CN112948950B - BIM technology-based integrated information intelligent management system and management method - Google Patents

BIM technology-based integrated information intelligent management system and management method Download PDF

Info

Publication number
CN112948950B
CN112948950B CN202110374424.4A CN202110374424A CN112948950B CN 112948950 B CN112948950 B CN 112948950B CN 202110374424 A CN202110374424 A CN 202110374424A CN 112948950 B CN112948950 B CN 112948950B
Authority
CN
China
Prior art keywords
construction
parameters
site
information
dimensional model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110374424.4A
Other languages
Chinese (zh)
Other versions
CN112948950A (en
Inventor
刘东峰
徐强
张正
诸葛运臣
魏耀鑫
杜佳伟
罗刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Shenzhen Engineering Co Ltd
Original Assignee
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Shenzhen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Guangzhou Engineering Group Co Ltd CRECGZ, CRECGZ Shenzhen Engineering Co Ltd filed Critical China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Priority to CN202110374424.4A priority Critical patent/CN112948950B/en
Publication of CN112948950A publication Critical patent/CN112948950A/en
Application granted granted Critical
Publication of CN112948950B publication Critical patent/CN112948950B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Software Systems (AREA)
  • Computer Graphics (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to an integrated information intelligent management system and method based on BIM technology, comprising the following steps: acquiring various construction parameters from a construction drawing to establish a construction site three-dimensional model; acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information; and adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not. In the construction process, construction parameters of each time period of each construction object in a construction site are acquired in real time, and after the information of the staged site construction parameters is acquired, relevant parameter information in the three-dimensional model of the construction site is adjusted according to the actually acquired data, so that the three-dimensional model of the construction site is consistent with each data of the site construction objects, and the three-dimensional model of the construction site is convenient for a user to watch.

