CN109559070A CN201811105789.1A CN201811105789A CN109559070A CN 109559070 A CN109559070 A CN 109559070A CN 201811105789 A CN201811105789 A CN 201811105789A CN 109559070 A CN109559070 A CN 109559070A
Authority
CN
China
Prior art keywords
raw material
time
database
information management
assembled architecture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811105789.1A
Other languages
Chinese (zh)
Inventor
叶浩文
樊则森
钟志强
林林
苏世龙
李新伟
谭睿楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Technology Group Co Ltd Shenzhen Branch
Original Assignee
China Construction Science and Technology Co Ltd Shenzhen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Science and Technology Co Ltd Shenzhen Branch filed Critical China Construction Science and Technology Co Ltd Shenzhen Branch
Priority to CN201811105789.1A priority Critical patent/CN109559070A/en
Publication of CN109559070A publication Critical patent/CN109559070A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention is suitable for as-built information modelling technique field, the equipment production information management method and device of a kind of assembled architecture platform are provided, the equipment production information management method includes: Raw Material Demand amount and the Raw Material Demand time that current production plan is obtained from the first database;Current raw material store storage is obtained from second database;Compare the size of the Raw Material Demand amount and the raw material store storage, if the Raw Material Demand amount is greater than the raw material store storage, generates materials procurement instruction.Raw Material Demand amount based on current production plan, Raw Material Demand time and current raw material store storage generate materials procurement instruction in real time, carry out materials procurement much sooner improves the intelligence degree of the equipment production information management process of assembled architecture platform.

Description

The equipment production information management method and device of assembled architecture platform
Technical field
The invention belongs to a kind of productions of the equipment of as-built information modelling technique field more particularly to assembled architecture platform to believe Cease management method and device.
Background technique
BIM, i.e. Building Information Model (Building Information Modeling) are based on construction-engineering project The big data established of every relevant information data, integrated architecture information model greatly is believed the engineering project correlation The detailed expression of breath.
In terms of traditional BIM application predominantly stays in BIM Digital Design, can not achieve design, buying, production, construction and The information realtime interactive of delivery, this causes materials procurement to lag, and production plan cannot be adjusted in real time according to raw materials inventory situation It is whole, seriously affect the development of construction industry.
Summary of the invention
In view of this, the embodiment of the invention provides a kind of equipment production information management method of assembled architecture platform and Device, to solve construction industry production process chinese raw materials buying lag in the prior art, production plan cannot be according to raw material store Deposit the problem of situation adjusts in real time.
The first aspect of the embodiment of the present invention provides a kind of equipment production information management method of assembled architecture platform, The assembled architecture platform includes server, first database, the second database, comprising:
Raw Material Demand amount and the Raw Material Demand time of current production plan are obtained from the first database;
Current raw material store storage is obtained from second database;
Compare the size of the Raw Material Demand amount and the raw material store storage, if the Raw Material Demand amount is greater than institute Raw material store storage is stated, then generates materials procurement instruction.
The second aspect of the embodiment of the present invention provides a kind of equipment production information management device of assembled architecture platform, The assembled architecture platform includes server, first database, the second database, comprising:
First information acquiring unit, for obtained from the first database current production plan Raw Material Demand amount and The Raw Material Demand time;
Second information acquisition unit, for obtaining current raw material store storage from second database;
Procurement directive generation unit generates when being greater than current raw material store storage for the former material doses required for producing Unit generates materials procurement instruction.
The third aspect of the embodiment of the present invention provides a kind of terminal device, and the terminal device includes memory, processing Device and storage in the memory and the computer program that can run on the processor, described in the processor execution The step of method such as above-mentioned first aspect is realized when computer program.
The fourth aspect of the embodiment of the present invention provides a kind of computer readable storage medium, the computer-readable storage Media storage has computer program, and the step of the method such as above-mentioned first aspect is realized when the computer program is executed by processor Suddenly.
5th aspect of the embodiment of the present invention provides a kind of computer program product, and the computer program product includes Computer program realizes the step of the method such as above-mentioned first aspect when the computer program is executed by one or more processors Suddenly.
