CN109993487A - The method and device of material supply scheme in warehouse is determined based on engineering project - Google Patents
The method and device of material supply scheme in warehouse is determined based on engineering project Download PDFInfo
- Publication number
- CN109993487A CN109993487A CN201910292535.3A CN201910292535A CN109993487A CN 109993487 A CN109993487 A CN 109993487A CN 201910292535 A CN201910292535 A CN 201910292535A CN 109993487 A CN109993487 A CN 109993487A
- Authority
- CN
- China
- Prior art keywords
- identification code
- warehouse
- engineering project
- inventory
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K17/00—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
- G06K17/0022—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/087—Inventory or stock management, e.g. order filling, procurement or balancing against orders
- G06Q10/0875—Itemisation or classification of parts, supplies or services, e.g. bill of materials
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Abstract
The embodiment of the invention discloses a kind of methods for determining material supply scheme in warehouse based on engineering project, are applied to warehouse management system, which comprises according to engineering project, the material information of material needed for determining the engineering project;According to the material information, the inventory information in warehouse with the matched material of the material information is determined;According to the material information and the inventory information, the material supply scheme of the engineering project is determined.The embodiment of the present invention further simultaneously discloses one kind and determines that material feeds scheme device, computer storage medium in warehouse based on engineering project.
Description
Technical field
The present invention relates to storage production management fields, more particularly to one kind to determine that material is fed in warehouse based on engineering project
The method, apparatus and computer storage medium of scheme.
Background technique
In current storehouse management, when an engineering project temporarily, can not quickly learn each needed for engineering project production
The quantity in stock of kind material or material, cannot find the shortage of stores or supplies in time, engineering project is caused not complete on schedule.
Summary of the invention
In view of this, the main purpose of the embodiment of the present invention be to provide it is a kind of can quickly be determined according to engineering project described in
The method of the material supply scheme of engineering project, can find the shortage of material in time, improve the completion efficiency of engineering project, simultaneously
Also be avoided that material waste determines that the method, apparatus of material supply scheme and computer storage are situated between in warehouse based on engineering project
Matter.
In order to achieve the above objectives, the technical solution of the embodiment of the present invention is achieved in that
The embodiment of the invention provides a kind of methods for determining material supply scheme in warehouse based on engineering project, are applied to
In warehouse management system, which comprises
According to engineering project, the material information of material needed for determining the engineering project;
According to the material information, the inventory information in warehouse with the matched material of the material information is determined;
According to the material information and the inventory information, the material supply scheme of the engineering project is determined.
In above scheme, the material information includes: first material identification code and corresponding with the first material identification code
First material usage amount;
It is described according to engineering project, the material information of material needed for determining the engineering project, comprising:
According to engineering project, the first material identification code of material needed for determining the engineering project and with the first material
The corresponding first material usage amount of identification code.
In above scheme, the inventory information includes at least one of: second material identification code and the second material
The corresponding quantity in stock of identification code, inventory's area occupied of single material corresponding with the second material identification code, with described the
The inventory of the corresponding single material of two material identification codes stores warehouse label, single object corresponding with the second material identification code
Inventory's resting period of material.
It is described according to the material information in above scheme, it determines in warehouse and believes with the matched inventory of the material information
Breath, comprising:
According to the first material identification code in the material information, the object with the first material codes match is inquired
Expect the second material identification code in warehouse;
According to the second material identification code, the quantity in stock corresponding with the second material identification code, described is determined
It is inventory's area occupied of single material corresponding with the second material identification code, described corresponding with the second material identification code
Single material inventory store warehouse label, the single material corresponding with the second material identification code inventory store
Time at least one of them.
It is described according to the material information and the inventory information in above scheme, determine the material of the engineering project
Supply scheme, including at least one of:
According to the first material usage amount corresponding with the first material identification code and described and second object
Expect the corresponding quantity in stock of identification code, determines the quantity of the purchase material needed for the engineering project;
According to the first material usage amount corresponding with the first material identification code and described and second object
The inventory's area occupied for expecting the corresponding single material of identification code, determines the storage area vacated in the engineering project;
According to the first material usage amount corresponding with the first material identification code and described and second object
Expect that the inventory of the corresponding single material of identification code stores warehouse label, with determining the warehouse that the material is taken in the engineering project
Location;
According to first material usage amount corresponding with the first material identification code and with the second material identification code
Inventory's resting period of corresponding single material, determine the priority that the material is taken in the engineering project.
In above scheme, the method also includes:
Pre-establish the inventory database in the warehouse;Wherein, the inventory database includes: inventory's letter of the material
Breath.
In above scheme, the method also includes:
It is corresponding to update the corresponding inventory information of the material when determining has material to enter and/or take out from the warehouse,
And updated inventory information is stored in the inventory database.
To achieve the above object, the embodiment of the invention also provides determine that material feeds scheme in warehouse based on engineering project
Device, described device includes: processor and for storing the memory that can run computer program on a processor, wherein
When the processor is used to run the computer program, realization is described in any of the above embodiments to be determined in warehouse based on engineering project
The method of material supply scheme.
To achieve the above object, the embodiment of the invention also provides a kind of computer storage mediums, are stored with executable journey
Sequence, when the executable code processor executes, realization is described in any of the above embodiments to determine object in warehouse based on engineering project
Expect the method for supply scheme.
The method, apparatus and calculating of material supply scheme in warehouse are determined provided by above-described embodiment based on engineering project
Machine storage medium, by according to engineering project, the material information of material needed for determining the engineering project;Believed according to the material
Breath, determines the inventory information of the matched material of material information described in warehouse;According to the material information and the inventory information,
Determine the material supply scheme of the engineering project.It so, it is possible by the material information and warehouse in engineering project
The inventory information, intelligently determine the supply scheme of the material of the engineering project, that is to say, that the material supply side
The formulation of case is that the inventory information of material in the material information and warehouse of the material as needed for engineering project codetermines, therefore,
The material service condition that the inventories and the engineering project of material in warehouse can be fully taken into account, can not only be replenished in time
Material needed for engineering project, moreover it is possible to avoid blind purchase material when engineering project arrives and cause a large amount of manpower, material wealth
The consumption of power can also timely use the material in warehouse according to inventory information further to mitigate inventory and store cost.
Detailed description of the invention
Fig. 1 is the method flow for determining material supply scheme in warehouse provided by the embodiment of the present invention based on engineering project
Schematic diagram;
Fig. 2 is the use for determining material supply scheme in warehouse provided by the specific embodiment of the invention based on engineering project
One schematic diagram of a scenario;
Fig. 3 is to determine that material feeds the another of scheme in warehouse based on engineering project provided by the specific embodiment of the invention
Usage scenario schematic diagram;
Fig. 4 is to determine that material feeds the another of scheme in warehouse based on engineering project provided by the specific embodiment of the invention
Usage scenario schematic diagram;
The function of the device of material supply scheme in warehouse is determined provided by Fig. 5 embodiment of the present invention based on engineering project
Structural schematic diagram;
Fig. 6 is to determine that material in warehouse feeds the hard of the device of scheme based on engineering project provided by the embodiment of the present invention
Part structural schematic diagram.
Specific embodiment
The present invention is further described in detail below with reference to the accompanying drawings and embodiments.It should be appreciated that described herein
Specific embodiment is only used to explain the present invention, is not intended to limit the present invention.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention
The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool
The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term as used herein "and/or" includes one or more phases
Any and all combinations of the listed item of pass.
The method that material supply scheme in warehouse is determined based on engineering project provided by the embodiment of the present invention, it is main to apply
In warehouse management system, which can be deployed in mobile terminal and/or server.
Based on above-mentioned warehouse management system, the embodiment of the present invention proposes one kind and determines material in warehouse based on engineering project
The method of supply scheme.Fig. 1 is to determine that material feeds scheme in warehouse based on engineering project provided by the embodiment of the present invention
Method flow schematic diagram, referring to Fig. 1, the described method comprises the following steps:
Step S101: according to engineering project, the material information of material needed for determining the engineering project.
Here, the engineering project may include construction-engineering project or production engineering project, in a word the work
Journey project is that can use the correlation engineering project of the material in warehouse included in the warehouse management system.
Here, the material information include: first material identification code and with the first material identification code corresponding first
Material usage amount.It is understood that each engineering project will be corresponding with multiple materials, for example, for an architectural engineering
For project, material needed for the construction-engineering project may include casement window, cement, brick, reinforcing bar etc..Here, to each
Kind material setting first material identification code is stored in warehouse management system, in this way, can be indicated according to first material identification code
The material out indicates the casement window of 01 model for example, the first material identification code of casement window is pkc01.Utilize first material
Identification code quickly identifies material to mark first material to can be convenient processor.
Here, described according to engineering project, the material information of material needed for determining the engineering project, comprising: according to work
Journey project, the first material identification code of material needed for determining the engineering project and corresponding with the first material identification code
One material usage amount.It is understood that each engineering project should be corresponding with engineering project institute material to be used
Inventory, the title of material and the usage amount of material are contained in the inventory of the material, in this way, can be by the clear of the material
It is singly entered into the system, by the system according to the Text region in the inventory, determines the engineering project required thing
The first material identification code of material and first material usage amount corresponding with the first material identification code.For example, in a building
In engineering project, casement window 50 of 01 model are needed, by these data inputs into the system, system will identify that 01 type
Number casement window first material identification code be pkc01, identify the casement window of 01 model first material usage amount be 50.
It should be noted that the method also includes: record the engineering project project label and the engineering project
Corresponding relationship between the material information of required material;According to the corresponding relationship, the corresponding engineering of the project label is determined
The first material identification code of material needed for project and the corresponding first material usage amount of the first material identification code.Here,
Based on to engineering project carry out project label, compared to directly use engineering project title for, system compare project label and
For the title for comparing engineering project, the result of identification is more accurate, and simultaneity factor identification is got up also faster.
Step S102: it according to the material information, determines in warehouse and believes with the inventory of the matched material of the material information
Breath.
Here, the inventory information includes at least one of: second material identification code and the second material identification code
Corresponding quantity in stock, inventory's area occupied of single material corresponding with the second material identification code and the second material
The inventory of the corresponding single material of identification code stores the library of warehouse label, single material corresponding with the second material identification code
Deposit the resting period.
It should be noted that in some embodiments, first material identification code can be phase with second material identification code
Same mark can so allow system identification to be got up more quickly.For example, first material identification code is pkc01, then direct basis
The second material identification code that the first material identification code is found in inventory management system in warehouse for marking material is also
Pkc01, so that it is determined that the inventory information in warehouse with the matched material of the material information.In other embodiments, institute
It states first material identification code and second material identification code can be different mark, for example, being identified for same material
First material identification code or user's first material identification code directly inputted and second material identification code between have it is predetermined
Transformation rule, or have scheduled password, for example, for the casement window of 01 model, first material identification code is
Pck01, and second material identification code is 2019pck01.In the present embodiment, the step 102 further include: according to the material
Information and the first input information received, determine the inventory information in warehouse with the matched material of the material information.This
In, the first input information be then the system receive inquiry's input the first material identification code be deformed to it is described
The character of the preset rules of second material identification code.In this way, the personnel other than system manager can be prevented to the object in warehouse
The inquiry of material improves the confidentiality of the inventory information of warehouse management system.
Further, described according to the material information, determine in warehouse with the matched inventory information of the material information,
It include: that the material with the first material codes match is inquired according to the first material identification code in the material information
Second material identification code in warehouse;According to the second material identification code, the described and second material identification code is determined
Corresponding quantity in stock, the single material corresponding with the second material identification code inventory's area occupied, it is described with it is described
The inventory of the corresponding single material of second material identification code stores warehouse label, described corresponding with the second material identification code
Inventory's resting period at least one of them of single material.
Specifically, Fig. 2 is seen, Fig. 2 is to determine in warehouse provided by the specific embodiment of the invention based on engineering project
Material feeds a usage scenario schematic diagram of scheme, as shown in Fig. 2, system can be according to the first material mark in the material information
Know code, inquires the second material identification code with the material of the first material codes match in warehouse;Here, the object
Material is a variety of different 50 casement windows, each 50 different casement window, possible color, and the difference such as height all corresponds to different the
One material identification code, here, the first material identification code and second material identification code are bar code.As can be seen from Figure 2, system
Can according to the second material identification code, determine the quantity in stock corresponding with the second material identification code, it is described and
It is inventory's area occupied of the corresponding single material of the second material identification code, described corresponding with the second material identification code
When the inventory of single material stores inventory's storage of warehouse label, the single material corresponding with the second material identification code
Between at least one of them.For example, the quantity in stock for 50 casement windows that second material identification code is 20181115002002 is 5, it is corresponding
Inventory's area occupied be 27.791, it is aluminium alloy at the corresponding resting period is not shown, but has that corresponding inventory, which stores warehouse,
A little embodiments can also find out the corresponding resting period.In this way, institute can intelligently be obtained directly according to engineering project
Inventory information of the material needed for engineering project in warehouse is stated, to specify and be adapted to each of inventory information according to inventory information
Kind material feeds scheme, improves user experience.
Referring to Fig. 3, Fig. 3 is to determine that material is fed in warehouse based on engineering project provided by the specific embodiment of the invention
Another usage scenario schematic diagram of scheme, as shown in figure 3, system can according to the first material identification code in the material information,
Inquire the second material identification code with the material of the first material codes match in warehouse;Here, the material is
A variety of different Hardware fittings, each different Hardware fitting, the corresponding supplier of possibility, color, height, are averaged at thickness
The difference such as weight, unit price all corresponds to different first material identification codes, here, the first material identification code and second material mark
Know the equal material class number of code.As can be seen from Figure 3, system can be determined described with described second according to the second material identification code
At least one of them such as the corresponding supplier of material identification code, warehouse title, unit price.Here, second material identification code is wide Asia-
Fanning the corresponding supplier of window GIB450SCS is Hunan Guang Yaquanlv household Co., Ltd, the corresponding entitled profile warehouse in warehouse
Deng the corresponding resting period is not shown, but some embodiments can also find out the corresponding resting period.In this way, can be with
Directly according to engineering project, inventory information of the material needed for intelligently obtaining the engineering project in warehouse, so as to according to library
Information is deposited, the specified various materials supply scheme for being adapted to inventory information improves user experience.
Referring to Fig. 4, Fig. 4 is to determine that material is fed in warehouse based on engineering project provided by the specific embodiment of the invention
Another usage scenario schematic diagram of scheme, as shown in figure 4, system can according to the first material identification code in the material information,
Inquire the second material identification code with the material of the first material codes match in warehouse;Here, the material is
A variety of different aluminium alloys, each different aluminium alloy, possible corresponding supplier, color, specification, unit price etc. are different all right
Different first material identification codes is answered, here, the first material identification code and the equal material class number of second material identification code.From figure
4 it is found that system can determine the supply corresponding with the second material identification code according to the second material identification code
At least one of them such as quotient, warehouse title, color, specification.For example, second material identification code is the bright -16 cun/16.5mm of sliding support of heavily fortified point
Corresponding supplier is Guangdong Jian Lang product limited liability company, and corresponding entitled Hardware fitting warehouse in warehouse etc. is corresponding
Resting period is not shown, but some embodiments can also find out the corresponding resting period.In this way, can be directly according to work
Journey project, inventory information of the material needed for intelligently obtaining the engineering project in warehouse, to specify according to inventory information
It is adapted to the various materials supply scheme of inventory information, improves user experience.
Step S103: according to the material information and the inventory information, the material supply side of the engineering project is determined
Case.
Specifically, described according to the material information and the inventory information, determine the material supply of the engineering project
Scheme, including at least one of: according to the first material usage amount corresponding with the first material identification code and institute
Quantity in stock corresponding with the second material identification code is stated, determines the quantity of the purchase material needed for the engineering project;Root
According to the first material usage amount corresponding with the first material identification code and the described and second material identification code pair
The inventory's area occupied for the single material answered, determines the storage area vacated in the engineering project;According to it is described with it is described
The corresponding first material usage amount of first material identification code and the single material corresponding with the second material identification code
Inventory store warehouse label, determine the warehouse address that the material is taken in the engineering project;According to the first material
When the inventory of the corresponding first material usage amount of identification code and single material corresponding with the second material identification code stores
Between, determine the priority that the material is taken in the engineering project.
Here, the first material usage amount corresponding with the first material identification code according to and described and institute
The corresponding quantity in stock of second material identification code is stated, determines the quantity of the purchase material needed for the engineering project, it is possible to understand that
For, system can according to the first material usage amount corresponding with the first material identification code, for example,
The usage amount of 20181115002002 50 casement windows is 10 and the inventory corresponding with the second material identification code
Amount calculates first object for needing to buy for example, the quantity in stock of 20,181,115,002,002 50 casement windows is 5 automatically
Expect the quantity of the corresponding material of identification code.Here, the quantity for calculating the material that needs are bought automatically is 5.It so, it is possible
Intelligently obtain the few order for also needing to avoid material to the replenishment quantity in warehouse to complete the engineering project, not in place, object
Phenomena such as material shortage.
Here, the first material usage amount corresponding with the first material identification code according to and described and institute
The inventory's area occupied for stating the corresponding single material of second material identification code determines the warehouse face vacated in the engineering project
Product, it can be understood as, system can according to the first material usage amount corresponding with the first material identification code, for example,
The usage amount of 20181115002002 50 casement windows is for 1 and described corresponding with the second material identification code single
Inventory's area occupied of material, for example, 20181115002002 50 casement windows area occupied be 27.791, calculate automatically
The storage area vacated in the engineering project.In this way, can know the storage area vacated in time, be conducive to the library in warehouse
Management is deposited, so that enough storage spaces can be judged whether there is in time in new material warehouse entry.
Here, the first material usage amount corresponding with the first material identification code according to and described and institute
The inventory for stating the corresponding single material of second material identification code stores warehouse label, determines and takes the material in the engineering project
Warehouse address, it can be understood as, system can be used according to corresponding with the first material identification code first material
Amount, for example, the usage amount of 20,181,115,002,002 50 casement windows is 1, and corresponding with the second material identification code
The inventory of single material stores warehouse label, for example, 20181115002002 50 casement windows warehouse marked as A, and warehouse mark
Number entitled aluminium alloy in the corresponding warehouse A is at warehouse name is corresponding with warehouse address, to intelligently push the engineering for inquiry
Work is improved so that engineering project responsible person can get rapidly required material in the warehouse address of the materials warehouse of material needed for project
Journey item purpose progress.
Here, basis first material usage amount corresponding with the first material identification code and with second object
The inventory's resting period for expecting the corresponding single material of identification code, determine the priority that the material is taken in the engineering project, it can
To be interpreted as, system can according to first material usage amount corresponding with the first material identification code, for example,
The usage amount of 20181115002002 50 casement windows is 1, and single material corresponding with the second material identification code
Inventory's resting period, it is successive according to inventory's resting period of the corresponding single material of the second material identification code, for institute
Stating engineering project recommends resting period longer material to be got, so as to be conducive to preferentially use inventory's resting period
Long material, avoid material for a long time store caused by corrosion, in turn result in engineering project quality it is bad the problems such as.Certainly,
In some embodiments, basis first material usage amount corresponding with the first material identification code and with described
It inventory's resting period of the corresponding single material of two material identification codes, determines and takes the preferential of the material in the engineering project
Grade, further includes: identified according to first material usage amount corresponding with the first material identification code and with the second material
Inventory's resting period of the corresponding single material of code identifies the corresponding second material that inventory's resting period is greater than threshold value
The corresponding single material of code carries out excluding and then determining the priority for taking the material in the engineering project.In this way, can base
At least expired obsolete material can also be foreclosed while preferentially using resting period more long material, promote work
Journey item purpose quality.
Further, the method also includes: system pre-establishes the inventory database in the warehouse;Wherein, the library
Deposit data library includes: the inventory information of the material.
Further, the method also includes: when determine there is material to enter and/or take out from the warehouse when, correspondence more
The newly corresponding inventory information of the material, and updated inventory information is stored in the inventory database.In this way, can be with
It when based on each inquiry is carried out on the basis of latest data, can guarantee the accuracy of inquiry data, to improve base
The availability of material supply scheme in warehouse is determined in engineering project.
The method for determining material supply scheme in warehouse based on engineering project provided by the embodiment of the present invention, passes through basis
Engineering project, the material information of material needed for determining the engineering project;According to the material information, object described in warehouse is determined
Expect the inventory information of the material of information matches;According to the material information and the inventory information, the engineering project is determined
Material feeds scheme.It so, it is possible through the material information in engineering project and the inventory information in warehouse, intelligence
Determine the supply scheme of the material of the engineering project in ground, that is to say, that the formulation that the material feeds scheme is by engineering project
The inventory information of material codetermines in the material information and warehouse of required material, therefore, object in warehouse can be fully taken into account
The material service condition of the inventories of material and the engineering project, material needed for engineering project can not only be replenished in time, also
Blind purchase material causes the consumption of a large amount of manpower, material financial resources when being avoided that engineering project arrival, further can also root
The material in warehouse has been timely used according to inventory information to mitigate inventory and store cost.
In order to further understanding convenient for the searching method to multimedia messages provided by the embodiment of the present application, mention
A specific embodiment is supplied, the project is by taking construction-engineering project as an example.
In the present embodiment, the system comprises the programs of a fast search current material amount, here, the current material
Amount can be understood as quantity in stock described in above-described embodiment.For example, when the aluminium, the shaped plastics that need to know to produce required door and window wall
Material, glass, Hardware fitting, auxiliary, finished product various quantity when, the method provided through the embodiment of the present invention can be checked quickly fastly
The quantity in stock in door and window curtain wall material storehouse management system is ask, finds the shortage of material, the program remedied in time in time.It is practical
On, described program is established based on a door and window curtain wall material storehouse inventory database.In door and window curtain wall material storehouse library
The material stored in deposit data library is using unified standard name, and here, the material can be understood as using unified standard name
The first material identification code of the material.
In this way, the embodiment of the present invention can quickly know the presence or absence of material and quantity, the extra order of material is avoided,
Warehouse space is wasted, warehouse space utilization rate is made to get a promotion, while also avoiding the product storehouse waste of excess stock, and is increased more
Remaining management and maintenance expense.And can quickly know to be produced as finished product quantity, it delivers in time, not will cause warehouse space finished product goods
Object collection pressure, utilization rate of warehouse get a promotion.
Further, the embodiment of the present invention also provides a kind of dress that material supply scheme in warehouse is determined based on engineering project
It sets, Fig. 5 is the function knot for determining the device of material supply scheme in warehouse provided by the embodiment of the present invention based on engineering project
Structure schematic diagram, as shown in figure 5, the device for determining material supply scheme in warehouse based on engineering project, comprising: first determines
Module 51, the second determining module 52 and third determining module 53;Wherein,
First determining module 51, for according to engineering project, the material of material needed for determining the engineering project to be believed
Breath;
Second determining module 52, for determining in warehouse and being matched with the material information according to the material information
Material inventory information;
The third determining module 53, for determining the engineering item according to the material information and the inventory information
Purpose material feeds scheme.
Optionally, the material information includes: first material identification code and corresponding with the first material identification code
One material usage amount;First determining module 51 is also used to according to engineering project, material needed for determining the engineering project
First material identification code and first material usage amount corresponding with the first material identification code.
Optionally, described device further include: logging modle, for record the engineering project project label and the work
Corresponding relationship between the material information of material needed for journey project;According to the corresponding relationship, the determining and project label pair
The first material identification code of material needed for the engineering project answered and first material corresponding with the first material identification code make
Dosage.
Optionally, the inventory information includes at least one of: second material identification code is identified with the second material
The inventory's area occupied and second object of the corresponding quantity in stock of code, single material corresponding with the second material identification code
The inventory for expecting the corresponding single material of identification code stores warehouse label, single material corresponding with the second material identification code
Inventory's resting period.
Optionally, second determining module 52 is also used to be looked into according to the first material identification code in the material information
Ask out the second material identification code with the material of the first material codes match in warehouse;According to the second material mark
Know code, determines the corresponding quantity in stock of the described and described second material identification code, described corresponding with the second material identification code
Inventory's area occupied of single material, the inventory of the single material corresponding with the second material identification code store warehouse mark
Number, inventory's resting period at least one of them of the single material corresponding with the second material identification code.
Optionally, the third determining module 53, is also used to execute at least one of:
According to the first material usage amount corresponding with the first material identification code and described and second object
Expect the corresponding quantity in stock of identification code, determines the quantity of the purchase material needed for the engineering project;
According to the first material usage amount corresponding with the first material identification code and described and second object
The inventory's area occupied for expecting the corresponding single material of identification code, determines the storage area vacated in the engineering project;
According to the first material usage amount corresponding with the first material identification code and described and second object
Expect that the inventory of the corresponding single material of identification code stores warehouse label, with determining the warehouse that the material is taken in the engineering project
Location;
According to first material usage amount corresponding with the first material identification code and with the second material identification code
Inventory's resting period of corresponding single material, determine the priority that the material is taken in the engineering project.
Optionally, described device further includes establishing module, for pre-establishing the inventory database in the warehouse;Wherein,
The inventory database includes: the inventory information of the material.
Optionally, described device further includes update module, for having material to enter and/or take out from the warehouse when determination
When, it is corresponding to update the corresponding inventory information of the material, and updated inventory information is stored in the inventory database.
It is provided by the above embodiment to determine that the device of material supply scheme in warehouse is being carried out based on work based on engineering project
When journey project determines the method for material supply scheme in warehouse, only carried out with the division of above-mentioned each program module for example, real
In the application of border, it can according to need and complete above-mentioned processing distribution by different program modules, i.e., by the content structure of device
It is divided into different program modules, to complete all or part of processing described above.In addition, base provided by the above embodiment
Material supply scheme in warehouse is determined with based on engineering project in the device that engineering project determines that material feeds scheme in warehouse
Embodiment of the method belongs to same design, and specific implementation process is detailed in embodiment of the method, and which is not described herein again.
As shown in fig. 6, the terminal or server include depositing the embodiment of the invention also provides a kind of terminal or server
Reservoir 62, processor 61 and it is stored in the computer instruction that can be run on memory 62 and on processor 61;The processor
It is realized when 61 execution described instruction and determines that material is mended in warehouse based on engineering project applied in the server or terminal
To scheme method the step of.
In some embodiments, the memory 62 in the embodiment of the present invention can be volatile memory or non-volatile deposit
Reservoir, or may include both volatile and non-volatile memories.Wherein, nonvolatile memory can be read-only memory
(Read-Only Memory, ROM), programmable read only memory (Programmable ROM, PROM), erasable programmable are only
Read memory (Erasable PROM, EPROM), electrically erasable programmable read-only memory (Electrically EPROM,
) or flash memory EEPROM.Volatile memory can be random access memory (Random Access Memory, RAM), use
Make External Cache.By exemplary but be not restricted explanation, the RAM of many forms is available, such as static random-access
Memory (Static RAM, SRAM), dynamic random access memory (Dynamic RAM, DRAM), synchronous dynamic random-access
Memory (Synchronous DRAM, SDRAM), double data speed synchronous dynamic RAM (Double Data
Rate SDRAM, DDRSDRAM), it is enhanced Synchronous Dynamic Random Access Memory (Enhanced SDRAM, ESDRAM), synchronous
Connect dynamic random access memory (Synchlink DRAM, SLDRAM) and direct rambus random access memory
(Direct Rambus RAM, DRRAM).The memory 62 of system and method described herein is intended to include but is not limited to these
With the memory of any other suitable type.
And processor 61 may be a kind of IC chip, the processing capacity with signal.It is above-mentioned during realization
Each step of method can be completed by the integrated logic circuit of the hardware in processor 61 or the instruction of software form.It is above-mentioned
Processor 61 can be general processor, digital signal processor (Digital Signal Processor, DSP), dedicated
Integrated circuit (Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field
Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic,
Discrete hardware components.It may be implemented or execute disclosed each method, step and the logic diagram in the embodiment of the present invention.It is general
Processor can be microprocessor or the processor is also possible to any conventional processor etc..In conjunction with institute of the embodiment of the present invention
The step of disclosed method, can be embodied directly in hardware decoding processor and execute completion, or with the hardware in decoding processor
And software module combination executes completion.Software module can be located at random access memory, and flash memory, read-only memory may be programmed read-only
In the storage medium of this fields such as memory or electrically erasable programmable memory, register maturation.The storage medium is located at
The step of memory 62, processor 61 reads the information in memory 62, completes the above method in conjunction with its hardware.
In some embodiments, embodiments described herein can with hardware, software, firmware, middleware, microcode or
A combination thereof is realized.For hardware realization, processing unit be may be implemented in one or more specific integrated circuits
(Application Specific Integrated Circuits, ASIC), digital signal processor (Digital Signal
Processing, DSP), digital signal processing appts (DSP Device, DSPD), programmable logic device (Programmable
Logic Device, PLD), field programmable gate array (Field-Programmable Gate Array, FPGA), general place
It manages in device, controller, microcontroller, microprocessor, other electronic units for executing herein described function or combinations thereof.
For software implementations, it can be realized herein by executing the module (such as process, function etc.) of function described herein
The technology.Software code is storable in memory and is executed by processor.Memory can in the processor or
It is realized outside processor.
Further embodiment of this invention provides a kind of computer storage medium, which has can
Program is executed, it can be achieved that being applied to the program in the server or terminal when the executable code processor 61 executes
The step of processing method.For example, such as one or more of Fig. 1 or Fig. 2 or Fig. 3 or method shown in Fig. 4.
In some embodiments, the computer storage medium may include: USB flash disk, mobile hard disk, read-only memory
(ROM, Read Only Memory), random access memory (RAM, Random Access Memory), magnetic or disk
Etc. the various media that can store program code.
It should be understood that between technical solution documented by the embodiment of the present invention, in the absence of conflict, Ke Yiren
Meaning combination.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any
Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain
Lid is within protection scope of the present invention.Protection scope of the present invention should be with the scope of protection of the claims with standard.
Claims (10)
1. a kind of method for determining material supply scheme in warehouse based on engineering project, is applied in warehouse management system, special
Sign is, which comprises
According to engineering project, the material information of material needed for determining the engineering project;
According to the material information, the inventory information in warehouse with the matched material of the material information is determined;
According to the material information and the inventory information, the material supply scheme of the engineering project is determined.
2. the method according to claim 1, wherein the material information include: first material identification code and with
The corresponding first material usage amount of the first material identification code;
It is described according to engineering project, the material information of material needed for determining the engineering project, comprising:
According to engineering project, the first material identification code of material needed for determining the engineering project and with the first material identify
The corresponding first material usage amount of code.
3. the method according to claim 1, wherein the method also includes:
Record the corresponding relationship between the project label of the engineering project and the material information of material needed for the engineering project;
According to the corresponding relationship, the first material identification code of material needed for determining engineering project corresponding with the project label
And first material usage amount corresponding with the first material identification code.
4. the method according to claim 1, wherein the inventory information includes at least one of: the second object
Expect identification code and the corresponding quantity in stock of the second material identification code, single material corresponding with the second material identification code
Inventory's area occupied, single material corresponding with the second material identification code inventory store warehouse label, with described the
Inventory's resting period of the corresponding single material of two material identification codes.
5. according to the method described in claim 4, it is characterized in that, described according to the material information, determine in warehouse with institute
State the matched inventory information of material information, comprising:
According to the first material identification code in the material information, inquires and exist with the material of the first material codes match
Second material identification code in warehouse;
According to the second material identification code, the quantity in stock corresponding with the second material identification code, described and institute are determined
State inventory's area occupied, the list corresponding with the second material identification code of the corresponding single material of second material identification code
The inventory of a material stores inventory's resting period of warehouse label, the single material corresponding with the second material identification code
At least one of them.
6. determining the engineering according to the method described in claim 5, described according to the material information and the inventory information
The material of project feeds scheme, including at least one of:
According to the first material usage amount corresponding with the first material identification code and the described and second material mark
Know the corresponding quantity in stock of code, determines the quantity of the purchase material needed for the engineering project;
According to the first material usage amount corresponding with the first material identification code and the described and second material mark
The inventory's area occupied for knowing the corresponding single material of code, determines the storage area vacated in the engineering project;
According to the first material usage amount corresponding with the first material identification code and the described and second material mark
The inventory for knowing the corresponding single material of code stores warehouse label, determines the warehouse address that the material is taken in the engineering project;
It is corresponding according to first material usage amount corresponding with the first material identification code and with the second material identification code
Single material inventory's resting period, determine the priority that the material is taken in the engineering project.
7. the method according to claim 1, wherein the method also includes:
Pre-establish the inventory database in the warehouse;Wherein, the inventory database includes: the inventory information of the material.
8. the method according to the description of claim 7 is characterized in that the method also includes:
It is corresponding to update the corresponding inventory information of the material when determining has material to enter and/or take out from the warehouse, and will
Updated inventory information is stored in the inventory database.
9. a kind of device for being determined material supply scheme in warehouse based on engineering project, is applied in warehouse management system, special
Sign is, comprising: processor and for storing the memory that can run computer program on a processor, wherein the processing
Device is determined in warehouse for when running the computer program, realizing that claim 1 to 8 is described in any item based on engineering project
The method of material supply scheme.
10. a kind of computer storage medium, which is characterized in that be stored with executable program, the executable code processor
When execution, realize such as the side described in any item of the claim 1 to 8 for determining material supply scheme in warehouse based on engineering project
Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910292535.3A CN109993487A (en) | 2019-04-12 | 2019-04-12 | The method and device of material supply scheme in warehouse is determined based on engineering project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910292535.3A CN109993487A (en) | 2019-04-12 | 2019-04-12 | The method and device of material supply scheme in warehouse is determined based on engineering project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109993487A true CN109993487A (en) | 2019-07-09 |
Family
ID=67133570
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910292535.3A Pending CN109993487A (en) | 2019-04-12 | 2019-04-12 | The method and device of material supply scheme in warehouse is determined based on engineering project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109993487A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115760009A (en) * | 2022-11-30 | 2023-03-07 | 中诚智信工程咨询集团股份有限公司 | Project progress management method, device, equipment and storage medium |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102467702A (en) * | 2010-11-05 | 2012-05-23 | 徐州中矿微星软件有限公司 | Inventory control method for extractive industries |
CN102930410A (en) * | 2011-08-09 | 2013-02-13 | 鸿富锦精密工业(深圳)有限公司 | Warehouse inventory management system and management method |
CN106920052A (en) * | 2015-12-24 | 2017-07-04 | 阿里巴巴集团控股有限公司 | Inventory type information processing method and processing device |
CN107784463A (en) * | 2016-08-26 | 2018-03-09 | 阿里巴巴集团控股有限公司 | Inventory information processing method, system and equipment |
CN108269033A (en) * | 2016-12-30 | 2018-07-10 | 博世汽车部件(苏州)有限公司 | Produce warehouse, production line material distribution method and system |
CN108427787A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of assembled stockyard layout management method and system based on BIM |
CN109523314A (en) * | 2018-11-12 | 2019-03-26 | 深圳云行智能科技有限公司 | A kind of supply chain management-control method and its system and storage medium based on AI technology |
CN109559070A (en) * | 2018-09-21 | 2019-04-02 | 中建科技有限公司深圳分公司 | The equipment production information management method and device of assembled architecture platform |
-
2019
- 2019-04-12 CN CN201910292535.3A patent/CN109993487A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102467702A (en) * | 2010-11-05 | 2012-05-23 | 徐州中矿微星软件有限公司 | Inventory control method for extractive industries |
CN102930410A (en) * | 2011-08-09 | 2013-02-13 | 鸿富锦精密工业(深圳)有限公司 | Warehouse inventory management system and management method |
CN106920052A (en) * | 2015-12-24 | 2017-07-04 | 阿里巴巴集团控股有限公司 | Inventory type information processing method and processing device |
CN107784463A (en) * | 2016-08-26 | 2018-03-09 | 阿里巴巴集团控股有限公司 | Inventory information processing method, system and equipment |
CN108269033A (en) * | 2016-12-30 | 2018-07-10 | 博世汽车部件(苏州)有限公司 | Produce warehouse, production line material distribution method and system |
CN108427787A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of assembled stockyard layout management method and system based on BIM |
CN109559070A (en) * | 2018-09-21 | 2019-04-02 | 中建科技有限公司深圳分公司 | The equipment production information management method and device of assembled architecture platform |
CN109523314A (en) * | 2018-11-12 | 2019-03-26 | 深圳云行智能科技有限公司 | A kind of supply chain management-control method and its system and storage medium based on AI technology |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115760009A (en) * | 2022-11-30 | 2023-03-07 | 中诚智信工程咨询集团股份有限公司 | Project progress management method, device, equipment and storage medium |
CN115760009B (en) * | 2022-11-30 | 2023-12-08 | 中诚智信工程咨询集团股份有限公司 | Engineering progress management method, device, equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Van der Laan et al. | Inventory control in hybrid systems with remanufacturing | |
Kang et al. | Inventory control in a two-level supply chain with risk pooling effect | |
Marklund | Inventory control in divergent supply chains with time‐based dispatching and shipment consolidation | |
Alemany et al. | Available-To-Promise modeling for multi-plant manufacturing characterized by lack of homogeneity in the product: An illustration of a ceramic case | |
Barros et al. | A systematic literature review about dimensioning safety stock under uncertainties and risks in the procurement process | |
Yadollahi et al. | Managing inventory and service levels in a safety stock‐based inventory routing system with stochastic retailer demands | |
CN116308026A (en) | Automatic warehouse inventory allocation method and device | |
Burinskiene | Pharma supply chain: Efficiency modelling approach | |
CN105139111A (en) | Agreement inventory material order allocation method based on greedy algorithm | |
CN109993487A (en) | The method and device of material supply scheme in warehouse is determined based on engineering project | |
CN116308031A (en) | Multi-warehouse inventory allocation method for shortening warehouse cargo allocation walking path | |
CN101510277A (en) | Method for rolling computation of material requirement in production management process | |
Luo et al. | Inventory allocation models for a two-stage, two-product, capacitated supplier and retailer problem with random demand | |
CN108320121B (en) | Warehouse management method and management device based on wireless communication | |
Krever et al. | Inventory control based on advanced probability theory, an application | |
JP6088850B2 (en) | Simulation system, control method and program | |
CN105512313B (en) | A kind of method and apparatus of incremented data processing | |
US10083416B2 (en) | Time phase work pool management for returned inventory asset routing | |
US20060010067A1 (en) | Real-time planning and execution with minimum perturbation | |
Cha-Ume et al. | Simulation of retail supply chain behaviour and financial impact in an uncertain environment | |
JP2019046183A (en) | Information processing method and program | |
US6970756B2 (en) | Computer-assisted pull flow production management method | |
REMBULAN et al. | An Integrated Model of Continuous Review Inventory and Vehicle Routing Problem with Time Windows | |
US8355939B2 (en) | Managing supply and demand for a ware | |
JP4361846B2 (en) | Shipment planning apparatus and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 3210 Kuanyu building, No. 139, Wanjiali Middle Road, dongtundu street, Furong district, Changsha City, Hunan Province Applicant after: Hunan zexia Energy Saving Technology Co., Ltd Address before: 410000 Nanzhushan South Building, Wufeng Village, Lianhua Town, Yuelu District, Changsha City, Hunan Province Applicant before: HUNAN CHANGLUO ENERGY SAVING TECHNOLOGY Co.,Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190709 |