Description

BIM technology-based integrated information intelligent management system and management method
Technical Field
The application relates to the field of buildings, in particular to an integrated information intelligent management system and method based on BIM technology.
Background
The mode of sand table demonstration relies on the model of establishing the entity to this realization simulation reality scene carries out emulation show, and sand table model is used for showing the actual model after construction is built in real estate field, building field more, but this kind of show mode can only carry out the demonstration of fixed mode, can't satisfy different show demands. For construction enterprises, sand table systems are rarely available for guiding the construction stages of residential projects.
For the related technology, a large number of engineering models made of gypsum, plastics and other materials are adopted at present, and based on the engineering models, the inventor considers that the engineering models have the defects that the entity sand table can only show the state of a certain finishing stage of a project and cannot be flexibly displayed on the models according to actual construction conditions.
Disclosure of Invention
In order to solve the problem of poor flexibility in construction site display, the application provides an integrated information intelligent management system and method based on BIM technology.
In a first aspect, the present application provides an integrated information intelligent management method based on a BIM technology, which adopts the following technical scheme:
An integrated information intelligent management method based on BIM technology comprises the following steps:
Acquiring various construction parameters from a construction drawing to establish a construction site three-dimensional model;
acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
and adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
By adopting the technical scheme, corresponding parameters of a construction site are obtained according to construction, and a three-dimensional model diagram of each object of the construction site is built according to the parameters, so that a user can intuitively see a simulated construction scene; in the construction process, construction parameters of each time period of each construction object in a construction site, such as a house, are obtained in real time, when the foundation is constructed by the house, information such as the number of piles, the depth of piles driven into the ground and the like is obtained, after the staged site construction parameter information is obtained, relevant parameter information in a three-dimensional model of the construction site is adjusted according to the actually obtained data, so that the three-dimensional model of the construction site is consistent with each item of data of the site construction objects; after some parameters in the three-dimensional model of the construction site are changed, parameters related to the parameters can be influenced, such as disappearance of other object models or change of positions, and the like, so that corresponding treatment measures are taken if the influence of the adjusted parameters on the related parameters is within a preset range by judging whether the influence occurs.
Preferably, the step of adjusting a part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the associated parameters is within a preset range includes:
And if the influence of the adjusted parameters on the associated parameters exceeds a preset range, triggering error alarm information.
By adopting the technical scheme, the mode of triggering the alarm information is set to remind the modified staff that the parameter modification has errors, and the modification needs to be further confirmed or stopped.
Preferably, the step of acquiring the construction parameters of each construction time period of each construction object in the construction process in real time to form the staged site construction parameter information includes:
acquiring the wind speed and the wind direction of a site in real time to form wind load information;
and adjusting the structural system of the building in the three-dimensional model of the construction site according to the wind load information.
By adopting the technical scheme, the effect of the wind on the building on the construction site is very complex, and the influence of the wind on the building is not only wind sound, but also the influence of wind load on horizontal displacement. The specific length of the wind can influence the local climate characteristics, the wind power condition, the site characteristics, the building object type and the like, so that the wind speed and the wind direction are obtained in real time in the construction process, and corresponding adjustment is made according to the influence of wind on the building actually, so that the construction quality is ensured.
Preferably, the step of acquiring the construction parameters of each construction time period of each construction object in the construction process in real time to form the staged site construction parameter information includes:
acquiring humidity information of a construction site;
Determining construction scheme adjustment parameters according to the humidity information;
and reconditioning a parameter model of the construction site three-dimensional model according to the construction scheme adjustment parameters to check whether the modified parameters have influence on other building parameters.
By adopting the technical scheme, the environmental humidity of the construction site is detected in real time, then the construction scheme is obtained according to the detected data to carry out adjustment needed to be carried out, corresponding adjustment parameters are generated, the parameter model of the three-dimensional model of the construction site is adjusted according to the parameters, whether the modification is carried out or not is checked to influence the parameters of the building, and if the modification is carried out, the parameters are needed to be further adjusted until the influence is eliminated.
Preferably, the step of acquiring the wind speed and the wind direction in the field in real time to form wind load information includes:
determining the change coefficient of the air pressure height according to the staged site construction parameter information;
Wind load information is determined based on the wind pressure altitude change factor.
By adopting the technical scheme, the wind load is related to the floor height, and the higher the wind pressure is, the larger the wind pressure is, but the simple proportional relation is not. For flat or slightly undulating terrain, the wind pressure height change coefficient should be determined according to the ground roughness class and the standard value. For buildings in mountainous areas, the wind pressure height change coefficient also needs to consider the correction of the terrain condition, so that the actual wind pressure height change coefficient needs to be determined according to the on-site staged on-site construction parameter information so as to obtain accurate wind load, and the influence of the wind load on the buildings can be calculated so as to make adjustment in time.
