiple units or components can be combined or can be integrated into another system, or some features can be ignored or not executed.Separately A bit, shown or discussed mutual coupling or direct-coupling or communication connection can be through some interfaces, device Or the INDIRECT COUPLING or communication connection of unit, it can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated module/unit be realized in the form of SFU software functional unit and as independent product sale or In use, can store in a computer readable storage medium.Based on this understanding, the present invention realizes above-mentioned implementation All or part of the process in example method, can also instruct relevant hardware to complete, the meter by computer program Calculation machine program can be stored in a computer readable storage medium, the computer program when being executed by processor, it can be achieved that on The step of stating each embodiment of the method.Wherein, the computer program includes computer program code, the computer program generation Code can be source code form, object identification code form, executable file or certain intermediate forms etc..The computer-readable medium It may include: any entity or device, recording medium, USB flash disk, mobile hard disk, magnetic that can carry the computer program code Dish, CD, computer storage, read-only memory (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), electric carrier signal, telecommunication signal and software distribution medium etc..It should be noted that the meter The content that calculation machine readable medium includes can carry out increase and decrease appropriate according to the requirement made laws in jurisdiction with patent practice, Such as in certain jurisdictions, according to legislation and patent practice, computer-readable medium do not include be electric carrier signal and electricity Believe signal.
Embodiment described above is merely illustrative of the technical solution of the present invention, rather than its limitations;Although referring to aforementioned reality Applying example, invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned each Technical solution documented by embodiment is modified or equivalent replacement of some of the technical features;And these are modified Or replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution should all It is included within protection scope of the present invention.

Claims (10)

1. a kind of data growing method of assembled architecture construct platform, which is characterized in that the data growing method includes:
Obtain the corresponding construction information of component;
By the corresponding construction information of the component store to in the associated database of the component;
Corresponding element numeral in pre-designed BIM model is completed according to the construction information stored in the database The component of construction, so that the BIM model is shown respectively to construction part and unfinished construction part is completed.
2. data growing method as described in claim 1, which is characterized in that described according to the construction stored in the database Corresponding element numeral in pre-designed BIM model is to complete the component of construction by information, comprising:
Interval preset duration obtains the construction information being newly stored in the database, and will according to the construction information of the new deposit Corresponding element numeral is to complete the component of construction in pre-designed BIM model.
3. data growing method as claimed in claim 2, which is characterized in that the interval preset duration obtains the database In the construction information that is newly stored in, and according to the construction information of the new deposit by corresponding structure in pre-designed BIM model After part is labeled as the component for completing construction, comprising:
Label in the BIM model is counted for the component of construction, obtains construction progress information;
By the construction progress information and the construction progress information matches planned in advance, judges whether there is construction and exceed the time limit;
Construction is exceeded the time limit if it exists, then is first to exceed the time limit component by construction corresponding element numeral of exceeding the time limit, so that the BIM model pair Construction part is completed, does not complete construction part and construction part of exceeding the time limit is shown respectively.
4. data growing method as claimed in claim 3, which is characterized in that the construction if it exists is exceeded the time limit, then construction is super Phase corresponding element numeral is first to exceed the time limit after component, comprising:
It obtains described first to exceed the time limit the corresponding construction information of component, and exceeding the time limit the corresponding construction information of component according to described first will Described first element numeral of exceeding the time limit is second to exceed the time limit component, so that the BIM model is to being completed construction part, do not complete construction Partially, the part that construction exceeds the time limit partially and completes to construct after exceeding the time limit is shown respectively.
5. data growing method as described in claim 1, which is characterized in that before obtaining the corresponding construction information of component, Further include: obtain the corresponding component design information of component, procurement information, production information and/or transit information;And by the component Corresponding component design information, procurement information, production information and/or transit information store respectively to the associated number of the component According in library.
6. data growing method as described in claim 1, which is characterized in that described to deposit the corresponding construction information of the component Include: in the associated database of component described in Chu Zhiyu
The component mark information for obtaining the component, according to the component mark information searching and the associated data of the component Library, and by the construction information of the component store to in the associated database of the component.
7. data growing method as claimed in claim 6, which is characterized in that the component mark information for obtaining the component Include: before
Obtain the component design information of each component in pre-designed BIM model;
Component mark information corresponding with each component is generated according to the component design information.
8. a kind of data grower of assembled architecture construct platform, which is characterized in that the data grower includes:
Module is obtained, for obtaining the corresponding construction information of component;
Memory module, for by the corresponding construction information of the component store to in the associated database of the component;
Display module, for will be corresponding in pre-designed BIM model according to the construction information stored in the database Element numeral be complete construction component so that the BIM model to be completed construction part and do not complete construction part respectively It is shown.
9. a kind of terminal device, including memory, processor and storage are in the memory and can be on the processor The computer program of operation, which is characterized in that the processor realizes such as claim 1 to 7 when executing the computer program The step of any one the method.
10. a kind of computer readable storage medium, the computer-readable recording medium storage has computer program, and feature exists In when the computer program is executed by processor the step of any one of such as claim 1 to 7 of realization the method.
CN201811101543.7A 2018-09-20 2018-09-20 The data growing method and device of assembled architecture construct platform Pending CN109558412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811101543.7A CN109558412A (en) 2018-09-20 2018-09-20 The data growing method and device of assembled architecture construct platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811101543.7A CN109558412A (en) 2018-09-20 2018-09-20 The data growing method and device of assembled architecture construct platform

Publications (1)

Publication Number Publication Date
CN109558412A true CN109558412A (en) 2019-04-02

Family

ID=65864617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811101543.7A Pending CN109558412A (en) 2018-09-20 2018-09-20 The data growing method and device of assembled architecture construct platform

Country Status (1)

Country Link
CN (1) CN109558412A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110135814A (en) * 2019-05-21 2019-08-16 湖北合联工程管理有限公司 The correlating method of BIM and project data, system and terminal device
CN110414922A (en) * 2019-06-28 2019-11-05 万翼科技有限公司 A kind of construction data management method and device based on Building Information Model
CN111506941A (en) * 2020-03-14 2020-08-07 宁波国际投资咨询有限公司 BIM technology-based assembly type building PC component storage method and system
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN112036722A (en) * 2020-08-21 2020-12-04 万翼科技有限公司 Assembly type building project progress remote management method, electronic equipment and related products
CN113408034A (en) * 2021-07-12 2021-09-17 贵州百胜工程建设咨询有限公司 Engineering construction intelligent cloud management platform based on BIM building three-dimensional model technology
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM
CN114819904A (en) * 2022-05-05 2022-07-29 阿里巴巴(中国)有限公司 Assembly type building data processing method and device and electronic equipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (en) * 2014-12-09 2015-04-01 张家驰 Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN105335559A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering standardized construction process control method and system on basis of BIM (building information modeling)
CN105512730A (en) * 2015-12-02 2016-04-20 中国南方电网有限责任公司 BIM model-based data center operation and maintenance system
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106485411A (en) * 2016-10-08 2017-03-08 上海建工五建集团有限公司 Prefabricated concrete structure based on BIM technology builds management method and system
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (en) * 2014-12-09 2015-04-01 张家驰 Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN105335559A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering standardized construction process control method and system on basis of BIM (building information modeling)
CN105512730A (en) * 2015-12-02 2016-04-20 中国南方电网有限责任公司 BIM model-based data center operation and maintenance system
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106485411A (en) * 2016-10-08 2017-03-08 上海建工五建集团有限公司 Prefabricated concrete structure based on BIM technology builds management method and system
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张江波等: "《EPC项目造价管理》", 28 February 2018 *
李建成等: "《建筑信息模型BIM应用丛书BIM应用导论》", 31 March 2015 *
蔡宁等: "《陈翔路地道工程BIM应用解析》", 31 August 2014 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110135814A (en) * 2019-05-21 2019-08-16 湖北合联工程管理有限公司 The correlating method of BIM and project data, system and terminal device
CN110414922A (en) * 2019-06-28 2019-11-05 万翼科技有限公司 A kind of construction data management method and device based on Building Information Model
CN111506941A (en) * 2020-03-14 2020-08-07 宁波国际投资咨询有限公司 BIM technology-based assembly type building PC component storage method and system
CN111506941B (en) * 2020-03-14 2022-12-02 宁波国际投资咨询有限公司 BIM technology-based assembly type building PC component storage method and system
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN111881501B (en) * 2020-07-23 2024-04-16 广东腾美建设工程有限公司 BIM and cloud service-based fabricated building management method and system
CN112036722A (en) * 2020-08-21 2020-12-04 万翼科技有限公司 Assembly type building project progress remote management method, electronic equipment and related products
CN113408034A (en) * 2021-07-12 2021-09-17 贵州百胜工程建设咨询有限公司 Engineering construction intelligent cloud management platform based on BIM building three-dimensional model technology
CN113408034B (en) * 2021-07-12 2022-02-18 贵州百胜数源工程技术管理有限公司 Engineering construction intelligent cloud management platform based on BIM building three-dimensional model technology
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM
CN114819904A (en) * 2022-05-05 2022-07-29 阿里巴巴(中国)有限公司 Assembly type building data processing method and device and electronic equipment

Similar Documents

Publication Publication Date Title
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
CN108846644B (en) Integrated simulation technology, cooperative work, knowledge management and project management and control system
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
CN106022979A (en) BIM-based water conservancy and hydropower project management cloud platform and application method thereof
WO2020056669A1 (en) Control method and apparatus for unmanned aerial vehicle cruise based on prefabricated building platform
CN111369158A (en) BIM-based informatization quality management method and system
Re Cecconi et al. Leveraging BIM for digital built environment asset management
CN107958328A (en) Green assembled architecture digitlization construct platform and its method of work
Duncheva et al. Multifaceted productivity comparison of off-site timber manufacturing strategies in Mainland Europe and the United Kingdom
CN109559379A (en) A kind of panorama based on assembled architecture platform sees room method and device
CN109559006A (en) A kind of monitoring method, device and the terminal device of the construction site based on unmanned plane
KR101245151B1 (en) Optimized digital factory production plan & confirm system by using real-time factory situation
CN111275297A (en) Building engineering EPC (electronic product code) cost and progress management system and management method based on BIM (building information modeling) technology
CN110019435A (en) Data processing method and system based on assembled architecture platform
CN109559070A (en) The equipment production information management method and device of assembled architecture platform
KR20160080388A (en) Bim-based construction value engineering (ve) processing system
Fernandes Advantages and disadvantages of BIM platforms on construction site
CN116739535B (en) Method for building accurate digital twin planning display platform for quotients
Politi Project planning and management using building information modeling (BIM)
CN113011832A (en) Engineering cost system based on BIM
CN109558047B (en) BIM lightweight model-based property repair method and device and terminal equipment
Wang et al. A hybrid building information modeling and collaboration platform for automation system in smart construction
KR100945523B1 (en) On-line construction management method
WO2020056671A1 (en) Data growth method and device for fabricated building construction platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190402

RJ01 Rejection of invention patent application after publication