CN107133769A - A kind of intelligent inventory pre-warning management system based on BIM models - Google Patents

A kind of intelligent inventory pre-warning management system based on BIM models Download PDF

Info

Publication number
CN107133769A
CN107133769A CN201710396592.7A CN201710396592A CN107133769A CN 107133769 A CN107133769 A CN 107133769A CN 201710396592 A CN201710396592 A CN 201710396592A CN 107133769 A CN107133769 A CN 107133769A
Authority
CN
China
Prior art keywords
stock
bim models
bim
inventory
management system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710396592.7A
Other languages
Chinese (zh)
Inventor
何敏杰
刘中华
王强强
徐立丰
高良
刘天成
孟玲霄
陈泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinggong Steel Structure Group Co Ltd
Original Assignee
Zhejiang Jinggong Steel Structure Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinggong Steel Structure Group Co Ltd filed Critical Zhejiang Jinggong Steel Structure Group Co Ltd
Priority to CN201710396592.7A priority Critical patent/CN107133769A/en
Publication of CN107133769A publication Critical patent/CN107133769A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • G06Q10/0875Itemisation or classification of parts, supplies or services, e.g. bill of materials
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders

Abstract

The present invention relates to a kind of intelligent inventory pre-warning management system based on BIM models, its method comprises the following steps, the first step:BIM models are imported in the system;Second step:The enquiry task scheduling based on BIM models is generated in systems, and is sent to factory;3rd step:BIM plan for cargo demands model decompositions, and count required element type quantity of material;4th step:System is judged current quantity in stock;5th step:System is judged not enough construction material amount, if enquiry planned time is less than required time T, triggers one-level stock's early warning;Otherwise bi- inventory early warning is triggered;6th step:Component inventory material carries out Coordinate Purchase;7th step:Whether system meets enterprise security stockpile number to current quantity in stock is detected.Present invention lifting building enterprise inventory management information operation level.