Preferably, the step of obtaining the information of the responsible person of each construction object and displaying the information in the three-dimensional model of the construction site includes:
acquiring three-dimensional coordinate information of information triggering operation actions;
And if the three-dimensional coordinate information is consistent with the three-dimensional coordinate information preset on each construction object, displaying responsible person information on one side of the corresponding construction object.
By adopting the technical scheme, the information of the responsible person of the construction object to be checked is obtained by performing corresponding actions, so that the corresponding responsible person can be found to determine the information related to the actual construction, and the user can know the actual situation.
In a second aspect, the present application provides an integrated information intelligent management system based on a BIM technology, which adopts the following technical scheme:
An integrated information intelligent management system based on BIM technology, the system includes:
the modeling module acquires various construction parameters from the construction drawing to establish a construction site three-dimensional model;
the construction site supervision module acquires construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
And the judging module is used for adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
By adopting the technical scheme, corresponding parameters of a construction site are obtained according to construction, and a three-dimensional model diagram of each object of the construction site is built according to the parameters, so that a user can intuitively see a simulated construction scene; in the construction process, construction parameters of each time period of each construction object in a construction site, such as a house, are obtained in real time, when the foundation is constructed by the house, information such as the number of piles, the depth of piles driven into the ground and the like is obtained, after the staged site construction parameter information is obtained, relevant parameter information in a three-dimensional model of the construction site is adjusted according to the actually obtained data, so that the three-dimensional model of the construction site is consistent with each item of data of the site construction objects; after some parameters in the three-dimensional model of the construction site are changed, parameters related to the parameters can be influenced, such as disappearance of other object models or change of positions, and the like, so that corresponding treatment measures are taken if the influence of the adjusted parameters on the related parameters is within a preset range by judging whether the influence occurs.
Preferably, the system further comprises:
And the alarm module is used for triggering error alarm information if the influence of the adjusted parameters on the related parameters exceeds a preset range.
By adopting the technical scheme, the mode of triggering the alarm information is set to remind the modified staff that the parameter modification has errors, and the modification needs to be further confirmed or stopped.
In a third aspect, the present application provides a computer device, including a memory, a processor and a computer program stored in the memory and executable on the processor, where the processor implements the steps of an integrated information intelligent management method based on BIM technology according to any one of the second aspects.
In a fourth aspect, the present application provides a computer readable storage medium storing a computer program capable of being loaded by a processor and executing the above fourth aspect.
In summary, the present application includes at least one of the following beneficial technical effects:
1. Acquiring corresponding parameters of a construction site according to construction, and establishing a three-dimensional model diagram of each object of the construction site according to the parameters so that a user can intuitively see a simulated construction scene; in the construction process, construction parameters of each time period of each construction object in a construction site are acquired in real time, and after the information of the staged site construction parameters is acquired, relevant parameter information in the three-dimensional model of the construction site is adjusted according to the actually acquired data, so that the three-dimensional model of the construction site is consistent with each data of the site construction objects, and the three-dimensional model of the construction site is convenient for a user to watch.
2. Detecting the environmental humidity of a construction site in real time, then obtaining the adjustment needed by the construction scheme according to the detected data, generating corresponding adjustment parameters, adjusting a parameter model of a three-dimensional model of the construction site according to the parameters, checking whether the modification is influenced on the building, and if the modification is influenced, further adjusting the parameters until the influence disappears.
3. And the information of the responsible person of the construction object to be checked is acquired by corresponding actions, so that the corresponding responsible person can be found to determine the information related to the actual construction, and the user can know the actual situation.
Drawings
FIG. 1 is a flow chart of an integrated information intelligent management method based on BIM technology according to an embodiment of the application;
FIG. 2 is a schematic diagram of an integrated information intelligent management system based on BIM technology according to an embodiment of the present application;
FIG. 3 is a schematic diagram of a computer device in accordance with an embodiment of the present application.
Detailed Description
The application is described in further detail below with reference to fig. 1-3.
The embodiment of the application discloses an integrated information intelligent management method based on BIM technology. Referring to fig. 1, the integrated information intelligent management method based on the BIM technology includes the steps of:
S100: and obtaining various construction parameters from the construction drawing to establish a construction site three-dimensional model.
In this embodiment, the construction drawing refers to a drawing designed by an engineer according to an on-site survey and design requirements before construction. The construction parameters refer to various data of various objects to be constructed in advance, such as the preset depth of the foundation, the preset coordinate position of the foundation, and the like.
Specifically, parameters related to construction are obtained from a designed construction drawing, and are input into three-dimensional modeling software to perform three-dimensional modeling so as to obtain a three-dimensional model of a construction site, so that a user can intuitively see a reduced model of the construction site after construction.
S200: and acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information.