Existing beneficial effect is the embodiment of the present invention compared with prior art: original of the application based on current production plan Materials demand amount, Raw Material Demand time and current raw material store storage generate materials procurement instruction in real time, much sooner Materials procurement is carried out, the intelligence degree of the equipment production information management process of assembled architecture platform is improved.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention some Embodiment for those of ordinary skill in the art without any creative labor, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is the assembled architecture platform schematic diagram that the embodiment of the present invention one provides;
Fig. 2 is a kind of reality of the equipment production information management method of assembled architecture platform provided by Embodiment 2 of the present invention Existing flow diagram;
Fig. 3 is a kind of reality of the equipment production information management method for assembled architecture platform that the embodiment of the present invention three provides Existing flow diagram;
Fig. 4 is a kind of showing for the equipment production information management device for assembled architecture platform that the embodiment of the present invention four provides It is intended to;
Fig. 5 is a kind of equipment production information management device inventory for assembled architecture platform that the embodiment of the present invention four provides The schematic diagram of analysis and early warning unit;
Fig. 6 is the schematic diagram for the terminal device that the embodiment of the present invention five provides.
Specific embodiment
In being described below, for illustration and not for limitation, the tool of such as particular system structure, technology etc is proposed Body details, to understand thoroughly the embodiment of the present invention.However, it will be clear to one skilled in the art that there is no these specific The present invention also may be implemented in the other embodiments of details.In other situations, it omits to well-known system, device, electricity The detailed description of road and method, in case unnecessary details interferes description of the invention.
It should be appreciated that ought use in this specification and in the appended claims, term " includes " instruction is described special Sign, entirety, step, operation, the presence of element and/or component, but be not precluded one or more of the other feature, entirety, step, Operation, the presence or addition of element, component and/or its set.
It is also understood that mesh of the term used in this description of the invention merely for the sake of description specific embodiment And be not intended to limit the present invention.As description of the invention and it is used in the attached claims, unless on Other situations are hereafter clearly indicated, otherwise " one " of singular, "one" and "the" are intended to include plural form.
It will be further appreciated that the term "and/or" used in description of the invention and the appended claims is Refer to any combination and all possible combinations of one or more of associated item listed, and including these combinations.
Embodiment one
Fig. 1 shows assembled architecture platform schematic diagram provided in an embodiment of the present invention, it should be noted that Fig. 1 is only mentioned A kind of specific implementation framework for having supplied the assembled architecture platform, it is contemplated that other can be realized the embodiment of the present invention The system architecture of the relative theory of the assembled architecture platform of offer may be used to realize this programme, and therefore, Fig. 1 embodiment mentions The specific implementation framework of confession is not used in the restriction present invention herein.
As shown in Figure 1, the assembled architecture platform is around assembled architecture design, Systemizing production and construction in concrete project;It builds It builds, structure, electromechanics, built-in integrated and technology, management, industrial integration (referred to as three integrations) integrated needs built, The technologies such as systematicness integrated BIM, internet, Internet of Things, assembled architecture, innovation research and development building+internet platform.The assembly The web interface of formula construction platform include Digital Design module, cloud build online shopping module, intelligent plant module, wisdom building site module with And happy space module.
The Digital Design module includes project library and component and component part library, and the project library is used for this platform pipe The all items of reason carry out Classification Management, wherein further include panorama, high building, index bed, project component under each project directory The subdirectories such as library and project component library.The all items that the component and component part library are used to manage this platform are used Component and component component carry out Classification Management, wherein the component is shown by way of two dimensional code, user can pass through platform Terminal clicks the two dimensional code and carries out the displaying of component material picture, or by two dimensional code described in mobile scanning terminal, is then moving It is shown in dynamic terminal.The component component is shown by three-dimensional live model image, and user can lead on platform terminal It crosses mouse to rotate the three-dimensional live model image of the component component, so as to realize that different angle is real to the three-dimensional Scape model image is shown.
It includes that BIM Cost Management submodule and cloud build net module that the cloud, which builds online shopping module, wherein BIM Cost Management Module is used to carry out Cost Management to all items of the platform management, and the cost includes civil engineering, steel construction, light current Intelligent, metal Roof cost.The cloud build net module provided by way of online shopping mall bidding relevant to project, The interface of worker's recruitment, the purchase of component component.User directly can realize online bidding, work by this assembled architecture platform People's recruitment and the purchase of component and component.
The intelligent plant module includes PC (prestressed concrete) factory management system, Active Eyes, life Produce plan designing system, prefabricated components production information system.The PC factory management system is for providing the office of each factory The login interface of system.The Active Eyes is used to transfer the interface of the monitoring camera of different factories, Yong Huke To select corresponding factory in the Active Eyes of this platform, so that it may the monitoring camera in the factory is called, The production of factory, personnel status are monitored.The production plan designing system is currently being carried out for providing for user Project manufacturing plan sheet is provided, user can carry out plan design by production plan designing system, and by the design side Case is sent to corresponding responsible party.The prefabricated components production information system is used to carry out the component information of all plant produceds Summarize, user can check the relevant information of component, such as amount of concrete, structure in the prefabricated components production information system of platform Part weight, reinforcing bar volume, reinforcing bar weight, steel content, sleeve number, suspender number, sunpender, screw number, hole count through walls and electricity Box number etc..