Description

A kind of intelligent inventory pre-warning management system based on BIM models
Technical field
Patent of the present invention belongs to BIM application field, and in particular to a kind of intelligent inventory based on BIM models Pre-warning management system.
Technical background
BIM, i.e. BIM(Building Information Modeling), it is to be based on construction-engineering project The big data set up of every relevant information data, big integrated architecture information model is that engineering project correlation is believed The detailed expression of breath.BIM is also a kind of new technical concept, is to be directed to building trade, using the model with digital information For carrier, in project construction, each stage utilizes informationization model, and carrying out Life cycle to construction-engineering project dynamically manages A kind of new technology.
In recent years, with the great variety of the fast development of construction industry, and market competition environment, many is engaged in production Shortening delivery cycle, reduction inventory cost are faced with the building enterprise of management and improve the pressure such as customer service.It is all These require that building enterprise quickly can adjust to fierce market.Built however, existing inventory management mode turns into The bottleneck of enterprise development is built, due to lacking the inventory management method of science, causes stock control can only be according to conventional datagram Table, can not accomplish monitoring in real time, it is difficult to ensure the promptness and accuracy of data, draw while a large amount of human and material resources are wasted Send various stock control problems.Such as, the shortage of stock cause delivery delay, Lost Sales volume, make client be discontented with etc.;And stock It is superfluous then take excessive resource, affect business capital operating etc..So, the stock that overall salary strategy is carried out to building enterprise Administrative reform is extremely urgent.
The present invention is namely based on above-mentioned background, all develops a kind of intelligent inventory early warning pipe based on BIM models in design Reason system, really realizes interactivity, and promptness is intelligent, the intelligent inventory management mode of reliability.
The content of the invention
The invention aims to solve at this stage because of Strategy of Inventory Control not in time, it is unreasonable and cause building enterprise The production schedule is inconsiderate, the problems such as purchasing unfavorable, so as to maintain production and stock's stabilization, the balance circulation occupation of capital, lifting client Satisfactory service.To realize the purpose of the present invention, the present invention specifically provides a kind of intelligent inventory forewarning management system based on BIM models System.
A kind of intelligent inventory pre-warning management system based on BIM models of the present invention, it comprises the following steps:
The first step:Import in the system and have corresponding base attribute on BIM models, the BIM model components;
Second step:According to the practice of construction situation at scene and the construction plan of next step, generate in systems based on BIM models Enquiry task scheduling, and send to factory;
3rd step:System is by BIM plan for cargo demands model decompositions, and element type quantity of material needed for counting each task scheduling;
4th step:System is judged current quantity in stock, if required element type quantity of material is less than quantity in stock, sends stock Surplus;
5th step:If required element type quantity of material is more than quantity in stock, system is judged not enough construction material amount, to Goods planned time is less than required time T, then triggers one-level stock's early warning, and send shortage of stock amount;Otherwise bi- inventory is triggered Early warning;
6th step:Factory carries out Coordinate Purchase according to stock's warning information and remaining quantity in stock to required component inventory material;
7th step:System judges whether current quantity in stock meets enterprise security stockpile number, if so, then sending safety inventory early warning Information is to director;If it is not, then terminating the detection to current stock.
The BIM models include:The formatted files such as Revit, Tekla, Navisworks, Rhinoceros, CATIA.
The base attribute is the range of information such as title, unique number, length, weight, specification, the material of component.
Component priming color in the system introducing BIM models orientates grey as, in enquiry of the generation based on BIM models After task scheduling, corresponding enquiry component is changed into blueness in BIM models.
The T is each construction material buying hour desired value that system is recorded.
After the BIM plans for cargo demands model decomposition, system is judged materials in storage amount data, if quantity in stock is had a surplus, BIM Corresponding enquiry component color is changed into green in model;Conversely, judge that construction material buying can be completed in enquiry task scheduling, If it is not, then respective members color is changed into red in BIM models after triggering stock's one-level early warning, and not enough quantity of material is sent, if It is that then respective members color is changed into yellow in BIM models after triggering two grades of early warning of stock.
The safety inventory quantity is the highest stock and minimum storehouse that building enterprise formulates according to conventional service operation situation The quantity deposited.
The beneficial effects of the present invention are:
1st, precisely production, reduces warehousing pressure.The present invention uses the visualization plan for cargo demands mode based on BIM models, helps work Factory formulates rational production planning and sequencing and procurement plan on demand, reduces because of phenomenons such as mistake processing or multi-processings, significantly reduces work Factory's inventory level, saves circulating fund.
2nd, intelligent early-warning, ensures production inventory balance.Using intelligent inventory management system, intuitively made in BIM models Determine enquiry task scheduling, can obtain quantity in stock rapidly from the link of front end enquiry and the difference of enquiry construction material amount is fed back, with Factory's Coordinate Purchase as early as possible is reminded, prevents to hold up work for lack of material, science, efficient production inventory balance is realized.
3rd, customer service quality is improved.The present invention realizes that building enterprise is quick in real time by intelligent inventory early warning system Adjust the imbalance between supply and demand, it is ensured that delivery just-in-time, postpone to bring to enterprise so as to avoid or reduce O/S or supply Economic loss.
Brief description of the drawings
Fig. 1 is system flow chart of the invention.
Embodiment
The present invention is further described with case study on implementation below in conjunction with the accompanying drawings:
Case study on implementation flow:Referring to figure one
A kind of intelligent inventory pre-warning management system based on BIM models of the present invention has put into operation, comprises the following steps that:
The first step:The formatted files such as Revit, Tekla, Navisworks, Rhinoceros, CATIA are imported in the system BIM models, the BIM model components priming color orientates grey as, and it is with corresponding title, unique number, length, again The range of information such as amount, specification, material, component priming color orientates grey as;
Second step:According to the practice of construction situation at scene and the construction plan of next step, generate in systems based on BIM models Enquiry task scheduling, and send to factory, while corresponding enquiry component is changed into blueness in BIM models;
3rd step:System is by BIM plan for cargo demands model decompositions, and element type quantity of material needed for counting each task scheduling;
4th step:System is judged current quantity in stock, if required element type quantity of material is less than quantity in stock, sends stock Surplus, while corresponding enquiry component color is changed into green in BIM models;
5th step:If required element type quantity of material is more than quantity in stock, system carries out data judgement to not enough construction material amount, If enquiry planned time is less than each construction material buying hour desired value that system is recorded, one-level stock's early warning, BIM are triggered Respective members color is changed into red in model, and sends shortage of stock amount;Otherwise phase in bi- inventory early warning, BIM models is triggered Component color is answered to be changed into yellow;
6th step:Factory carries out Coordinate Purchase according to stock's warning information and remaining quantity in stock to required component inventory material;
7th step:System judges whether current quantity in stock meets the most high basin that building enterprise formulates according to conventional service operation situation Deposit and minimum inventory quantity, if so, then sending safety inventory warning information to relevant enterprise director;If it is not, then terminating pair The detection of current stock.
Instant invention overcomes production inventory control strategy is improper, inventory information does not circulate and causes building enterprise's production procurement The defect such as unbalanced, assets benefit is poor, and a kind of intelligent inventory pre-warning management system based on BIM models of our company's research and development, Precisely in order to solve the above problems and adapt to social reality needs and research and develop, Successful utilization of the invention is in company's Project In, and achieve good Expected Results.
What the case study on implementation of the present invention was announced is one of case that our company applies the system, but is not limited thereto, this The R&D personnel in field, easily according to above-mentioned case study on implementation, understands the Technology Ways of the present invention, and make different amplifications And change, but as long as not departing from the implementation path and spirit of the present invention, all within the scope of the present invention.

Claims (7)

1. a kind of intelligent inventory pre-warning management system based on BIM models, it is characterised in that it comprises the following steps:
The first step:Import in the system and have corresponding base attribute on BIM models, the BIM model components;
Second step:According to the practice of construction situation at scene and the construction plan of next step, generate in systems based on BIM models Enquiry task scheduling, and send to factory;
3rd step:System is by BIM plan for cargo demands model decompositions, and element type quantity of material needed for counting each task scheduling;
4th step:System is judged current quantity in stock, if required element type quantity of material is less than quantity in stock, sends stock Surplus;
5th step:If required element type quantity of material is more than quantity in stock, system is judged not enough construction material amount, to Goods planned time is less than required time T, then triggers one-level stock's early warning, and send shortage of stock amount;Otherwise bi- inventory is triggered Early warning;
6th step:Factory carries out Coordinate Purchase according to stock's warning information and remaining quantity in stock to required component inventory material;
7th step:System judges whether current quantity in stock meets enterprise security stockpile number, if so, then sending safety inventory early warning Information is to director;If it is not, then terminating the detection to current stock.
2. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that institute Stating BIM models includes:Revit, Tekla, Navisworks, Rhinoceros, CATIA formatted file.
3. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that institute State title, unique number, length, weight, specification, material range of information that base attribute is component.
4. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that be The component priming color that system is imported in BIM models orientates grey as, after enquiry task scheduling of the generation based on BIM models, BIM Corresponding enquiry component is changed into blueness in model.
5. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that institute It is each construction material buying hour desired value that system is recorded to state T.
6. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that BIM After plan for cargo demands model decomposition, system is judged materials in storage amount data, if quantity in stock is had a surplus, corresponding enquiry in BIM models Component color is changed into green;Conversely, judging that construction material buying can be completed in enquiry task scheduling, if it is not, then in triggering Respective members color is changed into red in BIM models after stock's one-level early warning, and sends not enough quantity of material, if so, then in triggering storehouse Deposit after two grades of early warning that respective members color is changed into yellow in BIM models.
7. a kind of intelligent inventory pre-warning management system based on BIM models according to claim 1, it is characterised in that institute State the quantity of highest stock that safety inventory quantity formulated according to conventional service operation situation for building enterprise and minimum inventory.
CN201710396592.7A 2017-05-31 2017-05-31 A kind of intelligent inventory pre-warning management system based on BIM models Pending CN107133769A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710396592.7A CN107133769A (en) 2017-05-31 2017-05-31 A kind of intelligent inventory pre-warning management system based on BIM models

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710396592.7A CN107133769A (en) 2017-05-31 2017-05-31 A kind of intelligent inventory pre-warning management system based on BIM models

Publications (1)

Publication Number Publication Date
CN107133769A true CN107133769A (en) 2017-09-05

Family

ID=59734167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710396592.7A Pending CN107133769A (en) 2017-05-31 2017-05-31 A kind of intelligent inventory pre-warning management system based on BIM models

Country Status (1)

Country Link
CN (1) CN107133769A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108876015A (en) * 2018-05-22 2018-11-23 大连理工大学 Gas station's product oil inventory's dynamic monitoring method for early warning under environment of internet of things based on scene
CN109165887A (en) * 2018-07-21 2019-01-08 中铁十八局集团有限公司 One kind being based on BIM explosives magazine storage and managenent system
CN109472426A (en) * 2017-09-07 2019-03-15 上海嘉实(集团)有限公司 Material cost management method, system, storage medium and the terminal device of live project
CN109559070A (en) * 2018-09-21 2019-04-02 中建科技有限公司深圳分公司 The equipment production information management method and device of assembled architecture platform
CN110555639A (en) * 2018-05-31 2019-12-10 红塔烟草(集团)有限责任公司 Spare part management device and spare part inventory management method
CN111861299A (en) * 2019-04-30 2020-10-30 上海梅山钢铁股份有限公司 Iron and steel enterprise full-process inventory level early warning and control method
CN112785122A (en) * 2021-01-05 2021-05-11 广西路桥工程集团有限公司 Engineering project real-time data synchronous management and control system
CN113011776A (en) * 2021-04-07 2021-06-22 中建安装集团有限公司 Pipe excess material comprehensive utilization method based on BIM
CN113570307A (en) * 2021-07-22 2021-10-29 江苏金小满信息科技有限公司 Engineering material procurement management system
CN113742908A (en) * 2021-08-24 2021-12-03 吉利汽车集团有限公司 Material alignment judgment method based on discrete simulation
CN113888071A (en) * 2021-08-24 2022-01-04 上海赛扬信息技术有限公司 Spare part management method and system based on BIM technology
CN114677078A (en) * 2022-03-08 2022-06-28 中铁第四勘察设计院集团有限公司 Visual material storage management method, device and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103279613A (en) * 2013-05-30 2013-09-04 南京航空航天大学 Automatic matching method for high-precision complex product assembling materials
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN106022637A (en) * 2016-05-31 2016-10-12 浙江精工钢结构集团有限公司 Steel member delivery progress detection system based on BIM technology
CN106296087A (en) * 2016-08-04 2017-01-04 中冶赛迪电气技术有限公司 A kind of Spare Parts Inventory Management System of Facing to Manufacturing industry

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103279613A (en) * 2013-05-30 2013-09-04 南京航空航天大学 Automatic matching method for high-precision complex product assembling materials
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN106022637A (en) * 2016-05-31 2016-10-12 浙江精工钢结构集团有限公司 Steel member delivery progress detection system based on BIM technology
CN106296087A (en) * 2016-08-04 2017-01-04 中冶赛迪电气技术有限公司 A kind of Spare Parts Inventory Management System of Facing to Manufacturing industry

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周永杰 等: "BIM 视角下的机电工程物料管理优化分析", 《项目管理技术》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109472426A (en) * 2017-09-07 2019-03-15 上海嘉实(集团)有限公司 Material cost management method, system, storage medium and the terminal device of live project
CN108876015A (en) * 2018-05-22 2018-11-23 大连理工大学 Gas station's product oil inventory's dynamic monitoring method for early warning under environment of internet of things based on scene
CN108876015B (en) * 2018-05-22 2021-03-26 大连理工大学 Scene-based gas station finished product oil inventory dynamic monitoring and early warning method in Internet of things environment
CN110555639A (en) * 2018-05-31 2019-12-10 红塔烟草(集团)有限责任公司 Spare part management device and spare part inventory management method
CN110555639B (en) * 2018-05-31 2024-04-05 红塔烟草(集团)有限责任公司 Spare part management device and spare part inventory management method
CN109165887A (en) * 2018-07-21 2019-01-08 中铁十八局集团有限公司 One kind being based on BIM explosives magazine storage and managenent system
CN109559070A (en) * 2018-09-21 2019-04-02 中建科技有限公司深圳分公司 The equipment production information management method and device of assembled architecture platform
CN111861299A (en) * 2019-04-30 2020-10-30 上海梅山钢铁股份有限公司 Iron and steel enterprise full-process inventory level early warning and control method
CN111861299B (en) * 2019-04-30 2023-10-17 上海梅山钢铁股份有限公司 Whole-process inventory level early warning and control method for iron and steel enterprises
CN112785122B (en) * 2021-01-05 2022-05-31 广西路桥工程集团有限公司 Engineering project real-time data synchronous management and control system
CN112785122A (en) * 2021-01-05 2021-05-11 广西路桥工程集团有限公司 Engineering project real-time data synchronous management and control system
CN113011776A (en) * 2021-04-07 2021-06-22 中建安装集团有限公司 Pipe excess material comprehensive utilization method based on BIM
CN113570307A (en) * 2021-07-22 2021-10-29 江苏金小满信息科技有限公司 Engineering material procurement management system
CN113742908A (en) * 2021-08-24 2021-12-03 吉利汽车集团有限公司 Material alignment judgment method based on discrete simulation
CN113888071A (en) * 2021-08-24 2022-01-04 上海赛扬信息技术有限公司 Spare part management method and system based on BIM technology
CN113742908B (en) * 2021-08-24 2024-03-15 吉利汽车集团有限公司 Material alignment judging method based on discrete simulation
CN114677078A (en) * 2022-03-08 2022-06-28 中铁第四勘察设计院集团有限公司 Visual material storage management method, device and system

Similar Documents

Publication Publication Date Title
CN107133769A (en) A kind of intelligent inventory pre-warning management system based on BIM models
Kurilova-Palisaitiene et al. Remanufacturing challenges and possible lean improvements
US10878363B2 (en) Inland freight management
CN106991550B (en) Commodity object replenishment information processing method and device
Ramaa et al. Impact of warehouse management system in a supply chain
US8027860B2 (en) Systems and methods for planning demand for configurable products
Razmi et al. Developing a two-echelon mathematical model for a vendor-managed inventory (VMI) system
CN110097203A (en) Inventory's dispatching method, inventory's dispatching device and computer readable storage medium
CN107292550A (en) A kind of dispatching method of logistic resources, equipment and system
CN111340421A (en) Purchasing method
CN108428194A (en) A kind of management method and device of the building material processing dispatching based on BIM
US20170236082A1 (en) System and methods for real time display of supply chain and data processing of related tasks and events
Liu et al. Solutions for flexible container leasing contracts with options under capacity and order constraints
Knolmayer et al. Supply chain management based on SAP systems: Architecture and planning processes
CN104881758B (en) The ERP system and its operation method of integrated supply chain cooperating manufacture
US8069086B2 (en) Systems and methods for time-dependent protection of available quantities
CN106547262A (en) It is a kind of to carry out producing the method for object supply, equipment, system
CN111985862A (en) Method and apparatus for locating inventory items
Hariga et al. A Single-Vendor Multi-Retailer VMI Partnership Under Individual Carbon-Cap Constraints
Talibi et al. The relevance study of adaptive kanban in a multicriteria constraints context using data-driven simulation method
Rathmell et al. The Arena product family: enterprise modeling solutions
Hong et al. Integrated inventory and transportation decision for ubiquitous supply chain management
Koh et al. Overview of enterprise networks and logistics for agile manufacturing
KR101872070B1 (en) Apparatus for distributing goods based on production rate, method thereof, and computer recordable medium storing the method
Chang et al. Design Lean Supply Chain for Post COVID-19

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170905