In the present embodiment, the construction object refers to a foundation, a road, each building, and the like of a construction site; the construction time period refers to a time span for completing the stepwise construction, such as completing the construction of the foundation of the building A, completing the construction of the building B by one layer, and the like. The site operation parameter information refers to actual operation data of each operation object in the operation site, such as the actual operation quantity, the actual operation position and the like of the foundation of the building A after the foundation of the building A is operated.
Specifically, after the actual construction stage is stepped in, various data during site construction are obtained in a real-time and on-site measurement mode, the obtained various data are all data when each construction object finishes one construction stage, and the obtained data are converted into site construction parameter information.
Further, in an embodiment, the method comprises the steps of: acquiring the wind speed and the wind direction of a site in real time to form wind load information; and adjusting the structural system of the building in the three-dimensional model of the construction site according to the wind load information.
In this embodiment, the wind load information refers to pressure or suction force formed on the surface of the building when the flow of air is obstructed by the building. The structural system is meant to bear vertical and lateral loads.
Specifically, according to the formula wind load standard value = wind vibration coefficient =wind load body form coefficient ×wind pressure height change coefficient ×basic wind pressure, calculating to obtain wind load, then determining whether the current load of the building is in the bearing capacity range according to the wind load, and if overload occurs, performing corresponding replacement or adjustment in time.
Further, in an embodiment, the wind pressure altitude change coefficient is determined according to the staged site operation parameter information; wind load information is determined based on the wind pressure altitude change factor.
In this embodiment, the wind pressure height change coefficient refers to a coefficient reflecting the wind pressure change law with different sites, landforms and heights.
Specifically, the wind pressure height change coefficient is calculated according to the formula in the specification of 8.2.1 th strip in the building structural load of GB 50009-2012:
Class a relief: the air pressure altitude change coefficient=1.284 x (z/10)/(0.24)
Class B relief: wind pressure altitude change coefficient=1.000 x (z/10)/(0.30)
Class C relief: the barometric pressure altitude change factor = 0.544 x (z/10)/(0.44)
Class D relief: wind pressure altitude change coefficient=0.262 x (z/10)/(0.60)
Note that the class a, B, C, D height variation coefficient values are not less than 1.09,1.00,0.65 and 0.51, respectively (i.e., the respective cutoff heights are specified), and the maximum height variation coefficient is not more than 2.91; different wind pressure height change coefficients are correspondingly calculated according to the actual conditions of the construction site, and then actual wind load information is determined.
Further, in an embodiment, the method comprises the steps of: acquiring humidity information of a construction site; determining construction scheme adjustment parameters according to the humidity information; and (3) reconditioning the parameter model of the three-dimensional model of the construction site according to the construction scheme adjustment parameters to check whether the modified parameters have influence on other building parameters.
In this embodiment, the humidity information refers to the air humidity in the unit range of the construction site.
Specifically, humidity sensors are used for acquiring humidity at different positions of a construction site, a construction scheme is redetermined according to the acquired humidity, for example, the humidity of air in an area A is influenced by a topography and a nearby building and is larger than a preset condition, a moistureproof floor is required to be redefined for the building A in the area A, so that the related parameters of the bottom plate of the building A in the area A in a corresponding model are required to be correspondingly modified according to actual conditions, when the parameters are adjusted, whether the modified data influence other parameters of the building A or not is checked in a verification mode, if the wall of the building B is thicker than the preset condition, and the like, the influence of the modified parameters of the surface on other buildings is caused when the condition appears, alarm information is triggered, and the modified data are redefined.
S300: and adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
In this embodiment, the associated parameter refers to data associated with the adjustment parameter; the preset range refers to whether the influence of the adjustment parameter on the associated parameter is within the error fluctuation range of the associated parameter.
Specifically, after the progress data on each stage of the construction object is acquired in S200, if an inconsistency occurs between the actually acquired parameters and the preset parameters, the corresponding parameters in the three-dimensional model of the construction site set at the time of modeling are modified according to the actually measured conditions. The mode of judging the influence is as follows: and extracting relation features from the associated data, establishing a feature model based on weight, calculating and transmitting change influence degree to obtain an accurate and comprehensive change influence entity set so as to know whether the influence of the modified parameters on the associated parameters is within a preset range or not, and if the influence exceeds the preset range, changing the associated parameters. If the generated influence is within the preset range value, the associated parameter is unchanged.
Further, in an embodiment, the method comprises the steps of: and if the influence of the adjusted parameters on the associated parameters exceeds a preset range, triggering error alarm information.
In this embodiment, the condition that the parameter is beyond the preset range means that the modified parameter causes the associated parameter to change, so that the model structure formed by the corresponding associated parameter changes.
Specifically, when the terminal modifies a parameter, the parameter related to the parameter changes, so that the data is in error reporting during operation, and an alarm instruction is triggered to send alarm information to remind a user of verifying whether the modified parameter is correct again. For example, if the preset coordinates of the first foundation of the building a are (11,2,4) and the actual construction coordinates are (11,2,6), the coordinates of the first foundation need to be modified, and after the coordinates of the first foundation are modified, the length of the simulation model of the second foundation is shortened by 0.5 meter, so that the influence of the modification of the coordinates of the first foundation on the parameters of the second foundation associated with the modification of the coordinates of the first foundation is proved to be beyond a preset range, and corresponding alarm information is triggered.