Wisdom building site module includes remote monitoring unit, construction quality unit, site safety unit, contract planning list Member, cost accounting unit, component trace-back unit, personal management unit, point cloud scanning element.
The remote monitoring unit is used to carry out video monitoring to the different zones of construction site.The construction quality unit It is expired not rectify and improve quantity for showing quality related information, such as hidden danger quantity, quantity to be rectified and improved, quantity to be checked and accepted and Quantity is closed, and is classified to the hidden danger according to severity, is classified as major hidden danger, larger hidden danger and general hidden Suffer from.In this platform, shown by way of histogram by hidden danger that different subcontractors occur is strong.The site safety For showing the safety problem in building-site to user by way of chart, for example, by safety problem present in building site It is classified as high altitude operation, administration behaviour, falsework, hoisting machinery, four mouthfuls of Triratna, construction equipment, power supply for construction, external scaffolding And civilized construction, and above-mentioned safety problem is shown in the form of cake chart.The contract planning unit for pair Contract recruits the preposition pre-control for plan of adopting, and realizes the self energy monitoring for recruiting plan of adopting and task supervisor, it is ensured that and contract is correctly fulfiled, and It realizes the structured storage recruited and adopt contract, quick search, task supervisor and workflow examination and approval, realizes that data efficient is practical.It is described at This measuring and calculating unit is realized and is refined to subpackage, goods and materials, machinery, artificial and expense multi-level oil for being associated with project image progress Control, preposition early warning, correction assist business people to carry out whole process supervision to cost control, find risk, and take and accordingly arrange It applies, save the cost is generated profit.The component trace back block is realized by the component two dimensional code generated by BIM model to component It is traced from the Life cycle of design, production, examination, lifting.Using single component as basic unit body, the full Life Cycle of component is realized The information of phase summarizes.With docking BIM light weighed model, the real-time control to building-site progress is realized.By being based on lightweight The real-time mounting of component progress and model not only may be implemented in the virtual construction of BIM model, and segmentation, subregion carry out, according to color Subregion carries out progress simulation, also analog information can be associated with PROJECT, carries out target advance and reality by chart and model interaction The comparison of construction speed deviation is completed in the comparison of border progress.Key node payment plan in expansible docking commerce module simultaneously, Realize the one-to-one correspondence of engineering construction plan and commercial payment plan in engineering key node, the practical branch of the Zhi Fuyu that realizes a plan The real time contrast of the amount of money is paid, realize to the accurate control of cost caused by each node of engineering and provides auxiliary for project administrator and determines Plan information maximizes.
The personal management unit is big by completion personnel real name system, personnel positioning information, video monitoring information three The three-dimensional management to live labor service personnel may be implemented in combination of the data of function on platform.In conjunction with account permission Setting and critical data summarize, and manager is facilitated to pass through real-time control of the visualized data to live labor service personnel's situation.In conjunction with Front end bio-identification gate system carries out real-time remote monitoring to worker's number on the scene and personal information.Pass through analysis, cross simultaneously The digitization system management to project labor service worker is completed than personal information data.
Described cloud scanning element is scanned by infrared point cloud, it can be achieved that sweeping to completed indoor engineering Centimeter Level quality It retouches and is modeled with outdoor scene.Platform database is compared and is uploaded to BIM light weighed model for scanning result simultaneously to put on record, In conjunction with design information, construction deviation report is generated, provides data foundation for Construction Quality report.By the way that cloud scanning knot will be put Fruit input database is put on record, in conjunction with information is delivered, can also provide three-dimensional data for the house use of numerals specification of owner.
The happiness space module is based on VR, panoramic virtual reality technology, provides new home delivery, panorama building operation instruction The services such as book, panorama estate management navigation, panorama building physical examination.The VR and panorama experience sense for supporting mobile terminal are by auxiliary is checked and accepted Hand over room.It supports to identify the key messages such as property present position, surrounding enviroment, room number by mobile terminal barcode scanning, and Gao Pin can be based on It is made on the basis of matter is visual and selects room decision, select room result that can realize data statistics on platform.It is related during living Architectural drawing and household component library may be implemented on-line selection, the information of related maintenance facility may be implemented to visualize online and look into It askes.
Embodiment two
It is a kind of equipment production information management method of assembled architecture platform provided by Embodiment 2 of the present invention referring to fig. 2 Implementation process schematic diagram, concrete application method of the present embodiment as system described in embodiment one.It is described to be based on assembled The production management method of construction platform is executed by production management device, and the data production management device is configured at server, can By software and or hardware realization.
Assembled architecture platform described in the present embodiment includes server, first database and the second database, described one kind The equipment production information management method of assembled architecture platform is applied to server.It the described method comprises the following steps:
Step S201, when obtaining the Raw Material Demand amount and Raw Material Demand of current production plan from the first database Between;
In the present embodiment, the first database is for storing production plan data, including raw material coding, raw material Demand, Raw Material Demand time, Raw Material Demand station, operation number, production plan odd numbers and production plan performance number According to the production plan performance data include in not completing, producing, are completed.A production is selected in the present embodiment Plan performance data are unfinished production plan, and are set as current production plan.
Step S202 obtains current raw material store storage from second database;
In the present embodiment, second database is for storing raw material integrated information, including raw material coding, former material Gauge lattice, supplier information, serial code, raw material store storage, raw material geographical location information, entry time and Life Cycle issue According to.In the present embodiment, raw material are attached to identifiable identity, and each raw material have unique raw material information text Part, by identifying that the identity can the second database acquisition raw material integrated information.
Further, the file in second database is encoded with raw material and is named.It will be described by read-write equipment Raw material information file is written in raw material integrated information, and the raw material information file is named with serial code, the raw material letter File storage to the raw material are ceased to encode in corresponding file.
Preferably, the raw material store storage of raw material needed for the present embodiment only obtains current production plan.
Step S203, the size of the Raw Material Demand amount and the raw material store storage, if the raw material need The amount of asking is greater than the raw material store storage, then generates materials procurement instruction.
In the present embodiment, the Raw Material Demand that the assembled architecture platform will be got from the first database Amount data and the raw material store storage data got from the second database are compared, if per a in current production plan The demand of raw material is respectively less than its quantity in stock and then issues resource allocation instruction and fabrication order, refers to when receiving the resource allocation Resource allocation is carried out when enabling, the resource allocation is included in required time and required raw material is assigned to corresponding station before, When receiving the fabrication order, execution unit executes current production plan;If the Raw Material Demand amount data are greater than former material Expect that then the assembled architecture platform generates procurement directive to inventory data.
Further, the procurement directive generated in step S203 includes the raw material coding and raw material that need to be purchased Amount of purchase.
Preferably, the materials procurement amount is the Raw Material Demand amount and current raw material store storage of current production plan Difference.That is:
Materials procurement amount=current production plan Raw Material Demand amount-raw material store storage
Preferably, the difference of the estimated consumption of the raw material and current quantity in stock is difference A in a procurement cycle P, when The difference of the Raw Material Demand amount of preceding production plan and current raw material store storage is difference B, and the materials procurement amount is poor The greater in value A and difference B.I.e.
Preferably, the procurement cycle P is the average buying hour obtained according to the passing buying hour of the raw material.
Preferably, the procurement directive is pushed to preset buying terminal device.
Preferably, the procurement directive is pushed to relevant procurement staff.
Embodiment three
It is the equipment production information management of one of third embodiment of the invention assembled architecture platform refering to Fig. 3, Fig. 3 The implementation process schematic diagram of method.The difference of the present embodiment and second embodiment is, in the present embodiment after step S203 It further include S304~S305.S301~S303 particular content in the present embodiment please refers to S201~S203 in second embodiment Associated description, details are not described herein again.S304~S305 is specific as follows:
Step S304 obtains the raw material time of delivery from the third database;
In the present embodiment, third database is established in the server of the assembled architecture platform, for being stored in Way raw material data.It is described refer in way raw material purchased, but still on order raw material of supplier.The third number What it is according to library storage includes raw material coding, specifications of raw materials, supplier information and time of delivery in way raw material data.The friendship ETCD estimated time of commencing discharging refers to the estimated entry time in way raw material.
The raw material time of delivery is compared step S305 with the Raw Material Demand time, generates and compares knot Fruit;
In the present embodiment, after the completion of the procurement directive, the server of assembled architecture platform is by the raw material Time of delivery is compared with the Raw Material Demand time, generates comparison result.The comparison result represents raw material delivery Whether the time can satisfy the Raw Material Demand time of current production plan, and the comparison result includes: morning time of delivery In the Raw Material Demand time, the time of delivery is later than the Raw Material Demand time but earlier than deadline H and described Time of delivery is later than deadline H.
Further, step S305 further include:
Step S3051, if the comparison result is the time of delivery earlier than the Raw Material Demand time, basis is worked as Preceding production plan generates production ordering;
Step S3052, if the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than most Slow time limit H, then take level-one shortage of stock measure;
Step S3053 takes bi- inventory not if the comparison result is the time of delivery to be later than deadline H Sufficient measure.
In the present embodiment, the assembled architecture platform if the time of delivery is earlier than the Raw Material Demand time Server judges current production plan without adjustment, and the assembled architecture Platform Server assigns life to preset terminal device Instruction is produced, preset terminal device can be automatically processing device, be also possible to production information issue terminal, and user logs in It is available after production information issue terminal to arrive production ordering.
Further, the assembled architecture platform can also be under preset terminal device while assigning production ordering It is instructed up to resource allocation.The resource allocation instruction includes that raw material encode, raw material blending amount, demand station.It is described default Terminal device can be raw material blending equipment, be also possible to raw material deployment information issue terminal, user logs in former material The available resource allocation that arrives instructs after expecting deployment information issue terminal.
In the present embodiment, if the time of delivery is later than the Raw Material Demand time but earlier than deadline H, institute It states assembled architecture Platform Server and judges that raw material supply is not able to satisfy production plan demand, the assembled architecture platform clothes Business device takes level-one shortage of stock measure.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate from Raw material time of delivery at the latest.
Preferably, the level-one shortage of stock measure includes: to generate new production plan.
In the present embodiment, if the time of delivery is later than deadline H, the assembled architecture platform judges former material Material supply is not able to satisfy production plan demand, and the assembled architecture platform takes bi- inventory deficiency measure.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate from Raw material time of delivery at the latest.
Preferably, the bi- inventory deficiency measure includes: push raw material shortage of goods information to default terminal device.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each process Execution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limit It is fixed.
Example IV
It is a kind of equipment production information management device for assembled architecture platform that the embodiment of the present invention four provides referring to fig. 4 Schematic diagram, assembled architecture platform described in the present embodiment includes server, first database and the second database, described one kind The equipment production information management method of assembled architecture platform is applied to server.Described device includes:
First information acquiring unit 401, for obtaining the Raw Material Demand of current production plan from the first database Amount and Raw Material Demand time;
Second information acquisition unit 402, for obtaining current raw material store storage from second database;
Procurement directive generation unit 403, when being greater than current raw material store storage for the former material doses required for producing Generation unit generates materials procurement instruction.
Third information acquisition unit 404, for obtaining the raw material time of delivery from the third database;
Inventory analysis prewarning unit 405, for carrying out the raw material time of delivery and the Raw Material Demand time It compares, generates comparison result.
Fig. 5 is a kind of equipment production information management device inventory for assembled architecture platform that the embodiment of the present invention four provides The workflow schematic diagram of analysis and early warning unit 405, comprising:
If the comparison result is the time of delivery earlier than the Raw Material Demand time, according to current production plan Generate production ordering;
If the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than deadline H, Take level-one shortage of stock measure;
If the comparison result is the time of delivery to be later than deadline H, bi- inventory deficiency measure is taken.
Preferably, the level-one shortage of stock measure includes: to generate new production plan;
Preferably, the bi- inventory deficiency measure includes: push raw material shortage of goods information to default terminal device.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate from Raw material time of delivery at the latest.
Embodiment five
Fig. 6 is the schematic diagram for the terminal device that one embodiment of the invention provides.As shown in fig. 6, the terminal of the embodiment is set Standby 6 include: processor 60, memory 61 and are stored in the meter that can be run in the memory 61 and on the processor 60 Calculation machine program 62.The processor 60 is realized above-mentioned each based on assembled architecture platform when executing the computer program 62 Step in data processing method embodiment, such as step S301 to S305 shown in Fig. 3.Alternatively, the processor 60 executes The function of each module/unit in above-mentioned each Installation practice, such as module 401 shown in Fig. 4 are realized when the computer program 62 To 405 function.
Illustratively, the computer program 62 can be divided into one or more module/units, it is one or Multiple module/units are stored in the memory 61, and are executed by the processor 60, to complete the present invention.Described one A or multiple module/units can be the series of computation machine program instruction section that can complete specific function, which is used for Implementation procedure of the computer program 62 in the terminal device 6 is described.
The terminal device 6 can be desktop PC, notebook, palm PC, cloud server or server etc. Calculate equipment.The terminal device may include, but be not limited only to, processor 60, memory 61.Those skilled in the art can manage Solution, Fig. 6 is only the example of terminal device 6, does not constitute the restriction to terminal device 6, may include more or more than illustrating Few component perhaps combines certain components or different components, such as the terminal device can also be set including input and output Standby, network access equipment, bus etc..
Alleged processor 60 can be central processing unit (Central Processing Unit, CPU), can also be Other general processors, digital signal processor (Digital Signal Processor, DSP), specific integrated circuit (Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field- Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic, Discrete hardware components etc..General processor can be microprocessor or the processor is also possible to any conventional processor Deng.
The memory 61 can be the internal storage unit of the terminal device 6, such as the hard disk or interior of terminal device 6 It deposits.The memory 61 is also possible to the External memory equipment of the terminal device 6, such as be equipped on the terminal device 6 Plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital, SD) card dodge Deposit card (Flash Card) etc..Further, the memory 61 can also both include the storage inside list of the terminal device 6 Member also includes External memory equipment.The memory 61 is for storing needed for the computer program and the terminal device Other programs and data.The memory 61 can be also used for temporarily storing the data that has exported or will export.
It is apparent to those skilled in the art that for convenience of description and succinctly, only with above-mentioned each function Can unit, module division progress for example, in practical application, can according to need and by above-mentioned function distribution by different Functional unit, module are completed, i.e., the internal structure of described device is divided into different functional unit or module, more than completing The all or part of function of description.Each functional unit in embodiment, module can integrate in one processing unit, can also To be that each unit physically exists alone, can also be integrated in one unit with two or more units, it is above-mentioned integrated Unit both can take the form of hardware realization, can also realize in the form of software functional units.In addition, each function list Member, the specific name of module are also only for convenience of distinguishing each other, the protection scope being not intended to restrict the invention.Above system The specific work process of middle unit, module, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In the above-described embodiments, it all emphasizes particularly on different fields to the description of each embodiment, is not described in detail or remembers in some embodiment The part of load may refer to the associated description of other embodiments.
Those of ordinary skill in the art may be aware that list described in conjunction with the examples disclosed in the embodiments of the present disclosure Member and algorithm steps can be realized with the combination of electronic hardware or computer software and electronic hardware.These functions are actually It is implemented in hardware or software, the specific application and design constraint depending on technical solution.Professional technician Each specific application can be used different methods to achieve the described function, but this realization is it is not considered that exceed The scope of the present invention.
In embodiment provided by the present invention, it should be understood that disclosed device/terminal device and method, it can be with It realizes by another way.For example, device described above/terminal device embodiment is only schematical, for example, institute The division of module or unit is stated, only a kind of logical function partition, there may be another division manner in actual implementation, such as Multiple units or components can be combined or can be integrated into another system, or some features can be ignored or not executed.Separately A bit, shown or discussed mutual coupling or direct-coupling or communication connection can be through some interfaces, device Or the INDIRECT COUPLING or communication connection of unit, it can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated module/unit be realized in the form of SFU software functional unit and as independent product sale or In use, can store in a computer readable storage medium.Based on this understanding, the present invention realizes above-mentioned implementation All or part of the process in example method, can also instruct relevant hardware to complete, the meter by computer program Calculation machine program can be stored in a computer readable storage medium, the computer program when being executed by processor, it can be achieved that on The step of stating each embodiment of the method.Wherein, the computer program includes computer program code, the computer program generation Code can be source code form, object identification code form, executable file or certain intermediate forms etc..The computer-readable medium It may include: any entity or device, recording medium, USB flash disk, mobile hard disk, magnetic that can carry the computer program code Dish, CD, computer storage, read-only memory (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), electric carrier signal, telecommunication signal and software distribution medium etc..It should be noted that the meter The content that calculation machine readable medium includes can carry out increase and decrease appropriate according to the requirement made laws in jurisdiction with patent practice, Such as in certain jurisdictions, according to legislation and patent practice, computer-readable medium do not include be electric carrier signal and electricity Believe signal.
Embodiment described above is merely illustrative of the technical solution of the present invention, rather than its limitations;Although referring to aforementioned reality Applying example, invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned each Technical solution documented by embodiment is modified or equivalent replacement of some of the technical features;And these are modified Or replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution should all It is included within protection scope of the present invention.

Claims (10)

1. a kind of equipment production information management method of assembled architecture platform, the assembled architecture platform includes server, First database, the second database, which is characterized in that the equipment production information management method includes:
Raw Material Demand amount and the Raw Material Demand time of current production plan are obtained from the first database;
Current raw material store storage is obtained from second database;
Compare the size of the Raw Material Demand amount and the raw material store storage, if the Raw Material Demand amount is greater than the original Storage of materials then generates materials procurement instruction.
2. equipment production information management method according to claim 1, which is characterized in that the assembled architecture platform is also Including third database;The equipment production information management method further include:
The raw material time of delivery is obtained from the third database;
The raw material time of delivery is compared with the Raw Material Demand time, generates comparison result;
If the comparison result is the time of delivery earlier than the Raw Material Demand time, generated according to current production plan Production ordering;
If the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than deadline H, take Level-one shortage of stock measure;
If the comparison result is the time of delivery to be later than deadline H, bi- inventory deficiency measure is taken.
3. equipment production information management method according to claim 2, which is characterized in that the deadline H is basis Raw material time of delivery at the latest from being generated from the procurement directive of production and operation situation setting.
4. equipment production information management method according to claim 2, which is characterized in that the level-one shortage of stock measure It include: to generate new production plan.
5. equipment production information management method according to claim 2, which is characterized in that the bi- inventory deficiency measure It include: push raw material shortage of goods information to default terminal device.
6. a kind of equipment production information management device of assembled architecture platform, the assembled architecture platform includes server, First database, the second database, which is characterized in that the equipment production information management device includes:
First information acquiring unit, for obtaining the Raw Material Demand amount and former material of current production plan from the first database Expect required time;
Second information acquisition unit, for obtaining current raw material store storage from second database;
Procurement directive generation unit, generation unit when being greater than current raw material store storage for the former material doses required for producing Generate materials procurement instruction.
7. a kind of equipment production information management device of assembled architecture platform according to claim 6, which is characterized in that The assembled architecture platform further includes third database:
Third information acquisition unit, for obtaining the raw material time of delivery from the third database;
Inventory analysis prewarning unit, it is raw for the raw material time of delivery and the Raw Material Demand time to be compared At comparison result;If the comparison result is the time of delivery earlier than the Raw Material Demand time, according to current production Plan generates production ordering;If the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than at the latest Time limit H then takes level-one shortage of stock measure;If the comparison result is the time of delivery to be later than deadline H, take Bi- inventory deficiency measure.
The level-one shortage of stock measure includes: to generate new production plan;
The bi- inventory deficiency measure includes: push raw material shortage of goods information to default terminal device.
8. a kind of equipment production information management device of assembled architecture platform according to claim 7, which is characterized in that The deadline H is delivered goods at the latest according to the raw material from procurement directive generation of production and operation situation setting Time limit.
9. a kind of terminal device, including memory, processor and storage are in the memory and can be on the processor The computer program of operation, which is characterized in that the processor realizes such as claim 1 to 5 when executing the computer program The step of any one the method.
10. a kind of computer readable storage medium, the computer-readable recording medium storage has computer program, and feature exists In when the computer program is executed by processor the step of any one of such as claim 1 to 5 of realization the method.
CN201811105789.1A 2018-09-21 2018-09-21 The equipment production information management method and device of assembled architecture platform Pending CN109559070A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811105789.1A CN109559070A (en) 2018-09-21 2018-09-21 The equipment production information management method and device of assembled architecture platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811105789.1A CN109559070A (en) 2018-09-21 2018-09-21 The equipment production information management method and device of assembled architecture platform

Publications (1)

Publication Number Publication Date
CN109559070A true CN109559070A (en) 2019-04-02

Family

ID=65864587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811105789.1A Pending CN109559070A (en) 2018-09-21 2018-09-21 The equipment production information management method and device of assembled architecture platform

Country Status (1)

Country Link
CN (1) CN109559070A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109993487A (en) * 2019-04-12 2019-07-09 湖南长螺节能科技有限公司 The method and device of material supply scheme in warehouse is determined based on engineering project
CN111191984A (en) * 2019-12-25 2020-05-22 深圳市智微智能软件开发有限公司 Solder paste inventory management method and system
CN112541649A (en) * 2019-09-23 2021-03-23 珠海格力电器股份有限公司 Scheduling method of part cutting material, storage medium and electronic device
CN113570307A (en) * 2021-07-22 2021-10-29 江苏金小满信息科技有限公司 Engineering material procurement management system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1277401A (en) * 1999-06-14 2000-12-20 神达电脑股份有限公司 Production plan and order form system
JP2007179306A (en) * 2005-12-28 2007-07-12 Hitachi Ltd Production planning method and device for joint product item
CN102467702A (en) * 2010-11-05 2012-05-23 徐州中矿微星软件有限公司 Inventory control method for extractive industries
CN104331770A (en) * 2014-11-03 2015-02-04 叶校然 Intelligent management system of flexible production enterprise
CN107133769A (en) * 2017-05-31 2017-09-05 浙江精工钢结构集团有限公司 A kind of intelligent inventory pre-warning management system based on BIM models
CN108446950A (en) * 2018-02-11 2018-08-24 成都兴联宜科技有限公司 A kind of concrete raw material budget purchasing system based on Fabrication Order

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1277401A (en) * 1999-06-14 2000-12-20 神达电脑股份有限公司 Production plan and order form system
JP2007179306A (en) * 2005-12-28 2007-07-12 Hitachi Ltd Production planning method and device for joint product item
CN102467702A (en) * 2010-11-05 2012-05-23 徐州中矿微星软件有限公司 Inventory control method for extractive industries
CN104331770A (en) * 2014-11-03 2015-02-04 叶校然 Intelligent management system of flexible production enterprise
CN107133769A (en) * 2017-05-31 2017-09-05 浙江精工钢结构集团有限公司 A kind of intelligent inventory pre-warning management system based on BIM models
CN108446950A (en) * 2018-02-11 2018-08-24 成都兴联宜科技有限公司 A kind of concrete raw material budget purchasing system based on Fabrication Order

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109993487A (en) * 2019-04-12 2019-07-09 湖南长螺节能科技有限公司 The method and device of material supply scheme in warehouse is determined based on engineering project
CN112541649A (en) * 2019-09-23 2021-03-23 珠海格力电器股份有限公司 Scheduling method of part cutting material, storage medium and electronic device
CN111191984A (en) * 2019-12-25 2020-05-22 深圳市智微智能软件开发有限公司 Solder paste inventory management method and system
CN113570307A (en) * 2021-07-22 2021-10-29 江苏金小满信息科技有限公司 Engineering material procurement management system

Similar Documents

Publication Publication Date Title
CN109559069A (en) Production management method, apparatus and terminal device based on assembled architecture platform
Fadeyi The role of building information modeling (BIM) in delivering the sustainable building value
CN109557934A (en) A kind of control method and device of the unmanned plane cruise based on assembled architecture platform
CN109559070A (en) The equipment production information management method and device of assembled architecture platform
CN101901428B (en) A kind of electricity market simulating system adopting SOA technology
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN109559379A (en) A kind of panorama based on assembled architecture platform sees room method and device
CN109559006A (en) A kind of monitoring method, device and the terminal device of the construction site based on unmanned plane
CN109447481A (en) A kind of live cost monitoring system and method based on threedimensional model
KR101690211B1 (en) Bim-based construction value engineering (ve) processing system
WO2020056669A1 (en) Control method and apparatus for unmanned aerial vehicle cruise based on prefabricated building platform
CN109559086A (en) Checking method, device and terminal device based on BIM light weighed model
KR101167850B1 (en) Method on Generating Expaned Fee Information by Unit Item Comprising Direct Fee of Construction Cost Including Small Space or Element Information
CN108846644A (en) A kind of integrated emulation technology, collaborative work, information management and project management managing and control system
CN109460834A (en) Build operation management system and its management method
CN101163067A (en) Building industry cooperation network management system and management method thereof
CN110019435A (en) Data processing method and system based on assembled architecture platform
Yang et al. Building energy management systems
CN109558047A (en) Property based on BIM light weighed model reports method, apparatus and terminal device for repairment
CN108052726A (en) A kind of building materials business and construction Information uploading system based on BIM models
Baiardi et al. The integrated project for the redevelopment of a historic building: an example of BIM and IoT integration to manage the comfort of the building
KR101081880B1 (en) Construction Cost Information Processing System Including Small Space or Element Information and the Method on it
Zhang et al. Exploring the construction of an all-round cost management system for investment control in university engineering construction
Li Integrating building information modelling (BIM), cost estimating and scheduling for buildings construction at the conceptual design stage
Rojas Wettling et al. IDM for the Conceptual Evaluation Process of Industrialized Timber Projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination