CN110880096B - Multi-party collaborative office system for building engineering - Google Patents

Multi-party collaborative office system for building engineering Download PDF

Info

Publication number
CN110880096B
CN110880096B CN201911143743.3A CN201911143743A CN110880096B CN 110880096 B CN110880096 B CN 110880096B CN 201911143743 A CN201911143743 A CN 201911143743A CN 110880096 B CN110880096 B CN 110880096B
Authority
CN
China
Prior art keywords
module
engineering
data
management
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911143743.3A
Other languages
Chinese (zh)
Other versions
CN110880096A (en
Inventor
朱浩
梁一鸣
黎广夏
罗祖战
覃翔
苏重华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Knowmore Network Co ltd
Original Assignee
Guangxi Knowmore Network Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Knowmore Network Co ltd filed Critical Guangxi Knowmore Network Co ltd
Priority to CN201911143743.3A priority Critical patent/CN110880096B/en
Publication of CN110880096A publication Critical patent/CN110880096A/en
Application granted granted Critical
Publication of CN110880096B publication Critical patent/CN110880096B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/101Collaborative creation, e.g. joint development of products or services
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a multi-party cooperative office system for building engineering, which belongs to the field of engineering management systems and comprises a construction site supervision unit, an industry market detail unit, a server management unit, a project five-party cooperative unit, a project information management unit and a project quality and safety management unit. The foundation based on five-party management supports multiparty common management, solves the problems of personnel communication, project management, information sharing, work arrangement implementation, project site real-time monitoring and the like, enables personnel, data and management to be integrated through collaborative management, improves project management informatization level, achieves the purpose of finely managing building engineering, and multiparty collaborative management projects can be used in a cross-platform mode, responsibility rights of personnel are clear, data can be stored in a cloud end, convenient to call, light in weight and easy to operate.

Description

Multi-party collaborative office system for building engineering
Technical Field
The invention relates to the field of engineering management systems, in particular to a multiparty cooperative office system for constructional engineering.
Background
With the development of electronic information technology, especially the popularization of mobile internet, the frequency of people to acquire and send data is more and more dense, the means is more and more diverse, and the requirement of real-time is higher, so to speak, the requirement of information interaction is provided at any time and any place.
The construction engineering is characterized in that the site management of the construction site is chaotic, each company has own management system, and the companies do not communicate with each other or participate in each other. When serious problems often occur, mutual withholding occurs, and serious loss or slower overall construction progress of the engineering can be caused.
As the scale of more and more constructional engineering projects is continuously enlarged at present, the original engineering project management method can not better adapt to the large-scale constructional engineering project management requirements for controlling the cost and managing various resources in the construction process. However, in the prior art, the resource information of the building engineering project is usually collected, summarized and calculated manually to form a moon report and other forms to evaluate the progress of the project and analyze the project cost, while the engineering project is dynamically advanced, if the project is smaller, the project can also be dealt with, but if the project is larger in scale, the report presented in the moon report form can not timely reflect the current engineering dynamic information, and great technical difficulties are brought to project cost control and progress management.
However, the existing project management system is simple to manage, such as single manpower management, single engineering process management, single information management and the like, and does not have a management system for comprehensively planning the whole project, so that communication difficulties occur among parties responsible for the project, and the progress of the project, the quality of the project and the like are seriously affected.
Disclosure of Invention
The invention aims to provide a multiparty collaborative office system for construction engineering, which solves the technical problem that the prior engineering project does not have a management system for comprehensively planning the whole project, so that communication difficulties occur among parties responsible for the project.
The system comprises a construction site supervision unit, an industry market detail unit, a server management unit, a project five-party collaboration unit, a project information management unit and a project quality security management unit, wherein the construction site supervision unit, the industry market detail unit, the project five-party collaboration unit, the project information management unit and the project quality security management unit are all connected with the server management unit, and the construction site supervision unit is used for supervising construction data, safety data and supervision data of an engineering site in a construction process; the industrial market detail unit is used for displaying raw material merchants and equipment merchants required in the engineering construction process, positioning the site position and displaying the raw material merchants and equipment merchants nearby the site, the server management unit is used for storing engineering management data, equipment data and backup engineering construction process management data and equipment data, and the project five-party coordination unit is used for communicating and sharing data among a constructor, a supervisor, a designer and a reconnaissance party; the project information management unit is used for recording and inquiring data of project engineering construction process, meeting data, personnel management data, engineering diary data, five-party contact but visa data and five-party communication process recording data, and the project quality and safety management unit is used for recording and processing complaints of the project construction process, recording construction process spot check data and construction safety data entry inquiry.
The industry market detail unit comprises an engineering main material supply module, an engineering manpower service module, a hardware material supply module, a security material supply module, an electrician electrical material supply module, a mechanical equipment supply module, an electric tool supply module, a GPS project positioning module, a nearby supplier display module and a distribution service module, wherein the engineering main material supply module is used for displaying specific information and material price information of the main material supplier required in the engineering construction process, the engineering manpower service module is used for displaying worker information required in the engineering construction process, the worker training is directly contacted with the worker according to construction requirements, the hardware material supply module is used for displaying specific information and hardware material price information of the hardware material supplier required in the engineering construction process, the security material supply module is used for displaying specific information and security material price information of the security material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying specific information and electrical material price information of the electrician electrical material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying the specific information and the mechanical equipment supplier required in the engineering construction process, meanwhile, the position of the electrical equipment supply module is used for displaying the GPS position information of the nearby electrical material supplier in the engineering construction process, the position information is used for displaying the nearby electrical material supplier positioning module is used for positioning the position information of the electrical tool, and calculating specific distances and positions, wherein the distribution service module is used for selecting different distribution services to contact different logistics merchants according to the requirements of users.
The building site supervision unit includes deep basal pit monitoring module, crane monitoring module, lift monitoring module, house monitoring module, high formwork monitoring module, side slope monitoring module, raise dust monitoring module, noise monitoring module, dangerous source monitoring module, engineering image display module, attendance module and engineering panorama record module, deep basal pit monitoring module is used for monitoring and recording deep basal pit work process data, crane monitoring module is used for monitoring crane operation data to record data, the lift monitoring module is used for monitoring lift operation data to record data, the house monitoring module is used for monitoring building site workman house's environmental data, high formwork monitoring module has high data through the vertical degree of sensor monitoring high formwork, side slope monitoring module uses camera monitoring side slope environmental condition data, raise dust monitoring module uses dust sensor to monitor engineering construction site's dust concentration to judge whether to accord with the standard, start water smoke fall processing when not accord with the standard, noise monitoring module passes through sound sensor construction site's noise data to judge whether to accord with the interior time zone of sound sensor construction site, the noise data of taking place, and judge whether to accord with the panorama construction site work environment data that the time zone, the high formwork monitoring module is used for carrying out the record with the environmental condition data of the side slope monitoring module, whether the panorama construction site is used for carrying out the panorama construction site, the life-time zone of the factory work, the life image display module is used for carrying out the record of the environmental condition data of the high formwork.
The server management unit comprises a management data storage module, an equipment data storage module and a data backup module, wherein the management data storage module is used for storing management data information and process data information of construction in the engineering construction process, the equipment data storage module is used for storing equipment data used for construction, and the data backup module is used for backing up all data related to the engineering construction process in real time.
The project quality and safety management unit comprises an engineering complaint management module, an engineering selective inspection module and an engineering construction safety data input module, wherein the engineering complaint management module is used for receiving citizen complaints and checking complaint processing progress conditions, the engineering selective inspection module is used for recording specific data of selective inspection in a construction process, and the engineering construction safety data input module is used for recording safety data at each stage of the construction process.
The project information management unit comprises an engineering diary module, an engineering conference detail module, an engineering data module, an engineering personnel management module, a five-party contact list and visa list module and a five-party communication recording module, wherein the engineering diary module is used for recording daily recording data information in the construction process, the engineering conference detail module is used for recording conference information of each time in the construction process and recording problems and final solutions of conference discussion, the engineering data module is used for recording information of all materials used in engineering, the engineering personnel management module is used for recording related responsibility and related responsible persons of engineering construction, the five-party contact list and visa list module is used for managing and communicating among five parties, and the five-party communication recording module is used for recording and storing communication information among the five parties.
The project five-party collaboration unit comprises a constructor using end module, a designer using end module, a reconnaissance party using end module, a constructor using end module, a supervisor using end module and an engineering period supervision module, wherein the constructor using end module is used for checking and supervising whether engineering drawings of the constructor, the supervisor, the designer and the reconnaissance party accord with relevant standards, meanwhile, construction and reconnaissance are carried out according to requirements of the relevant standards, the designer using end module is used for uploading engineering drawings required to be used in engineering and communicating with other parties, the reconnaissance party using end module is used for reconnaissance detection of an engineering place to obtain detection data, the constructor using end module is used for carrying out construction according to the design drawings of the designer, the supervisor using end module is used for carrying out construction according to the relevant standards by the constructor, and the engineering period supervision module is used for recording whole process data from design to finish inspection and acceptance of the engineering and carrying out real-time inquiry by the five parties.
The invention adopts the technical proposal and has the following technical effects:
the system supports multiparty common management based on the basis of multiparty management, solves the problems of personnel communication, project management, information sharing, work arrangement implementation, project site real-time monitoring and the like, integrates personnel, data and management through collaborative management, improves project management informatization level, achieves the aim of finely managing building engineering, and is capable of cross-platform use, clear in personnel setting responsibility, data storage cloud, convenient to call, light in weight and simple in operation.
Drawings
Fig. 1 is a block diagram of the system of the present invention.
Fig. 2 is a block diagram of a worksite supervisory unit module of the present invention.
FIG. 3 is a block diagram of an industry market detail unit of the present invention.
Fig. 4 is a block diagram of a server management unit module of the present invention.
FIG. 5 is a block diagram of the project quality and safety management unit module of the present invention.
Fig. 6 is a block diagram of an item information management unit module of the present invention.
Fig. 7 is a block diagram of a five-party collaboration unit module in accordance with the present invention.
Detailed Description
The present invention will be described in further detail with reference to preferred embodiments for the purpose of making the objects, technical solutions and advantages of the present invention more apparent. It should be noted, however, that many of the details set forth in the description are merely provided to provide a thorough understanding of one or more aspects of the invention, and that these aspects of the invention may be practiced without these specific details.
As shown in fig. 1, the multi-party collaborative office system for construction engineering comprises a construction site supervision unit, an industry market detail unit, a server management unit, a project five-party collaborative unit, a project information management unit and a project quality and safety management unit. The construction site supervision unit, the industry market detail unit, the project five-party cooperation unit, the project information management unit and the project quality and security management unit are all connected with the server management unit. The technology takes national standard definition building industry role specification as a basis, takes collaborative management project as a target, links engineering management five parties, namely constructors, proctoring parties, design parties, reconnaissance parties and other personnel, supports multiparty common management based on the basis of the five party management, solves the problems of personnel communication, project management, information sharing, work arrangement implementation, project field real-time monitoring and the like, and enables personnel, data and management to be integrated through collaborative management, improves project management informatization level and achieves the purpose of finely managing building engineering. The multi-party collaborative management project can be used in a cross-platform manner, the responsibility right of personnel setting is clear, the data can be stored in the cloud, the data are convenient to call, the weight is reduced, and the operation is simple.
The existing project management technology is single, mainly solves the technical problems of manufacturing cost, design or part of engineering data in a certain project of participating in construction, does not have a cooperative office function, cannot solve communication management and the like, is not light enough, cannot cover most of the participants in the building, is complex in operation and is glorious in terms, a great deal of learning training is needed before use, and the use learning cost is too high.
The system not only can carry out mutual communication of other participators for sub-project engineering, such as related enterprises, finance, insurance, supervision, government and the like, but also can carry out post setting on related enterprises of projects through authority setting for all the enterprises of all the parties involved in building projects, the post authorities of different enterprises are different, responsibility rights are clear and easy to trace back and facilitate communication, and meanwhile, the system can be technically expanded to more participators according to national and market rule change platforms, is simple and convenient to operate, can be used across platforms, can be used for mobile phones and computers, and can be used for storing and retrieving project data at any time.
Personnel using the platform can manage (check) project progress at any time and any place at the terminal, so that remote control is convenient, and project conditions can be known without personally arriving at a project site;
the multi-side management worksite has clear responsibility and is convenient to trace;
a large amount of complicated project data are stored in the cloud, and can be referred by one-key searching;
the work is fairer, fair and public, the multi-party supervision and common management are performed, withholding and loss of projects caused by loose supervision are reduced, and the management efficiency is improved.
As shown in fig. 3, the worksite supervision unit is used for supervising construction data, safety data and supervision data of the engineering worksite during the construction process. The building site supervision unit includes deep basal pit monitoring module, crane monitoring module, house monitoring module, high formwork monitoring module, side slope monitoring module, raise dust monitoring module, noise monitoring module, dangerous source monitoring module, engineering image display module, attendance module and engineering panorama take photo recording module by plane, deep basal pit monitoring module is used for monitoring and recording deep basal pit work process data, crane monitoring module is used for monitoring crane operation data to record data, the elevator monitoring module is used for monitoring elevator operation data to record data, house monitoring module is used for monitoring the environmental data of building site workman house, high formwork monitoring module passes through sensor monitoring high formwork vertical degree and has high data, side slope monitoring module uses camera monitoring side slope environmental condition data, raise dust monitoring module uses dust sensor to monitor the dust concentration of engineering construction site to judge whether to accord with the standard, start the water smoke when not accord with, noise monitoring module passes through sound sensor monitoring construction site's noise data to judge whether to accord with the time quantum inner bag, the panorama is used for monitoring engineering image display module and taking photo by plane work site life, the dangerous condition data is used for recording each time quantum of engineering image display module, the engineering panorama take photo of life image display module is used for carrying out the engineering panorama construction site work picture each day.
As shown in fig. 2, the industry market detail unit is used for displaying raw material merchants and equipment merchants required in the engineering construction process, and positioning the site and displaying raw material merchants and equipment merchants nearby the site. The industrial market detail unit comprises an engineering main material supply module, an engineering manpower service module, a hardware material supply module, a security material supply module, an electrical and electronic material supply module, a mechanical equipment supply module, an electric tool supply module, a GPS project positioning module, a nearby supplier display module and a distribution service module, wherein the engineering main material supply module is used for displaying specific information and material price information of a main material supplier required in an engineering construction process, the engineering manpower service module is used for displaying worker information required in the engineering construction process, the worker is directly contacted with workers according to construction requirements to train the workers, the hardware material supply module is used for displaying specific information and hardware material price information of a hardware material supplier required in the engineering construction process, the security material supply module is used for displaying specific information and security material price information of the electrical and electronic material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying specific information and electrical and electronic material price information of the electrical and electronic material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying specific information and mechanical equipment price information of the mechanical equipment supplier required in the engineering construction process, meanwhile, the electrical tool supply module is used for displaying the position information of the electrical and the electrical material supplier in the vicinity of the engineering construction process, the electrical equipment supply module is used for positioning the GPS project positioning module according to the position information of the GPS project positioning module, and calculating specific distances and positions, wherein the distribution service module is used for selecting different distribution services to contact different logistics merchants according to the requirements of users.
As shown in fig. 4, the server management unit is configured to store engineering management data and equipment data, and backup engineering construction process management data and equipment data. The server management unit comprises a management data storage module, an equipment data storage module and a data backup module, wherein the management data storage module is used for storing management data information and process data information of construction in the engineering construction process, the equipment data storage module is used for storing equipment data used for construction, and the data backup module is used for backing up all data related to the engineering construction process in real time.
As shown in fig. 7, the project five-party collaboration unit is used for communication and data sharing among a constructor, a supervisor, a designer and a reconnaissance party. The project five-party collaboration unit comprises a constructor using end module, a designer using end module, an reconnaissance party using end module, a constructor using end module, a supervisor using end module and an engineering period supervision module, wherein the constructor using end module is used for checking and supervising whether engineering drawings of the constructor, the supervisor, the designer and the reconnaissance party accord with relevant standards, meanwhile, construction and reconnaissance are carried out according to requirements of the relevant standards, the designer using end module is used for uploading engineering drawings required to be used in the engineering and communicating with other parties, the reconnaissance party using end module is used for reconnaissance detection of an engineering land to obtain detection data, the constructor using end module is used for carrying out construction according to the design drawings of the designer, the supervisor using end module is used for supervising the construction of the constructor according to the relevant standards, and the engineering period supervision module is used for recording the whole process data from the engineering design to the completion of the engineering and acceptance and is used for five parties to query in real time.
As shown in fig. 6. The project information management unit is used for recording and inquiring data of project engineering construction process, meeting data, personnel management data, engineering diary data, five-party contact but visa data and five-party communication process record data. The project information management unit comprises an engineering diary module, an engineering conference detail module, an engineering data module, an engineering personnel management module, a five-party contact list and visa list module and a five-party communication recording module, wherein the engineering diary module is used for recording daily record data information in the construction process, the engineering conference detail module is used for recording conference information of each time in the construction process and recording problems and final solutions of conference discussion, the engineering data module is used for recording information of all materials used in engineering, the engineering personnel management module is used for recording related responsibility and related responsible persons of engineering construction, the five-party contact list and visa list module is used for management and communication among five parties, and the five-party communication recording module is used for recording and storing communication information among the five parties.
As shown in fig. 5, the project quality and safety management unit is used for recording and processing complaints of engineering construction processes, recording construction process spot check data and construction safety data entry query. The project quality and safety management unit comprises an engineering complaint management module, an engineering selective inspection module and an engineering construction safety data input module, wherein the engineering complaint management module is used for receiving citizen complaints and checking complaint processing progress conditions, the engineering selective inspection module is used for recording concrete data of selective inspection in a construction process, and the engineering construction safety data input module is used for recording safety data at each stage of the construction process.
The foregoing is merely a preferred embodiment of the present invention and it should be noted that modifications and adaptations to those skilled in the art may be made without departing from the principles of the present invention, which are intended to be comprehended within the scope of the present invention.

Claims (1)

1. The utility model provides a building engineering multiparty cooperation office system which characterized in that: the system comprises a construction site supervision unit, an industry market detail unit, a server management unit, a project five-party collaboration unit, a project information management unit and a project quality security management unit, wherein the construction site supervision unit, the industry market detail unit, the project five-party collaboration unit, the project information management unit and the project quality security management unit are all connected with the server management unit, and the construction site supervision unit is used for supervising construction data, safety data and supervision data of an engineering site in a construction process; the industrial market detail unit is used for displaying raw material merchants and equipment merchants required in the engineering construction process, positioning the site position and displaying the raw material merchants and equipment merchants nearby the site, the server management unit is used for storing engineering management data, equipment data and backup engineering construction process management data and equipment data, and the project five-party coordination unit is used for communicating and sharing data among a constructor, a supervisor, a designer and a reconnaissance party; the project information management unit is used for recording and inquiring data of data, meeting data, personnel management data, engineering diary data, five-party contact but visa data and five-party communication process record data of a project engineering construction process, and the project quality and safety management unit is used for recording and processing complaints of the engineering construction process, recording construction process spot check data and construction safety data input inquiry;
the industry market detail unit comprises an engineering main material supply module, an engineering manpower service module, a hardware material supply module, a security material supply module, an electrician electrical material supply module, a mechanical equipment supply module, an electric tool supply module, a GPS project positioning module, a nearby supplier display module and a distribution service module, wherein the engineering main material supply module is used for displaying specific information and material price information of the main material supplier required in the engineering construction process, the engineering manpower service module is used for displaying worker information required in the engineering construction process, the worker training is directly contacted with the worker according to construction requirements, the hardware material supply module is used for displaying specific information and hardware material price information of the hardware material supplier required in the engineering construction process, the security material supply module is used for displaying specific information and security material price information of the security material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying specific information and electrical material price information of the electrician electrical material supplier required in the engineering construction process, the mechanical equipment supply module is used for displaying the specific information and the mechanical equipment supplier required in the engineering construction process, meanwhile, the position of the electrical equipment supply module is used for displaying the GPS position information of the nearby electrical material supplier in the engineering construction process, the position information is used for displaying the nearby electrical material supplier positioning module is used for positioning the position information of the electrical tool, the distribution service module is used for selecting different distribution services to contact different logistics merchants according to the requirements of users;
the construction site supervision unit comprises a deep foundation pit monitoring module, a crane monitoring module, a lifter monitoring module, a house monitoring module, a high formwork monitoring module, a side slope monitoring module, a dust raising monitoring module, a noise monitoring module, a dangerous source monitoring module, an engineering image display module, an attendance module and an engineering panorama aerial recording module, wherein the deep foundation pit monitoring module is used for monitoring and recording deep foundation pit construction process data, the crane monitoring module is used for monitoring crane operation data and recording the data, the lifter monitoring module is used for monitoring the lifter operation data and recording the data, the house monitoring module is used for monitoring environmental data of a house of a construction site worker, the high formwork monitoring module monitors the vertical degree of the high formwork through a sensor, the side slope monitoring module monitors the environmental condition data of the side slope through a camera, the dust raising monitoring module monitors the dust concentration of the engineering construction site through a dust sensor and judges whether the dust concentration accords with a standard, water mist drop processing is started when the dust concentration monitoring module does not accord with the standard, the noise monitoring module monitors the noise data of the sound sensor construction site and judges whether the noise data of the construction site accord with a full view, and the dust concentration sensor displays whether the environmental protection data of the panorama construction site is recorded by the panorama construction site, and the expected time frame, and the dust sensor displays whether the panorama construction site is used for recording the environmental condition data;
the server management unit comprises a management data storage module, an equipment data storage module and a data backup module, wherein the management data storage module is used for storing management data information and process data information of construction in the engineering construction process, the equipment data storage module is used for storing equipment data used for construction, and the data backup module is used for backing up all data related to the engineering construction process in real time;
the project quality and safety management unit comprises an engineering complaint management module, an engineering selective examination module and an engineering construction safety data input module, wherein the engineering complaint management module is used for receiving citizen complaints and checking complaint processing progress conditions, the engineering selective examination module is used for recording specific data of selective examination in a construction process, and the engineering construction safety data input module is used for recording safety data in each stage of the construction process;
the project information management unit comprises an engineering diary module, an engineering conference detail module, an engineering data module, an engineering personnel management module, a five-party contact list and visa list module and a five-party communication recording module, wherein the engineering diary module is used for recording daily record data information in the construction process, the engineering conference detail module is used for recording conference information each time in the construction process and recording problems of conference discussion and final solutions, the engineering data module is used for recording information of all materials used in engineering, the engineering personnel management module is used for recording related responsibility and related responsible persons of engineering construction, the five-party contact list and visa list module is used for managing and communicating among five parties, and the five-party communication recording module is used for recording and storing communication information among the five parties;
the project five-party collaboration unit comprises a constructor using end module, a designer using end module, a reconnaissance party using end module, a constructor using end module, a supervisor using end module and an engineering period supervision module, wherein the constructor using end module is used for checking and supervising whether engineering drawings of the constructor, the supervisor, the designer and the reconnaissance party accord with relevant standards, meanwhile, construction and reconnaissance are carried out according to requirements of the relevant standards, the designer using end module is used for uploading engineering drawings required to be used in engineering and communicating with other parties, the reconnaissance party using end module is used for reconnaissance detection of an engineering place to obtain detection data, the constructor using end module is used for carrying out construction according to the design drawings of the designer, the supervisor using end module is used for carrying out construction according to the relevant standards by the constructor, and the engineering period supervision module is used for recording whole process data from design to finish inspection and acceptance of the engineering and carrying out real-time inquiry by the five parties.
CN201911143743.3A 2019-11-20 2019-11-20 Multi-party collaborative office system for building engineering Active CN110880096B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911143743.3A CN110880096B (en) 2019-11-20 2019-11-20 Multi-party collaborative office system for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911143743.3A CN110880096B (en) 2019-11-20 2019-11-20 Multi-party collaborative office system for building engineering

Publications (2)

Publication Number Publication Date
CN110880096A CN110880096A (en) 2020-03-13
CN110880096B true CN110880096B (en) 2023-10-31

Family

ID=69730188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911143743.3A Active CN110880096B (en) 2019-11-20 2019-11-20 Multi-party collaborative office system for building engineering

Country Status (1)

Country Link
CN (1) CN110880096B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220335365A1 (en) * 2021-03-08 2022-10-20 Tuler Technologies, LLC Construction networking application for construction project management, construction material ordering and delivery, construction retal equipment procurement, construction labor procurement and methods implementing the same
CN113516446A (en) * 2021-04-25 2021-10-19 李小龙 Combined office platform on construction line

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001195438A (en) * 2000-01-11 2001-07-19 Matsushita Electric Works Ltd Method and commercial form for cooperative design using internet, and system and recording medium for them
WO2005029250A2 (en) * 2003-09-16 2005-03-31 Meridian Project Systems Collaborative information system for real estate, building design, construction and facility management and similar industries
CN102129607A (en) * 2010-01-20 2011-07-20 朱浩 Method for performing personal financial management by utilizing mobile phone
CA2844763A1 (en) * 2013-03-15 2014-09-15 Iti - Innovative Technology Inc. Method for propagating information between a building information model and a specification document
CN106169131A (en) * 2016-05-16 2016-11-30 北京诺士诚国际工程项目管理有限公司 Project management cloud platform system based on the Internet
CN106228338A (en) * 2016-07-15 2016-12-14 广东中网电力有限公司 A kind of distribution engineering intelligentized design integrated service system and using method
CN107504946A (en) * 2017-08-24 2017-12-22 北京融通智慧科技有限公司 The Excavation Settlement real-time monitoring system and monitoring method of wisdom building site control platform
CN107958328A (en) * 2017-11-22 2018-04-24 北京善筑科技股份有限公司 Green assembled architecture digitlization construct platform and its method of work
CN108932586A (en) * 2018-06-28 2018-12-04 南京绿新能源研究院有限公司 EPC Project cooperation operation management system
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN109557934A (en) * 2018-09-20 2019-04-02 中建科技有限公司深圳分公司 A kind of control method and device of the unmanned plane cruise based on assembled architecture platform
CN109658067A (en) * 2018-12-20 2019-04-19 山东晟光电力设备安装工程有限公司 A kind of power engineering project control platform and system
CN109711639A (en) * 2019-01-16 2019-05-03 辽宁工程技术大学 A kind of greening supply chain collaborative design and optimization system and method
CN109947805A (en) * 2019-03-22 2019-06-28 国网上海市电力公司 A kind of engineering project process management system and its management method
CN109949018A (en) * 2019-04-17 2019-06-28 河北方舟工程项目管理有限公司 Construction-engineering project management overall process tracing system
CN109977496A (en) * 2019-03-09 2019-07-05 佰模伝信息科技(厦门)有限公司 Efficient information exchange and the architectural engineering artwork integrated system and method to cooperate
CN209231777U (en) * 2018-08-20 2019-08-09 东莞市太龙湾建设工程有限公司 Wisdom building site management system
CN110147579A (en) * 2019-04-19 2019-08-20 浙江省建工集团有限责任公司 A kind of Building Information Model dynamic cooperation management method
CN110310210A (en) * 2019-06-26 2019-10-08 广西越知网络股份有限公司 A kind of analysis of architectural engineering comprehensive data acquisition and long-distance Log server system
CN110322144A (en) * 2019-07-01 2019-10-11 南京凯菲科信息系统有限公司 A kind of construction-engineering project management system
CN110414909A (en) * 2019-05-21 2019-11-05 北京太空漫步科技有限公司 A kind of architecture system visualizing real-time collaborative

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080301142A1 (en) * 2007-06-03 2008-12-04 Im-Prove Llc Method and system for organizing and presenting construction knowledge-sharing tools
US20110190952A1 (en) * 2010-02-04 2011-08-04 Boris Goldstein Method and System for an Integrated Intelligent Building
US20180332102A1 (en) * 2018-03-22 2018-11-15 Michael Sheidaei Cloud-based system for collaborating engineering, operations, maintenance, project management, procurement and vendor data and activities

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001195438A (en) * 2000-01-11 2001-07-19 Matsushita Electric Works Ltd Method and commercial form for cooperative design using internet, and system and recording medium for them
WO2005029250A2 (en) * 2003-09-16 2005-03-31 Meridian Project Systems Collaborative information system for real estate, building design, construction and facility management and similar industries
CN102129607A (en) * 2010-01-20 2011-07-20 朱浩 Method for performing personal financial management by utilizing mobile phone
CA2844763A1 (en) * 2013-03-15 2014-09-15 Iti - Innovative Technology Inc. Method for propagating information between a building information model and a specification document
CN106169131A (en) * 2016-05-16 2016-11-30 北京诺士诚国际工程项目管理有限公司 Project management cloud platform system based on the Internet
CN106228338A (en) * 2016-07-15 2016-12-14 广东中网电力有限公司 A kind of distribution engineering intelligentized design integrated service system and using method
CN107504946A (en) * 2017-08-24 2017-12-22 北京融通智慧科技有限公司 The Excavation Settlement real-time monitoring system and monitoring method of wisdom building site control platform
CN107958328A (en) * 2017-11-22 2018-04-24 北京善筑科技股份有限公司 Green assembled architecture digitlization construct platform and its method of work
CN108932586A (en) * 2018-06-28 2018-12-04 南京绿新能源研究院有限公司 EPC Project cooperation operation management system
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN209231777U (en) * 2018-08-20 2019-08-09 东莞市太龙湾建设工程有限公司 Wisdom building site management system
CN109557934A (en) * 2018-09-20 2019-04-02 中建科技有限公司深圳分公司 A kind of control method and device of the unmanned plane cruise based on assembled architecture platform
CN109658067A (en) * 2018-12-20 2019-04-19 山东晟光电力设备安装工程有限公司 A kind of power engineering project control platform and system
CN109711639A (en) * 2019-01-16 2019-05-03 辽宁工程技术大学 A kind of greening supply chain collaborative design and optimization system and method
CN109977496A (en) * 2019-03-09 2019-07-05 佰模伝信息科技(厦门)有限公司 Efficient information exchange and the architectural engineering artwork integrated system and method to cooperate
CN109947805A (en) * 2019-03-22 2019-06-28 国网上海市电力公司 A kind of engineering project process management system and its management method
CN109949018A (en) * 2019-04-17 2019-06-28 河北方舟工程项目管理有限公司 Construction-engineering project management overall process tracing system
CN110147579A (en) * 2019-04-19 2019-08-20 浙江省建工集团有限责任公司 A kind of Building Information Model dynamic cooperation management method
CN110414909A (en) * 2019-05-21 2019-11-05 北京太空漫步科技有限公司 A kind of architecture system visualizing real-time collaborative
CN110310210A (en) * 2019-06-26 2019-10-08 广西越知网络股份有限公司 A kind of analysis of architectural engineering comprehensive data acquisition and long-distance Log server system
CN110322144A (en) * 2019-07-01 2019-10-11 南京凯菲科信息系统有限公司 A kind of construction-engineering project management system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
基于BIM技术的特大型多方协作智慧管理;杨晓毅等;土木建筑工程信息技术;第10卷(第5期);全文 *
杨富春 ; 王静 ; 谭丁文 ; .《建筑业10项新技术(2017版)》信息化技术综述.建筑技术.2018,(第03期),全文. *

Also Published As

Publication number Publication date
CN110880096A (en) 2020-03-13

Similar Documents

Publication Publication Date Title
CN105023188B (en) Digital city management data sharing system based on cloud data
CN105303306B (en) Electric power material dispatching platform system
CN106228497A (en) A kind of multi-operation mode emergency commading system and method for work thereof
WO2015123810A1 (en) Electric power field operation system combined with smartphone
CN110880096B (en) Multi-party collaborative office system for building engineering
CN112132535A (en) Wisdom production garden management system
CN115375146A (en) Digital construction integrated platform
CN107693997B (en) Fire fighting equipment detection and maintenance management system and management method
CN110430246A (en) Capital construction security management and control system
CN110221582A (en) A kind of production of five in one or engineering safety service and support method and system
F. Guerin A demonstration of how virtual meetings can enhance sustainability in a corporate context: quantified benefits of virtual meetings through video conferencing
CN116957341A (en) Intelligent safety risk management and control system based on steel mill
CN110599368A (en) DBM intelligent building management tool
CN109711572A (en) A kind of mobile O&M task processing system of photovoltaic plant
CN112364735A (en) Worker type identification system and method
CN111626575A (en) Construction safety quality hidden danger management method based on internet environment
CN110782198A (en) Webpage end rail transit equipment monitoring information control platform and implementation method thereof
Savchuk Development of Automation Systems for the Unified Duty Dispatch Service “System-112” in Order to Increase Efficiency Activities in the Field of Protection of the Population and Territories
CN103313187A (en) Construction engineering personnel positioning method based on mobile phone GPS (Global Positioning System)
CN113487293A (en) Engineering project management cloud platform system
CN112329960A (en) Inspection method and system based on block chain
CN109214767B (en) Roofing waterproof repair engineering quality process supervision platform
KR20040057068A (en) Integration and superintendence managing system and its method of construction in the network configuration
CN112270634A (en) Information construction supervision service system for municipal engineering
Syafar et al. Mobile Collaboration Technology in Engineering Asset Maintenance–What Technology, Organisation and People Approaches Are Required?

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 530000 Room 1103, Floor 11, Building 10, South Area, Industrial Standard Plant Construction Project, No. 189, Fazhan Avenue, Xixiangtang District, Nanning City, Guangxi

Patentee after: GUANGXI KNOWMORE NETWORK Co.,Ltd.

Country or region after: Zhong Guo

Address before: 530000 floor 14, South Building, training building, Xiangsihu campus, Guangxi construction vocational and technical college, No. 33, Luowen Avenue, XiXiangTang District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee before: GUANGXI KNOWMORE NETWORK Co.,Ltd.

Country or region before: Zhong Guo

CP03 Change of name, title or address