CN107958328A - Green assembled architecture digitlization construct platform and its method of work - Google Patents

Green assembled architecture digitlization construct platform and its method of work Download PDF

Info

Publication number
CN107958328A
CN107958328A CN201711172627.5A CN201711172627A CN107958328A CN 107958328 A CN107958328 A CN 107958328A CN 201711172627 A CN201711172627 A CN 201711172627A CN 107958328 A CN107958328 A CN 107958328A
Authority
CN
China
Prior art keywords
construction
management
project
design
examination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711172627.5A
Other languages
Chinese (zh)
Inventor
王衡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Building Polytron Technologies Inc
Original Assignee
Beijing Building Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Building Polytron Technologies Inc filed Critical Beijing Building Polytron Technologies Inc
Priority to CN201711172627.5A priority Critical patent/CN107958328A/en
Publication of CN107958328A publication Critical patent/CN107958328A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Computer Hardware Design (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of green assembled architecture digitlization construct platform and its method of work, belong to assembled architecture field, including:Construction Project Management module, BIM modules, design management module, purchasing management module and construction management module.The information data of each module stores in BIM, using digital information model as the basis of each construction project, carry out related work, can real-time update information, there is information share;The green assembled architecture of the present invention digitizes construct platform to construction project unified planning, Uniting, can be according to architectural engineering needs, by in the building structure component and common apparatus material of plant produced, transport on time to construction site, and remote supervisory, control and management can be carried out to the overall process of more than ten of construction project site operation at the same time.Fully achieve modularized design, industrialized production, prefabricated construction, intelligent management.

Description

Green assembled architecture digitlization construct platform and its method of work
Technical field
The present invention relates to assembled architecture technical field, particularly relates to a kind of green assembled architecture digitlization construct platform And its method of work.
Background technology
Traditional assembled architecture, in building course, once planning, design are completed, needs again in modification Come again, it is less efficient, it is impossible to remote monitoring, and construction management is chaotic in building course, builder, supervision side, supplier, logistics Business and high-ranking accountant etc. cannot timely be linked up, it is impossible to form integrated system, operational paradigm is low, much Cannot meet the needs of market.
With the development of internet, Building Information Model (Building Information Modeling, BIM) can be with Using every relevant information data of construction-engineering project as the basis of model, the foundation of buildings model is carried out, is believed by numeral Cease analogue simulation building possessed by real information, it have visualization, harmony, simulation, optimization property and figure can be gone out Five big features.Based on BIM and internet+, based on architectural engineering relevant information data model, it is badly in need of a kind of digitlization, can Management system is built depending on change, the long-range of analog simulation, can realize modularized design, industrialized production, prefabricated construction, intelligence Change management.
The content of the invention
The present invention, which provides one kind, can realize modularized design, industrialized production, prefabricated construction, intelligent management green Assembled architecture digitizes construct platform and its method of work.
In order to solve the above technical problems, present invention offer technical solution is as follows:
On the one hand, the present invention provides a kind of green assembled architecture digitlization construct platform, including:
Construction Project Management module, for undertake all construction project project verifications of platform, integrated management, construction project planning set Meter examination & verification, engineering open management of being completed, funds transfer, system information distribution and empowerment management;
BIM modules, for being responsible for construction project planning, design, establish architectural engineering relevant information data model, non-standard The design of module, the foundation and maintenance of standard and modular database;
Design management module, for the typing of primary demand, planned design management, design document uploads, and design point becomes More, tell somebody what one's real intentions are file polling, design alteration inquiry and uploads bill of materials at design document inquiry;
Purchasing management module, for being needed to purchase building structure component, accessory, equipment and material according to architectural engineering, and is transported To construction site;
Construction management module, for long-range work progress management, makes commencement of works, completion, construction speed, engineering material Remote management is carried out with situation, transfers to construction party to undertake engineering safety responsibility, the responsibility of engineering quality transfers to management side to undertake, and leads to Cross and the construction speed data of construction party and the signature examination & verification of management side is audited, the use of control project progress, engineering material Situation and change in the work situation.
Further, the green assembled architecture digitlization construct platform further comprises:
Preliminary budget management module, for according to Budgetary Estimates, being responsible for the management of construction project covering price and control;
Supply chain and member management module, all kinds of members for being responsible for supplier, logistics provider, builder and supervision side manage Reason;
Construction client manager module, including builder construction client manager module and supervision side's construction client-side management Module, instructs in due course reception system, gathers work progress relevant information, is submitted after management confirms, meet system to applying Supervision, management and the control of work overall process;
Engineering Settlement module, for based on contract and final accounts, being responsible for Engineering Settlement.
Further, the green assembled architecture digitlization construct platform further includes:
Module and equipment and materials management module, for carrying out data input to standardized building model and encoding, realization pair Each Modular building structure component of typing BIM modules, electromechanical equipment and material carry out integrated management;
Online house-purchase module, for according to the house-purchase information to strike a bargain on the net, specifying builder member to be responsible for construction nearby;
Financial management module, is inquired about for bank settlement flow, project finance;
Market tracking module, for market project management, track record is reported and audited, classification of the items is inquired about, pipe of submitting a tender Reason.
On the other hand, the present invention also provides a kind of work side of above-mentioned green assembled architecture digitlization construct platform Method, overall process include successively:Project tracking stage, project implementation phase, the design phase, the preliminary budget stage, the acquisition phase, apply Work stage and concluding a research item stage;
Wherein, the project tracking stage after tracking project, the successful project bidding mainly including signing a contract;
Project implementation phase mainly includes project verification establishment project and personnel assigned;
Design phase mainly includes Preliminary design and construction drawing design;
The preliminary budget stage is mainly included in the budgetary estimate after the completion of Preliminary design and the budget after the completion of construction drawing design;
Construction stage is mainly included in construction plan, work progress, construction negotiation and completion after the completion of construction drawing design Check and accept;
Acquisition phase is mainly included in procurement plan and executive plan after the completion of construction drawing design and construction plan;
The concluding a research item stage is mainly included in the financial final accounts after the completion of final acceptance of construction.
Further, the idiographic flow of project implementation phase includes:
S101:Establishment project, typing essential information and technical routine manager;
S102:Signal auditing is carried out, if signal auditing is not by going to S101, if signal auditing is by carrying out S103;
S103:Project planning, is carried out at the same time contract inputting, personnel assignment and planning, and project verification terminates.
Further, the idiographic flow of design phase includes:
S104:Typing data early period;
S105:Examination & verification is submitted, if the audit fails, goes to S104, if examination & verification passes through, carries out S106;
S106:Judge whether to require supplementation with other information, if so, S104 is gone to, if it is not, carrying out S107;
S107:Conceptual design;
S108:Examination & verification, after examination & verification passes through, carries out Preliminary design;
S109:Audit again, after examination & verification passes through, form preliminary project;
S110:Report declaration to a higher authorities for approval;
S111:Examination & verification is submitted, if examination & verification passes through, carries out S112;
S112:Judge whether to require supplementation with other information, if it is not, design terminates.
Further, the idiographic flow of construction stage includes:
S201:Project under construction typing, including construction party contract inputting and the contract inputting of management side;
S202:Construction party initiates to examine according to data;
S203:Audit management side;
S204:Construction manager audits;
S205:Judge whether project terminates, if not terminating, go to S202, if terminating, carry out concluding a research item application, construction terminates.
Further, the present invention also provides a kind of work side of above-mentioned green assembled architecture digitlization construct platform Method, the idiographic flow of acquisition phase include:
S301:Forward purchasing supply of material inventory is imported according to bill of quantities and its corresponding sub-project;
S302:Form material list;
S303:Mark procurement method;
S304:Examination & verification is submitted, if the audit fails, content is changed, resubmits examination & verification, if examination & verification passes through, generation is pre- Shopping list;
S305:Carry out supplier and/or logistics provider selects flow;
S306:Merchandising Manager audits;
S307:Project manager audits, and by rear, execution of order flow, completes buying.
Further, green assembled architecture digitlization construct platform uses member system, and member includes supplier, logistics Business, construction side and management side, wherein:
The membership flow of supplier and/or logistics provider include:
S501:Supplier and/or the application membership of forwarding agent website;
S502:Etc. pending, if the audit fails, S501 is gone to, if examination & verification passes through, carries out S503;
S503:Sign a contract under line;
S504:Typing supplier and/or carrier information;
S505:Upload contract information;
S506:Distribution account number cipher is with logging in port;
S507:The material information of typing supplier and the logistics price of forwarding agent;
S508:Signal auditing is carried out, if the audit fails, goes to S504, if examination & verification passes through, supplier and/or logistics provider Membership is completed;
The membership flow of construction side and/or management side includes:
S601:Sign a contract;
S602:Typing construction side and/or management side's information, including basic information, scale, qualification and numbering;
S603:Typing contract information simultaneously uploads contract;
S604:Signal auditing is carried out, if the audit fails, goes to S602, examination & verification passes through, and construction side/management side's membership is complete Into.
Further, generation goods orders and logistics order are also needed in the acquisition phase, goods orders is generated and logistics is ordered Single idiographic flow includes:
S701:Material requirement needed for importing, examination & verification forward purchasing supply of material inventory;
S702:Submit examination & verification;
S703:After examination & verification passes through, pre- shopping list is generated;
S704:According to order evaluation, supplier's logistics is carried out to sort by scoring height, carries out supply of material selection;
S705:Generate main order and confirm to record, including supplier determines to confirm with logistics provider, if supplier carries thing Stream, then be not required to logistics provider's confirmation;
S706:Examination & verification is submitted, judges whether to replace supplier and logistics provider;
S707:Supplier is confirmed after can supplying, and is submitted examination & verification, if the audit fails, is gone to S706, if examination & verification is logical Cross, carry out S708;
S708:Goods orders and logistics order are generated, including delivery, stock, delivery, the clearing of goods orders beat money, comment Valency and generation system data, the cargo collection of logistics order, deliver, sign for, settling accounts and beat money, evaluation and generation statistics.
The invention has the advantages that:
The green assembled architecture digitlization construct platform and its method of work of the present invention, with BIM and internet+, with Basis of the every relevant information data of construction-engineering project as model, carries out the foundation of buildings model, passes through digital information Real information possessed by analogue simulation building, has digitlization, visualization, harmony, simulation, optimization property and can go out The advantages of figure;Green assembled architecture digitlization construct platform includes Construction Project Management module, BIM modules, design management Module, purchasing management module and construction management module etc., the information data of each module stores in BIM, with digital information model As the basis of each construction project, carry out related work, can real-time update information, there is information share;
The green assembled architecture of the present invention digitizes construct platform to construction project unified planning, Uniting, can root Need according to architectural engineering, by the building structure component and common apparatus material of plant produced, transport on time to construction site, and Remote supervisory, control and management can be carried out to the overall process of more than ten of construction project site operation at the same time.Fully achieve mould Block design, industrialized production, prefabricated construction, intelligent management.
Brief description of the drawings
Fig. 1 is that the green assembled architecture of the present invention digitizes the composition schematic diagram of construct platform;
Fig. 2 is the overall process flow chart for the method for work that the green assembled architecture of the present invention digitizes construct platform;
Fig. 3 is the flow chart that the present invention carries out construction project project verification;
Fig. 4 is the flow chart that the present invention carries out construction project plans;
Fig. 5 is the flow chart that the present invention carries out construction project construction;
Fig. 6 is the flow chart that the present invention carries out construction project buying;
Fig. 7 is the membership flow chart of supplier of the present invention and/or logistics provider;
Fig. 8 is the membership flow chart of construction side and/or management side of the invention;
Fig. 9 is the flow table that construction project of the present invention generates goods orders and logistics order.
Embodiment
To make the technical problem to be solved in the present invention, technical solution and advantage clearer, below in conjunction with attached drawing and tool Body embodiment is described in detail.
On the one hand, the present invention provides a kind of green assembled architecture digitlization construct platform, as shown in Figure 1, including:
Construction Project Management module 1, for undertaking all construction project project verifications of platform, integrated management, construction project planning Design examination & verification, engineering open management of being completed, funds transfer, system information distribution and empowerment management;
BIM modules 2, for being responsible for construction project planning, design, establish architectural engineering relevant information data model, nonstandard The design of quasi-mode block, the foundation and maintenance of standard and modular database;
Design management module 3, for the typing of primary demand, planned design management, design document uploads, and design point becomes More, tell somebody what one's real intentions are file polling, design alteration inquiry and uploads bill of materials at design document inquiry;
Purchasing management module 4, for being needed to purchase building structure component, accessory, equipment and material according to architectural engineering, and is transported To construction site;
Construction management module 5, for long-range work progress management, to commencement of works, completion, construction speed, engineering material Service condition carries out remote management, transfers to construction party to undertake engineering safety responsibility, and the responsibility of engineering quality transfers to management side to undertake, By being audited to the construction speed data of construction party and the signature examination & verification of management side, control project progress, engineering material make With situation and change in the work situation.
The present invention with BIM and internet+, the base of model is used as using every relevant information data of construction-engineering project Plinth, carries out the foundation of buildings model, by real information possessed by digital information analogue simulation building, have digitlization, Visualization, harmony, simulation, optimization property and the advantages of figure can be gone out;Green assembled architecture digitizes construct platform bag Construction Project Management module, BIM modules, design management module, purchasing management module and construction management module etc. are included, each module Information data stores in BIM, using digital information model as the basis of each construction project, carries out related work, can be real-time Fresh information, has information share;
The green assembled architecture of the present invention digitizes construct platform to construction project unified planning, Uniting, can root Need according to architectural engineering, by the building structure component and common apparatus material of plant produced, transport on time to construction site, and Remote supervisory, control and management can be carried out to the overall process of more than ten of construction project site operation at the same time.Fully achieve mould Block design, industrialized production, prefabricated construction, intelligent management.
Specifically, in each module, Construction Project Management module is mainly used for construction project integrated management management and control, is to all The construction project signed a contract carries out the module of integrated management, and major regulators are led for decision-making layer and projects have been recognized Project manager that is fixed and authorizing;
Decision-making level leader can check all items, audit progress, appoint project manager, and project manager is responsible for establishment The project team, including design director, buying director, construction management director, and person is determined in the module;
Project manager mainly carries out all events period tracking management to the project appointed, and project manager passes through modules Middle corresponding management content, sends instruction, by each director other modules complete instruction after feedback result information, project manager into Row is supervised in overall process, and decision-making level leader can check all items, and project manager is managed, and decision-making is carried out to material items, The functions such as the statistical analysis access by system, understand company's whole project overview, carry on the work tactful and developing direction comprehensive Close decision-making.
Fed back by the information for digitizing each module on construct platform, Construction Project Management module can be to each project implementation Each stage carry out integrated management, meanwhile, inquired about by system interface and browsable arrive all items relevant information;
BIM modules mainly realize the visual design function, change the mode that tradition is carried out planar design by CAD, directly into Row 3 D stereo designs, and by importing modularization, standardized building structure component in BIM design softwares, is formed and is compiled with data The building structure component standards database (according to design requirement, also there is Non-standard database typing interface) of code, meanwhile, utilize BIM Existing traditional database is combined design in software, forms design document output, while the statistics carried using BIM softwares Function, can export the bill of quantities (module inventory, the bill of materials and equipment list etc.) with modules coding;
Purchasing management module, according to the geographical location in construction project location, is being supplied according to the procurement information obtained automatically Business's management system is answered according to delivery cycle, ability, price preferred supplier, and bids in the logistics company joined and chooses transport Business, delivered price send buying and transport instruction in setting range or after manual intervention.
Preferably, green assembled architecture digitlization construct platform further comprises:
Preliminary budget management module 6, for according to Budgetary Estimates, being responsible for the management of construction project covering price and control;Pass through Listed module type and number in design drawing, calculate the quantities of modules and carry out category column item (partial function by BIM modules are completed), comprehensive analysis, completion are each according to situations such as quota, raw material market price, labour cost, labor productivity The cost group valency of a module, and then determine the cost of a whole set of house and each house type;
In BIM module basis, during implementing management, corresponding preliminary budget can be chosen by building the quantity of module at any time By norm, the project cost of corresponding progress and final clearing are determined;
Supply chain and member management module 7, for being responsible for all kinds of members of supplier, logistics provider, builder and supervision side Management;Supply chain management module is using effective supply business (member) information management as core, for detailed programs with supplier's The commercial matters informations such as product price, class, location, availability are screened, cooperative relationship of identifying project, and are remembered by merchandising The information comprehensive managements such as record, performance, reach optimum management, reduce the purpose of cost;It is worth noting that, use supply chain and meeting Member management module premise be:Establish module, equipment and materials information database, supplier information database, contract information and confession Goods invoice price database, item information database;
Supply chain is a system for including multiple main bodys such as supplier, manufacturer, logistics provider, developer and client, Supply chain manages the various activities and mistake for just referring to whole supply chain system is planned, coordinates, operates, controls and optimized Journey, its target are can to send the correct product needed for customer according to correct quantity, quality and state in the correct time To correct place, and make totle drilling cost spent by this process minimum, it is clear that supply chain operation be one kind embody integration with The management model of Coordination, it is desirable to form member enterprise's Collaboration of supply chain system, tackle exterior market jointly Situation complicated and changeable, OEM OEM processings in China can be realized by supply chain, can meet different regions difference Weather conditions requirement, standardization, the production and processing of modular building structure component and deliverability;
Construction client manager module 8, including builder construction client manager module and supervision side's construction client's end pipe Module is managed, is instructed in due course reception system, work progress relevant information is gathered, is submitted after management confirms, meet system pair Supervision, management and the control of construction overall process;
Engineering Settlement module 9, for based on contract and final accounts, being responsible for Engineering Settlement;Engineering Settlement module comprehensive management is public Term of credit and the receipt and payment of related management functions contact fund are taken charge of, are connected to the instruction of preliminary budget module, according to purchasing management module, generally Budget module, project construction management module feedback information are checked, and are responsible for collection scheduled fun, final accounts money, client's payment for goods, is prompted Transfer payment engineering funds, equipment and materials money, subpackage money, deposit cash pledge, set-fee etc., Engineering Settlement module can separate cost tax, Valency tax adds up to.
Preferably, green assembled architecture digitlization construct platform further includes:
Module and equipment and materials management module 10, for carrying out data input to standardized building model and encoding, are realized Integrated management is carried out to each Modular building structure component, electromechanical equipment and material of typing BIM modules;
Online house-purchase module 11, for according to the house-purchase information to strike a bargain on the net, specifying builder member to be responsible for building nearby Make;
Financial management module 12, is inquired about for bank settlement flow, project finance;
Market tracking module 13, for market project management, track record is reported and audited, classification of the items is inquired about, is submitted a tender Management.
In the present invention, each functions of modules can be individually designed into corresponding submodule, modules it is specific Function, may refer to table 1:
Table 1:The feature list of modules
The function of Construction Project Management module 1 can include:Project information management, project contract management, project personnel's pipe Reason, project scheduling management, Project design management, preliminary budget management, Project Procurement Management, item construction management, financial settlement pipe Reason, Xiang Mingda management, quality safety management and project risk management, wherein:
Project information management can include the essential information of management project, and implementation project, entry item are created by typing personnel Mesh essential information, technical routine manager;Project contract management is mainly the contract for managing and being signed with Party A client, takes passages contract weight Information is wanted, while uploads contract sweep attachment;Project personnel's management is mainly project manager according to project situation allocated items power Limit to participant, there is provided typing, modification and query function;Project scheduling management formulates item for project manager according to project situation Mesh implementation plan, there is provided typing, upload, change, monitoring function;Project design management include checking the plan of design phase into Product is submitted in degree, and design;Preliminary budget management includes the destination file for checking that the preliminary budget stage submits, and the examination & verification budget stage carries The budget result file of friendship;Project Procurement Management includes checking procurement plan, purchase order, check the selected supplier of buying and Logistics provider's information, audits procurement plan;Item construction management includes construction speed result, procedure file is checked;Financial settlement pipe Reason includes financial settlement inquiry, project clearing, final accounts examination & verification, Payment Review, gathering initiation;Xiang Mingda management, which includes checking, to be applied Work changes and design alteration request record, examination & verification change request;Quality safety management includes project's earlier stage, design, construction etc. no The filing and inquiry of same stage quality, secure file;Project risk management includes checking risk alarm, same in Project Process Repeatedly the audit fails for one record, progress node early warning etc..
The function of BIM modules 2 can include:Export plug-in unit, race's library management plug-in unit, progress display and the virtualization of quantities Assembling, wherein:
The export plug-in unit of quantities can include by secondary development meet in reduced model be based on module numbering, material, Size, weight, density, volume, the bill of quantities of quantity;Progress display mainly quantifies tracking construction speed, passes through construction The builder's diary record of square typing, obtains the positions of materials numbering on corresponding construction drawing, the module information of position is corresponded to The three-dimensional data model of monolithic architecture is shown.
The function of design management module 3 can include:Primary demand typing, planned design management, design document are uploaded, set Count Status Change, file polling of telling somebody what one's real intentions are, design alteration inquiry, design document inquiry and upload bill of materials, wherein:
Primary demand typing can include Design Manager by the essential information typing of design, upload design contract file;If Meter planning management includes making a plan, and change of plan and three functions is checked to project overall progress, so as to according to project situation At any time design phase actual progress is adjusted and grasps to plan;Design document, which uploads, to be included providing in design process on document Pass the product such as function, the drawing of management design overall process;In design point change mainly design review process, rank is designed The Status Change of section;File polling of telling somebody what one's real intentions are can check the document that the design that builder uploads is told somebody what one's real intentions are at any time;Design alteration is inquired about Including for, it is necessary to the record of make a change is managed, the detailed of each design alteration can be inquired about in design review process Information;Design document inquiry can check document all in the design process that designer uploads at any time;Upload bill of materials The function of being uploaded including providing bill of materials.
The function of purchasing management module 4 can include:Management of purchasing plan, forward purchasing supply of material inventory management, pre- shopping list Management and purchase order management, wherein:
Management of purchasing plan can enter the management of purchasing plan page including Merchandising Manager, can check and be uploaded by builder Material plan for cargo arrival, formulate procurement plan according to material plan for cargo arrival, while submit to project manager's examination & verification, treat project manager After examination & verification passes through, procurement plan is synchronized in project corporate plan;Forward purchasing supply of material inventory management is mainly used for procurement staff and takes After bill of materials, the procurement method of marker material is that platform buying or ground are adopted, it is necessary to submit Merchandising Manager to examine after the completion of mark Core;Pre- shopping list management is mainly used for procurement staff according to forward purchasing supply of material inventory, recommends supplier and thing automatically by system Business is flowed, after procurement staff confirms availability and logistics capability, generates pre- shopping list, submits Merchandising Manager's examination & verification;Buying Order management mainly manages the order issued with supplier, logistics provider.Each Status Change of system meeting order.If order Abnormal state, can audit abnormal conditions in this module, and initiate filling mining order.When order normal termination, procurement staff needs To be that supplier and logistics provider evaluate, foundation is provided for later supplier logistics provider selection.
The function of construction management module 5 can include:Construction project management, work progress management, project under construction are changed, applied Work completion management etc., wherein:
Construction project management is mainly supported to create construction sub-project, and uploads corresponding subcontract;Work progress Management includes construction manager the various documents in work progress and application is examined, ensure construction speed be normally carried out and Construction manager grasps construction speed;The Xiang Mingda application that project under construction change is proposed primarily with respect to builder, by management After examination & verification, it is submitted at construction manager and is audited again, so that construction manager more accurately holds asking appeared in construction Topic, is solved in time;Construction, which is completed, to be managed, and can check what builder uploaded in part of being completed《Transfer maintenance record》With 《Property is told somebody what one's real intentions are record》, to builder propose concluding a research item application examine, can check document all in work progress.
The function of preliminary budget management module 6 can include:Quota management, merchandise module library management, budgetary estimate management, budget pipe Reason and finance, wherein:
Quota management can include merchandise control and store keeping, can increase newly, change;Merchandise module library management is pair The required comprehensive unit price analytical table of preliminary budget is managed, can be to the freight, commodity price, talent of each module The expenses such as machine are modified;Budgetary estimate management is basis《Preliminary design document》The budgetary estimate of carry out project;Budget management is basis《Work Journey design documentation》The detail budget of carry out project, calculates for Xiang Mingda increase and decrease item;Finance mainly receive quantities Money is audited, and checks the payment information of project.
The function of supply chain and member management module 7 can include:Merchandise control, supplier management, logistics provider manage, build Make business's management, supervision side's management, supplier's logentry, logistics provider's logentry;
Construction client manager module 8 can include showing towards the site construction management module of builder and towards supervision side Field construction management module, the function towards the site construction management module of builder include:Project under construction maintenance of information, construction meter Draw management, construction material management, work progress management, construction project management and construction completion management;Applied towards supervision side scene The function of work management module includes:Planned management of construction, construction material are checked, work progress management, project under construction change, order Receipt control and construction, which are completed, to be managed;
The function of financial management module 12 can include:Payment process processing, gathering flow processing and project finance inquiry;
The function of market tracking module 13 can include:Market project management, track record are reported and audited, classification of the items And bidding management.
The present invention using CAD design, can draw in accordance with the regulation modulus of green assembled architecture, form 3 D stereo Concrete graphic, fully coordinates, optimization design by BIM, goes out figure after approval, reaches the standard grade;
On the basis of 3 D stereo concrete graphic, formed agent structure, building enclosure and it is all building structure, component and The bill of materials, and nonstandard modules figure;Nonstandard modules design is carried out, and encodes, name, inputs nonstandard module database; OEM client is issued by purchasing system, signs OEM contracts;
Transfer and generated comprising code, title, specification and fabrication drawing in building, construction standard module database, Purchasing management module obtains automatically;Transfer and generated comprising code, title and specification in construction material (unified purchase) lane database, adopted Purchase management module obtains automatically;Unified purchase material refers mainly to architecture noumenon material requested, such as prevents fires, keeps the temperature, waterproof material.Water (warm) tubing, pipe fitting, electric wire, switch, cement, sandstone be adopt material, can be included in construction cost, tubing, pipe fitting, electricity Line, formed after purchasing scope also can unified purchase for switch;According to equipment, the CAD diagram paper and 3D models of electric specialty, obtain design and select All devices, specification, the model of material, purchasing management module obtains automatically;Purchasing management module is adopted according to what is obtained automatically Information is purchased, the geographical location according to construction project location;
In supply chain and member management module 7 according to delivery cycle, ability, price preferred supplier, and joining Logistics company, which is bidded, chooses forwarding agent, and delivered price sends buying and transport instruction in setting range or after manual intervention;Standard After change module, equipment and materials transport construction project construction site to, storage is scanned after institutional recipient is qualified by inspection, and feed back arrival Information, arrival information are obtained by preliminary budget management module, Construction Project Management module and financial management module at the same time;Construction project Management module is according to field basic acceptance information, the mark in construction project total figure, birds-eye view (or building site scene air map), figure Paper scanning input system, indicates design, construction, management and person in charge of acceptance;
Construction Project Management module 1 is according to standardized module, equipment and unified purchase material arrival information, by construction project to visitor Family end sends the instruction that goes into operation, and scene provides list typing construction note by system, indicates and opens time of accomplishment, work consumption, construction and prison Person liable is managed, every information for being related to cost variation must be audited through the department of project management, confirmed after approval in advance;Project management Portion participates in final acceptance of construction, and signs associated documents, scanning record system;
Preliminary budget management module 6 based on contract and budget, standardized module, equipment materials supply and the arrival that system obtains Material official fixed price information etc. is adopted on information, project management system cost transition information, the ground in construction site location, is responsible for pre- Calculate, progress is adjusted and budget needed for the completion of projects;
Financial management module 12 is connected to the instruction of preliminary budget system, according to purchasing system, arrival information, project management system Feedback information is checked, and is responsible for collection scheduled fun, final accounts money, transfer payment engineering funds, equipment and materials money, set-fee, the expenses of taxation etc.;
Construction client manager module 8, can be according to live function setting.
The operation of the green assembled architecture digitlization construct platform of the present invention also needs to production base, and production base is general Implement license assignee, the agent structure part product of main production carrying core technology property right, in assembled architecture work for technology As core main body structure supplier in journey.
In addition, green assembled architecture digitlization construct platform preferably uses member system, member includes supplier, transport Business, builder and supervision side, member are divided into A classes member, Sa classes member, Sb classes member, Ba classes member, Bb classes member, Bc class meetings Member, F classes member and J class members, wherein:
A classes member is VIP member, implements license assignee for technology, produces core component;Sa classes member for standardization, Modularization structure component OEM OEM processing manufacturers;Sb classes member passes through equipment, material supplier for construction of structures;Ba class members For the comprehensive building enterprise containing finishing;Bb classes member is the common buildings enterprise without finishing or natural person;Bc class members are Decoration company;F classes member is national logistics transportation company;J classes member is supervision companies.
On the other hand, as shown in Fig. 2, the present invention also provides a kind of above-mentioned green assembled architecture to digitize construct platform Method of work, overall process includes successively:Project tracking stage, project implementation phase, the design phase, the preliminary budget stage, adopt Purchase stage, construction stage and concluding a research item stage;
Wherein, the project tracking stage after tracking project, the successful project bidding mainly including signing a contract;
Project implementation phase mainly includes project verification establishment project and personnel assigned;
Design phase mainly includes Preliminary design and construction drawing design;
The preliminary budget stage is mainly included in the budgetary estimate after the completion of Preliminary design and the budget after the completion of construction drawing design;
Construction stage is mainly included in construction plan, work progress, construction negotiation and completion after the completion of construction drawing design Check and accept, wherein, the construction negotiation stage can be designed change;
Acquisition phase is mainly included in procurement plan and executive plan after the completion of construction drawing design and construction plan;
The concluding a research item stage is mainly included in the financial final accounts after the completion of final acceptance of construction.
Further, as shown in figure 3, the idiographic flow of project implementation phase includes:
S101:Establishment project, typing essential information and technical routine manager;
S102:Signal auditing is carried out, if signal auditing is not by going to S101, if signal auditing is by carrying out S103;
S103:Project planning, is carried out at the same time contract inputting, personnel assignment and planning, and project verification terminates.
Further, as shown in figure 4, the idiographic flow of design phase includes:
S104:Typing data early period;
S105:Examination & verification is submitted, if the audit fails, goes to S104, if examination & verification passes through, carries out S106;
S106:Judge whether to require supplementation with other information, if so, S104 is gone to, if it is not, carrying out S107;
S107:Conceptual design;
S108:Examination & verification, after examination & verification passes through, carries out Preliminary design;
S109:Audit again, after examination & verification passes through, form preliminary project;
S110:Report declaration to a higher authorities for approval;
S111:Examination & verification is submitted, if examination & verification passes through, carries out S112;
S112:Judge whether to require supplementation with other information, if it is not, design terminates.
Preferably, as shown in figure 5, the idiographic flow bag of construction stage (construction stage can be performed in the design process) Include:
S201:Project under construction typing, including construction party contract inputting and the contract inputting of management side;
S202:Construction party initiates to examine according to data;
S203:Audit management side;
S204:Construction manager audits;
S205:Judge whether project terminates, if not terminating, go to S202, if terminating, carry out concluding a research item application, construction terminates.
Preferably, as shown in fig. 6, the tool of acquisition phase (acquisition phase can be since S201 projects under construction be created and finished) Body flow includes:
S301:Forward purchasing supply of material inventory is imported according to bill of quantities and its corresponding sub-project;
S302:Form material list;
S303:Mark procurement method;
S304:Examination & verification is submitted, if the audit fails, content is changed, resubmits examination & verification, if examination & verification passes through, generation is pre- Shopping list;
S305:Carry out supplier and/or logistics provider selects flow;
S306:Merchandising Manager audits;
S307:Project manager audits, and by rear, execution of order flow, completes buying.
As a modification of the present invention, green assembled architecture digitlization construct platform uses member system, and member includes Supplier, logistics provider, construction side and management side, wherein:
As shown in fig. 7, the membership flow of supplier and/or logistics provider include:
S501:Supplier and/or the application membership of forwarding agent website;
S502:Etc. pending, if the audit fails, S501 is gone to, if examination & verification passes through, carries out S503;
S503:Sign a contract under line, it should be noted that S501, S502 can not be performed sometimes and directly perform S503;
S504:Typing supplier and/or carrier information;
S505:Upload contract information;
S506:Distribution account number cipher is with logging in port;
S507:The material information of typing supplier and the logistics price of forwarding agent;
S508:Signal auditing is carried out, if the audit fails, goes to S504, if examination & verification passes through, supplier and/or logistics provider Membership is completed;
As shown in figure 8, the membership flow of construction side and/or management side includes:
S601:Sign a contract;
S602:Typing construction side and/or management side's information, including basic information, scale, qualification and numbering;
S603:Typing contract information simultaneously uploads contract;
S604:Signal auditing is carried out, if the audit fails, goes to S602, examination & verification passes through, and construction side/management side's membership is complete Into.
In the present invention, as shown in figure 9, generation goods orders and logistics order are also needed in the acquisition phase, as shown in figure 9, The idiographic flow of generation goods orders and logistics order includes:
S701:Material requirement needed for importing, examination & verification forward purchasing supply of material inventory;
S702:Submit examination & verification;
S703:After examination & verification passes through, pre- shopping list is generated;
S704:According to order evaluation, supplier's logistics is carried out to sort by scoring height, carries out supply of material selection;
S705:Generate main order and confirm to record, including supplier determines to confirm with logistics provider, if supplier carries thing Stream, then be not required to logistics provider's confirmation;
S706:Examination & verification is submitted, judges whether to replace supplier and logistics provider;
S707:Supplier is confirmed after can supplying, and is submitted examination & verification, if the audit fails, is gone to S706, if examination & verification is logical Cross, carry out S708;
S708:Goods orders and logistics order are generated, including delivery, stock, delivery, the clearing of goods orders beat money, comment Valency and generation system data, the cargo collection of logistics order, deliver, sign for, settling accounts and beat money, evaluation and generation statistics.
The above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, without departing from the principles of the present invention, some improvements and modifications can also be made, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

  1. A kind of 1. green assembled architecture digitlization construct platform, it is characterised in that including:
    Construction Project Management module, for undertaking all construction project project verifications of platform, integrated management, programming design of engineering construction are examined Core, engineering open management of being completed, funds transfer, system information distribution and empowerment management;
    BIM modules, for being responsible for construction project planning, design, establish architectural engineering relevant information data model, nonstandard modules Design, the foundation and maintenance of standard and modular database;
    Design management module, for the typing of primary demand, planned design management, design document uploads, and design point change, is handed over Bottom file polling, design alteration inquiry, design document inquiry and upload bill of materials;
    Purchasing management module, for being needed to purchase building structure component, accessory, equipment and material according to architectural engineering, and transport to Construction site;
    Construction management module, for long-range work progress management, feelings are used to commencement of works, completion, construction speed, engineering material Condition carries out remote management, transfers to construction party to undertake engineering safety responsibility, the responsibility of engineering quality transfers to management side to undertake, by right Construction party and the construction speed data of management side's signature examination & verification are audited, control project progress, the service condition of engineering material And change in the work situation.
  2. 2. green assembled architecture digitlization construct platform according to claim 1, it is characterised in that the green assembling Formula building digitlization construct platform further comprises:
    Preliminary budget management module, for according to Budgetary Estimates, being responsible for the management of construction project covering price and control;
    Supply chain and member management module, for being responsible for all kinds of member managements of supplier, logistics provider, builder and supervision side;
    Construction client manager module, including builder construction client manager module and supervision side's construction client-side management mould Block, instructs in due course reception system, gathers work progress relevant information, is submitted after management confirms, meets system to construction Supervision, management and the control of overall process;
    Engineering Settlement module, for based on contract and final accounts, being responsible for Engineering Settlement.
  3. 3. green assembled architecture digitlization construct platform according to claim 2, it is characterised in that the green assembling Formula building digitlization construct platform further includes:
    Module and equipment and materials management module, for carrying out data input to standardized building model and encoding, are realized to having recorded The each Modular building structure component, electromechanical equipment and material for entering BIM modules carry out integrated management;
    Online house-purchase module, for according to the house-purchase information to strike a bargain on the net, specifying builder member to be responsible for construction nearby;
    Financial management module, is inquired about for bank settlement flow, project finance;
    Market tracking module, for market project management, track record is reported and audited, classification of the items is inquired about, bidding management.
  4. 4. the method for work of any green assembled architecture digitlization construct platforms of claim 1-3, it is characterised in that Overall process includes successively:Project tracking stage, project implementation phase, design phase, preliminary budget stage, acquisition phase, construction Stage and concluding a research item stage;
    Wherein, the project tracking stage after tracking project, the successful project bidding mainly including signing a contract;
    Project implementation phase mainly includes project verification establishment project and personnel assigned;
    Design phase mainly includes Preliminary design and construction drawing design;
    The preliminary budget stage is mainly included in the budgetary estimate after the completion of Preliminary design and the budget after the completion of construction drawing design;
    Construction stage is mainly included in construction plan, work progress, construction negotiation and final acceptance of construction after the completion of construction drawing design;
    Acquisition phase is mainly included in procurement plan and executive plan after the completion of construction drawing design and construction plan;
    The concluding a research item stage is mainly included in the financial final accounts after the completion of final acceptance of construction.
  5. 5. the method for work of green assembled architecture digitlization construct platform according to claim 4, it is characterised in that item The idiographic flow of mesh implementation phase includes:
    S101:Establishment project, typing essential information and technical routine manager;
    S102:Signal auditing is carried out, if signal auditing is not by going to S101, if signal auditing is by carrying out S103;
    S103:Project planning, is carried out at the same time contract inputting, personnel assignment and planning, and project verification terminates.
  6. 6. the method for work of green assembled architecture digitlization construct platform according to claim 4, it is characterised in that set The idiographic flow in meter stage includes:
    S104:Typing data early period;
    S105:Examination & verification is submitted, if the audit fails, goes to S104, if examination & verification passes through, carries out S106;
    S106:Judge whether to require supplementation with other information, if so, S104 is gone to, if it is not, carrying out S107;
    S107:Conceptual design;
    S108:Examination & verification, after examination & verification passes through, carries out Preliminary design;
    S109:Audit again, after examination & verification passes through, form preliminary project;
    S110:Report declaration to a higher authorities for approval;
    S111:Examination & verification is submitted, if examination & verification passes through, carries out S112;
    S112:Judge whether to require supplementation with other information, if it is not, design terminates.
  7. 7. the method for work of green assembled architecture digitlization construct platform according to claim 4, it is characterised in that apply The idiographic flow in work stage includes:
    S201:Project under construction typing, including construction party contract inputting and the contract inputting of management side;
    S202:Construction party initiates to examine according to data;
    S203:Audit management side;
    S204:Construction manager audits;
    S205:Judge whether project terminates, if not terminating, go to S202, if terminating, carry out concluding a research item application, construction terminates.
  8. 8. the method for work of green assembled architecture digitlization construct platform according to claim 4, it is characterised in that adopt The idiographic flow in purchase stage includes:
    S301:Forward purchasing supply of material inventory is imported according to bill of quantities and its corresponding sub-project;
    S302:Form material list;
    S303:Mark procurement method;
    S304:Examination & verification is submitted, if the audit fails, content is changed, resubmits examination & verification, if examination & verification passes through, generates pre- buying Inventory;
    S305:Carry out supplier and/or logistics provider selects flow;
    S306:Merchandising Manager audits;
    S307:Project manager audits, and by rear, execution of order flow, completes buying.
  9. 9. the method for work of green assembled architecture digitlization construct platform according to claim 4, it is characterised in that green Color assembled architecture digitlization construct platform uses member system, and member includes supplier, logistics provider, construction side and management side, its In:
    The membership flow of supplier and/or logistics provider include:
    S501:Supplier and/or the application membership of forwarding agent website;
    S502:Etc. pending, if the audit fails, S501 is gone to, if examination & verification passes through, carries out S503;
    S503:Sign a contract under line;
    S504:Typing supplier and/or carrier information;
    S505:Upload contract information;
    S506:Distribution account number cipher is with logging in port;
    S507:The material information of typing supplier and the logistics price of forwarding agent;
    S508:Signal auditing is carried out, if the audit fails, goes to S504, if examination & verification passes through, supplier and/or logistics provider's membership Complete;
    The membership flow of construction side and/or management side includes:
    S601:Sign a contract;
    S602:Typing construction side and/or management side's information, including basic information, scale, qualification and numbering;
    S603:Typing contract information simultaneously uploads contract;
    S604:Signal auditing is carried out, if the audit fails, goes to S602, examination & verification passes through, and construction side/management side's membership is completed.
  10. 10. the method for work of green assembled architecture digitlization construct platform according to claim 8, it is characterised in that Generation goods orders and logistics order are also needed in acquisition phase, generating the idiographic flow of goods orders and logistics order includes:
    S701:Material requirement needed for importing, examination & verification forward purchasing supply of material inventory;
    S702:Submit examination & verification;
    S703:After examination & verification passes through, pre- shopping list is generated;
    S704:According to order evaluation, supplier's logistics is carried out to sort by scoring height, carries out supply of material selection;
    S705:Generate main order and confirm to record, including supplier determines to confirm with logistics provider, if supplier carries logistics, Then it is not required to logistics provider's confirmation;
    S706:Examination & verification is submitted, judges whether to replace supplier and logistics provider;
    S707:Supplier is confirmed after can supplying, and is submitted examination & verification, if the audit fails, is gone to S706, if examination & verification passes through, into Row S708;
    S708:Generate goods orders and logistics order, including delivery, stock, delivery, the clearing of goods orders beat money, evaluate and Generation system data, the cargo collection of logistics order, deliver, sign for, settling accounts and beat money, evaluation and generation statistics.
CN201711172627.5A 2017-11-22 2017-11-22 Green assembled architecture digitlization construct platform and its method of work Pending CN107958328A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711172627.5A CN107958328A (en) 2017-11-22 2017-11-22 Green assembled architecture digitlization construct platform and its method of work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711172627.5A CN107958328A (en) 2017-11-22 2017-11-22 Green assembled architecture digitlization construct platform and its method of work

Publications (1)

Publication Number Publication Date
CN107958328A true CN107958328A (en) 2018-04-24

Family

ID=61963800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711172627.5A Pending CN107958328A (en) 2017-11-22 2017-11-22 Green assembled architecture digitlization construct platform and its method of work

Country Status (1)

Country Link
CN (1) CN107958328A (en)

Cited By (47)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108846644A (en) * 2018-06-22 2018-11-20 中船第九设计研究院工程有限公司 A kind of integrated emulation technology, collaborative work, information management and project management managing and control system
CN109064041A (en) * 2018-08-09 2018-12-21 西安市恒兴市政工程公司 A kind of project in construction management system and method
CN109087193A (en) * 2018-07-24 2018-12-25 广东金熙商业建设股份有限公司 The innovative financial service synthesis system of the Internet converged wisdom scene
CN109118161A (en) * 2018-07-03 2019-01-01 武汉鼎筑腾技术有限公司 A kind of construction supply chain SAAS management method and system
CN109191577A (en) * 2018-10-22 2019-01-11 杭州睿兴栋宇建筑科技有限公司 A kind of distribution BIM collaborative platform
CN109300187A (en) * 2018-09-27 2019-02-01 安捷睿(厦门)机器人有限公司 A kind of finishing management system, method and server
CN109409660A (en) * 2018-09-19 2019-03-01 北京天元创新科技有限公司 Business delivery management system and method
CN109447481A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of live cost monitoring system and method based on threedimensional model
CN109492876A (en) * 2018-10-15 2019-03-19 鼎宸建设管理有限公司 A kind of assembled architecture production and construction management module information system
CN109583015A (en) * 2018-10-19 2019-04-05 中铁第四勘察设计院集团有限公司 A kind of railway passenger goods traffic equipment overall process aided design system
CN109598409A (en) * 2018-10-30 2019-04-09 平安科技(深圳)有限公司 A kind of computer room installation and deployment method, system and readable storage medium storing program for executing
CN109767058A (en) * 2018-11-29 2019-05-17 耿思宁 A kind of construction project administration system
CN109784868A (en) * 2019-01-29 2019-05-21 杭州凌望建筑科技有限公司 BIM multidimensional mould based on Android examines platform
CN109801040A (en) * 2019-01-29 2019-05-24 杭州凌望建筑科技有限公司 Multidimensional mould based on BIM examines design collaboration platform
CN109886793A (en) * 2018-12-28 2019-06-14 金螳螂家装电子商务(苏州)有限公司 A kind of integrated system of supply platform chain and financial platform
CN109919499A (en) * 2019-03-12 2019-06-21 佛山市均林人防工程有限公司 A kind of project management method
CN109978501A (en) * 2019-03-20 2019-07-05 星杰云家居科技(上海)有限公司 A kind of user's scheme construction material audit quotation system
CN110428236A (en) * 2019-08-15 2019-11-08 宁夏信友监理咨询管理股份有限公司 A kind of communication engineering construction whole process engineering consulting management system
CN110598298A (en) * 2019-09-04 2019-12-20 北京华科软科技有限公司 Design and construction integrated visual management working platform based on BIM
CN110689316A (en) * 2019-09-06 2020-01-14 北京创艺汇文化传播有限公司 Catering construction project generation method and system
CN110728422A (en) * 2019-09-03 2020-01-24 广州轨道交通建设监理有限公司 Building information model, method, device and settlement system for construction project
CN110880096A (en) * 2019-11-20 2020-03-13 广西越知网络股份有限公司 Multi-party cooperative office system for constructional engineering
CN110910092A (en) * 2019-11-21 2020-03-24 四川高路交通信息工程有限公司 Highway construction information management platform
CN111738695A (en) * 2020-06-29 2020-10-02 中材建设有限公司 Engineering project material management system
CN111985893A (en) * 2020-08-15 2020-11-24 武汉华胜工程建设科技有限公司 Building engineering project material entry auditing method, intelligent terminal and storage medium
CN112150109A (en) * 2020-09-17 2020-12-29 水发规划建设有限公司 Water conservancy design construction management method and system for EPC general contract project
CN112163747A (en) * 2020-09-18 2021-01-01 华航环境发展有限公司 Construction engineering project quality management system
CN112232683A (en) * 2020-10-20 2021-01-15 中国能源建设集团浙江省电力设计院有限公司 Comprehensive pipe gallery full-period construction management system based on BIM
CN112241849A (en) * 2020-10-27 2021-01-19 陕西交建云数据科技有限公司 Project collaboration method for highway engineering designer
CN112348453A (en) * 2020-07-13 2021-02-09 南通四建集团有限公司 Material purchasing management method, management platform and management system based on BIM
CN112411895A (en) * 2020-12-16 2021-02-26 上海恪耐新材料科技有限公司 Preparation method of combined roof structure
CN112632650A (en) * 2020-12-18 2021-04-09 华荣科技股份有限公司 Intelligent design system and method for nonstandard explosion-proof electric appliance product
CN112862341A (en) * 2021-02-25 2021-05-28 中铁一局集团有限公司 Project cost management system
CN113012000A (en) * 2021-04-20 2021-06-22 重庆大学 BIM-based intelligent management method and system for assembly type building construction
CN113128973A (en) * 2021-04-28 2021-07-16 天津智中新窗业有限公司 Intelligent production method and device for building matching product and electronic information platform
CN113128974A (en) * 2021-04-28 2021-07-16 天津智中新窗业有限公司 Intelligent progress control method and device for building matching product and electronic information platform
CN113222405A (en) * 2021-05-11 2021-08-06 高锦红 On-line management and control platform for daily work of construction industry practitioners
CN113379369A (en) * 2021-05-14 2021-09-10 南京智慧建筑研究院有限公司 Full life cycle's management system based on wisdom building
CN113570430A (en) * 2021-07-26 2021-10-29 北京京东乾石科技有限公司 Cooperative feedback method, device, equipment and computer readable medium for purchase information
CN113743065A (en) * 2021-09-02 2021-12-03 三一筑工科技股份有限公司 Construction management method of building component, engineering data generation method and device
CN114201805A (en) * 2021-12-21 2022-03-18 悉图建筑设计(上海)有限公司 Building project design software system
CN114358748A (en) * 2022-03-17 2022-04-15 武汉法正信信息技术有限公司 BIM-based engineering construction informatization management method and device
CN114707216A (en) * 2022-04-02 2022-07-05 深圳市华艺阳光建设科技集团有限公司 Architectural decoration engineering management system based on BIM technology
CN115600306A (en) * 2022-11-28 2023-01-13 四川省建筑设计研究院有限公司(Cn) Assembly rate calculation platform for assembly type building based on IFC model
CN116451979A (en) * 2023-06-15 2023-07-18 河北建工集团有限责任公司 Intelligent construction integrated collaboration platform and method based on artificial intelligence
CN116739530A (en) * 2023-08-08 2023-09-12 国网浙江省电力有限公司宁波供电公司 Intelligent settlement method and settlement device for power grid materials
CN117852845A (en) * 2024-03-07 2024-04-09 中建科技集团有限公司 Visual management method and visual management system for building supply chain

Cited By (54)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108846644A (en) * 2018-06-22 2018-11-20 中船第九设计研究院工程有限公司 A kind of integrated emulation technology, collaborative work, information management and project management managing and control system
CN109118161A (en) * 2018-07-03 2019-01-01 武汉鼎筑腾技术有限公司 A kind of construction supply chain SAAS management method and system
CN109118161B (en) * 2018-07-03 2022-05-20 武汉筑链科技有限公司 SAAS management method and system for supply chain in construction industry
CN109087193A (en) * 2018-07-24 2018-12-25 广东金熙商业建设股份有限公司 The innovative financial service synthesis system of the Internet converged wisdom scene
CN109064041A (en) * 2018-08-09 2018-12-21 西安市恒兴市政工程公司 A kind of project in construction management system and method
CN109409660A (en) * 2018-09-19 2019-03-01 北京天元创新科技有限公司 Business delivery management system and method
CN109300187A (en) * 2018-09-27 2019-02-01 安捷睿(厦门)机器人有限公司 A kind of finishing management system, method and server
CN109300187B (en) * 2018-09-27 2022-11-25 安捷睿(厦门)机器人有限公司 Decoration management system, method and server
CN109492876A (en) * 2018-10-15 2019-03-19 鼎宸建设管理有限公司 A kind of assembled architecture production and construction management module information system
CN109583015A (en) * 2018-10-19 2019-04-05 中铁第四勘察设计院集团有限公司 A kind of railway passenger goods traffic equipment overall process aided design system
CN109583015B (en) * 2018-10-19 2023-05-19 中铁第四勘察设计院集团有限公司 Whole process aided design system of railway passenger freight equipment
CN109191577A (en) * 2018-10-22 2019-01-11 杭州睿兴栋宇建筑科技有限公司 A kind of distribution BIM collaborative platform
CN109598409A (en) * 2018-10-30 2019-04-09 平安科技(深圳)有限公司 A kind of computer room installation and deployment method, system and readable storage medium storing program for executing
CN109447481A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of live cost monitoring system and method based on threedimensional model
CN109767058A (en) * 2018-11-29 2019-05-17 耿思宁 A kind of construction project administration system
CN109886793A (en) * 2018-12-28 2019-06-14 金螳螂家装电子商务(苏州)有限公司 A kind of integrated system of supply platform chain and financial platform
CN109784868A (en) * 2019-01-29 2019-05-21 杭州凌望建筑科技有限公司 BIM multidimensional mould based on Android examines platform
CN109801040A (en) * 2019-01-29 2019-05-24 杭州凌望建筑科技有限公司 Multidimensional mould based on BIM examines design collaboration platform
CN109919499A (en) * 2019-03-12 2019-06-21 佛山市均林人防工程有限公司 A kind of project management method
CN109978501A (en) * 2019-03-20 2019-07-05 星杰云家居科技(上海)有限公司 A kind of user's scheme construction material audit quotation system
CN110428236A (en) * 2019-08-15 2019-11-08 宁夏信友监理咨询管理股份有限公司 A kind of communication engineering construction whole process engineering consulting management system
CN110728422A (en) * 2019-09-03 2020-01-24 广州轨道交通建设监理有限公司 Building information model, method, device and settlement system for construction project
CN110598298A (en) * 2019-09-04 2019-12-20 北京华科软科技有限公司 Design and construction integrated visual management working platform based on BIM
CN110689316A (en) * 2019-09-06 2020-01-14 北京创艺汇文化传播有限公司 Catering construction project generation method and system
CN110880096A (en) * 2019-11-20 2020-03-13 广西越知网络股份有限公司 Multi-party cooperative office system for constructional engineering
CN110880096B (en) * 2019-11-20 2023-10-31 广西越知网络股份有限公司 Multi-party collaborative office system for building engineering
CN110910092A (en) * 2019-11-21 2020-03-24 四川高路交通信息工程有限公司 Highway construction information management platform
CN111738695A (en) * 2020-06-29 2020-10-02 中材建设有限公司 Engineering project material management system
CN112348453A (en) * 2020-07-13 2021-02-09 南通四建集团有限公司 Material purchasing management method, management platform and management system based on BIM
CN111985893A (en) * 2020-08-15 2020-11-24 武汉华胜工程建设科技有限公司 Building engineering project material entry auditing method, intelligent terminal and storage medium
CN112150109A (en) * 2020-09-17 2020-12-29 水发规划建设有限公司 Water conservancy design construction management method and system for EPC general contract project
CN112163747A (en) * 2020-09-18 2021-01-01 华航环境发展有限公司 Construction engineering project quality management system
CN112232683A (en) * 2020-10-20 2021-01-15 中国能源建设集团浙江省电力设计院有限公司 Comprehensive pipe gallery full-period construction management system based on BIM
CN112241849A (en) * 2020-10-27 2021-01-19 陕西交建云数据科技有限公司 Project collaboration method for highway engineering designer
CN112411895A (en) * 2020-12-16 2021-02-26 上海恪耐新材料科技有限公司 Preparation method of combined roof structure
CN112632650A (en) * 2020-12-18 2021-04-09 华荣科技股份有限公司 Intelligent design system and method for nonstandard explosion-proof electric appliance product
CN112632650B (en) * 2020-12-18 2023-02-10 华荣科技股份有限公司 Intelligent design system and method for nonstandard explosion-proof electric appliance product
CN112862341A (en) * 2021-02-25 2021-05-28 中铁一局集团有限公司 Project cost management system
CN113012000A (en) * 2021-04-20 2021-06-22 重庆大学 BIM-based intelligent management method and system for assembly type building construction
CN113128973A (en) * 2021-04-28 2021-07-16 天津智中新窗业有限公司 Intelligent production method and device for building matching product and electronic information platform
CN113128974A (en) * 2021-04-28 2021-07-16 天津智中新窗业有限公司 Intelligent progress control method and device for building matching product and electronic information platform
CN113222405A (en) * 2021-05-11 2021-08-06 高锦红 On-line management and control platform for daily work of construction industry practitioners
CN113379369A (en) * 2021-05-14 2021-09-10 南京智慧建筑研究院有限公司 Full life cycle's management system based on wisdom building
CN113570430A (en) * 2021-07-26 2021-10-29 北京京东乾石科技有限公司 Cooperative feedback method, device, equipment and computer readable medium for purchase information
CN113743065A (en) * 2021-09-02 2021-12-03 三一筑工科技股份有限公司 Construction management method of building component, engineering data generation method and device
CN114201805A (en) * 2021-12-21 2022-03-18 悉图建筑设计(上海)有限公司 Building project design software system
CN114358748A (en) * 2022-03-17 2022-04-15 武汉法正信信息技术有限公司 BIM-based engineering construction informatization management method and device
CN114707216A (en) * 2022-04-02 2022-07-05 深圳市华艺阳光建设科技集团有限公司 Architectural decoration engineering management system based on BIM technology
CN115600306A (en) * 2022-11-28 2023-01-13 四川省建筑设计研究院有限公司(Cn) Assembly rate calculation platform for assembly type building based on IFC model
CN116451979A (en) * 2023-06-15 2023-07-18 河北建工集团有限责任公司 Intelligent construction integrated collaboration platform and method based on artificial intelligence
CN116451979B (en) * 2023-06-15 2023-08-18 河北建工集团有限责任公司 Intelligent construction integrated collaboration platform and method based on artificial intelligence
CN116739530A (en) * 2023-08-08 2023-09-12 国网浙江省电力有限公司宁波供电公司 Intelligent settlement method and settlement device for power grid materials
CN116739530B (en) * 2023-08-08 2023-12-29 国网浙江省电力有限公司宁波供电公司 Intelligent settlement method and settlement device for power grid materials
CN117852845A (en) * 2024-03-07 2024-04-09 中建科技集团有限公司 Visual management method and visual management system for building supply chain

Similar Documents

Publication Publication Date Title
CN107958328A (en) Green assembled architecture digitlization construct platform and its method of work
JP6913074B2 (en) Global smart manufacturing and sales service system
CN103136626B (en) The online management method of engineering project
CN104408559B (en) A kind of engineering information management system
CN107203610A (en) A kind of resource-sharing data processing equipment and method
US20040015367A1 (en) Business asset management system using virtual areas
CN103021219A (en) Intelligent simulation system for power ERP service
CN104537452A (en) Electric power project computer management system
CN108830534A (en) Computer network system for enterprise purchasing management
CN101256647A (en) Item management system being suitable for garden engineering
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN110211004A (en) Excellent room building sale system
KR20130047776A (en) Stand alone domain each construction web site with auto maker and using it for the group system
CN109615459A (en) A kind of digital intelligent house ornamentation method and system
CN108846645A (en) A kind of enterprise's flattened management method and system
CN108985703A (en) A kind of project management system and implementation method based on industrial cloud platform
CN109102364A (en) Air ticket supply management system and air ticket supplies management method based on the network platform
CN109816317A (en) Project Abroad logistic information management system
CN111915271A (en) Purchasing method and system based on data middling station
Safa An advanced construction supply nexus model
Yousefi et al. Solving a multi-objective mathematical model for aggregate production planning in a closed-loop supply chain under uncertain conditions
CN112348453B (en) Material purchase management method, management platform and management system based on BIM
CN110517006A (en) A kind of service monitoring system and method integrating purchase of goods and materials and transaction
US20080034290A1 (en) System for foreign and remote architectural and engineering services for U.S. construction projects
Jianghua et al. Digital Procurement of Nanjing Water Group

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180424