Further, in an embodiment, the method further comprises the steps of: acquiring three-dimensional coordinate information of information triggering operation actions; and if the three-dimensional coordinate information is consistent with the three-dimensional coordinate information preset on each construction object, displaying responsible person information on one side of the corresponding construction object.
In this embodiment, the information triggering operation action refers to controlling a scene in the three-dimensional model of the construction site to change by touching a display screen or operating a mouse. The responsible person information refers to personnel information of each area module of the construction site, including information of names, positions, engineer grades, project progress and the like of the personnel.
Specifically, coordinate trigger points are set on each construction object, three-dimensional coordinates set during modeling are used as a reference coordinate system of the information trigger operation action to read three-dimensional coordinate information of the information trigger operation action, when the information trigger operation action moves to a trigger point position set on the construction object, a display instruction is triggered, and corresponding information is displayed in a three-dimensional model of a construction site so as to be watched by a user. For example, the trigger coordinates of a trigger point at the roof position of the a building are set to be (30,20,25), and when the information trigger operation is detected to move to the coordinates (30,20,25), the relevant information is displayed at the position on the roof side of the a building in the three-dimensional model of the construction site.
The embodiment of the application also discloses an integrated information intelligent management system based on the BIM technology. Referring to fig. 2, the integrated information intelligent management system based on the BIM technology includes:
the modeling module acquires various construction parameters from the construction drawing to establish a construction site three-dimensional model;
the construction site supervision module acquires construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
the judging module is used for adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
Further, the system also comprises an alarm module, and if the influence of the adjusted parameters on the related parameters exceeds a preset range, false alarm information is triggered.
Further, the system also comprises a wind load module, and the on-site wind speed and direction are obtained in real time to form wind load information; and adjusting the structural system of the building in the three-dimensional model of the construction site according to the wind load information.
Further, the system also comprises a humidity module for acquiring humidity information of the construction site; determining construction scheme adjustment parameters according to the humidity information; and (3) reconditioning the parameter model of the three-dimensional model of the construction site according to the construction scheme adjustment parameters to check whether the modified parameters have influence on other building parameters.
Further, the system also comprises an air pressure altitude change coefficient module, and an air pressure altitude change coefficient is determined according to the staged site construction parameter information; wind load information is determined based on the wind pressure altitude change factor.
Further, the system comprises a display module for acquiring three-dimensional coordinate information of the information triggering operation action; and if the three-dimensional coordinate information is consistent with the three-dimensional coordinate information preset on each construction object, displaying responsible person information on one side of the corresponding construction object.
The embodiment of the application also discloses a computer device, which can be a server, referring to fig. 3. The computer device includes a processor, a memory, a network interface, and a database connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, computer programs, and a database. The internal memory provides an environment for the operation of the operating system and computer programs in the non-volatile storage media. The database of the computer device is used to store historical suspicious behavior data. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program is executed by a processor to realize an integrated information intelligent management method based on BIM technology, and the method comprises the following steps:
S100: acquiring various construction parameters from a construction drawing to establish a construction site three-dimensional model;
S200: acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
s300: and adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
The embodiment of the application also discloses a computer readable storage medium. In one embodiment, a computer readable storage medium is provided having a computer program stored thereon, which when executed by a processor, performs the steps of:
S100: acquiring various construction parameters from a construction drawing to establish a construction site three-dimensional model;
S200: acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
s300: and adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
Those skilled in the art will appreciate that implementing all or part of the above-described methods in accordance with the embodiments may be accomplished by way of a computer program stored on a non-transitory computer readable storage medium, which when executed may comprise the steps of the embodiments of the methods described above. Any reference to memory, storage, database, or other medium used in embodiments provided herein may include non-volatile and/or volatile memory. The nonvolatile memory can include Read Only Memory (ROM), programmable ROM (PROM), electrically Programmable ROM (EPROM), electrically Erasable Programmable ROM (EEPROM), or flash memory. Volatile memory can include Random Access Memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in a variety of forms such as Static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double Data Rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (SYNCHLINK) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), among others.
It will be apparent to those skilled in the art that, for convenience and brevity of description, only the above-described division of the functional units and modules is illustrated, and in practical application, the above-described functional distribution may be performed by different functional units and modules according to needs, i.e. the internal structure of the apparatus is divided into different functional units or modules to perform all or part of the above-described functions.
The above embodiments are only for illustrating the technical solution of the present invention, and are not limiting; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present invention, and are intended to be included in the scope of the present invention.

Claims (8)

1. An integrated information intelligent management method based on BIM technology is characterized in that: the method comprises the following steps:
Acquiring various construction parameters from a construction drawing to establish a construction site three-dimensional model;
acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not;
The step of acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information comprises the following steps:
acquiring the wind speed and the wind direction of a site in real time to form wind load information;
adjusting the structural system of the building in the three-dimensional model of the construction site according to the wind load information;
the step of acquiring the on-site wind speed and direction in real time to form wind load information comprises the following steps:
determining the change coefficient of the air pressure height according to the staged site construction parameter information;
Wind load information is determined based on the wind pressure altitude change factor.
2. The integrated information intelligent management method based on the BIM technology according to claim 1, wherein the method comprises the following steps: the step of adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range, comprises the following steps:
And if the influence of the adjusted parameters on the associated parameters exceeds a preset range, triggering error alarm information.
3. The integrated information intelligent management method based on the BIM technology according to claim 2, wherein the method is characterized in that: the step of acquiring construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information comprises the following steps:
acquiring humidity information of a construction site;
Determining construction scheme adjustment parameters according to the humidity information;
and reconditioning a parameter model of the construction site three-dimensional model according to the construction scheme adjustment parameters to check whether the modified parameters have influence on other building parameters.
4. The integrated information intelligent management method based on the BIM technology according to claim 1, wherein the method comprises the following steps: the step of obtaining the information of the responsible person of each construction object and displaying the information in the three-dimensional model of the construction site comprises the following steps:
acquiring three-dimensional coordinate information of information triggering operation actions;
And if the three-dimensional coordinate information is consistent with the three-dimensional coordinate information preset on each construction object, displaying responsible person information on one side of the corresponding construction object.
5. A system for implementing the integrated information intelligent management method based on the BIM technology as claimed in any one of claims 1 to 4, wherein: the system comprises:
the modeling module acquires various construction parameters from the construction drawing to establish a construction site three-dimensional model;
the construction site supervision module acquires construction parameters of each construction time period of each construction object in the construction process in real time to form staged site construction parameter information;
And the judging module is used for adjusting part of parameters of the three-dimensional model of the construction site in real time based on the site construction parameter information and judging whether the influence of the adjusted parameters on the related parameters is within a preset range or not.
6. The system of the integrated information intelligent management method based on the BIM technology according to claim 5, wherein: the system further comprises:
And the alarm module is used for triggering error alarm information if the influence of the adjusted parameters on the related parameters exceeds a preset range.
7. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized by: the steps of the integrated information intelligent management method based on BIM technology according to any one of claims 1-4 are realized when the processor executes the computer program.
8. A computer readable storage medium, characterized in that a computer program is stored which can be loaded by a processor and which performs the method according to any of claims 1-4.
CN202110374424.4A 2021-04-07 2021-04-07 BIM technology-based integrated information intelligent management system and management method Active CN112948950B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110374424.4A CN112948950B (en) 2021-04-07 2021-04-07 BIM technology-based integrated information intelligent management system and management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110374424.4A CN112948950B (en) 2021-04-07 2021-04-07 BIM technology-based integrated information intelligent management system and management method

Publications (2)

Publication Number Publication Date
CN112948950A CN112948950A (en) 2021-06-11
CN112948950B true CN112948950B (en) 2024-05-10

Family

ID=76230494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110374424.4A Active CN112948950B (en) 2021-04-07 2021-04-07 BIM technology-based integrated information intelligent management system and management method

Country Status (1)

Country Link
CN (1) CN112948950B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113326559A (en) * 2021-06-24 2021-08-31 广东昊迪工程项目咨询有限公司 Municipal bridge engineering construction supervision method and system
CN113656389B (en) * 2021-08-12 2022-05-27 北京可视化智能科技股份有限公司 Intelligent factory abnormal data processing method, device and system and storage medium
CN115309940B (en) * 2022-08-10 2023-05-19 公诚管理咨询有限公司 Intelligent construction data analysis method and system based on building site law enforcement recorder
CN117689821B (en) * 2023-12-29 2024-05-14 中铁一局集团第一建设有限公司 BIM-based temporary construction three-dimensional effect graph manufacturing method and device

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013174952A (en) * 2012-02-23 2013-09-05 Ohbayashi Corp Environment simulation system for construction site and environment simulation method for construction site
CN107886448A (en) * 2017-09-29 2018-04-06 四川隧唐科技股份有限公司 object position management method and device
CN108520342A (en) * 2018-03-23 2018-09-11 中建三局第建设工程有限责任公司 Platform of internet of things management method based on BIM and its system
CN109446664A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of scene progress control display device system
CN110070284A (en) * 2019-04-17 2019-07-30 江苏开通建设工程有限公司 A kind of wisdom beam course management system based on BIM technology
CN110782154A (en) * 2019-10-23 2020-02-11 中铁十八局集团有限公司 Construction plan management system based on BIM + GIS
CN111125808A (en) * 2019-11-12 2020-05-08 万翼科技有限公司 Intelligent construction site management model construction method and device
CN111598734A (en) * 2020-05-25 2020-08-28 中建三局第二建设工程有限责任公司 Intelligent building site integrated management system of BIM and Internet of things
CN111627099A (en) * 2019-02-27 2020-09-04 上海捷规建筑工程咨询有限公司 Steel structure non-contact actual measurement method and system based on three-dimensional scanning technology
CN111767603A (en) * 2020-09-03 2020-10-13 北京杜普信科技有限公司 BIM-based surrounding rock stability monitoring and evaluating method and system and storage medium
CN111814236A (en) * 2020-07-03 2020-10-23 广东恒实建设工程有限公司 Foundation pit excavation engineering design method based on BIM technology
CN112069694A (en) * 2020-09-15 2020-12-11 深圳市华壹装饰科技设计工程有限公司 Refined decoration XR (X-ray radiation) interactive experience method and system based on BIM (building information modeling) technology
CN112132543A (en) * 2020-09-25 2020-12-25 广西路桥工程集团有限公司 Engineering project progress management system
JP6806416B1 (en) * 2019-07-24 2021-01-06 東芝エレベータ株式会社 BIM control method

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013174952A (en) * 2012-02-23 2013-09-05 Ohbayashi Corp Environment simulation system for construction site and environment simulation method for construction site
CN107886448A (en) * 2017-09-29 2018-04-06 四川隧唐科技股份有限公司 object position management method and device
CN108520342A (en) * 2018-03-23 2018-09-11 中建三局第建设工程有限责任公司 Platform of internet of things management method based on BIM and its system
CN109446664A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of scene progress control display device system
CN111627099A (en) * 2019-02-27 2020-09-04 上海捷规建筑工程咨询有限公司 Steel structure non-contact actual measurement method and system based on three-dimensional scanning technology
CN110070284A (en) * 2019-04-17 2019-07-30 江苏开通建设工程有限公司 A kind of wisdom beam course management system based on BIM technology
JP6806416B1 (en) * 2019-07-24 2021-01-06 東芝エレベータ株式会社 BIM control method
CN110782154A (en) * 2019-10-23 2020-02-11 中铁十八局集团有限公司 Construction plan management system based on BIM + GIS
CN111125808A (en) * 2019-11-12 2020-05-08 万翼科技有限公司 Intelligent construction site management model construction method and device
CN111598734A (en) * 2020-05-25 2020-08-28 中建三局第二建设工程有限责任公司 Intelligent building site integrated management system of BIM and Internet of things
CN111814236A (en) * 2020-07-03 2020-10-23 广东恒实建设工程有限公司 Foundation pit excavation engineering design method based on BIM technology
CN111767603A (en) * 2020-09-03 2020-10-13 北京杜普信科技有限公司 BIM-based surrounding rock stability monitoring and evaluating method and system and storage medium
CN112069694A (en) * 2020-09-15 2020-12-11 深圳市华壹装饰科技设计工程有限公司 Refined decoration XR (X-ray radiation) interactive experience method and system based on BIM (building information modeling) technology
CN112132543A (en) * 2020-09-25 2020-12-25 广西路桥工程集团有限公司 Engineering project progress management system

Also Published As

Publication number Publication date
CN112948950A (en) 2021-06-11

Similar Documents

Publication Publication Date Title
CN112948950B (en) BIM technology-based integrated information intelligent management system and management method
CN108385691A (en) Pit retaining monitoring, early warning and the construction management D-BIM platforms of integrated Big Dipper high-accuracy position system
CN109992900B (en) Multi-field real-time online collaborative intelligent simulation method and system for mass concrete
CN107315862B (en) Method for establishing open cut foundation pit engineering investigation and simulation parameter relationship
CN103669366A (en) Remote monitoring early warning system for deep foundation pit support structure deformation
CN109708688A (en) A kind of monitoring of history culture building safety and early warning system and method
CN115167212B (en) Dynamic construction control system and method for foundation pit based on monitoring platform
Schweitzer et al. Modeling of quality for engineering geodesy processes in civil engineering
WO2023121612A1 (en) A digital twin system for predicting response of structures to natural disasters
CN112464494A (en) Construction system is built to wisdom
Zhou et al. Aeroelastic balance
CN116776444A (en) Digital twinning-based immersed tube tunnel construction method and system
JP7141309B2 (en) Quantitative evaluation system for disaster occurrence risk caused by ground displacement, its method, and its program
CN113191747A (en) High-rise building engineering measurement supervision control method
CN117332494A (en) Method, equipment and storage medium for real-time digital twinning of open caisson construction state
CN113011747A (en) Building monitoring method and device, electronic equipment and storage medium
CN110378023B (en) Roof rainfall runoff simulation method, device, computer equipment and storage medium
CN115601520B (en) Fire disaster simulation method and device based on two-dimensional prediction and multi-scale grid
CN116659440A (en) Landslide fine displacement monitoring and early warning method
CN117113745A (en) Stress rechecking method and system for tower crane cross beam foundation
JP3017154B2 (en) Earthquake damage estimation system
JP6642232B2 (en) Earthquake damage estimation system, structure with earthquake damage estimation system, and earthquake damage estimation program
KR101995898B1 (en) Method for calculating dip of aerial transmission line using electric wire survey and program
JP2020106524A (en) Building soundness monitoring system
CN112685826B (en) Foundation structure construction method, device, equipment and readable storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant